COST ANALYSIS:
MECHANIZED HAULINGDISTANCE (kms)
BY SEA HAULINGDISTANCE
MANUAL HAULINGDISTANCE (kms)
25.00 35.00 2.00
I. DIRECT COST 344,042.56 14,597.55 60,707.39 98,539.74
II. INDIRECT COST 21% of (I) 72,248.94 3,065.49 12,748.55 20,693.35
III. TAX 12% of (I+II) 49,954.98 2,119.56 8,814.71 14,307.97
IV.TOTAL CONSTRUCTION COST
(I+II+III)466,246.47 19,782.60 82,270.65 133,541.06
V. ENG'G OVERHEAD 3.5% of (IV) 16,318.63 692.39 2,879.47 4,673.94
VI. TOTAL PROJECT COST (IV+V) 482,565.10 20,474.99 85,150.12 138,214.99
% of TOTAL PROJECT COST 4.10% 17.05% 27.67%
DERIVED UNIT % MULTIPLIER 0.16% 0.49% 13.84%
SUMMARY :
A Hauling cost by LAND = (Standard AAE) x (DERIVED UNIT% MULTIPLIER) x (LAND DISTANCE)
B Hauling cost by SEA = (Standard AAE) x (DERIVED UNIT% MULTIPLIER) x (SEA DISTANCE)
C MANUAL Hauling Cost = (Standard AAE) x (DERIVED UNIT% MULTIPLIER) x (WALKING DISTANCE)
THEREFORE:
AMOUNT
(as per POW)
STANDARD 1CL 7m x 7m AAE (cost
estimate)
-
8/18/2019 1cl 7x7 M
2/2
TOTAL PROJECT COST with HAULING = Std. AAE + A + B + C