2-4c a-01 1:100 › downloadfile › 2 storey 4 rooms... · 3. read this drawing along with other...
TRANSCRIPT
-
A-01
Consultant:
Project Title:
Type Design :
Sheet Title :
2 STOREY 4 CLASSROOM
Sheet No.GROUND FLOOR PLAN &
2-4C
Print Sheet : A'3' Size0 1M 2M 3M 4M
5M
1:100
3. Read this drawing along with other related drawings
and other services drawings.
unless otherwise indicated.
2. Drawing are not to be directly measured.reported to the consultant or concerned engineer.
1. Any discrepancy in the drawing to be immediately
and coordinate with Structural, Electrical, Plumbing
5. Provide threshold at all exterior doors as per details,
4. Refer doors & windows schedule/elevations for sizeof doors & windows
NOTES:
6. The location of ramps to be adjusted as per site condition.
German Development Cooperation (giz)
ELEVATION
Date : May, 2016
Recovery Programme Nepal (RPN)School Recovery Project
Name of School :
Dandagaun, Rasuwa,Nepal
-
0 1M 2M 3M 4M
5M
1:100
A-02
Consultant:
Project Title:
Type Design :
Sheet Title :
2 STOREY 4 CLASSROOM
Sheet No.FIRST FLOOR PLAN &
2-4C
Print Sheet : A'3' Size
German Development Cooperation (giz)
ROOF PLAN
0 0.4M 0.8M 1.2M 1.6M
2M
1:40
3. Read this drawing along with other related drawings
and other services drawings.
unless otherwise indicated.
2. Drawing are not to be directly measured.reported to the consultant or concerned engineer.
1. Any discrepancy in the drawing to be immediately
and coordinate with Structural, Electrical, Plumbing
5. Provide threshold at all exterior doors as per details,
4. Refer doors & windows schedule/elevations for sizeof doors & windows
NOTES:
6. The location of ramps to be adjusted as per site condition.
Date : May, 2016
Recovery Programme Nepal (RPN)School Recovery Project
Name of School :
Dandagaun, Rasuwa,Nepal
-
0 1M 2M 3M 4M
5M
1:100
3. Read this drawing along with other related drawings
and other services drawings.
unless otherwise indicated.
2. Drawing are not to be directly measured.reported to the consultant or concerned engineer.
1. Any discrepancy in the drawing to be immediately
and coordinate with Structural, Electrical, Plumbing
5. Provide threshold at all exterior doors as per details,
4. Refer doors & windows schedule/elevations for sizeof doors & windows
NOTES:
6. The location of ramps to be adjusted as per site condition.
A-03
Consultant:
Project Title:
Type Design :
Sheet Title :
2 STOREY 4 CLASSROOM
Sheet No.ELEVATIONS & SECTION
Print Sheet : A'3' Size
German Development Cooperation (giz)
0 0.25M 0.5M 0.75M 1M1.25M
1:25
2-4C
Date : May, 2016
Recovery Programme Nepal (RPN)School Recovery Project
Name of School :
Dandagaun, Rasuwa,Nepal
-
3. Read this drawing along with other related drawings
and other services drawings.
unless otherwise indicated.
2. Drawing are not to be directly measured.reported to the consultant or concerned engineer.
1. Any discrepancy in the drawing to be immediately
and coordinate with Structural, Electrical, Plumbing
5. Provide threshold at all exterior doors as per details,
4. Refer doors & windows schedule/elevations for sizeof doors & windows
NOTES:
6. The location of ramps to be adjusted as per site condition.
A-04
Consultant:
Project Title:
Type Design :
Sheet Title :
2 STOREY 4 CLASSROOM
Sheet No.WALL SECTION AND DETAIL
Print Sheet : A'3' Size
German Development Cooperation (giz)
2-4C
Date : May, 2016
Recovery Programme Nepal (RPN)School Recovery Project
Name of School :
Dandagaun, Rasuwa,Nepal
0 0.4M 0.8M 1.2M 1.6M
2M
1:40
-
0 0.25M 0.5M 0.75M 1M
1.25M
1:25
3. Read this drawing along with other related drawings
and other services drawings.
unless otherwise indicated.
2. Drawing are not to be directly measured.reported to the consultant or concerned engineer.
1. Any discrepancy in the drawing to be immediately
and coordinate with Structural, Electrical, Plumbing
5. Provide threshold at all exterior doors as per details,
4. Refer doors & windows schedule/elevations for sizeof doors & windows
NOTES:
6. The location of ramps to be adjusted as per site condition.
A-05
Consultant:
Project Title:
Type Design :
Sheet Title :
2 STOREY 4 CLASSROOM
Sheet No.DOOR WINDOW DETAILS
Print Sheet : A'3' Size
German Development Cooperation (giz)
2-4C
Date : May, 2016
Recovery Programme Nepal (RPN)School Recovery Project
Name of School :
Dandagaun, Rasuwa,Nepal
-
A-06
Consultant:
Project Title:
Type Design :
Sheet Title :
2 STOREY 4 CLASSROOM
Sheet No.STAIRCASE DETAILS
Print Sheet : A'3' Size
German Development Cooperation (giz)
2-4C
Date : May, 2016
Recovery Programme Nepal (RPN)School Recovery Project
Name of School :
Dandagaun, Rasuwa,Nepal
0 0.4M 0.8M 1.2M 1.6M2M
1:40
0 0.2M 0.4M 0.8M 1M1.2M
1:20
-
S-00
Consultant:
Project Title:
Type Design :
Sheet Title :
2 STOREY 4 CLASSROOM
Sheet No.GENERAL NOTES &
2-4C
Print Sheet : A'3' Size
3. Read this drawing along with other related drawings
and other services drawings.
unless otherwise indicated.
2. Drawing are not to be directly measured.reported to the consultant or concerned engineer.
1. Any discrepancy in the drawing to be immediately
and coordinate with Structural, Electrical, Plumbing
5. Provide threshold at all exterior doors as per details,
4. Refer doors & windows schedule/elevations for sizeof doors & windows
NOTES:
6. The location of ramps to be adjusted as per site condition.
German Development Cooperation (giz)
TYPICAL DETAILS
Date : May, 2016
Recovery Programme Nepal (RPN)School Recovery Project
Dandagaun, Rasuwa,Nepal
-
S-01
Consultant:
Project Title:
Type Design :
Sheet Title :
2 STOREY 4 CLASSROOM
Sheet No.FOUNDATION DETAILS
2-4C
Print Sheet : A'3' Size
3. Read this drawing along with other related drawings
and other services drawings.
unless otherwise indicated.
2. Drawing are not to be directly measured.reported to the consultant or concerned engineer.
1. Any discrepancy in the drawing to be immediately
and coordinate with Structural, Electrical, Plumbing
5. Provide threshold at all exterior doors as per details,
4. Refer doors & windows schedule/elevations for sizeof doors & windows
NOTES:
6. The location of ramps to be adjusted as per site condition.
German Development Cooperation (giz)
0 1M 2M 3M 4M5M
1:100
0 0.25M 0.5M 0.75M 1M1.25M
1:25
0 0.2M 0.4M 0.6M 0.8M1M
1:20
Date : May, 2016
Recovery Programme Nepal (RPN)School Recovery Project
Name of School :
Dandagaun, Rasuwa,Nepal
-
S-02
Consultant:
Project Title:
Type Design :
Sheet Title :
2 STOREY 4 CLASSROOM
Sheet No.COLUMN, SILL & LINTEL
2-4C
Print Sheet : A'3' Size
3. Read this drawing along with other related drawings
and other services drawings.
unless otherwise indicated.
2. Drawing are not to be directly measured.reported to the consultant or concerned engineer.
1. Any discrepancy in the drawing to be immediately
and coordinate with Structural, Electrical, Plumbing
5. Provide threshold at all exterior doors as per details,
4. Refer doors & windows schedule/elevations for sizeof doors & windows
NOTES:
6. The location of ramps to be adjusted as per site condition.
German Development Cooperation (giz)
0 1M 2M 3M 4M5M
1:100
0 0.25M 0.50M 0.75M 1M
1:25
DETAILS
1.25M
Date : May, 2016
Recovery Programme Nepal (RPN)School Recovery Project
Name of School :
Dandagaun, Rasuwa,Nepal
-
S-03
Consultant:
Project Title:
Type Design :
Sheet Title :
2 STOREY 4 CLASSROOM
Sheet No.BEAM PLAN AND VERTICAL
2-4C
Print Sheet : A'3' Size
3. Read this drawing along with other related drawings
and other services drawings.
unless otherwise indicated.
2. Drawing are not to be directly measured.reported to the consultant or concerned engineer.
1. Any discrepancy in the drawing to be immediately
and coordinate with Structural, Electrical, Plumbing
5. Provide threshold at all exterior doors as per details,
4. Refer doors & windows schedule/elevations for sizeof doors & windows
NOTES:
6. The location of ramps to be adjusted as per site condition.
German Development Cooperation (giz)
0 1M 2M 3M 4M5M
1:100
METAL POST DETAIL0 0.1M 0.2M 0.3M 0.4M
0.5M
1:10
Date : May, 2016
Recovery Programme Nepal (RPN)School Recovery Project
Name of School :
Dandagaun, Rasuwa,Nepal
-
S-04
Consultant:
Project Title:
Type Design :
Sheet Title :
2 STOREY 4 CLASSROOM
Sheet No.BEAM SECTION DETAILS
2-4C
Print Sheet : A'3' Size
3. Read this drawing along with other related drawings
and other services drawings.
unless otherwise indicated.
2. Drawing are not to be directly measured.reported to the consultant or concerned engineer.
1. Any discrepancy in the drawing to be immediately
and coordinate with Structural, Electrical, Plumbing
5. Provide threshold at all exterior doors as per details,
4. Refer doors & windows schedule/elevations for sizeof doors & windows
NOTES:
6. The location of ramps to be adjusted as per site condition.
German Development Cooperation (giz)
0 0.25M 0.50M 0.75M 1M1.25M
1:25
0 0.5M 1M 1.5M 2M
1:50
2.5M
Date : May, 2016
Recovery Programme Nepal (RPN)School Recovery Project
Name of School :
Dandagaun, Rasuwa,Nepal
-
S-05
Consultant:
Project Title:
Type Design :
Sheet Title :
2 STOREY 4 CLASSROOM
Sheet No.BEAM SECTION DETAILS
2-4C
Print Sheet : A'3' Size
3. Read this drawing along with other related drawings
and other services drawings.
unless otherwise indicated.
2. Drawing are not to be directly measured.reported to the consultant or concerned engineer.
1. Any discrepancy in the drawing to be immediately
and coordinate with Structural, Electrical, Plumbing
5. Provide threshold at all exterior doors as per details,
4. Refer doors & windows schedule/elevations for sizeof doors & windows
NOTES:
6. The location of ramps to be adjusted as per site condition.
German Development Cooperation (giz)
0 0.25M 0.50M 0.75M 1M1.25M
1:25
0 0.5M 1M 1.5M 2M
1:50
2.5M
Date : May, 2016
Recovery Programme Nepal (RPN)School Recovery Project
Name of School :
Dandagaun, Rasuwa,Nepal
-
S-06
Consultant:
Project Title:
Type Design :
Sheet Title :
2 STOREY 4 CLASSROOM
Sheet No.SLAB DETAILS
2-4C
Print Sheet : A'3' Size
3. Read this drawing along with other related drawings
and other services drawings.
unless otherwise indicated.
2. Drawing are not to be directly measured.reported to the consultant or concerned engineer.
1. Any discrepancy in the drawing to be immediately
and coordinate with Structural, Electrical, Plumbing
5. Provide threshold at all exterior doors as per details,
4. Refer doors & windows schedule/elevations for sizeof doors & windows
NOTES:
6. The location of ramps to be adjusted as per site condition.
German Development Cooperation (giz)
0 0.25M 0.50M 0.75M 1M1.25M
1:25
0 1M 2M 3M 4M
1:100
5M
Date : May, 2016
Recovery Programme Nepal (RPN)School Recovery Project
Name of School :
Dandagaun, Rasuwa,Nepal
-
S-07
Consultant:
Project Title:
Type Design :
Sheet Title :
2 STOREY 4 CLASSROOM
Sheet No.STAIRCASE DETAILS
2-4C
Print Sheet : A'3' Size
3. Read this drawing along with other related drawings
and other services drawings.
unless otherwise indicated.
2. Drawing are not to be directly measured.reported to the consultant or concerned engineer.
1. Any discrepancy in the drawing to be immediately
and coordinate with Structural, Electrical, Plumbing
5. Provide threshold at all exterior doors as per details,
4. Refer doors & windows schedule/elevations for sizeof doors & windows
NOTES:
6. The location of ramps to be adjusted as per site condition.
German Development Cooperation (giz)
0 0.4M 0.8M 1.2M 1.6M2M
1:40
Date : May, 2016
Recovery Programme Nepal (RPN)School Recovery Project
Name of School :
Dandagaun, Rasuwa,Nepal
-
S-08
Consultant:
Project Title:
Type Design :
Sheet Title :
2 STOREY 4 CLASSROOM
Sheet No.TRUSS DETAILS
2-4C
Print Sheet : A'3' Size
3. Read this drawing along with other related drawings
and other services drawings.
unless otherwise indicated.
2. Drawing are not to be directly measured.reported to the consultant or concerned engineer.
1. Any discrepancy in the drawing to be immediately
and coordinate with Structural, Electrical, Plumbing
5. Provide threshold at all exterior doors as per details,
4. Refer doors & windows schedule/elevations for sizeof doors & windows
NOTES:
6. The location of ramps to be adjusted as per site condition.
German Development Cooperation (giz)
Date : May, 2016
Recovery Programme Nepal (RPN)School Recovery Project
Name of School :
Dandagaun, Rasuwa,Nepal
0 1M 2M 3M 4M5M
1:100
0 0.4M 0.8M 1.2M 1.6M2M
1:40
-
S-09
Consultant:
Project Title:
Type Design :
Sheet Title :
2 STOREY 4 CLASSROOM
Sheet No.TRUSS DETAIL
2-4C
Print Sheet : A'3' Size
3. Read this drawing along with other related drawings
and other services drawings.
unless otherwise indicated.
2. Drawing are not to be directly measured.reported to the consultant or concerned engineer.
1. Any discrepancy in the drawing to be immediately
and coordinate with Structural, Electrical, Plumbing
5. Provide threshold at all exterior doors as per details,
4. Refer doors & windows schedule/elevations for sizeof doors & windows
NOTES:
6. The location of ramps to be adjusted as per site condition.
German Development Cooperation (giz)
0 100MM 200MM 300MM 400MM500MM
1:10
Date : May, 2016
Recovery Programme Nepal (RPN)School Recovery Project
Name of School :
Dandagaun, Rasuwa,Nepal
-
S-10
Consultant:
Project Title:
Type Design :
Sheet Title :
2 STOREY 4 CLASSROOM
Sheet No.TRUSS DETAILS
2-4C
Print Sheet : A'3' Size
3. Read this drawing along with other related drawings
and other services drawings.
unless otherwise indicated.
2. Drawing are not to be directly measured.reported to the consultant or concerned engineer.
1. Any discrepancy in the drawing to be immediately
and coordinate with Structural, Electrical, Plumbing
5. Provide threshold at all exterior doors as per details,
4. Refer doors & windows schedule/elevations for sizeof doors & windows
NOTES:
6. The location of ramps to be adjusted as per site condition.
German Development Cooperation (giz)
0.5M0 0.1M 0.2M 0.3M 0.4M
1:10
0.25M0 0.05M 0.10M 0.15M 0.20M
1:5
Date : May, 2016
Recovery Programme Nepal (RPN)School Recovery Project
Name of School :
Dandagaun, Rasuwa,Nepal
-
EI-01
Sub-Consultant:
Project Title:
Type Design :
Sheet Title :
2 STOREY 4 CLASSROOM
Sheet No.LIGHT, POWER LAYOUT PLAN
2-4C
Print Sheet : A'3' Size0 1M 2M 3M 4M
5M
1:100
3. Read this drawing along with other related drawings
and other services drawings.
unless otherwise indicated.
2. Drawing are not to be directly measured.reported to the consultant or concerned engineer.
1. Any discrepancy in the drawing to be immediately
and coordinate with Structural, Electrical, Plumbing
5. Provide threshold at all exterior doors as per details,
4. Refer doors & windows schedule/elevations for sizeof doors & windows
NOTES:
6. The location of ramps to be adjusted as per site condition.
German Development Cooperation (giz)
& MAIN PANEL BOARD(GROUND FLOOR PLAN)
Recovery Programme Nepal (RPN)School Recovery Project
Name of School :
Dandagaun, Rasuwa,Nepal
Date : May, 2016
-
EI-02
Sub-Consultant:
Project Title:
Type Design :
Sheet Title :
2 STOREY 4 CLASSROOM
Sheet No.LIGHT, POWER LAYOUT PLAN
2-4C
Print Sheet : A'3' Size0 1M 2M 3M 4M
5M
1:100
3. Read this drawing along with other related drawings
and other services drawings.
unless otherwise indicated.
2. Drawing are not to be directly measured.reported to the consultant or concerned engineer.
1. Any discrepancy in the drawing to be immediately
and coordinate with Structural, Electrical, Plumbing
5. Provide threshold at all exterior doors as per details,
4. Refer doors & windows schedule/elevations for sizeof doors & windows
NOTES:
6. The location of ramps to be adjusted as per site condition.
German Development Cooperation (giz)
(FIRST FLOOR PLAN)
Recovery Programme Nepal (RPN)School Recovery Project
Name of School :
Dandagaun, Rasuwa,Nepal
Date : May, 2016