Central Maine Power Local System Plan
Presentation
Planning Advisory Committee Meeting
November 19, 2008
2
2
2
Local System Plan (LSP) Communication
Per Attachment K – Local, this LSP presentation:
• Describes projected improvements to non-PTF that are needed to maintain reliable customer service.
• LSP is presented at a Planning Advisory Committee meeting once a year
• PAC, Transmission Customers, and other Stakeholders have 30 days to provide written comments for consideration to CMP
– CMP’s contact:David M. ConroyManager System PlanningCentral Maine Power Company83 Edison DriveAugusta, Maine 04336 (email: [email protected])
3
3
3
LSP Communication cont.
• Each PTO is individually responsible for publicly posting and updating the status of its respective LSP and the transmission projects list on a website in a format similar to the RSP project list
• The ISO-NE RSP project list contains links to each individual PTO’s transmission project list
• CMP’s LSP project list is located at:
http://www.cmpco.com/SuppliersAndPartners/TransmissionServices/CMPTransmissionSvc/lsp.html
4
4
4
CMP LSP Project List
• Central Maine Power will update the LSP project list at least annually.
• A presentation of the LSP will be made annually.
• LSP Project List is a cumulative listing of proposed transmission solutions intended to meet identified needs.
• Similar to PTF projects in the RSP, the LSP project list contains a status of each non-PTF project:
• Concept• Proposed• Planned• Under Construction• In-Service
5
5
5
CMP’s Local System Planning Process
• All CMP system upgrades are determined in accordance with Central Maine Power Company Transmission Planning Criteria.
• Planning studies can result from:– Periodic Assessment of CMPs 14 Local Planning Areas– Load Growth– Retail or Wholesale Customer Request – Generator Interconnection Request– System-Wide Contingency Analysis
• Studies may utilize both ISO-NE Library Base Cases and/or Local CMP Base Cases.
• Generator Interconnections on the non-PTF Transmission System are guided by the CMP Transmission & Distribution Interconnection Requirements for Generation.
6
6
6
LSP ProjectsNeed Projected
In-Service Date
Major
Project
Project Status Needs Assessment Solutions
Load Growth/
Sub-Area Study
June 2009 Boothbay
Area Reliability
Study
Newcastle
Substation
Under Construction
Several transmission elements could overload under normal operating conditions in 2010
Add 2nd transformer, re-rate five 34.5 kV lines, add 115 kV breakers, add 5.4 MVAR capacitor bank
Load Growth/
Sub-Area Study
May 2009 Edgecomb
Substation
Under Construction
Potential widespread low voltage, post-contingency
Add 34.5 kV breakers, add 5.4 MVAR capacitor bank
Load Growth/
Sub-Area Study
February
2009
Boothbay
Substation
Under Construction
Potential Low Voltage, post-contingency
Add 5.4 MVAR capacitor bank
Load Growth/
Sub-Area Study
December
2008
Damariscotta
Substation
Under Construction
Potential Low Voltage, post-contingency
Add 3.6 MVAR capacitor bank
7
7
7
LSP ProjectsNeed Projected
In-Service Date
Major
Project
Project Status Needs Assessment Solutions
Load Growth/
Sub-Area Study
2010 Augusta
Area Reliability
Study
Line Re-ratings
Proposed Several transmission elements could overload under normal operating conditions
Re-rate 34 kV line Sections 39 & 41
Load Growth/
Sub-Area Study
2011 Bowman St Substation
Proposed Potential Bowman St 115/34.5 kV transformer overloaded and low voltage post-contingency
Add 2nd 115 115/34.5 kV transformer
Load Growth/
Sub-Area Study
2011 Maxcys
Substation
Proposed Low voltages following loss of Maxcys 115/34.5 kV transformer
Add second transformer at Maxcys
Coordinate w/MPRP
Load Growth/
Sub-Area Study
December 2008
Augusta East Side Substation
Under Construction
115 kV Line Section 88 fault results in loss of 115/34.5 kV supply at Augusta East Side and low voltages
Replace Augusta East Side 115 kV switch with a circuit breaker
8
8
8
LSP ProjectsNeed Projected In-
Service DateMajor
Project
Project Status Needs Assessment Solutions
Load Growth/
Sub-Area Study
2011 Berwick - Lebanon
Area Reliability
Study
Bassett Substation
Proposed Experiencing high load growth, thermal restriction on Section 118
Add 2nd 34.5 kV line from Quaker Hill to Bassett, new Bassett S/S
Load Growth/
Sub-Area Study
2013 Berwick Substation
Proposed Load growth, inadequate transformer capacity
Add 34.5 kV transmission line Bassett to Berwick, new Berwick S/S
Load Growth/
Sub-Area Study
2012 New Lebanon Substation
Proposed Load growth in Lebanon area will exceed area capacity
Add new Lebanon S/S, add 34.5 kV transmission line from Butler’s Corner
Load Growth/
Sub-Area Study
2010 High St
Substation
Proposed Thermal restrictions on transmission elements
Re-rate S114, S112A, S114A & S185
9
9
9
LSP ProjectsNeed Projected
In-Service Date
Major
Project
Project Status Needs Assessment Solutions
Load Growth/
Sub-Area Study
2010 Camden-Rockland
Area Reliability
Study
Camden Substation
Proposed Low voltage Add 5.4 MVAR capacitor bank
Load Growth/
Sub-Area Study
2011 Park St Substation
Proposed Low voltage Add 5.4 MVAR capacitor bank
Load Growth/
Sub-Area Study
2011 Meadow Rd Substation
Proposed Low voltage Add 10.8 MVAR capacitor bank
Load Growth/
Sub-Area Study
2012 Highland
Substation
Proposed Need for post-contingent support in the area provided by a new 34 kV line.
•New 34 kV transmission line to Meadow Rd•Add 1 mile 34.5 kV line to separate Warren – Waldoboro line
10
10
10
LSP ProjectsNeed Projected
In-Service Date
Major
Project
Project Status Needs Assessment Solutions
Load Growth/
Sub-Area Study
2008 & 2009 Lewiston-Auburn
Area Reliability
Study
Line
Re-ratings
Under Construction
Potential 34.5 kV line overloads for normal operating conditions
Re-rate five 34 kV lines: Sections 41, 45, 46, 50, & 72
Load Growth/
Sub-Area Study
2009 Hotel Road Substation
Proposed Potential post-contingency low voltages & overload of Hotel Rd 115/34.5 kV transformer
Install 2nd 115/34 kV transformer & 115 kV breaker at Hotel Road
Load Growth/
Sub-Area Study
2012 Gulf Island - Lewiston Lower Substations
Planned Overloading of Lewiston - Auburn Downtown Transmission Corridor
Reinforce Gulf Island – Lewiston Lower transmission system via new 115 kV transmission line.
Coordinate w/MPRP
Load Growth/
Sub-Area Study
2009 Leeds Substation
Planned Low voltage and transformer loading at Turner
Leeds 115/34.5 kV substation
11
11
11
LSP ProjectsNeed Projected
In-Service Date
Major
Project
Project Status Needs Assessment Solutions
Load Growth/
Sub-Area Study
2011 & 2012 Saco Bay
Area
Reliability
Study
New Ross Road & Goosefare Substations
Planned Additional 115 kV transformer capacity and voltage support is needed in the Saco Bay Area. Loss of Section 193 violates CMP’s loss of load criterion.
New 115 kV double-circuit line from Louden to Old Orchard Beach
New 115/34.5 kV Substation in Old Orchard Beach
Load Growth/
Sub-Area Study
June 2010 Section 174 Planned 34.5 kV line overload & condition
Rebuild Section 174
Load Growth/
Sub-Area Study
2013 Portland - North
Area Reliability
Study
2nd Portland Loop
Concept Support load growth in the Portland-North Area
Study started.
Potential for a 115 kV transmission line from Yarmouth to East Deering with 115/34.5 kV S/S
Coordinate w/MPRP
12
12
12
LSP ProjectsNeed Projected
In-Service Date
Major Project
Project Status Needs Assessment
Solutions
Load Growth/
Sub-Area Study
2012 Mid-Coast Reliability Study
Belfast Breakers
Proposed Loss of Section 86 exceeds CMP’s loss of load criterion and results in low voltages
•Add 115 kV breakers at Belfast•Build ~ 1 mile 115 kV tap line•Add 10.8 MVAR 34.5 kV capacitor bank
•Coordinate w/MPRP
Generator Interconnect
2009 ISO-NE Queue # 138
Under Construction
Meet Interconnection Request & Implement PPA requirements
•Rebuild Bigelow Substation•Wyman Hydro Sect 215 termination•Re-rate Sect 215•Several area capacitor banks
Generator Interconnect
2009 ISO-NE Queue # 197 RH
Concept Request to connect 55 MW to CMP 34.5 kV Section 54 north of Rumford 115 kV Substation
Undergoing System Impact Study
13
13
13
LSP ProjectsNeed Projected
In-Service Date
Major Project
Project Status Needs Assessment Solutions
Generator Interconnect
2012 ISO-NE Queue # 272
Concept Interconnection Request for 100 MW to CMP 115 kV Section 222 north of Wyman Hydro Substation
Undergoing Feasibility Study
Generator Interconnect
2012 ISO-NE Queue # 272
Concept Interconnection Request for 68 MW to CMP 34.5 kV Section 54 north of Rumford 115 kV Substation
Undergoing Feasibility Study
Generator Interconnect
2009 ISO-NE Queue # 215 LF
Concept Interconnection Request for 75 MW to CMP 34.5 kV Section 59 north of Rumford 115 kV Substation
Undergoing System Impact Study
Generator Interconnect
2010 ISO-NE Queue # 244 HP
Concept Interconnection Request for 156 MW to CMP 115 kV Section 215
Undergoing Feasibility Study