    Renton School District

    2009-10 General Fund Budget

    Development UpdatePresented by:

    Rich Moore: Assistant Superintendent: Operations

    and

    Tracy Patterson: Business Manager

    January 11, 2010

    1

  • 8/14/2019 10-11 budget development 1-11-2010 (2)

    2/17

    Agenda: Introduction

    Budget Priorities

    State Budget Impact

    Revenue Forecast

    Budget Expenditure Impacts

    2010-2011 Projected Summary

    Stakeholder Feedback

    Proposed Budget Development Process

    Closing Comments

    2

  • 8/14/2019 10-11 budget development 1-11-2010 (2)

    3/17

    2010-2011 Budget Priorities Dramatically accelerate P/K-12 achievement through

    research-proven initiatives

    Support high school on-time graduation and college readiness

    Ensure safe and secure learning environments

    Meet board goal of fund balance restoration

    3

  • 8/14/2019 10-11 budget development 1-11-2010 (2)

    4/17

    Scope of the Challenge Prolonged Recession

    Declining State Tax Revenue

    Growing 2010-2011 State Budget Deficit

    4

  • 8/14/2019 10-11 budget development 1-11-2010 (2)

    5/17

    Governors Budget Potential Impact K 4 Ratio 100% reduction

    Highly Capable program 100% reduction

    Learning Improvement Days 100% reduction

    Full Day Kindergarten 100% reduction

    I-728 100% reduction to allocation formula

    Middle School Vocational program 100% reduction

    I 732 Suspended

    5

  • 8/14/2019 10-11 budget development 1-11-2010 (2)

    6/17

    Potential Impact of 2010-2011 Governors BudgetK-4 Allocation

    Budgeted CurrentEnrollment State Staff Proposed State

    Grade Level FTE Allocation Staff Allocation

    Kindergarten 660.50 35.14 32.36

    Grade 1 3 3,301.80 175.66 161.79

    Grade 4 1,162.80 61.86 53.495,125.10 272.66 247.64

    Difference (25.02)Reductions from Governors budget

    K-4 Ratio Reduction to Basic Ed Allocation ($1,685,925)K-4 Associated NERC Reduction ($ 253,679)

    TOTAL POTENTIAL IMPACT OF K-4 RATIO REDUCTION ($1,939,604)

    6

  • 8/14/2019 10-11 budget development 1-11-2010 (2)

    7/17

    Potential Impact of 2010-2011 Governors BudgetOther Allocation Reductions

    Highly Capable ($124,278)

    Loss of One LID Day ($246,220) Initiative 728 ($1,318,715)

    Full Day Kindergarten ($580,509)

    Middle School Vocational ($52,231)

    Subtotal Lost Funding Other Allocations ($2,321,948)

    K-4 Ratio 100% Reduction ($1,939,604)

    TOTAL POTENTIAL IMPACT OF GOVERNORS BUDGET ($4,265,557)

    7

  • 8/14/2019 10-11 budget development 1-11-2010 (2)

    8/17

    Additional Estimated Expenditure Capacity NeedsEstimates Only

    1% COLA District wide $1,100,250

    Opening Honeydew $1,000,000 Utilities $400,000

    Increase to TRS, PERS, SERS Rates $300,000

    H/R Admin/Overload Costs $379,200

    Special Ed School Contracts Transp $125,000

    Increase Health Insurance $100,000

    8

  • 8/14/2019 10-11 budget development 1-11-2010 (2)

    9/17

    Additional Estimated Expenditure Capacity NeedsEstimates Only

    Increase General Liability Ins. $100,000

    Increase Retiree Subsidy $ 96,000

    Increase Legal/Audit Fees $ 50,000

    Total Estimated Capacity Needs $3,650,450

    9

  • 8/14/2019 10-11 budget development 1-11-2010 (2)

    10/17

    2010-2011 Estimated Revenue ForecastEstimates Only

    Enrollment Estimated 100 FTE Increase $ 500,000

    Local Levy Collection $ 599,168

    Other Small State Increases

    Basic Ed Programs $ 15,476

    Special Education $ 1,695

    Transportation Operations $ 1,739 Learning Assistance Programs $ 451

    Total Anticipated Revenue Increases $1,118,529

    10

  • 8/14/2019 10-11 budget development 1-11-2010 (2)

    11/17

    2010-2011 Revenue Projection SummaryEstimates Only

    2009 Budgeted Revenues $137,094,040 Add: New Revenues $ 1,118,529

    Less: State Revenue Reductions ($ 4,265,557)

    Total Projected Revenues $133,947,012

    11

  • 8/14/2019 10-11 budget development 1-11-2010 (2)

    12/17

    2010-2011 Expenditure Projection SummaryEstimates Only

    2009 Budgeted Expenditures $135,604,526 Additional Capacity Needs $ 3,650,450

    Total Projected Expenditures $139,254,976

    12

  • 8/14/2019 10-11 budget development 1-11-2010 (2)

    13/17

    2010-2011 Budget SummaryEstimates Only

    Anticipated Revenues $133,947,012

    Anticipated Expenditures ($139,254,976)

    Subtotal ($ 5,307,964)

    Fund Balance Restoration $ 800,000

    Needed to Balance ($ 6,107,964)

    13

  • 8/14/2019 10-11 budget development 1-11-2010 (2)

    14/17

    2009 Survey Results 5 Most Important1. Protect the benefits of smaller class size

    2. Maintain safety and security students and staff

    3. Maintain efforts to attract and retain high quality staff4. Seek opportunities for increased revenues

    5. Ensure that long range impacts of decisions considered

    14

  • 8/14/2019 10-11 budget development 1-11-2010 (2)

    15/17

    2009 Survey Results 5 Least Important1. Communication tools such as newsletters and printed

    calendars

    2. Transportation for optional programs3. Transportation for extra-curricular activities

    4. Community services such as theaters, swimming pools, and

    stadiums

    5. Transportation for high school students

    15

    16

  • 8/14/2019 10-11 budget development 1-11-2010 (2)

    16/17

    2010-2011 Budget Development Timelines 1-11-2010 Legislature Convenes

    1-11-2010 Budget Worksheets Distributed

    1-27-2010 Budget Worksheets Return Deadline

    1-29-2010 Develop Reduction Plan

    2-10-2010 School Board Budget Study Session

    2-13-2010 Enrollment Projections Complete

    2-22-2010 Community Budget Meetings- (3) 1 per Svc Area

    3-01-2010 Budget Update Leadership Team

    3-15-2010 Staffing Allocation Plan

    3-15-2010 Finalize Boundary Review Plan

    3-31-2010 Finalize Reduction Plan

    16

    17

  • 8/14/2019 10-11 budget development 1-11-2010 (2)

    17/17

    2010-2011 Budget Development Timelines 3-31-2010 Staffing Plan Complete

    4-23-2010 Legislature Adjourns

    5-26-2010 School Board Budget Study Session

    6-30-2010 Preliminary Budget Plan Presented

    to the School Board

    7-10-2010 Draft Budget Due to OSPI

    8-25-2010 Formal Adoption of Budget

    COMMENTS??? QUESTIONS????

    17