2. execution and commissioning

Upload: alo3m

Post on 10-Apr-2018

224 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/8/2019 2. Execution and Commissioning

    1/49

    PhotovoltaicSystemsTraining

    Session2

    Execution

    and

    Commissioning

    http://www.leonardo-energy.org/training-pv-systems-design-

    construction-operation-and-maintenance

    JavierRelancio&LuisRecuero

    GeneraliaGroup

    September16th 2010

  • 8/8/2019 2. Execution and Commissioning

    2/49

    PHOTOVOLTAICSYSTEM

    Design,Execution,Operation&Maintenance

    EXECUTIONANDCOMMISSIONING

    JavierRelancio.GeneraliaGroup. 16/09/2010

    www.generalia.es2

    http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance

  • 8/8/2019 2. Execution and Commissioning

    3/49

    INDEX

    Civil works. Infrastructure preparation

    Mechanical works

    Electrical works

    Environmental issues

    Quality. Critical issues during execution

    Safety & Labor risks

    Commissioning tests. Key points

    3http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance

  • 8/8/2019 2. Execution and Commissioning

    4/49

    INDEX

    Civil works. Infrastructure preparation

    Mechanical works

    Electrical works

    Environmental issues

    Quality. Critical issues during execution

    Safety & Labor risks

    Commissioning tests. Key points

    4http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance

  • 8/8/2019 2. Execution and Commissioning

    5/49

    5

    Rooftop projects

    We may find little civil works, but it will be reduced to the trench

    opening for the connection of the inverters and the meters

    Ground projects

    Civil works are very important

    A good definition for the civil works could mean an important

    saving in the project.

    Main civil works are:

    Terrain leveling

    Accesses and inside roads/paths Trench opening (AC & DC)

    Civ i l W o r k s: I n f r as t r u ctu r e p r epar a t i on

    http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance

  • 8/8/2019 2. Execution and Commissioning

    6/49

    6

    Ter r a in leve l ing

    It might be avoided as much as possible in order to reduce the environmental impact

    Only required works should be done:

    Selecting a flat terrain may avoid its leveling

    Selecting a structure type which can be fixed to the terrain by a ground anchor, instead

    of a concrete base

    Depending on the solution design, the choice between fixed or suntracking project can be

    determinant

    Source: QHOELET

    http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance

  • 8/8/2019 2. Execution and Commissioning

    7/49

    7

    I n t er n a l r oa d s & p a t h s

    It is recommended to use already existing paths

    We must take into account that the roads or paths have to allow the circulation of

    trucks. Truck turning radius must be considered:

    Vehicle Type Nomenclature Height Width LengthLength

    betweenaxis

    Minimum radius forexternal front-

    wheel

    Minimum radiusfor internal back-

    wheel

    Light vehicle VL 1,30 2,10 5,80 3,40 7,30 4,20

    2-Axis Omnibus B2 4,10 2,60 9,10 6,10 12,80 8,50

    3-Axis Omnibus B3 4,10 2,60 12,10 7,60 12,80 7,40

    2-Axis simple truck C2 4,10 2,60 9,10 6,10 12,80 8,50

    3-Axis simple truck C3 / C4 4,10 2,60 12,20 7.6 12,80 7,40

    Trailer (Semi) T2S1/ 2 / 3 4,10 * 2,60 15,204,00 /7,00

    12,20 5,80

    Trailer (Semi) T3S1 / 2 / 3 4,10 2,60 16,704,90 /

    7,9013,70 5,90

    2 Axis trailer + 1 Double C2 - R2 / 3 4,10 2,60 19,903,80 /6,10 /6,40

    13,70 6,80

    3 Axis trailer + 1 DoubleC3 - R2 / 3 /

    44,10 2,60 19,90

    3,80 /6,10

    /6,4013,70 6,80

    http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance

  • 8/8/2019 2. Execution and Commissioning

    8/49

    8

    Once the installation has been commissioned, internal paths & roads will not be used too

    much, so a 25 cm depth path of a mixture 75% gravel, 25 % river sand, may be enough.

    I n t er n a l r oa d s & p a t h s

    Minimal turning radius forB3/C3 vehicles

    Accesses and roads/paths detail

    75% gravel, 25 % river sand

    Natural terrain

    http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance

  • 8/8/2019 2. Execution and Commissioning

    9/49

    9

    Trenches

    In a PV project, all the cable must be buried underground

    Each 40 meters or each direction change, a manhole will be placed to ease the cable

    laying

    The project design might try to use the same section for all the trenches

    http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance

  • 8/8/2019 2. Execution and Commissioning

    10/49

    10

    Trenches

    The trenches will have:

    A river sand base

    Space for the pipes

    Backfill of sifted soil and soft sand

    Cable caution tape

    In the case it is a vehicle passingarea, it will have a concrete layer

    at the top

    http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance

  • 8/8/2019 2. Execution and Commissioning

    11/49

    INDEX

    Civil works. Infrastructure preparation

    Mechanical works

    Electrical works

    Environmental issues

    Quality. Critical issues during execution

    Safety & Labor risks

    Commissioning tests. Key points

    11http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance

  • 8/8/2019 2. Execution and Commissioning

    12/49

    12

    Mechan ical w o rk s

    Structuretype Weight Anticorrosionprotection Mechanical

    performance

    Galvanizedsteel Resistantrooftops 8years(nonsaltyatmosphere) Good

    Hotgalvanizedsteel Resistantrooftops Morethan25years Good

    AnodizingAluminum Light

    rooftops More

    than

    20

    years Medium

    Nostructure Lightrooftops

    For fixed installations, the structure can be set parallel to the surface

    where it is to be installed (flat), or with the optimum tilt for each

    latitude (Tilted)

    Flat Tilted

    Nowind action Important windaction

    Worse cooling Bestnatural cooling

    Lowercost(Bothforstructure&

    mounting)

    Highercost(Bothforstructure&

    mounting)

    Photo: Krannich

    http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance

  • 8/8/2019 2. Execution and Commissioning

    13/49

    13

    Mechan ical w o rk s

    The structure anchor for a ground installation may

    have the following possibilities:

    Ground anchor

    These screws have an average length

    between 1 -1,6 meters

    Easy to be dismounted

    They can be adapted to the terrain orography

    They cant be used in a rocky terrain

    Concrete basement

    Above or under the ground

    It requires a flat surface

    Easy to be dismounted (if it is above the

    ground)

    Source: Conectavol

    http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance

  • 8/8/2019 2. Execution and Commissioning

    14/49

    14

    Roof anchor age

    Metal roof anchors:

    We have two options:

    Direct to purlins anchorage

    Specially designed anchors to be fixed directly to the roof

    sheathing

    I t i s r ecom m ended t o use t he d i r ect t o pu r l i n ancho r age . I f

    t i l t ed s t ruc tu re i s be ing used , o th e r cho i ce cou ld be r i sky .

    Tile roof anchorage:

    A typical solution is using a U shaped piece which is

    anchored directly to the roof, avoiding to drill the tile

    It is necessary to move the tiles (danger of leaks)

    With a special piece we can go through the tile

    Danger to break the tile

    Source: SoportesSolares

    http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance

  • 8/8/2019 2. Execution and Commissioning

    15/49

    15

    Roof state:

    The following aspects are to be evaluated:

    Safety We have to verify if the roof is safe. If not, we may install lifeline, skylight

    network

    Roof type

    Asbestos (Uralita) roofs are the most difficult ones, as it may be cracked by

    stepping on it, producing leaks, or it could even be broken, being really risky for

    the installers. In this case, it is recommended to change the whole roof to metal

    roof.

    PV Roo f s

    Sealing

    It is important to use the most indicated sealing to avoid

    leaking. This sealers must have great elasticity and good

    mechanical resistance. They may be complemented by

    EPDM* bands

    * a type of synthetic rubber (e thy l ene p r opy l ene d i ene M onom er )

  • 8/8/2019 2. Execution and Commissioning

    16/49

    16

    Loads on the roof

    Material weight (average weight by square meter)

    Wind effect

    During the design, both panel height and exposed surface must be considered

    Extra loads during the execution: such us tools, workers, materials

    Accesses: The accesses will be distributed all along the roof surface, guaranteeing the

    worker safety and allowing them to carry up small materials and tools

    PV Roo f s

    Element Weight

    Structure 2KG

    Crystallinepanels 15KG

    Thinfilm glassglasspanel 22KG

    Thinfilmlaminatedpanel 6KG

    http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance

  • 8/8/2019 2. Execution and Commissioning

    17/49

    INDEX

    Civil works. Infrastructure preparation

    Mechanical works

    Electrical works

    Environmental issues

    Quality. Critical issues during execution

    Safety & Labor risks

    Commissioning tests. Key points

    17http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance

  • 8/8/2019 2. Execution and Commissioning

    18/49

    18

    Elect r i cal w o rk s

    Cable for the panel strings

    We usually use the cable included by the panel manufacturers.

    Important to confirm with the manufacturer that this cable is included

    This cable are composed of copper: 4mm; 0,6/1kV

    This cables usually are ended in fast connectors: Multicontact,

    Tyco, etc

    Source: Eastech Solar

    http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance

  • 8/8/2019 2. Execution and Commissioning

    19/49

    19

    Elect r i cal w o rk s

    Roof installations

    Cable canalization might be done under hot galvanized cable tray or tubular conduit

    Cable tray canalization simplifies mounting works, and eases the maintenance tasks.

    Indoor, plastic(or metallic) cable tray might be used, as well as halogen-free cable

    http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance

  • 8/8/2019 2. Execution and Commissioning

    20/49

    20

    Elect r i cal w o rk s

    Ground installations

    Electrical works will be done in the trenches, so the cable must be designed for this use.

    It is recommended to use anti-mice cable, inside a tubular conduit.

    Cable trenches might be really long, so the

    trench design, number of cables by pipeline,

    extra space by pipeline, manholes, etc.. could

    be decisive to optimize the electrical works

    duration

    The cable should be previously marked in order

    to avoid connecting issues

    It is important to avoid corners or any element

    which may cause any damage in the cable

    isolation.

    http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance

  • 8/8/2019 2. Execution and Commissioning

    21/49

    21

    Elect r ica l cab inet s

    Depending on its location, a different IP may be required

    For outdoor installations, at least IP 65 will be required

    For indoor installations, IP 21 could be enough (except for special conditions: water,

    powder)I t i s r eal ly i m po r t an t t o pay a t t en t i on a t t he e l em en t connec t i ons , and t he

    i den t i f i cat i on o f each cab le & com ponen t i n t h e p ro jec t docum enta t i on

    The thermal study of the cabinet is also important, verifying the minimal required volume

    for the heat dissipation, and raising additional solutions as the incorporation of a heatresistance in case of outdoor installations in very cold zones

  • 8/8/2019 2. Execution and Commissioning

    22/49

    22

    Ear t h ing syst em

    The follow ing elements must be earth connected

    PV panel frameworks

    Structure Metal cable tray

    Metal elements in electrical cabinets

    PV inverters

    For small facilities, the earthing system would be quite

    simple: 2 3 pegs, depending on the soil resistivity

    For bigger facilities, a cable grid is usually implemented,

    using the trench already opened for the energy cables, placingan uncovered copper cable below the energy cables.

    The section of this cable is to be calculated during the design

    EARTHCABLE

    http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance

  • 8/8/2019 2. Execution and Commissioning

    23/49

    INDEX

    Civil works. Infrastructure preparation

    Mechanical works

    Electrical works

    Environmental issues

    Quality. Critical issues during execution

    Safety & Labor risks

    Commissioning tests. Key points

    23http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance

  • 8/8/2019 2. Execution and Commissioning

    24/49

    Nowadays we can find

    A change in the social sensibility for the environmental impacts. The society begins to

    have a greater conscience and a harder implication.

    This will be the real engine for the new environmental initiatives to be managed in a

    suitable way.

    The ISO Certification 14001, allows us to take and to show the others, our

    environmental commitment.

    For all this, the solar power companies should demonstrate the coherence with their

    ecological message, developing a good environmental policy

    24

    Our so lar f aci l i t y and t he env i r onm en t

    http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance

  • 8/8/2019 2. Execution and Commissioning

    25/49

    25

    Definitions (ISO 14001):

    Environmental aspect: Any element of the activities, products or services that is

    causing some type of impact on the environment can be considered as an

    environmental aspect.

    Environmental impact: Any change in the environment, either adverse or beneficial,

    resulting from the activities, products and services of an Organization.

    Residue: Any substance or object from which his holder detaches or has the obligation

    to become detached following the European rules & standards

    Env i ronm en t a l aspect s & im pact s

    http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance

  • 8/8/2019 2. Execution and Commissioning

    26/49

    We must take into account the environmental management of our so lar facility

    a. To know the in force legislation

    b. To know the environmental aspects that concern our business

    c. To evaluate the impact that has on the environment

    d. To propose indicators that give us a tangible evidence about the measured aspects,

    and their impacts, and to use them to develop new preventive and corrective

    measures

    e. To have an emergency plan derived from the knowledge of the different environmental

    aspects

    f. To do the suitable management of the generated residues

    26

    The environmental management becomes necessary in the execution, as well as the operation

    of the solar plant, therefore, an individual analysis of every project will be required

    Env i ronm en t a l aspect s & im pact s

    http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance

  • 8/8/2019 2. Execution and Commissioning

    27/49

    27

    1. List of aspects and impacts

    2. Emergency classification

    Activity Aspect N/E Impact

    PVinstallations(and

    Suntrackers,incase

    ofbeingused)

    Electric

    energy

    consumption N

    Atmosphericcontaminations

    VisualImpacts

    Fuelconsumption N Atmosphericpollution

    Powdergeneration N Atmosphericpollution

    Residuesgeneration N Spaceinthedumpsite

    Fire EAtmosphericpollution

    Impactonthefauna&flora.

    N: Normal; E: Extraordinary

    Exam p le: Env i r onm en ta l m anagem en t du r i ng t h e p r o j ect execu t i on

    Aspect P S ASignificant

    YES=Y;NO=N

    Fire 2 4 8 Y

    P: Probability; S: Seriousness; A: Assessment

    http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance

  • 8/8/2019 2. Execution and Commissioning

    28/49

  • 8/8/2019 2. Execution and Commissioning

    29/49

    EVENT/EMERGENCY: FIRE

    Preventive

    measures Adaptation

    to

    the

    electrical

    and

    construction

    regulations.

    Fire

    extinguishers.

    Actuationplan

    Theworkmanageristhepersoninchargeoftheextinctionoffire.

    Incaseofnoncontrollableemergency,theworkmanagerwilltakechargeof

    warningtheexternalemergencyservices.

    Theworkresponsibleisthepersoninchargeofgivingthealarmand

    controllingtheevacuationofthewholestaff.Hemustcheckthatthe

    evacuationhasbeencompleted

    Practice Fire

    Practicedescription

    Theresponsetimewillbemeasuredforthefollowingaspects:

    Thefirewarning.

    Staffevacuation.

    Thecheckingthattheevacuationhasbeencompleted.

    Frequency Yearly

    29

    4. Emergency plan

    Exam p le: Env i r onm en ta l m anagem en t du r i ng t h e p r o j ect execu t i on

    http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance

  • 8/8/2019 2. Execution and Commissioning

    30/49

    5. Residue management general process:

    In every moment, we must:

    To develop a study of the residues that are being produced, in the execution and theoperation of the solar power facility;

    To quantify the quantity of each one, and to do a management of the residue

    according to its type.

    30

    Urbanresidues Dangerousresidues

    Paper Tonerwithmetalliccomponents

    Plastic Batteries

    Tins &Cans Fluorescents

    Toner withoutmetalliccomponents Oils(Vehicles/Motors)

    Exam p le: Env i r onm en ta l m anagem en t du r i ng t h e p r o j ect execu t i on

    http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance

  • 8/8/2019 2. Execution and Commissioning

    31/49

    INDEX

    Civil works. Infrastructure preparation

    Mechanical works

    Electrical works

    Environmental issues

    Quality. Critical issues during execution

    Safety & Labor risks

    Commissioning tests. Key points

    31http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance

  • 8/8/2019 2. Execution and Commissioning

    32/49

    32

    Qual i t y : Cr i t i cal aspec ts

    The critical aspects referred to quality in the phase of execution are:

    Materials

    Checking that we have received the goods that have been requested

    Inspection of the goods at their arrival to check possible material faults/defects

    This process will be developed for a certain number of samples previously defined by the

    quality department

    The checking of the electrical and mechanical parameters of the material, to avoid earlybreakdowns

    Work execution

    Correct planning of the work: in order to avoid delays, dead times of the workers,

    managing the activities in critical way

    Updated documentation for the works: It is important to check that the workers have the

    latest edition of the information

    http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance

  • 8/8/2019 2. Execution and Commissioning

    33/49

    33

    WorkManager

    Qual i t y : Cr i t i cal aspec ts

    Material Administration Material Reception

    1.Checking that the items that have

    arrived correspond to the items of

    the delivery note

    2.Visual checking

    3.Checking of electrical and

    mechanical characteristics

    1.Checking that the items indicated in

    the delivery notes corresponds with

    the ordered ones

    2. Checking any lacking item in the

    order and claiming for it

    3. Checking the payments

    1.Checking that the ordered material fits

    with the projects real requirements

    2.Checking that the real project conditions

    matched with the project design

    3.Managing the material administration and

    reception

    http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance

  • 8/8/2019 2. Execution and Commissioning

    34/49

    34

    Work Manager

    Worker

    1. Work execution according to the

    work order

    2. To notify incidents in the

    accomplishment of the works

    3. Accomplishment of the checking

    indicated in the work order

    1. Fulfillment of the planning deadlines

    2. Checking the documentation of the

    work orders

    3. Checking the quality in the

    intermediate milestones of the project

    4. Checking the management of the

    residues during and at the end of the

    project

    5. Final checking of the work

    Qual i t y : Cr i t i cal aspec ts

    http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance

  • 8/8/2019 2. Execution and Commissioning

    35/49

    Samplesselection

    VISUAL ELECTRICAL THERMAL

    Packages

    PanelsOF

    DETECTIONOF

    Panel arrays Panels

    Frame defects

    Glass defects

    Connection box defects

    Cable & connector defects

    The electrical

    characteristics differ from

    the technical specs, used

    for the design and they

    are out of the required

    range

    Cell defects

    Hot spots

    Cell bubbles

    35

    Pane l inspec t ion s

    Although it might be true that the panels are the most expensive element in

    the installation, a similar table should be done for the rest of the elementshttp://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance

  • 8/8/2019 2. Execution and Commissioning

    36/49

    The Thermography is a simple method to detect defaults in the solar panels

    The checking of the installation is developed in a rapid and visual form

    It saves time, as it identifies directly the problematic panel without having to docomplex checks in the different strings

    36

    T he r mog r aphy

    http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance

  • 8/8/2019 2. Execution and Commissioning

    37/49

    INDEX

    Civil works. Infrastructure preparation

    Mechanical works

    Electrical works

    Environmental issues

    Quality. Critical issues during execution

    Safety & Labor risks

    Commissioning tests. Key points

    37http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance

  • 8/8/2019 2. Execution and Commissioning

    38/49

    38

    1. Introduction

    Within every company it is obligatory to have a labor risk evaluation plan.

    Even in the case that we subcontract other companies, it is necessary to check that each

    company has its labor risk evaluation plan adapted to our activity.

    Knowledge

    of

    the

    particularities

    ofthecompanyactivities

    Riskanalysisforeachactivity

    Actions

    depending

    on

    the

    risks

    Labor r i sk s eva lua t ion p lan

    http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance

  • 8/8/2019 2. Execution and Commissioning

    39/49

    39

    2. Activitie character istics

    PVontheroof PVontheground(Fix) PVontheground(Suntracking)

    Smallfacilities:From23KWto100KW

    (Orevenmore) Largerfacilities:>100KW Largerfacilities:>100KW

    Workingatgreatheights Workingontheground Workingontheground

    Differenttypesofroofs Earthmovements Earthmovements

    Differenttiltsofroofs Trenchopenings Trenchopenings

    Sharingtheworkwiththeindustry

    whereourplantislocatedLargernumberofworkers Largernumberofworkers

    Electricalcabling

    and

    inverter

    commissioningPossibilityofusingcranes

    Usageof

    cranes

    to

    fix

    the

    panel

    structure

    totheSuntrackers

    Electricalcablingandinverter

    commissioning

    Electricalcablingandinverter

    commissioning

    Labor r i sk s eva lua t ion p lan

    http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance

    L b i k l t i l

  • 8/8/2019 2. Execution and Commissioning

    40/49

    3. Activity risks

    PVon

    the

    roof PV

    on

    the

    ground

    (Fix) PV

    on

    the

    ground

    (Suntracking)

    Fallsfromtheroof Fallsintotrenches Fallsintotrenches

    Accidentsduetomaterialfalling Toberunoverbyworkingvehicles Toberunoverbyworkingvehicles

    Riskfrom

    the

    industry

    where

    the

    plantislocatedElectrocutionrisk Electrocutionrisk

    Electrocutionrisk Accidentsduetomaterialfalling Accidentsduetomaterialfalling

    Accidentduetocollisionwiththesuntracker

    40

    Labor r i sk s eva lua t ion p lan

    http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance

    L b i k l t i l

  • 8/8/2019 2. Execution and Commissioning

    41/49

    4. Activitie summary

    To analyze the photovoltaic activities, to know and to evaluate the risks of every job

    inside every activity.

    To train the staff on the risks depending on their job or workstation

    To distribute the equipments of individual protection adapted to every workstation

    To designate a person in charge of checking the correct execution of the prevention

    plans

    To develop an emergency and evacuation plan

    41

    Labor r i sk s eva lua t ion p lan

    http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance

  • 8/8/2019 2. Execution and Commissioning

    42/49

    INDEX

    Civil works. Infrastructure preparation

    Mechanical works

    Electrical works

    Environmental issues

    Quality. Critical issues during execution

    Safety & Labor risks

    Commissioning tests. Key points

    42http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance

  • 8/8/2019 2. Execution and Commissioning

    43/49

  • 8/8/2019 2. Execution and Commissioning

    44/49

  • 8/8/2019 2. Execution and Commissioning

    45/49

    45

    Source: Geonica

    Plan t p r oduc t ion check ing

    Outdoor temperature

    (Optional)

    Irradiance

    AC Power (at themeter output)

    TEMP. PANEL FV

    For the capture of the indicated

    variables we will need to have:

    A meteorological station

    where the information of

    Temperature and irradiance

    will be registered

    A meter (with integrated

    communications) from which

    we can read the output

    power

    http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance

  • 8/8/2019 2. Execution and Commissioning

    46/49

    46

    In the case of using suntrackers, we have to verify the equipment performance every

    hour by testing the shadow projected by a rod perpendicular to the plane of the

    generator

    Minimal measure period: 5 consecutive days dawn - dusk

    Condition: The minimal period of irradiance over 600W/m2 must be at least 12 hours

    Periodicity of the measure of output power - irradiance-temperature: 10 mins

    The obtained measures of output power-irradiance-temperature are compared to the

    expected ones and the deviations between both are analyzed

    If the legislation allows it in the future, the modernization or extension of the plant for

    repowering might be recommended

    Plan t p r oduc t ion check ing

    http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance

    Test ing o f PV Genera t o r e lect r i ca l

  • 8/8/2019 2. Execution and Commissioning

    47/49

    47

    I

    V

    Test ing o f PV Genera t o r e lect r i ca l charac te r i s t i cs

    We obtain the C-V curve from the generator and the

    one from a standard module, and both are compared

    under the conditions above-mentioned

    These tests have to be done two hours before and after

    the local midday and the global irradiance has to be a

    over 700W/m2

    Nowadays we can find specific equipments to obtain the

    C-V curve of a PV generator and move it into standard

    conditions

    Objective: To determine the electrical characteristics underthe Standard metering conditions, defined by:

    Irradiance: G = 1000 W/m2 Cell temperature: CT=25C.

    http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance

    T t i f t h i t l t i l h t i t i

  • 8/8/2019 2. Execution and Commissioning

    48/49

    48

    Is the second most important element in a PV facility

    The European efficiency of the inverter, has to be

    verified with the measures commented in the previous

    slides, attaching the power measure and the voltage

    in the DC side

    Furthermore, it must be verified the inverter capacity

    to track the Maximum Power Point (MPP)

    Test ing o f t he i nv e r t e r e lect r i cal cha ract e r i st i cs

    Source: SMA

    Objective: To determine the characteristics which define theenergetic performance of an inverter:

    Efficiency Maximum Power Point Tracking

    http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance

    En d o f Session 2

  • 8/8/2019 2. Execution and Commissioning

    49/49

    49

    http://www.leonardo-energy.org/training-pv-systems-design-

    construction-operation-and-maintenance

    Thank you for attending