  • 8/19/2019 1401 SAP Customer Connection for SAP EAM Plant Maintenance 2014

    1/25

    Orange County Convention Center

    Orlando, Florida | June 3-5, 2014

    SAP Customer Connection for SAP EAMPlant Maintenance (2014)Bob Pennington / Hemant Rathod

  • 8/19/2019 1401 SAP Customer Connection for SAP EAM Plant Maintenance 2014

    2/25

    The information in this presentation is confidential and proprietary to SAP and may not be disclosed without

    the permission of SAP. This presentation is not subject to your license agreement or any other service or

    subscription agreement with SAP. SAP has no obligation to pursue any course of business outlined in this

    document or any related presentation, or to develop or release any functionality mentioned therein. This

    document, or any related presentation and SAP's strategy and possible future developments, products and

    or platforms directions and functionality are all subject to change and may be changed by SAP at any time

    for any reason without notice. The information in this document is not a commitment, promise or legal

    obligation to deliver any material, code or functionality. This document is provided without a warranty of any

    kind, either express or implied, including but not limited to, the implied warranties of merchantability, fitness

    for a particular purpose, or non-infringement. This document is for informational purposes and may not be

    incorporated into a contract. SAP assumes no responsibility for errors or omissions in this document, except

    if such damages were caused by SAP´s willful misconduct or gross negligence.

     All forward-looking statements are subject to various risks and uncertainties that could cause actual results

    to differ materially from expectations. Readers are cautioned not to place undue reliance on these forward-looking statements, which speak only as of their dates, and they should not be relied upon in making

    purchasing decisions.

    Legal disclaimer

  • 8/19/2019 1401 SAP Customer Connection for SAP EAM Plant Maintenance 2014

    3/25

    Agenda

    Introduction Customer Connection Program

    What has been accomplished so far

    Current status of EAM Plant Maintenance 2014 project

    Recommended process from ASUG

    Q & A?

  • 8/19/2019 1401 SAP Customer Connection for SAP EAM Plant Maintenance 2014

    4/25

    SAP Influencing Programs for customers

    SAP offers three channels for customer influence,

    each with a different focus:

    VisionInnovationImprovement

    Today’s Solution 

    Customer Connection

    Improvements

    Planned Solution

    Customer Engagement

    Initiative

    Next Products and

    Solutions

    Future Directions

    Executive Advisory

    Councils

    Strategic Concepts

  • 8/19/2019 1401 SAP Customer Connection for SAP EAM Plant Maintenance 2014

    5/25

    Customer Connection is the influencing channel for customers

    to improve today’s products and solutions 

    Improvement

    Today’s Solution 

    Customer

    Connection

    Improvements

    Channel for small enhancements & improvements of

    SAP products and solutions

    Improvement delivery takes place via SAP Notes and SP’s 

    Open channel to SAP User Groups/Customer Communities

    The program is driven by SAP customers, structured in

    Focus Topic projects

    Proven collaboration model established:SAP and customers co-operate in Focus Topic projects

  • 8/19/2019 1401 SAP Customer Connection for SAP EAM Plant Maintenance 2014

    6/25

    How Customer Connection Focus Topics are defined

    Customer Connection program follows a project approach

    SAP customers (user groups/communities) request Focus Topic (= scope of specific project)

    SAP defines Focus Topic projects with fast cycle times and dedicated scope 

    Each project within the Customer Connection program has a specific timeline

    Focus Topic RoadmapCustomer Connection Engagement

    Evaluate requested Focus Topic

    Check criteria for a Focus Topic project

    Transparency on decision based on:

    • Market demand/customer base

    • Active User Groups• Available and allocated capacity

    Approved projects

    Defined project timeline

    Focus Topic definition process

    Focus Topic requested by

    customers

  • 8/19/2019 1401 SAP Customer Connection for SAP EAM Plant Maintenance 2014

    7/25

    Contribute and Benefit from Customer Connection

    Tool Framework

    Benefit and Use

    Identify potentials and find relevant

    improvements for your SAP products

    Use established maintenance processes

    (Note/SP implementation)

    Contribute and Influence Submit Improvement Requests

    Discuss, subscribe and exchange with others

    influence.sap.com sapimprovementfinder.com

    New projects with start in June 2014

    • EAM Plant Maintenance (2014)

    • Document Management (2014)

    • Quality Management (2014)

    Contact project manager for

    details: [email protected]

    • Plant Maintenance / Enterprise

     Asset Management

    • Project and Portfolio

    Management

    • Project System (in development)

    • Document Management(in selection)

  • 8/19/2019 1401 SAP Customer Connection for SAP EAM Plant Maintenance 2014

    8/25

    YOUR take away… 

    USE delivered improvements GET INVOLVED in ongoing

    Focus Topic projectsREQUEST new Focus Topic

    project

    Search for useful improvements onSAP Improvement Finder  

    Download and adopt relevant

    Improvement Note/SP

    Follow your area of interest onCustomer Influence and get

    informed about new and upcoming

    Focus Topic projects

    Submit your improvement request

    for projects in COLLECT phase

    Drive Customer Connectionopportunity within your community

    Get aligned on your needs within

    your community

    Request your Focus Topic and

    trigger the process

    http://www.sapimprovementfinder.com/http://influence.sap.com/http://influence.sap.com/http://www.sapimprovementfinder.com/

  • 8/19/2019 1401 SAP Customer Connection for SAP EAM Plant Maintenance 2014

    9/25

    Customer Connection Focus Topic project

    SAP EAM Plant Maintenance (2014) - project timeline

    Collection of Improvement

    Requests

    Selection of

    improvement requests

    for implementation

    Improvements’ development 

    (delivery as notes/SP)

    Productive use in

    customers‘ systems

    Collect Select Develop Use

    Kick-Off Final Call Selection Call Delivery Call

    Provide feedback

    on productive use

    Provide feedback in

    development & support

    testing

    Detailed analysis

    and decision on

    implementation

    Development and

    delivery of notes and

    support packages

    Continuous improvement of

    the Customer Connection

    process

    Follows, moderates

    and comments on

    improvement request

    Submit improvement

    requests, subscribe for

    IR prioritization

    SAP Customers

    Project Team

    Oct. 21, 2013 Jan 23, 2014  ~ 15.05.2014  ~ Q1, 2015 

    open project workspace

    15.10.2013 

    close project workspace

    31.1.2014 

    Speaker’s Corner Sessions 

    Customers

  • 8/19/2019 1401 SAP Customer Connection for SAP EAM Plant Maintenance 2014

    10/25

  • 8/19/2019 1401 SAP Customer Connection for SAP EAM Plant Maintenance 2014

    11/25

    Agenda

    ?

    Introduction Customer Connection Program

    What has been accomplished so far

    Current status of EAM Plant Maintenance 2014 project

    Recommended process from ASUG

    Q & A

  • 8/19/2019 1401 SAP Customer Connection for SAP EAM Plant Maintenance 2014

    12/25

    Customer Connection for EAM related topics

    Piloting Customer Connection with SAP EAM

    Fall 2010: 3 long-term requested improvements selected for development in order to pilot

    Customer Connection

    Successful development and delivery in 2011

    Customer Connection for SAP EAM Plant Maintenance

    Fall 2011: Customer Connection project for EAM Plant Maintenance conducted

    7 Improvement Requests were selected to be developed

    2012: all scoped IRs delivered

    additional cross-module improvements which were required from EAM project delivered

    Customer Connection for EAM Plant Maintenance 2014

    Fall 2013: Started collection phase towards the end of 2013 Involvement of all the user group across the globe

    176 improvement requested presented in a span of four months

    Moe than 70 improvement requests are qualified (subscribed by more than five customers)

    Top 20 improvement requests are prioritized and evaluated in detail

  • 8/19/2019 1401 SAP Customer Connection for SAP EAM Plant Maintenance 2014

    13/25

    Plant Maintenance (PM / EAM) Cycle 1 - PILOT

    Improvements delivered

    # Improvement Request Description Business Benefit Delivery 1 

    1. Enhancement of

    component and operation

    overview screen in EAM

    order

    Allow entry of all fields (and some

    more) of purchase requisition which

    are available on the details purchase

    data screen also on the overview

    screen for components and

    operations.

    The user does not have to navigate to

    the details screens of operation and

    components to enter specific fields or to

    access specific information.

    ERP 6.0 and higher

    Notes – see note 1573936

    (15.04.2011)

    2. Rescheduling of

    Maintenance Plans

    Automatically reschedule a

    maintenance plan after change of a

    maintenance cycle (of a package) ofthe strategy used in maintenance

    plans.

    Reduce the manual work and make it

    easier to find and support the optimal

    maintenance strategy for groups ofequipment or functional locations.

    ERP 6.0 and higher

    Notes – see note 1553173 (15.04.2011)

    3. Mass change of EAM order

    operations

    The order operation list (transaction

    IW37) is enhanced by mass change

    functionality for order operations.

    The user can change selected fields of

    operations for many orders with very

    few steps.

    ERP 6.0 and higher

    Notes – see note 1552769 

    (15.04.2011)

    1 As planned in SAP’s roadmap which might be subject to change 

    Successful adoption of improvements by DSAG members.

    Decision to continue the pilot cycle with Focus Topic PM/EAM Cycle 2.

    https://service.sap.com/sap/support/notes/1573936https://service.sap.com/sap/support/notes/1553173https://service.sap.com/sap/support/notes/1553173https://service.sap.com/sap/support/notes/1552769https://service.sap.com/sap/support/notes/1552769https://service.sap.com/sap/support/notes/1553173https://service.sap.com/sap/support/notes/1553173https://service.sap.com/sap/support/notes/1573936

  • 8/19/2019 1401 SAP Customer Connection for SAP EAM Plant Maintenance 2014

    14/25

    Focus Topic PM/EAM Cycle 2 – DELIVERED

    1   As planned in SAP’s roadmap which might be subject to change 

    2  If planned feature being made available by SAP

    Nr. Headline Description Status

    1 PM-110 Enable basic order view with all

    existing screens, especially the costoverview

    Enhance the work order view to a variable

    view that supports all existing sub-screensespecially the cost information

    DELIVERED

    Note 1703800 

    2 PM-117 Display classification data in

    FL/EQ lists:

    Display classification data in FL/EQ lists: save

    user layout settings, show all characteristicsDELIVERED

    Note 1674343 

    3 PM-082 Include incoming invoice

    document in document flow of order

    In the document flow of the work order the

    goods receipt and invoice should be displayed

    with the ID and the possibility to navigate tothese documents

    DELIVERED

    Note 1674883 

    4 PM-097 Display additional information

    in document flow

    Display additional information in document

    flow, such as vendor name, PO descriptionDELIVERED

    Note 1674883 

    5 PM-087 Link DMS documents to

    maintenance orders Enable the link to DMS for work orders without

    reference to notification or technical objectDELIVERED

    Note 1673999 

    6 PM-091-04 Enable possibility to enter

    opening horizon in calendar days

    Enable possibility to enter opening horizon in

    calendar days and not only as % of

    maintenance cycle

    DELIVERED

    Note 1665158 

    7 Defence Industry Group (DEIG) Deactivation of measurement points /

    counters via listNote 1664764 

    https://cw.sdn.sap.com/cw/ideas/5395https://websmp130.sap-ag.de/sap(bD1lbiZjPTAwMQ==)/bc/bsp/spn/sapnotes/index2.htm?numm=1703800https://cw.sdn.sap.com/cw/ideas/5396https://websmp130.sap-ag.de/sap(bD1lbiZjPTAwMQ==)/bc/bsp/spn/sapnotes/index2.htm?numm=1674343https://cw.sdn.sap.com/cw/ideas/5397https://websmp130.sap-ag.de/sap(bD1lbiZjPTAwMQ==)/bc/bsp/spn/sapnotes/index2.htm?numm=1674883https://cw.sdn.sap.com/cw/ideas/5414https://websmp130.sap-ag.de/sap(bD1lbiZjPTAwMQ==)/bc/bsp/spn/sapnotes/index2.htm?numm=1674883https://cw.sdn.sap.com/cw/ideas/5398https://websmp230.sap-ag.de/sap(bD1lbiZjPTAwMQ==)/bc/bsp/spn/sapnotes/index2.htm?numm=1673999https://cw.sdn.sap.com/cw/ideas/5403https://websmp130.sap-ag.de/sap(bD1lbiZjPTAwMQ==)/bc/bsp/spn/sapnotes/index2.htm?numm=1665158https://websmp130.sap-ag.de/sap(bD1lbiZjPTAwMQ==)/bc/bsp/spn/sapnotes/index2.htm?numm=1664764https://websmp130.sap-ag.de/sap(bD1lbiZjPTAwMQ==)/bc/bsp/spn/sapnotes/index2.htm?numm=1664764https://websmp130.sap-ag.de/sap(bD1lbiZjPTAwMQ==)/bc/bsp/spn/sapnotes/index2.htm?numm=1665158https://cw.sdn.sap.com/cw/ideas/5403https://cw.sdn.sap.com/cw/ideas/5403https://cw.sdn.sap.com/cw/ideas/5403https://cw.sdn.sap.com/cw/ideas/5403https://cw.sdn.sap.com/cw/ideas/5403https://websmp230.sap-ag.de/sap(bD1lbiZjPTAwMQ==)/bc/bsp/spn/sapnotes/index2.htm?numm=1673999https://cw.sdn.sap.com/cw/ideas/5398https://cw.sdn.sap.com/cw/ideas/5398https://cw.sdn.sap.com/cw/ideas/5398https://websmp130.sap-ag.de/sap(bD1lbiZjPTAwMQ==)/bc/bsp/spn/sapnotes/index2.htm?numm=1674883https://cw.sdn.sap.com/cw/ideas/5414https://cw.sdn.sap.com/cw/ideas/5414https://cw.sdn.sap.com/cw/ideas/5414https://websmp130.sap-ag.de/sap(bD1lbiZjPTAwMQ==)/bc/bsp/spn/sapnotes/index2.htm?numm=1674883https://cw.sdn.sap.com/cw/ideas/5397https://cw.sdn.sap.com/cw/ideas/5397https://cw.sdn.sap.com/cw/ideas/5397https://websmp130.sap-ag.de/sap(bD1lbiZjPTAwMQ==)/bc/bsp/spn/sapnotes/index2.htm?numm=1674343https://cw.sdn.sap.com/cw/ideas/5396https://cw.sdn.sap.com/cw/ideas/5396https://cw.sdn.sap.com/cw/ideas/5396https://websmp130.sap-ag.de/sap(bD1lbiZjPTAwMQ==)/bc/bsp/spn/sapnotes/index2.htm?numm=1703800https://cw.sdn.sap.com/cw/ideas/5395https://cw.sdn.sap.com/cw/ideas/5395https://cw.sdn.sap.com/cw/ideas/5395

  • 8/19/2019 1401 SAP Customer Connection for SAP EAM Plant Maintenance 2014

    15/25

    Agenda

    ?

    Introduction Customer Connection Program

    What has been accomplished so far

    Current status of EAM Plant Maintenance 2014 project

    Recommended process from ASUG

    Q & A

    Pl M i (PM / EAM) C l 3

  • 8/19/2019 1401 SAP Customer Connection for SAP EAM Plant Maintenance 2014

    16/25

    Plant Maintenance (PM / EAM) Cycle 3

    Improvement requests reviewedNr. Headline Description Status

    1 7135: Counting entries in ALV reports Enhance ALV lists within plant maintenance

    area to display number of rows selected by the

    selection criteria

    Technically Evaluated

    (May get delivered)

    2 7138: Deleting technical objects should

    also ensure deletion of maintenance

    plans

    Status of technical objects should be linked to

    status of maintenance plans. This will ensure

    that no calls will be generated for deleted

    objects

    Technically Evaluated

    (May get delivered)

    3 15195: Mass change of maintenance

    plans and Items

    Enable mass change of maintenance plans and

    item with fields grouped based on plan type

    and call horizon

    Technically Evaluated

    (May get delivered)

    4 6886: IW38 additional functions: Cancel

    TECO and „do not execute“ 

    Enabling list report to set Cancel TECO and “Do

    not Execute” status.Technically Evaluated

    (May get delivered)

    5 7132: Inactivation of notification codes There are multiple type of codes catalogue to

    record history in notification. Enable marking

    of codes that are not relevant in future.

    Technically Evaluated

    (May get delivered)

    6 10599: Create order as a following order It should be possible to create a new order

    based on work completed while executing an

    order. (for work arising or deferred tasks)

    Technically Evaluated

    (May get delivered)

    7 7006: PM order: cancellation of status

    NCMP (do not execute)

    Reset do not execute status of the order if it

    was done by an error.Needs further

    evaluation

    Pl M i (PM / EAM) C l 3

  • 8/19/2019 1401 SAP Customer Connection for SAP EAM Plant Maintenance 2014

    17/25

    Plant Maintenance (PM / EAM) Cycle 3

    Improvement requests reviewed

    Nr. Headline Description Status

    8 5416: Redesign of BAPIs in PM/CS Technically Evaluated

    (May get delivered)

    9 7456: copy of components (and tasks)

    within an order

    Technically Evaluated

    (May get delivered)

    10 15294: Overview dates to maintenanceplans and maintenance dates to a

    functional location/fl-structure

    Technically Evaluated(May get delivered)

    11 15283: Profile for default values within

    creation of Maintenance Plans

    Technically Evaluated

    (May get delivered)

    12 5400: BADI for influencing order data(e.g. Recipient in Task list, Plant for

    purchase)

    Technically Evaluated(May get delivered)

    13 7633: Validation maintenance plans

    (Valid to date)

    Technically Evaluated

    (May get delivered)

    14 5435: Enabling budgeting for orders

    when WBS-element is assigned

    Needs further

    evaluation

  • 8/19/2019 1401 SAP Customer Connection for SAP EAM Plant Maintenance 2014

    18/25

    Agenda

    ?

    Introduction Customer Connection Program

    What has been accomplished so far

    Current status of EAM Plant Maintenance 2014 project

    Recommended process from ASUG

    Q & A

  • 8/19/2019 1401 SAP Customer Connection for SAP EAM Plant Maintenance 2014

    19/25

    Mission

    Purpose for Starting EAM influence program within ASUG

    1. SAP EAM has a large installed base customers and it isgrowing

    2. Customers have implemented their solution for long time

    and not able leverage enhanced solution delivered by SAP

    3. EAM solution needs high integration with other modules in

    ECCWhat we want to hear

    1. Functionality gaps to meet business requirements

    2. Opportunities to enhance the current product

    3. Custom solutions and workarounds

    Why we’re here1. Foster communication between companies that use SAP

    EAM solution

    2. Influence SAP to improve the SAP EAM solution by sharing

    pain points in using the solution in their productive

    environment

  • 8/19/2019 1401 SAP Customer Connection for SAP EAM Plant Maintenance 2014

    20/25

    Objective and expectation from participants

    Objectives:

    1. Provide feedback for enhancements to future releases:2. Compile a list of enhancements to SAP EAM and its integration with

    MM/IM/PP/PS etc. Management

    3. Prioritize enhancement requests

    4. Provide feedback to SAP on possible solutions as required

    5. Identify opportunities for improvement in the current product

    Expectations from participants:

    1. Participants must be in actively using SAP EAM Project Prep through

    Implementation

    2. Live customer

    3. Participants must attend monthly council meetings and stay engaged

    with the feedback collection and prioritization4. Engage with SAP to provide business requirements, testing, etc. for

    agreed improvements

    f h

  • 8/19/2019 1401 SAP Customer Connection for SAP EAM Plant Maintenance 2014

    21/25

     

    from SAP…• We put our faith in being able to

    influence SAP through ASUG

    • Prepare logically important topics

    that could be subscribed by largenumber of users that we can get

    approval for focus topic in 2015

    • Collection of topics using influence

    platform 

    Hope and faith

  • 8/19/2019 1401 SAP Customer Connection for SAP EAM Plant Maintenance 2014

    22/25

    YOUR take away… 

    USE delivered improvements GET INVOLVED in ongoing

    Focus Topic projectsREQUEST new Focus Topic

    project

    Search for useful improvements onSAP Improvement Finder  

    Download and adopt relevant

    Improvement Note/SP

    Follow your area of interest onCustomer Influence and get

    informed about new and upcoming

    Focus Topic projects

    Submit your improvement request

    for projects in COLLECT phase

    Drive Customer Connectionopportunity within your community

    Get aligned on your needs within

    your community

    Request your Focus Topic and

    trigger the process

    http://www.sapimprovementfinder.com/http://influence.sap.com/http://influence.sap.com/http://www.sapimprovementfinder.com/

  • 8/19/2019 1401 SAP Customer Connection for SAP EAM Plant Maintenance 2014

    23/25

    Thank You!

     

  • 8/19/2019 1401 SAP Customer Connection for SAP EAM Plant Maintenance 2014

    24/25

    FOLLOW US

  • 8/19/2019 1401 SAP Customer Connection for SAP EAM Plant Maintenance 2014

    25/25

    THANK YOU

    THANK YOU FOR PARTICIPATING 

    Please provide feedback on this session by completinga short survey via the event mobile application.

    SESSION CODE: ####

    For ongoing education on this area of focus,visit www.ASUG.com