1 preliminary design of china iter tbm with helium-cooled and solid breeder concept preliminary...
TRANSCRIPT
1
Preliminary Design of China ITER TBM
with Helium-Cooled and Solid Breeder Concept
Preliminary Design of China ITER TBM
with Helium-Cooled and Solid Breeder Concept
Presented By: K.M. Feng
(On behalf of CH HCSB TBM Team)
Presented at 3rd PRC/US MCF Collaboration workshop – Dalian, China, May 18-19, 2006` 1
2
Outline
I. Introduction
II. Design Progress
III. Performance Analysis
IV. R&D and Test Plans
V. Possible Collaborations
VI. Summary
3
ITER will pay a very important role in first integrated blanket testing in fusion environment. Some DEMO blanket relevant technologies, such as tritium-breeding self-sufficiency, exaction of high-grade heat, safety requirement, and design criteria will be demonstrated in ITER test blanket modules (TBMs).
China planed to develop independently own TBM for testing during ITER operation period based on China’s DEMO definition and development strategy.
The preliminary design and analysis of HC-SB TBM have been carried out recently. Possible collaborations on TBM R&D with other partiers have been proposed.
I. IntroductionI. Introduction
4
ITER,TBM and DEMO
5
Definition of DEMO in China The DEMO in China is to demonstrate the safety,
reliability and environment feasibility of the fusion power plants, meanwhile to demonstrate the prospective economic feasibility of the commercial fusion power plants.
Utilization of fusion energy have still a long way to go towards an economically commercial power plant. DEMO in China should be an indispensable step prior to the commercial application.
In addition, China is interested in non-electric applications of fusion energy, such as HLW disposal and hydrogen production, etc.; we expect that these applications will benefit the ultimate development of the fusion power plants.
6
Two options of breeding blanket with ceramic and lead lithium-lead breeders might be chosen as China’s DEMO blanket concepts under the conditions of meeting the requirement of the neutronics, thermo-hydraulics and mechanics aspects.
Selection of DEMO Blanket
HC-SB DEMO Blanket(SWIP) DCLL DEMO Blanket(ASIPP)
7
Selected HCSB DEMO Parameters
Chinese HC-SB Demo Parameters
Fusion power/electric power (MW) 2000 / ~ 600MWe
Major radius (m) 7.0m
Minor radius (m) 2.5m
Neutron wall load (MW/m2) ~ 2.0
Surface heating (MW/m2) ~0.3
Tritium breeding ratio (TBR) >1.1
Availability (%) 50-70
Divertor peak load (MW.a/m2) 8.0 (water-cooled)
Plasma operation mode Continuous
HC-SB DEMO Blanket Design
23
The assembly view of HCSB-DEMO blanket
The isometric view The bird view
24The explosive view of HCSB-DEMO blanket
9
II. Design progressII. Design progress of of CH CH HC-SB EM-TBMHC-SB EM-TBM
10
It is in agreement with other parties’s design, HC-SB TBM design is based on a vertical half-port space in test Port C;
630mm(d) X 660mm(w) X 890mm(h)
Test Port Space for CH HC-SB TBM
HCS
TWCS
HC-SB
EM-TBM
(I)
HC-SB
EM-TBM
(II)
Port C
HC-SB TBM
11
Originally Design of CH HC-SB TBM
( 2004 Version )
12
1-beryllium armor, 2-multiplier zone, 3-sidewall, 4-U-shaped shell, 5-cooling pipes, 6-breeder zone, 7-backplane, 8-He coolant(hot leg), 9-measure access, 10-attachment, 11-purged, 12-He coolant (cold leg)
Outline view for CH originally HC-SB TBM design
Be
SolidBreeder
Back-plane
He He
13
Exploded 3-D view of Modified Design of HC-SB TBM (2005 Version)
Structure and components design in detail is on going.
14
Structure Design for EM-TBNBe armor: 2 mm Max Temp. 514OCFirst wall thickness: 30 mm Material: Eurofer Max T: 506OC Cooling tube: 18x14.5mmUnit cells: 3X3 sub-modulesHe pressure: 8 MPa
664mm
Integration view of structure design
Sub-modules0.190 m in toroidal0.420 m in radial0.260 m in poloidal
664mm
890mm
630mm
15
Schematic view of CH HC-SB EM-TBM
Outside of structure Cross-section of module Coolant manifold
Sub-module structure View of the back-plane Configuration of Sub-modules
16
Connection of Up-down Modules
HC Pipe (outlet)
HC Pipe (inlet)
Connection
•Modularizing structure
•Parallel connecting two modules
Up module
Down module
17
Connection of ComponentsHe outlet of FW He inlet of FW
Structure View of FW and Backplane
He
He
He outlet of FW
He inlet of FW
He CollectionOf Grid
He outlet of FW
He inlet of FW
Flow path of Coolant (1)
Purgemanifold
Flow path of Coolant (2)U-shaped first wall
Sub-modules
Back-plane
Test Blanket Module Port Plug Frame Plumbing Interface 2
HC-SB EM-TBM in frame
FW attachment
TBM in ITER frameFlow path of coolant
18
Structure View of Back-plane
He outlet
Purge outlet
Measure Channel
Purge inlet
He inlet
Purge Collectionmanifold
Purge Supplymanifold
He Supplymanifold
He Collectionmanifold
He Middlemanifold
The back-plane closes the sub-module box from the near
side, provides the support for the mechanical attachment
at the interface with the ITER Port Plug and forms a
manifold system for others part of TBM
Arrangement of back-plane
Top view of manifold
19
Assembly of HC-SB EM-TBM in frame
TBM module Frame
20
HCSB TBM integrated assembly
21
Items NT-TBM EM-TBM
Configuration BOT (Breeder Out of Tube) Modules: 3×3 Sub-modules Modules: 3×3 Sub-modules
First wall area
Neutron wall loading
Surface heat flux
0.664 m(W)×0.890 m(H) 0.591 m2.
0.78 MW/m2
0.3 MW/m2 (normal condition)
0.5 MW/m2 (extreme condition)
0.591 m2 + 0.591 m2 (Vertical).
0
0.1 MW/m2 (normal condition)
0.3 MW/m2 (extreme condition)
Total heat deposition surface heat flux included 0.76 MW 0.177 MW
Globe TBR Lithium orthosilicate, Li4SiO4 1.15 (1-D), 80% Li-6
Tritium production rate ITER operation condition 2.23 ×10-2 g/d
Sub-module dimension (P)× (T) × (R) 260 mm×190 mm×420 mm 260 mm×190 mm×420 mm
Ceramic breeder (Li4SiO4)
Two size
Thickness
Max. Temperature
Diameter: 0.5~1 mm, pebble bed
90 mm (four zones)
737 ℃
SiC pebble bed, 0.5~1 mm
Neutron multiplier
(Beryllium)
Two size
Thickness
Max. Temperature
Diameter: 0.5~1 mm, Pebble bed
200 mm(five zones)
617 ℃
Al pebble bed, 0.5~1 mm
Be armor Thickness
Max. Temperature
2mm
543 ℃2mm
514 ℃
Structure Material Ferritic steel
Max. Temperature
EUROFER
530 ℃
EUROFER
506 ℃
Coolant helium (He)
Pipes size
Pressure
Pressure drop
Temperature range (inlet/outlet)
Mass flow
Diameter (OD/ID)
8 Mpa
0.294 MPa
300/500 ℃0.73 kg/s
85/80 mm
8 Mpa
0.051 MPa
300/411 ℃0.31 kg/s
85/80 mm
He purge flow (He) Pressure
Pressure drop
0.12 MPa
0.02 MPa
Design parameters for the HC-SB TBM
22
Schematic views of Coolant flow
Coolant flow in the sub-module Coolant flow in FW
Back-plate
Coolant Flow Direction
Back-plate
23
HC-SB TBM Auxiliary System
HC-SB
TBM
HC-SB
TBM HCS CPS
VV Port Cell TWCS vault
Tritium Building
BC
TES
TMS
NMS
24
HC-SB TBM Auxiliary Sub-system Design
21Flow scheme of the HCS system
HC-SB TBM
3 . 5 x2.5m2
Dust filter
Main HX
recuperator
Electric heater
Circulator
Valve
Draft layout of the helium cooling subsystem in the TCWS
TWCSHCS
TBM
Helium Cooling System (HCS)
29
Neutron Measurement System (NMS)
Schematic diagram of neutron fluxes
and spectra measurement system
micro-fission chamber
micro-fission chamber assembly 23Space Arrangement in TCWS for HCS subsystem
Space requirement:
A minimum net foot print area of 16 m2 in the TCWS vault, 0.5m3 in transfer cask, will be needed
Space requirement:
A minimum net foot print area of 16 m2 in the TCWS vault, 0.5m3 in transfer cask, will be needed
HCS TMS TES
CPS NMS TCWS
27
Coolant Purification System (CPS)
1
3 a
4
6 a 6b
7a 7b
8
9
He , 30 0 ℃
3 00 ℃H e, 1 0M P a
5
E S
E S
3 b
1 0
H e
2 a2 b
Layout of the CPS
Flow chart of the CPS
2200
1500
1200
1-gas flow controller; 2a/2b-impurities getter bed; 3a/3b-tritium getter bed; 4-heater; 5-cooler; 6a/6b-buffer bank; 7a/7b-ionizationchamber;
8-gas chromatograph9—circulator; 10—ZrCobed
Space requirement:A space of 1500mm×1200mm×2200mm (L×W×H) is neededfor its assembly, maintenance and operation of the CPS.
26
Tritium Extraction Subsystem (TES)
4 b
9 b
34 a
E S
6
7
8 a 8 b
9 a 1 0
1 1 a
1 2
E S
1 3 a
1 4 b
1 4 a
9 c
1 5H e
1 1 b
1 6
H 2
T r i t i u m E x t r a c t i o n S y s t e m f o r T B M
1 3 b
1 3 c
4 c
1
2 a
2 b
1 T B M2 a / 2 b F i l t e r3 C o o l e r4 a / 4 b / 4 c I o n i z a t i o n C h a m b e r5 C o l d T r a p6 W a t e r C o l l e c t o r7 R e c u p e r a t o r8 a / 8 b M o l e c u l a r S i e v e s9 a / 9 b / 9 c B u f f e r1 0 H o t M g B e d1 1 a / 1 1 b C o m p r e s s o r1 2 P d / A g P e r m e a t e r1 3 a / 1 3 b / 1 3 c G e t t e r B e d1 4 a / 1 4 b I S S1 5 H e a t e r1 6 M a k e - u p U n i t
C h e c k v a v l eO p e n v a v l eC l o s e d v a v l eP r e s s u r e r e d u c i n g v a v l e
E S E v a c u a t i o n s y s t e m
± ±
± 5
V 1V 2
Flow chart of the TES sub-system Lay-out of the TES sub-system
Space Requirem ent:
The TES system must be installed in a glove box.
The size of the G love Box is: 5.5m× 1.2m× 5.5m (L× W× H).30
Tritium Measurement System (NMS)
The schematic of the gas flow calorimeter
Flow chart of the TMS
Layout of the TMS
25
Neutronics Measurement System Design
Schematic diagram of neutron fluxes and spectra measurement system and
cooling loop for NT-TBM
micro-fission chamber
micro-fission chamber assembly
26
Iii. Performance Analysis for EM-TBMIii. Performance Analysis for EM-TBM
27
A. Neutronics design B. Thermo-hydraulic Analysis C. Thermo-Mechanical Analysis D. Preliminary E-M analysis; E. Preliminary LOCA, LOFA analysis, etc.,
Above performance analysis have been completed. Others calculation and performances analyses are on going.Related results have been given in the CH HC-SB TBM DDD report last year.
Preliminary Performance Analysis for EM-TBM
28
Performance Analysis for HC-SB TBM (Con’t)
Calculation Model
Temperature on Flow Channel Flow scheme
27
Coolant Flow Scheme
Temperature distribution of FW(Coolant velocity in FW outlet is 69m/s)
Normal Condition, Max. T=453 0C Extreme Condition, Max. T=513 0C
Normal Condition, Max. T=340 0C Extreme Condition, Max. T=422 0C
Temperature distribution The displacement vector sum
The stress distribution
Peak stress is 63.5 MPa
[1].Temperature at FW outlet is fixed at 4110C for test of high temperature performance of FW.
Components
Normal condition Extreme condition
EM-TBM NT-TBM EM-TBM NT-TBM
Neutron surface loading [MW/m2] 0 0.78 0 0.78
Surface heat flux [MW/m2] 0.1 0.3 0.3 0.5
Helium pressure [MPa] 8 8 8 8
Helium inlet/outlet temperature [°C] 300/411 300/500 300/411 300/500
Total power (surface heat flux included) [MW] 0.059 0.64 0.177 0.76
Power from surface heat flux [MW] 0.059 0.18 0.177 0.30
Power from nuclear heating [MW] 0 0.46 0 0.46
Total Mass flow rate of helium [kg/s] 0.10 0.62 0.31 0.73Mass flow rate of helium in
FW [kg/s] 0.10 0.62 0.31 0.73
Single sub-module [kg/s] 0.011 0.065 0.032 0.077
Top and bottom plates [kg/s] 0.0057 0.03 0.017 0.04
Velocity of helium in
FW [m/s] 9.0 58 27 69
Sub-module [m/s] 2.4 15 7.2 18
Pressure drop of coolant in module [MPa] 0.0066 0.21 0.051 0.29
Pressure drop in FW [MPa] 0.0059 0.19 0.045 0.26
Pressure drop in sub-module [MPa] 0.00068 0.02 0.0052 0.03
Main Design Parameters of HC-SB EM-TBM[1]
[2]. Coolant velocity in FW outlet is fixed at 69m/s, to test the hydromechanics performance of FW channel.
ComponentsNormal condition Extreme condition
EM-TBM NT-TBM EM-TBM NT-TBM
Neutron surface loading [MW/m2] 0 0.78 0 0.78
Surface heat flux [MW/m2] 0.1 0.3 0.3 0.5
Helium pressure [MPa] 8 8 8 8
Helium inlet/outlet temperature [°C] 300/313.4 300/500 300/341 300/500
Total power (surface heat flux included) [MW] 0.059 0.64 0.177 0.76
Power from surface heat flux [MW] 0.059 0.18 0.177 0.30
Power from nuclear heating [MW] 0 0.46 0 0.46
Total Mass flow rate of helium [kg/s] 0.85 0.62 0.83 0.73Mass flow rate of helium in
FW [kg/s] 0.85 0.62 0.83 0.73
Single sub-module [kg/s] 0.089 0.065 0.087 0.077
Top and bottom plates [kg/s] 0.047 0.03 0.046 0.04
Velocity of helium in
FW [m/s] 69 58 69 69
Sub-module [m/s] 18 15 18 18
Pressure drop of coolant in module [MPa] 0.31 0.21 0.31 0.29
Pressure drop in FW [MPa] 0.28 0.19 0.28 0.26
Pressure drop in sub-module [MPa] 0.033 0.02 0.031 0.03
Main Design Parameters of HC-SB EM-TBM (con’t)[2]
31
Safety Analysis of CH HC-SB TBM
Direction: The relevant safety analysis is need to meet the requirements in GSSR and French Nuclear Safety Authority (NSA); For each component all the possible failure modes, in the various operating phases, will be evaluated.
Progress: Some results of safety analysis are presented in the CH HC-SB TBM DDD report last year.
A safety working group (SWG) in China for licensing, QA and safety report of CH TBM, which consists of State Nuclear Safety Bureau, State Environment Protection Bureau and design institutions, will be organized soon. A systematic approach ( FMEA) will be established after determining all components and sub-systems;
32
Safety Analysis (con’t)
36
Safety Analysis of CH HC-SB TBM (cont.)? activity and decay heat analysis
Total activity generated and contribution from each material
Total afterheat generated from each material
A total activity of 5.43×105 Ci is attained at shutdown with a contribution of 5.39× 105Ci from the structure, 3.7×103Ci from the Li4SiO4.
At shutdown, the total decay heat is ~8.77× 10-3 MW with a contribution of 8.71× 10-3 MW and 6.36× 10-5 MW from structure material and Li4SiO4, respectively.
38
Safety Analysis for CH HC-SB TBM (cont.)? LOCA and reliability analysis
Pressure transients from different models vs. time
Temperature changes of materials after the end of blow-down
LOCA analysis shows depressurization of the TBM helium coolant occurs within 10 to 15 s. Contribution to the pressure build-up in the VV is small (17.8 kPa). Tritium and activation products released from the TBM into the VV are insignificant compared to the total amount mobilized from non-TBM components. The TBM FW temperature can be kept, after the disruption burst has decayed variant to the reference case, with postulated unlimited steam access to the pebble beds, the estimated hydrogen production is the order of g only and the chemical heat is negligible.
Deformation Equivalent Stress
39
Simplified 1/4 sub-moduleSeparated model
MODEL A MODEL B
Safety Analysis of CH HC-SB TBM (cont.)? electromagnetic analyses models
41
Safety analysis of CH HC-SB TBM (cont.)? electromagnetic analysis
The simplified 3-D model The maximum induced eddy currents under CDII The maximum stresses components of model B
The maximum stresses of model A The EM torques of model A and model B The EM torques of the nine sub-modules
45
Safety Analysis for CH HC-SB EM-TBM (cont.)? Preliminary LOFA analysis for EM-TBM
e=0. 7
0
100
200
300
400
500
600
700
800
900
1000
0. 1 1 10 100 1000 10000 100000
Ti me/ s
Temp
erat
ure/
o C
Fi r st Wal lBack Wal lHot t est Poi nt
e=0. 3
0
200
400
600
800
1000
1200
1400
0. 1 1 10 100 1000 10000 100000
Ti me/ s
Temp
erat
ure/
o C
Fi r st Wal lBack Wal lHot t est Poi nt
Plasma no disruption: ex-vessel TBM coolant leaks
The two figures show temperature changes of materials after loss of flow accident. The smaller heat radiation emissivity of material is , the rapider temperatures of material increase. Under this accident condition, the auxiliary coo l sys tem is necessa ry to decrease the tem perature o f TBM shel l.
44
Plasma disruption: in-vessel TBM coolant leaks
e=0. 7
0
100
200
300
400
500
600
700
0. 1 1 10 100 1000 10000 100000
Ti me/ s
Te
mp
er
at
ur
e/oC
Fi r st Wal lBack Wal lHot t est Poi nt
e=0. 3
0
100
200
300
400
500
600
700
0. 1 1 10 100 1000 10000 100000
Ti me/ s
Temp
erat
ure/
o C
Fi rst Wal lBack Wal lHot test Poi nt
Safety Analysis for CH HC-SB EM-TBM (cont.)? Preliminary LOCA analysis for EM-TBM
This figure shows temperature changes of m aterials after the end of blow -down. When heat radiation emissivity of material is 0.7, the peaking value of FW is about 623 OC at the transient time of about 1s.
This figure shows temperature changes of materials after the end of blow-down. W hen heat radiation emissivity of material is 0.3 , the peaking value of FW is about 623 OC, too, at the transient time of about 1s. But curves have different change trends after 1000s.
Activation & afterheat Reliability analysis E-M calculation model
E-M analyses LOCA analyses LOFA analyses
33
VI. Test and R&D plansVI. Test and R&D plansVI. Test and R&D plansVI. Test and R&D plans
34
Relevant R&D plans System Integration, Out-pile R&D
• Module fabrication technology
• Thermo-mechanical integrity of module
• Thermo-mechanical performance
• Thermal hydraulic research
System Integration, Out-pile R&D
• Module fabrication technology
• Thermo-mechanical integrity of module
• Thermo-mechanical performance
• Thermal hydraulic research
In-pile R&D
• Breeder/multiplier development
• Irradiation technology development
• Irradiation tests of blanket partial mockup
In-pile R&D
• Breeder/multiplier development
• Irradiation technology development
• Irradiation tests of blanket partial mockup
Tritium Recovery System Development
• Process and system development
for hydrogen pump,
• Coolant purification system
Tritium Recovery System Development
• Process and system development
for hydrogen pump,
• Coolant purification system
Neutronics / Tritium Production
Tests with 14MeV neutrons
• Neutronics performance of blanket
mockup and improvement of analysis accuracy
Neutronics / Tritium Production
Tests with 14MeV neutrons
• Neutronics performance of blanket
mockup and improvement of analysis accuracy
Material Development
• Irradiation data of RAFM (CLAM), etc.
• Environmental effect, etc.
Material Development
• Irradiation data of RAFM (CLAM), etc.
• Environmental effect, etc.
35
Irradiation Test on High Flux Reactors
China has built a High Flux Engineering Test Reactor (HFETR) in the China Institute of Nuclear Power (CINP) . HFETR is a largest one in Asia.
Neutron Flux: Thermal neutrons : 6.2×1014 n/cm2•sec; (E<0.625eV) Fast neutrons : 1.7 ×1015 n/cm2•sec; (E>0.625eV) 235U of 90% enriched in U fuel. Total power: 125 MW (th)
In addition, there are two sets experiment reactors with power of 20MW and 40MW are constructing in CIAE and CAEP of China.
These facilities and their ability are useful for the irradiation experiment of the TBM structure materials, tritium breeders, neutron multiplier etc.
High Flux Engineering Test Reactor (HFETR)
36
High Temperature He Experiment Loop
A High Temperature He Experiment Loop (HTHEL) with 700 OC and 8-10 MPa, which is useful for HC-SB TBM design and R&D activities, is proposed to be built in SWIP.
China has built a high temperature gas-cooled reactor (HTGR). The technologies and experiences gained in HTGR project will be useful.
Temp.: 900 OC, Total Power: 10MW Pressure: 3 MPa
He Test Loop for HTGRHTHEL sketch map
37
Solid Breeder Technology China has studied tritium-processing technology supported by
national fusion program for many years. Knowledge accumulated in this field is useful for the TBM tritium technology.
Two kinds of ceramic breeder( Li4SiO4 , Li2TiO3 ), are developing in China.
Fabrication sample of the Li4SiO4 pebbles Fabrication of the ceramic powder
38
General Design and R&D Schedule for HC-SB TBM
Items 06 07 08 09 10 11 12 13 14 15 Day 1
Design Phase
Detail design
Engineering design
Materials Development
Ceramic Breeder, Li4SiO4 , Li2TiO3
Structural material , (RAFS steel)
Neutron multiplier, Be
Performance Testing
In-pile testing
Out--pile testing
Tritium Technology
Tritium Extraction Technology
Tritium permeation Barriers
Coolant purification simulation loop
39
Years 06 07 08 09 10 11 12 13 14 15TBM Sub-components qualification.
Small mock-ups fabrication
Test/qualification
TBM Functional tests
Small and medium size mock-ups fabrication
Small and medium sizes mock-ups tests
Full size mock-ups fabrication
Full size mock-ups tests
EM-TBM for installation
CH EM-TBM fabrication
CH EM- TBM acceptance tests
ITER OperationDay one
Time Schedule for CH HC-SB TBM Fabrication and Test
40
Proposed test facilities prior to TBMs installation in ITER
Facilities name Main objectives Parameters Location
A high temperature He Experiment Loop based on China HTGR technologies.
TBM mock-ups test 500-700 OC and 8-10 MPa (adjustable)
SWIP/ (planning)
A facility for high heat flux properties test
Evaluation of plasma facing materials and components
Max. power density: 20 MW/m2,
Active cooling, control of the temperature of coolant from RT-150
SWIP/ (planning)
High Flux Engineering Test Reactor (HFETR)
Materials Test Thermal neutrons : 6.2×1014 n/cm2•sec; (E<0.625eV)Fast neutrons : 1.7 ×1015 n/cm2•sec; (E>0.625eV)
CINP/ (existing)
Facilities of tritium extraction, purification, permeation , and test
Tritium extraction and recovery experiment from the purge gas and coolant.
TBD CAEP,
CIAE & SWIP (planning)
41
1. CH TBM Projects1. CH TBM Projects
1.1 Test Blanket Module1.1 Test Blanket Module
1.3.1 QA Management 1.3.1 QA Management
1.3.2 Safety & Licensing
1.3.2 Safety & Licensing
1.3.3 Test Plane Management
1.3.3 Test Plane Management
1.1.1 Design1.1.1 Design
1.2 Ancillary System1.2 Ancillary System 1.3 Project Strategy1.3 Project Strategy
1.3.4 Testing Relevant R&D
1.3.4 Testing Relevant R&D
1.1.2 Performance Analysis
1.1.2 Performance Analysis
1.1.4 Prototype Fabrication & Testing
1.1.4 Prototype Fabrication & Testing
1.1.5 TBM Fabrication & Assembly
1.1.5 TBM Fabrication & Assembly
1.2.1 Design, R&D1.2.1 Design, R&D
HCSHCS TESTESCPSCPS
MSMS
1.2.3 Fabrication & Assembly
1.2.3 Fabrication & Assembly
1.2.4 TBM integration installation
1.2.4 TBM integration installation
1.1.3 Technology Relevant R&D
1.1.3 Technology Relevant R&D
1.2.2 Testing integrationPerformance
1.2.2 Testing integrationPerformance
Work Breakdown Structure of HC-SB TBM
..\..\WBS系统\WBS(06-02-28).xls
Tritium technologies - Tritium extraction & - Tritium control and ISS
- Tritium loop qualification
- Tritium permeation Barriers
Ceramic breeder technologies
- Fabrication;
- Performance test;
- Irradiation test. Thermo-mechanics and helium flow test
Test of on the pebble bed thermo-mechanics and helium flow stability and distribution by means of a high temperature, high pressure He test loop.
Expected Collaboration on TBM R&D
43
Domestic Cooperation Units on R&D for HCSB TBM
SWIP Southwestern Institute of Physics
(TBMs)
SICCAS Shanghai Institute of Ceramics, Chinese Academy of Sciences
(Ceramic Breeder)
TUNETTinghua Uni, Institute
of Nucl. Energy Tech.(HCS)
TUNETTinghua Uni, Institute
of Nucl. Energy Tech.(HCS)
CAEPChina Academy of Engineering Physics
(CPS, TES)
CAEPChina Academy of Engineering Physics
(CPS, TES)
Ningxia Orient Non-ferrous Metal Group CO.,LTD
Be pebbles
44
V. SummaryV. Summary
New progress and status of CH HC-SB TBM are introduced briefly. By ITER TBM testing, demonstrative data of blanket functions will be obtained in fusion environment.
A preliminary design and analysis for CH HC-SB TBM has been preformed The detailed design and analysis of EM-TBM are ongoing.
Preliminary R&D program, timescale and milestones, up to the installation in ITER (2015), as well as the collaboration expected with other Parties are presented.
Relevant R&D on the key techniques will be preformed with the cooperation of domestic and international institutions and companies.
45
Thank you for your attention!