Page 1: 160355 M271 Consultation Brochure V6 - Citizen Space · 9 November 2016 and 16 December 2016. M271 A35 A33 Redbridge roundabout Western Docks Southampton Southampton Common ... NB

M271/A33/A35Redbridge Roundabout

Improvement scheme

Have your say between9 November 2016 and 16 December 2016

Page 2: 160355 M271 Consultation Brochure V6 - Citizen Space · 9 November 2016 and 16 December 2016. M271 A35 A33 Redbridge roundabout Western Docks Southampton Southampton Common ... NB

M271

A35

A33Redbridgeroundabout

Western Docks

Southampton

Southampton Common

SouthamptonSolent

University

A3057

A33River Test

River Test

Railway

Providing a ‘free fl ow’ lane from M271

southbound to A33 eastbound towards

Southampton – so traffi c won’t need to

stop at the roundabout.

Removing the bus lane traffi c signals from

A33 westbound whilst keeping the bus lane

and improving the bus stops.

Option 1, our initial design for a ‘hamburger’ style

roundabout, providing a direct link for the traffi c

going from the A33 to M271 northbound, was

rejected. This is because the existing subways

and footbridge would need to be demolished and

replaced by Toucan crossings which are less safe

for pedestrians and cyclists and potentially cause

delays on other arms of the roundabout.

We now have developed an Option 2 for further

consideration. It proposes:

4 lanes to the south side of the roundabout

3 lanes to the east side of the roundabout

Removal of the Toucan crossings across the

A33 sliproads to the east of the roundabout

Improving the subways and footbridge,

including modifi cations to approach ramps, so

that they are better, safe and attractive places

for pedestrians and cyclists

Maintain the existing shared pedestrian and

cycle route to the south of the roundabout.

Additional features

The scheme could be further enhanced,

depending on funding availability and the results

of further traffi c modelling with:

Wider traffi c lanes (4m instead of 3.5m)

3 lanes also provided to western side of the

roundabout

Additional exit lane onto the M271.

Impacts of proposed scheme

More road space to reduce congestion and

improve journey reliability

Better environment to make walking and

cycling easier, reduce noise and pollution.

About us

Highways England is the government company

responsible for operating and maintaining

England’s major A roads and motorways. Formerly

known as the Highways Agency, we are also

responsible for delivering improvements to the

existing strategic road network.

Redbridge Roundabout

Redbridge Roundabout is situated to the west

of Southampton City at the intersection of M271,

A33 and A35. It is a key gateway on the route

into Southampton City Centre and the Port of

Southampton from the west.

Need for the scheme

The Port of Southampton is the second busiest in

the country and is very important to Southampton

and the UK economy. Substantial levels of freight

and cruise passengers travel in and out every

day onto the motorway network. Maintaining a

well-functioning transport network is vital to the

competitiveness of the port and the continued

development and success of Southampton. A

congested, unreliable road network with poor

journey times has an environmental impact and

could jeopardise growth and job creation.

Current situation

The east-west traffi c between A33 and A35

travels on a fl yover above the roundabout,

whilst the main routes for the M271 are via

Redbridge roundabout.

Have your say

Your views and feedback will help shape our

proposal. You can:

Visit our website:

www.highways.gov.uk/M271A35Redbridge

See the plans in full and meet the project team:

Redbridge School

Cuckmere Lane

Southampton SO16 9RJ

Friday 25 Nov 4:00pm - 8:00pm

Saturday 26 Nov 10:00am - 4:00pm

Feedback forms will be available at the

school events and also from the Civic Centre,

Southampton SO14 7LY.

All feedback needs to be received by 16

December 2016.

Your feedback and comments must be received

before the consultation deadline of 16 December

so we can consider your response.

Scheme timeline

Options Phase

Currentlyunderway

Spring2017

Design Phase

Construction Phase

Spring 2020but may

startearlier

We are looking for public feedback on our proposed scheme design.

We will design the fi nal scheme in further detail, involving our key stakeholders and partners.

Congestion, particularly during the afternoon

peak, severely restricts traffi c movements

between Southampton and the M271 and

queues back into the city centre. Queuing

from A35 westbound also impacts on the

roundabout.

This divides the local communities, creating an

obstacle for people who want to walk or cycle

between different areas.

Aims of scheme improvement

We aim to deliver improvements to:

Support economic growth at a local and

regional level by improving strategic access

into city of Southampton.

Provide a safe and serviceable network

by improving safety and environment for

non-motorised users.

Deliver a more free-fl owing network by

relieving traffi c congestion and improving

capacity and journey times.

Improve the environment through public realm

improvements and landscaping and controlling

road traffi c noise through free-fl owing traffi c

and low noise surfacing.

Scheme design

We have looked at a number of options to achieve

the aims of the scheme, which include:

Reducing the number of traffi c signals.

32

Page 3: 160355 M271 Consultation Brochure V6 - Citizen Space · 9 November 2016 and 16 December 2016. M271 A35 A33 Redbridge roundabout Western Docks Southampton Southampton Common ... NB

CONISTON ROAD

CU

CK

ME

RE

REDBRIDGE ROAD

REDBRIDGE

OLD REDBRIDGE ROAD

LAN

E

FLYOVER

REDBRIDGE ROAD

OLDREDBRIDGE

ROAD

4.624.

64

4.63

4.63

4.31

4.29

4.27

4.29

4.41

4.65

6.29

6.25

4.31 4.28

4.324.38

4.28

4.28

4.21

4.40

4.43

5.25

BOL

BOL

BOLBOL

BOL

BOL

BOL

B

BOL

BOL

BOL

BOL

BOL

BOL

BS

BS

BOX

BOX

BOX

BOX

BOX

BOX

BOX BOX

BOXBOX

BOX

BOX

BOX

BOX

BOX

BOX

BOX

BOX

CATV

CATV

CATV

CATVCATV

CATV

CATV

CATVCATV

CATV

CATV

CATV

FH

FH

FH

Chart Nodes

Chart Nodes

GAS

GAS

GAS

GAS

GAS

GAS

GAS

GAS

GAS

GAS

GAS

GAS

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GULGUL

GUL

GUL

GUL

GUL

GUL GUL

GUL

GULGUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GULGUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

GUL

IC

IC

IC

IC

IC

IC

IC

IC

IC

IC

IC

IC

IC

ICIC

IC

IC

IC

ICICIC

IC

ICIC

IC

IC

IC

IC

ICIC

IC

IC

IC

IC

IC

IC

IC

IC

IC

IC

IC

IC

IC

IC

IC

KW

KW

KW

KW

KW

KW

KW

LP

LP

LP

LP

LP

LP

LP

LP

LP

LP

LP

LP

LP

LP

LP

LP

LP

LP

LP

LP

LP

LP

LP

LP

LP

LP

LP

LP

LP

LP

LP

LP

LP

LP

LP

LP

LP

LP

LP

LP

LP

LP

LP

LP

BB

LP

4.21MH

4.28MH

4.60MH

4.60MH

4.58MH

4.75MH

4.64MH

4.43MH

4.11MH

4.37MH

4.24MH

4.67MH

4.94MH

4.89MH

5.23MH

5.20MH

5.47MH

4.89MH

4.31MH

4.02MH

4.11MH

5.01MH

4.33MH

4.51MH

4.69MH

4.22MH

4.18MH

4.33MH

4.36MH

4.42MH

MK

MK

MK

MK

MK

MK

NB

4.58TC

4.45TC

4.54TC

4.48TC

4.22TC

4.50TC

4.41TC

4.23TC

4.30TC

5.34TC

4.25TC

3.97TC

4.20TC

4.15TC

4.08TC

4.29TC

4.31TC

4.96TC5.08

TC

4.25TC

4.36TC

4.33TC

4.18TC

4.45TC

Post

Post

Post

Post

Post

Post

Post

Post

RP

RP

RS

RS

RS

RS

RS

RS

RS

RS

RS

RS

RS

RS

RS

RS

RS

RS

RS

RS

RS

RS

RS

RS

RS

RS

RS

RS

RS

RS

RS

RS

SV

SV

SV

SV

SV

SV

SV

SV

SV

SV

SV

SV

SV

TL

TL

TL

TL

TL

TL

TL

TL

TL

TL

TL

TL

TLTL

TL

TL

TP

IC

IC

IC

IC

TS

TS

ICIC

IC

IC

IC

IC

IC

IC

IC

IC

IC

IC

IC

IC

IC

IC

IC

IC

IC

IC

IC

IC

RN

S

RNS

RNS

RN

S

RNS

RNS

RNS

RNS

RNS

RN

S

RN

SR

NS

RN

S

RNS

RNS

RNS

RNS

RNS

RNS

RNS

RNS

RNS

RNS

RNS

RNS

RNS

RN

S

RN

S

RNS

RNS

RN

S

LP

RS

KW

BUSSHELTER

BS

A33 WESTBOUND

A33 EASTBOUND

A35 WESTBOUNDA35 EASTBOUNDTL

C

ICIC

4.5m

4.5m

4.4m

2.0m

4.0m

TP

TP

TP

4.0m

4.0m

4.0m

3.0m

TP

4.0m

3.7m3.7m3.4m

4.0m4.0m

4.0m

GULGUL

5m5mmLPm555mm55..5.5.5555m554....

GUL

B

B

3.8m

4.5m

3.8m

4.0m

4.5m

4.0m

4.5m1.5m

1.5m

CARRIAGEWAY

FLYOVER

EXISTING PEDESTRIAN INFRASTRUCTUREMAINTAINED AND IMPROVED

PROPOSED WIDENING OF CARRIAGEWAYWITHIN SCC EXTENT

HIGHWAYS ENGLAND BOUNDARY

PROPOSED CRASH BARRIER

PROPOSED SHARED FOOTWAY

PROPOSED LAND TAKE

EXISTING FOOTBRIDGE IMPROVED

KEY:

Date: Scale: Sheet:

Designed:

Drawn:

Approved:

Checked:

© WSP UK Ltd

AppChkByDescriptionDateRev

A1

Title:Site/Project:Client:Key:

Revision:Drawing Number:

Notes:

© Crown Copyright and Database Rights 2015 Ordnance Survey 100030649

0 1 2 3 4 5 6 7 8 9 10

M271/A33/A35REDBRIDGE ROUNDABOUT

OPTION 2

PROPOSED ALIGNMENT

FOR CONSULTATIONIRC

ML

MB

EC

11.10.2016 1:500 @ A1

HE551515-WSPPB-HGN-M271PCF1-SK-HE-20003 P6

- 2 lane throughabout A33 westbound to M271northbound

- free flowing lane M271 southbound to A33 eastbound

MBMLISSUED FOR CONSULTATION28.07.16P5 WC

MBMLISSUED FOR CONSULTATIONRemoved Sustrans Text11.10.16P6 EC

54

Carriageways to be resurfaced with ‘low

noise’ tarmac

Improved green space on

roundabout

Existing fl yover

Widening of roundabout

Removal of signal that gives buses

priority

Improved shared use path

Port of Southampton

M27

M271

‘Free fl ow’ left turning lane from

M271 to the Port of Southampton

Improved subways and footbridge

Page 4: 160355 M271 Consultation Brochure V6 - Citizen Space · 9 November 2016 and 16 December 2016. M271 A35 A33 Redbridge roundabout Western Docks Southampton Southampton Common ... NB

M271 Redbridge roundabout feedback form

We value your views on this proposal to help reach a decision which benefi ts local communities,

motorists, pedestrians and cyclists alike. The closing date for responses is 14 December 2016.

You can give your feedback to us:

Online: A link to an online feedback form is on www.highways.gov.uk/M271/A35REDBRIDGE

By post: You can send this feedback form back to us using the freepost envelope provided.

Q1. In an average week, how often do you use Redbridge Roundabout by the following types of transport?

(Please tick one answer in each row applicable)

5 days or more

3-4 days 1-2 daysLess than

once a weekNever

By car

Bicycle

On foot

Motorcycle

Q2. How would you describe your experience of using Redbridge Roundabout?

(Please tick one answer in each row applicable)

Very satisfied

Fairly satisfied

NeutralFairly

dissatisfiedVery

dissatisfied

By car

Bicycle

On foot

Taxi

Motorcycle

Fo

ld a

nd

te

ar

76

Page 5: 160355 M271 Consultation Brochure V6 - Citizen Space · 9 November 2016 and 16 December 2016. M271 A35 A33 Redbridge roundabout Western Docks Southampton Southampton Common ... NB

Fo

ld a

nd

te

ar

Q3. Do you think that any of the following CURRENTLY apply to Redbridge Roundabout?

(Please tick all that apply)

In my experience Redbridge Roundabout is often congested

Redbridge Roundabout feels too small and constrained when I am using it

I rarely experience any congestion or delays when using Redbridge Roundabout

The footways and paths around the roundabout are unpleasant to use

Redbridge Roundabout acts as a barrier between communities on either side of it

I fi nd the footpaths under and over the Redbridge Roundabout pleasant to use

I feel unsafe when I am using Redbridge Roundabout

Q4. Option 2 is the scheme we propose to take forward. Do you agree that this proposal will achieve our scheme objectives?

Scheme objectives Strongly agree

AgreeDon’t know

DisagreeStrongly disagree

Support economic growth

Improve safety

Reduce congestion

Improve the environment

Q5. How did you fi nd out about the Redbridge Roundabout upgrade scheme?

Received a letter

Highways England website

Southampton City Council website

Local radio or television news

Local newspaper

Online media (news websites)

Poster

Other (please specify below)

Q6. Have you found this brochure helpful in answering your questions?

Yes To some extent No Did not read

Q7. Have you found our public exhibitions helpful in answering your questions?

Yes To some extent No Did not attend

Q8. Do you have any additional comments about the improvement scheme that you would like us to consider?

To ensure that we are meeting our quality and diversity guidelines, please fi ll in the following section of

the questionnaire. This information will only be used by Highways England to monitor its effectiveness at

consulting with the community. This information will not be used for any other purpose, and individuals

will not be identifi ed when the results are published.

Q9. Please tell us your age

Under 18 18-24 25-34 35-44 45-54 55-64 Over 65

Q10. Gender

Male FemalePrefer not to

say

Fo

ld a

nd

te

ar

98

Page 6: 160355 M271 Consultation Brochure V6 - Citizen Space · 9 November 2016 and 16 December 2016. M271 A35 A33 Redbridge roundabout Western Docks Southampton Southampton Common ... NB

Q11. Please let us know which group you identify yourself as:

White British (English, Welsh, Scottish)

Irish

Other white

Asian or British Asian

Black or black British

Mixed race

Other (please specify)

Q12. Please let us know which group you identify yourself as:

Christian (all denominations)

Muslim

Jewish

Hindu

Buddhist

No religion/Atheist/Agnostic

Other (please specify)

Q13. Do you consider yourself to have a disability?

Prefer not to say

No

Yes (please specify if you wish to do so)

Fo

ld a

nd

te

ar

1110

Page 7: 160355 M271 Consultation Brochure V6 - Citizen Space · 9 November 2016 and 16 December 2016. M271 A35 A33 Redbridge roundabout Western Docks Southampton Southampton Common ... NB

If you need help accessing this or any other Highways England information,

please call 0300 123 5000 and we will help you.

Contact us

If you have any queries relating to the M271/A33/A35 Redbridge roundabout improvement

scheme, please do not hesitate to contact us at:

[email protected]

For the latest information and updates, please visit our website:

www.highways.gov.uk/M271A35redbridge

This document is also available on our website at:

www.gov.uk/highways

If you have any queries relating to Highways England, you should contact the information line on:

0300 123 5000

or alternatively email:

[email protected]

Working in partnership with Highways England

© Crown copyright 2016.

You may re-use this information (not including logos) free of charge in any format or medium,under the terms of the Open Government Licence. To view this licence:

visit www.nationalarchives.gov.uk/doc/open-government-licence, write to the Information Policy Team, The National Archives, Kew, London TW9 4DU,

or email [email protected]

This document is also available on our website at www.gov.uk/highways

If you have any enquiries about this publication email [email protected] or call 0300 123 5000*. Please quote the Highways England

publications code PR102/16

Highways England, Creative S160355

*Calls to 03 numbers cost no more than a national rate call to an 01 or 02 number and must count towards any inclusive minutes in the same way as 01 and 02 calls.

These rules apply to calls from any type of line including mobile, BT, other fi xed line or payphone. Calls may be recorded or monitored.

Printed on paper from well-managed forests and other controlled sources.

Registered offi ce Bridge House, 1 Walnut Tree Close, Guildford GU1 4LZ

Highways England Company Limited registered in England and Wales number 09346363