1 iter test blanket module (tbm) current u.s. designs, plans, issues, and material r&d needs...

39
1 ITER Test Blanket Module (TBM) Current U.S. Designs, Plans, Issues, and Material R&D Needs Prepared by: Presented at the MASCO meeting Washington DC, August 23-24, 2005 M. Abdou, A. Ying, N. Morley, C. Wong D. Sze, S. Malang, S. Smolentsev M. Sawan, M. Dagher, P. Calderoni, B. Merrill

Upload: geoffrey-hunter

Post on 27-Dec-2015

216 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: 1 ITER Test Blanket Module (TBM) Current U.S. Designs, Plans, Issues, and Material R&D Needs Prepared by: Presented at the MASCO meeting Washington DC,

1

ITER Test Blanket Module (TBM)

Current U.S. Designs, Plans, Issues, and Material R&D Needs

Prepared by:

Presented at the MASCO meeting

Washington DC, August 23-24, 2005

M. Abdou, A. Ying, N. Morley, C. Wong

D. Sze, S. Malang, S. Smolentsev

M. Sawan, M. Dagher, P. Calderoni, B. Merrill

Page 2: 1 ITER Test Blanket Module (TBM) Current U.S. Designs, Plans, Issues, and Material R&D Needs Prepared by: Presented at the MASCO meeting Washington DC,

2

OutlineI. ITER Plans

• ITER basic device components for TBM and support systems and ITER/TBM interface.

• What the International Partners (TBWG), including US, agreed to.

II. U.S. Current Plans (as they have evolved during the past year)

• TBM options and strategy.

• Description of designs of TBM test articles.

• External loops and ancillary equipment (piping, heat exchangers, tritium extraction, etc.).

III. TBM key requirements related to materials

IV. What is needed from the Materials Program

• R&D for TBM.

• R&D for higher performance TBM and Power Plants.

Page 3: 1 ITER Test Blanket Module (TBM) Current U.S. Designs, Plans, Issues, and Material R&D Needs Prepared by: Presented at the MASCO meeting Washington DC,

3

What is the ITER TBM Program?Integrated testing of breeding blanket and first wall components and

materials in a Fusion Environment

• Breeding Blankets/FWs will be tested in ITER, starting on Day One, by inserting Test Blanket Modules (TBMs) in specially designed ports.

• Each TBM will have its own dedicated systems for tritium recovery and processing, heat extraction, etc. Each TBM will also need new diagnostics for the nuclear-electromagnetic environment.

• Each ITER Party is allocated limited space for testing two TBMs. (Number of Ports reduced to 3. Number of Parties increased to 6).

• ITER’s construction plan includes specifications for TBMs because of impacts on space (port, port area, hot cell, TCWS), shielding, vacuum vessel, remote maintenance, ancillary equipment, safety, availability, etc.

• The ITER Test Program is managed by the ITER Test Blanket Working Group (TBWG) with participants from the ITER International Team and representatives of the Parties. (However, this entity may change under the new international agreement being negotiated.)

Page 4: 1 ITER Test Blanket Module (TBM) Current U.S. Designs, Plans, Issues, and Material R&D Needs Prepared by: Presented at the MASCO meeting Washington DC,

4

Blanket Testing in ITER is essential • Achieve a key element of the “ITER Mission”

“demonstrate the scientific and technological feasibility of fusion power for peaceful purposes” “test tritium breeding module concepts that would lead in a future reactor to tritium self-sufficiency, the extraction of high grade heat, and electricity production”

• Achieve the most critical milestone in fusion nuclear technology research: testing in the integrated fusion environment

– This has been the focus of the US Technology Program for a long time. It is the first real opportunity to apply the results of R&D from the past 30 years on blankets, materials, PFC, etc.

• The ITER TBM project provides a driving force to bring Fusion Nuclear Technology R&D the first step toward reality

• Develop the technology necessary to install breeding capabilities to supply ITER with tritium for its extended phase of operation

• Resolve the critical “tritium supply” issue for fusion development - and at a fraction of the cost to buy tritium for large D-T burning plasma

Page 5: 1 ITER Test Blanket Module (TBM) Current U.S. Designs, Plans, Issues, and Material R&D Needs Prepared by: Presented at the MASCO meeting Washington DC,

5

“Test tritium breeding module concepts that would lead in a future reactor to tritium self-sufficiency, the extraction of high

grade heat, and electricity production.”

1. validation of TBM structural integrity under combined and relevant thermal, mechanical and electromagnetic loads

2. validation of Tritium breeding predictions3. validation of Tritium recovery process

efficiency, tritium control and inventories4. validation of thermal predictions for strongly

heterogeneous breeding blanket concepts with volumetric heat sources

5. demonstration and understanding of the integral performance of the blanket components and material systems

TBM Mission

Specific TBM Test Objectives in ITER:

Page 6: 1 ITER Test Blanket Module (TBM) Current U.S. Designs, Plans, Issues, and Material R&D Needs Prepared by: Presented at the MASCO meeting Washington DC,

6

ITER Operation

• ITER operation starts in 2016. It has HH operation (~3yr), DD phase (~1yr), low duty cycle DT (~3yr), high duty DT (~3yr)

• The ITER schedule shows Test Blanket Module operating in the device from Day 1• The ITER International Partners agreed on a general strategy for each blanket concept:

4 sequential test articles corresponding to the 4 modes of ITER operation• Average fluence: 0.09 MW•y/m2 after 10 years; 0.3 MW•y/m2 after 20 years

Page 7: 1 ITER Test Blanket Module (TBM) Current U.S. Designs, Plans, Issues, and Material R&D Needs Prepared by: Presented at the MASCO meeting Washington DC,

7

TBWG agreed to allocate the 3 test ports by blanket concept, not by party

Port # 16:

Helium-cooled Ceramic Breeder TBMs (all Parties)

Port # 18:

Helium-cooled Lithium Lead /Dual Function Lithium Lead TBMs (EU/China)

Water-Cooled Ceramic Breeder TBM (Japan)

Port # 2:

Dual-Cooled Lithium Lead /Dual Function Lithium Lead TBMs (US/China)

Li-Breeder TBMs (RF, KO)

Helium-Cooled Ceramic Breeder TBM (only if a liquid breeder option does not make it)

Note: The interface with ITER device & facilities has been fixed (7/2005)Note: The interface with ITER device & facilities has been fixed (7/2005)

Page 8: 1 ITER Test Blanket Module (TBM) Current U.S. Designs, Plans, Issues, and Material R&D Needs Prepared by: Presented at the MASCO meeting Washington DC,

8

VV Port Extension

VV – Cryostat Duct

Cryostat Bio-Shield

TBM Frame Assy

VV Closure Plate

Pb-Li Concentric Pipe

Transporter

Port Cell Area

Bio-Shield Port Opening

Pb-Li Primary Coolant Loop Ancillary systemTBM

Plasma

ITER test port configuration has been fixed (by ITER & TBWG)(U.S. DCLL TBM is shown for illustration of how a TBM fits into this configuration)

Page 9: 1 ITER Test Blanket Module (TBM) Current U.S. Designs, Plans, Issues, and Material R&D Needs Prepared by: Presented at the MASCO meeting Washington DC,

9

Port plug = Frame + TBMsFrame = FW structure + Box structure + Backside shields

Cut-view Vertical cross-section of Frame(at the center of flexible supports)

1660

484

TBM Frame Assembly

Vertical Port Frame Opening space for TBM

Backside Shield 20

20 Test Blanket

Module

20 mm gap all around inside frame openings

Unit: mm

• Port can be divided vertically or horizontally• The maximum size of a test module (half vertical port) is 1.66m x 0.484m (TBM maximum first wall area is 0.8m2)

Configuration (and size) of TBM within ITER Test Port

Page 10: 1 ITER Test Blanket Module (TBM) Current U.S. Designs, Plans, Issues, and Material R&D Needs Prepared by: Presented at the MASCO meeting Washington DC,

10

II. Current U.S. TBM Plans

• TBM selected concepts and strategy.

• Description of designs of TBM test articles.

• External loops and ancillary equipment (piping, heat exchangers, tritium extraction, etc.)

US TBM plans evolved during the past year through technical studies, interactions with the community, VLT and DOE, as well as interactions with the international ITER partners and our work within TBWG.

Page 11: 1 ITER Test Blanket Module (TBM) Current U.S. Designs, Plans, Issues, and Material R&D Needs Prepared by: Presented at the MASCO meeting Washington DC,

11

US TBM Selected Concepts1. The Dual-Coolant Pb-17Li Liquid Breeder Blanket concept with self-

cooled Pb-Li breeding zone and flow channel inserts (FCIs) as MHD and thermal insulator-- Innovative concept that provides “pathway” to higher outlet

temperature/higher thermal efficiency while using ferritic steel.-- US lead role in collaboration with other parties (most parties are interested

in Pb-Li as a liquid breeder, especially EU and China).

-- Plan an independent TBM that will occupy half an ITER test port with corresponding ancillary equipment.

2. The Helium-Cooled Solid Breeder Blanket concept with ferritic steel structure and beryllium neutron multiplier, but without an independent TBM-- Support EU and Japan efforts using their TBM structure & ancillary

equipment

-- Contribute only unit cell /submodule test articles that focus on particular technical issues

Page 12: 1 ITER Test Blanket Module (TBM) Current U.S. Designs, Plans, Issues, and Material R&D Needs Prepared by: Presented at the MASCO meeting Washington DC,

12

Dual Coolant Lead-Lithium (DCLL) FW/Blanket Concept

Idea of “Dual Coolant” concept – Push towards higher performance with present generation materials (FS)

Ferritic steel first wall and structure cooled with helium

Breeding zone is self-cooled Pb-17Li

Structure and Breeding zone separated by SiCf/SiC composite flow channel inserts (FCIs) that

Self-cooled Pb-17Li

Breeding Zone

He-cooled steel

structure

SiC FCI

DCLL Typical Unit Cell

Provide thermal insulation to decouple Pb-17Li bulk flow temperature from ferritic steel wall

Provide electrical insulation to reduce MHD pressure drop in the flowing liquid metal

Pb-17Li exit temperature can be significantly higher than the operating temperature of the steel structure High Efficiency

Page 13: 1 ITER Test Blanket Module (TBM) Current U.S. Designs, Plans, Issues, and Material R&D Needs Prepared by: Presented at the MASCO meeting Washington DC,

13

US DCLL TBM module

SS frame

Front

Back

Be front face

FS structure

FCI is the Thermal and MHD Insulator lining all PbLi channels

He out

He in

PbLi inPbLi out

All structures are He-cooled @ 8MPa

self-cooled PbLi flows in poloidal direction

PbLi inPbLi out

FW He counter flow

Page 14: 1 ITER Test Blanket Module (TBM) Current U.S. Designs, Plans, Issues, and Material R&D Needs Prepared by: Presented at the MASCO meeting Washington DC,

14

FW He Coolant Manifolds

FW He Coolant Channels

Pb-Li Outlet Pipe

Pb-Li Inlet Pipe

Pb-Li Inlet Manifold

Plasma Facing First Wall

Pb-Li Flow Separation Plate with He coolant

Channels

FCI

Pb-Li Inlet Flow Channel

Pb-Li Return Flow Channel

Bottom Plate He Coolant Channels

Page 15: 1 ITER Test Blanket Module (TBM) Current U.S. Designs, Plans, Issues, and Material R&D Needs Prepared by: Presented at the MASCO meeting Washington DC,

15

DCLL TBM Calculated Temperatures

• Nominal (reference) operation (350C<He<450C;370C<PbLi<470C)

FS/PbLi=462C SiC/PbLi=470C Calculations performed at k=15 W/m-K (not so important), =20

S/m

• High performance (example) (350C<He<450C;450C<PbLi<620C)

FS/PbLi=482C SiC/PbLi=607C Calculations performed at k=3 W/m-K (reduced to minimize heat

losses into He, =20 S/m

He/FS

FS/PbLi

PbLi/SiC

SiC/PbLi

-0.08 -0.04 0 0.04 0.08y, m

400

450

500

550

600

650

700

T, C

Radial T distribution at the exithigh perform ance operationnom inal operation

Page 16: 1 ITER Test Blanket Module (TBM) Current U.S. Designs, Plans, Issues, and Material R&D Needs Prepared by: Presented at the MASCO meeting Washington DC,

16

DCLL Design Temperatures

For both TBM and power reactor design, the following temperature limits were designed to and can be achieved:

TBM Reference operation Higher performance operationFS Tmax ≤ 550° C ≤ 550° CFS/PbLi < 500° C < 500° CSiC/PbLi < 500° C < 700° CSiC Tmax < 500° C < 700° C

350° C < He < 450° C 350° C < He < 450° C370° C < PbLi ≤ 470° C 450° C < PbLi ≤ 650° C

For the DCLL TBM higher PbLi exit temperature ~650° C can be achieved via the bypass loop without requiring high-temperature materials for external piping/HX/TX. High-temperature materials (compatible with Pb-17Li up to 700° C) will be needed for the external lead lithium loop (HX/TX tubes) ONLY for the high performance power plant (NOT for TBM, and NOT for moderate performance power plants)

Page 17: 1 ITER Test Blanket Module (TBM) Current U.S. Designs, Plans, Issues, and Material R&D Needs Prepared by: Presented at the MASCO meeting Washington DC,

17

DCLL TBM Bypass Loop Schematic

DCLLTBM

PbLi mixingtank

Pump

Valveoff bypass

line

8 MPaHeliumloop

PbLi loop

400 C

470 C

470 C

400 C

30.3 kg/s

30.3 kg/s

0 kg/s

0.4 MW

Tritium extraction tank

PbLi/HeHeat Exchanger

180 C

300 C

Concentricpipe with FCI

Higher PbLi exit temperature can be achieved without requiring high-temperature materials for external piping/HX/TX. This can be achieved by turning the bypass valve “on” to allow mixing a lower temperature stream with the high-temperature stream in the PbLi mixing tank

Page 18: 1 ITER Test Blanket Module (TBM) Current U.S. Designs, Plans, Issues, and Material R&D Needs Prepared by: Presented at the MASCO meeting Washington DC,

18

Page 19: 1 ITER Test Blanket Module (TBM) Current U.S. Designs, Plans, Issues, and Material R&D Needs Prepared by: Presented at the MASCO meeting Washington DC,

19

Helium-Cooled Ceramic Breeder (HCCB) Blanket/First Wall Concept for TBM

Idea of “Ceramic Breeder” concepts – Tritium produced in immobile lithium ceramic and removed by diffusion into purge gas flow

First wall / structure / multiplier /breeder all cooled with helium

Beryllium multiplier and lithium ceramic breeder in separate particle beds separated by cooling plates

Temperature window of the ceramic breeder and beryllium for the release of tritium is a key issue for solid breeder blanket.

Schematic view of an example ITER HCCB test blanket submodule showing typical configuration layout of ceramic breeder, beryllium multiplier and cooling structures and manifolds

Thermomechanical behavior of breeder and beryllium particle beds under temperature and stress (and irradiation) loading affects the thermal contact with cooled structure and impacts blanket performance

Nuclear performance and geometry is highly coupled and must be balanced for tritium production and temperature control

Side Wall

Page 20: 1 ITER Test Blanket Module (TBM) Current U.S. Designs, Plans, Issues, and Material R&D Needs Prepared by: Presented at the MASCO meeting Washington DC,

20

Ceramic Breeder TBMInserting “US” unit cells into the EU HCPB structural box

Unit (mm)

Electromagnetics/Neutronics unit cell design

Typical Operating Temperature

Helium Coolant In/Out 300/500 CFerritic Max 550 CCeramic breeder Min 350-400 C(for tritium release) Max 900-1000 CBeryllium Max 600 C

Page 21: 1 ITER Test Blanket Module (TBM) Current U.S. Designs, Plans, Issues, and Material R&D Needs Prepared by: Presented at the MASCO meeting Washington DC,

21

Example: DCLL TBM Testing Schedule in ITER (4 sequential test articles)

ITER Year -1 1 2 3 4 5 6 7 8 9 10

ITEROperation Phase

Magnet testing & vacuum

HH-First

PlasmaHH HH DD

LowDutyDT

LowDutyDT

LowDutyDT

High DutyDT

High DutyDT

HighDutyDT

ProgressiveITERTesting Conditions

Toroidal B field

Vacuum

Heat flux

B Field

Disrup-tions

Small neutron

flux

NWL

Full disruption

energy

FluenceAccumula

-tion

Electromagnetic/Structural (EM/S) TBM

• Install•RH•System check-out

• Transient EM Loading on structure and FCIs

• FW heat flux loading• ITER field perturbation• LM-MHD tests

Nuclear Field/ Tritium Prod.(NF/TP) TBM

FinalizeDesign

• Nuclear field • Tritium production• Nuclear heating• Structure and FW

heating

Thermofluid/ MHD (T/M) TBM

FinalizeDesign

• Thermal and electrical insulation

• Tritium permeation

• Velocity profiles

Integrated (I)TBM

FinalizeDesign

• High temperature effects• Tritium permeation/recovery• Integrated function, reliability

Page 22: 1 ITER Test Blanket Module (TBM) Current U.S. Designs, Plans, Issues, and Material R&D Needs Prepared by: Presented at the MASCO meeting Washington DC,

22

DCLL TBM Pre-ITER Schedule to deliver test module one year before ITER Day One of operation

ITER HCLL TBM Schedule

2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015

TBWG activities and ITER parties interface

R&D

Basic thermofluid MHD

SiC/SiC FCI Fab and Compatibility

EM/S TBM Specific

Module design specific R&D

Subsequent TBM Specific

Design and analysis

Conceptual design

Preliminary design

Final design

Development of TBM TSD (Technical specification data)

Mock-ups and Qualification tests

Facility definition and preparation

Sub-components verification test

1/4 to 1/2 scale mock-ups

TBM design and fabrication

Call for tender / Contract award

Manufacturing design (tooling and processing)

Material procurement

Fabrication and procurement

Delivery to ITER site installation and testsUpdate: 08/19/05

design review

First plasmaITER Director appointed

final design

Page 23: 1 ITER Test Blanket Module (TBM) Current U.S. Designs, Plans, Issues, and Material R&D Needs Prepared by: Presented at the MASCO meeting Washington DC,

23

HCCB TBM Pre-ITER Schedule to deliver test submodule one year before ITER Day One of operation

ITER HCCB TBM Schedule

2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015

TBWG activities and ITER parties interface

R&D

Solid breeder thermonechanics and T recovery

T control and predictive capability

Virtual TBM (integrated modeling)

In-pile tritium release test

Diagnostics and instrumentation

Design and analysis

Conceptual design

Preliminary design

Final design

Development of TBM TSD (Technical specification data)

Mock-ups and Qualification tests

Facility definition and preparation

Sub-components verification test

1/4 to 1/2 scale mock-ups

TBM design and fabrication

Call for tender / Contract award

Manufacturing design (tooling and processing)

Material procurement

Fabrication and procurement

Delivery to ITER site installation and testsUpdate: 08/17/05

design review

First plasmaITER Director appointed

final design

Page 24: 1 ITER Test Blanket Module (TBM) Current U.S. Designs, Plans, Issues, and Material R&D Needs Prepared by: Presented at the MASCO meeting Washington DC,

24

III. TBM Key Requirements Related to Materials

Page 25: 1 ITER Test Blanket Module (TBM) Current U.S. Designs, Plans, Issues, and Material R&D Needs Prepared by: Presented at the MASCO meeting Washington DC,

25

TBM Materials and Key Parameters• Materials:

• Maximum fluence < 0.09 MW•y/m2 (< 1 dpa)

• Neutron wall load: ~ 0.8 MW/m2

• Ferritic Steel: maximum temperature < 550°C

• Surface heat flux: maximum 0.5 MW/m2 (local)

design average 0.3 MW/m2

• maximum number of pulses: < 30,000 cycles

• FS/PbLi interface < 500°C

• SiC/PbLi < 600°C (~500°C also o.k.)

-- DCLL: Ferritic Steel, PbLi, He, FCI (SiC or Sandwich type)

-- HCCB: Ferritic Steel, Be, Ceramic Breeder (Li2TiO3 or Li4SiO4), He coolant,

He purge

Page 26: 1 ITER Test Blanket Module (TBM) Current U.S. Designs, Plans, Issues, and Material R&D Needs Prepared by: Presented at the MASCO meeting Washington DC,

26

Relevant MHD issues for US DCLL that impact material requirements and performance

MHD Pressure drop is a serious concern for inboard LM blankets in high field, high power density reactors. Even moderate, but non-uniform, MHD pressure drops (arising from flaws for example) can seriously affect flow balance between parallel channels leading to hot channels

MHD velocities profiles can exhibit strong jets next to regions of stagnation and even reversed flow

Non-uniform volumetric heating can cause natural convection flows that MHD effects do not damp – can swamp forced flow velocity in slow moving breeder zone regions

Turbulence/stability modification and suppression by MHD forces and joule dissipation will likely affect performance

Ha and Re numbers ~1-3 x 104

All of these MHD issues strongly influence heat transfer, corrosion, tritium permeation, material requirements, and ultimate design.

Page 27: 1 ITER Test Blanket Module (TBM) Current U.S. Designs, Plans, Issues, and Material R&D Needs Prepared by: Presented at the MASCO meeting Washington DC,

27

Optimization of FCI Properties  Properties of the FCI need to be optimized in order to address

competing requirements: reduce MHD pressure drop to acceptable levels minimize heat losses from PbLi to helium coolant minimize temperature drop across the FCI (thermal stress) limit RAFS/PbLi interface temperature minimize corrosion rate ▪ minimize tritium diffusion

 Optimal mix of thermophysical & mechanical properties depends strongly on the thermofluid MHD and will be determined by R&D and design tradeoffs

Properties given on another slide give some approximate goals and requirements for SiC development for the FCI

=500 1/Ohm-m 100 20 5

Effect of on MHD jet formation

Velocity normalized to vave = 0.1 m/s

B = 4 T

Page 28: 1 ITER Test Blanket Module (TBM) Current U.S. Designs, Plans, Issues, and Material R&D Needs Prepared by: Presented at the MASCO meeting Washington DC,

28

Pressure equalization opening makes the pressure on both sides of the FCI equal, resulting in almost no primary stresses. The opening is either a slot (PES) or a row of holes (PEH).

Analysis shows significant MHD pressure drop reduction with FCI as compared to the case without insulation:a factor of 10 at = 500 S/m (acceptable)a factor of 200-400 at = 5 S/m (desired)

1 10 100 1000Electrical conductivity, S/m

0

100

200

300

400

500

(dP

/dx)

0 /

(d

P/d

x)

PEHPES

Effectiveness of SiCf/SiC FCI as Electric/Thermal Insulator depends on the Thermophysical properties

And Design of FCI (e.g PES VS. PEH and location relative to magnetic field)

B-field

X (poloidal)

He flows

Pb-17Li bulk flow

Pb-17Li gap flow

PES

Fe wall

FCI

Page 29: 1 ITER Test Blanket Module (TBM) Current U.S. Designs, Plans, Issues, and Material R&D Needs Prepared by: Presented at the MASCO meeting Washington DC,

29

Desired Flow Channel Insert Properties Low transverse electrical and thermal conductivity of the SiC/SiC

Goal ~1-10 S/m transverse electrical conductivity, Acceptable <500 S/m for TBM operation

Goal ~2-5 W/mK transverse thermal conductivity, Acceptable <15 W/mK for TBM operation

The inserts need to be compatible with flowing Pb-17Li Goal ~800°C, Acceptable 500°C for initial TBM operation

Liquid metal must not “soak” into pores of the composite (or foam) in order to avoid increased electrical conductivity. In general, closed porosity and/or dense SiC layers are required on all surfaces of the inserts.

Secondary stresses and deformation caused by temperature gradients must not endanger the integrity of FCIs.

Goal 200°C temperature difference, Acceptable 100°C temperature difference for initial TBM operation

The insert shapes needed for various flow elements must be fabricable Basic box-channel element

Cross sections up to 150 x 150 mm for TBM

Lengths 500-1000 mm for TBM

Page 30: 1 ITER Test Blanket Module (TBM) Current U.S. Designs, Plans, Issues, and Material R&D Needs Prepared by: Presented at the MASCO meeting Washington DC,

30

IV. What is needed from the Materials Program

DCLL

Solid Breeders

A) R&D for TBM

B) R&D for Power Plants

B1) Moderate Performance

B2) Higher Performance

-- R&D for TBM

Page 31: 1 ITER Test Blanket Module (TBM) Current U.S. Designs, Plans, Issues, and Material R&D Needs Prepared by: Presented at the MASCO meeting Washington DC,

31

Material Application for FCI (and associated external piping, HX, and TX) for TBM and Power Plants

TBM Power Plants

Reference Higher Performance*

Moderate Perfor-mance

Higher Perfor-mance

FCI Sandwich Yes N/A Yes N/A

FCI Mod. Temp SiC (500°C) (X) Yes N/A Yes N/A

FCI High Temp SiC No Yes No Yes

Advanced Materials for HX and TX tubes

No No(use bypass / mixing tank)

No Yes

(X) Requirements on σ and к for the moderate temp SiC FCI are less demanding than those for high-temperature, high performance SiC FCI

* If development of high temperature SiC for power plants is available around 2015-2020, a higher performance TBM can be considered for later stages of ITER testing.

Page 32: 1 ITER Test Blanket Module (TBM) Current U.S. Designs, Plans, Issues, and Material R&D Needs Prepared by: Presented at the MASCO meeting Washington DC,

32

A. Needs for the DCLL TBM

a) Development of flow channel inserts for thermal and electrical insulation

• inserts made of SiC-composite suitable for moderate temperature (< 500ºC)

• inserts made of sandwich-structure (i.e. steel-alumina-steel, welded at all edges), back-up solution in case the SiC inserts can not be developed in time, suitable for lead lithium exit temperatures up to 500ºC (defer this until after the first MHD tests around 2008)

• for higher performance TBM: SiC FCI for high temperature (up to 650°C) lead lithium at the exit

b) Fabrication of the TBM structure from RAFS (F82H or EUROFER) including forming of the complicated structure (i.e. FW panel), welding (diffusion, TiG, Laser, electron beam), PWHT.

• Most of these steps are under development in the EU and Japan, and the alternative is therefore to either procure from their industry, or to develop the required technology in the US (Iteration with the detailed TBM design will be needed)

Page 33: 1 ITER Test Blanket Module (TBM) Current U.S. Designs, Plans, Issues, and Material R&D Needs Prepared by: Presented at the MASCO meeting Washington DC,

33

A. Needs for the DCLL TBM (cont’d)

c) Code-qualification of the RAFS and the welds for ITER applications

d) Development of suitable FE-codes for the analysis of the steel/Pb-17 Li compatibility tests and the extrapolation of these results to the conditions in a blanket ( flow conditions, impact of magnetic field, suitable criteria for determining temperature limits)

e) Data base for the compatibility of Pb-17 Li with RAFS and SiC-composites (e.g. forced convection loop with temperature gradients in flow direction, measurement of depositions, impact of irradiation)

f) Recommendations regarding suitable materials for the external lead-lithium loop including limits on the allowable interface temperatures (maximum lead lithium temperature 470ºC).

Page 34: 1 ITER Test Blanket Module (TBM) Current U.S. Designs, Plans, Issues, and Material R&D Needs Prepared by: Presented at the MASCO meeting Washington DC,

34

B. DCLL Material R&D for Power Plants

Two kinds of operation of the DCLL blankets in power plants can be considered: B1) Moderate Performance with lead lithium exit temperatures up to

500 C and a RANKINE cycle (steam turbine) power conversion system

• B1 can be realized with sandwich-type flow channel inserts and a primary loop build of well known ferritic steels

B2) Higher Performance: high temperature operation with exit temperatures up to 700°C, allowing the use of a BRAYTON cycle (He turbines) power conversion system.

• For B2 SiC-composite FCI are required, and the materials used in the primary loop (tritium extraction system, intermediate HX) must be compatible with Pb-17 Li up to 700°C.

• Certainly, the high power operation is more attractive, but a DCLL blanket with lead-lithium exit temperatures of ~ 500°C has already a number of advantages compared to a HCLL blanket (simpler structure, no need for large internal heat transfer surfaces, less void space in tokamak inboard, smaller pumping power, tritium control easier).

Page 35: 1 ITER Test Blanket Module (TBM) Current U.S. Designs, Plans, Issues, and Material R&D Needs Prepared by: Presented at the MASCO meeting Washington DC,

35

B. DCLL Material R&D for Power Plants (cont’d)

Common issues for both B1 and B2 cases

For both kinds of power plants, the following issues have to be addressed by the material program:

a) Qualification of the RAFS and its welds for high fluence irradiation,

b) Development of suitable methods for the purification of Pb-17 Li (corrosion products, on-line Bi removal, Po control),

c) Tritium extraction and control (e.g. tritium permeation barriers)

Page 36: 1 ITER Test Blanket Module (TBM) Current U.S. Designs, Plans, Issues, and Material R&D Needs Prepared by: Presented at the MASCO meeting Washington DC,

36

B. DCLL Material R&D for Power Plants (cont’d)

B1) Issues to be addressed for moderate performance power plantsd) Long time behavior of sandwich-type FCI ,e) Suitable tritium extraction system (main candidate: vacuum

permeator with ferritic steel tubes),f) Tritium control, especially the required reduction of permeation losses

in the Pb-17Li/steam HXB2) Issues to be addressed for high performance power plants

g) Qualification of the SiC flow channel inserts for high temperature applications (Interface temperature SiC/Pb-17 Li up to 800 C)

h) Development of suitable tritium extraction methods from Pb-17 Li, leading to low tritium partial pressure (< 100 mPa), (candidate method: vacuum permeator with Nb or Ta tubes)

• operational limits on the impurities in Pb-17 Li, maintain extremely low impurity level in the vacuum chamber,

• impact of different materials in the primary Pb-17 Li loop : RAFS, SiC-composite, Nb-or Ta permeator tubes, HX tube material.

i) Development of HX between primary (Pb-17Li) and secondary (He) loops, candidate material for the HX tubes include Nb or Ta, SiC-composites, Ni-base alloy with high Al content for forming protective coatings.

Issues specific to the B1 and B2 cases

Page 37: 1 ITER Test Blanket Module (TBM) Current U.S. Designs, Plans, Issues, and Material R&D Needs Prepared by: Presented at the MASCO meeting Washington DC,

37

Materials Needs for Ceramic Breeder TBM

• Ferritic steel structure: needs are satisfied by those for the DCLL

• Pebble ceramics and beryllium: evaluate US strategy for procurement (Do we want to collaborate with EU, Japan and other parties on development or just purchase from EU/Japanese industry?)

• There is an active R&D program on ceramic breeder blankets worldwide. The US materials program may wish to explore making contributions to this area.

Page 38: 1 ITER Test Blanket Module (TBM) Current U.S. Designs, Plans, Issues, and Material R&D Needs Prepared by: Presented at the MASCO meeting Washington DC,

38

Additional Material Issues Common to All TBM Concepts and Parties

• Development of Be/FS joining capability

• Transition elements between FS in the TBM and the coolant access pipes (preferably austenitic steel for remote welding)

Page 39: 1 ITER Test Blanket Module (TBM) Current U.S. Designs, Plans, Issues, and Material R&D Needs Prepared by: Presented at the MASCO meeting Washington DC,

39

There are Immediate Needs for Human Resources from the Material Program to participate in the TBM activities and to work as part of the ITER TBM TEAM

Those are in addition to performing the R&D described earlier

For Example:• to help the team perform design trade offs, more detailed

design, and analysis for the TBM test articles and associated systems

• To provide advice on all aspects of materials limits and considerations

• To help the team decide on key areas of and strategy for international collaboration

• To assist in calculating costs for the TBM Program (including R&D, mockups, test articles, ancillary equipment, etc) (URGENT)

Approximate for FY06: 1.5 – 2.5 FTE