12.9.03trd status meeting alice week hdclemens adler trd chamber status news: new leak rate...

10
12.9.03 TRD Status meeting Alice week Hd Clemens Adler TRD Chamber Status News: New leak rate measurements Production is imminent Some material arrived Soldering machine arrived at Frankfurt X-Ray test stand is taking shape Bukarest joins Production Goal: get ready by end of this year

Post on 22-Dec-2015

214 views

Category:

Documents


0 download

TRANSCRIPT

12.9.03 TRD Status meeting Alice week Hd Clemens Adler

TRD Chamber Status

News:• New leak rate measurements

• Production is imminent

• Some material arrived

• Soldering machine arrived at Frankfurt

• X-Ray test stand is taking shape

• Bukarest joins ProductionGoal: get ready by end of this year

12.9.03 TRD Status meeting Alice week Hd Clemens Adler

Leak rate

New Gas system from Rainer:– ~0 intrinsic leak rate

Leak Rate < 0.1 mbar* l/h (~precision limit)

with greased gas connectors

See how it develops with realistic configuration: 5 chambers in a row, some angular deviation...

12.9.03 TRD Status meeting Alice week Hd Clemens Adler

Soldering• Soldering machine

arrived at IKF (mid August)

• Where to put the solder still unresolved

• Start tests

as soon as

possible

(Monday)

12.9.03 TRD Status meeting Alice week Hd Clemens Adler

X-ray Test Stand

• Requirements defined

• Mechanical impementation decided:

• needs engineering work: September

• Material ordering (Hd): September

• Delivery:

Oktober

• Assembly/ TÜV:

Okt./Nov.

12.9.03 TRD Status meeting Alice week Hd Clemens Adler

X-ray test stand cont.

• Increase of HV ensures longer tube life

• Possible with planned Power supply

12.9.03 TRD Status meeting Alice week Hd Clemens Adler

Winding machine

• New winding frame is sturdy enough, even in weight reduced version

• Meteor displays a loss of tension over first windings.

• Winding machine modification: scheduled beginning of Sept. need to check

12.9.03 TRD Status meeting Alice week Hd Clemens Adler

Crane

• New crane for the clean room is ordered: arrives 2nd Oct. Week

• Needed for moving of winding frames to tables

12.9.03 TRD Status meeting Alice week Hd Clemens Adler

Material Status

Arrived:• Wacosit profile (frame) arrived:Side profiles warped, but OK after

glueing to Al profiles• Voltage divider PCBs arrived• Signal cables arrivedIn Approach:In Approach:• Padplanes (slight delay, due to

manufacturing confusion): finished end of next week

• Fischer panel:~4 weeks from now

To order:

• Vacuum tables

• Glueing tables

• Connectors (ROB):Minimum 15k pc. = 3930 €

60% TRD: 39k pc. = 10218 €

Need add. Offers? Delay...

12.9.03 TRD Status meeting Alice week Hd Clemens Adler

Padplane

• Production steps were discussed with Optiprint to optimize mechanical precision where we need it.

• Result: Question from Optiprint 2 weeks ago: „do we need this precision?? Will bring up the price considerably.“

= some unfortunate mixup...

2 week delay

12.9.03 TRD Status meeting Alice week Hd Clemens Adler

Near Term Schedule