OUTLINEDefinition of some termsPart I: Preliminary-IntroductionPart II : Internal Organisation of Procuring
EntitiesPart III: General Procurement Rules.Part IV: Open TenderingPart V :Alternative Procurement MethodsPart VI- Administrative Review of
Procurements and ProceedingsPart VII Investigation, Debarment and Disposal Schedules
3
DEFINITIONS OF TERMS• Procurement Acquisition by purchase, rental, lease, hire purchase, tenancy,
franchise or any other contractual means of any type of works, assets, services of goods including livestock or any combination
• Assets Movable and immovable property, tangible and intangible
including immovable property stores equipment, shares, intellectual rights vested in the state or proprietary rights.
• Procurement Plan A document prepared annually to plan all procurement
requirements• Public private partnership Agreement between a procuring entity and private party under
which a private party undertakes to perform a public function or provide a service on behalf of the procuring entity.
4
DEFINITIONS OF TERMS
• Pre-qualification procedure Pre-qualification procedure set out in the
regulations (Reg.23 that is- ……..to include nature of requirements,
quantities….timetable for delivery, etc . Note: This is not same as procedures for
maintaining and updating annually a registered list of potential tenderers as per Reg.(8) (3) (a).
• A tenderer A person submitting a tender
5
PART I PRELIMINARY INTRODUCTION • These Regulations apply to public entities as enlisted under
Section 3(1) of the ACT that is- Any body using public assets in any form of contractual
undertaking. Companies owned by public entity Any body in which the Government has a controlling share• Capacity building levy( Regulation 4 ) The capacity building levy payable under section 18(5)(d) of
the Act shall be 1.5 % of the contract price Payable in respect to the portion funded by the Government
for contracts partly funded by donors. Not applicable where the contract is 100% funded by
donor.
6
PART I PRELIMINARY cont’d
The Advisory Board (Regulation 5) • Membership Nine members from prescribed institutions as
per First Schedule of the Act plus the Director General
A total of 14 prescribed bodies to nominate two persons –one a woman {(Reg.5(1)}.
The appointments to be approved by Parliament.
7
PART I PRELIMINARY cont’d Threshold matrix (Reg.6). • Prescribed under First Schedule of the
Regulations• Apply to PEs differently according to Classes A ,B
& C – Gazette Notice - Legal No3 of 2007 dated 24th January 2007.
• Contains: Responsibility for awarding contracts Responsibility for signing contracts Responsibility for Inspection/Verification and
Acceptance of Goods ,services and works
8
PART I PRELIMINARY cont’d
Role of User Department (Reg. 9)• Initiation of requirements and participating in
management of contracts.• Preparing specifications and undertaking
conformity assessment.• Preparation of procurement plan• Compliance with the Act and regulations Note : In response to Section 27(3) of the Act-
“Responsibility for compliance with the Act and regulations by employees, members of a board or committee”
9
PART II INTERNAL ORGANISATION OF PROCURING ENTITIES.
Role of Accounting officer(Regulation7)• Pursuant to Sub- Section27(2) of the Act –
Accounting officer shall: Ensure establishment of Tender
/Procurement Committees.Ensures establishment of Procurement Unit
(staffed with procurement professionals)Ensures that Procurement Plans are
preparedEnsure proper documentation of
procurement proceedings.
10
PART II INTERNAL ORGANISATION OF PROCURING ENTITIES cont’d
Tender committee ( Reg. 10) • Member of the tender committee may be paid
such honoraria as the procuring entity may determine.
• Where the value of the contract is above Kshs 50,000,000 at least two observers will be invited to the tender committee meetings.
• Decisions to be by consensus, and minutes prepared or by vote if consensus is not feasible
• Declared conflicts of interest and dissenting views to be recorded.
11
PART II INTERNAL ORGANISATION OF PROCURING ENTITIES cont’d
Tender committee ( Reg. 10)• No ratification of decisions made outside the
committee.• Reviewing decisions made by Procurement
Committees• Review, verify and ascertain that all procurement
and disposal are undertaken in accordance with the Act and the Regulations.
• Alternate members with adequate experience to be appointed
• Quorum-Five members including the Chairman
12
PART II INTERNAL ORGANISATION OF PROCURING ENTITIES cont’d
Procurement committee• Procurement committee established by as per
Section 26 (4)• Functions similar to those of the Tender
Committee but for procurement values below the Tender Committees thresholds.
• Approve, reject or approve subject to clarifications submissions by the procurement unit.
• Alternate members with adequate experience to be appointed
• Quorum-Chairman and at least two other members.
13
PART II INTERNAL ORGANISATION OF PROCURING ENTITIES cont’d
Establishment of Procurement Unit• Summary of responsibilities Maintaining and updating registered list of tenderers. Preparing and publishing procurement opportunities Managing the whole procurement and disposal
process including inventory management Advising the entire PE on aggregation of
procurement to promote economies of scale Coordinating internal monitoring and evaluation of
the supply chain function Verifying that available stock levels warrant initiation
of procurement process.
14
PART II INTERNAL ORGANISATION OF PROCURING ENTITIES cont’d
Evaluation committee• To be formed for each procurement with threshold of
tender committee • It is advised that procurements within the
threshold for the procurement committee also warrant some evaluation for effective adjudication by the Procurement Committee
• To comply with the evaluation procedures –Section 66(3) i.e.”
• Using procedures and criteria in the tender documents.• No other criteria to be used• The criteria must be to the extent possible be objective
and quantitative
15
PART II INTERNAL ORGANISATION OF PROCURING ENTITIES cont’d
Evaluation committee cont’d• Criteria (as stipulated in the bid document) to
be expressed taking into account price, quality and service to enhance effective evaluation
• Evaluation may be by by Technical Committee and Financial Committee
• Technical Evaluation to be completed within30 days
• Financial Evaluation Committee to complete the exercise within 5 days after completion of technical evaluation
16
PART II INTERNAL ORGANISATION OF PROCURING ENTITIES cont’d
Inspection and Acceptance Committee• Composed of Chairman and at least two other
members• To inspect ,test goods to ensure correctness of
quantity, and compliance with specifications.• To ensure effectiveness in completion of
works and services as well.• Ensure required manuals and documents are
submitted• Issue interim or a complete certificate or reject
goods, works or services
17
Transfer of procurement responsibility
• By the Authority to:Procuring agents.Or another Procuring EntityA procuring agent shall pay a registration
fee of Ksh.20,000 to the authority.
• This role is also vested in the Accounting Officer but remains responsible.
PART II CONTD.
18
PART II CONTD. Procurement planning Reg.20(1) to(5) pursuant
to Section 26(3)(a)( b) and (c) of the Regulations
• Plan to be integrated in the applicable budgetary processes and based on indicative and approved budget as appropriate
• Where appropriate Multi-year procurement plans may be prepared and shall be integrated into the medium term expenditure framework (MTEF)
• A head of department shall submit procurement plan to Accounting Officer at least 30 days before the close of each financial year
19
PART II CONTD.
• Procurement planning cont’d• Consolidated plan to be approved by the
Head of the procuring entity and where applicable by the Board of Directors or similar body.
• Note: Role of Board of Directors in PPOA’s circular Ref:PPD.4/07Vol.1/(47) dated 2nd February 2007
20
PART II CONTD.Procurement plans shall include:• A breakdown of goods, works or services • A schedule of planned delivery, implementation
or completion dates• An indication and justification for whether an
procurement shall be undertaken within a single year or under a multi-year arrangement.
• An indication of which items can be aggregated for a procurement a single package or for procurement through any applicable arrangement for common user items
21
PART II CONTD.Procurement plans shall include • An indication of which items will be packaged
into lots• An estimate of value of each package of
goods, works or services. • The budgets available and sources of funds• Procurement method for each procurement • Format to be provided by PPOANB: But it is advised that you do not wait for the
format-use an appropriate one to capture the above and others necessary information.
22
PART II CONTD.
Purchase requisition and authorization.• Requisitions to have estimates that reflect up-to-date information on economic and
market conditions.• Approval as per First Schedule of the
Regulations -the Threshold Matrix.• Procurement unit to prepare plan for each individual requirement to include TIME for
each stage in the procurement cycle.
23
PART III GENERAL PROCUREMENT RULES
• Prequalification procedure.Candidates to be allowed 14 days to prepare and
submit application( for specific procurement).Maintain and update a list( for future purchases)• Procuring entity shall maintain and update a list of
suppliers –Section39 (7)• Procuring approvals.• A procuring entity shall maintain specimen
signatures of all persons authorised to make approvals in the procurement process
24
PART III GENERAL PROCUREMENT RULES• Restrictions-Limitation on contract with employees and
relatives etc by PE ( Reg.26 ) For purpose of section 33 (2) of the Act relative is limited to
spouse and child.• Conflict of interest -Pursuant to Section 43• An employee or agent of PE or member of Committee, Board,
shall no take part in the proceedings or on any matter to do with the contract awarded to a relative
• A relative means:A spouse child, parent brother or sisterA child. parent brother or sister of a spouse or any prescribed relative.NB: Note the relationship between this provision with
limitation to entering into contract with persons under Section 33 and 43 of the Act
25
Preferences and Reservation-Section 39(8) (a) &(b)Preferences to citizens of Kenya-Applicable thresholds for:Goods and services Kshs. 50 M.Works Kshs. 200M.Section 39(8) (b) (i) goods manufactured, mined extracted and
grown in Kenya– margin of preference :15% orSection 39(8) (b) (ii) works, goods and service where
preference may be applied depending on shareholding as follows:
- Less than 20% shareholding-margin of preference :6% -Less than 50% shareholding -margin of preference: 8%
PART III CONTD. 1
26
PART III CONTD. Tender documents – Third schedule.1. Standard tender document for design
construction, supply, installation, testing commissioning and handing over of plant/project (turnkey project.)
2. Standard tender document for supply installation and commissioning of plant and equipment.
3 Standard tender document for prequalification of procurement candidates.
4 Standard tender document for procurement of works (Roads, Bridges, Water and other Civil Engineering works).
27
PART III CONTD.
Tender documents – Third schedule.5 Standard tender document for procurement
of works (small works6 Standard tender document for procurement
of Works (Buildings and associated civil engineering Works)
7 Standard tender document for procurement of works. (Electrical and mechanical works)
8 Standard tender document for procurement of goods.
28
PART III CONTD. Tender documents co9 Standard tender document for
procurement of insurance services10 Standard tender document for
procurement of services11 Standard tender document for letting,
leasing, licensing, tenancy, franchise and management contracting.
12 Standard request for proposals (RFP) (Selection of consultants
29
PART III CONTD.
Tender documents cont’d13 Standard tender document for Request
for Proposals (RFP) (selection of
individual professional consultants14 Standard tender document for sale of
boarded stores and equipment.• The standard tender documents are
usually customized by purchasers.
30
PART III GENERAL PROCUREMENT RULES cont’d
• Contract Administration• The Act covers contract management Section 4(1)
of the Act and detailed in the Regulations in respect of:
Price variation to be based on prevailing consumer price index obtained from CBS or the monthly inflation rate issued by CBK
Quantity variation for goods and services not to exceed 10% of the original contract quantity.
Quantity (bill of quantities /scope of works) variation for works not to exceed 15% of the original contract quantity.
31
PART III GENERAL PROCUREMENT RULES cont’d
• Contract AdministrationContract termination.Grounds and procedures for termination to be specified in
the contractThe request for termination to be made by procurement
unit for the tender committee approval prior to terminationThe request for termination to includeReasons for terminationContractual grounds for termination andCost of termination Discussion: How can costs of contract termination be
avoided or minimized?
32
PART IV OPEN TENDERING
• Threshold for Open tendering advertisement
CLASS GOODS WORKS SERVICES
A 6000000/- 6000000/- 3000000/-
B 4000000/- 4000000/- 2000000/--
C 3000000/- 3000000/ 1000000/
33
PART IV OPEN TENDERING
• Advertisement period. ICB – 30 days minimum NCB – 21 days minimum.• Evaluation of tenders Preliminary Evaluation Technical Evaluation Financial Evaluation Evaluation within 30 days after opening of
tenders. See timeframe for Technical and Financial evaluation above
34
Issuance of Tender Documents• Fee for tender documents
– Not to Exceed Ksh 5,000.
Tender Security– Not to exceed 2% of the estimated value of
contract.– Insurance company guarantee acceptable if
approved by the Authority.
PART IV CONTD.
35
PART V – ALTERNATIVE PROCUREMENT METHODS.
• Restricted Tendering.• Request for proposals.• Request for quotations.• Direct procurement.• Low value procurement .• Specially permitted procedure. -It is important to know the following: -When a procedure may be used -Have prior approval of the Tender committee. For choice of procurement methods –see Matrix
Presentation
36
PART V CONTD. Award of contract ( As per the first schedule-
the Matrix)• By Tender /Procurement Committee depending
on threshold for each class of PE• By user in case of Low Value Procurement• Notification of award:To successful tenderers as well as unsuccessful
tenderes. After notification of award where an unsuccessful
tenderer requests a procuring entity shall within 14 days after a request provide written reasons as to why the tenderer was unsuccessful
37
PART VI - ADMINISTRATIVE REVIEW OF PROCUREMENTS AND PROCEEDINGS
• Composition of membership of Review Board• The Director General shall appoint from amongst the
staff of the Authority to be the secretary to the Review Board
• To be appointed for a term of three years• The membership to be six appointed from the names
submitted by 13 professional bodies and COTU• Three other persons appointed by the Minister• A Chairman appointed by the Minister from six
persons referred above.• Procedures in review (Refer to presentations for the
Overview of the ACT)
38
Part VII INVESTIGATION, DEBARMENT AND DISPOSAL• Investigation.
Investigator pursuant to section103 not to advice PE on matters being investigated.
• DebarmentThe Director General with the approval of the
Advisory Board may debar a person from participating in procurement proceedings on the ground that the person has breached a code of ethics (s.139 of the Act)
Where a person is debarred from participating in procurement proceeding as under section 115 of the Act, the debarment extends to any firm in which a person has a controlling interest
39
PART VII CONTD.• Disposal As recommended by disposal committee May be by : Sale by Open tender Transfer to another public entity or part of
public entity with or without financial adjustment Sale by public auction Destruction, dumping or burying Trade-in
40
PART VII CONTD. Disposal cont’d• Disposal to employees When: Time and cost required to dispose to any other person
would be disproportionate to the value of the item
The employee is in the possession of the stores or equipment to be disposed of and may be given the firstly priority to purchase the same
Any disposal made to staff should be reported to the authority within 14 days of the disposal by the accounting officer
41
SCHEDULES
• First - Threshold matrix• Second – Composition of Tender Committee• Third – Standard tender documents• Fourth – Review forms and fees for review
42
Never decide to do nothing just because
you can do a little
Do the little you can
Thank you!
43
END
DISCUSSIONS
“THANK YOU”