12.9.03 TRD Status meeting Alice week Hd Clemens Adler
TRD Chamber Status
News:• New leak rate measurements
• Production is imminent
• Some material arrived
• Soldering machine arrived at Frankfurt
• X-Ray test stand is taking shape
• Bukarest joins ProductionGoal: get ready by end of this year
12.9.03 TRD Status meeting Alice week Hd Clemens Adler
Leak rate
New Gas system from Rainer:– ~0 intrinsic leak rate
Leak Rate < 0.1 mbar* l/h (~precision limit)
with greased gas connectors
See how it develops with realistic configuration: 5 chambers in a row, some angular deviation...
12.9.03 TRD Status meeting Alice week Hd Clemens Adler
Soldering• Soldering machine
arrived at IKF (mid August)
• Where to put the solder still unresolved
• Start tests
as soon as
possible
(Monday)
12.9.03 TRD Status meeting Alice week Hd Clemens Adler
X-ray Test Stand
• Requirements defined
• Mechanical impementation decided:
• needs engineering work: September
• Material ordering (Hd): September
• Delivery:
Oktober
• Assembly/ TÜV:
Okt./Nov.
12.9.03 TRD Status meeting Alice week Hd Clemens Adler
X-ray test stand cont.
• Increase of HV ensures longer tube life
• Possible with planned Power supply
12.9.03 TRD Status meeting Alice week Hd Clemens Adler
Winding machine
• New winding frame is sturdy enough, even in weight reduced version
• Meteor displays a loss of tension over first windings.
• Winding machine modification: scheduled beginning of Sept. need to check
12.9.03 TRD Status meeting Alice week Hd Clemens Adler
Crane
• New crane for the clean room is ordered: arrives 2nd Oct. Week
• Needed for moving of winding frames to tables
12.9.03 TRD Status meeting Alice week Hd Clemens Adler
Material Status
Arrived:• Wacosit profile (frame) arrived:Side profiles warped, but OK after
glueing to Al profiles• Voltage divider PCBs arrived• Signal cables arrivedIn Approach:In Approach:• Padplanes (slight delay, due to
manufacturing confusion): finished end of next week
• Fischer panel:~4 weeks from now
To order:
• Vacuum tables
• Glueing tables
• Connectors (ROB):Minimum 15k pc. = 3930 €
60% TRD: 39k pc. = 10218 €
Need add. Offers? Delay...
12.9.03 TRD Status meeting Alice week Hd Clemens Adler
Padplane
• Production steps were discussed with Optiprint to optimize mechanical precision where we need it.
• Result: Question from Optiprint 2 weeks ago: „do we need this precision?? Will bring up the price considerably.“
= some unfortunate mixup...
2 week delay