1 nottingham-lincoln stakeholder board – network rail update doreen marsh – 26 th february 2015

16
1 Nottingham-Lincoln Stakeholder Board – Network Rail update Doreen Marsh – 26 th February 2015

Upload: diana-lyons

Post on 19-Dec-2015

217 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 1 Nottingham-Lincoln Stakeholder Board – Network Rail update Doreen Marsh – 26 th February 2015

1

Nottingham-Lincoln Stakeholder

Board – Network Rail update

Doreen Marsh – 26th February 2015

Page 2: 1 Nottingham-Lincoln Stakeholder Board – Network Rail update Doreen Marsh – 26 th February 2015

2

Network Rail Update – Items 6a to 6iItem 6a Lowdham-Newark re-signalling and level crossing upgrade

Continuing with finalising the design, some site preparation works are underway

Page 3: 1 Nottingham-Lincoln Stakeholder Board – Network Rail update Doreen Marsh – 26 th February 2015

3

Network Rail Update – Items 6a to 6i

• Due to changes to the design of the modular signalling solution and signalling resource constraints the commissioning of the Lowdham to Newark signalling is now likely to be Summer 2016 (was November 2015), subject to consultation.

Page 4: 1 Nottingham-Lincoln Stakeholder Board – Network Rail update Doreen Marsh – 26 th February 2015

4

Item 6b Lowdham – Newark Castle proposed line speed increase

Network Rail Update – Items 6a to 6i

The second train per hour from Nottingham to Newark with altered stopping patterns may now create a Business Case to increase the linespeed.

The 3rd way analysis work undertaken in 2013 demonstrated potential for non-stopping trains to benefit from linespeed improvements. If funding is made available and the business case is satisfactory further analysis can be undertaken to look at the impact of increased speed on the infrastructure, including level crossings

Page 5: 1 Nottingham-Lincoln Stakeholder Board – Network Rail update Doreen Marsh – 26 th February 2015

5 5

Network Rail Update – Items 6a to 6i

Item 6c Newark Castle Switch & Crossing (points) Relocation & Item 6e Newark East Switch & Crossing (Points) Relocation)

The installation of the new S&C to the East of Newark Castle is programmed for August 2015.

The existing S&C at Newark Castle operated locally at the Signalbox will remain in use until the new signalling is commissioned. At this point the existing S&C will be removed and the new layout controlled from the Workstation in EMCC.

Page 6: 1 Nottingham-Lincoln Stakeholder Board – Network Rail update Doreen Marsh – 26 th February 2015

6 6

Network Rail Update – Items 6a to 6i

Item 6d Newark Flyover Scheme

•GRIP 2 feasibility report issued for comment

•Further work required to close out alternative options to a flyover e.g. tunnel (this will be required for TWA process)

•Dynamis modelling to be undertaken to prove the proposed gradients are acceptable for freight operators – to be completed by end of April 2015

•The Business Case for Newark flyover does include the benefits to services of removing the speed restriction on the ECML at the flat crossing. The flat crossing is the only constraint on the line speed here.

Page 7: 1 Nottingham-Lincoln Stakeholder Board – Network Rail update Doreen Marsh – 26 th February 2015

7 7

Network Rail Update – Items 6a to 6i

Item 6f Newark Castle – Swinderby Journey Time Improvement

• The funding from the Network Rail Discretionary Fund has been endorsed for GRIP2/3 development. At the close of the development and subject to revisited business case an application for the funding to deliver the full scheme will be made.

• The project team are currently reviewing the remit and scope with a view to providing an estimate and programme by the end of February.

• Governance for Railway Investment Projects (GRIP)

Page 8: 1 Nottingham-Lincoln Stakeholder Board – Network Rail update Doreen Marsh – 26 th February 2015

8 8

Network Rail Update – Items 6a to 6i

Item 6g Collingham – Swinderby Resignalling

• The purpose of the Swinderby Signalling Renewals Project is to renew signalling, power and level crossing assets in the Swinderby Signal Box Control Area. With the addition of an upgraded power supply, the project will provide more reliable infrastructure.

• The project will close Swinderby Signal Box and transfer signalling control into the Lincoln Signalling Control Centre.

• A number of the level crossings are to be converted to MCB-OD, and it is anticipated that Cross Lane AHBC is to be closed.

• The Project Remit and scope documents have been assigned to a Project Manager and are being assessed prior to inception.  Whilst the initial project programme is being developed, it is anticipated that commissioning / completion will take place in the 2018/19 Financial Year.

Page 9: 1 Nottingham-Lincoln Stakeholder Board – Network Rail update Doreen Marsh – 26 th February 2015

9 9

Network Rail Update – Items 6a to 6i

Item 6h Lincoln Level Crossings

Brayford • Planning approved on 9.4.13 with 12 conditions• The swan island was launched in December 2013 and is

successfully being used by swans.• A value engineering exercise has recently been

completed and the design will shortly be submitted to the Planning authority under an Amendment to the original planning application.

• Footbridge Construction programme is anticipated commence in March 2015 with the service diversions.

Page 10: 1 Nottingham-Lincoln Stakeholder Board – Network Rail update Doreen Marsh – 26 th February 2015

10 10

Network Rail Update – Items 6a to 6i

Item 6h Lincoln Level Crossings

High Street• Planning approved on 29.1.14.• The design is continuing.• Vacant possession of 179 High Street has been obtained.• Soft stripping within the building has commenced.• The service diversions and other enabling works (removal of

trees) have been completed in February 2015.• The highway enabling works are planned to commence

under a full road closure from 23rd February 2015 for 2 weeks.

• Construction will commence on 9th March 2015 under partial road closures and should be in completed by March 2016

Page 11: 1 Nottingham-Lincoln Stakeholder Board – Network Rail update Doreen Marsh – 26 th February 2015

11 11

Network Rail Update – Items 6a to 6i

Item 6i Station Car Parks• Annual Passenger Journeys data from the ORR indicate historical growth trends

at Carlton, Lowdham and Fiskerton

CARLTON

• There is potential to improve current facilities-surface & cycle facilities. Max car park spaces 10-15.

Page 12: 1 Nottingham-Lincoln Stakeholder Board – Network Rail update Doreen Marsh – 26 th February 2015

12 12

Network Rail Update – Items 6a to 6i

Item 6i Station Car Parks

LOWDHAM

Network Rail and EMT have looked at the possibility of a car park at Lowdham on the land shown in pink above.

The ground conditions are very poor and the costs associated with trying to sort this out far exceed the benefit of a 15 space car park.

Propose that we do not take this forward.

Page 13: 1 Nottingham-Lincoln Stakeholder Board – Network Rail update Doreen Marsh – 26 th February 2015

13 13

Network Rail Update – Items 6a to 6i

Item 6i Station Car Parks

FISKERTON

• A 12 space car park but could be expanded.

EMT Estates and Network Rail will look at the suitability of a car park at Fiskerton and will report back at the next Board meeting.

Page 14: 1 Nottingham-Lincoln Stakeholder Board – Network Rail update Doreen Marsh – 26 th February 2015

14 14

Network Rail Update – Items 6a to 6i

Item 6i Station Car Parks

FUNDING

• If Stations Commercial Project Fund (SCPF) is re-launched at some point criteria and business case should be checked.

• National Stations Improvement Project (NSIP) funds are currently fully allocated,

and to date there is no indication of a second tranche.

Page 15: 1 Nottingham-Lincoln Stakeholder Board – Network Rail update Doreen Marsh – 26 th February 2015

15 15

Network Rail Update – Items 6a to 6i

Item 6i Station Car Parks

CURRENT NSIP SCHEMES

• A contribution to the wider Lindongate scheme (City of Lincoln Council Scheme), where the station footbridge will be replaced, the car park will be relocated and improvements will be made to the station forecourt. The car parking numbers will remain the same, however this may change. Lindongate Scheme (extract from plan subject to change)

Page 16: 1 Nottingham-Lincoln Stakeholder Board – Network Rail update Doreen Marsh – 26 th February 2015

16 16

Network Rail Update – Items 6a to 6i

Item 6i Station Car Parks

CURRENT NSIP SCHEMES

• Reopening of the station building at Newark Castle to provide waiting area, ticket office, retail and toilets.  The condition survey has been completed and the remedial works are due to start in the next few weeks. No plan available. Newark Castle Station Building to be re-opened: