1 © the delos partnership 2004 project management planning the project
TRANSCRIPT
1 © The Delos Partnership 2004
Project ManagementProject Management
Planning the Project
2 © The Delos Partnership 2004
Up, Down and Acrossthe Company
PlanningPlanning
At the end of this session you will have an understanding of the following:-
• The Planning Process
• The Planning Hierarchy– WBS– Plans– Schedules
3 © The Delos Partnership 2004
Planning ProcessesPlanning Processes
6.3 6.3 Activity Activity Duration Duration
EstimatingEstimating
6.3 6.3 Activity Activity Duration Duration
EstimatingEstimating
5.2 5.2 Scope Scope
PlanningPlanning
5.2 5.2 Scope Scope
PlanningPlanning
5.3 5.3 Scope Scope
DefinitionDefinition
5.3 5.3 Scope Scope
DefinitionDefinition
6.1 6.1 Activity Activity
DefinitionDefinition
6.1 6.1 Activity Activity
DefinitionDefinition
7.17.1Resource Resource PlanningPlanning
7.17.1Resource Resource PlanningPlanning
6.26.2Activity Activity
SequencingSequencing
6.26.2Activity Activity
SequencingSequencing
7.27.2CostCost
EstimatingEstimating
7.27.2CostCost
EstimatingEstimating
6.46.4Schedule Schedule
DevelopmentDevelopment
6.46.4Schedule Schedule
DevelopmentDevelopment
7.37.3CostCost
BudgetingBudgeting
7.37.3CostCost
BudgetingBudgeting
4.14.1Project Plan Project Plan DevelopmentDevelopment
4.14.1Project Plan Project Plan DevelopmentDevelopment
N.B. All numbering refers to the PMI® Project Management Body of Knowledge (PMBOK) Knowledge Areas
4 © The Delos Partnership 200419/04/23
InputInput OutputOutputProcessProcess
Phases
Objectives
Deliverables
Acceptance Criteria
CharterProjectCharter Scope
Plan
Wave 1 Wave 2
Scope PlanningScope Planning
5 © The Delos Partnership 200419/04/23
InputInput OutputOutputProcessProcess
Decomposition
Objective
Work Breakdown Structure
Charter
ScopePlan
Charter
Scope Plan
WBS
Scope DefinitionScope Definition
6 © The Delos Partnership 2004
Why Define the Why Define the Work Breakdown Structure?Work Breakdown Structure?
•To manage a project successfully, you must first have a clear understanding of the amount of work you are required to complete
•Only then can the cost and schedule of your project be estimated and controlled with any confidence
•The WBS identifies all the work to be performed I.e. the Scope of the Project. If it is not in the WBS it is not part of the project
•It can often be as important to say what is not within scope
7 © The Delos Partnership 2004
GoalGoalGoalGoal
Objective 1Objective 1Objective 1Objective 1 Objective 2Objective 2Objective 2Objective 2 Objective 3Objective 3Objective 3Objective 3
Deliverable 1Deliverable 1Deliverable 1Deliverable 1 Deliverable 2Deliverable 2Deliverable 2Deliverable 2 Deliverable 3Deliverable 3Deliverable 3Deliverable 3
Defining the WBSDefining the WBS
TaskSub Tasks
Task Sub Task
TaskSub Tasks
Task Sub Task
TaskSub Tasks
Task Sub Task
8 © The Delos Partnership 200419/04/23
InputInput OutputOutputProcessProcess
Activity ListsCharter
Scope Plan
WBS
Charter
Scope Plan
WBS
Project Task List
Activity DefinitionActivity Definition
9 © The Delos Partnership 2004
Case StudyCase Study
Breakout Session 2
10 © The Delos Partnership 200419/04/23
InputInput OutputOutputProcessProcess
Dependencies
Project Visual (Network Diagram)
Charter
Scope Plan
WBS
Charter
Scope Plan
WBS
Project Task List Project Task List
NetworkDiagram
Activity SequencingActivity Sequencing
11 © The Delos Partnership 200419/04/23
Creating the Project VisualCreating the Project Visual(The Network Diagram)(The Network Diagram)3 Types of Dependencies
– Mandatory• No choice e.g. the walls must go up before the
roof can go on
– Discretionary• Preferred by stakeholders e.g. like the kitchen
done before the lounge
– External• Legally required e.g. planning permission before
you start
12 © The Delos Partnership 2004
Creating the Project VisualCreating the Project Visual(The Network Diagram)(The Network Diagram)• Facilitates engaging the project team
and other stakeholders
• Sanity Check
• Helps determine the critical path
Critical Path = A:D:E:F:H:I= 2+6+2+2+2 = 16 (weeks)
A
D
B C
E
G
F
H I
2
2 6
11 2
1 1
2
2
13 © The Delos Partnership 2004
Critical Path MethodCritical Path Method
The focus on CPM is to determine float in order to determine which tasks have the most and the least scheduling flexibility
A
D
B C
E
G
F
H I
Critical Path = A:D:E:F:H:I= 2+6+2+2+2 = 16 (weeks)
2
2 6
11 2
1 1
2
2
14 © The Delos Partnership 200419/04/23
Critical Path MethodCritical Path Method
• What is the critical path? (no scheduling flexibility)
• Where is the float/slack? (some scheduling flexibility)
Start Finish
A=1
F=1
B=4
P=3
M=3
I=3
D=2
O=2
G=1
N=1
Dummy
C= 2
Q=3
L=6H=2
15 © The Delos Partnership 200419/04/23
Creating the Project VisualCreating the Project Visual(The Network Diagram)(The Network Diagram)Network Diagram (AON, AOA)
– Shows interdependencies of all tasks– Used for planning the project– Used for crashing and fast tracking the
project
16 © The Delos Partnership 200419/04/23
Network Diagrams Aid Network Diagrams Aid Planning Planning Crashing
– Adding more resources to critical path tasks while maintaining scope
• E.g. move resources from non-critical tasks which have float or adding extra resources
Fast Tracking– Doing critical path tasks in parallel that were originally
planned in series
Resource Levelling– Plans out time of tasks (and costs) in favour of a stable
number of resources used consistently in full
17 © The Delos Partnership 2004
Case StudyCase Study
Breakout Session 3
18 © The Delos Partnership 200419/04/23
InputInput OutputOutputProcessProcess
Top Down (Analogous) Estimating
Expert Judgement
Monte Carlo Analysis
Heuristic (Rule of Thumb
Historical Information (Benchmarking)
PERT
a combination of the above….
Charter
Scope Plan
WBS
Project Task List
NetworkDiagram
Charter
Scope Plan
WBS
Project Task List
NetworkDiagram
Duration Estimates
&Assumptions
Activity Duration EstimatingActivity Duration Estimating
19 © The Delos Partnership 200419/04/23
EstimatingEstimating
Estimating– Should be done by people doing the work not just by project
managers
Estimating Methods– CPM
• Has one task per estimate• Emphasis on controlling costs and leaving time line flexible• Can only be drawn on AOA• Can have dummies
– PERT• Has 3 estimates per activity
– Optimistic, pessimistic, most likely– Can be used for time and cost– Emphasis on time with flexibility on cost
© The Delos Partnership 200419/04/23
PERTPERT(Program Evaluation and Review Technique)(Program Evaluation and Review Technique)
1. Estimate for 3 separate scenarios:• Best Case (B), • Most Likely (ML) and • Worst Case (W)
2. Calculate Weighted average estimate by:
(B + 4 ML + W ) / 6
© The Delos Partnership 200419/04/23
Pert Analysis - ExamplePert Analysis - Example
N.B. Standard Deviation = (Best Case + Worse Case) / 6Variance = [(Best Case + Worse Case) / 6] 2
1. Best Case estimate = 10 hours,
Most Likely estimate = 15 hours,
Worst Case estimate = 25 hours.
2. Average estimate = (10 + 4*15 + 25) / 6
= 16 hours.
22 © The Delos Partnership 200419/04/23
PERT PERT
PERT– Estimate = (P+4M+O)/6– Standard Deviation = (P-O)/6– Variance = [(P-O)/6]2
Task
A
B
C
D
O
3
2
5
7
M
6
3
12
8
P
8
4
20
8
DurationStandardDeviation
Variance
23 © The Delos Partnership 200419/04/23
InputInput OutputOutputProcessProcess
PERT (Project Evaluation and Review Technique)
CPM (Critical Path Method)
Resource Levelling
Charter
Scope Plan
WBS
Project Task List
NetworkDiagram
Duration Estimates
&Assumptions
Charter
Scope Plan
WBS
Project Task List
NetworkDiagram
Duration Estimates
&Assumptions
Project Schedule
Schedule DevelopmentSchedule Development
24 © The Delos Partnership 2004
Project ScheduleProject Schedule
Project PlansProject Plans
Activity ListActivity List
• A multi page document (not a Gantt chart)
• Down to the level that you are going to control at
• Rolling Weekly schedule of tasks (<4 weeks out)
The Planning HierarchyThe Planning HierarchyWBS
© The Delos Partnership 200419/04/23
Activity ListsActivity Lists
• Designed to reduce overhead associated with maintenance of more detailed project plan on a weekly basis
• Activity List is a detailed picture of the work assignments and schedule of activities over the coming weeks ( <4 weeks)
– It specifies tasks, resource assignments and the expected start and end dates
– It is updated on a weekly basis, based on actual performance during the preceding week
– Changes in the project work plan are reflected in the activity lists and vice-versa
99
1122
33
66
26 © The Delos Partnership 2004
What is required?...………………...
by when?…………………………….
What must be done?………………….
in what order?………………………….
and by whom?……………………….
How long will each activity (and therefore the whole project) take?...
So how do I make it fit ?…………...
Objectives and deliverables
High level estimates/external milestones
Activities
Dependencies
Resourcing
Detailed work estimates
Reconcile
Scheduling SummaryScheduling Summary
27 © The Delos Partnership 2004
ReconcilingReconciling
• More resources• De-scope• Further breakdown - focus on what’s actually
required• Critical path analysis• Re-time• Levelling - better utilisation of existing resources• Overtime!• Crash• Fast Track
28 © The Delos Partnership 200419/04/23
InputInput OutputOutputProcessProcess
What type of resources are required?
How many?
For how long?
What % of time
Charter
Scope Plan
WBS
Project Task List
NetworkDiagram
Duration Estimates
&Assumptions
Project Schedule
Charter
Scope Plan
WBS
Project Task List
NetworkDiagram
Duration Estimates
&Assumptions
Project Schedule
ResourceRequirements
Resource PlanningResource Planning
29 © The Delos Partnership 200419/04/23
InputInput OutputOutputProcessProcess
Top Down (Analogous) Estimating
Bottom Up Estimating
Parametric Estimating
Resource RatesChart of Accounts
Historical Information
Charter
Scope Plan
WBS
Project Task List
NetworkDiagram
Duration Estimates
&Assumptions
Project Schedule
ResourceRequirements
Charter
Scope Plan
WBS
Project Task List
NetworkDiagram
Duration Estimates
&Assumptions
Project Schedule
ResourceRequirements
Cost Estimates
Cost EstimatingCost Estimating
30 © The Delos Partnership 200419/04/23
InputInput OutputOutputProcessProcess
Grouping of estimatesCharter
Scope Plan
WBS
Project Task List
NetworkDiagram
Duration Estimates
&Assumptions
Project Schedule
ResourceRequirements
Cost Estimates
Charter
Scope Plan
WBS
Project Task List
NetworkDiagram
Duration Estimates
&Assumptions
Project Schedule
ResourceRequirements
Cost Estimates
Baseline Budget
Cost BudgetingCost Budgeting
31 © The Delos Partnership 200419/04/23
InputInput OutputOutputProcessProcess
Project Management Information System
C h a r t e rS c o p e P l a n
W B SP r o j e c t T a s kL i s tN e t w o r k
D i a g r a mD u r a t i o n E s t i m a t e s
&A s s u m p t i o n sP r o j e c t
S c h e d u l eR e s o u r c e
R e q u i r e m e n t s
C o s t E s t i m a t e s
B a s e l i n e B u d g e t
Project Plan DevelopmentProject Plan Development
32 © The Delos Partnership 200419/04/23
InputInput OutputOutputProcessProcess
Quality PlanOrganisational PlanCommunication Plan
External Resource PlanProcurement Plan
Risk Management Plan
InitialProjectCharter
InitialProjectCharter
Project Management Information System
Project Standards
Stakeholder know how
Project Plan DevelopmentProject Plan Development
33 © The Delos Partnership 2004
Quality PlanQuality Plan
• Standards– What requirements do you need to meet?
• Assurance– How will you assure the requirements will
be met?
• Control– How will you verify that the requirements
have been met?
34 © The Delos Partnership 2004
Organisation PlanOrganisation Plan
• Responsibility Breakdown Structure– Who does what?
• Staffing Management Plan– When and how human resources will be
taken on and off the project
• Organisational Chart
35 © The Delos Partnership 2004
Communication PlanCommunication Plan
Themes
Objectives, Scope
Agree “What” to Communicate
Channels, Media
Principles
Agree “How” to Communicate
People
Materials
Develop CapabilityTo Communicate
Escalate Major Issues
Adjust Approach
Review EffectivenessAddress Issues
Listen & Document
Immediate Response
Gather Feedback
Check Understanding
Open Environment
Deliver Communication
36 © The Delos Partnership 2004
Communication PlanCommunication Plan
Channel/Vehicle Description Frequency Potential Audience
Project Plan Microsoft Project Plan with deliverables
Ongoing Steering committee; key stakeholders
Status Reports Progress against deliverables and identification of issues and risks
Weekly Project Office
Update Presentations
Monthly summary of status reports
Monthly All Staff [via key Process owners]
Info Letter Update on Schedule, benefits of Project one
Every Quarter
All Staff
37 © The Delos Partnership 2004
Case StudyCase Study
Breakout Session 4
38 © The Delos Partnership 2004
Procurement Procurement Management PlanManagement Plan• Procurement Planning
• Solicitation Planning
• Solicitation
• Source Selection
• Contract Administration
• Contract Close Out
39 © The Delos Partnership 200419/04/23
InputInput OutputOutputProcessProcess
Make or Buy
Expert Judgement (internal capability / internal capacity / need
for control/ Protection of Intellectual Property / Cost)
Contract Type Selection (Fixed Cost / Cost Reimbursable / Unit Price
Contract)
Scope Statement
Market Conditions
Procurement Management Plan
e.g. What type of contracts will be used?
How will multiple suppliers be managed?
Statement of Work
Procurement PlanningProcurement Planning
40 © The Delos Partnership 200419/04/23
InputInput OutputOutputProcessProcess
Standard Forms
Expert Judgement
Procurement Management Plan e.g. What type of contracts will be used? How will multiple suppliers be
managed?
Statement of Work
Bid Documents
Evaluation Criteria
Solicitation PlanningSolicitation Planning
41 © The Delos Partnership 200419/04/23
InputInput OutputOutputProcessProcess
Advertising
Bidders Conference
Agencies
Internet
Bid Documents
Evaluation Criteria
Proposal
SolicitationSolicitation
42 © The Delos Partnership 200419/04/23
InputInput OutputOutputProcessProcess
Screening System
Weighting System
Contract Negotiation
ContractProposal
Evaluation Criteria
Organisational Policies
Source SelectionSource Selection
43 © The Delos Partnership 200419/04/23
InputInput OutputOutputProcessProcess
Change Control
Performance Measurement
Payment
Contract
Work Results
Invoices
Change Requests
Contract Changes
Payment Requests
Contract AdministrationContract Administration
44 © The Delos Partnership 200419/04/23
InputInput OutputOutputProcessProcess
Procurement AuditContract Documentation
Contract File
Formal Acceptance and Closure
Contract Close OutContract Close Out
© The Delos Partnership 200419/04/23
Risk Management PlanRisk Management Plan
• Risk Identification
• Risk Quantification
• Risk Response Development
• Risk Response Control
© The Delos Partnership 200419/04/23
EVERY project carries a number of risks...
• How likely is it to happen?
• How severe will the impact be if it does happen?
• How do we reduce the likelihood (mitigation)?
• How do we deal with the consequences if it occurs (contingency)?
What is a Risk?What is a Risk?
A condition or circumstance which may occur which could a negative affect on the success of your project at some point IN THE FUTURE
47 © The Delos Partnership 200419/04/23
InputInput OutputOutputProcessProcess
Check Lists
Interviewing
Feedback
Contract Documentation
Sources of Risk
Potential Risk Events
Risk Symptoms
Risk IdentificationRisk Identification
48 © The Delos Partnership 200419/04/23
InputInput OutputOutputProcessProcess
Judgement
Decision Trees
Statistical Sums
Stakeholder Tolerance
Potential Risk Events
Cost Estimates
Duration Estimates
Risks to Accept
Risks to Pursue
Risk QuantificationRisk Quantification
49 © The Delos Partnership 2004
Statistical SumsStatistical Sums
PERT
• Standard Deviation = (Worse Case - Best Case)/6
• Variance = [(Worse Case - Best Case)/6]2
The higher the variance the greater the risk...
50 © The Delos Partnership 200419/04/23
InputInput OutputOutputProcessProcess
Mitigating Approach
Contingency Planning
Insurance
Procurement
Risk Management Plan
Contingency Plans
Reserves
Risks to Accept
Risks to Pursue
Risk Response DevelopmentRisk Response Development
51 © The Delos Partnership 200419/04/23
InputInput OutputOutputProcessProcess
Work Arounds Corrective ActionRisk Management Plan
Actual Risks
Risk Response ControlRisk Response Control
© The Delos Partnership 200419/04/23
Some Common Risk Some Common Risk FactorsFactors
•Project size and/or complexity•External environment influences•Technology (experience, reliability, etc)•Availability of experienced resources•Project sponsorship•Clarity of project direction
53 © The Delos Partnership 2004
Risk Management Plan Risk Management Plan (continued)(continued)During the life of the project, the project manager should strive to
reduce the:– impact, and– probability
of all risks facing the project. Regular (at least monthly) review meetings should re-assess the probability and impact of all risks and the risk management plan should be updated accordingly.
Severe risks should have a robust contingency plan and a comprehensive mitigation strategy, although a ‘wait and see’ policy may be appropriate in some circumstances.
54 © The Delos Partnership 2004
Rate Risks based on probability x Impact
Risk Probability x Impact = Rating
a 1 1 = 1
b 3 3 = 9
c 2 3 = 6
Risk Management Plan Risk Management Plan (continued(continued))
55 © The Delos Partnership 2004
Risk Management PlanRisk Management Plan
Tips: • Avoid probability ratings of 2 (make a
decision is it high or low)• Convert low probability risks to assumptions
based on mitigating approach• Place mitigating approach to high probability
risks into action plans• Escalate risks to steering committee based
on severity and/or lack of contingency plan
56 © The Delos Partnership 2004
Case StudyCase Study
Breakout Session 5
57 © The Delos Partnership 2004
• Review / Establish Project Standards & Procedures;
• Develop Project Management Information System
• Develop Project Plans
Planning the ProjectPlanning the ProjectKey Project Manager ActivitiesKey Project Manager Activities
58 © The Delos Partnership 2004
The PMI® Project The PMI® Project Management Life CycleManagement Life Cycle
InitiatingProcesses
InitiatingProcesses
PlanningProcesses
PlanningProcesses
ControllingProcesses
ControllingProcesses
ClosingProcesses
ClosingProcesses
ExecutingProcesses
ExecutingProcesses