Page 1: Project Plan 1.Project Organization 2.Roles & Responsibility 3.Development Schedule 4.Resource Allocation 5.Cost Estimation 1.Project Organization 2.Roles

Ⅲ. Project PlanⅢ. Project Plan

1. Project Organization

2. Roles & Responsibility

3. Development Schedule

4. Resource Allocation

5. Cost Estimation

1. Project Organization

2. Roles & Responsibility

3. Development Schedule

4. Resource Allocation

5. Cost Estimation

Page 2: Project Plan 1.Project Organization 2.Roles & Responsibility 3.Development Schedule 4.Resource Allocation 5.Cost Estimation 1.Project Organization 2.Roles

Copyright © 2008 Samsung SDSA Inc. All rights reserved | Confidential

Ⅲ. Project Plan1. Project Organization1. Project Organization

20/28

Project OwnerProject Owner

Business SideBusiness Side Bill Higdon

Jay Reynolds

Bill Higdon

Jay Reynolds

Project ManagerProject Manager

Jim DavisJim Davis

Hangwoo Lee Hangwoo Lee

SDSA ConsultingSDSA Consulting

Project Leader: Youngrak Cho

Web Developer: 2 TBD

Web Designer: TBD

ABAP: TBD

Project Leader: Youngrak Cho

Web Developer: 2 TBD

Web Designer: TBD

ABAP: TBD

Steering CommitteeSteering Committee

CSD: Brian Chi

Chris Kim

SDSA: Sungkwon Kim

CSD: Brian Chi

Chris Kim

SDSA: Sungkwon Kim

Technical PMTechnical PM

Josh Kim Josh Kim

Business SideBusiness SideIS TeamIS Team

Project Leader: Heetae Shin

Web Developer: Myungjun Cha

Project Leader: Heetae Shin

Web Developer: Myungjun Cha

Page 3: Project Plan 1.Project Organization 2.Roles & Responsibility 3.Development Schedule 4.Resource Allocation 5.Cost Estimation 1.Project Organization 2.Roles

Copyright © 2008 Samsung SDSA Inc. All rights reserved | Confidential

Ⅲ. Project Plan2. Roles & Responsibility2. Roles & Responsibility

21/28

Title Role

Project Owner- Ownership of this project & give direction of the project - Decision making for mission critical issues

Project Manager

- Lead the project & day-to-day project management- Gathering & defining customer’s requirements- Production system roll-out

Technical PM

- Give direction for system design - Design Review- Test Plan review and supervising the test

Dev. Leader

- System configuration and function design for each system- Data Modeling and Algorithm Design- Interface between system Design- Database Design- Integration Test & user training- Data Modeling and Documentation

Web Developer - Implementation- JSP Coding & Interface Programming

SAP Developer

- Data Modeling- Program Definition & ABAP Coding- Documentation

Quality Engineer - Data collection test

Web Designer- Design page layout and graphics (HTML, Images)- User interface design

Page 4: Project Plan 1.Project Organization 2.Roles & Responsibility 3.Development Schedule 4.Resource Allocation 5.Cost Estimation 1.Project Organization 2.Roles

Copyright © 2008 Samsung SDSA Inc. All rights reserved | Confidential

Ⅲ. Project Plan3. Development Schedule3. Development Schedule

22/28

Phases ActivityWeek *

Documentation1 2 3 4 5 6 7 8 9 10 11 12

Initiation - Project Staffing & Planning Project Planning

Analysis

- Current Status Analysis System Configuration

- Requirements Definition Requirements Definition

- To-be Modeling To-Be Process

Design

- Navigation Design Navigation Structure

- System Design & DB Design ERD, Storyboard

Development

- Development

- Interface ProgrammingImage, HTML files

- Coding & Unit Testing JSP Source

Release

- Integration TestAdditional Requirements

- User Validation User Manual

- System Open & Monitoring

Page 5: Project Plan 1.Project Organization 2.Roles & Responsibility 3.Development Schedule 4.Resource Allocation 5.Cost Estimation 1.Project Organization 2.Roles

Copyright © 2008 Samsung SDSA Inc. All rights reserved | Confidential

Ⅲ. Project Plan4. Resource Allocation4. Resource Allocation

23/28

Role Name

Week

M/W1 2 3 4 5 6 7 8 9

10

11

12

Optimizer

Project Leader TBD 13 weeks

Web Developer TBD 11 weeks

Web Developer TBD 11 weeks

SAP Developer 7 weeks

Communicator

Project Leader TBD 12 weeks

Web Developer TBD 10 weeks

Programmer TBD 10 weeks

SAP Developer 6 weeks

KPI

Project Leader TBD 11 weeks

Web Developer TBD 10 weeks

SAP Developer 17 weeks

CommonPM 7 weeks

Web Designer Sangsoo Oh 9 weeks

M/W Total Weeks

Page 6: Project Plan 1.Project Organization 2.Roles & Responsibility 3.Development Schedule 4.Resource Allocation 5.Cost Estimation 1.Project Organization 2.Roles

Copyright © 2008 Samsung SDSA Inc. All rights reserved | Confidential

Ⅲ. Project Plan3. Cost Estimation3. Cost Estimation

Resource Requirement Duration Total (US$)

Project Leader 6 weeks $38,400

KPIEvaluator

MAP Developer 6 weeks $33,600

Web Developer 9 weeks $50,400

Web Designer 4 weeks $0

SAP Developer 6 weeks $0

ASCCommunicato

r

ServiceNetwork

Simulator

Total 32 weeks $122,400

24/28

Page 7: Project Plan 1.Project Organization 2.Roles & Responsibility 3.Development Schedule 4.Resource Allocation 5.Cost Estimation 1.Project Organization 2.Roles

Ⅳ. Appendix (ASC optimization)Ⅳ. Appendix (ASC optimization)

1. Estimate Product Sell-Through Distribution

2. Forecast Service Requests per Region

3. Coverage Simulation & Result Feedback

1. Estimate Product Sell-Through Distribution

2. Forecast Service Requests per Region

3. Coverage Simulation & Result Feedback

Page 8: Project Plan 1.Project Organization 2.Roles & Responsibility 3.Development Schedule 4.Resource Allocation 5.Cost Estimation 1.Project Organization 2.Roles

Copyright © 2008 Samsung SDSA Inc. All rights reserved | Confidential

Estimate Product Sell-Thru DistributionEstimate Product Sell-Thru Distribution11 ProceduresProcedures

Distribute Sell-Through

of Each Stores onto

Coverage Zip Codes

Apply Mathematical

Modeling Techniques

60 60 60 60 60

60 60 60 60 60

80 80 80 80 8060

60 60 60 60

80 80 80 80 8060

60 60 60 60

80 80 80 10080

1008060

10060

10060

10060

60

80 80 80 10080

10080

100 100 100

80 80 80 10080

10080

100 100 100

100 100 100 100 100

100 100 100 100 100

26/28

Page 9: Project Plan 1.Project Organization 2.Roles & Responsibility 3.Development Schedule 4.Resource Allocation 5.Cost Estimation 1.Project Organization 2.Roles

Copyright © 2008 Samsung SDSA Inc. All rights reserved | Confidential

Forecast Future Service Requests per RegionForecast Future Service Requests per Region22 ProceduresProcedures

Combine Sell-Through

Distribution & Error Ratio

Extract Regions Exposed

to Service Overflow

27/28

Sell-Thru Distribution

Product Error Ratio

+

Service Requests Forecast

Page 10: Project Plan 1.Project Organization 2.Roles & Responsibility 3.Development Schedule 4.Resource Allocation 5.Cost Estimation 1.Project Organization 2.Roles

Copyright © 2008 Samsung SDSA Inc. All rights reserved | Confidential

Coverage Simulation & Results FeedbackCoverage Simulation & Results Feedback33 ProceduresProcedures

Extract Sell-Thru for Each

Service Zone

Distribute Sell-Thru to

Each Zip Code (Modeling)

Service Forecast & ASC

Optimization

Base Data Regression by

Feedback Repair History &

User Registration

28/28

Marketing Information

Estimated Distribution

Zip Code 1

Zip Code 2

Zip Code 3

Zip Code n

Population

Economic Level

Region

TV

Monitor

Printer

HA

Within 5 miles

Demo-graphics

Product

Sell-Thru

Within 10 miles

Within 25 miles

No. of

Stores

+

- Product Quality- Simulation Factor

ASC 1

ASC 2

ASC 3

ASC n

Service Forecast &

ASC Optimization

RepairHistory

UserRegistratio

n Back