1 14 Material Requirements Planning (MRP) and ERP PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint slides by Jeff Heyl

Upload: edgardo-atlee

Post on 30-Mar-2015

263 views

Category:

Documents


10 download

TRANSCRIPT

Page 1: 1 14 Material Requirements Planning (MRP) and ERP PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations

1

1414 Material Requirements Planning (MRP) and ERP

Material Requirements Planning (MRP) and ERP

PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e

PowerPoint slides by Jeff Heyl

Page 2: 1 14 Material Requirements Planning (MRP) and ERP PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations

2

Outline

Dependent Inventory Model Requirements Master Production Schedule Bills of Material Lead Times for Components

MRP Structure MRP Management MRP In Services Enterprise Resource Planning (ERP)

Advantages and Disadvantages of ERP Systems

Page 3: 1 14 Material Requirements Planning (MRP) and ERP PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations

3

Learning Objectives

1. Develop a product structure

2. Build a gross requirements plan

3. Build a net requirements plan

4. Describe MRP II

5. Describe closed-loop MRP

6. Describe ERP

Page 4: 1 14 Material Requirements Planning (MRP) and ERP PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations

4

Wheeled Coach Largest manufacturer of ambulances

12 major ambulance designs 18,000 different inventory items 6,000 manufactured parts 12,000 purchased parts

Four Key Tasks Material plan must meet both the

requirements of the customer and the capabilities of production

Plan must be executed as designed Minimize inventory investment Maintain excellent record integrity

Page 5: 1 14 Material Requirements Planning (MRP) and ERP PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations

5

Dependent Demand The demand for one item is related

to the demand for another item Given a quantity for the end item,

the demand for all parts and components can be calculated

In general, used whenever a schedule can be established for an item

MRP is the common technique

Page 6: 1 14 Material Requirements Planning (MRP) and ERP PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations

6

Dependent Demand

1. Master production schedule

2. Specifications or bill of material

3. Inventory availability

4. Purchase orders outstanding

5. Lead times

Effective use of dependent demand inventory models requires the following

Page 7: 1 14 Material Requirements Planning (MRP) and ERP PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations

7Figure 14.1

Change production

plan?Master production schedule

ManagementReturn oninvestmentCapital

EngineeringDesigncompletion

Aggregate production

plan

ProcurementSupplierperformance

Human resourcesManpowerplanning

ProductionCapacityInventory

MarketingCustomerdemand

FinanceCash flow

The Planning Process

Page 8: 1 14 Material Requirements Planning (MRP) and ERP PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations

8

The Planning Process

Figure 14.1

Is capacity plan being

met?

Is execution

meeting the plan?

Change master

production schedule?

Change capacity?

Change requirements?

No

Execute material plans

Execute capacity plans

Yes

Realistic?

Capacity requirements plan

Material requirements plan

Master production schedule

Page 9: 1 14 Material Requirements Planning (MRP) and ERP PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations

9

Master Production Schedule (MPS)

1. A customer order in a job shop (make-to-order) company

2. Modules in a repetitive (assemble-to-order or forecast) company

3. An end item in a continuous (stock-to-forecast) company

Can be expressed in any of the following terms:

Page 10: 1 14 Material Requirements Planning (MRP) and ERP PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations

10

MPS Examples

Gross Requirements for Crabmeat Quiche

Gross Requirements for Spinach Quiche

Day 6 7 8 9 10 11 12 13 14 and so onAmount 50 100 47 60 110 75

Day 7 8 9 10 11 12 13 14 15 16 and so onAmount 100 200 150 60 75 100

Table 14.1

For Nancy’s Specialty Foods

Page 11: 1 14 Material Requirements Planning (MRP) and ERP PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations

11

Bills of Material

List of components, ingredients, and materials needed to make product

Provides product structure Items above given level are called

parents Items below given level are called

children

Page 12: 1 14 Material Requirements Planning (MRP) and ERP PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations

12

BOM Example

B(2) Std. 12” Speaker kit C(3)

Std. 12” Speaker kit w/ amp-booster1

E(2)E(2) F(2)

Packing box and installation kit of wire,

bolts, and screws

Std. 12” Speaker booster assembly

2

D(2)

12” Speaker

D(2)

12” Speaker

G(1)

Amp-booster

3

Product structure for “Awesome” (A)

A

Level

0

Page 13: 1 14 Material Requirements Planning (MRP) and ERP PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations

13

BOM Example

B(2) Std. 12” Speaker kit C(3)

Std. 12” Speaker kit w/ amp-booster1

E(2)E(2) F(2)

Packing box and installation kit of wire,

bolts, and screws

Std. 12” Speaker booster assembly

2

D(2)

12” Speaker

D(2)

12” Speaker

G(1)

Amp-booster

3

Product structure for “Awesome” (A)

A

Level

0

Part B: 2 x number of As = (2)(50) = 100Part C: 3 x number of As = (3)(50) = 150Part D: 2 x number of Bs

+ 2 x number of Fs = (2)(100) + (2)(300) = 800Part E: 2 x number of Bs

+ 2 x number of Cs = (2)(100) + (2)(150) = 500Part F: 2 x number of Cs = (2)(150) = 300Part G: 1 x number of Fs = (1)(300) = 300

Page 14: 1 14 Material Requirements Planning (MRP) and ERP PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations

14

Lead Times

The time required to purchase, produce, or assemble an item For production – the sum of the

order, wait, move, setup, store, and run times

For purchased items – the time between the recognition of a need and the availability of the item for production

Page 15: 1 14 Material Requirements Planning (MRP) and ERP PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations

15

Time-Phased Product Structure

| | | | | | | |

1 2 3 4 5 6 7 8Time in weeks

F

2 weeks

3 weeks

1 week

A

2 weeks

1 weekD

E

2 weeks

D

G

1 week

Start production of DMust have D and E completed here so

production can begin on B

Figure 14.4

1 week

2 weeks to produce

B

C

E

Page 16: 1 14 Material Requirements Planning (MRP) and ERP PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations

16

MRP Structure

Figure 14.5

Output Reports

MRP by period report

MRP by date report

Planned order report

Purchase advice

Exception reports

Order early or late or not needed

Order quantity too small or too large

Data Files

Purchasing data

BOM

Lead times

(Item master file)

Inventory data

Masterproduction schedule

Material requirement

planning programs

(computer and software)

Page 17: 1 14 Material Requirements Planning (MRP) and ERP PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations

17

Determining Gross Requirements

Starts with a production schedule for the end item – 50 units of Item A in week 8

Using the lead time for the item, determine the week in which the order should be released – a 1 week lead time means the order for 50 units should be released in week 7

This step is often called “lead time offset” or “time phasing”

Page 18: 1 14 Material Requirements Planning (MRP) and ERP PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations

18

Determining Gross Requirements

From the BOM, every Item A requires 2 Item Bs – 100 Item Bs are required in week 7 to satisfy the order release for Item A

The lead time for the Item B is 2 weeks – release an order for 100 units of Item B in week 5

The timing and quantity for component requirements are determined by the order release of the parent(s)

Page 19: 1 14 Material Requirements Planning (MRP) and ERP PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations

19

Determining Gross Requirements

The process continues through the entire BOM one level at a time – often called “explosion”

By processing the BOM by level, items with multiple parents are only processed once, saving time and resources and reducing confusion

Low-level coding ensures that each item appears at only one level in the BOM

Page 20: 1 14 Material Requirements Planning (MRP) and ERP PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations

20

Gross Requirements Plan

Table 14.3

Week

1 2 3 4 5 6 7 8 Lead Time

A. Required date 50Order release date 50 1 week

B. Required date 100Order release date 100 2 weeks

C. Required date 150Order release date 150 1 week

E. Required date 200 300Order release date 200 300 2 weeks

F. Required date 300Order release date 300 3 weeks

G. Required date 600 200Order release date 600 200 1 week

G. Required date 300Order release date 300 2 weeks

Page 21: 1 14 Material Requirements Planning (MRP) and ERP PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations

21

Net Requirements Plan

Page 22: 1 14 Material Requirements Planning (MRP) and ERP PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations

22

Net Requirements Plan

Page 23: 1 14 Material Requirements Planning (MRP) and ERP PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations

23

Determining Net Requirements

Starts with a production schedule for the end item – 50 units of Item A in week 8

Because there are 10 Item As on hand, only 40 are actually required – (net requirement) = (gross requirement - on- hand inventory)

The planned order receipt for Item A in week 8 is 40 units – 40 = 50 - 10

Page 24: 1 14 Material Requirements Planning (MRP) and ERP PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations

24

Determining Net Requirements

Following the lead time offset procedure, the planned order release for Item A is now 40 units in week 7

The gross requirement for Item B is now 80 units in week 7

There are 15 units of Item B on hand, so the net requirement is 65 units in week 7

A planned order receipt of 65 units in week 7 generates a planned order release of 65 units in week 5

Page 25: 1 14 Material Requirements Planning (MRP) and ERP PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations

25

Determining Net Requirements

A planned order receipt of 65 units in week 7 generates a planned order release of 65 units in week 5

The on-hand inventory record for Item B is updated to reflect the use of the 15 items in inventory and shows no on-hand inventory in week 8

This is referred to as the Gross-to-Net calculation and is the third basic function of the MRP process

Page 26: 1 14 Material Requirements Planning (MRP) and ERP PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations

26

S

B C

12 138 9 10 11

20 3040

Lead time = 6 for SMaster schedule for S

Gross Requirements Schedule

Figure 14.6

1 2 3

10 10

Master schedulefor B

sold directly

Periods

Therefore, these are the gross requirements for B

Gross requirements: B 10 40 50 2040+10 15+30=50 =45

1 2 3 4 5 6 7 8Periods

A

B C

Lead time = 4 for AMaster schedule for A

5 6 7 8 9 10 11

40 1550

Page 27: 1 14 Material Requirements Planning (MRP) and ERP PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations

27

Net Requirements Plan

The logic of net requirements

Available inventory

Net requirements

On hand

Scheduled receipts+– =

Total requirements

Gross requirements Allocations+

Page 28: 1 14 Material Requirements Planning (MRP) and ERP PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations

28

MRP Management

MRP is a dynamic system Time fences put limits on replanning Pegging links each item to its parent MRP II

Closed-Loop MRP Capacity Planning Outputs include

Scrap Packaging waste Carbon emissions

Data used by purchasing, production scheduling, capacity planning, inventory

Page 29: 1 14 Material Requirements Planning (MRP) and ERP PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations

29

Closed-Loop MRP System

Figure 14.8

Priority Management

Develop Master ProductionSchedule

Prepare MaterialsRequirements Pan

Detailed ProductionActivity Control

(Shop Scheduling/Dispatching)

Capacity Management

Evaluate Resource Availability(Rough Cut)

Determine Capacity Availability

Implement Input/Output Control

Aggregate Production Plan

OK?NO

OK?NO OK? YES

OK? YES

Planning

Execution(in repetitive systems JIT techniques are used)

Page 30: 1 14 Material Requirements Planning (MRP) and ERP PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations

30

MRP in Services

Some services or service items are directly linked to demand for other services

These can be treated as dependent demand services or items Restaurants Hospitals Hotels

Page 31: 1 14 Material Requirements Planning (MRP) and ERP PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations

31

Uncooked linguini #30004

Sauce #30006

Veal #30005

MRP in Services

Chef;Work

Center #1

Helper one;Work

Center #2

Asst. Chef;Work

Center #3

Cooked linguini #20002

Spinach #20004

Prepared veal and sauce

#20003

(a) PRODUCT STRUCTURE TREE

Veal picante #10001

Figure 14.10

Page 32: 1 14 Material Requirements Planning (MRP) and ERP PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations

32

Enterprise Resource Planning (ERP)

An extension of the MRP system to tie in customers and suppliers Allows automation and integration of

many business processes Shares common data bases and

business practices Produces information in real time

Coordinates business from supplier evaluation to customer invoicing

Page 33: 1 14 Material Requirements Planning (MRP) and ERP PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations

33

ERP and MRP

Figure 14.11

Page 34: 1 14 Material Requirements Planning (MRP) and ERP PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations

34

Advantages of ERP Systems

1. Provides integration of the supply chain, production, and administration

2. Creates commonality of databases

3. Can incorporate improved best processes

4. Increases communication and collaboration between business units and sites

5. Has an off-the-shelf software database

6. May provide a strategic advantage

Page 35: 1 14 Material Requirements Planning (MRP) and ERP PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations

35

Disadvantages of ERP Systems

1. Is very expensive to purchase and even more so to customize

2. Implementation may require major changes in the company and its processes

3. Is so complex that many companies cannot adjust to it

4. Involves an ongoing, possibly never completed, process for implementation

5. Expertise is limited with ongoing staffing problems

Page 36: 1 14 Material Requirements Planning (MRP) and ERP PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations

36

ERP in the Service Sector

ERP systems have been developed for health care, government, retail stores, hotels, and financial services

Also called efficient consumer response (ECR) systems

Objective is to tie sales to buying, inventory, logistics, and production

Page 37: 1 14 Material Requirements Planning (MRP) and ERP PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations

37

In-Class Problems from the Lecture Guide Practice Problems

Problem 1:The Hunicut and Hallock Corporation makes two versions of the same basic file cabinet, the TOL (Top-of-the-line) five drawer file cabinet and the HQ (High-quality) five drawer filing cabinet. The TOL and HQ use the same cabinet frame and locking mechanism. The drawer assemblies are different although both use the same drawer frame assembly. The drawer assemblies for the TOL cabinet use a sliding assembly that requires four bearings per side whereas the HQ sliding assembly requires only two bearings per side. (These bearings are identical for both cabinet types.) 100 TOL and 300 HQ file cabinets need to be assembled in week #10. No current stock exists.

Develop a material structure tree for the TOL and the HQ file cabinets.