1.1 site daily diary
TRANSCRIPT
-
7/25/2019 1.1 Site Daily Diary
1/1
Project Title: KBK Project ( Kyee Myin Daing) Weather: Fine
Basement1+12 Storey Office Building Rain
CQHP Rn No.: 12 12
Reference No.: DPR 305 (03 YG 00400) 9 3 9 3
Date: 18.06.2016 6 6
am pm
1. Casting concrete Betw; GL 1&2 and - Casting concrete from basement floor to mid of upper flight. 90.0%
for Staircase- B Betw; GL D&E
2. Dewatering Site Area - Dewatering from site area to public drain.
Delivered to Site- Ready Mixed Concrete (G-35) = 2.5 M3
Stop Work Order from YCDC
U Kyaw Shwe (Project Director, MDC) , U Swe Linn Aung ( Project Manager, MDC )
B. Materials & Equipment
Work
ForceDescription / ParticularsLocations
SITE DIARY
Progress
(%)A. Activities
Progress
(%)A. Activities
E. Name & Signature of Site Supervisor
Non-compliance /
C. Defective Works /
Delivered to /
Removed from Site
D. Visitors at Site
Instructions / Other Comments