z:w hotelsnew orleanslobby barfs-1 layout1 (1) · mark stech-novak restaurant consultation &...
TRANSCRIPT
Mark Stech-NovakRestaurant
Consultation & Design
Drawing No.
Scale
1/4"=12"
AD-FS 1.0
7
of
Drawing Title
Proj
ect T
itle
Plan & Schedulefor Kitchen Equipment
Le M
erid
ien
New
Orle
ans,
LA
Designed By
Drawn By
Reviewed By
Project Manager
Date
Revision
Project ID
CAD File Name
Plot Date
MSN/AD
MSN/AD
MSN
MSN
DEC 04-2012
Culinary Concepts
LM_NOLA_FS_121204
No.
Dat
eIs
sue
Not
es
935 Aquarius WayOakland California 94611
Phone: 510-601-7142Fax: [email protected]
ARCHITECT:
1
1
2
2
3
3
4
4
5
5
6
6
7
7
8
8
9
9
A A
B B
C C
D D
E E
F F
G G
General Notes and Conditions1. Mark Stech-Novak & Restaurant Consultation & Design DO NOT REPRESENT THEMSELVES AS ARCHITECTS, CONTRACTORS OR ENGINEERS. THESE DRAWINGS ARE PROVIDED FOR THE CONVENIENCE OF THE ARCHITECT, CONTRACTOR AND/OR SUBCONTRACTORS TO SHOW THE GENERAL PLACEMENT OF EQUIPMENT, FIXTURES, FURNISHINGS AND/OR MATERIALS AND WERE MADE FROM AVAILABLE INFORMATION AT THE TIME THEY WERE DRAWN.2. ALL PLUMBING, ELECTRICAL, VENTILATION AND REFRIGERATION, ROUGH-IN WORK, FINAL CONNECTIONS TO ALL FOOD SERVICE EQUIPMENT AND FIXTURES INCLUDING TAPS, VALVES, GREASE TRAPS, MISC. FITTINGS, SWITCHES, WIRING, CONDUIT OR FLEX, MAGNETIC STARTERS, DISCONNECTS, ELECTRICAL PANELS, THERMAL OVERLOAD PROTECTION, CORDS AND PLUGS, ETC. MUST BE SPECIFIED AND PROVIDED BY EQUIPMENT PROVIDER.3. WORK BY ANY TRADE INDICATED ON THESE PLANS DOES NOT NECESSARILY REFLECT COMPLIANCE WITH EACH TRADE'S RESPECTIVE CODES, ORDINANCES AND REGULATIONS AND THEREFORE DOES NOT RELIEVE THEM OF THEIR RESPONSIBILITY TO ASSURE SUCH.4. All dimensions and conditions must be verified at the job site. Details shown are typical.5. All dimensions when shown in plan are to face of finished surfaces unless otherwise noted. Installer must verify all field dimensions and relay any discrepencies and problems to the designer and PM for resolution in a timely manner.6. Contractors, subcontractors, sheetmetal fabricators and trades shall provide and submit their own necessary rough-in plans, elevations and drawings.7. General contractor shall provide all ceiling, wall and floor penetrations and all sleeves for plumbing, electrical, refrigeration and CO2 lines and ventilation ducts as required. All penetrations and remote location sites must be verified and approved by project engineers.8. A fire suppression system conforming to all local codes and specifications shall be fitted to all required equipment and hoods and shall be specified and shown on a separate drawing by food service equipment supplier.9. Plumbing contractor shall select, provide and locate correctly-sized grease traps, floor sinks, drains as required and co-ordinate the installation of these to comply with the requirements as specified by the foodservice equipment supplier.10. Any errors, omissions or conflict found in the various parts of the schematic documents shall be brought to the attention of the architect and/or project manager before proceeding with the work.11. Foodservice equipment supplier agrees to carry out commissioning on all equipment, materials, and systems in accordance with manufacturer's recommendations and upon completion of the installation at such time as designated by employer or project manager.12. Foodservice equipment supplier warrants all standards, fabrications and designs meet or exceed local environmental health, fire and safety codes and regulations. Any issue, design or standard of manufacture found to not meet these codes and regulations shall be brought to the attention of the architect and/or project manager before proceeding with the work.13. All equipment must be NSF approved.
MEP CONTRACTORS AND ENGINEERS: Please note that these drawings are for planning locations and costs for rough-in connections to equipement as noted in these plans. The final selection of equipment may change and effect the size, location and cost of the work associated. All services to the equipment shown should be reverified with the final "For Construction" drawings produced by the installer.
Summary of work1. The work to be performed by the Contractor(s) under this set of contract documents is the demolition, alteration and new construction as is necessary to provide for the installation of the foodservice equipment shown herein, and includes the following:2. It is the intent of the contract notes and documentation that all materials, equipment, and all systems be installed properly and complete for their intended function in the completed work.3. The work includes, but is not limited to all labor, materials, equipment, tools, machinery, construction, facilities and temporary controls, transportation and other facilities and services necessary to produce the construction required by the contract documents.4. All specifications books, addenda, inquiries and requests attached to or distributed with these drawings constitute the complete scope of work to be fufilled in these plans.
S
CORRIDOR
2460
CC
G
D
Trash
F24N
SFR
EEZ
ER
Trash
Trash
B18
B01 B02B03B04
B05
B06
B07B08
B14
B09
B06
B13
B11B15
B16
B17
B21
B11
B09
B22
B23
B24
B25
B26
B27
B06
B28
B29
C01C04 C06C07C08C11C12
C13
C14
C15
C21 C22 C23 C24
D01
D02
D03
D04D05 D06
D07
D08
D11
D12
D13D14
D15
D16
C10
C03
B19
C16
C19
D09
C18
C04
C17
B12
C09C02
A15
A16
A17
A18
B30
A17a
B31
A01
A02
A03
A04
A05
A06
A07
A08
A09
A10
A11
A12
A13
A14
A14
A13
A12
A11a
A11
A11a
A11b
Item # QTY Description Manufacturer Model Electrical Ph Amps Elec. Hgt. AFF Elec. Location Elec. Info. Gas BTU Gas Hgt. AFF CW HW Water Hgt. AFF Drain Drain Hgt. AFF Plumb. Location Notes Other Information Energy Star or N/AA01 1 Four head beer tap Micro Matic USA D7744PSSKR
A02 1 Water carbonator Crysalli CR-UC1 120/60 1 9.6 amps 12" Wall NEMA 5-15P 3/4" 18" 3/4" Indirect Floor Sink Wall Vfy air floow & orientation CO2 from below.Water supply from water filter.
A03 1 Still & Sparkling tap Crysalli CBR-V2 from A02 A04 1 Drip tray Fabricator Custom 1/2" Indirect Floor SinkA05 1 Beer drip tray & washer Micromatic DP-1604 1/2" 18" 3/4" Indirect Floor Sink WallA06 1 Handsink Omniteam HWV 3/8" 3/8" 1 1/2" Indirect Floor Sink WallA07 1 Front Load Freezer Perlick HC24FS 115/60 1 2.3 amps 12" Wall NEMA 5-15P 1/6 hpA08 1 Soiled glass center Omniteam GWS-24-M 1/2" 1/2" 18" 1" Indirect Floor Sink WallA09 1 Glasswasher Stero SGW-H-M 2@115/60 1 9.5 + 17.4 amps 12" Wall 2@Junction Box 3/8"@140°F 2-1/4" Indirect Floor Sink WallA10 1 POS stand Omni CustomA11 2 Jockey station Omniteam RP-40P8-M 120/60 1 15.0 amps 1/2" 1/2" 18" 3 @ 1" Indirect Floor Sink Wall M = reduced lengthA11a 2 Scupper drain Fabricator Custom 1" indirectA11b 1 Glass spritzer Micromatic GR-UCM 1/4" 1/2" indirect mount to underside of bar topA12 2 Soda gun By Vendor TBD
A13 2 REMOTE 37" High underbar refrigerator Omniteam 6LGS-TK-SSS-PPBRBBR-3FL-F-AS
115/60 1 2.3 amps 12" Wall Junction Box 1,700 BTUs condensing unit. Refrigeration lines from remote
A14 2 REMOTE 37" High underbar refrigerator Omniteam 6LGS-TK-SSS-PPBRBBR-2FL-F-AS
115/60 1 1.7 amps 12" Wall Junction Box 1,300 BTUs condensing unit. Refrigeration lines from remote
A15 1 Bag-in-box system/carbinator By Vendor TBD 115/60 1 20.0 est. amps 3/8" Verify all utilities with vendor.Water supply from water filter.
A16 1 Glycol System Chill-rite MLN-33 see FS 1.3 1 see FS 1.3 water in/out0.5gpm. 4@ 3/8" Condenser
A17 1 REMOTE Walk-in cooler complex American Panel Custom 120/208/60 1 20.0 amps Verify Ceiling Junction Box
A17a 1 Evaporator fan - cooler RDT ADT 115-208/60 1 TBD Verify Ceiling Junction Box 3/4" Indirect Floor Sink condensing unit.Refrigeration lines from remote
A18 2 Keg rack furnish)New Age (Chillrite to
31842TT7 100B01 1 Prep counter Fabricator Custom
B02 1 REMOTE Undercounter refrigerator - 2 door Fabricator Custom 120/60 1 15.0 est. amps 12" Wall NEMA 5-15P 1" Indirect Floor Sink condensing unit.Refrigeration lines from remote
B03 1 REMOTE Undercounter refrigerator - 2 door Fabricator Custom 120/60 1 15.0 est. amps 12" Wall NEMA 5-15P 1" Indirect Floor Sink condensing unit.Refrigeration lines from remote
B04 1 REMOTE refrigerated rail Fabricator Custom 120/60 1 15.0 est. amps 12" Wall NEMA 5-15P 1" Indirect Floor Sink condensing unit.Refrigeration lines from remote
B05 2 Wall shelving Fabricator Custom 120/60 1 5.0 amps 66" Wall Junction BoxB06 3 Remote printer Verify Verify 120/60 1 15.0 est. amps 66" Wall NEMA 5-15P Verify utility requirements with vendor.
B07 1 REMOTE Undercounter refrigerator - 2 door Fabricator Custom 120/60 1 15.0 est. amps 12" Wall NEMA 5-15P 1" Indirect Floor Sink condensing unit.Refrigeration lines from remote
B08 1 REMOTE refrigerated rail Fabricator Custom 120/60 1 15.0 est. amps 12" Wall NEMA 5-15P 1" Indirect Floor Sink condensing unit.Refrigeration lines from remote
B09 2 Faucet T & S Brass B-0221 1/2" 1/2" 12" WallB10 - Spare numberB11 2 Drop-in sink Fabricator Custom 1-1/2" Indirect Floor SinkB12 1 Pass-over shelving structure Fabricator Custom 120/60 1 5.0 amps 66" Wall Junction Box 2@1" indirectB13 2 Wall shelving Fabricator Custom 120/60 1 5.0 amps 66" Wall Junction BoxB14 1 Microwave Amana RC22S 208-240/60 1 15.4 amps 54" Wall NEMA 6-20P
B15 1 REMOTE Undercounter refrigerator - 2 door Fabricator Custom 120/60 1 15.0 est. amps 12" Wall NEMA 5-15P 1" Indirect Floor Sink condensing unit.Refrigeration lines from remote
B16 1 REMOTE UndercounterFREEZER - 2 door Fabricator Custom 208/120/60 1 15.0 est. amps 12" Wall NEMA 5-15P 1" Indirect Floor Sink condensing unit.Refrigeration lines from remote
B17 1 REMOTE Refrigerated rail Fabricator Custom 120/60 1 15.0 est. amps 12" Wall NEMA 5-15P 1" Indirect Floor Sink condensing unit.Refrigeration lines from remote
B18 1 Warmer Equipex SEM-60 VC 208-240/60 1 3.0 kW 66" Wall NEMA 6-20PB19 2 Wall shelving Fabricator Custom 120/60 1 5.0 est. amps 66" Wall Junction BoxB20 - Spare numberB21 1 Microwave Panansonic NE-1051 120/60 1 14.0 amps 70" Wall NEMA 5-20B22 1 Prep counter Fabricator CustomB23 2 Wall shelving Fabricator Custom 120/60 1 5.0 amps 66" Wall Junction Box
B24 1 Fully automated espresso machine Schaerer Coffee Art Plus 1 208/60 1 30.0 amps 50" Wall NEMA L14-30P 3/8" 50" 1/2" Indirect Floor Sink Wall 3.6.9510 below.Water supply from water filter
B25 1 Water Filter Cuno CFS6135-C-SUSA 3/8" 18" Wall
B26 1 REMOTE Undercounter refrigerator - 1 door Fabricator Custom 120/60 1 15.0 est. amps 12" Wall NEMA 5-15P 1" Indirect Floor Sink condensing unit.Refrigeration lines from remote
B27 1 Water boiler Fetco HWB-5 120-208/60 1 11.3 amps 54" Wall Junction box 3/8" 54" By vendor.B28 2 Wall shelving Fabricator Custom 120/60 1 5.0 amps 66" Wall Junction BoxB29 2 Wall shelving Fabricator Custom 120/60 1 5.0 amps 66" Wall Junction BoxB30 1 Trash receptacle By ownerB31 1 Prep counter Fabricator Custom
C01 1 Type 1 Exhaust hood Caddy AirSystems x 2SHBC-C-W-91-ND-60
120/60 1 0.24 kW Verify Ceiling Junction Box Two (2) hoodsC02 1 Meat resting rack Fabricator CustomC03 1 Frenchtop on conv. oven Jade JTRH-2FHT-36C 120/60 1 10.0 amps 24" wall 5-15P 1 1/4" 95,000 front gas manifold loop gas supply see FS1.2C04 2 Salamander Jade JSB-36RM 3/4" 35,000 58"C05 - Spare numberC06 1 Pasta cooker Jade Rosito Bisani CPG1 3/8" 60,000 3/8" 12" 1 1/4" Indirect Floor Sink Wall front gas manifold loop gas supply see FS1.2C07 1 Grill - 18" Jade JTRH-18B 1 1/4" 45,000 front gas manifold loop gas supply see FS1.2C08 1 6 burner/conv oven Jade JTRH-6-36C 120/60 1 10.0 amps 24" wall NEMA 5-15P 1 1/4" 245,000 front gas manifold loop gas supply see FS1.2C09 1 Spreader on cab base Jade JTRH-18S 1 1/4" Verify front gas manifold loop gas supply see FS1.2C10 1 Tubular shelf Fabricator CustomC11 1 Plancha on cab base Jade JTRH-18P 1 1/4" 17,500 front gas manifold loop gas supply see FS1.2C12 2 Fryer - 25 lb. cap. Jade JTFF-25-12 1 1/4" 60,000 front gas manifold loop gas supply see FS1.2C13 4 Pot rails on hoods Fabricator Custom see SD-029
C14 2 Combi-oven stacked -gas-fired Rational SCC WE 61 G 120/60 1 15.0 amp circuit 24" Wall NEMA 5-15P 3/4" 41,000 24" 3 @ 3/4" 18" 2" Indirect Floor Sink Wall Requires dedicated circuit & ground wire. oven to be filtered.One (1) water connection per
C15 1 Type 1 Exhaust Hood Caddy AirSystems SHBC-C-W-48-ND-60 120/60 1 0.24 kW Verify Ceiling Junction BoxC16 lot S/S wall flashing Fabricator CustomC17 1 Fire suppression system Ansul R102 120/60 1 15.0 amps Verify Ceiling Junction box Locate manual pull stations as required.C18 1 Prep table Fabricator Custom
C19 1 REMOTE Undercounter refrigerator - 2 door Fabricator Custom 120/60 1 15.0 est. amps 12" Wall NEMA 5-15P 1" Indirect Floor Sink condensing unit.Refrigeration lines from remote
C20 - Spare numberC21 2 Wall shelving Fabricator Custom 120/60 1 5.0 amps 66" Wall Junction BoxC22 1 Remote printer Verify Verify 120/60 1 15.0 est. amps 66" Wall NEMA 5-15P Verify utility requirements with vendor.C23 1 Hand sink Advance-Tabco 7-PS-81 1/2" 1/2" 12" 1 1/2" Direct 18" Wall w/ foot pedalsC24 1 Water Filter Everpure EV9797-22 3/4" Mount on wall as high as possibleD01 1 Plastic shelving Metro MetroMaxiQD02 2 Dish cart Cambro CD2020110D03 1 Pot wash sinks Fabricator Custom (3) 2" Wall Pipe drains to grease trapD04 2 Splash-mount faucets 12" spiggot T&S Brass B-0231 1/2" 1/2" 12" Wall w/ B-WH-6" blade handlesD05 1 Wall shelf Advance Tabco PS-18-84 D06 1 Hand sink Advance-Tabco 7-PS-81 1/2" 1/2" 12" 1 1/2" Indirect Floor Sink Wall w/ foot pedalsD07 1 Soiled dish landing Fabricator Custom 1" Indirect Floor Sink w/ mushroom overshelf
D08 1 Food waste scraper & control panel Salvajor S914 & MSS-LD 208/60 3 3.2 amps 12" Wall Junction Box 3/4" 3/4" 12" 2" Wall connection.Reduce water supply to 1/2" @ Pipe drain to grease trap.
D09 1 Hose Reel & Mixing Cabinet Fisher 1801/2985 1/2" 1/2" 90" Wall Reel @ 90" AFFD10 - Spare numberD11 1 Rack wall shelf Fabricator CustomD12 1 Floor trough Fabricator Custom 3" Direct -3" FloorD13 1 Dishwasher Hobart AM15T-2 208-240/60 3 45.4 amps 18" Wall Junction Box 3/4" @140°F 12" 1 1/2" Indirect Floor Sink WallD14 1 Vapor hood Caddy AirSystems CH-C-W-42-SD-42 1" Indirect Floor Sink 600 cfmD15 1 Clean landing Fabricator Custom custom length Dwg # 020917-1D16 1 Rack wall shelf Fabricator Custom R01 1 Remote refrigeration rack RDT IRW2-7 208-230/60 3 26.0 VFY) Verify Junction Box 1-1/8" in/out Verify exactly location with architect and engineer.
DRAWING DESCIPTION SHEET NAMEEquipment Plan FS 1.0
Special Conditions Plan FS 1.1Plumbing & Mechanical Plan FS 1.2Electrical PlanRefrigeration & Ventilation
FS 1.3FS 1.4FS 1.5
√Equipment Schedule FS 1.0a
09-S
ept-1
2
Selected Elevations FS 1.6Selected Elevations
√√√√
√
17-S
ept-1
2
√√√√√√
√
30-N
ov-1
2
√√√√√√
√
03-D
ec-1
2
√√√√√√
1FS
1.6
5FS 1.6
2FS
1.6
3FS 1.6
6FS
1.6
4FS
1.6
7
FS 1.6
8FS 1.6
9FS 1.7
10
FS 1.7
11FS 1.7
12FS
1.7
90"
42"
36"
24"
12"
12"
REMOTE REFRIGERATIONRACK - N.T.S.
ELECTRICALCONTROL PANEL
REFRIGERANT LINE STUB OUTWATER INLET/OUTLET
MAIN FUSED DISCONNECT
90"
42"
64"
Raised curb areas
Floor sink -5" depression
Wall blocking by G.C.from noted height tonoted height in inches
6" depression in slab
Corner guards by G.C. (NIKEC)(mount to 60" from coved floor.)
KEC Kitchen Equipment Contractor
NIKEC Not in kitchen equipment contract
GC General Contractor
cg
WB
Non-combustiblewall construction
Unistrut bracing by KEC above drop ceiling, braced to building beams rated to specific load. Hood hangers representational only. See shop drawings for verification.
Area drain
Reduced-size Hub drain for indirect waste(where permitted)
FLOORS, WALLS, CEILING FINISHES -UNLESS OTHERWISE NOTED(all samples must be verified w/ MSN-RCD prior to final selection and purchase.)
FLOOR TROUGH SECTION - NTS
WASTE
SEAL (LEAD & OKUM)
STRAINEROR BEE-HIVEREMOVABLE MESH6" DIA.
NOTCH SLAB
STRAINER BASKET
MEMBRANEWATER-PROOF
GRATING
MEMBRANEWATERPROOF
TROUGH PAN
WASTESEAL
KECKEC
GC
KECPCPC
KEC
GC
GC
PCPC
KEC
TABSS/S ANCHORING
INSTALL
KEC
FURNISH
KEC
FOOTWASTE 1/2" PERSLOPE TO
TO BOTTOM OFSLEEVE WELDED16 GA. S/S
TROUGH SIDES OF BOTH LONGRADIUS ON TROUGH W/ 1"WELDED FLOOR14 GA. S/S ALL
APPROX. 12"O.C.TO TROUGHTABS WELDEDS/S ANCHORING3" WIDE X 14 GA.
4" CUP
4"
1"
6-1/2"
SEAL
SECTIONSGRATING INREMOVABLEFINISHED
FLOOR
CONDENSER DRAIN DETAIL—NTS
RUN IN CURBIF HOLLOWCURB USED
CONDENSER DRAIN DETAIL—NTS
FRAME TRENCHES IN WOODBEFORE POUR IF SOLIDCURB USED
Mark Stech-NovakRestaurant
Consultation & Design
Drawing No.
Scale
1/4"=12"
AD-FS 1.1
7
of
Drawing Title
Proj
ect T
itle
Building Conditionsfor Kitchen Equipment
Le M
erid
ien
New
Orle
ans,
LA
Designed By
Drawn By
Reviewed By
Project Manager
Date
Revision
Project ID
CAD File Name
Plot Date
MSN/AD
MSN/AD
MSN
MSN
Dec 04-2012
Culinary Concepts
LM_NOLA_FS_121204
No.
Dat
eIs
sue
Not
es
935 Aquarius WayOakland California 94611
Phone: 510-601-7142Fax: [email protected]
ARCHITECT:
1
1
2
2
3
3
4
4
5
5
6
6
7
7
8
8
9
9
A A
B B
C C
D D
E E
F F
G G
S
CORRIDOR
2460
CC
G
D
Trash
F24N
SFR
EEZ
ER
Trash
Trash
B18
B01 B02B03B04
B05
B06
B07B08
B14
B09
B06
B13
B11B15
B16
B17
B21
B11
B09
B22
B23
B24
B25
B26
B27
B06
B28
B29
C01C04 C06C07C08C11C12
C13
C14
C15
C21 C22 C23 C24
D01
D02
D03
D04D05 D06
D07
D08
D11
D12
D13D14
D15
D16
C10
C03
B19
C16
C19
D09
C18
C04
C17
B12
C09C02
A15
A16
A17
A18
B30
A17a
B31
A01
A02
A03
A04
A05
A06
A07
A08
A09
A10
A11
A12
A13
A14
A14
A13
A12
A11a
A11
A11a
A11b
WB 48 108
2'-4"4'-7"
2'-1
1"
WB 48 108
3'-8
"
1'-11
"
WB 48 108
7'-2"
WB 48 120
6'-6"
WB 48 120
3'-8
"3'
-10"
WB 48 108
5"
WB 48 1082'-8"
Provide support above ceilingfor pass-over shelving structure
4'-0"
1'-9"
6'-2
"
1'-1
1"
1'-9"1'-2"
8"2'-7"
1'-6" 1'-1"
11"
1'-8
"
1'-4
"4'
-4"
1'-9
"1'
-4"
1'-1" 10"
1'-6"
5"5'-8"2'-0"
5"9"
1'-5
"
6" deep depression below Cooler. Depressed area to be smooth and level with plumb vertical sides. GC to provide anywater-proofing materials prior to final dimensioning. Mfr. to provide insulated and reinforced floor panels consisting of 5" thick foamed-in-place urethane in min 20 ga panel frames. Mfr. wall panels to be fastended to floor panels. Finished interior floor surface to be same as kitchen. After walk-in installation GC to extend flooring material from kitchen area into cooler and cove up all interior sides. Walk-in mfr. to verify and provide tile-cut doors, if applicable.
4'-0
"
1'-2"
3'-6"
WB 84 CEILING
WB 48 108
1'-5"
WB 20 42
1'-5"
WB 20 42
VFY w/ARCH
VFY ID CURB DESIREDFOR COOKING BATTERY
6" Ø BEER LINE CHASE FROMGLYCOL PUMP TO TAPS
90"
42"
36"
24"
12"
12"
REMOTE REFRIGERATIONRACK - N.T.S.
ELECTRICALCONTROL PANEL
REFRIGERANT LINE STUB OUTWATER INLET/OUTLET
MAIN FUSED DISCONNECT
90"
42"
64"
CONDUIT NOTES:
BEER TOWER & TROUGH
CO2 REGULATOR
AIR COMPRESSORAIR / CO2 REGULATOR
COUNTER TOPCOOLING/ PUMP UNITCOOLANT LINE
AIR FILTER
CO2 SOURCE
30"X30" BOX (MIN) FOR DIRECTIONAL CHANGE.PULL BOX: 12"X30" BOX (MIN) FOR STRAIGHT RUN.3.
BEER SYSTEM CONDUIT ROUTING
CONDUIT IS NOT REQUIRED ABOVE SLAB IN POINT OF SERVICE AREA.
6" PVC (OR METAL) ELECTRICAL CONDUIT. SOLVENT CEMENTED (OR SEALED)
SCHEDULE 40 CONDUIT. PLUMBING PVC OR CAST IRON IS NOT ACCEPTABLE.UL STD 651, NEMA SPECIFICATION TC-2. IE: CARLON PV-DUIT PLUS ANDCONNECTIONS. 24" MIN. RADIUS. AS DESECRIBED IN ARTICLE 347 OF NEC TO MEET
WALK-IN COOLERTYGON TUBING
(BEER LINES & INSULATION)TRUNK HOUSING
HOLES IN MILLWORK TOPPRIMARY AIR REGULATOR
TAPPING HARDWARE
AIR FILTER
SECONDARY CO2 REGULATOR
AIR/ CO2 BLENDER
CO2 SOURCECO2 REGULATOR
KECKEC
KEC
KECKEC
VENDOR
KECKEC
2.
1.
MWKECMW
KEC
KECKEC
KEC
KECKECKEC
PULL BOX
FURNISH INSTALL
KECKEC
KEC
VENDOR
KEC
KEC
KECKEC
KEC
MWKECECKECKEC
-
EC
FURNISH
REGULATORPRIMARY AIRAIR COMPRESSOR
INSTALL
HARDWARETAPPING
BEER TOWER
REGULATORCO2
PANEL
INSULATEDLINE
COOLERWALK-IN
SLAB
& TROUGH
GLYCOLCHILLED
REGULATORSECONDARY
BEEROUT
OUTBACKGLYCOL
PUMP UNITCOOLING/
& INSULATION)
TRUNK HOUSING(BEER LINES
PULL BOX.PULLED THRUCANNOT BEBRANCH "T"PRE-MANUFACT.
COUNTER TOPCOUNTERTOP HOLES
Gas Connection
Direct Waste Connection
Indirect Waste Connection
Cold Water connection
Hot Water connection
Floor Sink: use 1/2 or 3/4 grate coverwherever possible
Floor Drain (location suggested onlyverify w/ plumbing req. & local codes)
Reduced-size Hub drain for indirect waste(where permitted)
Remote refrigeration connection(routing per KEC)
Building Chilled water loop connection
Building Chilled water loop returnFLOOR TROUGH SECTION - NTS
WASTE
SEAL (LEAD & OKUM)
STRAINEROR BEE-HIVEREMOVABLE MESH6" DIA.
NOTCH SLAB
STRAINER BASKET
MEMBRANEWATER-PROOF
GRATING
MEMBRANEWATERPROOF
TROUGH PAN
WASTESEAL
KECKEC
GC
KEC
PCPCKEC
GC
GC
PCPCKEC
TABSS/S ANCHORING
INSTALL
KEC
FURNISH
KEC
FOOTWASTE 1/2" PERSLOPE TO
TO BOTTOM OFSLEEVE WELDED16 GA. S/S
TROUGH SIDES OF BOTH LONGRADIUS ON TROUGH W/ 1"WELDED FLOOR14 GA. S/S ALL
APPROX. 12"O.C.TO TROUGHTABS WELDEDS/S ANCHORING3" WIDE X 14 GA.
4" CUP
4"
1"
6-1/2"
SEAL
SECTIONSGRATING INREMOVABLEFINISHED
FLOOR
PLUMBING NOTESNote: All locations for connections, sizes and runs are approximate and relative only to itemized food service equipment. Items not labeled either in the schedule or directly on the drawing are to be determined and verified on construction contract drawings. ALL WORK SHOWN ON THE PLUMBING PLANS IS THE RESPONSIBILITY OF THE GENERAL CONTRACTOR, UNLESS OTHERWISE NOTED.1. All work must be verified by site measurements and with the final equipment selection. Equipment makes and models may change and will thus affect final placement. Verify all work with foodservice equipment installer's final rough-in plans.2. Height details are for stub-outs and are to be measured above finished floor level. Stub-outs to extend 4” beyond finished walls and 6” above finished floor or top of equipment pad. All appliance connections must be verified with foodservice equipment installer's final specifications and rough-in details.3. Connections to grease traps and location of same must be made in accordance with local codes and requirements and must be reviewed and approved by owner, appropriate inspectors and MSN-RCD.4. All gas appliances must be connected with properly sized regulators. Verify with foodservice equipment installer's final specifications.5. All plumbing materials, including pipes, traps, stops, valves, fittings, vacuum breakers, hammer-arrestors, pressure reducing valves, gauges, unions and insulation are to be provided by the plumbing trades. These items must be connected so as not to interfere with the operation or use of the equipment. It is the responsibility of the plumbing trades to insure the proper sizing, fit and utilization of these according to manufacturer’s specifications.6. All plumbing labor, including mounting of drains, faucets and connections from point-of-connection on equipment to rough-in point as shown schematically on these plans is to be provided by plumbing trades.7. Utilities are to be concealed in walls wherever possible. Exposed pipes or conduit must be approved by architect or owner.8. All lines are to be flushed free of debris and foreign matter and line strainers cleaned prior to make-up of final utility connection.9. Drain lines from evaporator coils must be trapped outside of refrigerated area and extended over building drain.10. Gas main to be provided with a readily accessible manual shut-off valve by plumbing trades. A looped gas service is recommended to provide for balanced fuel distribution. Size of gas main to be determined by architect or architect's engineers. 11. Plumbing requirements for water wash hoods and hood fire protection systems will be detailed in rough-in plans supplied by others. Mechanical or electrical gas solenoid shut-off valves to be used with the fire protection system to be provided by plumbing trades per specifications supplied by hood provider. Kitchen equipment supplier will show final location for Ansul/gas emergency shut-off points once these have been coordinated with building engineers, hood manufacturer and MSN-RCD.12. Water wash ventilators and wash down control panels will be furnished with loose components. Plumbing trades will be responsible for all interconnections per manufacturer’s instructions.13. Kitchen Equipment Contractor to provide and install indirect waste runs from walk-in evaporator coils. Connections through walls to be coordinated with project architect. Freezer runs are to be heated and insulated.14. Locations for floor drains are suggested. Building engineer and plumbing engineer to co-ordinate existing drains and locations with those shown on this plan and review same with architect and MSN-RCD.15. Furnish all large items in pre-piped sections. All connections are to be clearly labeled. Written connection instructions from manufacturer are to be provided to the plumbing trades. Plumbing trades to make final connections between sections.16. Steam lines are to be installed per local codes. All exposed lines to be insulated and covered either in chrome-plated or stainless steel sleeves.17. Food service equipment contractor to furnish all gate valves, strainers, condensate traps, temperature controllers check valves and interconnecting piping within steam using equipment. Plumbing trades to blow out lines and make all final connections between equipment and stub outs.
Mark Stech-NovakRestaurant
Consultation & Design
Drawing No.
Scale
1/4"=12"
AD-FS 1.2
7
of
Drawing Title
Proj
ect T
itle
Plumbing Rough-insfor Kitchen Equipment
Le M
erid
ien
New
Orle
ans,
LA
Designed By
Drawn By
Reviewed By
Project Manager
Date
Revision
Project ID
CAD File Name
Plot Date
MSN/AD
MSN/AD
MSN
MSN
Dec 04-2012
Culinary Concepts
LM_NOLA_FS_121204
No.
Dat
eIs
sue
Not
es
935 Aquarius WayOakland California 94611
Phone: 510-601-7142Fax: [email protected]
ARCHITECT:
1
1
2
2
3
3
4
4
5
5
6
6
7
7
8
8
9
9
A A
B B
C C
D D
E E
F F
G G
A01 1 Four head beer tap
A02 1 Water carbonator 3/4" 18" 3/4" Indirect Floor Sink Wall below.Water supply from water filter. CO2 from
A03 1 Still & Sparkling tap from A02 A04 1 Drip tray 1/2" Indirect Floor SinkA05 1 Beer drip tray & washer 1/2" 18" 3/4" Indirect Floor Sink WallA06 1 Handsink 3/8" 3/8" 1 1/2" Indirect Floor Sink WallA07 1 Front Load FreezerA08 1 Soiled glass center 1/2" 1/2" 18" 1" Indirect Floor Sink WallA09 1 Glasswasher 3/8"@140°F 2-1/4" Indirect Floor Sink WallA10 1 POS standA11 2 Jockey station 1/2" 1/2" 18" 3 @ 1" Indirect Floor Sink WallA11a 2 Scupper drain 1" indirectA11b 1 Glass spritzer 1/4" 1/2" indirectA12 2 Soda gunA13 2 REMOTE 37" High underbar refrigerator Refrigeration lines from remote condensing unit. A14 2 REMOTE 37" High underbar refrigerator Refrigeration lines from remote condensing unit.
A15 1 Bag-in-box system/carbinator 3/8" with vendor.Water supply from water filter. Verify all utilities
A16 1 Glycol System 0.5gpm. 4@ 3/8" Condenser water in/outA17 1 REMOTE Walk-in cooler complex A17a 1 Evaporator fan - cooler 3/4" Indirect Floor Sink Refrigeration lines from remote condensing unit.A18 2 Keg rackB01 1 Prep counterB02 1 REMOTE Undercounter refrigerator - 2 door 1" Indirect Floor Sink Refrigeration lines from remote condensing unit.B03 1 REMOTE Undercounter refrigerator - 2 door 1" Indirect Floor Sink Refrigeration lines from remote condensing unit.B04 1 REMOTE refrigerated rail 1" Indirect Floor Sink Refrigeration lines from remote condensing unit.B05 2 Wall shelvingB06 3 Remote printerB07 1 REMOTE Undercounter refrigerator - 2 door 1" Indirect Floor Sink Refrigeration lines from remote condensing unit.B08 1 REMOTE refrigerated rail 1" Indirect Floor Sink Refrigeration lines from remote condensing unit.B09 2 Faucet 1/2" 1/2" 12" WallB10 - Spare numberB11 2 Drop-in sink 1-1/2" Indirect Floor SinkB12 1 Pass-over shelving structure 2@1" indirectB13 2 Wall shelvingB14 1 MicrowaveB15 1 REMOTE Undercounter refrigerator - 2 door 1" Indirect Floor Sink Refrigeration lines from remote condensing unit.B16 1 REMOTE UndercounterFREEZER - 2 door 1" Indirect Floor Sink Refrigeration lines from remote condensing unit.B17 1 REMOTE Refrigerated rail 1" Indirect Floor Sink Refrigeration lines from remote condensing unit.B18 1 WarmerB19 2 Wall shelvingB20 - Spare numberB21 1 MicrowaveB22 1 Prep counterB23 2 Wall shelvingB24 1 Fully automated espresso machine 3/8" 50" 1/2" Indirect Floor Sink Wall Water supply from water filter below.B25 1 Water Filter 3/8" 18" WallB26 1 REMOTE Undercounter refrigerator - 1 door 1" Indirect Floor Sink Refrigeration lines from remote condensing unit.B27 1 Water boiler 3/8" 54"B28 2 Wall shelvingB29 2 Wall shelvingB30 1 Trash receptacleB31 1 Prep counterC01 1 Type 1 Exhaust hoodC02 1 Meat resting rackC03 1 Frenchtop on conv. oven 1 1/4" 95,000 loop gas supply see FS1.2C04 2 Salamander 3/4" 35,000 58"C05 - Spare numberC06 1 Pasta cooker 3/8" 60,000 3/8" 12" 1 1/4" Indirect Floor Sink Wall loop gas supply see FS1.2C07 1 Grill - 18" 1 1/4" 45,000 loop gas supply see FS1.2C08 1 6 burner/conv oven 1 1/4" 245,000 loop gas supply see FS1.2C09 1 Spreader on cab base 1 1/4" Verify loop gas supply see FS1.2C10 1 Tubular shelfC11 1 Plancha on cab base 1 1/4" 17,500 loop gas supply see FS1.2C12 2 Fryer - 25 lb. cap. 1 1/4" 60,000 loop gas supply see FS1.2C13 4 Pot rails on hoods
C14 2 Combi-oven stacked -gas-fired 3/4" 41,000 24" 3 @ 3/4" 18" 2" Indirect Floor Sink Wall filtered.One (1) water connection per oven to be
C15 1 Type 1 Exhaust HoodC16 lot S/S wall flashingC17 1 Fire suppression systemC18 1 Prep tableC19 1 REMOTE Undercounter refrigerator - 2 door 1" Indirect Floor Sink Refrigeration lines from remote condensing unit.C20 - Spare numberC21 2 Wall shelvingC22 1 Remote printerC23 1 Hand sink 1/2" 1/2" 12" 1 1/2" Direct 18" WallC24 1 Water Filter 3/4"D01 1 Plastic shelvingD02 2 Dish cartD03 1 Pot wash sinks (3) 2" Wall Pipe drains to grease trapD04 2 Splash-mount faucets 12" spiggot 1/2" 1/2" 12" WallD05 1 Wall shelfD06 1 Hand sink 1/2" 1/2" 12" 1 1/2" Indirect Floor Sink WallD07 1 Soiled dish landing 1" Indirect Floor Sink
D08 1 Food waste scraper & control panel 3/4" 3/4" 12" 2" Wall to 1/2" @ connection.Pipe drain to grease trap. Reduce water supply
D09 1 Hose Reel & Mixing Cabinet 1/2" 1/2" 90" Wall Reel @ 90" AFFD10 - Spare numberD11 1 Rack wall shelfD12 1 Floor trough 3" Direct -3" FloorD13 1 Dishwasher 3/4" @140°F 12" 1 1/2" Indirect Floor Sink WallD14 1 Vapor hood 1" Indirect Floor SinkD15 1 Clean landingD16 1 Rack wall shelf
R01 1 Remote refrigeration rack in/out1-1/8"
S
CORRIDOR
2460
CC
G
D
Trash
F24N
SFR
EEZ
ER
Trash
Trash
B18
B01 B02B03B04
B05
B06
B07B08
B14
B09
B06
B13
B11B15
B16
B17
B21
B11
B09
B22
B23
B24
B25
B26
B27
B06
B28
B29
C01C04 C06C07C08C11C12
C13
C14
C15
C21 C22 C23 C24
D01
D02
D03
D04D05 D06
D07
D08
D11
D12
D13D14
D15
D16
C10
C03
B19
C16
C19
D09
C18
C04
C17
B12
C09C02
A15
A16
A17
A18
B30
A17a
B31
A01
A02
A03
A04
A05
A06
A07
A08
A09
A10
A11
A12
A13
A14
A14
A13
A12
A11a
A11
A11a
A11b
HWCW
CW
CW
Water supply from water filter
CW
IW
W
HW CWIW
CWWater supply from
water filter IW
HWCW
IW
IW
IW
IW
HW
CW
IW
IWIW IWIW IW IW
CW
IW
Front manifold gasconnection
Vfy waste routing withplumbing engineer
HWCW
HWCW
W
HW CW
W
IW
W
HW
IW
IW
CW
CW
CW
Water supply from water filter
IW
IW IW
To grease trap
IW
CW
HWIW
IW
IW
CW
Water supply from water chiller beneath counter
Water supply from water filter
HW
CWIW
HW
IW
HW
CWIW
IWIW
HW
CWIW
IW
IW
IW
IW
IW
IW
90"
42"
36"
24"
12"
12"
REMOTE REFRIGERATIONRACK - N.T.S.
ELECTRICALCONTROL PANEL
REFRIGERANT LINE STUB OUTWATER INLET/OUTLET
MAIN FUSED DISCONNECT
90"
42"
64"
CW
3'-0"
6"
2'-2"
1'-4"
1'-2"
6"
5'-2"
BACKSPLASH
SHELVES PERSD-021
C/L 5'-6" ELEC.
CEILING HEIGHTV.I.F.
ELECTRICAL NOTES
Note: All locations for connections, sizes and conduit runs are approximate and relative only to the foodservice equipment noted on these plans. Items not labeled either in the schedule or directly on the drawing are to be determined and verified on construction contract drawings. ALL WORK SHOWN ON THE ELECTRICAL PLANS IS THE RESPONSIBILITY OF THE GENERAL CONTRACTOR, UNLESS OTHERWISE NOTED.1. All work must be verified by site measurements and with the final equipment selection. Equipment makes and models may change and will thus affect final placement. Verify all work with foodservice equipment installer's final rough-in plans.2. Height details are for point of connection and are to be measured above finished floor level to centerline of outlet or point of connection. Stub-outs to extend 6” beyond finished walls and 6” above finished floor or top of equipment pad. All appliance connections must be verified with foodservice equipment installer's final specifications and rough-in details.3. Utilities shown and listed are the minimum required to operate equipment. Locations of any additional utilities must be located and specified by the project architect or project engineer.4. Final connections to equipment and inter-connections between equipment where necessary are to be made by electrical trades. Items of fabricated equipment which require electrical service are to be pre-wired to a junction box or terminal panel, ready for connection by electrical trades. Any variation from this, or lack of proper connection on any give item must be brought to the attention of the project architect and MSN-RCD before any changes are made or modifications done to any piece of equipment.5. All electrical materials including wire, conduit, main switches, safety cut-outs, junction boxes, fuse boxes, shunt-trip breakers, disconnect switches and controls are to be provided by electrical trades. Electrical trades to furnish and install lock-out devices on circuit breakers controlling ventilation, refrigeration and fire suppression control panels.6. Utilities are to be concealed in walls and stubbed out at appropriate locations. Do not run surface mounted conduit or wire. Electrical trades to furnish and install conduit and pull boxes for all beverage, refrigeration, and wash down system lines. Conduit to be round with minimum 24” radius bends and to terminate 4” above finished floor, 6” beyond wall, or flush with the tops of equipment pads. Pull boxes must be located every 75 feet or per every three bends, whichever occurs first.7. Electrical components of any kind, including switches, fuse boxes, panels, disconnects, conduit, or other connections must be installed so as to not interfere with the operation or use of the food-service equipment.8. Amperages indicated are for each unit shown and do not reflect any additional requirements for HP or kw listed.9. NEMA numbers must be verified with the appropriate cut sheet information before final installation of duplexes or surface mounted items. All direct connections are to be made by electrical trades.10. Motors exceeding 1 horsepower or appliances with heating elements exceeding 5.0 kw must generally be connected to 3 phase electrical service and provided with overload protection and a quick disconnect switch wherever necessary. Electrical trades must verify these requirements with project engineer before connection.11. Control and power wiring between electrical defrost evaporator, time clock, temperature control device and condensing unit by electrical trades. Verify final connection with refrigeration shop drawings and installer's final rough-in plans.12. Drain line from freezer coils are to wrapped with heater cables, taped and insulated by electrical trades.13. Walk-in lighting, door and drain heaters and fan and coil connections to be connected and inter-wired by electrical trades.14. Control and power wiring between the ventilator control panel, ventilators, exhaust and supply fan magnetic starters, shunt-trip breakers, and/or contactors, remote fire pull stations, detergent dispensing systems, fenwall detectors and other ancillary components to be shown in engineer's drawings and installed by electrical trades. Engineer to refer to ventilation shop drawings and co-ordinate with installer's final rough-in plans for all final connections and requirements.15. Fire protection system remote fire cable pull box to be recessed into wall and installed per manufacturer's and project engineer's specifications.16. Computer grade isolated and grounded wiring is required for computerized cash registers, printers, and connected devices. Verify exact locations with POS equipment supplier.
Junction box at noted height abovefinished floor
Convenience Outletfurnished with Equipment
Convenience Outletwall mounted
Convenience Outlet208-240v/1ph mounted on equipment
Safety switch to equipmentwall mounted
S
POS Connection-provide low voltage conduit & cabling per vendor
Telephone Connection
PConvenience Outlet208v/1ph wall-mounted
Drop cord from ceiling
Flex feeder (36" tail exposed)
Vaporproof light furnished with equipment
Pull box or breaker panel supplied with equipment
Junction box at noted height aspart of equipment
Waterproof stub up through floor
T
Mark Stech-NovakRestaurant
Consultation & Design
Drawing No.
Scale
1/4"=12"
AD-FS 1.3
7
of
Drawing Title
Proj
ect T
itle
Electrical Rough-insfor Kitchen Equipment
Le M
erid
ien
New
Orle
ans,
LA
Designed By
Drawn By
Reviewed By
Project Manager
Date
Revision
Project ID
CAD File Name
Plot Date
MSN/AD
MSN/AD
MSN
MSN
Dec 04-2012
Culinary Concepts
LM_NOLA_FS_121204
No.
Dat
eIs
sue
Not
es
935 Aquarius WayOakland California 94611
Phone: 510-601-7142Fax: [email protected]
ARCHITECT:
1
1
2
2
3
3
4
4
5
5
6
6
7
7
8
8
9
9
A A
B B
C C
D D
E E
F F
G G
S
CORRIDOR
2460
CC
G
D
Trash
F24N
SFR
EEZ
ER
Trash
Trash
B18
B01 B02B03B04
B05
B06
B07B08
B14
B09
B06
B13
B11B15
B16
B17
B21
B11
B09
B22
B23
B24
B25
B26
B27
B06
B28
B29
C01C04 C06C07C08C11C12
C13
C14
C15
C21 C22 C23 C24
D01
D02
D03
D04D05 D06
D07
D08
D11
D12
D13D14
D15
D16
C10
C03
B19
C16
C19
D09
C18
C04
C17
B12
C09C02
A15
A16
A17
A18
B30
A17a
B31
A01
A02
A03
A04
A05
A06
A07
A08
A09
A10
A11
A12
A13
A14
A14
A13
A12
A11a
A11
A11a
A11b
P
P
P
15.0A-120V-1P duplexconv. GFCI outlet
54" AFF
P15.0A-120V-1P duplex conv. GFCI outlet54" AFF
15.0A-120V-1P duplex conv. GFCI outlet54" AFF
P
SInterwire hoodTo Fan Motor
15.0A-120V-1P duplex conv. GFCI outlet54" AFF
S
Interwire hoodTo Fan Motor
SInterwire hoodTo Fan Motor
P
power forundershelf lightsB12
15.0A-120V-1P duplex conv. GFCI outlet54" AFF
15.0A-120V-1P duplexconv. GFCI outlet
12" AFF
65" AFF
15.0A-120V-1P duplex conv. GFCI outlet24" AFF
Item # QTY Description Manufacturer Model Electrical Ph Amps Elec. Hgt. AFF Elec. Location Elec. Info. NotesA01 1 Four head beer tap Micro Matic USA D7744PSSKRA02 1 Water carbonator Crysalli CR-UC1 120/60 1 9.6 amps 12" Wall NEMA 5-15P Vfy air floow & orientationA03 1 Still & Sparkling tap Crysalli CBR-V2A04 1 Drip tray Fabricator CustomA05 1 Beer drip tray & washer Micromatic DP-1604A06 1 Handsink Omniteam HWVA07 1 Front Load Freezer Perlick HC24FS 115/60 1 2.3 amps 12" Wall NEMA 5-15P 1/6 hpA08 1 Soiled glass center Omniteam GWS-24-MA09 1 Glasswasher Stero SGW-H-M 2@115/60 1 9.5 + 17.4 amps 12" Wall 2@Junction BoxA10 1 POS stand Omni CustomA11 2 Jockey station Omniteam RP-40P8-M 120/60 1 15.0 amps M = reduced lengthA11a 2 Scupper drain Fabricator CustomA11b 1 Glass spritzer Micromatic GR-UCM mount to underside of bar topA12 2 Soda gun By Vendor TBD
A13 2 REMOTE 37" High underbar refrigerator Omniteam 6LGS-TK-SSS-PPBRBBR-3FL-F-AS
115/60 1 2.3 amps 12" Wall Junction Box 1,700 BTUs
A14 2 REMOTE 37" High underbar refrigerator Omniteam 6LGS-TK-SSS-PPBRBBR-2FL-F-AS
115/60 1 1.7 amps 12" Wall Junction Box 1,300 BTUsA15 1 Bag-in-box system/carbinator By Vendor TBD 115/60 1 20.0 est. amps A16 1 Glycol System Chill-rite MLN-33 see FS 1.3 1 see FS 1.3 A17 1 REMOTE Walk-in cooler complex American Panel Custom 120/208/60 1 20.0 amps Verify Ceiling Junction BoxA17a 1 Evaporator fan - cooler RDT ADT 115-208/60 1 TBD Verify Ceiling Junction Box
A18 2 Keg rack furnish)New Age (Chillrite to
31842TT7B01 1 Prep counter Fabricator CustomB02 1 REMOTE Undercounter refrigerator - 2 door Fabricator Custom 120/60 1 15.0 est. amps 12" Wall NEMA 5-15P B03 1 REMOTE Undercounter refrigerator - 2 door Fabricator Custom 120/60 1 15.0 est. amps 12" Wall NEMA 5-15P B04 1 REMOTE refrigerated rail Fabricator Custom 120/60 1 15.0 est. amps 12" Wall NEMA 5-15P B05 2 Wall shelving Fabricator Custom 120/60 1 5.0 amps 66" Wall Junction BoxB06 3 Remote printer Verify Verify 120/60 1 15.0 est. amps 66" Wall NEMA 5-15P Verify utility requirements with vendor.B07 1 REMOTE Undercounter refrigerator - 2 door Fabricator Custom 120/60 1 15.0 est. amps 12" Wall NEMA 5-15P B08 1 REMOTE refrigerated rail Fabricator Custom 120/60 1 15.0 est. amps 12" Wall NEMA 5-15P B09 2 Faucet T & S Brass B-0221B10 - Spare numberB11 2 Drop-in sink Fabricator CustomB12 1 Pass-over shelving structure Fabricator Custom 120/60 1 5.0 amps 66" Wall Junction BoxB13 2 Wall shelving Fabricator Custom 120/60 1 5.0 amps 66" Wall Junction BoxB14 1 Microwave Amana RC22S 208-240/60 1 15.4 amps 54" Wall NEMA 6-20PB15 1 REMOTE Undercounter refrigerator - 2 door Fabricator Custom 120/60 1 15.0 est. amps 12" Wall NEMA 5-15P B16 1 REMOTE UndercounterFREEZER - 2 door Fabricator Custom 208/120/60 1 15.0 est. amps 12" Wall NEMA 5-15P B17 1 REMOTE Refrigerated rail Fabricator Custom 120/60 1 15.0 est. amps 12" Wall NEMA 5-15P B18 1 Warmer Equipex SEM-60 VC 208-240/60 1 3.0 kW 66" Wall NEMA 6-20PB19 2 Wall shelving Fabricator Custom 120/60 1 5.0 est. amps 66" Wall Junction BoxB20 - Spare numberB21 1 Microwave Panansonic NE-1051 120/60 1 14.0 amps 70" Wall NEMA 5-20B22 1 Prep counter Fabricator CustomB23 2 Wall shelving Fabricator Custom 120/60 1 5.0 amps 66" Wall Junction BoxB24 1 Fully automated espresso machine Schaerer Coffee Art Plus 1 208/60 1 30.0 amps 50" Wall NEMA L14-30P 3.6.9510B25 1 Water Filter Cuno CFS6135-C-SUSAB26 1 REMOTE Undercounter refrigerator - 1 door Fabricator Custom 120/60 1 15.0 est. amps 12" Wall NEMA 5-15P B27 1 Water boiler Fetco HWB-5 120-208/60 1 11.3 amps 54" Wall Junction box By vendor.B28 2 Wall shelving Fabricator Custom 120/60 1 5.0 amps 66" Wall Junction BoxB29 2 Wall shelving Fabricator Custom 120/60 1 5.0 amps 66" Wall Junction BoxB30 1 Trash receptacle By ownerB31 1 Prep counter Fabricator Custom
C01 1 Type 1 Exhaust hood Caddy AirSystems x 2SHBC-C-W-91-ND-60
120/60 1 0.24 kW Verify Ceiling Junction Box Two (2) hoodsC02 1 Meat resting rack Fabricator CustomC03 1 Frenchtop on conv. oven Jade JTRH-2FHT-36C 120/60 1 10.0 amps 24" wall 5-15P front gas manifoldC04 2 Salamander Jade JSB-36RMC05 - Spare numberC06 1 Pasta cooker Jade Rosito Bisani CPG1 front gas manifoldC07 1 Grill - 18" Jade JTRH-18B front gas manifoldC08 1 6 burner/conv oven Jade JTRH-6-36C 120/60 1 10.0 amps 24" wall NEMA 5-15P front gas manifoldC09 1 Spreader on cab base Jade JTRH-18S front gas manifoldC10 1 Tubular shelf Fabricator CustomC11 1 Plancha on cab base Jade JTRH-18P front gas manifoldC12 2 Fryer - 25 lb. cap. Jade JTFF-25-12 front gas manifoldC13 4 Pot rails on hoods Fabricator Custom see SD-029C14 2 Combi-oven stacked -gas-fired Rational SCC WE 61 G 120/60 1 15.0 amp circuit 24" Wall NEMA 5-15P Requires dedicated circuit & ground wire.C15 1 Type 1 Exhaust Hood Caddy AirSystems SHBC-C-W-48-ND-60 120/60 1 0.24 kW Verify Ceiling Junction BoxC16 lot S/S wall flashing Fabricator CustomC17 1 Fire suppression system Ansul R102 120/60 1 15.0 amps Verify Ceiling Junction box Locate manual pull stations as required.C18 1 Prep table Fabricator CustomC19 1 REMOTE Undercounter refrigerator - 2 door Fabricator Custom 120/60 1 15.0 est. amps 12" Wall NEMA 5-15P C20 - Spare numberC21 2 Wall shelving Fabricator Custom 120/60 1 5.0 amps 66" Wall Junction BoxC22 1 Remote printer Verify Verify 120/60 1 15.0 est. amps 66" Wall NEMA 5-15P Verify utility requirements with vendor.C23 1 Hand sink Advance-Tabco 7-PS-81 w/ foot pedalsC24 1 Water Filter Everpure EV9797-22 Mount on wall as high as possibleD01 1 Plastic shelving Metro MetroMaxiQD02 2 Dish cart Cambro CD2020110D03 1 Pot wash sinks Fabricator Custom D04 2 Splash-mount faucets 12" spiggot T&S Brass B-0231 w/ B-WH-6" blade handlesD05 1 Wall shelf Advance Tabco PS-18-84 D06 1 Hand sink Advance-Tabco 7-PS-81 w/ foot pedalsD07 1 Soiled dish landing Fabricator Custom w/ mushroom overshelfD08 1 Food waste scraper & control panel Salvajor S914 & MSS-LD 208/60 3 3.2 amps 12" Wall Junction Box D09 1 Hose Reel & Mixing Cabinet Fisher 1801/2985 D10 - Spare numberD11 1 Rack wall shelf Fabricator CustomD12 1 Floor trough Fabricator CustomD13 1 Dishwasher Hobart AM15T-2 208-240/60 3 45.4 amps 18" Wall Junction BoxD14 1 Vapor hood Caddy AirSystems CH-C-W-42-SD-42 600 cfmD15 1 Clean landing Fabricator Custom custom length Dwg # 020917-1D16 1 Rack wall shelf Fabricator Custom R01 1 Remote refrigeration rack RDT IRW2-7 208-230/60 3 26.0 VFY) Verify Junction Box Verify exactly location with architect and engineer.
90"
42"
36"
24"
12"
12"
REMOTE REFRIGERATIONRACK - N.T.S.
ELECTRICALCONTROL PANEL
REFRIGERANT LINE STUB OUTWATER INLET/OUTLET
MAIN FUSED DISCONNECT
90"
42"
64"
VENTILATION NOTES
THE INFORMATION SHOWN ON THE VENTILATION PLANS IS THE RESPONSIBILITY OF THE GENERAL CONTRACTOR UNLESS NOTED OTHERWISE.
1. VENTILATION REQUIREMENTS ARE RELATIVE ONLY TO ITEMIZED FOOD SERVICE EQUIPMENT. SEE CONSTRUCTION CONTRACT DOCUMENTS FOR ADDITIONALVENTILATION REQUIREMENTS. REQUIRED MAKE-UP AIR IS NOT SHOWN ON THESE PLANS.
2.DIMENSIONS ARE FOR GENERAL INFORMATION PURPOSES AND ARE APPROXIMATE INDICATIONS FROM FACE OR FINISH WALLS, FINISH FLOOR OF FINISHED CEILING. INCLUDE ALLOWANCE FOR THICKNESS OF FINISHED MATERIALS. VERIFY EXACT LOCATION, SIZE AND OTHER REQUIREMENTS WITH DIMENSIONED SHOP DRAWINGS PROVIDED BY THE KITCHEN EQUIPMENT CONTRACTOR.
3. PROVIDE AND INSTALL EXHAUST AND MAKE-UP AIR DUCTS WITH FANS. KITCHEN EQUIPMENT CONTRACTOR SHALL PROVIDE ALL EXPOSED EQUIPMENT DUCT WORK TO CEILING AND MAKE FINAL DUCT CONNECTIONS. ALL AIR SCRUBBERS, SMOG-CONTROL DEVICES, FILTRATION SYSTEMS AND NOISE ABATEMENT SYSTEMS ARE THE RESPONSIBILITY OF THE GENERAL CONTRACTOR.
4.COOKING EQUIPMENT EXHAUST SYSTEM SHALL BE DESIGNED AS A SEPARATE AND INDIVIDUAL SYSTEM. DUCT JOINTS TO BE WELDED AND GREASE PROOF. HORIZONTAL DUCTS SHALL BE PITCHED BACK TO VENTILATOR PER LOCAL CODES. EXHAUST FAN DESIGN SHALL PROVIDE FOR ALL EXHAUST SYSTEM LOSSES, INCLUDING GREASE AND VAPOR EXTRACTION FRICTION LOSS FOR SELECTED HOOD OR VENTILATOR SHOWN IN VENTILATION SCHEDULE.
5.PROVIDE A TEMPERED MAKE-UP AIR SUPPLY AND DISTRIBUTION SYSTEM TO SUPPLY AIR VELOCITIES AT ACCEPTABLE LEVELS TO AVOID DRAFTS AND FLOW DISTURBANCES UNDER THE HOOD OR VENTILATOR FROM THE WORK SIDE AREA OF COOKING EQUIPMENT. PROVIDE MAKE-UP AIR PLAN FOR APPROVAL BY MSN-RCD AND PROJECT CHEF.
6.SUPPLY AND EXHAUST IN KITCHEN AND OTHER ADJACENT AREAS SHALL BE BALANCED TO PREVENT COOKING ODORS AND WARMER AIR FROM ENTERING PUBLIC SPACES.
7.IN ADDITION TO SPECIFIC REQUIREMENTS INDICATED, PROVIDE GENERAL ROOM SUPPLY AND EXHAUST TO ALL FOOD SERVICE AREA INCLUDING STOREROOMS TO PRECLUDE SOILED MARKINGS OF CEILING OR WALLS.
8.ALL REFRIGERATION EQUIPMENT AREAS SHALL BE ADEQUATELY VENTILATED TO REMOVE GENERATED HEAT.
REFRIGERATION NOTES
REFRIGERATION SYSTEMS AND THIER CONNECTIONSARE THE RESPONSIBILITY OF THE FOODSERVICE EQUIPMENTCONTRACTOR.
PENETRATIONS SHALL BE PROVIDED BY GC, LINES RUN BY KEC AND FINAL SEAL AND CLOSURE BY GC. ALL PLACEMENT OF LINE RUNS AND INSPECTIONS SHALL BE COORDINATED WITH THE GC.
THE REFRIGERATION SERVICE AGENT SHALL SUBMIT A ROOF MOUNTPAD DESIGN TO GC CONSTRUCTED IN SUCH A WAY AS TO MINIMIZE ALL SOUND TRANSMISSION TO BUILDING INTERIOR.
SCHEDULE AND RACK DESIGN IS TYPICAL AND SUBJECT TO CHANGE.FOODSERVICE EQUIPMENT CONTRACTOR MUST VERIFY AND RESUBMIT REVISED PLANS TO SELECTED REFRIGERATION SERVICE AGENCY FORFINAL SPECIFICATIONS.
A FINAL AND REVISED SCHEDULE OF SYSTEMS AND COMPRESSORSAND ROUTING PLAN FOR RUNS AND PENETRATIONS MUST BE SUBMITTEDBY THE REFRIGERATION SERVICE AGENT FOR APPROVAL BY MSN-RCDAND ARCHITECT'S ENGINEERS BEFORE PROCEEDING WITH WORK.
REFRIGERATION & VENTILATION SYMBOLS LEGEND
Exhaust duct connection(size calcs. approximate per current equip. selection)
Remote refrigerated item connected to rack
Remote refrigerated raised rail on refrigerated base
Remote freezer compartment connected to rack
Make-up air plenum duct connection(size calcs. approximate per current equip. selection)
Mark Stech-NovakRestaurant
Consultation & Design
Drawing No.
Scale
1/4"=12"
AD-FS 1.4
7
of
Drawing Title
Proj
ect T
itle
Refrigeration &VentilationPlan View
Le M
erid
ien
New
Orle
ans,
LA
Designed By
Drawn By
Reviewed By
Project Manager
Date
Revision
Project ID
CAD File Name
Plot Date
MSN/AD
MSN/AD
MSN
MSN
Dec 04-2012
Culinary Concepts
LM_NOLA_FS_121204
No.
Dat
eIs
sue
Not
es
935 Aquarius WayOakland California 94611
Phone: 510-601-7142Fax: [email protected]
ARCHITECT:
1
1
2
2
3
3
4
4
5
5
6
6
7
7
8
8
9
9
A A
B B
C C
D D
E E
F F
G G
S
CORRIDOR
2460
CC
G
D
Trash
F24N
SFR
EEZ
ER
Trash
Trash
B18
B01 B02B03B04
B05
B06
B07B08
B14
B09
B06
B13
B11B15
B16
B17
B21
B11
B09
B22
B23
B24
B25
B26
B27
B06
B28
B29
C01C04 C06C07C08C11C12
C13
C14
C15
C21 C22 C23 C24
D01
D02
D03
D04D05 D06
D07
D08
D11
D12
D13D14
D15
D16
C10
C03
B19
C16
C19
D09
C18
C04
C17
B12
C09C02
A15
A16
A17
A18
B30
A17a
B31
A01
A02
A03
A04
A05
A06
A07
A08
A09
A10
A11
A12
A13
A14
A14
A13
A12
A11a
A11
A11a
A11b
A
B
A
B
NO. MODEL L W H MIN. CFM L W QTYHST. PR.SPEC. CFMHOOD INFORMATION EXHAUST COLLAR
C15 SHBC-C-W-48-ND-60 48" 60" 24" 1000 10" 10" 14"1.6"1000
NO. MODEL L W H MIN. CFM L W QTYHST. PR.SPEC. CFMHOOD INFORMATION EXHAUST COLLAR
C01 SHBC-C-W-91.5-ND-60x 2
91" 60" 24" 2275 22" 10" 24"1.6"2275
NO. MODEL L W H MIN. CFM L W QTYHST. PR.SPEC. CFMHOOD INFORMATION EXHAUST COLLAR
D14 CH-C-W-42-SD-42 42" 42" 24" 525 7" 7" 14"0.25"525
TYPE ITEM TEMP INFO
REMOTE 37" High underbar refrigerator A14b 35-45ºF 6LGS-TK-SSS-PPBROmniteam BBRR-2FL-F-AS
REMOTE 37" High underbar refrigerator A14a 35-45ºF 6LGS-TK-SSS-PPBROmniteam BBR-2FL-F-AS
REMOTE 37" High underbar refrigerator A13b 35-45ºF 6LGS-TK-SSS-PPBROmniteam BBR-3FL-F-AS
REMOTE 37" High underbar refrigerator A13a 35-45ºF 6LGS-TK-SSS-PPBROmniteam BBR-3FL-F-AS
REMOTE refrigerated rail B08 35-45ºF raised railREMOTE refrigerated rail B04 35-45ºF raised railREMOTE refrigerated rail B17 35-45ºF raised railREMOTE Undercounter Freezer - 2 door B16 -10-15ºF mullion coil
doorREMOTE Undercounter refrigerator - 1
B26 35-45ºF mullion coil
doorREMOTE Undercounter refrigerator - 2
C19 35-45ºF mullion coil
doorREMOTE Undercounter refrigerator - 2
B07 35-45ºF mullion coil
doorREMOTE Undercounter refrigerator - 2
B15 35-45ºF mullion coil
doorREMOTE Undercounter refrigerator - 2
B03 35-45ºF mullion coil
doorREMOTE Undercounter refrigerator - 2
B02 35-45ºF mullion coilREMOTE Walk-in cooler complex A17 35-45ºF evaporator fan
90"
42"
36"
24"
12"
12"
REMOTE REFRIGERATIONRACK - N.T.S.
ELECTRICALCONTROL PANEL
REFRIGERANT LINE STUB OUTWATER INLET/OUTLET
MAIN FUSED DISCONNECT
90"
42"
64"
FACTORY EQUIPPED
OLF
PROVIDED BY OTHERSLOOSE (FIELD INSTALLATION)
EVAPORATOR ACCESSORIES
OFF CYCLEELECO.C.
ELECTRIC
DEFROST TYPE
SEMI-HERMETIC
ZHS
SCROLLHERMETIC
COMPRESSOR TYPE
EVAPORATOR DETAILS - MODEL ADT
FIELD WIRINGFACTORY WIRING
ENGINEERING SUMMARY POWER SUPPLY: 208-230/60/3CONNECTED LOAD: 26.0 AMPS
MAX FUSE SIZE: 30 AMPSMINIMUM CIRCUIT AMPACITY: 27.8
SY
STE
M
ITE
M #
FIXTURES
RE
FRIG
. R-
COMPRESSORS EVAPORATOR COILS
TOTALSYSTEM
LOAD
DEFROST
CLOCK
REFRIGERANTLINE SIZES
(110' MAX LINE RUN)
ACCESSORIES
DESCRIPTION
TEMP
MODEL NO.
H.P
.
RATINGBTUCAP.
@90°F
TYP
E
MODEL NO.
QTY
.
FAN MOTORS HEATERS
DE
FRO
ST
TYP
E
THE
RM
OS
TAT
VA
LVE
TXV
FIX
T.
SU
CT.
@ 60 Hz @ 60 Hz @ 60 Hz
RLA V PH RLA V PH RLA V PH SUCT. LIQ.
NOTE:REFRIGERATION SYSTEM IS SIZED FOR 110' MAXIMUM LINE RUNS. IT IS THE INSTALLING CONTRACTORS RESPONSIBILITY TO FOLLOW ALL APPLICABLE CODES AND CURRENT REFRIGERATION INDUSTRY STANDARDS AND PRACTICES WHEN DETERMINING LINE SIZES, AND INSTALLING AND STARTING UP RDT EQUIPMENT.
WIRING DIAGRAM - OFF CYCLE DEFROST
L1 L2 L3
WALK-IN COOLER
UNDERBAR REFRIGERATORA1
B1
A13A
C
VERTICAL RISE DETAIL
RACK MODEL NO: IRW2-7
DESCRIPTION: INDOOR WATER COOLED
DIMENSIONS: 90" (L) X 42" (W) X 64" (H)
WEIGHT: 870 LBS.
FLOW RATE: 11.0 GPM
PRESSURE DROP: 1.4 PSIG
INCOMING WATER TEMP: 40-80 DEG FI
MAXIMUM OPERATING PRESSURE: 150 PSI
THR: 54,996 BTU/H (INTO WATER)
HEAT EMISSION: 1,041 BTU/H (INTO AIR)
WATER INLET/OUTLET: 1-1/8"
IRW SERIES ENGINEERING SPECIFICATIONS
SYSTEM DETAILS
Multi compressor, water-cooled. the refrigeration package shall be a pre-engineered and factory assembled unit, trade name "IRW", as manufactured by Refrigeration Design Technologies, 1808 FM 66, P.O. Box 622, Waxahachie 75168. Phone: (972) 937-3215; Fax: (972) 937-0970.
1. Water-Cooled Refrigeration SystemA. The RDT UL-Listed "water-cooled" refrigeration system shall be housed in a single, compact structural steel frame. The unit shall include a water-cooled condenser sized to operate at 15 degree TD. Entire frame shall be pre-assembled welded, cleaned and painted with two coats of polyurethane.B. Compressor units shall be mounted individually on one common structural steel frame. Each unit shall be hermetic type designed for rack installations. The units shall be factory assembled and designed to operate with the coolant specified. Medium and low temperature units shall use R-404a refrigerant. C. The water circuits of the condensers shall be valved separately and pre-piped to a common supply and return header. The header shall employ a bronze ball valve for connection to building condenser or chilled water supply. D. Compressor units shall include a control panel oversized shell and tube water-cooled condenser and receiver. The control panel shall contain all the necessary controls for food service fixtures and evaporators and shall be factory-wired to the motor compressors.E. Each compressor shall feature adjustable water regulators, suction filter, sight glass, drier, liquid line inlet and outlet valves and stainless steel superhose connections.F. Compressors shall feature a separate power relay for defrost circuits, interlocked with the compressor relay, to insure full pumpdown prior to the defrost cycle and prevent simultaneous operation of compressor and heater.
2. Evaporator CoilsA. Evaporator coils shall be direct expansion type fabricated of copper tubes with aluminum fins.B. All evaporator coils shall be provided with solenoid valve, thermostatic expansion valve suction "p" trap and thermostat.
3. Electrolysis PreventionA. Each unit shall be equipped with a dielectric union or flexible rubber connection at the water entry point to prevent electric conduction and extend equipment life. Dielectric unions shall be used to connect the water entry point to building water supply.
4. Pre-PipingA. All refrigerant lines shall be extended to one side of the package in a neat orderly manner.
B. All tubing shall be securely supported and anchored with non-corrosive coated clamps.C. Joints must be brazed not soldered.D. All piping and controls shall be factory pressure tested with nitrogen at 150 PSI.E. Water supply and return header shall be installed using copper tubing.
5. Control PanelA. The panel shall be delivered complete with main fused disconnect, circuit breakers, contactors and time clocks (where required) wired for single point power connection.
General InformationContractors shall verify all dimensions and coordinate with other trades. Installation shall be performed according to legal codes.
Refrigeration ContractorAll copper tubing to be refrigerant grade A.C.R. or type "L". silfos brazing should be used for all refrigerant piping. soft solder is not acceptable. All piping to be pressure tested with nitrogen at 300 PSI after the condensing unit and coil have been connected, the balance of the system shall be leak tested with the valves open at 200 PSI. The complete system shall be evacuated with vacuum pump. Each unit should be charged tested and adjusted to assure operation. Refrigeration contractor should provide and install the drain-line heater in freezer. Heater shall be connected by electrical contractor.
Electrical ContractorElectrical contractor to provide power to refrigeration package and connect control and defrost system as called for in the wiring diagram. Electrical contractor to provide 6-wire color-coded service from the time clock to blower coil in fixture when electric defrost is used, either cooler or freezer. Electrical contractor to connect drain-line heater in the freezer.
Plumbing ContractorPlumbing contractor to supply and connect building condenser water to supply and return compressor rack. Plumbing contractor to provide A.C.R. or "L" copper drain lines for walk-in refrigerator and freezer, pitched 1/4" per foot of run. Trap drain-line outside of refrigerator space to avoid entrance of warm, moist air. Plumbing contractor to provide individual drain-line for each evaporator unless other arrangements made.
24.3 26.0 26.0
8" A
.F.F
.
INSULATED SUCTION LINE & LIQUID LINE
REFRIGERATION CONT'R TO SEAL PENETRATION
COPPER DRAIN LINE
INSULATED WALL
COILAIR FLOW
COPPER UNION
15"
ALL DRAIN LINES REQUIRE AMINIMUM OF 1/4" FALL PER FT.
TRAP(TERMINATED 1"ABOVE FLOOR SINK)
EVAPORATOR MOUNTING DETAIL (TYPICAL)
A13B
A17
404A ASE24C3E 0.3 4.2 208 H1 400035 25 1/2 3/8
20 10 404A
BY OTHERS O O O
D1 REFRIG RAISED RAILB04
35 25 404A
RST40C1E 208 1 H0.4 5.1 5990
ADT-052 0.9 - - - O.C.1 115 1
A2 A14A
404A
RST80C1E 1.5 5.7 208 H3 9640
20 10
F F F
B2 A14B
35 25 404A RST55C1E 208 1 H0.6 6.8 8490
REFRIG RAISED RAILD2
E1
B08
E3
U/C REFRIGERATORB02
B07
F1 B15
REFRIG RAISED RAILD3 B17
E2 B03
UNDERBAR REFRIGERATOR
UNDERBAR REFRIGERATOR
UNDERBAR REFRIGERATOR
BY OTHERS
BY OTHERS
BY OTHERS
404A35 25
404A35 25
404A35 25
1700
1300
1700
1300
404A35 25 5815 RST40C1E 0.4 5.1 208 H1 5900
404A20 10
3463
1800
3463
F2 B16
G1 B26
G2 C19
U/C REFRIGERATOR
U/C REFRIGERATOR
U/C REFRIGERATOR
U/C FREEZER
U/C REFRIGERATOR
U/C REFRIGERATOR
35 25 404A
35 25 404A
35 25 404A
35 25 404A
35 25 404A
2440
2440
2440
2440
2440
1200
2440
BY OTHERS
BY OTHERS
BY OTHERS
BY OTHERS
BY OTHERS
BY OTHERS
BY OTHERS
BY OTHERS
BY OTHERS
BY OTHERS
4.2
5.1
5.7
5.1
4.2
5.1
6.8
5.7
6.8
5.1
5.7
1/2 3/8
7/8 3/8
5/8 3/8
7/8 3/8
O O O
O O O
O O O
O O O
O O O
O O O
O O O
O O O
O O O
O O O
O O O
O O O
O O O
15'
Insulate suction lines with 3/4" wall Armaflex insulation.
All joints brazed with minimum 15% silver content brazing rod.
Install "P" trap on suction line every 15' vertical rise.
Not to exceed 45' vertically over all.
"P" Trap
Slope Toward CompressorSuction Line
Liquid Line
Suction Line
Liquid Line
15'
"P" Trap
15'
"P" TrapADT
SizeA
Inches
B
Inches
C
Inches
Approx.
Net Wt.
Lbs.
DIMENSIONS ELECTRICAL DATA
Qty.Motors 115V
EC Motor Fan Amps
CONNECTIONS
(Inches)
Coil Inlet Suction Drain 208V
D
Inches
AIR
ENDELECTRICALREFRIGERANT
END
14.94"
C D
B
A
13.44
12"
6.13"
1.74"
6.12"
052 29-1/2 31 11/2 OD 7/8 OD17-1/4 - - 3/4 MPT 0.9 0.5
R
ASSEMBLY
LISTEDFINAL
T-Stat
Com.
N/O Com.
120v
FANMOTOR
M2
SWITCHON/OFFEVAP
M1
115/60/1
VALVESOL
ASE24C3E 0.3 4.2 208 H1 4000
ASE24C3E 0.3 4.2 208 H1 4000
4.2 4.2
4.2 4.2
1/2 3/8
1/2 3/8
REQ'DFIXTRBTU/H
REMOTE REFRIGERATION
1: Bar Equipment Elevation— 1/2"=12"
4: Prep Area Elevation — 1/2"=12"
Mark Stech-NovakRestaurant
Consultation & Design
Drawing No.
Scale
1/4"=12"
AD-FS 1.5
7
of
Drawing Title
Proj
ect T
itle
Selected ElevationsKitchen Equipment
Le M
erid
ien
New
Orle
ans,
LA
Designed By
Drawn By
Reviewed By
Project Manager
Date
Revision
Project ID
CAD File Name
Plot Date
MSN/AD
MSN/AD
MSN
MSN
Dec 04-2012
Culinary Concepts
LM_NOLA_FS_121204
No.
Dat
eIs
sue
Not
es
935 Aquarius WayOakland California 94611
Phone: 510-601-7142Fax: [email protected]
ARCHITECT:
1
1
2
2
3
3
4
4
5
5
6
6
7
7
8
8
9
9
A A
B B
C C
D D
E E
F F
G G
1/2"=12"
B19
Millwork bar by G.C.Fabricator to coordinate construction with foodservice equipment
Ceiling HeightV.I.F.
Ceiling HeightV.I.F.
Ceiling HeightV.I.F.
Ceiling HeightV.I.F.
Ceiling HeightV.I.F.
Ceiling HeightV.I.F.
Ceiling HeightV.I.F.
Ceiling HeightV.I.F.
Trashcan inside cabinet
3'-6
"
ADA compliantbar section
A12 A11A11
A12POS system
A10
A07 A06 A08 A09
A05
A01 A04 A03
A02
Millwork fabricator to provide louver panel in door for adequate air flow
A13 A14 A14 A13
B12
POS printer
B29B28 B27
B24
B26B25
B23
B22
B30B31
B06
POS printer
B06
B05B12 B04
B02B03Concrete curb by G.C.
B08 B14
B09
POS printer
B06
B13
B11
B01
B07
B09POS printer
B06
B13
B14
B01
B15 B16
B17
B18
B01
3'-0
"6"
3'-0
"6"
B19
B18(wall mnt'd)
B11B11
B01Concrete curb by G.C.
Concrete curb by G.C.
B21
S/S enclosure panels from top of exhaust hood to finished ceiling, by KEC
C01
C13
S/S wall panels from top of floorbase to bottom of exhaust hood,
by KEC
C10
C12
C11 C08 C09 C07 C03 C06
C04
Concrete curb by G.C.
FRP wall surface
Open to kitchen
Baskets provided insmallwares package
Baskets provided insmallwares package
3'-2
"
LEAVE OPEN FORLINEN HAMPERS
4'-1
1"
Vfy clearances
A11a A11bA11a
2: Bar Equipment Elevation— 1/2"=12"
3: Pass-Thru Elevation— 1/2"=12" 5: Prep Area Elevation — 1/2"=12"
6: Prep Area Elevation — 1/2"=12" 7: Prep Area Elevation — 1/2"=12" 8: Cooking Equipment Elevation — 1/2"=12"FS 1.5FS 1.5
FS 1.5 FS 1.5FS 1.5
FS 1.5
FS 1.5 FS 1.5
Mark Stech-NovakRestaurant
Consultation & Design
Drawing No.
Scale
1/4"=12"
AD-FS 1.6
7
of
Drawing Title
Proj
ect T
itle
Selected ElevationsKitchen Equipment
Le M
erid
ien
New
Orle
ans,
LA
Designed By
Drawn By
Reviewed By
Project Manager
Date
Revision
Project ID
CAD File Name
Plot Date
MSN/AD
MSN/AD
MSN
MSN
Dec 04-2012
Culinary Concepts
LM_NOLA_FS_121204
No.
Dat
eIs
sue
Not
es
935 Aquarius WayOakland California 94611
Phone: 510-601-7142Fax: [email protected]
ARCHITECT:
1
1
2
2
3
3
4
4
5
5
6
6
7
7
8
8
9
9
A A
B B
C C
D D
E E
F F
G G
1/2"=12"
C17
Ceiling HeightV.I.F.
Ceiling HeightV.I.F.
Ceiling HeightV.I.F.
Ceiling HeightV.I.F.
S/S enclosure panels from top of exhaust hood to finished ceiling, by KEC
D09
Mount water filter as high as possible on wall
C24
C24POS
printer
C21
C23
C19 C19Shelf with upturnon back per
standard details
C15
S/S wall panels from top of floor base to bottom of exhaust hood, by KEC
C14
Verify waste routing withplumbing engineer
P.C. to pipe drains to grease trap
D03
D05 D04
Ansultanks
FRP wall surface FRP wall surface FRP wall surface
FRP wall surface
S/S enclosure panels from top of exhaust hood to finished ceiling, by KEC
D11
D14
D08
D07
D13
D16
D15
Glass rack slides
Back & sidebracing
Back & side bracing
Glass rack slides
Back & sidebracing
Back & side bracing
9: Cooking Equipment — 1/2"=12" 10: Pot Wash Sink Elevation — 1/2"=12" 11: Ware Washing Elevation — 1/2"=12"FS1.6
12: Ware Washing Elevation — 1/2"=12"
FS1.6FS1.6
FS1.6