2 project description 2.1 project locality · 2019-11-01 · environmental resources management...
TRANSCRIPT
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
2-1
2 PROJECT DESCRIPTION
2.1 PROJECT LOCALITY
The 133MR operation falls within the Gert Sibande District Municipality and
Dr Pixley Ka Isaka Seme Local Municipality (Figure 2.1). The nearest town is
Piet Retief in Mpumalanga Province, which is approximately 45 km east of
133MR (Figure 2.1). Driefontein village is located approximately 12km to the
east.
The 133MR mining operations fall under Savmore Colliery in the
Mpumalanga Province. The current operational sections under Savmore
Colliery are Maquasa East, Maquasa West and Maquasa West Extension (such
as Nooitgesien opencast mining operation). All these operations are covered
under the Mining Right 133MR and the Consolidated EMPr.
The relevant farm portions which make up Mining Right 133MR are listed in
Table 2.1 as well as the associated 21 digit Surveyor General (SG) Code.
Table 2.1 21 Digit Surveyor General Code for the relevant Farm Portions Included in
Mining Right 133MR
APPROVED EMPR FARM NAME PORTION NUMBER SG CODE
Maquasa East Maquasa 19 HT Remaining extent T0HT00000000001900000
Roodekral 21 HT Remaining extent T0HT00000000002100000
Maquasa West
Rooikop 18 HT Portion of mineral area
1 on the remainder
T0HT00000000001800000
Maquasa 19 HT Portion of Mineral area
1
T0HT00000000001900001
Nooitgesien 381 IT Portion of the
remainder
T0HT00000000038100000
Maquasa West
Extension
Kransbank 15 HT Portion 1 T0HT00000000001500001
Kransbank 15 HT Portion 2 T0HT00000000001500002
Figure 2.1 Kangra Coal Mining Right 133MR Project Locality
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
2-3
This Chapter provides a summary of the existing operations as authorised
under 133MR by DMR in 2014 (DMR, 2014) and a description of the new
activities and infrastructure to be consolidated into the existing EMPr. The
new activities and infrastructure for which approval is being applied for in
this EMPr Consolidation are:
A Central Discard Dump at Maquasa East area;
Previously omitted underground mining works that is part of Maquasa
West Extension under the former section 209MR; and
An adit located at the Kransbank portion forming part of the Maquasa
West Extension area. It will provide access to these underground workings
located in the same portion.
An overland conveyor and service road connecting the new adit with the
existing infrastructure at the Maquasa West operations.
The new activities and infrastructure will link to the existing coal processing
facilities at Maquasa West and Maquasa East operations.
Maquasa East, Maquasa West and Maquasa West Extension mining
operations all fall under the current Mining Right 133MR and Consolidated
EMPr. The demarcation of these operational areas can be seen in Figure 2.2.
The authorised existing infrastructure/mining areas as well as the authorised
future infrastructure/mining areas are discussed in Section 2.2.
Figure 2.2 MR 133 Operational Areas – Maquasa East, Maquasa West and Maquasa West Extension
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
2-5
2.2 AUTHORISED EXISTING AND FUTURE OPERATIONS AND INFRASTRUCTURE
This section includes a summary description of the authorised mining
operations and infrastructure as per the approved 2014 Consolidated EMPr
(133MR) (GCS, 2014) (Annex 2A).
Underground mining activities at Maquasa East operation have ceased.
Maquasa West is an active underground and opencast operation. Most of the
mining related surface infrastructure, including the coal beneficiation plant, is
located at the Maquasa East operation. All the coal mined at Maquasa West
and Maquasa West Extension is processed firstly at the primary crushing and
screening facility located at Maquasa West and then at the Maquasa East
beneficiation plant.
Figure 2.3 indicates the location of all existing operations, infrastructure and
activities that are authorised (under 133MR) and including operations that are
currently underway, mined out or still to be undertaken. These activities and
related infrastructure are described in the following sections.
Figure 2.3 Authorized operations and infrastructure on 133MR
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
2-7
2.2.1 Maquasa East
The layout of the Maquasa East operation is illustrated in Figure 2.4. As
previously mentioned, the underground and some of the opencast (Pit A,
Pit D and Romar Pit) mining activities have ceased. However, the section still
hosts the beneficiation plant that serves for all Maquasa operations. Opencast
Pit B & C have been authorized in the 2014 Consolidated EMPr. However,
they have not yet been mined.
Figure 2.4 Maquasa East Operational Area
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
2-9
Authorised Operations and Infrastructure
This section includes a summary of the existing permitted mining operations
and infrastructure at Maquasa East as per the approved 2014 Consolidated
EMPr (133MR). The permitted infrastructure found at Maquasa East is
described in Table 2.2.
Table 2.2 Authorised Existing Operations and Infrastructure at Maquasa East
Operational Component /
Infrastructure
Description / Notes
Discard Dump All coal mined under Mining Right 133MR is processed at
Maquasa East beneficiation plant. The discard produced is
disposed of onto the existing Maquasa East discard dump.
Beneficiation Plant Located at Maquasa East. The components of the plant include
Offices and Workshops, secondary crushing and screening,
discard plant, coal stockpiles, and inland plant and export plant.
ENPROTEC Plant Plant for the treatment of coal slurry in order to obtain a coal
product in the form of a filter pressed ‘cake’. Water extracted
from the slurry during this process is re-used in the
beneficiation plant. The slurry plant is currently being
expanded.
Diesel storage facilities Tanks for storage of diesel for the vehicle fleet.
Pit A Mining at Pit A has been completed. Pit A is located to the south
west of Maquasa East coal beneficiation plant on the farm
Roodekraal 21HT (27°0'39.53"S; 30°23'56.59"E) and Maquasa
19HT. This pit has been levelled and top soil has been applied.
Pit D Mining at Pit D has been completed. Pit D is located to the north
west of the current Maquasa East coal beneficiation plant on the
farm Rooikop 18HT (27°00'51.41"S; 30°23'24.41"E) and
Roodekraal 21HT. The pit has been mined out with the majority
of the pit having been levelled and top soil has been applied.
The final void is used for water storage and management.
Evaporators have been installed in the final void for
management of excess water.
Romar Pit Mining at the Romar Pit has been completed. The Romar Pit is
located in the north of the Maquasa East operational area on the
farm RoodeKraal 21HT (27° 0' 12.33" S; 30° 23' 53.38" E). The pit
has been mined out. The pit has been levelled and top soil has
been applied.
Maquasa East Adit Operations at this adit are now complete and there are no
further operations planned.
Public Roads There is one main public road running through the Maquasa
East operational area, this is the M22 and it is located on the
western side of the Maquasa East operation.
Haul Roads There are numerous haul roads and tracks linking the various
operational components of the Maquasa East operations.
Powerlines A 22 kV Eskom power line supplies the existing Maquasa East
Beneficiation Plant and the associated infrastructure. This line
also supplies the Maquasa West operations with power,
including all adits and offices.
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
2-10
Authorised Future Operations and Infrastructure
Most of the mining activities in Maquasa East have been completed and only
the Beneficiation Plant remains. However, there are some areas which are
authorised for mining that may be accessed in the future. These are described
in Table 2.3 below.
Table 2.3 Authorised Maquasa East Future Operations and Infrastructure
Operational Component /
Infrastructure
Description / Notes
Pit B Pit B is located to the south east of the current Maquasa East
coal washing plant on the farm Roodekraal 21HT (27°0'42.43"S;
30°25'09.64"E).
Pit C Pit C is located in close proximity to the northern boundary of
133MR, north east of the current Maquasa East coal washing
plant on the farm Roodekraal 21HT (27°00'49.66"S;
30°24'32.64"E). The Driefontein settlement is within 500 m
radius of the proposed pit.
2.2.2 Maquasa West
The layout of the Maquasa West operation is illustrated in Figure 2.5.
Maquasa West has both opencast and underground mining operations. The
main surface infrastructure includes the Maquasa West offices and workshop,
mine adits, primary crushing and screening facilities and an overland
conveyor connecting to Maquasa East.
Figure 2.5 Maquasa West Operational Area
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
2-12
Authorised Operations and Infrastructure
This section includes a summary of the existing authorized mining operations
and infrastructure at Maquasa West under the consolidated EMPr. The
Maquasa West authorized infrastructure is described in Table 2.4.
Table 2.4 Authorised Maquasa West Operations and Infrastructure
Operational Component /
Infrastructure
Description
Overburden dumps There are various overburden dumps servicing the Nooitgesien
Pits.
Offices and Workshops Currently located at Adit 1 but are progressively being moved
to be near Adit 4.
Diesel storage facilities Tanks for storage of diesel for the vehicle fleet.
Nooitgesien Opencast Pits Nooitgesien Opencast Pits G1 and G2 are currently being
mined. Nooitgesien Opencast Pit G3 has been mined out.
Nooitgesien Underground
Works
There are two areas of resource underground that are currently
being mined.
Nooitgesien Waste Rock
Dump
There is one waste rock dump at Nooitgesien
Maquasa West South Opencast
Pits
The existing pits are located on the farm Maquasa 19HT
(27°01'48.33"S; 30°22'41.04"E). The pits are located adjacent to
an existing access road. There are three opencast mining areas
associated with the Maquasa West South Opencast Operations:
Maquasa West South – Main;
Maquasa West South – Block B; and
Maquasa West South – Block D.
Mining has been completed in these areas and they have been
levelled and topsoil has been applied.
Adit 1 This adit is currently used for accessing the Maquasa West
underground operations. At this location there is also the
following infrastructure:
Offices and workshop;
Stores;
Main ventilation fans; and
Lamp house.
Adit 2 This adit is currently used for accessing the Maquasa West
underground operations extended from the opencast
operations.
Adit 4 This adit is used to access underground operations at
Nooigesien. At adit 4 there are also the following facilities:
Waste water treatment works;
Water storage facilities; and
A change house
Overland Conveyor The overland conveyor runs from the Maquasa West adit to
Maquasa East. It transports coal to Maquasa East beneficiation
plant. It is approximately 6 km in length.
Public Roads An unnamed public road passes through the northern section of
the Nooitgesien operational areas. The road leads to Volkrust
Haul Roads There are numerous haul roads and tracks linking the various
operational components of the Maquasa West operations.
Powerlines There is a 22 kV Eskom power line that supplies the existing
Maquasa West operations.
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
2-13
Authorised Future Operations and Infrastructure
This section includes a summary of the future mining operations and
infrastructure at Maquasa West which have been authorised under the
consolidated EMPr. The authorised future infrastructure is described in Table
2.5.
Table 2.5 Maquasa West Permitted Future Operations and Infrastructure
Operational Component /
Infrastructure
Description
Opencast mining Mining operations through opencast method at Nooitgesien Pit E,
F and H.
2.2.3 Maquasa West Extension
The Maquasa West Extension operational area is indicated in Figure 2.6.
Maquasa West Extension has only underground operations taking place as
approved under Consolidated EMPr (133MR).
Figure 2.6 Maquasa West Extension Operational Area
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
2-15
Authorised Operations and Infrastructure
This section includes a summary of the permitted mining operations at
Maquasa West Extension as per the approved Consolidated EMPr (133MR).
The permitted existing infrastructure found at Maquasa West Extension is
described in Table 2.6.
Table 2.6 Maquasa West Extension Permitted Operations and Infrastructure
Operational Component / Infrastructure Description
Underground mining operations Underground mining operations accessed
from Adit 1, Adit 2 and Adit 4.
Authorised Future Operations and Infrastructure
This section includes a summary of the permitted future mining operations at
Maquasa West Extension as per the approved Consolidated EMPr (133MR).
The permitted future operations at Maquasa West Extension are described in
Table 2.7.
Table 2.7 Maquasa West Permitted Future Operations and Infrastructure
Operational Component / Infrastructure Description
Nooitgesien Opencast Operations Mining operations through opencast method at
Nooitgesien Pit G4.
2.3 PROPOSED INFRASTRUCTURE AND MINING UNDER CURRENT APPLICATION
Kangra Coal intends to extend the current operations under the 2014
Consolidated EMPr. This section describes the new activities applied for as
part of this Section 102 Amendment application. The activities applied for are:
The development of the Central Discard Dump at Maquasa East
operations (Section 2.3.1);
The mining of the MWE underground works (portion of the Maquasa
West Extension omitted activities from the current 2014 Consolidated
EMPr) (Section 2.3.2);
The development of Adit 5 to access the MWE underground workings
(Section 2.3.3); and
The development of an overland conveyor and service road connecting
Adit 5 with the existing Maquasa West operational area (Section 2.3.3).
Existing facilities at Maquasa West and Maquasa East will be utilised for coal
processing.
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
2-16
2.3.1 Central Discard Dump
Introduction
The EIA and EMPr for the Central Discard Dump was undertaken by GCS
(GCS, 2016). The full report and supporting technical reports are contained in
Annex 2B.
The current discard dump does not have sufficient capacity to accommodate
the discard to be produced from the proposed future operations. A new
Discard Dump, called the Central Discard Dump, is proposed on the south
eastern side of the current discard dump in Maquasa East on the remaining
(RE) portion of the farm Rooikop 18 HT, with a small area of the dump on the
remaining (RE) portion of the farm Maquasa 19 HT (Figure 2.7). The Central
Discard Dump will be utilized for discard generated by the proposed new
underground mining, the proposed Kusipongo operations and from the
beneficiation plant located at Maquasa East.
The discard dump was designed by Geotail (Pty) Ltd and the description
provided in this section has been extracted from the Design Report (GCS,
2016). The recommendations made in the Geotechnical Report and in the draft
Groundwater Assessment Report were incorporated into the Discard Dump
design.
The discard dump will be developed as a three-compartment side hill type
storage facility with a footprint of approximately 65ha (Table 2.8). The three-
compartment layout allows for a modular implementation approach (phases
1, 2 and 3) with the benefit of delaying capital expenditure.
The following structures will be required:
Lined discard dump (to be constructed in three different
compartments/phases);
Under-drainage system;
Boundary fence;
Internal haul roads;
Catchment paddocks;
Two compartment, High Density Polyethylene (HDPE) lined Pollution
Control Dam (PCD) (one compartment to be operated as empty); and
Stormwater management infrastructure, such as berms and trenches.
The proposed discard dump was three-dimensionally modelled for an
accurate determination of the relationship between the height, area and
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
2-17
capacity. The results of this modelling are the capacity and dimensions of the
discard dump and these are summarised in Table 2.8.
Table 2.8 Dimensions and Capacity of the proposed Discard Dump
Description Total/Unit Phase 1 Phase 2 Phase 3
Life of facility 20 years 7.4 7.4 5.4
Extent of Discard Dump 65ha 23.5 21.9 19.3
Capacity of discard dump 20.2 million tonnes (Mt) 7.4 7.4 5.4
Airspace available 11.2 million m³ 4.1 4.1 3.0
Final vertical height of Discard Dump m 34 33 32
Deposition rate 1 million tonnes per
annum of coarse
material
- - -
Final side slope area ha 13.1 9.0 8.2
Final top surface area 38ha 9.5 13.9 14.6
Figure 2.7 Central Discard Dump Location and Layout
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
2-19
Description of the Discard Material
A hydro-geochemical assessment was performed on a 52kg sample of discard
provided by Kangra (GCS, 2016).
The sample provided was crushed, split into two samples (ABK601 and
ABK602), and milled prior to testing.
Mineralogy and Total Chemical Composition
The results showed that Gypsum (CaSO42H2O) and Quartz (SiO2) (originating
from calcic rock) were the major minerals in the sample.
Kaolinite (Al2Si2O5 (OH) 4); Microcline (KAlSi3O8); and Muscovite
(KAl2(Si3Al)O10(OHF)2) occurred as minor minerals within the sample. Calcite
(CaCO3) occurred as an accessory mineral and is an important mineral in the
neutralisation of acidity produced by pyrite oxidation in acid-mine drainage
(AMD) and frequently occurs in Karoo sedimentary rocks.
Plagioclase (NaAlSi3O8-CaAl2Si2O8) and Pyrite (FeS2) occurred in trace
quantities.
Acid Rock Drainage Potential
The potential of geological material to oxidise and generate acidic drainage
were determined through acid-base accounting (ABA) and net acid generation
(NAG) analyses, respectively.
ABA is a set of analytical methods that measures acid generation potential
through independent determination of acid generating (AP) and neutralising
(NP) content. These tests provide an important first order assessment of
potential drainage that could be expected from the discard material.
NAG analysis, in combination with ABA tests, can be used to indicate the
likelihood of acid generation or stored acidity.
From the ABA and NAG test results, the following observations could be
made:
Pyrite was the only sulphide detected in the rock through means of X-
ray Diffraction (XRD). It was assumed that oxidation of pyrite will be
the only contributor to acidity;
Both samples showed high percentage Sulphur (%S), above 0.3%, of
0.55% and 1.49% respectively;
The neutralisation potential for the one sample is slightly higher than
the acid potential, while the other sample has a higher acid potential
and is likely to generate AMD; and
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
2-20
During the NAG tests, only the second sample acidified. However, the
part of the discard with lower the percentage of Sulphur will not be
able to neutralise all acidity generated by the discard with the higher
percentage of Sulphur.
Overall, it could be concluded that the discard has a significant potential to
generate acid mine drainage/seepage.
Static Leach Tests
Discard material was subjected to the following leach tests in order to identify
the constituents that may leach out:
Peroxide leaching test – reacted with 400 ml of 15 % hydrogen
peroxide with a rock/water ratio of 1:100. This test simulates extreme
conditions as all pyrite is oxidised at once. Under field conditions, not
all pyrite constituents will be oxidised as some minerals are physically
shielded by the rock matrix and oxidation will occur over a long
period of time.
Reagent water leach test – 50g discard material reacted 1 000ml of
reagent water solution for 18 hours with water/rock ratio of 1:20. The
test was performed using the extraction procedure for mono-filled
waste according to Australian Standard (AS) 4439.3.
Toxicity Characteristic Leaching Procedure (TCLP) test – the test was
performed using the extraction procedure for mono-filled waste
according to AS 4439.3.
The leachate composition does not reflect the leachate that may be expected
from the discard materials under field conditions. This is due to the fact that
different leach rates and water rock ratios are used in the leach tests and do
not reflect conditions that is site-specific.
The following observations were made from the leach testing:
Peroxide leach test:
o The pH of the discard material is neutral to acidic, ranging
between 3.26 and 6.92 (pH unit);
o The leachate showed elevated dissolved concentrations of
aluminium, iron, manganese, nickel, lead and vanadium and to
a lesser degree chromium; and
o A positive correlation is present between the %percentage
Sulphur and the sulphate extracted from the material.
Reagent water leach test:
o The pH of the discard material is neutral, ranging between 6.49
and 6.55 (pH unit); and
o The leachate showed no elevated dissolved concentrations for
metals or trace elements.
TCLP leach test:
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
2-21
o The pH of the discard material is acidic, ranging between a pH
unit of 5.25 and 5.39; and
o The leachate showed elevated dissolved concentrations of iron
and manganese and to a lesser degree aluminium and nickel.
Waste Classification
The NEMWA, Waste Classification and Management Regulations
(Government Notice No. 634, published in Government Gazette No. 36784,
dated 23 August 2013) require that all waste generated by waste generators,
subject to sub regulation (2) of the act, be classified in accordance with SANS
10234 within one-hundred-and-eighty (180) days of generation.
Waste must be assessed in terms of the NEMWA National Norms and
Standards for the Assessment of Waste for Landfill Disposal (GN634). Waste
is assessed for the purpose of disposal to the landfill, by identifying the
chemical substances present in the waste. This is done by sampling and
analysing the total concentrations (TC) and leachable concentrations (LC) of
the elements that have been identified in the waste and comparing that to the
threshold limits specified in Section 6 of the Norms and Standards.
The results of the TC and LC are summarised below (GCS, 2016):
Barium, copper and lead results fall below the total concentration
threshold (TCT0) limits (<TCT0); and
All chemicals falls below the total leachable concentration (LTC0) limits
(<LTC0).
The discard material would be classified as Type 3 Waste based on the results
of the TC and LC analysis and the determination of waste types for landfill
disposal Section 7(2) (d) that stipulates: “Wastes with all element or chemical
substance leachable concentration levels for metal ions and inorganic anions below or
equal to the LCT0 limits are Type 3 Waste.”
Construction/Disposal Method
The coal discard will be transported by truck from the Maquasa East
beneficiation plant to the new discard dump, where it will be placed and
compacted mechanically. The discard will be placed in horizontal layers
(bottom-up) following an approved performance compaction specification.
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
2-22
Groundwater Management
In order to protect the groundwater resource below and within the vicinity of
the discard dump, two mechanisms will be employed to manage seepage from
the facility:
1. An under-drainage system; and
2. A liner.
Under-Drainage System
The under drainage system is designed to collect seepage on top of the liner
and to achieve phreatic surface drawdown at the toe of the discard dump. As
such, the under-drainage system is strategically placed along the critical
downstream toe line of the discard dump.
Discard Dump Liner
The proposed liner system for the discard dump generally complies with the
Class C liner type in the waste classification regulations (published in
Government Notice R. 634) and comprises four layers (Figure 2.8).
Figure 2.8 Proposed Liner for the Discard Dump
Source: Geotail, 2014
PCD Liner
The liner system for the PCD generally complies with the Class B liner type as
described in the waste regulation, GNR643. This liner comprises three layers
and as shown in Figure 2.9.
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
2-23
Figure 2.9 Proposed Liner for the PCD
Source: Geotail, 2014
Surface Water/Stormwater Management
The surface or stormwater management measures are designed to separate
clean and dirty water, divert clean water away from the discard dump and
collect and contain water found within the discard dump footprint (dirty
water).
Stormwater Diversion Channels
Two channels are deemed necessary to divert clean stormwater away from the
discard dump, i.e. the North and South channel. A local watershed runs
generally east west through the southern portion the centre compartment of
the discard dump. The two channels originate on this watershed. The North
Channel runs generally northwards while the South Channel runs southwards
before turning west and then northwest around the southern perimeter of the
discard dump.
The proposed channels have been sized to comply with the GN704
requirements and as such they are designed to convey the 50-year design
flood peak (Table 2.9). The catchments for the channels are relatively small.
Table 2.9 Stormwater Channel Dimensions
Parameter North Channel South Channel
Catchment Size 32.9ha 4.9ha
Shape Trapezoidal Trapezoidal
Base width 1m 1m
Side slopes 1:1.5 (V:H) 1:1.5 (V:H)
Flow depth 0.83m 0.48m
Channel depth* 1.1m 0.8m
Max flow velocity** 3.7m/s 2.7m/s-
Flow type at max velocity Supercritical Supercritical
**Note: Flow velocities are based on the maximum longitudinal gradient.
The stormwater channels have been sized assuming unlined channels, and
will be excavated into the ground. The material excavated from the channel
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
2-24
will be placed in a berm on the downstream side of the channel to increase the
capacity of the channel above its design capacity and provide additional
freeboard where required; and to allow cost effective construction as load and
haul volumes are minimised. The berm should be compacted and vegetated
and the channel kept free of long grass, shrubs and woody vegetation.
Discard Dump Design Features
The discard dump has been designed to avoid storage of water on the facility,
thereby increasing its stability.
The side slopes will be terraced and berm penstocks will be utilised to drain
the permanent benches. This water will be captured by the catchment
paddocks, which will be located at ground level. The runoff will be diverted to
the PCD.
It is recommended that the discard dump is operated with the minimum of
water stored on the top surface at all times.
Pollution Control Dams
The PCD will serve to collect and contain direct rainfall, runoff from the
discard dump surface and the “dirty water catchment” of the discard dump,
as well as seepage captured by the under-drainage system (within the
catchment paddocks). The stormwater diversion channels will divert clean
water away from the “dirty” area in order to reduce the amount of polluted
water which must be contained, thereby reducing the PCD capacity
requirement. The proposed maximum capacity of the PCD is 100,000m³. The
water pumped out of the PCD will be sent to the washing plant, before being
pumped to Pit D East where it will be evaporated.
Access Control
A boundary fence will be erected around the perimeter of the discard dump
facility to keep out livestock and discourage entry by people.
A haul road will be constructed around the discard dump. This haul road will
connect to the existing haul road to the east of the proposed discard dump
complex. The internal haul road will also lead to the PCD. The haul roads
within the discard dump complex will not exceed a width of 8m.
2.3.2 Maquasa West Extension Underground Works
Introduction
The authorization for the underground workings was initially approved
under the MP 30/5/1/1/2/209MR EMPr for the Maquasa extension by the
DMR on the 15 August 2008 (Annex 1B) (Oryx Environmental, 2006).
However, during the consolidation of the EMPr’s into 133MR (as approved in
July 2014, Annex 1A and Annex 2A), a section of the 209MR activities were
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
2-25
accidentally omitted. This was discovered in 2015 during the second EMPr
amendment application. The DMR informed Kangra that they could not
approve an adit location that accesses a mining resource that was technically
null and void (i.e. the omitted section of MWE, 209MR). This S102
Amendment application therefor includes the MWE underground works so
that this activity can be approved. This section, based on the project
description as per the Oryx (2006) report and updated by Kangra Coal,
describes the proposed underground works activities.
The proposed mine plan for the MWE underground works can be seen in
Figure 2.11. These works will be accessed by the proposed new Adit 5 which
is discussed in detail in Section 2.3.3. The proposed MWE underground works
will be located under the properties detailed in Table 2.10.
Table 2.10 Project Infrastructure Summary Description
Property Surveyor General Cadastral Code
Kransbank 15 HT, Portion 1 T0HT00000000001500001
Kransbank 15 HT, Portion 2 T0HT00000000001500002
Maquasa 19 HT Remaining Extent T0HT00000000001900000
Mining will occur by underground board and pillar methods with
chequerboard pillar extraction. Board-and-pillar, or room-and-pillar, is an
extensively used underground mining technique. This method uses a grid of
tunnels and involves progressively cutting panels into the coal seam whilst
leaving behind pillars of coal to support the overburden (1). This will be done
using a horizontal continuous miner.
Mined material is extracted across a horizontal plane and open areas or
"rooms" are created underground. "Pillars" of untouched material are left to
support the roof overburden. This technique is usually used for relatively flat-
lying deposits. The key to successful board and pillar mining is in the selection
of the optimum pillar size, considering the required safety factors to avoid
subsidence on surface. Board and pillar mining is depicted in Figure 2.10.
(1) http://www.nswmining.com.au/industry/mining-methods , Accessed 19 September 2016.
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
2-26
Figure 2.10 Diagram of Typical Board and Pillar Mining Method
Source: Okubo & Yamatomi,.date unknown
Figure 2.11 Maquasa West Extension Underground Works
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
2-28
Project Phases
Mining projects are developed in set phases, with each phase having a
different combination of activities. These phases include the construction,
operation and decommissioning/closure phases.
These Project phases are discussed in the following sections.
Construction Phase
For underground mining operations there are few construction activities
strictly related to the underground portion of the project. Construction
activities are almost all related to the construction of the access adit. These
activities are discussed in detail in Section 2.3.3.
Operations Phase
As previously discussed mining will occur using continuous mining
equipment and will access the coal reserves using the board and pillar
method. Mining will take place from the new Adit 5 and will extend in a
southerly and easterly direction as shown in Figure 2.11. A mine schedule is
provided in Table 2.11.
Table 2.11 Maquasa West Extension Underground Works Mine Schedule
Year Tonnes
2016 2,647,620
2017 2,858,135
2018 2,071,044
2019 1,577,220
2020 1,459,909
2021 1,533,748
2022 459,126
All coal that is mined from this area will be transported from the Adit 5 via
the new overland conveyor to the coal processing facilities at Maquasa West
operation, and from there the coal will be transported via the existing
overland conveyor to the beneficiation plant located at Maquasa East. Discard
from this process will initially be disposed of at the existing discard dump and
later to the new Central Discard Dump.
Closure
Closure is planned for the end of the Project life (approximately 7 years) and
will include:
Decommissioning and sale of mining equipment and infrastructure;
Restoration and rehabilitation of disturbed areas;
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
2-29
Management of mine water decant and water treatment prior to discharge;
and
Post closure monitoring.
2.3.3 Adit 5 and Overland Conveyor
Introduction
In addition to the proposed underground workings in the previous section,
Kangra Coal intends to develop and operate a new adit in the Maquasa West
Extension area (the Adit 5), an overland conveyor connecting the Adit 5 to
Maquasa West coal processing facilities, and an associated service road. The
coordinates of these facilities are listed in Table 2.12.
Table 2.12 Co-Ordinates of Surface Infrastructure
Infrastructure Latitude Longitude
Main Adit– centre point 270 02’ 10.21” S 300 18’ 33.14” E
Overland conveyor 270 02’ 9.82” S 300 18’ 33.92” E (start pt.)
270 01’ 08.53” S 300 19’ 47.47” E (middle pt.)
270 00’ 36.85” S 300 21’ 21.30” E (end pt.)
This proposed infrastructure will be located on the properties detailed in
Table 2.13.
Table 2.13 Details of the properties associated with the Adit 5 and the Overland
Conveyor
Property Surveyor General
Cadastral Code
Title Deed
Number
Infrastructure
Development
Footprint (Ha)
Adit 5
Kransbank 15HT, Portion 2 T0HT00000000001500002 T21311/980 12.37
Overland Conveyor
Kransbank 15HT, Portion 2 T0HT00000000001500002 T21311/980 10.67
Kransbank 15HT, Portion 1 T0HT00000000001500001 T139369/2000
Rooikop 18HT, Portion Re T0HT00000000001800000 T78816/2004
Proposed Project Infrastructure and Activities
The proposed infrastructure forming part of this application is described in
this section and can also be referred to in the site layout diagram in Figure
2.14.
Adit 5
The Adit 5 will include main ventilation fans to provide fresh air to the
underground mining operations and will allow workers, materials and
machinery access to underground mining operations (inclined adit). Figure
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
2-30
2.12 and Figure 2.13 are examples of a mine adit. The inclined adit will include
a conveyor to bring mined coal to the surface.
Figure 2.12 Existing Adit and Coal Handling Facilities at Maquasa West Operations
Figure 2.13 Maquasa West Adit: Portal Entrance and Ventilation Fans
Figure 2.14 Proposed Adit 5 Infrastructure Layout
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
2-32
The following support infrastructure and facilities are required and will be
developed at Adit 5:
Electrical distribution substation, switch gear and step-down transformers
(emergency back-up generators will also be included);
An access road along the new overland conveyor to the Adit 5;
A stormwater management system;
Mobile potable water treatment plant;
Septic tank system at Adit 5 which will be periodically purged and
transported to the sewage treatment plant at Adit 4;
Firefighting system complete with water storage;
A wash bay (including an oil trap) that will be used to wash mining
equipment and light duty vehicles;
Brake test ramp for mine vehicles;
A fuel and oil depot which will be provided by the fuel provider;
Small storage building for minor equipment (main stores at Maquasa West
to be utilised);
Drop-off facility for workers;
Above ground parking bays;
Temporary waste storage facilities to accommodate general (domestic,
recyclables, etc.) and hazardous waste (used oil, solvents, spent batteries,
contaminated rags, overalls, descants, etc.);
First aid facilities;
Lime silo;
A security fence around the perimeter of the property and substation; and
A security (guard) house.
This primary and support infrastructure is described in more detail in Table
2.14.
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
2-33
Table 2.14 Infrastructure at the Adit 5
Operational Component /
Infrastructure
Description
Overburden Dump Excavated rock from the mine portal is proposed to be placed
immediately adjacent to the portal. This overburden dump will
have an area of 2.1 ha and a volume of approximately 379,000m3.
Topsoil Dump Topsoil is required to be stored separately for use during
rehabilitation. The topsoil dump will have an area of
approximately 2.1 ha.
Administration Block There will be containerized offices and a security house at the
entrance of the Adit 5. A lamp house and a containerized control
room will also be developed in the Adit 5 complex.
Pollution Control Dam A silt trap with a footprint of approximately 750m2 and a volume
of approximately 1,000m3 will be installed at the Adit 5 to manage
dirty / oily water from the wash bay and dirty water separation
channels. Water from the silt trap will be directed into a PCD of
approximately 10,000m3. The PCD will contain all dirty and
excess mine water and have an approximate surface footprint of
0.3 ha.
Excess water will be pumped to water storage facilities at
Maquasa West and Maquasa East operations. The current water
storage facilities are pollution control dams at Maquasa West and
East and the void located at Maquasa East Pit (referred to as Pit D
East). Kangra Coal utilizes Evaporators to aid in excess water
reduction at Pit D East through evaporation process. As this is a
fairly new technology the overall efficacy of the evaporators is
still to be determined through long term monitoring and analysis
Process water pipeline
Process water will initially be supplied to the Adit 5 from the
existing facilities at the Maquasa West operations through a
pipeline along the proposed new overland conveyor route
between the Maquasa West adit and Adit 5. Further details are
discussed in the section below. The water pumped from the
underground workings will be utilised as process water for the
remainder of the life of the operation.
Incline Conveyor
An incline conveyor will be constructed to transport mined coal
from the MWE underground works to the surface at the Adit 5.
Feed Stockpile
A stockpile for feeding the overland conveyor will be developed
at the Adit 5 with an approximate volume of 2,000 tonnes.
Electrical
A 6.6 kV overhead power line will link the Adit 5 to Maquasa
West, from which the drive systems for the overland conveyor
will be supplied. The transmission line at the Adit 5 will be
constructed along the conveyor route. A containerized substation
will be constructed at the Adit 5 to provide power to the internal
reticulation system at 400/500V.
The area will be equipped with emergency power generators for
power supply to the main surface fans during power failure.
Access Road
Only one access road will provide access from Maquasa West
operation to the Adit 5 complex. The road will also be used
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
2-34
Operational Component /
Infrastructure
Description
during construction and maintenance of the overland conveyor.
The proposed access road is 10.2m wide and 6 Km in length
(same as proposed conveyor) and will be compacted with gravel.
Stormwater Management
System
Surface water management at the Adit 5 will ensure that there are
clean water systems that divert clean water away from the
complex. Earth fill berms, designed to divert clean stormwater
runoff associated with a 1:100, 24 hour storm event will be
constructed. Storm-water cut-off berms will be constructed
during the main earthworks.
Impacted ‘dirty’ stormwater runoff within the Adit 5 footprint
will be collected and routed via a silt trap to the PCD.
Potable water tank
The potable water will be sourced from a borehole with adequate
yield at Nooitgesien. The water will be treated at Maquasa West
Adit 4 offices at the Water Treatment plant prior being reticulated
to the tank at the Adit 5 complex.
Sewage sump
Sewage generated within the Adit 5 complex will be collected into
a sump. It will be purged on a periodic basis and transported to
the sewage treatment plant at the adit 4 offices.
Vehicle Wash Bay
The wash bay structure will consist of a building with sheeted
roofing and side cladding. It will accommodate washing of all the
mine vehicles. It will be equipped with a high pressure washing
systems, vehicle hoist, and ramp systems for effective vehicle
washing at all angles.
Water emanating from the wash bay will drain into an oil trap
equipped with a silt trap. Oil free water released from the oil trap
will be directed into the silt trap and then into the PCD.
Fuel Storage
A fuel and oil depot will accommodate a cumulative volume of
less than 30m3 is proposed. All fuel and oil storage facilities will
have all legally required safety measures and will be provided by
the fuel supplier.
Stores A small storage building for minor equipment will be
constructed. The main stores to be used will be the existing one at
Maquasa West.
Drop off Facility
The drop off facility will allow mine workers to be dropped off
and picked up safely, ensuring the least amount of pedestrian
movement across roadways.
Parking Bays
Provision will be made for a fenced parking area to which access
will be controlled.
Temporary General and
Hazardous Waste Storage
Areas
General waste will be collected and temporarily stored in waste
skips located near the centre of the Adit 5. Skips will be labelled
so that recyclable and reusable items are separated. Skips will be
removed from the site by a certified waste service provider.
All waste classified as hazardous will be collected in designated
hazardous waste skips. A hazardous waste skip will be stored in
bunded and roofed facility designated for temporary storage of
waste. All hazardous waste such as oil will be recycled or reused.
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
2-35
Operational Component /
Infrastructure
Description
It will be regularly collected by certified waste processors. For
disposal, a licensed hazardous waste collecting company will be
contracted for transportation and disposal of waste to a licensed
landfill site. Skips will also be provided for general waste.
The anticipated hazardous waste temporary storage volume of
80 m3, shall not be exceeded
Security and Fencing of the
Adit 5
The entire Adit 5 will be fenced. It will be provided with access
control such as vehicle and pedestrian gates and security access
points. Each facility within the Adit 5 will have its own fencing
and security where necessary.
Overland Conveyor System
The footprint of the overland conveyor system is approximately 10.67 Ha. The
infrastructure listed below is proposed and will be developed along the
overland conveyor system:
An overland conveyor;
Road over conveyor crossings;
Stream and wetland crossings; and
Fencing and security of the overland conveyor system.
The overland conveyor system will transport coal from the Adit 5 to the
existing facilities at Maquasa West operation, from where it will be
transported to the beneficiation plant at Maquasa East through the existing
overland conveyor. Included in the conveyor servitude will be overhead
transmission lines (OHTL) (approximately 5 m north of the overland
conveyor), an access road and a security fence (fenced width of 20m). The
conveyor will be ground run supported by light overland modules with angle
roof sheeting. Figure 2.15 shows the existing conveyor at Maquasa West.
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
2-36
Figure 2.15 Existing Maquasa West Overland Conveyor
Approximately ten over passes will be constructed over the overland
conveyor to allow the local farmers and communities safe access to either side
of the conveyor when necessary (Figure 2.16). Guardrails will be placed on
either side of the ramps over the conveyor route crossing.
Figure 2.16 Road over Conveyor Crossing
The proposed overland conveyor will cross a number of streams and
wetlands. The section of conveyor that traverses a stream, and that is situated
within a distance of 12m from the edge of the 1:100 year flood line, will be
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
2-37
fully enclosed and raised on a steel gantry (Figure 2.17). Furthermore, the
entire raised section will have a bunded concrete floor to catch any potential
coal spillage. Spilled coal will be hand swept into a bunded concrete area,
which is positioned at ground level. Any potentially spilled coal will then be
removed from the bunded area and returned to Adit 5.
Figure 2.17 Enclosed Conveyor Over Stream Crossing
The gravel service road running parallel to the conveyor will traverse the
stream over concrete culverts (Figure 2.18). The gravel road and conveyor
terrace will be reduced to one lane to minimise culvert lengths.
Figure 2.18 Road Over Stream Crossing
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
2-38
Fencing will be placed on both sides along the entire route of the conveyor
with the exception of the conveyor gantries where the fence will be
constructed under the gantry and join up with the fence on the adjacent side.
This fence denotes the conveyor servitude. The fence will also enclose the
service road along the conveyor route.
Project Phases
The proposed Project will be developed in set phases, with each phase having
a different combination of activities. For ease of reference, the proposed
Project has been divided into the following phases:
Construction Phase;
Operational Phase; and
Decommissioning and Closure Phase.
Construction Phase
Construction of the surface infrastructure is planned to commence in 2017.
The construction phase will include the following initial activities:
Construction of an access road and a powerline to the site of the proposed
Adit 5 and along the route of the proposed overland conveyor;
Establishment of the mobile offices and support facilities at the Adit 5;
Establishment of the Adit 5;
Development of the overburden dump and topsoil dump during the adit
development;
Establishment of the main ventilation fans;
Construction of stormwater management features such as diversion
berms, stormwater channels and an evaporation dam;
Establishment of the overland conveyor;
Transmission line development in the overland conveyor servitude;
Establishment of a water pipeline along the overland conveyor route;
Installation of the water storage tank; and
Installation of sewage sump which will be serviced periodically (Sewage
effluent be sucked up and transported by tanker to the sewage treatment
plant at Adit 4).
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
2-39
Operational Phase
The operational phase of the project will include the following activities:
Conveyance of coal from the underground mining operation at the MWE
underground works, via the Maquasa West operation where primary
crushing and screening will take place, and then to the existing Maquasa
East coal beneficiation plant;
Temporary storage of general and hazardous waste in containers at the
Adit 5 which will be removed on a regular basis by a licensed waste
contractor;
Delivery of explosives, fuel, various kinds of machinery typical in mining
operations, construction materials from time to time, spare parts for minor
reparations of machinery, etc.;
Maintenance of all water management facilities on site such as the
evaporation dam and stormwater management system;
Management of excess underground water (dewatering and storage );
Management of the on-site sewage storage and disposal; and
Ongoing maintenance of the service road, overland conveyor, process
water supply pipeline, and transmission line.
Decommissioning Phase and Closure
Decommissioning and closure occurs at the end of the Project life
(approximately 7 years) and will include:
Decommissioning and sale of mining equipment and infrastructure;
Restoration and rehabilitation of disturbed areas;
Management of mine water decant and water treatment prior to discharge;
and
Post closure monitoring.
2.4 NEED AND DESIRABILITY
Coal provides around 30.1% of global primary energy needs, generates over
40% of the world's electricity and is used in the production of 70% of the
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
2-40
world's steel (1). South Africa possesses Africa’s only significant coal reserves;
over 95% of Africa’s coal reserves are found in South Africa (2), with coal
reserves of 30,2 billion short tonnes at the end of 2012, which represents 4% of
the world’s total coal production. .South Africa is the world’s seventh largest
coal producer, and produced 3.3% of the world’s coal in 2013 (256 million
tonnes).
In 2013, South Africa used coal for 93% of its electricity generation needs, and
was the second most dependent coal-to-electricity country in the world, after
Mongolia. Apart from its domestic needs, South Africa is currently the world’s
sixth largest coal exporting country, with exports in excess of 70 million
tonnes in 2013.
Coal plays a crucial role in the South African energy-economy and is fuelling
local industry. The consumption of coal in South African coal-fired power
stations will continue in the near future.
Both local and international markets are, at present, highly dependent on
South Africa being a main provider of coal, now and in the future. The
identification and exploitation of new coal reserves in South Africa is thus a
prerequisite in meeting this demand.
In addition coal plays a crucial role in the provincial economy of
Mpumalanga, where the proposed Project is located and coal mining is a key
economic activity in this Province. According to the Mpumalanga Provincial
Growth and Development Strategy (PGDS 2004 – 2014) (3), Mpumalanga
contributed 7.7% to the national Gross Domestic Product (GDP) in 2001. The
majority of the contribution to the provincial economy is made up by the
manufacturing sector (28.0%) followed by the mining sector (18.0%). To
provide growth and development within the Province, the PGDS has
prioritised economic development comprising inter alia, job creation, Small
Medium and Micro Enterprises (SMMEs), BEE, mining, manufacturing,
tourism and agriculture
The economy of the Gert Sibande District Municipality is supported
predominantly by mining and manufacturing. Other key sectors that drive
the economy of the District include energy supply and agriculture (Nhlabathi,
2008). In terms of employment mining employs 14.3% of the population in the
district (Nhlabathi, 2011). In terms of employment in the mining sector in the
local municipalities, 7.6% of the population from Mkhondo in 2011 (Mtshali,
2016) and 2.4% of the population from Dr Pixley Ka Isaka Seme in 2012
(Malatsi, 2015) were employed in the mining industry.
Both the Mkhondo Local Municipality IDP (Mtshali, 2016) and the Dr. Pixley
Kalsaka Seme IDP (Malatsi, 2015), recognise the importance of mining as a key
(1) World Coal Organisation; https://www.worldcoal.org/resources. Accessed 19 April 2015 (2) US Energy Information Administration; https://www.eia.gov/. Accessed 19 April 2015 (3) Mpumalanga Province. Provincial Growth and Development Strategy. www.pgds.gov.za/framework.asp. Accessed 20
April 2015
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
2-41
economic sector within these two Municipalities and both recognise the
significant challenge they are facing, in balancing the economic and
developmental needs of the Region with the needs of environmental
protection.
The proposed Project components being applied for as part of this application
are key factors from a strategic point of view for Kangra Coal. Given that the
existing operations are approaching depletion (in 3 years’ time
approximately), new resources are required to maintain the current levels of
production and employment. Should the mining operations close, jobs will be
lost, both directly at the mine and indirectly in terms of local contractors and
businesses providing goods and services to the operation, as well as the
people dependent on those working for Kangra Coal (both directly and
indirectly).