1. Current Situation of Power Electricity2. Power Development Plan until 20253. Vietnam Power Market4. Generation Power Development Plan5. Hydropower Development Plan
4
0102030405060
1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006
Generation Sales
02000400060008000
100001200014000
1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006
Installed Peak
5
20.5% 19.6%
14.4%15.8%
10.3%
14.6% 15.4%17.1%
15.3%13.7% 13.2% 14.2%
0%
5%
10%
15%
20%
25%
1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006
% Sales' Development
0123456789
10
1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006
Mil
Cus
tom
ers
0%
5%
10%
15%
20%
25%
No Customers % Loss
6
HYDRO
COAL
OIL & GAS
5,321MW; 43.37%
OTHERS
832MW; 6.78%HYDRO 4,487MW;
36.57%
COAL
1,630MW; 13.28%
OIL & GAS
OTHERS
EVN = 77.8%
IPP&BOT = 22.22%
HYDRO
COAL1,245; 10.1%
GAS & OIL3,462; 28.2%
HYDRO 104; 0.85%
COAL
GAS & OIL
HYDRO
4,383; 35.7%
COAL
GAS & OIL
HYDRO
COAL385; 3.14%
GAS & OIL 1,859; 15.15%
HYDRO
COAL
GAS & OIL
HYDRO
COAL
GAS & OIL
100.0013,13827TOTAL
6.33832NAOTHERS
4.385753OIL
39.585,2005GAS
13.171,7307COAL
36.544,80114HYDRO
% TOTALCAPACITY (MW)
NUMBER Of PPs
TYPE
7
RURAL ELECTRIFICATION RURAL ELECTRIFICATION (12/2007)(12/2007)
U « n g BÝ
Ph − í c L o n g
6KV(3,9%) 10KV(16%) 15KV(22%) 22KV(31,9%)22KV(31,9%)35KV(28,1%)
116,660 km TG: 3662 MVA 109.000 km 32.061 MVA
220V
92.8%Rural HHs96.5%Village100%District100%Province
9(Km)(MVA)
2007 2010 2015 2020
(Km)(MVA)
(Km)(MVA)
58,434 96,200 210,000 340,000
66,860 105,800 227,000 363,000
11,500 18,000 38,000 60,000
13,138 25,700 50,000 78,000
3,286 4,823 7,115 9,779
6,600 14,100 25,500 41,400
5,650 11,484 15,138 17,442
15,932 32,818 57,191 90,066
11,053 19,188 22,949 25,949
20,656 41,271 65,707 105,680
2025
450,000
484,000
79,000
100,000
11,989
56,250
19,033
126,127
28,449
146,106
11
- Chau Doc–Phnom Penh: 230kV; 90km; 2008
- Ha Tinh – Nam Theun 2: 500kV; 160km; 2015 – Exchange with Thailand
- Soc Son – Malutang (400MW): 230/500kV; 250km; 2019
- Maybe earlier!
- Tan Dinh – Sambor: 230kV; 150km; 2019
- Pleiku – Ban Sok: 500kV; 180km; 2012
- 1,600MW exchanged in 2020
- Ban Mai – Nam Mo (105MW): 230kV; 85km; 2012
(SOURCE: Norconsult International AS)
13
2005 2009 2014 2016 2022 2024
Generation competitive market
(Single Buyer)
Wholesale Competitive
MarketRetail Market
Inte
rnal
Mar
ket
(Sin
gle
Buy
er)
Pilo
t Who
lesa
le M
arke
t
Who
lesa
le C
ompe
titiv
e M
arke
t
Gen
erat
ion
com
petit
ive
mar
ket (
Sing
le B
uyer
)
Pilo
t Ret
ail M
arke
t
Ret
ail C
ompe
titiv
e M
arke
t
14
EVNHeadquarter
17 Power Plants
National Load Dispatching
Center
7 PowerDistributionCompanies
4 Power Transmission
Companies 4 PowerEngineering
Consulting Co.
InstitudeOf
Energy
ElectricTelecomunication
Company
InformationTechnology
Center
3 Power Network
Project MBs
2 ThermalPower Project
MBs
7 HydropowerProject MBs
2 Electro-MachineryCompaniesAdmin & Tele
Center ProjectMB
Public Center
ElectricalCollege
3 ElectricalTrainingSchools
15
VS-SH HPPThac Ba HPPPha Lai TPPHai Phong TPPQuang Ninh TPPKhanh Hoa DCEquipment CoMechanical Co4 PECCsEVN Cambodia
Current JSCs
DN-HT-DM HPPThac Mo HPPUong Bi TPPNinh Binh TPPBa Ria TPPIT CenterMechanical Co.PC1 ADCPC2 ADCPC3 ADCGeneration JSCsFinance JSCs
Future JSCs
Sesan 3A HPPEletricity Development Co.IQ Links Ltd CoAn Binh BankCentral HPPViet – Lao HPP Co.
Power Transmission
Companie
Can Tho TPP*Phu My TPPThu Duc TPPHai Duong PDCNinh Binh PDCDa Nang PDC
Current Ltd Co.
EVN Tel Hanoi PDCHCMC PDCDongnai PDCHaiphong PDC
Future Ltd Co.
PDC: Provincial Distribution Co
ADC: Area Distribution Co
National Load Dispatching
Center
Public Center
ElectricityInstitude
GenerationProject MBs
Hoa Binh; Ialy; Tri An HPP
2 Electrical Coleges
Electrical University
Electrical Vocational
School
TPP: Thermal Power Plant
HPP: Hydro Power Plants