14 th liu-sps coordination meeting

14
14 th LIU-SPS Coordination Meeting Update on the renovation of the 200 MHz RF system

Upload: maegan

Post on 24-Feb-2016

64 views

Category:

Documents


0 download

DESCRIPTION

14 th LIU-SPS Coordination Meeting. Update on the renovation of the 200 MHz RF system . Cavities redistribution. 2011 : 4 cavities 2 x 4 sections 2 x 5 sections + 3 spare sections. 2018 : 6 cavities 2 x 4 sections 4 x 3 sections + 1 spare section. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: 14 th  LIU-SPS Coordination Meeting

14th LIU-SPSCoordination Meeting

Update on the renovation of the 200 MHz RF system

Page 2: 14 th  LIU-SPS Coordination Meeting

14th LIU-SPS Coordination Meeting 2

Cavities redistribution

26 October 2011

2011 : 4 cavities

2 x 4 sections

2 x 5 sections

+ 3 spare sections

2018 : 6 cavities

2 x 4 sections

4 x 3 sections

+ 1 spare section

Courtesy of Elena

Shaposhnikova

Page 3: 14 th  LIU-SPS Coordination Meeting

14th LIU-SPS Coordination Meeting 3

First upgrade: Present amplifiers

26 October 2011

Ratings Present FutureCW5 seconds 650 kW 700kW

Pulsed43 kHz 900 kW 1100 kW

Tubes per year 6 + 16 7 + 18

BW-3dBCompromise to be

discussed with LLRFSiemens HVPS need a full re-cabling

and an air cooling improvementPhilips air cooling plant has to be

modifiedto allow higher power

Tetrodes:Present lifetime statistics, operating ~650 kW cw:

RS2004 : 20’000 hrs: 6 tubes per year

YL1530 : 25’000 hrs: 16 tubes per

year

HVPS need a full re-cabling and air cooling improvement to allow higher pulsed mode

It is planned to do ‘pre-modifications’ during next Xmas stop and to test

new configuration during a devoted MD in 2012

Page 4: 14 th  LIU-SPS Coordination Meeting

14th LIU-SPS Coordination Meeting 4

New RF power plant

26 October 2011

New RF Amplifier

New RF Building

LSS3 Tunnel integration

RF amplifier

1 mW

Coaxial transmission line150 meters

Accelerating cavity

1.7 MW

RF amplifier

1 mW

Accelerating cavity

1.7 MW

New RF Building

Page 5: 14 th  LIU-SPS Coordination Meeting

14th LIU-SPS Coordination Meeting 5

1.7 MW amplifier, i.e 1.4 MW cavity

26 October 2011

To have 1.4 MW available at the cavity input, 1.7 MW at the Final output are needed

A major improvement to present systems would be to have individual SSA drivers per PA

Taking advantage of the long experience we have with tetrodes and combiners, the solution will be 16 x PAs combined through 3 dB combiners

Four contracts : Drivers (SSA) Finals (SSA or Tetrodes) Combiners (3 dB above 100 kW) Transmission lines (coaxial, 345 mm

outer)

Drivers16 SSAFinal16 PAs

3 dBcombinersand power loads

120 m and 180 mCoaxial lines

To cavity input 120 m away

From Beam Control

1/16 splitter

1.7 MW-0.6 dB

total

1.5 MW

-0.2 dB

1.4 MW

Page 6: 14 th  LIU-SPS Coordination Meeting

14th LIU-SPS Coordination Meeting 6

2018 : two new power amplifiers

26 October 2011

Pulse mode: 1.7 MW max (10 µs / 43 kHz)

Average: 850 kW (thermal limitation)

Must be reliable: 24/24 hours 300/365 days

(2 months winter Technical stopAND a 1 day stop every 8 weeks)

Minimum 20 years of operation,(3 years of operation + 1 year off cycle)

Qualified solution must have demonstrated to be reliable under scientific operation (not only broadcast operation)

2 x 1.7 MW Klystron

2 x 4 x 450 kW Diacrodes

2 x 8 x 225 kW IOTs

2 x 8 x 225 kW tetrodes Equivalent to ‘Siemens’

2 x 16 x 106 kW tetrodes Equivalent to ‘Philips’

2 x 2048 x 830 W SSA Equivalent to ‘SOLEIL’

Page 7: 14 th  LIU-SPS Coordination Meeting

14th LIU-SPS Coordination Meeting 7

16 Tetrodes vs 2048 SSA

26 October 2011

Tetrodes tube costs over 20 years will be added : 20 years * 3/4 * 335 * 24 * 16 * 2 =

3’859’200 total hours With 20’000 hours per tube = ~ 200 tubes

SSA : + 20% to 25% additional transistors (not

module) Individual circulators are mandatory

Wall plug efficiency will be part of the adjudication HVPS included (Tetrodes) Losses in all SSA combiners, circulators and

loads included

1.7 MW

16 x128 x 830

WSSA

Final Tetrodes(gain = 12 dB)

SSA(Gain = 20 dB)

Nominal ratings

16 x 106 kW = 1700 kW

2048 x 830 W = 1700 kW

Maximum ratingsFor 1400 kW at cavity input

Maximum2 faulty tubes14 x 138 kW = 1932 kW

Maximum48 faulty modules2000 x 891 W = 1782 kW

Maximum ratingsDriver

16 x 8.7 kW 16 x 1.1 kW

16 x106 kW Tetrodes

Page 8: 14 th  LIU-SPS Coordination Meeting

14th LIU-SPS Coordination Meeting 8

SSA vs Tetrodes

26 October 2011

First contract : SSA Drivers Two options : 16 x 1.1 kW 16 x 1.1 kW x 8

Second contract : Finals Two options : 16 x 1.1 kW + SSA 16 x 1.1 kW x 8 + Tubes

KT too difficult and too long to be involved No SSA prototyping

DRs done (Drivers and Finals)

Two MS expected by end of 2011

Drivers IT March 2012

Finals IT September 2012 Taking into account Drivers

Page 9: 14 th  LIU-SPS Coordination Meeting

14th LIU-SPS Coordination Meeting 9

New RF building

26 October 2011

Only possible location is between two existing buildings (BA3 and BB3)

Maximum ‘RF’ foot print will be 2x450m2

Whatever the solution, SSA or Tetrodes, the same building

Some difficulties with BB3 transformers (Oil vs Cast resin; 12 Tons vs 24 Tons)

New place is being agreed Distance between BA3 air

ventilation and new building at its minimum

Page 10: 14 th  LIU-SPS Coordination Meeting
Page 11: 14 th  LIU-SPS Coordination Meeting
Page 12: 14 th  LIU-SPS Coordination Meeting

14th LIU-SPS Coordination Meeting 12

Transport area

26 October 2011

LSS3 -

LSS3 +

2011 2013

2360

Page 13: 14 th  LIU-SPS Coordination Meeting

14th LIU-SPS Coordination Meeting 13

LSS3 Tunnel integration : LS1 ?

26 October 2011

Three new cavity sections : ~ 3 years Measure Build new devices Proceed to power tests

New power couplers : ~ 4-5 years More power and shorter -> new design Prototyping and tests (resonant ring) Series and pre-conditioning of 24

couplers + spares

New amplifiers : ~ 5 years New building Long duration tests

Impossible to re-arrange cavities within LS1

Clean old cables in 314 and 321

Move pickups in 314 and integrate new kicker in 321

Install coaxial transmission lines

Page 14: 14 th  LIU-SPS Coordination Meeting

14th LIU-SPS Coordination Meeting 14

Draft schedule

26 October 2011

InstallBuild new hardware

Year 4Year 3Year 2Year 1 Year 5

BuildingServices

RF :

Building:

20172014201320122011 2015 2016 2018Year 6 Year 7

Tendering

Commissioning

Authorizations

Tunnel :

Build New hardwareInstallation phase 1

(pickups + dampers + EL + coax lines …)

Installation phase 2(cavities + pickups + CV + EL +

vacuum)

Cavities re-arrangement within a LS ( > 6

months)

Studies (amplifiers, couplers, cavities)

MS

Studies

Studies

Services