04-0605TNtechnical archives
TRIC Training Log: 06-05-04
Client: ARS Rescue Rooter, Memphis, TN
Job: Residence, under driveway
Pull: 45’ / 4” / SDR17
![Page 2: 2004_0605TN](https://reader033.vdocument.in/reader033/viewer/2022052602/55a1a0091a28ab315c8b4796/html5/thumbnails/2.jpg)
04-0605TNtechnical archives
For Sale: A grand old home in the historic district of Memphis. Sewer needs work.
![Page 3: 2004_0605TN](https://reader033.vdocument.in/reader033/viewer/2022052602/55a1a0091a28ab315c8b4796/html5/thumbnails/3.jpg)
04-0605TNtechnical archives
The connection: Under the driveway, joining the cottage adjacent to the garage (behind trees) with the main house.
![Page 4: 2004_0605TN](https://reader033.vdocument.in/reader033/viewer/2022052602/55a1a0091a28ab315c8b4796/html5/thumbnails/4.jpg)
04-0605TNtechnical archives
Saving the surface: The connection at the house is roughly 8’ deep; all excavation is done in the planted areas.
![Page 5: 2004_0605TN](https://reader033.vdocument.in/reader033/viewer/2022052602/55a1a0091a28ab315c8b4796/html5/thumbnails/5.jpg)
04-0605TNtechnical archives
Garden view. Note excavator to the right.
![Page 6: 2004_0605TN](https://reader033.vdocument.in/reader033/viewer/2022052602/55a1a0091a28ab315c8b4796/html5/thumbnails/6.jpg)
04-0605TNtechnical archives
Entry point: PVC irrigation pipe can be cut. Unused steel pipe protruding above surface at edge of hole will also be removed.
![Page 7: 2004_0605TN](https://reader033.vdocument.in/reader033/viewer/2022052602/55a1a0091a28ab315c8b4796/html5/thumbnails/7.jpg)
04-0605TNtechnical archives
Facing.
![Page 8: 2004_0605TN](https://reader033.vdocument.in/reader033/viewer/2022052602/55a1a0091a28ab315c8b4796/html5/thumbnails/8.jpg)
04-0605TNtechnical archives
Keep blades moving: Watch for full ribbons of trim from both faces.
![Page 9: 2004_0605TN](https://reader033.vdocument.in/reader033/viewer/2022052602/55a1a0091a28ab315c8b4796/html5/thumbnails/9.jpg)
04-0605TNtechnical archives
Clean and check: Remove shaved material from fusing area.
![Page 10: 2004_0605TN](https://reader033.vdocument.in/reader033/viewer/2022052602/55a1a0091a28ab315c8b4796/html5/thumbnails/10.jpg)
04-0605TNtechnical archives
Before heating: Double check mating surfaces, and remove any debris from edges with a clean cloth.
![Page 11: 2004_0605TN](https://reader033.vdocument.in/reader033/viewer/2022052602/55a1a0091a28ab315c8b4796/html5/thumbnails/11.jpg)
04-0605TNtechnical archives
Heating the pipe: Make firm, even contact with heating iron, then use neutral pressure.
![Page 12: 2004_0605TN](https://reader033.vdocument.in/reader033/viewer/2022052602/55a1a0091a28ab315c8b4796/html5/thumbnails/12.jpg)
04-0605TNtechnical archives
The melt: This varies according to pipe size and rating; for SDR 17 in smaller sizes (3”, 4”, 6”) look for a melt of 1/8” or slightly less.
![Page 13: 2004_0605TN](https://reader033.vdocument.in/reader033/viewer/2022052602/55a1a0091a28ab315c8b4796/html5/thumbnails/13.jpg)
04-0605TNtechnical archives
Entry: Breaking out the old pipe. Note minimal excavation.
![Page 14: 2004_0605TN](https://reader033.vdocument.in/reader033/viewer/2022052602/55a1a0091a28ab315c8b4796/html5/thumbnails/14.jpg)
04-0605TNtechnical archives
Entry: Cutting away unused protruding pipe in “drag path” (left).
![Page 15: 2004_0605TN](https://reader033.vdocument.in/reader033/viewer/2022052602/55a1a0091a28ab315c8b4796/html5/thumbnails/15.jpg)
04-0605TNtechnical archives
Feeding the cable: In many cases, it is not necessary to use the duct rod to pull cable through the line. Here the pull is downhill, relatively short, and steep.
![Page 16: 2004_0605TN](https://reader033.vdocument.in/reader033/viewer/2022052602/55a1a0091a28ab315c8b4796/html5/thumbnails/16.jpg)
04-0605TNtechnical archives
Positioning the new pipe: Making the approach as direct as possible.
![Page 17: 2004_0605TN](https://reader033.vdocument.in/reader033/viewer/2022052602/55a1a0091a28ab315c8b4796/html5/thumbnails/17.jpg)
04-0605TNtechnical archives
Attaching hydraulic hoses.
![Page 18: 2004_0605TN](https://reader033.vdocument.in/reader033/viewer/2022052602/55a1a0091a28ab315c8b4796/html5/thumbnails/18.jpg)
04-0605TNtechnical archives
Pulling end: Cribbing the wall to provide even support for the resistance plate.
![Page 19: 2004_0605TN](https://reader033.vdocument.in/reader033/viewer/2022052602/55a1a0091a28ab315c8b4796/html5/thumbnails/19.jpg)
04-0605TNtechnical archives
Ready for tension: Keep pressure gauge visible.
![Page 20: 2004_0605TN](https://reader033.vdocument.in/reader033/viewer/2022052602/55a1a0091a28ab315c8b4796/html5/thumbnails/20.jpg)
04-0605TNtechnical archives
Feeding the pipe: It’s important to give the bursting head a good start.
![Page 21: 2004_0605TN](https://reader033.vdocument.in/reader033/viewer/2022052602/55a1a0091a28ab315c8b4796/html5/thumbnails/21.jpg)
04-0605TNtechnical archives
Well underway: After a good entry, pipe often needs little attention.
![Page 22: 2004_0605TN](https://reader033.vdocument.in/reader033/viewer/2022052602/55a1a0091a28ab315c8b4796/html5/thumbnails/22.jpg)
04-0605TNtechnical archives
End of the pull: Removing the cotter pin from the clevis bolt.
![Page 23: 2004_0605TN](https://reader033.vdocument.in/reader033/viewer/2022052602/55a1a0091a28ab315c8b4796/html5/thumbnails/23.jpg)
04-0605TNtechnical archives
“Bumping”: Fuse enough pipe to have this option when the pull is done.
![Page 24: 2004_0605TN](https://reader033.vdocument.in/reader033/viewer/2022052602/55a1a0091a28ab315c8b4796/html5/thumbnails/24.jpg)
04-0605TNtechnical archives
Photo Op: Hands-on Management!
![Page 25: 2004_0605TN](https://reader033.vdocument.in/reader033/viewer/2022052602/55a1a0091a28ab315c8b4796/html5/thumbnails/25.jpg)
04-0605TNtechnical archives
Ready to connect: When possible, give plenty of cutoff length behind the head. (Note brass water supply line, which was easily avoided with the TRIC system.)