1 managing mo’s with obpm how to use browser/powerlink technology to revolutionize manufacturing...
TRANSCRIPT
1
Managing MO’s with OBPMHow to use Browser/PowerLink
technology to revolutionize Manufacturing Orders
Jim Simunek, CPIM
2
Introduction• Order Based Production Management (OBPM)
allows for Manufacturing Order:– Create– Change– Receipt (RM) production– Complete, material & labor– Cancel (status 10 orders)– Close (both Force & Normal)
3
Introduction• All activity is ‘immediate update’ (i.e. no
batches to close and update)
• Templates can minimize the amount of data entry
• MRP and Reorder Report recommendations can be used to create MO’s and/or PO’s
• Can create MO’s from Customer Order line items
4
Introduction• This presentation has been created using
Release 7 (PowerLink)
• Most functions are available at the R6 level also
• This presentation does not address Repetitive Schedules– Schedules are only available for inquiry in
Browser/PowerLink
5
EPDM Impacts (R6 & R7)• When using EPDM, MO’s are kept by site
• Site Master file controls– Work List default values– Order Closeout options– Work Center Analysis report default values
• With PDM, data in Site Master is maintained in PC&C tailoring questionnaire
• Order Close & Purge and WIP Value report is by site
6
7
8
9
EPDM• Use ‘Site Host Jobs’ to create Work List
reports (can still use Green Screen also)
10
Planner File• OBPM has a ‘Planner’ file to create a code file
of valid planner numbers
11
Planner Numbers• Item Balance (Warehouse) record holds the
default planner number for the item
• All MRP and MPSP reports and work (green screen) screens sort primarily by planner number
• Planner number is copied into Manufacturing Orders for reports and subsets
• One person can be responsible for multiple planner numbers
12
Planner• From the Planner screen, you can display all
MO’s associated with a planner
13
Questions?
14
Creating MO’s• Template controls initial fields that are
displayed:
15
Creating MO’s• With Cards, there is the ability to:
– Pre-assign batch/lot number– Maintain the component allocations– Maintain operations– Add Miscellaneous Charges– Link MO to CO– If using EPDM, copy an Alternate Processes BOM
and Routing to the MO
16
Alternate Processes• EPDM allows for the creation of multiple
‘processes’ for the same item – i.e. alternate bills of material and/or routings
• When adding the MO, do NOT check the ‘Include Primary BOM’ and ‘Include Primary Routing’ boxes
• ‘Import’ button on Component and Routing cards allow for Alternate Process to be chosen
17
Creating MO’s• When ‘Create Order’ button is pressed, MO is
added (i.e. no ‘Order Release’ required)
• Same files as Green Screen are created:– MOMAST – header information– MODATA – Component Allocations– MOROUT – Operations– MOMISC – Miscellaneous Charges
• Order is added at Status 10 – Open, no Activity
18
MO Status CodesOrder Status
• 10 – Open, Not Started• 40 – Activity Reported• 45 – Material Complete• 50 – Labor Complete• 55 – Both Material &
Labor Complete• 99 - Cancelled
Operation Status• 00 – Inactive, labor cannot
be reported• 10 – Open• 30 – Started• 40 – Operation Complete
19
Material Transactions• At the present time, can only report Production
Receipt transactions through Browser/PowerLink
• When reporting RM transaction, if there are controlled floorstock components, Planned Issue (IP) transactions will be created
• Pick Complete, Planned Issue, Unplanned Issue, Component Return and Scrap transactions are not available
20
Statusing MO’s• Can display open MO’s and PO’s for
component parts allocated to an MO
21
Labor Reporting• Labor is not reported through Browser/PowerLink• Labor can be reported through:
– PC&C – green screen labor entry
– PM&C – Job ON and OF transactions
– PaperLess – feeds PM&C
• Per Operation, report– Time spent: Set-up, Run and/or Machine
– Quantity Complete (good)
– Quantity Scrapped
– Operation Complete
22
Labor History• Browser/PowerLink will display labor history
transactions• PC&C Control File determines if Labor
Reporting history is kept– If using EPDM, Site record holds Labor History
question
• History is kept regardless of what application is used to report labor
• History is stored in files MOTRAN (open MO) and MOHTRN (MO History)
23
24
Production Receipt (RM)• Can report Production Receipt (RM)
transactions with OBPM
• Template controls fields that will be displayed
• If Controlled Floorstock Components exist, they will be issued (IP transactions)
25
Receipt Template
26
Backflush Components
27
MO Transaction History• Can display transaction history for an MO:
28
Completing MO’s • Use OBPM to Complete:
– Material (takes MO to status 45 or 55 if Labor has been previously completed)
– Labor (takes MO to status 50 or 55 if Material has been previously completed)
29
Material Complete• If quantity ordered has not been completely
received, ‘Receipt of Material’ card will be displayed to allow RM transaction
• Controlled Floorstock components will be issued
• ‘Material Complete’ card allows for input of Reference, Reason and Date
• If operation scrap has been reported, controlled floorstock components for scrap quantity will be issued
30
Material Complete
31
Labor Complete• From ‘Maintain’ menu, Labor can be reported
as complete
• Reference and Reason codes can be entered
• ‘Incomplete’ Operations (i.e. Operation Status not equal to 40) can be displayed and completed– Any incomplete operations will be taken to status
40 when Labor Complete is reported
32
Labor Complete
33
Labor Complete – Incomplete Oper.
34
Questions?
35
Select MO for Closeout• Can select MO for either normal or force close
– Status 55 (Complete) orders have normal close– Less than status 55 orders must be force closed
• Must select orders for closeout one at a time– If MO’s are taken to Complete (55) status, may
want to use PC&C green screen to select MO’s for close (more efficient)
• Closeout selection does not change MO status• Can Re-Open an order that has been selected
for close
36
MO Close
37
Production Facility• Can display all MO’s scheduled to go through
a certain Facility
• This is useful if you have outside operations and have made the vendor a Production Facility
• From the Production Facility list, click on a facility, then ‘Display’, then ‘MO Operations Where Used’
38
Facility Where Used
39
MO Operation Where Used
40
Create MO from CO• Can use CO line items to create MO
• Will tie the CO to the MO
• Will use CO quantity and Manufacturing Due Date for MO
• With PTF download, RM transaction for MO will create discrete allocation for CO (must be in a controlled warehouse)
41
Create MO from CO
42
Create MO from MRP• Can Create MO’s from MRP recommendation
file:
43
Create MO from MRP• From MRP Recommendation window, use
‘Customize’ →’Preferences’ to set screen to immediate update
44
Component Availability• From MRP Recommendations, you can:
– Highlight multiple planned MO’s (Control + click)– Check component availability
45
Check Component Availability
46
Check Component Availability
47
MO Create from MRP Recommendation
48
Summary• OBPM provides much easier access and
reporting to MO’s
• Ability to Create, Maintain, Cancel, Receive, Complete and Re-open makes it much more ‘user friendly’ to report against MO’s
• Ability to display MO’s by Planner or Work Center provides better ‘status’ information
• MRP Recommendations provides component availability capability