14. building works_ dismantaling & demolishing

Upload: arup-debnath

Post on 03-Jun-2018

225 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/12/2019 14. Building Works_ Dismantaling & Demolishing

    1/4

    SH:14/DISMANTLING_DEMOLISH

    Note:

    1

    2

    3

    Code No. Description Unit Rate

    14.1 Demolishing lime concrete manually / by mechanical

    means including disposal of material with all lifts and

    upto 50 m lead etc. complete as per direction of theEngineer- in-charge.

    Cum. R 136.70

    14.2 Demolishing cement concrete manually / by

    mechanical means including disposal of material with

    all lifts and upto 50 m lead etc. complete as per

    direction of the Engineer- in-charge:-

    14.2.1 1 : 3 : 6 or leaner mix. Cum R 305.50

    14.2.2 1 : 2 : 4 or richer mix. Cum R 460.40

    14.3 Demolishing reinforced cement concrete manually /by mechanical means including stacking of steel bars

    properly and disposal of unserviceable material with

    all lifts and upto 50 m lead etc. complete as per

    direction of the Engineer- in-charge.

    Cum R 583.20

    14.4 Demolishing reinforced brick work manually / by

    mechanical means including stacking of steel bars,

    bricks/ brick slump properly and disposal of

    unserviceable material with all lifts and upto 50 m lead

    etc. complete as per direction of the Engineer- in-

    charge.

    Cum R 435.00

    14.5 Extra for cutting reinforcement in RCC or R.B. work

    manually / by mechanical means (payment to made on

    the cross sectional area of RCC or R.B. work) etc.

    complete as per direction of the Engineer- in-charge.

    Sqm. R 257.80

    Dismantling of utilities like water supply lines, electric and telephone lines is

    required to be done under the supervision of concerned departments with prior

    information to the users.

    The dismantled materials should be examined and a realistic assessment and

    provision should be made after due process for the salvage value for such

    materials, can be utilised for works or auctioned.

    SUB HEAD : 14.0DISMANTLING AND DEMOLISHING WORK

    For dismantling of structures, which remain submerged in water, the cost may be

    enhanced by 50%. If site condition warrant lowering of water level to facilitate

    dismantling, the cost may be enhanced by additional 25%.

    \\vboxsrv\conversion_tmp\scratch_6\218141169.xls.ms_office/Schedule SH:14-Page:2

  • 8/12/2019 14. Building Works_ Dismantaling & Demolishing

    2/4

    SH:14/DISMANTLING_DEMOLISH

    Code No. Description Unit Rate

    14.6 Extra for scrapping, cleaning and straightening

    reinforcement obtained from RCC or R.B. work etc.

    complete as per direction of the Engineer- in-charge. Kg. R 1.30

    14.7 Demolishing brick work including stacking of

    serviceable materials and disposal of unserviceablematerials with all lifts and upto a lead of 50m etc.

    complete as per direction of the Engineer- in-charge:-

    14.7.1 In mud mortar. Cum R 117.00

    14.7.2 In lime mortar. Cum R 139.40

    14.7.3 In cement mortar. Cum R 335.60

    14.8 Removing mortar from brick and cleaning bricks

    including stacking bricks and disposal rubbish with all

    lifts and upto a lead of 50 m etc. complete as perdirection of the Engineer- in-charge:-

    14.8.1 In mud mortar. Each R 0.80

    14.8.2 In lime mortar. Each R 0.90

    14.8.3 In cement mortar. Each R 1.10

    14.9 Dismantling doors, windows and clerestory windows (

    steel or wood ) shutter including chowkhats,

    architrave, hold fasts etc. complete including stacking

    of serviceable materials and unserviceable materialsseparately with all lifts and upto a lead of 50m etc.

    complete as per direction of the Engineer- in-charge:-

    14.9.1 Of area 3 sqm and below. Each R 83.60

    14.9.2 Of area beyond 3 sqm. Each R 113.20

    14.10 Dismantling doors, windows and clerestory windows (

    steel or wood ) shutter including stacking of

    serviceable materials and unserviceable materials

    separately with all lifts and upto a lead of 50m etc.

    complete as per direction of the Engineer- in-charge:-

    14.10.1 Of area 3 sqm and below. Each R 36.00

    14.10.2 Of area beyond 3 sqm. Each R 46.00

    \\vboxsrv\conversion_tmp\scratch_6\218141169.xls.ms_office/Schedule SH:14-Page:3

  • 8/12/2019 14. Building Works_ Dismantaling & Demolishing

    3/4

    SH:14/DISMANTLING_DEMOLISH

    Code No. Description Unit Rate

    14.11 Dismantling wood work in frames, trusses, purlins,

    rafters, etc. upto 10m span and 5m height including

    stacking of serviceable materials and unserviceable

    materials separately with all lifts and upto a lead of 50

    m etc. complete as per direction of the Engineer- in-

    charge:-

    14.11.1 Of sectional area 40 sq cm and below. Mtr. R 5.00

    14.11.2 Of sectional area beyond 40 sq cm. Cum. R 712.90

    14.12 Extra for dismantling trusses, rafters, purlins etc. of

    wood work for every additional span of 1 m or part

    thereof beyond 10 m etc. complete as per direction of

    the Engineer- in-charge:-

    14.12.1 Of sectional area 40 sq cm and below. Metre/ metrespan

    R 0.40

    14.12.2 Of sectional area beyond 40 sq cm. Cum/ metrespan

    R 96.10

    14.13 Extra for dismantling trusses, rafters, purlins etc. of

    wood work for every additional height of 1 m or part

    thereof beyond 5 m etc. complete as per direction of

    the Engineer- in-charge:-

    14.13.1 Of sectional area 40 sq cm and below. Metre/ metreheight

    R 0.70

    14.13.2 Of sectional area beyond 40 sq cm. Cum/ metreheight

    R 178.80

    14.14 Dismantling steel work in single section including

    dismembering and stacking of serviceable materials

    and unserviceable materials separately with all lifts

    and upto a lead of 50 m etc.complete as per direction

    of the Engineer- in-charge:-

    14.14.1 R.S Joists. Kg. R 0.80

    14.14.2 Channels, angles, tees and flats. Kg. R 0.60

    14.15 Dismantling steel work in built up section in channels,

    angles, tees, flats including all gusset plates, bolts, nuts,

    cutting rivets, welding including dismembering and

    stacking of serviceable materials and unserviceable

    materials separately with all lifts and upto a lead of 50

    m etc. complete as per direction of the Engineer- in-

    charge.

    Kg. R 1.50

    \\vboxsrv\conversion_tmp\scratch_6\218141169.xls.ms_office/Schedule SH:14-Page:4

  • 8/12/2019 14. Building Works_ Dismantaling & Demolishing

    4/4

    SH:14/DISMANTLING_DEMOLISH

    Code No. Description Unit Rate

    14.16 Dismantling steel work in built up section manually /

    mechanically without dismembering and stacking of

    serviceable materials and unserviceable materials

    separately with all lifts and upto a lead of 50 m etc.

    complete as per direction of the Engineer- in-charge.

    Kg. R 1.20

    14.17 Dismantling steel work in frames, trusses, purlins, and

    rafters etc. upto 10 m span and 5 m height including

    dismembering and stacking of serviceable materials

    and unserviceable materials separately with all lifts

    and upto a lead of 50 m etc. complete as per direction

    of the Engineer- in-charge.

    Kg. R 1.60

    14.18 Extra for dismantling trusses, rafters, purlins etc. of

    steel work for every additional span of 1 m or part

    thereof beyond 10 m etc. complete as per direction of

    the Engineer- in-charge.

    Kg/ metre

    span.R 0.20

    14.19 Extra for dismantling trusses, rafters, purlins etc. of

    steel work for every additional height of 1 m or part

    thereof beyond 5 m etc. complete as per direction of

    the Engineer- in-charge.

    Kg/ metre

    height.R 0.40

    14.2 Dismantling dry brick pitching in floors, drains etc.

    including stacking of serviceable materials and

    unserviceable materials separately with all lifts and

    upto a lead of 50 m etc.complete as per direction of the

    Engineer- in-charge.

    Cum. R 211.80

    14.21 Dismantling GS sheet roofing including ridges, hips,

    valleys, gutters wind ties etc. including dismembering

    and stacking of serviceable materials and

    unserviceable materials separately with all lifts and

    upto a lead of 50 m etc.complete as per direction of the

    Engineer- in-charge.

    Sqm. R 26.30

    14.22 Dismantling old plaster or pointing, raking out joints,

    cleaning and preparing the surface for re-plastering or

    re-pointing including disposal of rubbish to the

    dumping ground with all leads and lifts etc.complete asper direction of the Engineer- in-charge.

    Sqm. R 14.20

    14.23 Dismantling old glass panes from wooden / steel

    structures including stacking of serviceable materials

    and disposal of rubbish and unserviceable materials to

    the dumping ground with all leads and lifts

    etc.complete as per direction of the Engineer- in-

    char e.

    Sqm. R 7.50

    \\vboxsrv\conversion_tmp\scratch_6\218141169.xls.ms_office/Schedule SH:14-Page:5