  • 8/12/2019 1- BU-18 PVT Sampling Operation Design2013.11.23

    1/18

    BU-18 Slickline PVT Sampling

    Operation Design

    Prepared by:

    Reviewed by:

    Reviewed by:

    Reviewed by:

    Approved by:

    Well-tech of China Oilfield Services Limited

    Nov 232013

  • 8/12/2019 1- BU-18 PVT Sampling Operation Design2013.11.23

    2/18

    Contents

    1 Basic Data ................................................................................................................................ 1

    1.1 Basic data of well drilling and completion ........................................................................... 11.2 Perforation data sheet ........................................................................................................... 12 The Purpose and work scope for well test ............................................................................... 13 Construction geological conditions ......................................................................................... 14 Operation program and time limit ........................................................................................... 15 Job preparation ........................................................................................................................ 15.1 Operator and service content ................................................................................................ 15.2 Job preparation ..................................................................................................................... 25.3 Onsite preparation ................................................................................................................ 26 Operation interface .................................................................................................................. 27 Operation steps ........................................................................................................................ 37.1 Fix the wellhead ................................................................................................................... 37.2 Wiper trip .............................................................................................................................. 37.3 RIH the PDS sampler ........................................................................................................... 47.4 Pull the PDS sampler and measure flowing pressure gradient ............................................. 4

    7.5 Sample transferring6

    8 Notice ...................................................................................................................................... 69 Safety measures ....................................................................................................................... 59.1 Safety requirements of slick line operation .......................................................................... 59.2 Safety measures in exceptional circumstances ..................................................................... 69.3 Emergency measures of hydrocarbon releasing ................................................................... 79.4 Potential risk and methods ................................................................................................... 710 Appendix ............................................................................................................................... 8Appendix1: Device listing .......................................................................................................... 8Appendix2: Wiper trip tool string .............................................................................................. 8Appendix3: PVT sampling tool string ........................................................................................ 9Appendix4: Production pipe schematic .................................................................................... 10Appendix5: BU-18 well test JSA ............................................................................................. 10

  • 8/12/2019 1- BU-18 PVT Sampling Operation Design2013.11.23

    3/18

    BU-18 Slickline PVT Sampling Operation Design

    Page 1 of 17

    1 Basic Data

    1.1Basic data of well drilling and completion(1) Well No.:BU-18

    (2) Well type: natural flow oil well

    (3) Test interval: 3830m

    (4) Target formation: Mishrif

    (5) Current producing horizon: Mishrif reservoir

    (6) Completion: case hole perforated completion

    (7) Inclination data: the well is vertical well

    1.2Perforation data sheetWell No. Perforation depth (m) Unit Reservoir

    BU-18 3825-3833 MB21 Mishrif

    2 The Purpose and work scope for PVT sampling

    1) Run the PDS sampler down into nearly the mid-depth of Mishrif reservoir when the oil wellproduce normally, take two PVT sample of reservoir fluid.

    2) Take the flowing pressure gradient.

    3 Construction geological conditions

    AppendixReservoir Design of Well BU-18

    4 Operation program and time limit

    NO. working programplan time

    h

    Time

    h

    Total time

    h

    1 Wiper trip 3

    2 RIH the PDS sampler 3

    3Pull the PDS sampler and measure flowingpressure gradient

    3

    5 Job preparation

    5.1 Operator and service content

    1) One job supervisor :control the onsite job

    2) Each one person for crane and rigger of Well-tech: provide crane operation service. Four slick line

    operators of well-tech, one windlass, and one tool case: provide slick line job service.

    3) person of Well-tech slick line department, 1 slick line winch, 1 tool box, 2 Pressure gauge, provide

  • 8/12/2019 1- BU-18 PVT Sampling Operation Design2013.11.23

    4/18

    BU-18 Slickline PVT Sampling Operation Design

    Page 2 of 17

    slick line service.( Appendix 1Device listing )

    5.2 Job preparation

    1) Edit, verify and confirm the job design.

    2) Job mobilization according the job time demand,Do this operation mobilization.

    3) Slick line equipment preparation of well-tech.

    Take all the equipments and accessories relate with slick line job for BU-18 well.

    Check slick line windlass carefully, and test it, the depth reading of slick line should beaccurate.

    4) All the down hole tools and surface equipments should be checked by job supervisor before go tothe onsite, detailing content as follows:

    The qualification of equipment.

    The certification of proof before job.

    All the pressure and functional tests of the equipments should check-out and be recorded.

    All the measuring instruments should check-out.

    Pressure testing for the lubricator is 3000psi/10min.

    Call all related responsible official together to introduce the detailing of the job design.

    5.3 Onsite preparation

    1) Check the situation and number of all tools and equipments reached the well-site.

    2) Hold a meeting to study the safety regulation and operation procedure and let all the people knowthe procedure, emergency program and escape line.

    3) Make sure the responsible of every position when there is emergency situation.

    4) The job responsible official need communicate with the chief of well-site for the fixing and layingof equipment.

    6 Operation interface

    1) The supervisor is responsible for the coordination and management during the job, make sure theworking go smoothly.

    2) The slick line team of well-tech is responsible for the pressure test, combine and optimize toolstring to satisfy meet the job goal.

  • 8/12/2019 1- BU-18 PVT Sampling Operation Design2013.11.23

    5/18

    BU-18 Slickline PVT Sampling Operation Design

    Page 3 of 17

    7 Operation steps

    7.1 Fix the wellhead

    1) Company man gives the order to all the contractors and organizes the conducting.

    2) After the approval of the onsite director, under the guiding of the oilfield production supervisor orattendant, Make sure the swab valve of X-tree is closing, Keep the main valve and production wingvalve opening, then hang the sign of slick line.

    3) Close pressure gauges needle valve to take off the pressure gauge,and then leak off the pressurebetween swab valve and x-tree head.

    4) Position the slick line equipments; Make up BOP and lubricator, and do the functional testing of

    BOP at 3000psi, keeping it stable for 10 minutes. The length of lubricator should long enough tomeet the job situation.

    7.2Wiper trip

    1) Inform job supervisor all the slick line things have prepared, it needs the surface safe valve positionat open situation, the main valve position kept at open situation, production wing valve position

    kept at open situation, the well reach at working situation.

    2) Connect suitable size(58 mm)of gauge cutter, check zero of depth at surface ground.

    3) Open the swab valve 1 to 2 circles slowly, the down hole pressure go into lubricator grandly andobserve it for 10 minutes, and check if there is leaking from wellhead and lubricator. If the leakingis happen, close swab valve immediately, blow down the pressure and processing it; otherwise

    continue open it totally, record the turn number, observing it for 10 minutes.

    4) Slick line tools should down hole slowly and smoothly, after wiper trip to about 3850m, take outslick tools, wiper hole job needs:

    Assemble tool string simulate well test. (Appendix 2Wiper trip tool string)

    Up and down tool string test every 500 meters.

    Notice the down speed and record it.

    The maximum up and speed shall not faster than 80 m/min. if pull weight is abnormal, stopwinch immediately and analyze the reason.

    5) Take out wiper tools to lubricator and confirm it, then close swab valve, leak the pressure in thelubricator, take off lubricator, disconnect wiper tool string.

    6) If we select normal sequence from big to small gauge cutter(70 mm , 65 mm ) to wiper trip,operating procedures as the same; if successful, report to the supervisor, continue the next step work,if fail, communicate with supervisor and talk about resolve method.

  • 8/12/2019 1- BU-18 PVT Sampling Operation Design2013.11.23

    6/18

    BU-18 Slickline PVT Sampling Operation Design

    Page 4 of 17

    7.3 RIH the PDS sampler

    1) Change the oil choke to 24/64 24hours before the job start, and keep the fluid production stableuntil the job finish.

    2) Prepare two PDS sampler;

    3) Assemble PDS sampling tools string (Appendix 3: RIH the PDS sampling tool string);

    4) Open the swab valve 1 to 2 circles slowly, the down hole pressure go into lubricator grandly andobserve it for 10 minutes, and check if there is leaking from wellhead and lubricator. If the leakingis happen, close swab valve immediately, blow down the pressure and processing it; otherwise

    continue open it totally, record the turn number, observing it for 10 minutes.

    5) Slick line tools should down hole slowly and smoothly, the maximum up and speed shall not fasterthan 60 m/min;

    6) Up and down tool string test every 500 meters, record the weight detailed;

    7) When tool strings reach to 3830m, move up and down PDS sampling tool strings for three times,then wait to the PDS sampler to take sample. Leave it inside the well for at least one hour after theset clock time is over;

    7.4 Pull the PDS sampler and measure flowing pressure gradient

    1) Pull the tool strings up and stop at 3830m, 3780m, 3730m, 3500m, 3000m, 2500m, 2000m,2000m, 1500m, 1000m, 500m for 5 minutes to measure flowing pressure ;

    NO. Stop depth Stop time Point interval

    1 3830m 5min 10s

    2 3780m 5min 10s

    3 3730m 5min 10s4 3500m 5min 10s5 3000m 5min 10s

    6 2500m 5min 10s

    7 2000m 5min 10s

    8 1500m 5min 10s

    9 1000m 5min 10s10 500m 5min 10s

    11 0m 5min 10s

    2) Pull the strings out of hole;

    8 Notice

    1) It needs to check if the pipe string depth has something wrong to make sure the operation successratio.

    2) In case the leaking of main valve and surface safety valve to avoid the failing of lubricator systempressure testing, operator should check carefully, maintenance and make necessary exchangingfor sealing before fixing lubricator system.

  • 8/12/2019 1- BU-18 PVT Sampling Operation Design2013.11.23

    7/18

    BU-18 Slickline PVT Sampling Operation Design

    Page 5 of 17

    3) It should know clearly blow down procedure before blow down every time.

    4) Someone should on duty on well-site to check the wellhead all day during slick line job.

    5) It should have warning belt around slick line equipments.

    6) Forbidden hoisting goods above slick line area during working period.

    9 Safety measures

    9.1 Safety requirements of slick line operation

    1) The linking of the above tools and operation must under the present direction of team header.

    2) Slick line winch and other devices should be holding well, layout reasonably, and operate easily andsafety.

    3) The lubricator must have pressure gauge and relief valve, the length of lubricator should be greaterthan the length of tool string.

    4) Strictly control the slick line actual tension is not exceeding the limitation range.

    5) After X-tree operation, open swab valve and master valve, it should be list slick line operationand other words.

    6) When connecting slick line tools and pulling out or exchanging device every time, before running

    in, the place of threaded connection should be fastened again.

    7) During operation processing, if blocking is happen, it should up and down tools slowly, dontrunning in being forced.

    8) If doing many times slick line job continuously, cutting off a short part of slick line and makingrope socket again to keep the device in a good working condition.

    9) If do slick line fishing job, the running tools should be considerate it can be released.

    10) All the running tools must be measured length, outside diameter, internal diameter before runningin.

    11) When cutting off slick line on the ground, it should hold slick line with two hands to prevent slickline head from jumping up to hurt yourself and others.

    12) The end portion of slick line unit must be firmly fixed.

    13) During slick line job, irrelevant personnel should stay away wellhead, operator also pay attention tothe wellhead safety. If found abnormal circumstances, operator should immediately stop slick line

    job and deal with it.

    14) The lubricator and winch should fixing reliable, binding tightly and holding well by iron link orslick line; if blocking is happen, after the approval of supervisor and the direction of first party,

    processing it by taking short distance moving, and taking relevant measurements to avoid hurting

    incident because of slick line snapping.

  • 8/12/2019 1- BU-18 PVT Sampling Operation Design2013.11.23

    8/18

    BU-18 Slickline PVT Sampling Operation Design

    Page 6 of 17

    15) If there is overlapping job, safety measures and techniques must be in place. It should takefeasibility analysis at first to confirm the scientific and feasible before carry out.

    16) We must know enough about the condition of well. it should know the pipe string, well deviation, minimum inside diameter and so on.

    17) Set the implementation procedures according to first partys construction requirements. Beforeoperation, holding safety meeting to make operator know the risk in every operations.

    18) Make full analysis for potential problems of operation equipment, tools, material. It should knowservice condition of semi-fragile component and the number of accessory.

    9.2 Safety measures in exceptional circumstances

    1) When there is slick line tools down hole emergency, it should report to field supervisor, oilfielddirector, branch office, Well-tech department at first.

    2) Stop operation firstly, analyzing and finding reason right away and determine the type of accident.

    3) Making relevant dealing measures according to accident type.

    4) If tools couldnt be pulled out, tools could move down but not go up, we should try to change theplace of tools or the condition of stuck point to find opportunities in the process of trying. Dont

    pull out by force to avoid entire tool string being stuck.

    5) If tools get stuck in down hole, dont go up and down, it should make sure jar if in normal condition.If jar work well, it should consider which is the major way between upward jarring and downward

    jarring. In general, upward jarring is the major way, but downward jarring is also important,Velocity is the key.

    6) If tools get stuck in down hole, dont go up and down, and the jar cant work. It is very probablytool string get stuck with tubing wall. The reason is tha t the tubing is in the shape of S. The basicapproach is to open or close the well to change the temperature in down hole. Temperaturechanging will cause the changing of tubing shape of tube, which is in favor of unfreezing.

    7) If all three or more ways have failed to resolve, it should consider cut off slick line in down hole (atbullhead) purposely for recovering whole slick line. Then run in suitable tools and tool string to

    deal with the problem.

    8) Operation method: close slick line BOP on ground, release the pressure of lubricator above the BOP,pull up lubricator, assemble cut rod onto the slick line. Connect lubricator well, open BOP, let cutrod sliding down to the top position of bullhead and cut off slick line suddenly.

    9) Shear method: After open BOP, slotted bar slide down along slick line, make use of the impactforce to cut off the slick line from rope cap by inclined force which produced from slotted bar and

    bullhead. After slick line being cut off, it can recover entire slick line to ground. Reassemble toolstring to do next work.

    10) To avoid cutting tool not being in place or not cutting off at the right position, it should have donethe following works well in advance.

    Think over all the preparatory work. For example, what about the ability of BOP? Theperformance of BV and related tool, hand pump, pipelines and so on.

  • 8/12/2019 1- BU-18 PVT Sampling Operation Design2013.11.23

    9/18

    BU-18 Slickline PVT Sampling Operation Design

    Page 7 of 17

    Tools selection: There are several kinds of cutting tools, such as impact bar that play asupporting role. In order to prevent cutting tool get stuck in the middle road, it can use1-1/2cut rod or increase the numbers of impact bar to strengthen the down force. Even use

    1-1/2 ,x 3or 5impact bar.

    Tighten the slick line when cutting bar slide down, pull to 800 LBS.

    In normal circumstances, the slick line will loosing after 20 minutes, which indicate the slickline have been cut off. Otherwise it means the slick line hasnt been cut off. Put into anotherimpact bar to impact cut rod down or increase shear force to cut off slick line from the position

    of rope socket.

    If specific implementation measures crash with processing method, please shutdown operation,waiting for the order from leaders. Same problem have different phenomena in different well,

    solving measures and parameters are not the same too. The above measures and parameters are

    reference only, dont apply mechanically, or get the differently results.

    9.3 Emergency measures of hydrocarbon releasing

    1) The slick line operator should find out the point of hydrocarbon releasingat first time.

    2) If processing measures failure, on site supervisor and slick line captain have right to close all thevalves of x-tree.

    3) If there is hydrocarbon releasing occur during normal operation processing, all the people inwell-site should stop hot working at once.

    4) When there is hydrocarbon release occur during normal operation processing, notice slick linecaptain and site supervisor ; If hydrocarbon release is out of control, it should notice all the workers

    to keep in emergency situation on well site by broadcast at once.

    5) In operation processing, slick line operator must equip work interphone.

    9.4 Potential risk and methods

    1) Wellhead X-tree cannot be removed or some accessories damaged and so on. Equipped allremoving tools and special tools, when the accessories damaged or cannot be used, it should

    communicate with onsite supervisor to provide appropriate accessories by first party

    2) The X-tree flange or valve have leakage, it should communicate with jobsite supervisor to repair itbefore working

    3) If wiper trip working cannot go smoothly during operation, slick line operator should make sure thesituation of tubing, there are several methods:

    Exchanging smaller gauge ring to wiper trip, exchanged the size by followed, every time 4mmsmaller than last one to confirm, and it cannot exceed than 3 times to watch which time will be

    ok. If go through, then go to the goal depth, and go through many times at the last blocking

    position, until it can running tool string smoothly, then exchange gauge ring from smaller tobigger to wiper hole, till the designing gauge ring can wiper hole smoothly.

    If wiper trip cannot go smoothly, selecting suitable font to confirm the blocking situation towatch if there are tubing distorted, hard objects, sand and so on. If it still cannot be confirmed

  • 8/12/2019 1- BU-18 PVT Sampling Operation Design2013.11.23

    10/18

    BU-18 Slickline PVT Sampling Operation Design

    Page 8 of 17

    by font, first party should provide coiled tubing or pump car to flush the tubing, and then wiper

    hole again to confirm.

    4) It is possible there is no marking on the font in mark font job, so that the down hole situation will benot clearly. Method: first party provides coiled tubing to flush the wellbore, and then do impression

    tool job. If the font marking is clearly, then do the next job, otherwise communicate with first partysupervisor again or do long time flushing job or fish the down hole crud.

    5) During operation processing, in order to avoid possible fire hazard, it should take appropriatemeasures: ensure the performance of the riot, the personnel onsite safety education, not allow to use

    non- explosion-proof equipment in safe area, not permitted with a fire source, having appropriate

    fire fighting equipments, there are portable fire extinguisher near the X-tree and the equipments.

    10 Appendix

    Appendix1: Device listing

    Appendix2: Wiper trip tool string

    Name length in.) OD in. )Rope socket 6.1 1.875

    Swivel joint 11.0 1.875

    Weight bar 59.8 1.875

    Knuckle joint 9.8 1.875

    Quick release joint 13.8 1.875

    Weight bar 35.8 1.875

    Quick release joint 13.8 1.875

    Mechanical jar 81.151.2 1.875

    Crossover 3.9 1.875

    Gauge cutter 8.7 2.28

    total 162.7

  • 8/12/2019 1- BU-18 PVT Sampling Operation Design2013.11.23

    11/18

    BU-18 Slickline PVT Sampling Operation Design

    Page 9 of 17

    Appendix3: PVT sampling tool string

    Namelengthin.)

    ODin. )

    Weightlbs)

    Rope socket 6.0 1.875 3.08

    Swivel joint 7.0 1.875 6.6

    Weight bar 24 1.875 29

    Quick release joint 13.8 1.875 8.58

    Crossover 3.9 1.875 2.42

    PVT 137.8 1.7 25

    Crossover 1.9 1.7 0.5

    Crossover 3.9 1.875 2.42

    Knuckle joint 9.8 1.875 5.5

    Quick release joint 13.8 1.875 8.58

    Crossover 3.9 1.875 2.42

    PVT 137.8 1.7 25

    Crossover 1.9 1.7 0.5

    Shock absorber 21.0 1.875 13.2

    Crossover 3.9 1.5 1.5

    Pressure gauge 9.5 1.25 2

    Total 399.9 136.3

  • 8/12/2019 1- BU-18 PVT Sampling Operation Design2013.11.23

    12/18

    BU-18 Slickline PVT Sampling Operation Design

    Page 10 of 17

    Appendix4: Production pipe schematic

    Appendix6: BU-18 well test JSA

    BU-18 slick line well test JSA

    BU-18 JSA Table Complete date

    Fauqioil field

    The member of JSA team

  • 8/12/2019 1- BU-18 PVT Sampling Operation Design2013.11.23

    13/18

    BU-18 Slickline PVT Sampling Operation Design

    Page 11 of 17

    Step Job ProcedurePotential

    HazardsRisk Control Measures

    Resp

    onsibl

    e

    official

    Remark

    1

    Work

    environment

    and geography

    factor

    person hurt

    and equipment

    losing

    1. Before working,know nearby society and

    culture situation;

    2. Be careful the sunny

    and high temperature;

    3. Prepare first aid box

    in case of emergency

    accidents;

    4. Prepare some

    medicine to resist

    mosquito and snake ants

    etc;5. Know the roads,

    6. Equipped with

    security protection

    equipment and personnel

    security.

    7.According to thenumber of vehicles with

    homework on duty on duty

    and prevent of emergency

    2

    Equipments

    hanging on

    base

    Personnel Hurt

    and equipment

    damage

    1. Check the equipments

    carefully according to the

    driving requirements;

    2. Make sure the cranein the hanging situation;

    3.Tell the true weight of

    equipment to crane driver;

    4.It needs professional

    person direct the crane and

    forbidden unrelated

    persons

    Equipment

    transporting

    Equipment

    damage

    1.Ready-made the

    position and fixing of

    equipments with driver;

    2. If it is possible, let the

    engineer take part in the

    transporting to monitor thewhole processing.

    Equipment

    position onsite

    Personnel Hurt

    and equipment

    damage

    1.Related person take

    enough protective

    inventory;

    2. Position the

    equipments after them

    arrived at the onsite as

    soon as possible;

    3. Pay attention to the

    stability and safety during

    hanging;

    4. Check the equipment

    in time, discover theproblem and deal

  • 8/12/2019 1- BU-18 PVT Sampling Operation Design2013.11.23

    14/18

    BU-18 Slickline PVT Sampling Operation Design

    Page 12 of 17

    3 Handover well

    Handover not

    clearly;

    operationwrong; person

    and well

    accidents

    1. Confirm the working

    status of each valve and

    make sure the situation of

    the well;2. When transfer wells,

    unrelated personnel do not

    operate valves without

    permission.

    4

    take off

    wellhead

    devices

    Environment

    pollution at

    the wellhead;

    wellhead

    pressure gauge

    damage;

    Personnel

    hurt(Falling,

    bruising,

    crushing,

    pummeling,high

    pressure) ;

    blowout; sling

    breaking

    1. Blowout according to

    nation or customers

    requirements, otherwise

    obey rule of operator ;

    2. Stop all the hot work,

    oil spill should use the

    hosepipe to designate

    emission;

    3. In case of presence ofH2S the release will be

    made according to the

    procedures given by the

    Company and issued on

    the operating program.

    4. For H2S Wells aInjection Nipple shall be

    installed between the

    Stuffing Box and the

    Lubricator and shall have a

    pipe, cock valve and a

    flexible to flush the

    lubricator with water afterbleeding off the lubricator

    pressure. The

    hydrocarbons liquid and

    water shall be recovered in

    the Flow Line and Sump

    Tank.

    5. In the presence

    of H2S, always carry

    escape masque during

    the job.

    A self-breathingapparatus must be used by

    the operator for bleeding

    off lubricator.

    5

    surfacepreparation

    before BOP

    system fixing

    person hurt;

    packing partsand packing

    position of

    BOP system

    damage

    1. Take on enough

    protective inventories;2. Checking carefully;

    3. Be ready related

    packing parts.

    fixing BOP

    system

    Blowout;

    device

    damage;

    person hurt;danger during

    tools hanging

    1. Forbidden random

    operation of wellhead

    valve during operation;

    hang forbidden label,operate the valves by

    slickline operator;

  • 8/12/2019 1- BU-18 PVT Sampling Operation Design2013.11.23

    15/18

    BU-18 Slickline PVT Sampling Operation Design

    Page 13 of 17

    and wrong

    direction; slick

    line damage;

    deviceaccident

    because of

    corrosion.

    2. It needs professional

    person direct the crane, the

    crane driver should work

    with certification, and thecrane should work v

    6Power on the

    equipment

    Personnel

    Hurt; devices

    damage

    1. Operators should

    wear necessary inventory,

    including protective glass

    and so on;

    2.Stay in the safety field

    to avoid personnel hurt

    because of the elasticity of

    the slick line;

    3. Before power on the

    equipments, check allkinds of fluid level and

    pipe

    7pressure test

    of BOP

    system

    Personnel hurt

    ( line break,

    crushed by

    shaking

    booboo,

    bruise )

    1. Personnel must wear

    the qualified protection

    supplies, including

    protective glasses;

    2. Through radio,warning tape for isolation;

    3. Special person check

    it in a safe location,

    prohibit irrelevant

    personnel enters a high

    pressure area.

    BOP

    installation

    failed

    1. Check the ring and

    the ring groove;

    2. Ensure locate the

    BOP correct, on the

    balance of the diagonal.

    Equipment

    damage

    ( pressure

    build)

    1.Check the diesel oil,

    cooling water before

    starting the diesel engine;2. Check the safety

    valve set pressure is up to

    the standard before starting

    the mud pump;

    3. Operating the pumpshould be smoothly and

    slowing.

    8 check slick

    line situationperson hurting

    1. Take necessary

    protective inventories in

    case of accidents in

    checking processing;

    2. Pay attention the

    standing position prevent

    the damage from elastic

    slick line;

    3. Drag slick line stable

    out of roller when the

    windlass in neutralposition.

  • 8/12/2019 1- BU-18 PVT Sampling Operation Design2013.11.23

    16/18

    BU-18 Slickline PVT Sampling Operation Design

    Page 14 of 17

    make slickline cap

    1.The major operator

    need pay attention safety

    during making slick line

    knot;2.Unrelated person not

    allow to stay near in case

    of damaging;

    3. The operator pay

    attention to protect the

    wellhead.

    9

    confirm and

    prepare for

    running down

    hole

    person

    hurting; slick

    line and knot

    cap damaging;

    wellbore junk

    1. Operator pay

    attention safety;

    2. Check the quality of

    screw thread, connection

    order; make sure the tool

    string meet the

    requirement.

    design tool

    string

    Mismatch job

    design, cannot

    finish the job;

    do not know

    the well

    situation andcannot reach

    job goal, even

    have accident

    happen.

    1. Understanding the job

    requirements which is

    based on the design;

    2. Know whole working

    situation and well history;

    3.The final and best

    design should beenapproved by onsite

    supervisor;

    4. All the tools must H2S

    resisting in case of

    accidence.

    10

    preparation

    and check

    person hurting

    and tools

    damage

    1. take on enough andsuitable protective

    inventory;

    2. Preparation and

    checking according to the

    slick line wellhead

    preparation procedure and

    requirement.

    wellhead

    fixing

    person

    hurting; slick

    line and downhole tools,

    BOP system

    damaging;

    wellbore junk

    1. Take on enough andsuitable protective

    inventory;

    2. Fix wellhead system

    according to the slick line

    wellhead preparationprocedure and

    requirement;

    3.Related persons need

    pay attention the

    coordinate between each

    other during fixing, to

    avoid the drama

    11open x-tree

    valves

    high pressure,

    oil and gas

    leakage,

    danger caused

    by poison gas;

    the dangercaused by the

    1. Open the valves

    according to slick line

    processing procedure,

    oilfield and related

    technique requirements, it

    needs two personscooperate each other to

  • 8/12/2019 1- BU-18 PVT Sampling Operation Design2013.11.23

    17/18

    BU-18 Slickline PVT Sampling Operation Design

    Page 15 of 17

    up rush of

    slick line; the

    danger caused

    by semi-openvalves

    operate, and take on

    breather if it is necessary;

    2. Wellhead valves

    operator ensure if thevalves is

    close x-tree

    valves

    valves uptight;accidents

    caused by

    slick line and

    tool string

    broken

    1. Inform valve operator

    after the major slick lineoperator ensures slick line

    and tool string inside the

    BOP system totally;

    2. Wellhead valves

    operator ensure if the

    valves is opening totally.

    12

    combine tool

    string and

    select thegauge ring

    cannot finish

    job; tools drop

    out and lost

    down hole;person

    hurting

    1. Select suitable the

    size of tools according to

    schematic, check fishingtools carefully, select

    suitable gauge ring;

    2. When exchange thetool string, tight threading

    for tools in case of losing;

    3. Worker should take

    on quantified protective

    inventory

    wiper trip

    processing

    tool string

    blocking orsticking,

    cannot finish

    the job; slickline snap

    because of

    oversized

    pulling power;

    person

    hurting; close

    valve wrong to

    cause slickline cut off;

    depth wrong,

    tools losing;

    saver leakage

    1. Before working,

    know the well situation, becare for wrong depths

    interval, sometime it is

    necessary to get approve of

    supervisor to start the job;

    2. Forbidden mark font

    two times;

    3. When pulling power

    greater than normal, reportit to supervisor, co

    13Well test

    process

    Due to thepressure gauge

    fault, cause thetest failed; The

    necessary data

    forget to

    record, cause

    test results

    cannot be

    calculated;

    Personal

    injury;

    Shut off

    wrong valve,Cut wire;

    1.Make carefulexamination to pressure

    gauge and relatedequipment before test,

    make careful records;

    2. Pressure gauge

    Engineer check on the data

    carefully;

    3.Personnel must wear

    an approved protective

    equipment, enhance

    self-protect consciousness;

    4.Irrelevant personnel

    should be away from thework area; Winding

  • 8/12/2019 1- BU-18 PVT Sampling Operation Design2013.11.23

    18/18

    BU-18 Slickline PVT Sampling Operation Design

    Page 16 of 17

    Pressure gauge

    damage;

    operation area with yellow

    caution tape in, lock valve,

    and hanging operation is

    prohibited sign;5.When replace pressure

    gauge, be circumspect,

    RIH AND POOH speed

    should not exceed the rated

    speed;

    14

    rig out

    wellhead BOP

    system

    Blowout;

    device

    damage;

    person hurt;

    danger duringtools hanging

    and wrong

    direction; slickline damage;

    device

    accident

    because of

    corrosion.

    1. Forbidden random

    operation of wellhead

    valve during operation;

    hang forbidden label,operate the valves by slick

    line operator;

    2. It needs professionalperson direct the crane, the

    crane driver should work

    with certification, and the

    crane should work

    15

    recover

    wellhead

    devices

    Environment

    pollution at

    the wellhead;

    Personnel

    hurt(Falling,

    bruising,

    crushing,pummeling,

    highpressure) ;

    blowout

    1. Worker should take

    on qualified protective

    inventory, operator should

    equip with safe-belt whenthe x-tree is high,

    forbidden operating with

    pressure;

    2. The threading shouldin position well by

    operator, and smearcompound and twist crude

    material