1 © the delos partnership 2004 project management planning the project

58
1 © The Delos Partnership 2004 Project Management Project Management Planning the Project

Upload: hector-wells

Post on 26-Dec-2015

216 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: 1 © The Delos Partnership 2004 Project Management Planning the Project

1 © The Delos Partnership 2004

Project ManagementProject Management

Planning the Project

Page 2: 1 © The Delos Partnership 2004 Project Management Planning the Project

2 © The Delos Partnership 2004

Up, Down and Acrossthe Company

PlanningPlanning

At the end of this session you will have an understanding of the following:-

• The Planning Process

• The Planning Hierarchy– WBS– Plans– Schedules

Page 3: 1 © The Delos Partnership 2004 Project Management Planning the Project

3 © The Delos Partnership 2004

Planning ProcessesPlanning Processes

6.3 6.3 Activity Activity Duration Duration

EstimatingEstimating

6.3 6.3 Activity Activity Duration Duration

EstimatingEstimating

5.2 5.2 Scope Scope

PlanningPlanning

5.2 5.2 Scope Scope

PlanningPlanning

5.3 5.3 Scope Scope

DefinitionDefinition

5.3 5.3 Scope Scope

DefinitionDefinition

6.1 6.1 Activity Activity

DefinitionDefinition

6.1 6.1 Activity Activity

DefinitionDefinition

7.17.1Resource Resource PlanningPlanning

7.17.1Resource Resource PlanningPlanning

6.26.2Activity Activity

SequencingSequencing

6.26.2Activity Activity

SequencingSequencing

7.27.2CostCost

EstimatingEstimating

7.27.2CostCost

EstimatingEstimating

6.46.4Schedule Schedule

DevelopmentDevelopment

6.46.4Schedule Schedule

DevelopmentDevelopment

7.37.3CostCost

BudgetingBudgeting

7.37.3CostCost

BudgetingBudgeting

4.14.1Project Plan Project Plan DevelopmentDevelopment

4.14.1Project Plan Project Plan DevelopmentDevelopment

N.B. All numbering refers to the PMI® Project Management Body of Knowledge (PMBOK) Knowledge Areas

Page 4: 1 © The Delos Partnership 2004 Project Management Planning the Project

4 © The Delos Partnership 200419/04/23

InputInput OutputOutputProcessProcess

Phases

Objectives

Deliverables

Acceptance Criteria

CharterProjectCharter Scope

Plan

Wave 1 Wave 2

Scope PlanningScope Planning

Page 5: 1 © The Delos Partnership 2004 Project Management Planning the Project

5 © The Delos Partnership 200419/04/23

InputInput OutputOutputProcessProcess

Decomposition

Objective

Work Breakdown Structure

Charter

ScopePlan

Charter

Scope Plan

WBS

Scope DefinitionScope Definition

Page 6: 1 © The Delos Partnership 2004 Project Management Planning the Project

6 © The Delos Partnership 2004

Why Define the Why Define the Work Breakdown Structure?Work Breakdown Structure?

•To manage a project successfully, you must first have a clear understanding of the amount of work you are required to complete

•Only then can the cost and schedule of your project be estimated and controlled with any confidence

•The WBS identifies all the work to be performed I.e. the Scope of the Project. If it is not in the WBS it is not part of the project

•It can often be as important to say what is not within scope

Page 7: 1 © The Delos Partnership 2004 Project Management Planning the Project

7 © The Delos Partnership 2004

GoalGoalGoalGoal

Objective 1Objective 1Objective 1Objective 1 Objective 2Objective 2Objective 2Objective 2 Objective 3Objective 3Objective 3Objective 3

Deliverable 1Deliverable 1Deliverable 1Deliverable 1 Deliverable 2Deliverable 2Deliverable 2Deliverable 2 Deliverable 3Deliverable 3Deliverable 3Deliverable 3

Defining the WBSDefining the WBS

TaskSub Tasks

Task Sub Task

TaskSub Tasks

Task Sub Task

TaskSub Tasks

Task Sub Task

Page 8: 1 © The Delos Partnership 2004 Project Management Planning the Project

8 © The Delos Partnership 200419/04/23

InputInput OutputOutputProcessProcess

Activity ListsCharter

Scope Plan

WBS

Charter

Scope Plan

WBS

Project Task List

Activity DefinitionActivity Definition

Page 9: 1 © The Delos Partnership 2004 Project Management Planning the Project

9 © The Delos Partnership 2004

Case StudyCase Study

Breakout Session 2

Page 10: 1 © The Delos Partnership 2004 Project Management Planning the Project

10 © The Delos Partnership 200419/04/23

InputInput OutputOutputProcessProcess

Dependencies

Project Visual (Network Diagram)

Charter

Scope Plan

WBS

Charter

Scope Plan

WBS

Project Task List Project Task List

NetworkDiagram

Activity SequencingActivity Sequencing

Page 11: 1 © The Delos Partnership 2004 Project Management Planning the Project

11 © The Delos Partnership 200419/04/23

Creating the Project VisualCreating the Project Visual(The Network Diagram)(The Network Diagram)3 Types of Dependencies

– Mandatory• No choice e.g. the walls must go up before the

roof can go on

– Discretionary• Preferred by stakeholders e.g. like the kitchen

done before the lounge

– External• Legally required e.g. planning permission before

you start

Page 12: 1 © The Delos Partnership 2004 Project Management Planning the Project

12 © The Delos Partnership 2004

Creating the Project VisualCreating the Project Visual(The Network Diagram)(The Network Diagram)• Facilitates engaging the project team

and other stakeholders

• Sanity Check

• Helps determine the critical path

Critical Path = A:D:E:F:H:I= 2+6+2+2+2 = 16 (weeks)

A

D

B C

E

G

F

H I

2

2 6

11 2

1 1

2

2

Page 13: 1 © The Delos Partnership 2004 Project Management Planning the Project

13 © The Delos Partnership 2004

Critical Path MethodCritical Path Method

The focus on CPM is to determine float in order to determine which tasks have the most and the least scheduling flexibility

A

D

B C

E

G

F

H I

Critical Path = A:D:E:F:H:I= 2+6+2+2+2 = 16 (weeks)

2

2 6

11 2

1 1

2

2

Page 14: 1 © The Delos Partnership 2004 Project Management Planning the Project

14 © The Delos Partnership 200419/04/23

Critical Path MethodCritical Path Method

• What is the critical path? (no scheduling flexibility)

• Where is the float/slack? (some scheduling flexibility)

Start Finish

A=1

F=1

B=4

P=3

M=3

I=3

D=2

O=2

G=1

N=1

Dummy

C= 2

Q=3

L=6H=2

Page 15: 1 © The Delos Partnership 2004 Project Management Planning the Project

15 © The Delos Partnership 200419/04/23

Creating the Project VisualCreating the Project Visual(The Network Diagram)(The Network Diagram)Network Diagram (AON, AOA)

– Shows interdependencies of all tasks– Used for planning the project– Used for crashing and fast tracking the

project

Page 16: 1 © The Delos Partnership 2004 Project Management Planning the Project

16 © The Delos Partnership 200419/04/23

Network Diagrams Aid Network Diagrams Aid Planning Planning Crashing

– Adding more resources to critical path tasks while maintaining scope

• E.g. move resources from non-critical tasks which have float or adding extra resources

Fast Tracking– Doing critical path tasks in parallel that were originally

planned in series

Resource Levelling– Plans out time of tasks (and costs) in favour of a stable

number of resources used consistently in full

Page 17: 1 © The Delos Partnership 2004 Project Management Planning the Project

17 © The Delos Partnership 2004

Case StudyCase Study

Breakout Session 3

Page 18: 1 © The Delos Partnership 2004 Project Management Planning the Project

18 © The Delos Partnership 200419/04/23

InputInput OutputOutputProcessProcess

Top Down (Analogous) Estimating

Expert Judgement

Monte Carlo Analysis

Heuristic (Rule of Thumb

Historical Information (Benchmarking)

PERT

a combination of the above….

Charter

Scope Plan

WBS

Project Task List

NetworkDiagram

Charter

Scope Plan

WBS

Project Task List

NetworkDiagram

Duration Estimates

&Assumptions

Activity Duration EstimatingActivity Duration Estimating

Page 19: 1 © The Delos Partnership 2004 Project Management Planning the Project

19 © The Delos Partnership 200419/04/23

EstimatingEstimating

Estimating– Should be done by people doing the work not just by project

managers

Estimating Methods– CPM

• Has one task per estimate• Emphasis on controlling costs and leaving time line flexible• Can only be drawn on AOA• Can have dummies

– PERT• Has 3 estimates per activity

– Optimistic, pessimistic, most likely– Can be used for time and cost– Emphasis on time with flexibility on cost

Page 20: 1 © The Delos Partnership 2004 Project Management Planning the Project

© The Delos Partnership 200419/04/23

PERTPERT(Program Evaluation and Review Technique)(Program Evaluation and Review Technique)

1. Estimate for 3 separate scenarios:• Best Case (B), • Most Likely (ML) and • Worst Case (W)

2. Calculate Weighted average estimate by:

(B + 4 ML + W ) / 6

Page 21: 1 © The Delos Partnership 2004 Project Management Planning the Project

© The Delos Partnership 200419/04/23

Pert Analysis - ExamplePert Analysis - Example

N.B. Standard Deviation = (Best Case + Worse Case) / 6Variance = [(Best Case + Worse Case) / 6] 2

1. Best Case estimate = 10 hours,

Most Likely estimate = 15 hours,

Worst Case estimate = 25 hours.

2. Average estimate = (10 + 4*15 + 25) / 6

= 16 hours.

Page 22: 1 © The Delos Partnership 2004 Project Management Planning the Project

22 © The Delos Partnership 200419/04/23

PERT PERT

PERT– Estimate = (P+4M+O)/6– Standard Deviation = (P-O)/6– Variance = [(P-O)/6]2

Task

A

B

C

D

O

3

2

5

7

M

6

3

12

8

P

8

4

20

8

DurationStandardDeviation

Variance

Page 23: 1 © The Delos Partnership 2004 Project Management Planning the Project

23 © The Delos Partnership 200419/04/23

InputInput OutputOutputProcessProcess

PERT (Project Evaluation and Review Technique)

CPM (Critical Path Method)

Resource Levelling

Charter

Scope Plan

WBS

Project Task List

NetworkDiagram

Duration Estimates

&Assumptions

Charter

Scope Plan

WBS

Project Task List

NetworkDiagram

Duration Estimates

&Assumptions

Project Schedule

Schedule DevelopmentSchedule Development

Page 24: 1 © The Delos Partnership 2004 Project Management Planning the Project

24 © The Delos Partnership 2004

Project ScheduleProject Schedule

Project PlansProject Plans

Activity ListActivity List

• A multi page document (not a Gantt chart)

• Down to the level that you are going to control at

• Rolling Weekly schedule of tasks (<4 weeks out)

The Planning HierarchyThe Planning HierarchyWBS

Page 25: 1 © The Delos Partnership 2004 Project Management Planning the Project

© The Delos Partnership 200419/04/23

Activity ListsActivity Lists

• Designed to reduce overhead associated with maintenance of more detailed project plan on a weekly basis

• Activity List is a detailed picture of the work assignments and schedule of activities over the coming weeks ( <4 weeks)

– It specifies tasks, resource assignments and the expected start and end dates

– It is updated on a weekly basis, based on actual performance during the preceding week

– Changes in the project work plan are reflected in the activity lists and vice-versa

99

1122

33

66

Page 26: 1 © The Delos Partnership 2004 Project Management Planning the Project

26 © The Delos Partnership 2004

What is required?...………………...

by when?…………………………….

What must be done?………………….

in what order?………………………….

and by whom?……………………….

How long will each activity (and therefore the whole project) take?...

So how do I make it fit ?…………...

Objectives and deliverables

High level estimates/external milestones

Activities

Dependencies

Resourcing

Detailed work estimates

Reconcile

Scheduling SummaryScheduling Summary

Page 27: 1 © The Delos Partnership 2004 Project Management Planning the Project

27 © The Delos Partnership 2004

ReconcilingReconciling

• More resources• De-scope• Further breakdown - focus on what’s actually

required• Critical path analysis• Re-time• Levelling - better utilisation of existing resources• Overtime!• Crash• Fast Track

Page 28: 1 © The Delos Partnership 2004 Project Management Planning the Project

28 © The Delos Partnership 200419/04/23

InputInput OutputOutputProcessProcess

What type of resources are required?

How many?

For how long?

What % of time

Charter

Scope Plan

WBS

Project Task List

NetworkDiagram

Duration Estimates

&Assumptions

Project Schedule

Charter

Scope Plan

WBS

Project Task List

NetworkDiagram

Duration Estimates

&Assumptions

Project Schedule

ResourceRequirements

Resource PlanningResource Planning

Page 29: 1 © The Delos Partnership 2004 Project Management Planning the Project

29 © The Delos Partnership 200419/04/23

InputInput OutputOutputProcessProcess

Top Down (Analogous) Estimating

Bottom Up Estimating

Parametric Estimating

Resource RatesChart of Accounts

Historical Information

Charter

Scope Plan

WBS

Project Task List

NetworkDiagram

Duration Estimates

&Assumptions

Project Schedule

ResourceRequirements

Charter

Scope Plan

WBS

Project Task List

NetworkDiagram

Duration Estimates

&Assumptions

Project Schedule

ResourceRequirements

Cost Estimates

Cost EstimatingCost Estimating

Page 30: 1 © The Delos Partnership 2004 Project Management Planning the Project

30 © The Delos Partnership 200419/04/23

InputInput OutputOutputProcessProcess

Grouping of estimatesCharter

Scope Plan

WBS

Project Task List

NetworkDiagram

Duration Estimates

&Assumptions

Project Schedule

ResourceRequirements

Cost Estimates

Charter

Scope Plan

WBS

Project Task List

NetworkDiagram

Duration Estimates

&Assumptions

Project Schedule

ResourceRequirements

Cost Estimates

Baseline Budget

Cost BudgetingCost Budgeting

Page 31: 1 © The Delos Partnership 2004 Project Management Planning the Project

31 © The Delos Partnership 200419/04/23

InputInput OutputOutputProcessProcess

Project Management Information System

C h a r t e rS c o p e P l a n

W B SP r o j e c t T a s kL i s tN e t w o r k

D i a g r a mD u r a t i o n E s t i m a t e s

&A s s u m p t i o n sP r o j e c t

S c h e d u l eR e s o u r c e

R e q u i r e m e n t s

C o s t E s t i m a t e s

B a s e l i n e B u d g e t

Project Plan DevelopmentProject Plan Development

Page 32: 1 © The Delos Partnership 2004 Project Management Planning the Project

32 © The Delos Partnership 200419/04/23

InputInput OutputOutputProcessProcess

Quality PlanOrganisational PlanCommunication Plan

External Resource PlanProcurement Plan

Risk Management Plan

InitialProjectCharter

InitialProjectCharter

Project Management Information System

Project Standards

Stakeholder know how

Project Plan DevelopmentProject Plan Development

Page 33: 1 © The Delos Partnership 2004 Project Management Planning the Project

33 © The Delos Partnership 2004

Quality PlanQuality Plan

• Standards– What requirements do you need to meet?

• Assurance– How will you assure the requirements will

be met?

• Control– How will you verify that the requirements

have been met?

Page 34: 1 © The Delos Partnership 2004 Project Management Planning the Project

34 © The Delos Partnership 2004

Organisation PlanOrganisation Plan

• Responsibility Breakdown Structure– Who does what?

• Staffing Management Plan– When and how human resources will be

taken on and off the project

• Organisational Chart

Page 35: 1 © The Delos Partnership 2004 Project Management Planning the Project

35 © The Delos Partnership 2004

Communication PlanCommunication Plan

Themes

Objectives, Scope

Agree “What” to Communicate

Channels, Media

Principles

Agree “How” to Communicate

People

Materials

Develop CapabilityTo Communicate

Escalate Major Issues

Adjust Approach

Review EffectivenessAddress Issues

Listen & Document

Immediate Response

Gather Feedback

Check Understanding

Open Environment

Deliver Communication

Page 36: 1 © The Delos Partnership 2004 Project Management Planning the Project

36 © The Delos Partnership 2004

Communication PlanCommunication Plan

Channel/Vehicle Description Frequency Potential Audience

Project Plan Microsoft Project Plan with deliverables

Ongoing Steering committee; key stakeholders

Status Reports Progress against deliverables and identification of issues and risks

Weekly Project Office

Update Presentations

Monthly summary of status reports

Monthly All Staff [via key Process owners]

Info Letter Update on Schedule, benefits of Project one

Every Quarter

All Staff

Page 37: 1 © The Delos Partnership 2004 Project Management Planning the Project

37 © The Delos Partnership 2004

Case StudyCase Study

Breakout Session 4

Page 38: 1 © The Delos Partnership 2004 Project Management Planning the Project

38 © The Delos Partnership 2004

Procurement Procurement Management PlanManagement Plan• Procurement Planning

• Solicitation Planning

• Solicitation

• Source Selection

• Contract Administration

• Contract Close Out

Page 39: 1 © The Delos Partnership 2004 Project Management Planning the Project

39 © The Delos Partnership 200419/04/23

InputInput OutputOutputProcessProcess

Make or Buy

Expert Judgement (internal capability / internal capacity / need

for control/ Protection of Intellectual Property / Cost)

Contract Type Selection (Fixed Cost / Cost Reimbursable / Unit Price

Contract)

Scope Statement

Market Conditions

Procurement Management Plan

e.g. What type of contracts will be used?

How will multiple suppliers be managed?

Statement of Work

Procurement PlanningProcurement Planning

Page 40: 1 © The Delos Partnership 2004 Project Management Planning the Project

40 © The Delos Partnership 200419/04/23

InputInput OutputOutputProcessProcess

Standard Forms

Expert Judgement

Procurement Management Plan e.g. What type of contracts will be used? How will multiple suppliers be

managed?

Statement of Work

Bid Documents

Evaluation Criteria

Solicitation PlanningSolicitation Planning

Page 41: 1 © The Delos Partnership 2004 Project Management Planning the Project

41 © The Delos Partnership 200419/04/23

InputInput OutputOutputProcessProcess

Advertising

Bidders Conference

Agencies

Internet

Bid Documents

Evaluation Criteria

Proposal

SolicitationSolicitation

Page 42: 1 © The Delos Partnership 2004 Project Management Planning the Project

42 © The Delos Partnership 200419/04/23

InputInput OutputOutputProcessProcess

Screening System

Weighting System

Contract Negotiation

ContractProposal

Evaluation Criteria

Organisational Policies

Source SelectionSource Selection

Page 43: 1 © The Delos Partnership 2004 Project Management Planning the Project

43 © The Delos Partnership 200419/04/23

InputInput OutputOutputProcessProcess

Change Control

Performance Measurement

Payment

Contract

Work Results

Invoices

Change Requests

Contract Changes

Payment Requests

Contract AdministrationContract Administration

Page 44: 1 © The Delos Partnership 2004 Project Management Planning the Project

44 © The Delos Partnership 200419/04/23

InputInput OutputOutputProcessProcess

Procurement AuditContract Documentation

Contract File

Formal Acceptance and Closure

Contract Close OutContract Close Out

Page 45: 1 © The Delos Partnership 2004 Project Management Planning the Project

© The Delos Partnership 200419/04/23

Risk Management PlanRisk Management Plan

• Risk Identification

• Risk Quantification

• Risk Response Development

• Risk Response Control

Page 46: 1 © The Delos Partnership 2004 Project Management Planning the Project

© The Delos Partnership 200419/04/23

EVERY project carries a number of risks...

• How likely is it to happen?

• How severe will the impact be if it does happen?

• How do we reduce the likelihood (mitigation)?

• How do we deal with the consequences if it occurs (contingency)?

What is a Risk?What is a Risk?

A condition or circumstance which may occur which could a negative affect on the success of your project at some point IN THE FUTURE

Page 47: 1 © The Delos Partnership 2004 Project Management Planning the Project

47 © The Delos Partnership 200419/04/23

InputInput OutputOutputProcessProcess

Check Lists

Interviewing

Feedback

Contract Documentation

Sources of Risk

Potential Risk Events

Risk Symptoms

Risk IdentificationRisk Identification

Page 48: 1 © The Delos Partnership 2004 Project Management Planning the Project

48 © The Delos Partnership 200419/04/23

InputInput OutputOutputProcessProcess

Judgement

Decision Trees

Statistical Sums

Stakeholder Tolerance

Potential Risk Events

Cost Estimates

Duration Estimates

Risks to Accept

Risks to Pursue

Risk QuantificationRisk Quantification

Page 49: 1 © The Delos Partnership 2004 Project Management Planning the Project

49 © The Delos Partnership 2004

Statistical SumsStatistical Sums

PERT

• Standard Deviation = (Worse Case - Best Case)/6

• Variance = [(Worse Case - Best Case)/6]2

The higher the variance the greater the risk...

Page 50: 1 © The Delos Partnership 2004 Project Management Planning the Project

50 © The Delos Partnership 200419/04/23

InputInput OutputOutputProcessProcess

Mitigating Approach

Contingency Planning

Insurance

Procurement

Risk Management Plan

Contingency Plans

Reserves

Risks to Accept

Risks to Pursue

Risk Response DevelopmentRisk Response Development

Page 51: 1 © The Delos Partnership 2004 Project Management Planning the Project

51 © The Delos Partnership 200419/04/23

InputInput OutputOutputProcessProcess

Work Arounds Corrective ActionRisk Management Plan

Actual Risks

Risk Response ControlRisk Response Control

Page 52: 1 © The Delos Partnership 2004 Project Management Planning the Project

© The Delos Partnership 200419/04/23

Some Common Risk Some Common Risk FactorsFactors

•Project size and/or complexity•External environment influences•Technology (experience, reliability, etc)•Availability of experienced resources•Project sponsorship•Clarity of project direction

Page 53: 1 © The Delos Partnership 2004 Project Management Planning the Project

53 © The Delos Partnership 2004

Risk Management Plan Risk Management Plan (continued)(continued)During the life of the project, the project manager should strive to

reduce the:– impact, and– probability

of all risks facing the project. Regular (at least monthly) review meetings should re-assess the probability and impact of all risks and the risk management plan should be updated accordingly.

Severe risks should have a robust contingency plan and a comprehensive mitigation strategy, although a ‘wait and see’ policy may be appropriate in some circumstances.

Page 54: 1 © The Delos Partnership 2004 Project Management Planning the Project

54 © The Delos Partnership 2004

Rate Risks based on probability x Impact

Risk Probability x Impact = Rating

a 1 1 = 1

b 3 3 = 9

c 2 3 = 6

Risk Management Plan Risk Management Plan (continued(continued))

Page 55: 1 © The Delos Partnership 2004 Project Management Planning the Project

55 © The Delos Partnership 2004

Risk Management PlanRisk Management Plan

Tips: • Avoid probability ratings of 2 (make a

decision is it high or low)• Convert low probability risks to assumptions

based on mitigating approach• Place mitigating approach to high probability

risks into action plans• Escalate risks to steering committee based

on severity and/or lack of contingency plan

Page 56: 1 © The Delos Partnership 2004 Project Management Planning the Project

56 © The Delos Partnership 2004

Case StudyCase Study

Breakout Session 5

Page 57: 1 © The Delos Partnership 2004 Project Management Planning the Project

57 © The Delos Partnership 2004

• Review / Establish Project Standards & Procedures;

• Develop Project Management Information System

• Develop Project Plans

Planning the ProjectPlanning the ProjectKey Project Manager ActivitiesKey Project Manager Activities

Page 58: 1 © The Delos Partnership 2004 Project Management Planning the Project

58 © The Delos Partnership 2004

The PMI® Project The PMI® Project Management Life CycleManagement Life Cycle

InitiatingProcesses

InitiatingProcesses

PlanningProcesses

PlanningProcesses

ControllingProcesses

ControllingProcesses

ClosingProcesses

ClosingProcesses

ExecutingProcesses

ExecutingProcesses