Page 1: 1/71 Project Management Organizing And Staffing The Project Office And Team

1/71

Project Management

Organizing And Staffing

The Project

Office And Team

Page 2: 1/71 Project Management Organizing And Staffing The Project Office And Team

2/71

Outline

1. Introduction

2. The Staffing Environment

3. Selecting the project Manager

4. Skill Requirement for Project and Program Manager

5. Special Case for Project Manager Selection

6. Selecting the Wrong project Manager

7. Next Generation Project Managers

8. Duties and Job Descriptions

Page 3: 1/71 Project Management Organizing And Staffing The Project Office And Team

3/71

Outline (Continued)

8. The Organizational Staffing Process

9. The Project Office

10. The Functional Team

11. The Project Organizational Chart

12. Special Problems

13. Selecting the Project management Implementation Team

Page 4: 1/71 Project Management Organizing And Staffing The Project Office And Team

4/71

Introduction

Project Personnel includes: A project manager An assistant project manager (if necessary) A project (home) office A project team

Page 5: 1/71 Project Management Organizing And Staffing The Project Office And Team

5/71

The Staffing Environment Staffing questions to ask:

What are the requirements for an individual to become a successful project manager?

Who should be a member of the project team? Who should be a member of the project office? What problems can occur during recruiting

activities? What can happen downstream to cause the loss of

key team members?

Page 6: 1/71 Project Management Organizing And Staffing The Project Office And Team

6/71

Project manager’s skills needed: Honesty and integrity Understanding of personnel problems Understanding of project technology Business management competence

Management principles Communications

Alertness and quickness Versatility Energy and toughness Decision-making ability Ability to evaluate risk and uncertainty

The Staffing Environment (Continued)

Page 7: 1/71 Project Management Organizing And Staffing The Project Office And Team

7/71

Selecting the Project Manager: Executive Consideration

Acquire the best available assets and try to improve them

Provide a good working environment for all personnel

Make sure that all resources are applied effectively and efficiently so that all constraints are met, if possible

Page 8: 1/71 Project Management Organizing And Staffing The Project Office And Team

8/71

Project Manager Selection A project manager is given a license to cut

across several organizational lines. His activities, therefore, take on a flavor of general management, and must be done well.

Project management will not succeed without good project managers. Thus, if general management sees fit to establish a project, it should certainly see fit to select a good person as its leader.

Page 9: 1/71 Project Management Organizing And Staffing The Project Office And Team

9/71

Project Manager Selection (Continued)

A project manager is far more likely to accomplish desired goals if it is obvious that general management has selected and appointed him.

Page 10: 1/71 Project Management Organizing And Staffing The Project Office And Team

10/71

Selection Process for Project Manager

Questions to ask: What are the internal and external sources? How do we select? How do we provide career development in project

management? How can we develop project management skills? How do we evaluate project management

performance?

Page 11: 1/71 Project Management Organizing And Staffing The Project Office And Team

11/71

Project Manager’sResponsibilities

To produce the end-item with the available resources and within the constraints of time, cost, and performance/technology

To meet contractual profit objectives To make all required decisions whether

they be for alternatives or termination To act as the customer (external) and

upper-level and functional management (internal) communications focal point

Page 12: 1/71 Project Management Organizing And Staffing The Project Office And Team

12/71

Project Manager’s

Responsibilities (Continued)

To “negotiate” with all functional disciplines for accomplishment of the necessary work packages within the constraints of time, cost, and performance/technology

To resolve all conflicts, if possible

Page 13: 1/71 Project Management Organizing And Staffing The Project Office And Team

13/71

Personal Characteristics for Project Manager

Flexibility and adaptability Preference for significant initiative and

leadership Aggressiveness, confidence,

persuasiveness, verbal fluency Ambition, activity, forcefulness Effectiveness as a communicator and

integrator Broad scope of personal interests Poise, enthusiasm, imagination, spontaneity

Page 14: 1/71 Project Management Organizing And Staffing The Project Office And Team

14/71

Able to balance technical solutions with time, cost, and human factors

Well organized and disciplined A generalist rather than a specialist Able and willing to devote most of his time to

planning and controlling Able to identify problems Willing to make decisions Able to maintain proper balance in the use of

time

Personal Characteristics for Project Manager

Page 15: 1/71 Project Management Organizing And Staffing The Project Office And Team

15/71

Additional Skills Needed

Are feasibility and economic analyses necessary? Is complex technical expertise required? If so, is

it within the individual’s capabilities? If the individual is lacking expertise, will there be

sufficient backup strength in the line organizations?

Is this the company’s or the individual’s first exposure to this type of project and/or client? If so, what are the risks to be considered?

Page 16: 1/71 Project Management Organizing And Staffing The Project Office And Team

16/71

Additional Skills Needed (Continued)

What is the priority for this project, and what are the risks?

With whom must the project manager interface, both inside and outside the organization?

Page 17: 1/71 Project Management Organizing And Staffing The Project Office And Team

17/71

Worker Skills

They must know what they are supposed to do, preferably in terms of an end product.

They must have a clear understanding of their authority and its limits.

They must know what their relationship with other people is.

They should know where and when they are falling short.

Page 18: 1/71 Project Management Organizing And Staffing The Project Office And Team

18/71

Worker Skills (Continued)

They must be made aware of what can and should be done to correct unsatisfactory results.

They must feel that their superior has an interest in them as individuals.

They must feel that their superior believes in them and is anxious for their success and progress.

Page 19: 1/71 Project Management Organizing And Staffing The Project Office And Team

19/71

Skill Requirement for Project and Program Managers

Team building Leadership Conflict resolution Technical expertise Planning Organization Entrepreneurship

Page 20: 1/71 Project Management Organizing And Staffing The Project Office And Team

20/71

Skill Requirement for Project and Program Managers (Continued)

Administration Management support Resource allocation

Page 21: 1/71 Project Management Organizing And Staffing The Project Office And Team

21/71

Team Building Skills

Team members committed to the program Good interpersonal relations and team spirit The necessary expertise and resources Clearly defined goals and program

objectives Involved and supportive top management Good program leadership

Page 22: 1/71 Project Management Organizing And Staffing The Project Office And Team

22/71

Team Building Skills (Continued)

Open communication among team members and support organizations

A low degree of detrimental interpersonal and intergroup conflict

Page 23: 1/71 Project Management Organizing And Staffing The Project Office And Team

23/71

Leadership Skills

Clear project leadership and direction Assistance in problem solving Facilitating the integration of new members

into the team Ability to handle interpersonal conflict Facilitating group decisions Capability to plan and elicit commitments Ability to communicate clearly

Page 24: 1/71 Project Management Organizing And Staffing The Project Office And Team

24/71

Leadership Skills (Continued)

Presentation of the team to higher management Ability to balance technical solutions against

economic and human factors

Page 25: 1/71 Project Management Organizing And Staffing The Project Office And Team

25/71

Conflict Resolution Skills Understand interaction of the organizational

and behavioral elements in order to build an environment conducive to their team’s motivational needs. This will enhance active participation and minimize unproductive conflict.

Communicate effectively with all organizational levels regarding both project objectives and decisions. Regularly scheduled status review meetings can be an important communication vehicle.

Page 26: 1/71 Project Management Organizing And Staffing The Project Office And Team

26/71

Conflict Resolution Skills (Continued)

Recognize the determinants of conflict and their timing in the project life cycle. Effective project planning, contingency planning, securing of commitments, and involving top management can help to avoid or minimize many conflicts before they impede project performance.

Page 27: 1/71 Project Management Organizing And Staffing The Project Office And Team

27/71

Technical Skills Technology involved Engineering tools and techniques employed Specific markets, their customers, and

requirements Product applications Technological trends and evolutions Relationship among supporting

technologies People who are part of the technical

community

Page 28: 1/71 Project Management Organizing And Staffing The Project Office And Team

28/71

Planning Skills

Information processing Communication Resource negotiations Securing commitments Incremental and modular planning Assuring measurable milestones Facilitating top management involvement

Page 29: 1/71 Project Management Organizing And Staffing The Project Office And Team

29/71

Organizational Skills

Defining the reporting relationship Defining responsibility Defining lines of control Defining information needed Defining program objectives Opening communication channel Obtaining senior management supports

Page 30: 1/71 Project Management Organizing And Staffing The Project Office And Team

30/71

Special Cases in project Manager Selection

Part-time versus full-time assignments Several projects assigned to one project

manager Projects assigned to functional managers The project manager’s role retained by the

general manager

Page 31: 1/71 Project Management Organizing And Staffing The Project Office And Team

31/71

Selecting the Wrong Project Manager--Risks

The greater the project manager’s technical expertise, the higher the propensity that he will overly involve himself in the technical details of the project.

The greater the project manager’s difficulty in delegating technical task responsibilities, the more likely it is that he will overinvolve himself in the technical details of the project. (Depending upon his expertise to do so).

Page 32: 1/71 Project Management Organizing And Staffing The Project Office And Team

32/71

Risks (Continued)

The greater the project manager’s interest in the technical details of the project, the more likely it is that he will defend the project manager’s role as one of a technical specialist.

The lower the project manager’s technical expertise, the more likely it is that he will overstress the non-technical project functions (administrative functions).

Page 33: 1/71 Project Management Organizing And Staffing The Project Office And Team

33/71

Next Generation Project Manager

The primary skills needed to be an effective project manager in the 21st century are: Knowledge of business Risk management Integration skill

Page 34: 1/71 Project Management Organizing And Staffing The Project Office And Team

34/71

Changing skills needed in the 21st century for the Project

Managers

Page 35: 1/71 Project Management Organizing And Staffing The Project Office And Team

35/71

How Do Project Managers Spend Their Time?

Page 36: 1/71 Project Management Organizing And Staffing The Project Office And Team

36/71

Duties and Job Descriptions(Continued)

Page 37: 1/71 Project Management Organizing And Staffing The Project Office And Team

37/71

Duties and Job Descriptions(Continued)

Page 38: 1/71 Project Management Organizing And Staffing The Project Office And Team

38/71

Duties and Job Descriptions(Continued)

Page 39: 1/71 Project Management Organizing And Staffing The Project Office And Team

39/71

The Organizational Staffing Process

Recruitment Concerns Line mangers often receive no visibility or

credit for a job well done. Be willing to introduce line managers to the customer.

Be sure to show people how they can benefit by working for you or on your project.

Any promises made during recruitment should be documented. The functional organization will remember them long after your project terminates.

Page 40: 1/71 Project Management Organizing And Staffing The Project Office And Team

40/71

The Organizational Staffing Process (Continued)

Recruitment Concerns As strange as it may seem, the project manager

should encourage conflicts to take place during recruiting and staffing. These conflicts should be brought to the surface and resolved. It is better for conflicts to be resolved during the initial planning stages than to have major confrontations later.

Page 41: 1/71 Project Management Organizing And Staffing The Project Office And Team

41/71

Recruitment Policy Unless some other condition is paramount,

project recruiting policies should be as similar as possible to those normally used in the organization for assigning people to new jobs.

Everyone should be given the same briefing about the project, this rule can be modified to permit different amounts of information to be given to different managerial levels, but at least everyone in the same general classification should get the same briefing. It should be complete and accurate.

Page 42: 1/71 Project Management Organizing And Staffing The Project Office And Team

42/71

Recruitment Policy (Continued)

Any commitments made to members of the team about treatment at the end of the project should be approved in advance by general management. No other commitments should be made.

Every individual selected for a project should be told why he or she was chosen.

A similar degree of freedom should be granted all people, or at least all those within a given job category, in the matter of accepting or declining a project assignment.

Page 43: 1/71 Project Management Organizing And Staffing The Project Office And Team

43/71

Degrees of Permissiveness

The project is explained and the individual is asked to join and given complete freedom to decline, no questions asked.

The individual is told he will be assigned to the project. However, he is invited to bring forward any reservations he may have about joining. Any sensible reason he offers will excuse him from the assignment.

Page 44: 1/71 Project Management Organizing And Staffing The Project Office And Team

44/71

Degrees of Permissiveness (Continued)

The individual is told he is assigned to the project. Only a significant personal or career preference is accepted as a reason for excusing him from joining the project.

The individual is assigned to the project as he would be to any other work assignment. Only an emergency can excuse him from serving on the project team.

Page 45: 1/71 Project Management Organizing And Staffing The Project Office And Team

45/71

Staffing Pattern Versus Time

RAMP UP FROM OTHERPROJECTS OR FUNCTIONAL

GROUPS

RELEASE TO OTHERPROJECTS OR FUNCTIONAL

GROUPS

CONSTANT MANPOWER

ST

AF

FIN

G

TIME (LIFE CYCLE PHASES)

Page 46: 1/71 Project Management Organizing And Staffing The Project Office And Team

46/71

The Project Office -- Organization

PROJECTMANAGER

ASST. PROJ. MGRS.

FUNCTIONAL MANAGERS

EMPLOYEES

PROJECT OFFICE

PROJECT TEAM

Page 47: 1/71 Project Management Organizing And Staffing The Project Office And Team

47/71

Special Problems

Personnel connected with project forms of organization suffer more anxieties about possible loss of employment than members of functional organizations.

Individuals temporarily assigned to matrix organizations are more frustrated by authority ambiguity than permanent members of functional organizations.

Page 48: 1/71 Project Management Organizing And Staffing The Project Office And Team

48/71

Special Problems (Continued)

Personnel connected with project forms of organization that are nearing their phase-out are more frustrated by what they perceive to be “make work” assignments than members of functional organizations.

Personnel connected with project forms of organization feel more frustrated because of lack of formal procedures and role definitions than members of functional organizations.

Page 49: 1/71 Project Management Organizing And Staffing The Project Office And Team

49/71

Special Problems (Continued)

Personnel connected with project forms of organization worry more about being set back in their careers than members of functional organizations.

Personnel connected with project forms of organization feel less loyal to their organization than members of functional organizations.

Page 50: 1/71 Project Management Organizing And Staffing The Project Office And Team

50/71

Special Problems (Continued)

Personnel connected with project forms of organization have more anxieties in feeling that there is no one concerned about their personal development than members of functional organizations.

Permanent members of project forms or organization are more frustrated by multiple levels of management than members of functional organizations.

Page 51: 1/71 Project Management Organizing And Staffing The Project Office And Team

51/71

Special Problems (Continued)

Frustrations caused by conflict are perceived more seriously by personnel connected with project with project forms of organization than members of functional organizations.

People trained in single line-of-command organizations find it hard to serve more than one boss.

Page 52: 1/71 Project Management Organizing And Staffing The Project Office And Team

52/71

Special Problems (Continued) People may give lip service to teamwork,

but not really know how to develop and maintain a good working team.

Project and functional managers sometimes tend to compete rather than cooperate with each other.

Individuals must learn to do more “managing” of themselves.

Page 53: 1/71 Project Management Organizing And Staffing The Project Office And Team

53/71

Assigning Project Managers

Promote the individual in salary and grade and transfer him into project management.

Laterally transfer the individual into project management without any salary or grade increase. If, after three to six months, the employee demonstrates that he can perform, he will receive an appropriate salary and grade increase.

Page 54: 1/71 Project Management Organizing And Staffing The Project Office And Team

54/71

Assigning Project Managers (Continued)

Give the employee a small salary increase without any grade increase or a grade increase without any salary increase, with the stipulation that additional awards will be forthcoming after the observation period, assuming that the employee can handle the position.

Page 55: 1/71 Project Management Organizing And Staffing The Project Office And Team

55/71

TheTheAggressorAggressor

TheTheAggressorAggressor

DestructiveDestructiveRolesRoles

DestructiveDestructiveRolesRoles

DominatorDominatorDominatorDominator

Devil’sDevil’sAdvocateAdvocateDevil’sDevil’s

AdvocateAdvocate

TopicTopicJumperJumperTopicTopic

JumperJumperRecognitionRecognition

SeekerSeekerRecognitionRecognition

SeekerSeeker

TheTheWithdrawerWithdrawer

TheTheWithdrawerWithdrawer

TheTheBlockerBlocker

TheTheBlockerBlocker

People Roles Which Undermine Project Management Implementation

Page 56: 1/71 Project Management Organizing And Staffing The Project Office And Team

56/71

The AggressorThe Aggressor

Criticizes Everybody and Everything on Project Management

Deflates Status and Ego of OthersAlways Aggressive

Criticizes Everybody and Everything on Project Management

Deflates Status and Ego of OthersAlways Aggressive

Destructive Roles

Page 57: 1/71 Project Management Organizing And Staffing The Project Office And Team

57/71

DominatorDominator

Always Tries to Take OverProfesses to Know Everything About

Project ManagementTries to Manipulate People Will Challenge Your Leadership

Always Tries to Take OverProfesses to Know Everything About

Project ManagementTries to Manipulate People Will Challenge Your Leadership

Destructive Roles

Page 58: 1/71 Project Management Organizing And Staffing The Project Office And Team

58/71

Devil’s AdvocateDevil’s Advocate

Finds Fault in All Areas of Project Management

Refuses to Become a Believer Unless Threatened

More Devil Than Advocate

Finds Fault in All Areas of Project Management

Refuses to Become a Believer Unless Threatened

More Devil Than Advocate

Destructive Roles

Page 59: 1/71 Project Management Organizing And Staffing The Project Office And Team

59/71

Topic JumperTopic JumperMust Be the First with a New

Idea/Approach for Project ManagementContinuously Changes TopicsCannot Focus on Issues for a Long Time

Unless It Is His/HersProject Management Implementation

Remains an “Action Item” Forever

Must Be the First with a New Idea/Approach for Project Management

Continuously Changes TopicsCannot Focus on Issues for a Long Time

Unless It Is His/HersProject Management Implementation

Remains an “Action Item” Forever

Destructive Roles

Page 60: 1/71 Project Management Organizing And Staffing The Project Office And Team

60/71

Recognition SeekerRecognition Seeker Always Argues in Favor of His/Her Own Ideas

Is Very Status Conscious Volunteers to Become the Project Manager If

Status Is Recognized Continuous Talks (Likes to Hear

Himself/Herself Speak) Often Boasts Rather Than Providing

Meaningful Information

Always Argues in Favor of His/Her Own Ideas

Is Very Status Conscious Volunteers to Become the Project Manager If

Status Is Recognized Continuous Talks (Likes to Hear

Himself/Herself Speak) Often Boasts Rather Than Providing

Meaningful Information

Destructive Roles

Page 61: 1/71 Project Management Organizing And Staffing The Project Office And Team

61/71

The WithdrawerThe Withdrawer

Is Afraid of CriticismWill Not Participate OpenlyWithholds InformationMay Become a Back-StabberMay Be Shy

Is Afraid of CriticismWill Not Participate OpenlyWithholds InformationMay Become a Back-StabberMay Be Shy

Destructive Roles

Page 62: 1/71 Project Management Organizing And Staffing The Project Office And Team

62/71

The BlockerThe BlockerLikes to CriticizeRejects the Views of OthersCites Unrelated Examples and Personal

ExperiencesHas Multiple Reasons Why Project

Management Will Not Work

Likes to CriticizeRejects the Views of OthersCites Unrelated Examples and Personal

ExperiencesHas Multiple Reasons Why Project

Management Will Not Work

Destructive Roles

Page 63: 1/71 Project Management Organizing And Staffing The Project Office And Team

63/71

InitiatorsInitiatorsInitiatorsInitiators

SupportiveSupportiveRolesRoles

SupportiveSupportiveRolesRoles

InformationInformationSeekersSeekers

InformationInformationSeekersSeekers

InformationInformationGiversGivers

InformationInformationGiversGivers

EncouragersEncouragersEncouragersEncouragers

ClarifiersClarifiersClarifiersClarifiersHarmonizersHarmonizersHarmonizersHarmonizers

ConsensusConsensusTakersTakers

ConsensusConsensusTakersTakers

GateGateKeepersKeepers

GateGateKeepersKeepers

People Roles Which Support Project Management Implementation

Page 64: 1/71 Project Management Organizing And Staffing The Project Office And Team

64/71

InitiatorsInitiators

“Is There a Chance That This Might Work?”

“Let’s Try This!”

“Is There a Chance That This Might Work?”

“Let’s Try This!”

Supportive Roles

Page 65: 1/71 Project Management Organizing And Staffing The Project Office And Team

65/71

Information SeekersInformation Seekers

“Have We Tried Anything Like This Before?”

“Do We Know Other Companies Where This Has Worked?”

“Can We Get This Information?”

“Have We Tried Anything Like This Before?”

“Do We Know Other Companies Where This Has Worked?”

“Can We Get This Information?”

Supportive Roles

Page 66: 1/71 Project Management Organizing And Staffing The Project Office And Team

66/71

Information GiversInformation Givers

“Other Companies Found That …..”“The Literature Says That …..”“Benchmarking Studies Indicate That …...”

“Other Companies Found That …..”“The Literature Says That …..”“Benchmarking Studies Indicate That …...”

Supportive Roles

Page 67: 1/71 Project Management Organizing And Staffing The Project Office And Team

67/71

EncouragersEncouragers

“Your Idea Has a Lot of Merit.” “The Idea Is Great But We May Have to

Make a Small Change.” “What You Said Will Really Help Us.”

“Your Idea Has a Lot of Merit.” “The Idea Is Great But We May Have to

Make a Small Change.” “What You Said Will Really Help Us.”

Supportive Roles

Page 68: 1/71 Project Management Organizing And Staffing The Project Office And Team

68/71

ClarifiersClarifiers

“Are We Saying That …..” “Let Me State in My Own Words What I

Think You Said.” “Let’s See if We Can Put This Into

Perspective.”

“Are We Saying That …..” “Let Me State in My Own Words What I

Think You Said.” “Let’s See if We Can Put This Into

Perspective.”

Supportive Roles

Page 69: 1/71 Project Management Organizing And Staffing The Project Office And Team

69/71

HarmonizersHarmonizersHarmonizersHarmonizers

““We Sort of Agree, Don’t We?”We Sort of Agree, Don’t We?” ““Your Ideas and Mine Are Close Your Ideas and Mine Are Close

Together.”Together.” ““Aren’t We Saying the Same Thing?”Aren’t We Saying the Same Thing?”

““We Sort of Agree, Don’t We?”We Sort of Agree, Don’t We?” ““Your Ideas and Mine Are Close Your Ideas and Mine Are Close

Together.”Together.” ““Aren’t We Saying the Same Thing?”Aren’t We Saying the Same Thing?”

Supportive Roles

Page 70: 1/71 Project Management Organizing And Staffing The Project Office And Team

70/71

Consensus TakersConsensus Takers

““Let’s See if We Are in Agreement.”Let’s See if We Are in Agreement.” ““Let’s Take a Vote on This.”Let’s Take a Vote on This.” ““Let’s See How the Rest of the Group Let’s See How the Rest of the Group

Feels About This.”Feels About This.”

““Let’s See if We Are in Agreement.”Let’s See if We Are in Agreement.” ““Let’s Take a Vote on This.”Let’s Take a Vote on This.” ““Let’s See How the Rest of the Group Let’s See How the Rest of the Group

Feels About This.”Feels About This.”

Supportive Roles

Page 71: 1/71 Project Management Organizing And Staffing The Project Office And Team

71/71

Gate KeepersGate Keepers

“Who Hasn’t Given Us Their Opinions on This yet?”

“Should We Keep Our Options Open?” “Are We Prepared to Make a Decision or

Recommendation, or Is There Additional Information to Be Reviewed?”

“Who Hasn’t Given Us Their Opinions on This yet?”

“Should We Keep Our Options Open?” “Are We Prepared to Make a Decision or

Recommendation, or Is There Additional Information to Be Reviewed?”

Supportive Roles