1 2014 report on the performance of the defense acquisition system on contract incentives dr. dan...
TRANSCRIPT
1
2014 Report on the Performance of the Defense Acquisition System
On Contract Incentives
Dr. Dan DavisSenior Economist
Acquisition Policy Analysis CenterOUSD(AT&L) / PARCA
Improving policies and performance through data analysis
7 April 2015
Not Cleared for Public ReleaseApproved for public release; distribution unlimited: 14-S-1935, 19 June 2014.
2Approved for public release; distribution unlimited: 14-S-1935, 19 June 2014.
• What contract incentives work the best?– Predetermined, formulaic?– Award fee?– Firm fixed price?– Competition– Future margin
• Are final margins affected by contractor performance?
• Are fixed-price contracts better than cost-reimbursement?
Objective: Use statistical analysis of contract data to understand incentive effectiveness
3Approved for public release; distribution unlimited: 14-S-1935, 19 June 2014.
• At the median (central tendency), DoD-wide margin is systematically predicted by:Exogenous constant 5.7 %Margin change effect – 0.9 %Size (by schedule) + 1.6 % Total predicted margin 6.4 %(N=81)
Other variables (statistically insignificant or spurious):
– Cost growth– Price growth– Schedule slips– Contract type– Army, Navy, or Air Force– Quantity change– Commodity type (9 types)– Overhead share of costs– Fixed-cost share of costs– Time trend– Size of contract by spend
Final margins were not dependent on cost, price, or schedule performance in development!
Regression over 81 MDAP development contracts, 95 percent of which were started in or after 2000. Price and cost growth are adjusted for inflation.
Issue is not what the final margin is, but that it does not systematically vary by performance!
4Approved for public release; distribution unlimited: 14-S-1935, 19 June 2014.
• At the median (central tendency), DoD-wide margin is systematically predicted by:Exogenous constant 14 %Margin change effect + 1 %LRIP effect – 2 %Ship effect – 1 %Space effect – 1 %Total predicted margin = 11 %(N=83)
Other variables (statistically insignificant or spurious):
– Cost growth– Price growth– Schedule slips– Contract type– Service component– Quantity change– Other 7 Commodities– Overhead share of costs– Fixed-cost share of costs– Time trend– Size of contract by schedule– Size of contract by spend
Also, final margins were not dependent on cost, price, or schedule performance in production!
Issue is not what the final margin is, but that it does not systematically vary by performance!
Regression over 81 MDAP development contracts, 95 percent of which were started in or after 2000. Price and cost growth are adjusted for inflation.
5Approved for public release; distribution unlimited: 14-S-1935, 19 June 2014.
Across all phases, fixed-price (FP) contracts had significantly lower cost growth…
-40%
-20%
0%
20%
40%
60%
80%
100%
120%
140%
160%
Contract cost growth for all cost-type and other contracts
17%
(adjusted for inflation)
CP/H
Costgrowth
Comparison of contract cost growth by contract-type, all contracts
-40%
-20%
0%
20%
40%
60%
80%
100%
120%
140%
160%
Contract cost growth for all cost-type and other contracts (weighted)
Costgrowth
-40%
-20%
0%
20%
40%
60%
80%
100%
120%
140%
160%
Contract cost growth for all fixed-price contracts
-2%
FP
-40%
-20%
0%
20%
40%
60%
80%
100%
120%
140%
160%
Contract cost growth for all fixed-price contracts (weighted)
14%
FP
Not weighted
Weighted
n=71 n=95
n=71 n=95
33%
CP/H
6Approved for public release; distribution unlimited: 14-S-1935, 19 June 2014.
…but this was because FP were used primarily in lower-risk cases (production)
-40%
-20%
0%
20%
40%
60%
80%
100%
120%
140%
160%
Contract cost growth in production (weighted)
11%
Weighted by spend
-40%
-20%
0%
20%
40%
60%
80%
100%
120%
140%
160%
Contract cost growth in development (weighted)
41%
Development Production
n=83 n=83
-40%
-20%
0%
20%
40%
60%
80%
100%
120%
140%
160%
Contract cost growth for all fixed-price contracts (weighted)
14%
-40%
-20%
0%
20%
40%
60%
80%
100%
120%
140%
160%
Contract cost growth for all cost-type and other contracts (weighted)
CP/H
n=95 n=71
33%
FP
90% CP/H10% FP
27% CP/H73% FP
7Approved for public release; distribution unlimited: 14-S-1935, 19 June 2014.
-10%
0%
10%
20%
30%
Margin for FFPcontracts,weighted
In development, CPIF / FPIF perform better than CPAF/FF on equal or lower margins
Caution: FFP has very low sample size
-20%
0%
20%
40%
60%
80%
100%
Price growth onincentivized contracts,
weighted
-20%
0%
20%
40%
60%
80%
100%
Price growth on FFPcontracts,weighted
-20%
0%
20%
40%
60%
80%
100%
Price growth on non-incentivized contracts,
weighted
40%29%
8%
-20%
0%
20%
40%
60%
80%
100%
Price growth on FFPcontracts,
unweighted
-20%
0%
20%
40%
60%
80%
100%
Price growth onincentivized contracts,
unweighted
38%
9%
FFP
Price growth
CPAF, CPFF, CS, OFormulaic Incentive
unweighted weighted unweighted weighted
Statistically significant
-10%
0%
10%
20%
30%
Margin on incentivizedcontracts,weighted
-10%
0%
10%
20%
30%
Margin for non-incentivized contracts,
weighted
6%3%
-20%
0%
20%
40%
60%
80%
100%
Price growth on non-incentivized contracts,
unweighted
-10%
0%
10%
20%
30%
Margin for non-incentivized contracts,
unweighted
6%
-10%
0%
10%
20%
30%
Margin on incentivizedcontracts,
unweighted
-10%
0%
10%
20%
30%
Margin for FFPcontracts,
unweighted
3%6%
Final margin
unweighted weighted unweighted weighted unweighted weighted
21%
8%
Statistically significant
n = 44 n = 6 n = 33
unweighted weighted
Caution
8Approved for public release; distribution unlimited: 14-S-1935, 19 June 2014.
In LRIP, FPIF / CPIF perform as well or better than FFP and have lower margins
-50%
0%
50%
100%
150%
Price growth onincentivized contracts,
weighted
-50%
0%
50%
100%
150%
Price growth on FFPcontracts,weighted
-50%
0%
50%
100%
150%
Price growth on non-incentivized contracts,
weighted
106%
2% 3%
-50%
0%
50%
100%
150%
Price growth onincentivized contracts,
unweighted
-50%
0%
50%
100%
150%
Price growth on FFPcontracts,
unweighted
- 0.5% - 1%
FFP
Price growth
CPAF, CPFF, CS, OFormulaic Incentive
unweighted weighted unweighted weighted unweighted weighted
Statistically significant Much less
volatility
-15%
-10%
-5%
0%
5%
10%
15%
20%
25%
30%
Margin for incentivizedcontracts,
unweighted
-15%
-10%
-5%
0%
5%
10%
15%
20%
25%
30%
Margin for FFPcontracts,weighted
-15%
-10%
-5%
0%
5%
10%
15%
20%
25%
30%
Margin for non-incentivized contracts,
weighted
8%
15%
9%
-15%
-10%
-5%
0%
5%
10%
15%
20%
25%
30%
Margin for incentivizedcontracts,
unweighted
-15%
-10%
-5%
0%
5%
10%
15%
20%
25%
30%
Margin for FFPcontracts,
unweighted
15%
n = 4 n = 11 n = 28
10%
Final margin
unweighted weighted unweighted weighted unweighted weighted
Statistically significant
-50%
0%
50%
100%
150%
Price growth on non-incentivized contracts,
unweighted
-15%
-10%
-5%
0%
5%
10%
15%
20%
25%
30%
Margin for non-incentivized contracts,
unweighted
164%
10%
Caution
9Approved for public release; distribution unlimited: 14-S-1935, 19 June 2014.
In full-rate production, FFPs had lowest unweighted price growth but LRIP FPIFs did better by spend
-20%
-10%
0%
10%
20%
30%
40%
50%
60%
70%
Price growth on FFPcontracts, weighted
11%
–1%
(none)
Price growth
FFP
Caution
CPAF, CPFF, CS, OFormulaic Incentive
unweighted weighted unweighted weighted
–1%
-20%
-10%
0%
10%
20%
30%
40%
50%
60%
70%
Price growth on FFPcontracts, unweighted
-5%
0%
5%
10%
15%
20%
25%
30%
Margin on FFPcontracts, unweighted
-5%
0%
5%
10%
15%
20%
25%
30%
Margin on FFPcontracts, unweighted
-10%
-15%
–11%-5%
0%
5%
10%
15%
20%
25%
30%
Margin on FFPcontracts, weighted
15%
n = 38
–12%
n = 2
(none)
Final margin
-5%
0%
5%
10%
15%
20%
25%
30%
Margin on FFPcontracts, unweighted
-5%
0%
5%
10%
15%
20%
25%
30%
Margin on FFPcontracts, unweighted
-10%
-15% unweighted weighted unweighted weighted
Statistically significant
Lowest of all unweighted
(just below formulaic LRIP at median)
Formulaic LRIPs better than this at median when weighted
-20%
-10%
0%
10%
20%
30%
40%
50%
60%
70%
Price growth on FFPcontracts, unweighted
-5%
0%
5%
10%
15%
20%
25%
30%
Margin on FFPcontracts, unweighted
- 2%
15%
10Approved for public release; distribution unlimited: 14-S-1935, 19 June 2014.
• Striking benefits for competition on new systems– Price growth– Schedule
growth
• Similar results for competition on system modifications/ upgrades
• Final margins were lower than all sole-sourced contracts
Benefits of competition
-25%
0%
25%
50%
75%
100%
125%
Price growth on newsole source contracts,
unweighted
-25%
0%
25%
50%
75%
100%
125%
Price growth on solesource mod contracts,
unweighted
-25%
0%
25%
50%
75%
100%
125%
Price growth oncompeted contracts,
unweighted
11% 13%
n = 52 n = 17 n = 14
48%
CompetedSole-source
or 1 bid: modSole-source or 1 bid: new
Pricegrowth
-1
0
1
2
3
4
5
6
Schedule growth on newsole source contracts,
unweighted
-1
0
1
2
3
4
5
6
Schedule growth on solesource mod contracts,
unweighted
-1
0
1
2
3
4
5
6
Schedule growth oncompeted contracts,
unweighted
0.07 yrs 0.25 yrs
n = 52 n = 17 n = 14
1.66 yrs
CompetedSole-source
or 1 bid: modSole-source or 1 bid: new
Schedulegrowth(years)
-10%
0%
10%
20%
30%
Margin for competedcontracts,
unweighted
-10%
0%
10%
20%
30%
Margin for new solesource contracts,
unweighted
-10%
0%
10%
20%
30%
Margin for sole sourcemod contracts,
unweighted
5.5%8.4%
n = 52 n = 17 n = 14
7.7%
CompetedSole-source
or 1 bid: modSole-source
or 1 bid: newFinalmargin
unweighted
11Approved for public release; distribution unlimited: 14-S-1935, 19 June 2014.
• Program analysis suggests:– Higher margins in production incentivize contractors to get out
of development faster• Shorter schedule slips in development are rewarded with higher
margins in production• Statistically significant (but small sample)
Effects of schedule slip in development on margin in production (on same program)
0%
2%
4%
6%
8%
10%
12%
14%
16%
0 1 2 3 4 5 6 7
Mar
gin
in p
rodu
ction
Schedule slip during development ( in years)
margin in production Fitted trend
for every 1-year slip in development, we expect a 0.5% drop in production margin
12Approved for public release; distribution unlimited: 14-S-1935, 19 June 2014.
Some Conclusions from the 2014 report
• Not all incentives work. Contractual incentives are effective if1. We use them,2. They are significant, stable, and predictable, and 3. They are tied directly to our objectives.
• “Cost-plus versus fixed-price” is a red herring• CPIF and FPIF contracts perform well and share realized
savings• FFP contracting requires knowledge of actual costs• Competition is effective—when viable• Production margins may help minimize development time
13Approved for public release; distribution unlimited: 14-S-1935, 19 June 2014.
Inadequate incentives mean dissolution,
or changes of organization purpose,
or failure to cooperate.
Hence, in all sorts of organizations
the affording of adequate incentives
becomes the most definitely emphasized task
in their existence.
It is probably in this aspect of executive work
that failure is most pronounced.
Chester Barnard
The Functions of the Executive (1938)
14Approved for public release; distribution unlimited: 14-S-1935, 19 June 2014.
Backup slides
15Approved for public release; distribution unlimited: 14-S-1935, 19 June 2014.
Price growth by Prime Contractor(Development)
LockheedMartin
BoeingNorthrop Grumman
General Dynamics
Raytheon BAEOther
Contractors
PriceGrowth(weighted by spend)
-20%
0%
20%
40%
60%
80%
100%
120%
Price growth forOther Contractors,
weighted
-20%
0%
20%
40%
60%
80%
100%
120%
Price growth forBAE,
weighted
-20%
0%
20%
40%
60%
80%
100%
120%
Price growth forRaytheon,weighted
-20%
0%
20%
40%
60%
80%
100%
120%
Price growth forGeneral Dynamics,
weighted
-20%
0%
20%
40%
60%
80%
100%
120%
Price growth forNorthrop Grumman,
weighted
-20%
0%
20%
40%
60%
80%
100%
120%
Contract price growthfor Boeing,weighted
-20%
0%
20%
40%
60%
80%
100%
120%
Contract price growthfor Lockheed,
weighted
n = 14 n = 13 n = 13 n = 10 n = 7 n = 6 n = 20
37% 41%
77%
8%
32%
−3%
Overallmedian:
29%22%
Weighted by spend
16Approved for public release; distribution unlimited: 14-S-1935, 19 June 2014.
Schedule growth by Prime Contractor(Development)
LockheedMartin
BoeingNorthrop Grumman
General Dynamics
Raytheon BAEOther
Contractors
ScheduleGrowth(years; weighted by spend)
-1
0
1
2
3
4
5
Schedule growthfor Other Contractors,
unweighted
-1
0
1
2
3
4
5
Schedule growthfor BAE ,weighted
-1
0
1
2
3
4
5
Schedule growthfor Raytheon,
weighted
-1
0
1
2
3
4
5
Schedule growthfor General Dynamics,
unweighted
-1
0
1
2
3
4
5
Schedule growthfor Northrop Grumman,
weighted
-1
0
1
2
3
4
5
Schedule growthfor Boeing,weighted
-1
0
1
2
3
4
5
Schedule growthfor Lockheed,
weighted
n = 14 n = 13 n = 13 n = 10 n = 7 n = 6 n = 20
Overallmedian:
2.5 yr2.5 yr
0.2 yr
3.4 yr
0.8 yr
2.8 yr
0.0 yr
0.9 yr
Weighted by spend
17Approved for public release; distribution unlimited: 14-S-1935, 19 June 2014.
Price growth by Prime Contractor(Production)
-20%
0%
20%
40%
60%
80%
100%
120%
Price growthfor Other,weighted
-20%
0%
20%
40%
60%
80%
100%
120%
Price growthfor ULA,
weighted
-20%
0%
20%
40%
60%
80%
100%
120%
Price growth forOshkosh,weighted
-20%
0%
20%
40%
60%
80%
100%
120%
Price growth forHuntington Ingalls,
weighted
-20%
0%
20%
40%
60%
80%
100%
120%
Price growth forRaytheon,weighted
-20%
0%
20%
40%
60%
80%
100%
120%
Price growth forGeneral Dynamics,
weighted
-20%
0%
20%
40%
60%
80%
100%
120%
Price growth forNorthrop Grumman,
weighted
-20%
0%
20%
40%
60%
80%
100%
120%
Contract price growthfor Boeing,weighted
-20%
0%
20%
40%
60%
80%
100%
120%
Contract price growthfor Lockheed,
weighted
LockheedMartin
BoeingNorthrop Grumman
General Dynamics
RaytheonHuntington
IngallsOshkosh ULA
Other Contractors
PriceGrowth(weighted by spend)
n = 12 n = 4 n = 8 n = 20 n = 9 n = 7 n = 4 n = 11 n = 8
Overallmedian:
12%
−1% −3% −4%
21%13%
−2%
24%
2% −1%
Weighted by spend
18Approved for public release; distribution unlimited: 14-S-1935, 19 June 2014.
Schedule growth by Prime Contractor(Production)
Weighted by spend
LockheedMartin
BoeingNorthrop Grumman
General Dynamics
RaytheonHuntington
IngallsOshkosh ULA
Other Contractors
ScheduleGrowth(years; weighted by spend)
-1
0
1
2
3
4
5
Schedule growthfor Other,weighted
-1
0
1
2
3
4
5
Schedule growthfor ULA,
weighted
-1
0
1
2
3
4
5
Schedule growth forOshkosh,weighted
-1
0
1
2
3
4
5
Schedule growth forHuntington Ingalls,
weighted
-1
0
1
2
3
4
5
Schedule growth forRaytheon,weighted
-1
0
1
2
3
4
5
Schedule growth forGeneral Dynamics,
weighted
-1
0
1
2
3
4
5
Schedule growth forNorthrop Grumman,
weighted
-1
0
1
2
3
4
5
Schedule growth forBoeing,
weighted
-1
0
1
2
3
4
5
Schedule growthfor Lockheed,
weighted
n = 12 n = 4 n = 8 n = 20 n = 9 n = 7 n = 4 n = 11 n = 8
0.5 yr
2 yr
0.8 yr
−0.7 yr
1.1 yr 1.3 yr
2.4 yr
Overallmedian:
0.5 yr0.0 yr 0.0 yr
19Approved for public release; distribution unlimited: 14-S-1935, 19 June 2014.
Operating Margins (SEC Filings)
Averages (percent) 2009 2010 2011 2012 2013 Defense 9 9 9 9 9 Commercial * 6 10 11 10 11
Capital goods 10 ‡ 13 ‡ 14 ‡ 14 ‡ 14 Engineering services * 5 * 5 * 6 * 5 * 6 Automobiles and automotive parts * −3 * 7 8 6 7
Defense
Boeing (BDS only) 10 13 10 9 10 CACI 7 6 7 8 7 General Dynamics (except Aerospace) 11 11 12 8 8 Huntington Ingalls 3 4 2 5 7 ITT Defense/Exelis 12 11 8 11 10 L-3 Communications 11 11 11 10 10 Lockheed Martin 10 9 9 9 11 Mantech 9 8 8 7 6 Northrop Grumman 8 10 12 12 13 Raytheon 12 10 11 12 12
Capital goods
* Statistically lower than defense margins‡ Statistically higher than defense margins
Commercial average is that for the 23–24 margins shown for all three sectors. SOURCE: Public SEC filings (Bloomberg, Capital Alpha Partners).
20Approved for public release; distribution unlimited: 14-S-1935, 19 June 2014.
Operating Margins (SEC Filings)
Capital goods Caterpillar 2 9 12 14 9 Cummins 6 12 15 11 12 Danaher 14 16 16 17 17 Dover 10 15 15 16 16 Eaton 4 9 10 9 12 Emerson Electric 13 15 16 18 17 Flowserve 14 14 14 14 15 Honeywell 13 14 15 11 16 Illinois Tool Works 10 15 15 17 18 Ingersoll-Rand 7 9 10 9 10 Joy Global 20 20 21 21 19 Lennox 4 6 4 7 9 Parker Hannifin 8 9 12 13 11 Rockwell Automation 8 13 15 16 17
Engineering services Aecom 4 5 5 4 5 CBI 7 8 8 8 7 Fluor 5 3 4 3 4 Jacobs Engineering 5 4 5 5 6
Automobiles and automotive parts Borg Warner 1 9 11 10 12 Delphi 7 10 10 11 Ford −1 7 6 4 4 General Motors −20 4 5 −2 5 Johnson Controls 1 5 5 4 4 TRW 4 9 8 8 7
Averages (percent) 2009 2010 2011 2012 2013
21Approved for public release; distribution unlimited: 14-S-1935, 19 June 2014.
2 contracts each:• General Atomics• Huntington Ingalls• Bell Textron• Sikorsky• Rockwell Collins• Alliant
1 contract each:• General Electric• Austral• VT Halter Marine• Computer Sciences
Corporation• ITT• Tybrin Electronics• SAIC• VIASAT
“Other Contractors” category
2222
In God we trust; all others must bring data.
Attributed to W. Edward Deming
Approved for public release; distribution unlimited: 14-S-1935, 19 June 2014.