Partner States
Cyprus Egypt France
Greece Israel Italy Jordan Lebanon
Malta Palestinian Authority Portugal Spain Syria Tunisia
ENPI CBC Mediterranean Sea Basin
set up by the Autonomous Region of Sardinia as Joint Managing Authority
2010 Annual Implementation Report
INDEX
IDENTIFICATION
A. TECHNICAL PART
B. FINANCIAL PART
ANNEXES:
ANNEX 1 - EXTERNAL AUDIT REPORT
- Expenditure And Revenue Verification Report 2010
- Auditor’s Report – Report On The Financial Statements
- Bank Account Statements
ANNEX 2 - INTERNAL AUDIT REPORT
REQUEST FOR PRE-FINANCING 2011
IDENTIFICATION
Operational Programme
ENPI Cross Border Cooperation
Cooperation Area: Mediterranean
Programming Period: 2007-2013
Programme Title: ENPI CBC Mediterranean Sea Basin
Date of approval by the European Commission:
Decision EC (2008) 4242 of 14.08.2010
Joint Managing Authority
Autonomous Region of Sardinia
Ufficio Speciale ENPI CBC MED
Via Bacaredda 184
09127 Cagliari - Italy
Email: [email protected]
Annual Implementation Report Reporting years: 2010
Date of approval of the report by the Programme Joint Monitoring Committee:
29.06.2011 (written procedure)
A. TECHNICAL PART
INDEX
Preamble ............................................................................................................................................................ 3
1. Activities carried out by the Managing Bodies ......................................................................................... 4
1.1 Joint Monitoring Committee ..................................................................................................................... 4
1.2 Project Selection Committee ................................................................................................................... 7
1.3 Joint Managing Authority ....................................................................................................................... 10
1.3.1 Organisation of the JMA ............................................................................................................. 10
1.3.2 Technical Assistance activities carried out (2010) ...................................................................... 11
1.4 Joint Technical Secretariat .................................................................................................................... 13
1.5 Branch Offices ....................................................................................................................................... 15
1.5.1 Valencia Branch Office ............................................................................................................... 15
1.5.2 Aqaba Branch Office ................................................................................................................... 16
1.6 Complementarity with other instruments ............................................................................................... 16
1.7 Difficulties encountered ......................................................................................................................... 17
1.8 Monitoring Arrangements ...................................................................................................................... 18
2. Project Implementation .............................................................................................................................. 22
2.1 Standard projects ................................................................................................................................... 22
2.1.1 The First Call for proposals ......................................................................................................... 22
2.1.2 The evaluation and selection process ........................................................................................ 22
2.1.3 List of preselected projects ......................................................................................................... 27
2.2 Strategic projects ................................................................................................................................... 31
3. Information and communication activities .............................................................................................. 34
3.1 2011 Information and Communication Plan ......................................................................................... 34
3.1.1 Drafting the 2011 Information and Communication Plan ............................................................ 34
3.1.2 Overview of the 2011 Information and Communication Plan ..................................................... 35
3.1.3 Specific Features of The 2011 Information and Communication Plan ...................................... 36
3.1.4 Support to the Implementation of the Programme Coomunication Strategy: Branch Offices Working Plans ...................................................................................................................................... 37
3.2 Information and Communication Actions ............................................................................................... 37
3.2.1 Promotion at External Events ..................................................................................................... 37
3.2.2 Programme Website ................................................................................................................... 39
3.3 Communication activities carried out by the Branch Offices ................................................................. 42
3.3.1 Valencia Branch Office ............................................................................................................... 42
3.3.2 Aqaba Branch Office ................................................................................................................... 44
2
4. Programme of activities to be implemented the following year ............................................................ 45
GANTT Chart Indicative Activity Plan 2012 ................................................................................................. 46
3
PREAMBLE
According to Article 28 of Council Regulation (EC) 951/2007of 9 August 2007 laying down
implementing rules for cross-border cooperation programmes financed under Regulation (EC)
1638/2006 every year the Joint Managing Authority (JMA) shall submit to the European
Commission by 30 June an annual report on the implementation of the Joint Operational
Programme approved by the Joint Monitoring Committee (JMC) and certified by the audit report.
The present document is the second Annual Report about the ENPI CBC MED Programme
covering 2010 and it is approved by the JMC through written procedure.
The activities reported are clustered as follows:
- activities related to Programme implementation;
- activities related to projects implementation;
- activities related to communication.
As documented throughout this report, considerable progress was made in each of these areas.
Indeed, the approval of project proposals within the first call for standard projects by the JMC -
despite the time-consuming process - and the launch of the call for strategic projects early in 2011
proved to be concrete achievements of the fruitful cooperation among the participating countries.
Moreover, these activities were carried out in parallel with the definition of several open procedures
foreseen under the technical assistance budget.
Taking full advantage of the activities implemented in 2008 and 2009 concerning the setting-up of
the Programme bodies, a detailed plan of improvements was considered in 2010 as a starting point
for the future of the ENPI CBC MED cooperation.
4
1. ACTIVITIES CARRIED OUT BY THE MANAGING BODIES
1.1 JOINT MONITORING COMMITTEE
The JMC consists of a national delegation for each of the 14 countries participating in the
Programme, the Director of the JMA acting as Chairperson, a Secretary, an observer from the
European Commission and one representative per each Branch Office.
Each national delegation may include up to a maximum of five members, however each country
can express only one vote and the voting right is attributed to only one representative within each
delegation (the Head of Delegation or his/her substitute).
The third JMC meeting took place in Valencia (Spain) on December 13th and 14th 2010. The
main decisions adopted were:
• Approval of the list of 31 projects selected under the first call for proposals for standard
projects, for a total amount of € 42.514.125.
• Decision to extend the composition of the PSC to 14 members - one from each participating
country - for the next two calls for proposals (strategic and standard projects); the Joint
Operational Programme has to be modified accordingly.
• Approval of the indicative Working Plan 2011.
• Approval of the indicative Financial Plan 2011.
• Decision to have only one call for strategic projects during the Programme lifetime (to be
launched in 2011), concentrating all the financial resources available for this typology of
projects (€ 62,4 million).
• Agreement on a JMC common statement to be submitted to the European Commission,
concerning the possible increase of Programme resources.
• Approval of the modified JMC Rules of Procedure.
Further to the above mentioned meetings, the JMC has been directly involved in the overall
Programme management and has taken some important decisions via written procedures (see
table below) according to its Rules of Procedure.
5
Content of the written procedure Dates
(from – to) Results
Composition of the Projects Selection
Committee for the first Call for proposals for
standard projects.
05/01/2010
–
19/01/2010
Approval of PSC composition
Terms of reference for the selection of a pool
of senior experts in charge of the definition of
the call for strategic projects
14/01/2010
–
28/01/2010
Approval of the Terms of Reference for the
selection of experts
Updated composition of the Joint Monitoring
Committee
15/02/2010
–
01/03/2010
Approval of the updated composition of the
JMC (changes in the national delegations of
Spain, Greece and Israel)
Allocation of resources for the recruitment of
a pool of senior experts in charge of the
definition of the call for strategic projects
02/03/2010
–
16/03/2010
Approval of the proposed financial allocation
(€ 157.858,00 - Technical Assistance budget)
Annual Work Programme for Grants 2010
04/03/2010
–
18/03/2010
Approval of the Annual Work Programme for
Grants 2010 (2 calls foreseen, one for
strategic and one for standard projects)
Updated composition of the Projects
Selection Committee for the first Call for
proposals for standard projects
16/03/2010
–
31/03/2010
Approval of the updated PSC composition
(two additional internal assessors)
Updated composition of the Projects
Selection Committee for the first Call for
proposals for standard projects
22/04/2010
–
06/05/2010
Approval of the updated PSC composition
(Lebanese and Egyptian voting members)
Modification of 2009 financial plan: coverage
of travel and accommodation costs for JTS
candidates participating in the final interviews
29/04/2010
–
13/05/2010
Approval of the proposed modification of 2009
financial plan (additional € 50.000)
Appointment of external assessors for the
first Call for proposals for standard projects
12/05/2010
–
26/05/2010
Approval of the list of external assessors
6
Modification of 2009 financial plan: additional
resources for the remuneration of external
assessors
13/05/2010
–
27/05/2010
Approval of the proposed modification of 2009
financial plan (additional € 50.000)
Inclusion of the staff of the INTERACT ENPI
Point Florence as observers in the PSC for
the first Call for proposals for standard
projects
25/05/2010
–
08/06/2010
Approval of the inclusion of INTERACT
observers in the PSC
First Call for proposals for standard projects
– Evaluation of projects involving Moroccan
partners
22/06/2010
–
06/07/2010
Objection to the JMA proposal and
consequent exclusion of the projects involving
Moroccan partners from the evaluation
process
Updated composition of the Projects
Selection Committee for the first Call for
proposals for standard projects.
08/07/2010
–
22/07/2010
Approval of the updated PSC composition
(Chairperson, Egyptian and Palestinian
substitute members, EC observer, additional
internal assessor)
Updated composition of the Projects
Selection Committee for the first Call for
proposals for standard projects.
12/07/2010
–
26/07/2010
Approval of the updated PSC composition
(Portuguese substitute member)
First Call for proposals for standard projects
– Increase of the financial allocation
03/08/2010
–
17/08/2010
Approval of the increase of the financial
allocation of the first call for standard projects
from € 32,8 million to € 55 million.
First Call for proposals for standard projects
– Administrative verification: projects rejected
for non compliance with criterion No. 3
(signature of the Grant Application Form)
29/09/2010
–
13/10/2010
Objection to the JMA proposal and
consequent readmission of the two concerned
projects to the evaluation process
First Call for proposals for standard projects
– Administrative verification: projects rejected
for non compliance with criterion No. 8
(signature of the Partnership Statements)
29/09/2010
–
13/10/2010
Approval of the JMA proposal and consequent
definitive exclusion of the two concerned
projects from the evaluation process
New selection procedure for the recruitment
of the second JTS financial officer
12/10/2010
–
26/10/2010
Approval of the launching of a selection
procedure for the recruitment of the second
JTS financial officer
7
Updated composition of the Projects
Selection Committee for the first Call for
proposals for standard projects.
18/10/2010
–
01/11/2010
Approval of the updated PSC composition
(two additional internal assessors)
Annual Implementation Report 2008-2009
21/10/2010
–
05/11/2010
Approval of the Annual Implementation Report
for the years 2008-2009
Information and Communication Plan 2011
(1st written procedure)
25/10/2010
–
08/11/2010
Objection to the JMA proposal and
consequent launching of a second written
procedure
Information and Communication Plan 2011
(2nd
written procedure)
22/11/2010
–
06/12/2010
Approval of the Information and
Communication Plan 2011
Call for tenders: support to the JMA for the
implementation of information and
communication activities and for the
organization of JMC meeting
24/11/2010
–
08/12/2010
Approval of the launching of the call for
tenders and of the related financial allocation
1.2 PROJECT SELECTION COMMITTEE
According to the Joint Operational Programme and to the Guidelines for Applicants, the Projects
Selection Committee (PSC) is the body responsible for carrying out and supervising the overall
evaluation and selection process. The PSC, in carrying out the projects evaluation, could be
supported by internal and external assessors.
As far as the first call for proposals is concerned, the PSC was composed of 7 voting members
from Egypt, Greece, Jordan, Spain, Lebanon, Portugal and Palestinian Authority. These countries
were selected through a sort by lot during the first JMC meeting in Cagliari (November 2008).
Despite several requests made by the JMA to the selected countries, only on January 5, 2010, the
complete list of PSC members, including the voting and advisory/substitute members, the
Chairperson, the Secretary and the JMA staff appointed as internal assessors, was submitted by
the JMA to the JMC for its approval through a written procedure. On January 19, 2010 the JMC
approved the composition of the Projects Selection Committee for the first Call for standard
projects.
Consequently, the JMA adopted through an internal act (No 8 / 260 of 20/01/2010), the formal
appointment of the PSC. According to the same procedure, the list of the PSC members was
8
updated several times during the whole evaluation process mainly due to the unavailability of the
designated members to attend all the meetings. The different steps are indicated in the following
table:
Written procedures for the JMC approval of the first
PSC composition and Formal appointment of the
PSC
From 05/01/2010
to 19/01/2010
JMA internal act N. 8 / 260
dated 20.01.2010
Written procedures for the JMC approval of the
updated composition of the PSC
From 16/03/2010
to 31/03/2010
JMA internal act N. 24 / 1010
dated 08.04.2010
Written procedures for the JMC approval of the
updated composition of the PSC
From 22/04/2010
to 06/05/2010
JMA internal act N. 38 / 1772
dated 18.05.2010
Written procedures for the JMC approval of the
updated composition of the PSC
From 08/07/2010
to 22/07/2010
JMA internal act N. 49 / 2823
dated 27.07.2010
Written procedures for the JMC approval of the
updated composition of the PSC
From 12/07/2010
to 26/07/2010
Written procedures for the JMC approval of the
updated composition of the PSC
From 18/10/2010
to 01/11/2010
JMA internal act N. 77 / 3679
dated 03.11.2010
During the evaluation procedure of the projects submitted under the first call, the Project Selection
Committee met three times always in Cagliari, at the JMA premises:
1) First meeting on the 8th and 9th of June 2010 for the STEP 1 - Opening session and
administrative check;
2) Second meeting from the 27th to the 29th of July 2010 for the STEP 2 - Quality evaluation;
3) Third meeting from the 24th to the 25th of November 2010 at the end of the STEP 3 -
Eligibility check.
A training session addressed to the PSC members was developed by INTERACT (8th June)
before starting the works of the first meeting. In the same occasion the Declarations of Impartiality
9
and Confidentiality of the PSC Voting Members and advisors were distributed and collected. Finally
the rules of procedure of the PSC were described and adopted (the same rules applicable to the
JMC with some minor modifications due to the limited composition of the PSC).
The description of the evaluation procedure is included in Section 2 Project Implementation, par.
2.1 - Standard projects.
10
1.3 JOINT MANAGING AUTHORITY
1.3.1 ORGANISATION OF THE JMA
Comparing to the situation in 2009, the JMA staff has been integrated with two additional human
resources:
1. the Head of Internal Audit Unit has been appointed in April 2010.
2. An additional contract has been awarded in March 2010 to the second candidate included
in the ranking list of profile 1 - Expert in the management of international relations, under
the public procedure for the recruitment of external experts closed in December 2009.
Moreover, in January 2010 a “First-level control office”, independent form the JMA, has been
established within the Presidency of the Sardinia Region (General Directorate) in order to carry out
a preliminary check on the JMA technical assistance procedures for the purchase of goods and
services.
Table 1. JMA organisational chart
JMA Director
Operational
Management Unit (6)
Financial and
certification Unit (4) Internal Audit Unit
(2)
1 Head of Unit 5 officers
Authorising Section
1 Head of Unit
1 officer
1 Head of Unit 1 officer
Accounting Section
1 Head of Unit
1 officer
External experts (3)
11
1.3.2 TECHNICAL ASSISTANCE ACTIVITIES CARRIED OUT (2010)
During 2010, different technical and administrative procedures were launched by the Operational
Management Unit for the purchasing of goods and services from external economic operators. All
the contracts were awarded according to the Italian law on the public procurements (Legislative
decree n° 163 of 12 April 2006).
The technical assistance procedures are listed below:
a. External Audit on JMA direct expenditures 2008/2009 and 2010
A negotiated procedure for the assignment of external audit service for the verification of the JMA
direct expenditures 2008/2009 and 2010 was launched in January, 2010 and closed in March
2010.
b. Creation of an economic operators roster
During 2010, a roster of economic operators was created by the JMA in order to proceed with the
purchase of goods and services.
The call for expression of interest was published on February 3, 2010. Only the economic
operators in possession of formal and administrative requirements as foreseen in the public notice
have been included in the lists organized according the different categories of goods and services.
The roster was formally created on April 8, 2010 and published both in the Programme and in the
Autonomous Region of Sardinia official websites. It will be annually updated and enables the JMA
to award contracts for the provision of goods and services through negotiated procedures inviting
at least 5 economic operators per procedure to submit offers.
c. Selection of the Joint Technical Secretariat and Branch Offices Staff
The public notice for the selection of the JTS and Branch Offices staff was published on 17th
February, 2010.
The selection process, conducted with the support of a company specialized in human resources
selection, was concluded on June 11, 2010, and contracts were signed starting from September,
2010.
An ad-hoc selection procedure has been then launched in October 2010 in order to recruit the
second financial officer of the JTS (only one of the five candidates included in the ranking list has
12
accepted the offered post) based on the same criteria already set for this profile in the previous
public notice. The procedure was managed by the JMA and was closed in February 2011 with the
publication of the final ranking list.
More details on the JTS and Branch offices recruitment procedure are included in par 1.4.
d. Organisation of the JMC and PSC meetings
In May 2010, the JMA selected an external company through a negotiated procedure and award a
contract for the organization of the JMC meeting foreseen in Valencia in December 2010 and the
two PSC meetings foreseen under the first call for standard projects.
A separate procedure has been carried out in October 2010 for the organization of the 3rd PSC
(November 2010) and a different company was chosen.
The services provided by the selected companies (Consulviaggi srl and Promoteo) included,
among others, the booking and the purchasing of travel tickets, the hotel reservations, the rental of
meeting room and appropriate conference equipment, the organization of coffee and lunch breaks.
e. Implementation of the Programme Accounting System
In November 2009 the Operational Management Unit undertook a research within the Autonomous
Region of Sardinia for IT systems and their related applications that could be used to set up a
dedicated software for the management of the Programme, as per JOP.
In 2010 the Region General Accounting Office decided to deactivate the software used for the
extraordinary accounting management; since this software was used for the financial management
of the ENPI Programme too, the Operational Management Unit was charged to find a prompt
solution to provide the Programme with a software enabling analytical monitoring of the specific
accounts of the Programme, as well as a separate monitoring of the expenditures of the various
managing structures (EC Regulation n. 951/07 of 9 August 2007).
The software was realized through an Agreement with the IT Unit of the General Affairs
Department of the Autonomous Region of Sardinia, extending the contract signed in 2009 by the
same Department with the company “Accenture”. The software, integrated with the basic IT system
of the Region (SIBAR), is in use since October 2010.
f. Call for tenders on communication activities
13
In order to ensure a smooth implementation of the communication activities until the end of the
Programme life cycle, the JMA launched on 15 December 2010 an international call for tenders.
The tender aims at selecting a external service provider to support the logistical arrangement
related to the implementation of the following actions, avoiding to tender any single communication
action:
- organization of the meetings of the Joint Monitoring Committee, Heads of Delegation and
Projects Selection Committee including services such as travel, accommodation of participants,
rent and arrangement of meeting rooms, catering, interpreting, photographers;
- organization of the Programme information events (Annual conferences, events on the calls for
proposals, technical seminars on projects implementation) with particular reference to the rent
of meeting rooms, interpreting, photographers, catering.
Given the administrative delays necessary for the assessment of the bids submitted according to
the Italian legislation, the tender has been awarded in June 2011.
g. Selection of external assessors for the evaluation of standard projects
A public procedure for the recruitment of the external assessors in charge of the evaluation of
standard projects submitted within the first call for proposals, was launched by the JMA in
December 2009 and closed in January 2010. The JMA received and assessed 244 candidatures,
of which 44 were included in the roster. Only 38 assessors, from those included in the long list,
were contracted by the JMA in June (the others did not accept the offered post).
h. Selection of thematic experts
A public procedure for the recruitment of 8 experts (6 thematic experts, 1 team leader, 1 specialist
in programme management procedures) in charge of the definition of the terms of reference of
strategic projects, was launched by the JMA on 25 March, 2010.
Since 4 positions out of 8 remained uncovered after the conclusion of the first selection procedure,
an additional procedure was then launched on 23 June, 2010.
The recruitment process was finally completed with the contracts’ signature on 15 October, 2010.
1.4 JOINT TECHNICAL SECRETARIAT
14
The public notice for the selection of the JTS and Branch Offices staff was published on February
17, 2010.
The selection was carried out with the support of the company SAM Headhunting Italy, chosen by
the JMA through a public procedure, providing executives, managers and specialists search
services. It started in April 2010 and closed in June 2010 and was articulated into three main steps:
First step: a preliminary selection performed in order to assess the possession of the
admission criteria and the formal regularity of the applications. A ranking list has been
established for each profile.
Second step: phone interviews for the first ten candidates of each profile in order to establish
a further ranking list. The first 5 candidates for each profile entered the 3rd step (final
Interview).
Third step: final interviews for the 5 selected candidates for each profile conducted by an
evaluation committee established by the JMA and composed of JMA staff and other four
members representing the Branch Offices and two participating countries (France and
Israel). The interviews took place from 7 to 11 June 2010 in Rome, at the premises of the
Sardinia Region.
The final ranking list was approved by the JMA on 25 June, 2010 and published on the Programme
official website.
As for the JTS staff, the contracts were signed by the JMA starting from September, 2010 for the
following profiles:
- 2 project officers
- 1 financial officer
- 1 communication officer
- 1 assistant
Due to the refusal by the two first ranked candidates, the position of coordinator has not been
assigned and the role has been taken by the Director of the JMA.
As regards the profile of financial officer, only one of the five candidates included in the ranking list
has accepted the offered post (the others refused or asked to postpone the recruitment until mid
2011). An ad-hoc selection procedure has been then launched in October 2010 in order to recruit
15
the second financial officer based on the same criteria already set for this profile in the previous
public notice. The procedure was managed by the JMA and was closed in February 2011 with the
publication of the final ranking list.
The recruited JTS personnel attended a two-day-training delivered by Interact and RCBI on 13 and
14 October, 2010. This training helped a deeper understanding of the roles and responsibilities
both in general and with specific regard to relevant activities concerning project management as:
- Support to project applicants during technical and financial monitoring;
- Audits at programme level and expenditures verification;
- Information and communication activities.
At the end of 2010, the JTS structure was the following:
Section Providing
Assistance to Project
Applicants
Section for
Communication,
Information and
Visibility
1 Assistant
2 Project Officers
1 Communication Officer
1 Financial Officer
Financial Section
JTS Coordinator
JMA Director
(ad interim)
A. Catte
1.5 BRANCH OFFICES
1.5.1 VALENCIA BRANCH OFFICE
16
The public procedure for the recruitment of the JTS and Branch offices staff was closed in June
2010 (see paragraph on the Joint Technical Secretariat). As for Valencia Branch Office two
positions were contracted directly by the Generalitat Valenciana, as following:
- 1 Coordinator of the Valencia Branch Office for the Western Mediterranean
- 1 Coordinator of the Liaison Office ENPI CBC MED - MED Programmes
Both positions have been officially incorporated in the body structure of ENPI CBC MED
Programme on 1st October 2010, working full time for the Programme.
According to the Annual Communication Plan 2010, Valencia Branch Office should have carried
out some specific events and activities but some delays related to the Programme procedures and
activities have prevented Valencia Branch Office from working as planned.
1.5.2 AQABA BRANCH OFFICE
The public procedure for the recruitment of the JTS and Branch offices staff was closed in June
2010 (see paragraph on the Joint Technical Secretariat). As for Aqaba Branch Office, three
positions were contracted directly by ASEZA (Aqaba Special Economic Zone Authority), as
following:
- 1 Coordinator of Aqaba Branch Office for the Eastern Mediterranean;
- 1 accountant/administrator;
- 1 assistant.
See par. 3.3.2 for more details on communication activities carried out by Aqaba Branch Office.
1.6 COMPLEMENTARITY WITH OTHER INSTRUMENTS
In 2010 the JMA strived for a further improvement of its fruitful cooperation with other programmes
and initiatives. Regular exchanges, which also systematically occur through the Interact platform,
were intensified with CBC programmes for the definition of the procedures of the technical
assistance.
In particular, the JMA’s action was geared towards deeper exchanges (i.e. definition of the tender
procedure for the monitoring system) which proved to be very profitable for programme
17
implementation, coordination of national and transnational actions and offered a useful preliminary
base to support the smooth and efficient assistance to projects.
The exchange on daily management proceeded in 2010 also with the support and the integration in
the programme cycle management of the Liaison Office with the Mediterranean (MED) Programme
financed by the Structural Funds (under the European Territorial Cooperation Objective) located in
Valencia (Spain).
As previously reported, considering that this Programme concerns the same EU Member States -
and often the same eligible regions – than the ENPI CBC Mediterranean Sea Basin Programme,
the Liaison Office aims at coordinating the activities carried out by the two Programmes in order to
avoid the overlapping of project funds.
To this regard, the MED/ENPI Liaison Office kept on performing 4 main tasks:
- inform about particularities and differences between MED and ENPI CBC MED
Programmes;
- guide potential beneficiaries towards the right programme;
- promote exchange of experiences between the beneficiaries of MED and ENPI CBC MED
areas;
- encourage capitalisation of best practices and results achieved by the two programmes
MED and ENPI CBC MED.
1.7 DIFFICULTIES ENCOUNTERED
Some factors have been identified as having an impact on the development, management and
implementation of the Programme. Practical difficulties in getting visas for key stakeholder
(especially for PSC members) have caused some delays in organising meetings and events and
still represent a major challenge for this Programme which largely base its success on mobility.
The main difficulties encountered in 2010 were related to the implementation of the selection
procedure for the first call for proposals.
The very high number of applications received (599), required a long verification phase.
Furthermore, the delays in the designation of the PSC members by some Countries delayed the
formal appointment of the PSC and the formal launch of the selection process. This implied also a
18
lack of information on the projects submitted and the outcomes of the administrative check sent to
the JMC.
The number and formats of the application documents to be filled in were not effective in order to
avoid mistakes and to check inconsistencies among different sections and/or documents, as for
example: partnership information to be provided in different parts of the Grant Application Form
and to be cross checked with the Partnership Statements; budget information to be provided (and
cross checked) both in the Grant Application Form and in the Budget; budget forms with limited
and unclear information not including alert messages for detecting major mistakes or missing parts;
uncertainties on the application of the rule concerning the allocation of 50% of the budget to
activities implemented in Mediterranean Partner Countries, leading to mistakes in the related
budget table; list of adjoining regions not included in the Guidelines for Applicants; the call for
proposals launched under suspension clause, affecting projects including Moroccan partners.
Moreover, the notification of administrative check results to applicants led to a prolongation of the
planned time schedule (time necessary to prepare and notify letters, reply to requests for
information and treatment of more than 100 complaints).
In addition, the limited number of information events to support potential applicants turned out to be
one of the main problems leading (in combination with the formats used) to an high number of
rejections and requests for clarifications. These latter had to be sent to almost half of the submitted
applications, leading to time-consuming activities (time necessary to prepare letters, examine
clarifications and/or new documents provided by applicants and partners).
Finally, the national non binding consultations, which required some additional efforts, proved to be
not useful for the PSC. The large number of assessors (38) implied also different approaches to
the evaluation process despite the training seminar held by the JMA with the support of Interact in
June. Moreover, the lack of thematic focus of the ToRs for the external assessors (selected per
priority) required additional information on their previous experiences in order to best match
assessors and proposals.
1.8 MONITORING ARRANGEMENTS
According to art. 28 of the Implementing Rules the Annual Report shall report, among others, the
“measures undertaken to monitor, evaluate and audit projects, their results and actions undertaken
to remedy to the problems identified.”
19
This task was defined in 2010 as a systematic and continuous collecting, analysis and using of
information for the purpose of management and decision making of the day-to-day programme
implementation. Based on the two existing IT tools used by the JMA / JTS (one for projects
selection and the other one for accounting management) an open tender procedure was drafted to
select the best offer for the implementation of an integrated monitoring system. This design phase
was shared among a dedicated working group of the JMA and JTS from September onwards. The
internal meetings took into account also the experiences made by other ENPI CBC Programmes.
In this regard, the exchanges with the EC and other Programmes during the seminar held in
Bruxelles on 9-10 September were really helpful for the establishment and the use of effective
project/programme monitoring systems including methodological advices and technical references.
These latter were then considered for the definition of the open tender launched early in 2011.
In particular, the JMA/JTS focused the tender on the definition of a web platform able to regularly
update all relevant stakeholders on the extent of achievement of objectives and progress on the
use of allocated funds striving towards greater cross-border cooperation effectiveness.
The final version of the IT monitoring system will be established after the final selection of the
system supplier (contractor) but it will be divided into three main components:
- Management and decision making
- Projects monitoring, reporting and control
- Statistics
However, the future monitoring system will have as main reference for data collection the model
format defined in the PRaG rules, the Result Oriented Monitoring (ROM) established by Europaid
and relevant best practices at international level considered according to specific emerging needs.
In particular, the monitoring system shall support the:
- Programme and project document management keeping complete documentation covering all
steps in the life cycle of all call for proposals (standard and strategic);
- Project management (from submission to selection to contracting and closure, e-submission of
interim reports and requests for payment by the Applicants, verification process within the
system)
20
- Financial management at Programme and project level (transfer of pre-financing and balance
payment, expenditure verification)
- Project and programme level monitoring (indicators) and audits conducted by the JMA on a
sample of projects
- Programme level finances including management of Technical Assistance
- Various and flexible reporting functions including storing of data on on-spot-checks,
irregularities and recoveries started by the JMA.
Moreover the monitoring system shall be able to:
- include standardised procedures / work-flow of managing bodies and be interlinked with other
tools and forms (e.g. progress reports forms/checks, field visits, outcomes of ROM visits, on-
spot checks etc.);
- process both project proposals submitted within the calls and activity and financial reports of
approved projects presented by the Applicants;
- be selective and flexible: different user rights and quick adaptation to changes shall be
defined;
- be interactive uploading formats in word, excel, pdf and including comments, corrections,
email etc.;
- generate and export both predefined statistics and user-defined statistics according to the
input received from different forms;
- contain the input and the processing of the data at operation level as well as of the main data
at the Project Partner level in case of approved projects;
- provide end users with various data report sheets;
- be accessible from everywhere.
With regard to the existing financial IT system - in the framework contract used by the Region for
its ordinary accounts - the JMA set up in 2010 a new computerized accounting system to manage
the Programme’s funds. The ENPI accounting system is based on the SAP (Systems Applications
and Products) accounting software which has been adopted by the Regional Sardinian Authority. It
is an Accrual Based Accounting System (ABAC) organized by modules, which incorporates the
four accounting systems: Fund Management, Financials, Controlling, Project System. The ENPI
21
computerized accounting system has been designed, personalized and adapted, by the JMA to
meet the specific needs of the ENPI Programme, as follows:
- The separate and independent drawing up of accounts (according to art. 22 IR 951/2007);
- The separate and mutually incompatible function of the authorising officer and accounting
officer (according to art 14 IR 951/2007);
- The requested signatures of both the authorizing officer and the accounting officer (according
to art 21 IR 951/2007);
- A Bank Reconciliation: The JMA shall present the JMC with reports reconciling these
accounts with the balance in the bank account for the Programme. (art. 22 IR 951/2007) and
report (back on) reconciling payments and revenues with the bank account for the
Programme (art. 28 IR 951/2007);
- An Annual financial report with the amounts allocated to the JMA by the Commission, the
payments made and amounts recovered by JMA for technical assistance and for projects
(art. 28 IR 951/2007).
Finally, the definition of the financial circuits of the Programme was successfully and timely
completed according to the provisions set by the Italian law that foresees that all the European
Funds should transit through a bank account at the Italian Ministry of Economic and Finance.
Several meetings have been made in order to define the flow of the ENPI funds from this account
to the Autonomous Region of Sardinia and to the bank account dedicated to the Programme. The
circuit has been defined and tested, in 2009 e 2010, with the request of the annual pre-financing
that was received in two tranches (one for the ERDF quota and the other for the ENPI).
22
2. PROJECT IMPLEMENTATION
2.1 STANDARD PROJECTS
2.1.1 THE FIRST CALL FOR PROPOSALS
The First Call for proposals for Standard projects was launched on 19 of May 2009 after a long
negotiation of the call documents with the participating countries and the European Commission
(see par. JMC). The call for proposals was originally open for 120 calendar days (until mid
September) but its deadline was postponed to 20 of October 2009 upon request of the majority of
the participating countries.
The call was open to all the four priorities and ten measures of the Programme and the total
allocated budget was 32,8 million euro. Following the decision of the JMC in August 2010, the
budget allocation for the call was increased to 55 million euro. The new budget breakdown for each
priority, according the percentages fixed by the JOP, was therefore set as follows:
PRIORITY PERCENTAGE AVAILABLE BUDGET
1. Promotion of socio-economic development and
enhancement of territories 40% € 22.000.000
2. Promotion of environmental sustainability at the
basin level 30% € 16.500.000
3. Promotion of better conditions and modalities for
ensuring the mobility of persons, goods and capitals 10% € 5.500.000
4. Promotion of cultural dialogue and local governance 20% € 11.000.000
TOTAL 100% € 55.000.000
2.1.2 THE EVALUATION AND SELECTION PROCESS
During 2010, the JMA started the evaluation and selection procedure for the first call for standard
projects. It was based on the legal framework applying to the implementation and management of
the ENPI CBC MED Programme, i.e. the ENPI Regulation and the ENPI CBC Implementing Rules,
23
the Practical Guide to contract procedures for EC external action (PRAG), the Joint Operational
Programme and the Application Pack published for the first call for proposals, in particular the
Guidelines for Applicants.
It was articulated into three main steps:
- STEP 1 – Opening session and administrative check;
- STEP 2 – Quality evaluation;
- STEP 3 – Eligibility check.
According to the Joint Operational Programme and to the Guidelines for Applicants, the body
responsible for carrying out and supervising the overall evaluation and selection process is the
Projects Selection Committee (PSC) composed of 7 members proposed by 7 Countries and
appointed by the JMC and supported by internal and external assessors.
The JMC approved the composition of the PSC and the list of independent external assessors
recruited by the JMA through a call for expressions of interest. Finally, the JMC has taken the final
decision on the projects to be financed as well as on the amount granted to them.
The participating Countries were also involved in the evaluation process through non binding
national consultations carried out during Step 2 of the procedure, focusing on the eligibility of the
proposed national partnerships in terms of technical and administrative capacity to implement
projects as well as on the coherence of the proposals with the policies and programmes at national
and regional level.
The JMA has acted as Contracting Authority in accordance with PRAG rules, ensuring respect and
compliance with the agreed procedures. Staff members of the JMA were appointed as Chairperson
and Secretary of the PSC and have acted as internal assessors of the projects (staff members of
the JTS were also involved as internal assessors during Step 3).
Detailed “Guidelines for Evaluation and Selection of project proposals” were drafted by the
JMA with the support of INTERACT, in accordance with the indications provided by the European
Commission. This document, adopted by the PSC and then sent to the JMC to ensure
transparency, illustrated the general principles applicable to the overall evaluation and selection
process and describes the methodology and the specific procedures to be followed in the different
24
phases (in particular Step 1 and Step 2), with reference to the actors involved, their responsibilities
and the outcomes of each step.
In order to guarantee the respect of the principles of transparency and confidentiality, the JMA has
developed a secure intranet system whose access has been given to the PSC members (and to
the EC and INTERACT observers). All the information and documents related to the projects
evaluation have been uploaded in the system for each step of evaluation. The system required a
personal user name and password provided by the JMA while the documents could be only
consulted online without the possibility to download them.
The JMA informed the JMC at the end of each Step on the state of play of the evaluation process.
The full list of projects submitted within the call for proposals (including the indication of those
passed and rejected at each step as well as the related reasons for selection or rejection) were
transmitted to the JMC only after the conclusion of the evaluation process by the PSC, in view of
the final JMC award decision.
Information to applicants were provided at each stage of the evaluation through official letters,
while no information on results of the evaluation process were delivered to any external actor.
STEP 1: OPENING SESSION AND ADMINISTRATIVE CHECK
The step 1 of the evaluation process has been developed through two phases: the opening
session and the administrative check carried out by the JMA staff acting as internal assessors.
During the opening session it has been verified that the submission deadline has been respected.
The administrative compliance check has assessed whether the project proposals satisfy all the
criteria mentioned in the checklist included in the Guidelines for Applicants (i.e. administrative
requirements and technical requirements).
Timeframe
Opening session: from the end of January to the beginning of February
Administrative check: February/May
First PSC meeting: 8th and 9th June 2010
Main results of Step 1
- Opening session
25
Total project proposals received: n. 599
Total projects admitted to the administrative check n. 591
- Administrative check:
Total number of rejected projects: n. 302
Total number of project admitted to the Step 2: n. 289
STEP 2: QUALITY EVALUATION
After the first meeting of PSC all the Applicants have been notified about the outcomes of the
Opening Session and the Administrative Check concerning their project proposals.
Having these communication raised some complaints from the Applicants whose proposals have
been rejected, the JMA has replied to all them through official letters and immediately informing the
PSC in case of complaints accepted because justified, in order to assess their quality.
The assessment carried out by independent external assessors
38 external assessors were recruited by the JMA through a public procedure in June 2010. They
all received complete guidance and technical support during the quality assessment. In addition,
34 among them attended a one-day training held in Rome mid-June 2010 on the Programme
priorities, legal framework and evaluation criteria. Information on how to fill in the evaluation grid,
how to score and comment sub-criteria and on the IT system completed the training session.
All projects have been assigned to the external assessors by using the above mentioned dedicated
IT system with a limited, secure, and temporary access to the assigned project proposals forms
(around 15 each) and related documents of the Application Pack (Grant Application Form, Logical
Framework and Budget).
The external quality assessment lasted about one month. An ongoing and an internal quality check
were performed during the assessment by the JMA officers and then by the PSC Chairperson.
Finally the results were made available to the Project Selection Committee through the secure IT
system about 15 days before the second PSC meeting (the PSC members had also the possibility
to constantly check the work carried out by the assessors on the same secure IT system that
enable a constant monitoring of the whole evaluation process). This allowed the PSC to examine
the results before the meeting for the final approval.
26
The PSC was convened in Cagliari on the 27th, 28th and 29th of July 2010 with the aim to validate
the quality evaluation carried out by the external assessors and approve the 2nd evaluation report.
Only for two cases the PSC performed a third (final) assessment as the discrepancies between the
two assessors were significant. In these two cases the re-assessment of the PSC had already
been foreseen in the evaluation guide. Moreover during its second meeting, the PSC decided, after
a full examination of the evaluations made by the external assessors, not to re-assess other 12
projects having a difference of more than 30 points and one of the score equal to the one of the
projects that could be pre-selected.
Finally the outcome of the work of the assessors was entirely confirmed by the PSC by approving
the evaluation report on the quality assessment.
Timeframe
Selection of external assessors (call launched in December 2009 / May 2010)
Contracts, training of assessors, assignment of applications, assessment: June/July 2010
Second PSC meeting, 27, 28 and 29 of July 2010.
Main results of Step 2
Total number of assessed projects: n.289 of which:
- n.168 project proposals compliant with the minimum threshold set in the evaluation grid;
- n. 121 project proposals rejected because not compliant with the minimum threshold of the
evaluation grid.
STEP 3 - ELIGIBILITY CHECK
In order to carry out the eligibility check a request of supporting documents was sent to the
Applicants of the 34 potentially pre-selected projects (according to the scores obtained and the
available budget) together with the official notification of outcomes of Step 2.
The internal assessors in charge of the eligibility check used an evaluation Grid drafted on the
basis of requirements set by the Guidelines for Applicant par. 4.3.1. The Declaration by the
Applicant and the Partnership statements was cross-checked with the supporting documents
provided. In case some documents were not clear or missing, some clarification have been
requested to the Applicant.
27
Moreover the PSC decided to request the supporting documents to additional 13 proposals
according to the ranking list. The number was decided on the basis of the budget allocated to each
priority (the number of additional projects was calculated on the basis of the 50% of the total
budget allocated by each priority).
The PSC verified the eligibility checks performed by the JMA internal assessors and its decision is
contained in the Final Report and its Annex I “list of projects recommended to the JMC”. The final
check grids were made available in the Intranet system.
Timeframe
Request of supporting documents and eligibility check: from September to November 2010
Third PSC meeting: 24 - 25 November 2010
Main results of Step 3
Total number of assessed projects: n.35
Total number of projects recommended to the JMC: n.33
The graphic below shows the overview by step and priority of the selection process.
2.1.3 LIST OF PRESELECTED PROJECTS
28
Priority 1 - Promotion of socio-economic development and enhancement of territories
Measure 1.1 - Support to innovation and research in the process of local development of the Mediterranean Sea Basin countries
Reference number
Project title and Acronym Applicant ENPI contribution1
I-B/1.1/051 Cultural and Archaeological heritage in the Mediterranean Basin (ArcheoMED)
Academic Pole of the Province of Agrigento – ITALY
€ 1.215.065,70 (90%)
I-B/1.1/493 Promotion des systèmes camelins innovants et des filières locales pour une gestion durable des territoires sahéliens (PROCAMED)
CIRAD Centre de Coopération Internationale en Recherche Agronomique pour le Développement – CIRAD – FRANCE
€ 1.716.246,75 (90%)
I-B/1.1/287 Promoting socio-economic sustainable development through innovative technological actions for Mediterranean tourism heritage and landscapes protection clusters” (HELAND)
University of MALTA, Department of Tourism Studies - MALTA
€ 1.740.600,00 (90%)
I-B/1.1/288 Bio Exploration – Novel methodology for the Identification of Valuable Natural Products Derived from Mediterranean Flora (Bio-Xplore)
Hadassah College Jerusalem – ISRAEL
€ 1.799.469,00 (90%)
Priority 1 - Promotion of socio-economic development and enhancement of territories
Measure 1.2. - Strengthening economic clusters creating synergies among potentials of the Mediterranean Sea Basin countries
Reference number
Project title and Acronym Applicant ENPI contribution
I-B/1.2/155 Supporting and connecting rural women’s traditional know how within the Mediterranean Sea Basin through the promotion of fair products to enhance their economic and social future and to participate towards the achievement of an harmonious development for a good neighborhood in the region
Assembly of Cooperation for Peace / Asamblea de Cooperación por la Paz – SPAIN
€ 1.795.155,87 (90%)
I-B/1.2/441 Mediterranean Network of sustainable small-scale fishing communities (FISHINMED)
Apulia Region, Regional Ministry to Agrofood Policies, Dpt. Hunting and Fishing – ITALY
€ 1.325.597,64 (90%)
1 Amounts might vary due to ongoing negotiation procedure.
29
I-B/1.2/368 Mediterranean Route for Tourism and Culture (MED-ROUTE)
Prefectural Authority of Evia – GREECE
€ 1.395.000,00 (90%)
I-B/1.2/442 MARAKANDA Municipality of Florence- ITALY
€ 1.219.500,00 (90%)
Priority 1 - Promotion of socio-economic development and enhancement of territories
Measure - 1.3. Strengthening the national strategies of territorial planning by integrating the different levels, and promotion of balanced and sustainable socio-economic development
Reference number
Project title and Acronym Applicant ENPI contribution
I-B/1.3/406 Mediterranean Network for the promotion of Sustainable Urban Development Strategies and three news UDS (USUDS)
Metropolitan Hydraulic Services and Waste Treatment Organisation of the Metropolitan Area of Barcelona acting as Medcities General Secretariat – SPAIN
€ 1.783.742,47 (62,30%)
I-B/1.3/561 New Cities of the Mediterranean Sea Basin (NEWCIMED)
Municipality of Latina - ITALY € 1.792.759,60 (90%)
I-B/1.3/563 Territorial networking for capacity building and local development: a cross border experience linking Lebanon, Jordan, France, Italy
(T-NET)
Regional Authority of Tuscany – ITALY
€ 1.673.281,40 (87,95%)
I-B/1.3/350
LOCAL AGENDA 21 in territorial planning in energy and waste management
PROVINCE OF VITERBO – ITALY
€ 1.546.623,00 (90%)
I-B/1.3/482 Empowerment of Management Capacities of the Middle Eastern Public Bodies on Public Services and Socio-Economical Local Development – (MIDEMP)
Province of Cagliari – ITALY € 1.152.693,67 (90%)
Priority 2. Promotion of environmental sustainability at the basin level
Measure - 2.1. Prevention and reduction of risk factors for the environment and enhancement of natural common heritage
Reference number
Project title and Acronym Applicant ENPI contribution
I-B/2.1/395 Management of Port areas in the MEDiterranean Sea Basin (MAPMED)
University of Cagliari – ITALY € 1.799.380,00 (77,71%)
I-B/2.1/249 Improving the Environmental Sustainability of Irrigated Agricultural Production in Lebanon and Jordan
ICU - Institute for University Cooperation – ITALY
€ 1.797.743,31 (89,99%)
30
(ENSIAP)
I-B/2.1/243 Promoting sustainable groundwater resources in the Mediterranean Basin: improving technical and administrative skills in select Mediterranean Basin municipalities to alleviate pollution of groundwater Ecopeace
Middle East Environmental NGO Forum/Friends of the Earth Middle East ("EcoPeace/FoEME") – ISRAEL
€ 1.439.223,73 (90%)
I-B/2.1/529 AQUA
KNowledge and Innovation transfer for water savinG in tHe mediTerranean basin (AQUAKNIGHT)
Institute of Communication and Computer Systems - GREECE
€ 1.799.217,00 (90%)
I-B/2.1/548 Sustainable domestic Water Use in Mediterranean Regions (SWMED)
Region of Latium – Italy € 1.609.547,04 (90%)
I-B/2.1/122 Shmile 2 - De l'expérimentation à la diffusion de l'Ecolabel en Méditerranée
Chambre de Commerce et de l'Industrie Nice - Cote d'Azur - FRANCE
€ 1.799.098,75 (90%)
I-B/2.1/090 Mediterranean Cooperation in the Treatment and Valorisation of Olive Mill Wastewater (OMW) MEDOLICO
University of Cyprus € 1.769.416,00 (90%)
Priority 2. Promotion of environmental sustainability at the basin level
Measure - 2.2. Promotion of renewable energy use and improvement of energy efficiency contributing to addressing, among other challenges, climate change
Reference number
Project title and Acronym Applicant ENPI contribution
I-B/2.2/063 Réseau d’Action en matière de Mobilité Urbaine Durable (RAMUD)
Municipalité de Barcelone – Espagne
€ 750.897,62 (88,75%)
I-B/2.2/099 Production of biodiesel from Algae in selected Mediterranean Countries (MED-ALGAE)
Agricultural Research Institute (ARI) – CYPRUS
€ 1.800.000,00 (88,75%)
I-B/2.2/180 Rénovation Energétique des LogementS (RELS)
Ministère de l’Environnement et du Logement Gouvernement de la Catalogne – Espagne
€ 1.792.431,00 (90%)
Priority 3 Promotion of better conditions and modalities for ensuring the mobility of persons, goods and capitals
Measure - 3.2 Improvement of conditions and modalities of circulation of goods and capitals among the territories
Reference number
Project title and Acronym Applicant ENPI contribution
I-B/3.2/500 Improving the goods circulation between the Middle East and the EU by networking and adopting shared procedures and technologies (CUSTOM
University of Genoa – Transport Research Centre – ITALY
€ 1.046.880,00 (90%)
31
MED)
Priority 4. Promotion of cultural dialogue and local governance
Measure - 4.2. Support to the artistic creativity in all its expressions to encourage dialogue among communities
Reference number
Project title and Acronym Applicant ENPI contribution
I-B/4.2/391 Dramaturgies contemporaines du monde arabe (DCMA)
Systeme Friche Théâtre – FRANCE
€ 446.177,00 (86,61%)
Priority 4. Promotion of cultural dialogue and local governance
Measure - 4.3 Improvement of the governance processes at local level.
Reference number
Project title and Acronym Applicant ENPI contribution
I-B/4.3/412 Transfert de savoir-faire en Méditerranée pour le développement durable des communautés locales en zones rurales défavorisées (VILLAGES)
Centre International pour l’Environnement Alpin ICALPE – FRANCE
€ 1.522.774,00 (89,99%)
I-B/4.3/367 Mediterranean Network for E-Government (MEDeGOV)
Prefectural Authority of Evia – GREECE
€ 1.260.000,00 (90%)
Priority 4. Promotion of cultural dialogue and local governance– below 500.000
Measure - 4.2 Support to the artistic creativity in all its expressions to encourage dialogue among communities
Reference number
Project title and Acronym Applicant ENPI contribution
I-B/4.2/164 Nostoi – Histoires de retours et d’exodes (NOSTOI)
Coopérative Archéologie – Italie
€ 446.708,73 (90%)
I-B/4.2/275 JOUSSOUR Conférence Permanente de l'Audiovisuel Méditerranéen – Italie
€ 447.290,73 (89,99%)
I-B/4.2/445 Culture in the Mediterranean and Europe – Weaving on Common Threads (CulMe-WeOnCT)
Interbalkan Institute of Public Administration – GREECE
€ 449.280,00 (90%)
Priority 4. Promotion of cultural dialogue and local governance – below 500.000
Reference number
Project title and Acronym Applicant ENPI contribution
I-B/4.3/587 New Performances for Mediterranean Tourism Newper
Promuovi Italia J.S.C. Joint Stock Company – ITALY
€ 382.325,30 (90%)
2.2 STRATEGIC PROJECTS
32
Alongside the evaluation process for the first call for standard projects, the JMA has prepared the
launch of the call for strategic projects according to the requirements and procedures defined in the
JOP and PRAG. The main problem in the preparation of the documents for the strategic call was
the delay concerning the selection procedure of the external experts to be recruited for each topic
addressed by the call.
In fact, 4 topics out of 6 remained uncovered after the conclusion of the first selection procedure. In
particular, the experts for the integrated coastal management, waste treatment and recycling,
water management and solar energy were not selected and an additional procedure was then
launched on 23 June, 2010. The recruitment process was finally completed and a first expert group
meeting was held in Cagliari on 15 October, 2010. This meeting aimed at introducing a common
working methodology, discuss and agree upon objectives and an indicative timetable capitalising
also on the experience of the first call for proposals. Specifically, the main topic of the pre-selected
standard projects were presented by the JMA / JTS and discussed with experts in order to
underline differences between standard and strategic projects and focus on some preliminary
findings of the first call. The main fields of action identified were namely: Spatial planning and local
development; Culture and tourism; Climate including both water and energy efficiency; Transports
and mobility.
The main topics discussed concerning the selection process: rules and procedures to be simplified;
MPC participation to be improved; link with national, local authorities and other donors; potential
synergies with MED and other programmes to be exploited.
Possible actions to be taken within the call for strategic projects: application package to be
improved; targeted dissemination and communication activities; mandatory networking and
communication activities; targeted monitoring system and impact indicators.
The experts were coordinated by a team leader and supported by the JMA and a specialist in
programme management procedures who addressed the definition of the documents for the call
according to PRAG. The team leader coordinated the work of experts and assisted the Programme
management bodies in the preparation the call while the specialist harmonized the draft of ToRs
with PraG requirements and with its formats. All experts supported the JMA in elaborating the
relevant documents composing the application pack participating in relevant meetings as required
by JMA.
33
In particular, they prepared the background analysis and the questionnaires for the consultation of
national reference persons. A preliminary draft of the ToRs for each topic was discussed in
Valencia during the JMC meeting held on 13 and 14 December 2010. The background analysis
contained an in-depth context analysis of the Programme cooperation area in relation to the
concerned topic, mainly in terms of international, national and regional strategies, existing relevant
programmes and projects, main strengths, weaknesses, opportunities and threats (SWOT
analysis). The background analysis was transmitted to the Heads of Delegation in order to receive
their comments during the JMC meeting.
During the JMC meeting, the JMA introduced the main possible rules for the selection of strategic
projects, as well as a detailed questionnaire for the consultation of national reference persons
aimed at collecting comments on the SWOT. It was also agreed to define a detailed set of
indicators for each topic. The previous tasks of the identification of potential activities and key
actors were then replaced by the indicative list of coherent projects implemented, ongoing or
foreseen within the same topics in the Mediterranean area.
Finally, a preliminary draft of the project evaluation criteria it was defined and the project evaluation
grid starting from the PraG requirements and formats (suggesting potential integration or
adaptation) was prepared. According to the preliminary feedback received by the delegations, the
drafting of the Guidelines for applicants was started, including the Concept Note, the Gull
Application Form and their annexes.
34
3. INFORMATION AND COMMUNICATION ACTIVITIES
With regards to information and communication activities, 2010 was entirely dedicated to the
preparation of year 2011 considered as a major milestone in the Programme life cycle. In fact, in
2011 two calls are due to be launched (call for strategic projects and second call for standard
projects) while the implementation of the projects selected under the first call standard projects will
start.
Therefore, although no larger communication campaign was carried out in 2010, two important
preparatory activities for actions to be implemented in 2011 were completed: the 2011 Information
and Communication Plan and the call for tender on communication activities, as the operational
tool for implementing efficiently and timely communication actions until the end of the Programme
life cycle (see section 1.3.2 point f) for more information on the content of the call for tender).
3.1 2011 INFORMATION AND COMMUNICATION PLAN
3.1.1 DRAFTING THE 2011 INFORMATION AND COMMUNICATION PLAN
The 2011 Information and Communication Plan was drafted with the full involvement of the 14
participating countries.
The methodology approved to prepare and share the Communication Plan was based on a
targeted questionnaire and various meetings with relevant parties such as Branch Offices and
Programme National Contact Points.
In order to evaluate the communication activities carried out in 2009 to support the launching of the
first call for standard projects and to better target future information actions on the actual needs
and expectations of the 14 participating countries, the JMA launched a consultation with the
National Contact Points through a dedicated questionnaire sent in November 2009.
The results of the questionnaire were carefully analyzed to prepare the first draft of the 2011
Communication Plan which was discussed with the staff from the two Branch Offices during two
meetings held in Rome 2 December 2009 and 15 March 2010.
In May 2010 during a meeting in Brussels, the results of the Questionnaire were discussed with
the NCPs allowing to integrate some useful additional inputs to the draft of the Communication
Plan.
35
The draft Communication Plan was then circulated among the Joint Monitoring Committee and
integrated based on the comments/suggestions expressed. The final draft of the 2011 Information
and Communication Plan was approved by the JMC through written procedure on 6 December
2010.
3.1.2 OVERVIEW OF THE 2011 INFORMATION AND COMMUNICATION PLAN
The adopted Communication Plan foresees some specific actions related to the two calls for
proposals to be launched in 2011 while other actions have a crosscutting dimension and will be
implemented during the whole Programme life cycle. All actions are coordinated to achieve the
general three objectives set by the JOP:
- Communicate effectively to public opinion the political and strategic aims that the European
Union intends to achieve, in partnership with the countries involved, through activities financed
by the Programme and, more generally, by the ENPI;
- Guarantee transparency in the use of community resources, through regular dissemination of
information and the use of simple and effective procedure and instrument of direct
participation;
- Make potential beneficiaries aware of the purposes, of the opportunity offered by the
Programme and the modalities of participation.
The 2011 Communication Plan is based on Logical Framework approach to ensure more efficient
actions, to measure the actual results of each action carried out and to guarantee the full
coherence between general objective, specific objectives, activities, target groups, foreseen budget
and expected results. One of the innovative features of the 2011 Communication Plan consists in
the use of result indicators that will allow to measure the effectiveness of the different actions
carried out. That way, the JMA and the different stakeholders involved in communication activities
will be able to assess the results on an annual basis, enhance activities that proved successful and
adapt those actions that turned out less efficient.
Following the approval of the JMC, the Plan will be annually updated, enabling further coordination
between all stakeholders involved, especially with regards to the nature of the different actions to
be implemented.
36
3.1.3 SPECIFIC FEATURES OF THE 2011 INFORMATION AND COMMUNICATION PLAN
The Communication Plan is structured in 3 general objectives articulated in 10 specific objectives
as follows:
Objective 1 - Communicate effectively to public opinion the political and strategic aims that the European Union intends to achieve
Specific objectives Actions
1.1 Improve the Programme awareness and visibility
1.1.1 Ensure the use of the Programme logo and visual identity
1.2 Broadcast the Programme information through networking communication tools
1.2.1 Enhance the website
1.2.2 Design and build two public databases
1.2.3 Design and build a private database
1.3 Promote the Programme activities through PR material
1.3.1 Produce and disseminate information and visibility materials
1.4 Communicate the Programme aims during meetings and seminars
1.4.1 Organize events:
Launching Conference ( Strategic projects, 1th call)
Launching Conference (Standard projects, 2nd call)
1.5 Organize Media information campaigns
1.5.1 Prepare a short Programme presentation to be broadcasted through the national media of participating countries.
1.5.2 Publish an extract of the next call for proposals in national newspapers of the beneficiaries countries
Objective 2 - Guarantee transparency in the use of community resources
Specific objectives Actions
2.1 Inform granted projects on rules and expectations by the JMA
2.1.1 Participate in Projects Kick off meetings
2.1.2. Participate in official Projects meetings
2.2 Co-ordinate Programme Projects about the utilization of common accepted procedures
2.2.1 Organize informative seminars
2.2.2 Organize training seminars with Projects on: Management, Communication and Finance
37
2.3 Produce handbooks on sector guidelines
2.3.1 Draft guidelines on Programme common standards for Communication and Reporting formats
Objective 3 - Make potential beneficiaries aware of the purposes, of the opportunity offered by the Programme and the modalities of participation
Specific objectives Actions
3.2 Create synergies and links with other EC Regional and Co-operation Programmes
3.2.1 Co-operation and cross-links with other EC Programmes
3.1.4 SUPPORT TO THE IMPLEMENTATION OF THE PROGRAMME COOMUNICATION
STRATEGY: BRANCH OFFICES WORKING PLANS
The two Programme Branch Offices, respectively located in Valencia and Aqaba, were fully
operational in October 2010 after their staff had been recruited.
The Branch Offices are key players in the Programme implementation. In fact, given the
Programme complexity and the wide extension of the eligible area, the decentralization of the
management of some activities to the Branch Offices is necessary to:
- ensure closer proximity to the potential beneficiaries and main involved actors at local level;
- favor the beneficiaries and actors participation in the Programme.
The decentralization is therefore intended to enhance and maximize the actions planned and
undertaken by the JMA and the JTS supporting their implementation throughout the whole eligible
area. In some cases, the BOs manage and direct certain actions and activities, but always under
the coordination and supervision of JMA on whom they are functionally dependent and to whom
they have to report periodically.
The foreseen tasks of each Branch Office have been detailed in a dedicated Working Plan for the
year 2011. The Working Plans have been discussed and shared with Aqaba (November 2010) and
Valencia (December 2010) Branch Offices.
3.2 INFORMATION AND COMMUNICATION ACTIONS
3.2.1 PROMOTION AT EXTERNAL EVENTS
Where possible, the JMA participated in external events with the intent of presenting the
opportunities offered by the Programme and explain the general rules of the first call for proposals.
38
Here is a synthesis of the most relevant events attended by the JMA:
• Informative seminar for local NGOs, Consulate of Italy in Jerusalem (Israel), 29 April 2010.
Following the invitation of the Technical Local Unit of the Italian Consulate of Italy, an informative
seminar took place in Jerusalem. More than 70 representatives of local NGOs attended the event
and got information on the state of advancement of the Programme’s implementation, the calendar
of the calls and were provided with an overview of the main eligibility rules applying to EBPI CBC
Med projects.
• ASCAME General Assembly, Cagliari (Italy), 3 May 2010. The Association of the Mediterranean
Chambers of Commerce and Industry (ASCAME) was formed on 1 October 1982. The Constitutive
General Assembly was held in Barcelona, hosted by the Barcelona Chamber of Commerce,
Industry and Navigation. ASCAME is an Organization with a potential membership of 500
Chambers of Commerce, and other associated entities, from the 23 countries bordering the
Mediterranean Sea. During the 2010 general Assembly of the ASCAME Secretariat that took place
in Cagliari on 3 May, the funding opportunities offered by the Programme were presented to the
representatives of chambers of commerce from the Euro-Med region.
• Seminar on European territorial cooperation, Bari (Italy), 17 June 2010. Sharing experience
between different Managing Authorities of cooperation programmes dealing with the Mediterranean
area: that was the objective of the seminar organized by Puglia Region. During the event the JMA
also discussed the methodology adopted for the drafting of the call for strategic projects.
• Med Programme Annual event, Thessaloniki (Greece), 23 September 2010. Within the
frnmework of the Med Programme annual event, the JMA shared its views on the future
perspectives for cooperation in the Mediterranean together with representatives of the European
Commission, local authorities and civil society.
• Meeting between European Territorial cooperation programmes, Bologna (Italy), 28 September
2010. During this operational event organised by Emilia-Romagna Region, the JMA shared its
experience in the management of a complex cooperation programme with other authorities
involved in Italy in the implementation of programmes/projects dealing with European Territorial
Cooperation.
• Meda Finance 2010, Cairo (Egypt), 19 and 20 October. Organized by the Confederation of
Egyptian European Business Associations in the framework of the EU funded “Invest in Med”
programme, the goal of MedaFinance 2010 (Cairo, 19th and 20th October) was to raise awareness
39
on funds available, clarify the application processes and encourage SMEs to make use of these
instruments. The Conference provided to over 500 participants a comprehensive overview of
financial instruments offered by donors such as United Nations, European Investment Bank,
African and Arab development banks. During the plenary session on “Grants and Technical
Assistance” bringing together representatives from UNDP, European Commission, German (GTZ)
and Japanese (JICA) national development agencies, the JMA, while presenting the opportunities
of the ENPI CBC Med Programme, highlighted the need to better coordinate the various existing
initiatives - over 250 instruments exceeding € 22 billion are available in the Mediterranean area -
in order to avoid any projects duplication and maximize the effects of Euro-Med cooperation.
The Programme logo features two important symbols of the Mediterranean area: the sea and the
sun. The sea, as the common space uniting all the countries participating in the Programme, is
represented by waves. The sun is made of people holding hands, symbolising cooperation and
common benefits.
3.2.2 PROGRAMME WEBSITE
The Programme website (www.enpicbcmed.eu) was further enhanced in 2010. In particular, as the
main tool for communicating the state of advancement of the Programme and results achieved in
its implementation aims at reaching the widest possible audience in the eligible territories.
The webiste was regularly updated throughout 2010 in order to inform interested stakeholders
about the selection process of the call for standard projects, the calendar related to the publication
of the call for strategic projects and the various Programme recruitment/tender notices.
Any relevant news was also forwarded to RCBI, Interact and ENPI Info Centre websites and to
those of the national delegations in order to ensure maximum visibility of the opportunities offered
by the Programme.
Below are some statistics regarding the access to the Programme website.
40
41
42
3.3 COMMUNICATION ACTIVITIES CARRIED OUT BY THE BRANCH OFFICES
3.3.1 VALENCIA BRANCH OFFICE
The following activities were carried out in 2010 by the Valencia Branch Office, including the
Liaison office:
- Management of 125 questions received via email or telephone concerning the call for
proposals for Standard Projects and the next call for Strategic Projects. All questions were
duly answered also in collaboration with Joint Managing Authority Staff.
- 3rd meeting of the Joint Monitoring Committee in Valencia (13-14 December 2010): the
Branch Office collaborated in the organization of the JMC meeting with reference to the
logistical arrangements. Welcome remarks were made by Mr. Rafael Ripoll Navarro, Regional
Vice-Minister for European Affairs, Generalitat Valenciana.
- Maintenance of the contacts’ and potential beneficiaries’ database created in 2009, using
in part the contacts of the Liaison Office and those provided by National Contact Points. The
database contains more than 700 contacts, especially coming from the participating countries
covered by the Branch Office, and includes local, regional and national public bodies,
development agencies, public and private foundations, civil society associations, NGOs and
consultancies.
43
- Promotion at external events: the BO participated in external events with the intent of
presenting the opportunities offered by the Programme. Here is a synthesis of the most
relevant events attended by the BO:
- The Energy Efficiency Challenge for Cities. European Funds to generate local employment.
11th May 2010. Castellón (Spain). This seminar was held in Castellón (Spain) and was
organized by the City Council of Castellón and the Valencia Regional Ministry for European
Affairs. The main purpose of this conference was to contribute to achieve that municipalities
optimize the use of financial tools in order to create employment and training in building
techniques based on energy and environmental efficiency, contributing to reach the
different policies to prevent environmental change as well as the objectives of the Covenant
of Mayors. The Valencia Branch Office was invited to participate in the seminar as speaker
in order to explain the opportunity to participate in ENPI CBC MED Programme with
projects related to energy efficiency sector.
- 3rd Interact ENPI Annual Conference: in October 2010, the Valencia Branch Office attended
the Seminar “3rd INTERACT ENPI Annual Conference” on 21-22 October in Kiev to discuss
current problems and future challenges of ENPI Cross-border Co-operation Programmes
funded by EU. The 3rd Interact ENPI Annual Conference met in Kiev the main actors
related to the managing and coordination activities from the ENPI CBC Programmes.
During the Conference, the role of BOs was discussed and the following points were
highlighted.
Branch Offices are a very useful tool to be used by beneficiaries and Programs and they
should be fully exploited to maximize the resources of Branch Offices at their disposal. At
this regard, Branch Offices should increase their role in the monitoring of the projects, like:
Making the last check and ask for additional documents to the Leaders.
Organising discussions and meetings with beneficiaries.
Helping on consulting with the rules for procurement and other rules.
Being involved in the spot-visits to the projects.
- Liaison Office ENPI CBC MED:
Enhance new communication strategy and working plan with MED Programme;
Drafting of MED and ENPI CBC MED programmes “Comparative brochure” in
September 2010, with a total of 700 copies (500 in English version and 200 in French
44
version). The brochure was prepared by Liaison Offices and in close collaboration the
JMAs of both Programmes. The objective of this brochure is to highlight in 10 key
points the main features of the programmes and comparing their different nature,
objectives, eligible territories and actors.
In October 2010, the Liaison Office attended a bilateral meeting in Cagliari (Italy)
between the JMA and the JTS of both MED and ENPI CBC Med programmes in order
to define the Working Plan of the Liaison Office for the year 2011 and analyse how the
Liaison Office could contribute to the necessities of the two Mediterranean programmes
in an efficient way.
Due to fact that the selection process of Valencia Branch Office staff was finalized in October 2010
all activities foreseen in the 2010 Communication Plan could not be achieved.
3.3.2 AQABA BRANCH OFFICE
As the Aqaba Branch Office was not fully operational till October 2010, it could not perform its
tasks as foreseen. The following activities were carried out in 2010 by the Aqaba Branch Office:
- Organize the work of the Branch Office, with reference to the definition of the tasks of each
staff member, as well as of the relations with the hosting institution and the JMA.
- Hosting the coordination meeting (JMA/JTS/BO/ASEZA) in Aqaba (29-30 November 2010).
The meeting was organised to discuss the 2010 and 2011 Working plan.
- Contribution to the drafting of the 2011 Information and Communication plan.
- Participation in 3rd JMC Meeting in Valencia on 13-14 Dec 2010.
45
4. PROGRAMME OF ACTIVITIES TO BE IMPLEMENTED THE FOLLOWING YEAR
The main activities for 2012 are mainly related to the evaluation and closure of the call for
proposals for strategic projects, the second call for standard projects as well as to the starting
phase of the first selected standard projects. These latter will start their full implementation phase
in September 2011 and will present their first financial and activity reports in the second half of
2012.
As far as the call for strategic projects is concerned, the evaluation of the Concept Notes (stage 1)
should be performed within mid-September by the PSC and finally decided by the JMC by the end
of October 2011. The Full Application Form (stage 2) evaluation will last until the end of April 2012
when the award decision of the JMC is expected. Notification to successful Applicants and
negotiation following the award decision should lead to the signature of the contracts in July 2012.
The second call for standard projects is expected to be launched in November 2011 while the
evaluation phase (including all evaluation steps) will last till September 2012. The signature of
contracts should take place at the end of the same year due to a simplification of the procedure
taking full advantage of the integrated monitoring system.
In parallel, communication activities will be intensified and will focus on key events, systematically
addressing the capitalisation of experiences as a way to improved connections with media.
As reported in the indicative GANTT chart below, the main milestones of the Programme (mainly
JMC and PSC meetings) are all directly linked to the above mentioned objectives.
GANTT CHART INDICATIVE ACTIVITY PLAN 2012
47
B. FINANCIAL PART
1 DECLARATION OF REVENUE AND EXPENDITURE
1,2 Provisional budget for the following year (commitments and expenditure)
1,3 Bank accounts
1,4 Payments from European Commission
1,5 Payments from participating countries at programme level
1,6 Reconciliation with the financial table of the JOP
2 PROJECTS
2,1 PROJECTS - Payments
2,2 PROJECTS - Recoveries
3 TECHNICAL ASSISTANCE (TA)
3,1 TA - Staff
3,2 TA - Subsistence costs
3,3 TA - Travel
3,4 TA - Equipment and supplies
3,5 TA - Consumables
3,6 TA - Subcontracting
3,7 TA - Other costs
3,8 TA - Revenue
Contents of the annual financial report
REVENUE - current reporting period 11.953.068,39
Amount received from EC 11.836.209,43
Revenue from TA 0,00
Gross interest on prefinancing 116.858,96
Other revenues (penalties, interest on recoveries, etc.) 0,00
EXPENDITURE - current reporting period 1.572.404,75
Amount paid on projects 0,00
Amount paid on TA 1.572.404,75
BALANCE on 31 December 2009 16.642.366,53
BALANCE 27.023.030,17
Balance of the ENPI bank account on 31 December 2010 27.987.673,43
(A ) Aqaba Branch Office bank account balance 32.759,28
(B) Amount of TA expenditures advanced by the Sardinia Region to be reimbursed -956.480,41
(C) Amount of TA expenditures advanced by the Comunitat Valenciana to be
reimbursed
-40.922,13
RECONCILIATION OF THE BALANCE* 27.023.030,17
0,00
Programme: ENPI CBC Mediterranean Sea Basin
1. DECLARATION OF REVENUE AND EXPENDITURE
all amounts in EUR
I, the undersigned, Anna Maria Catte, director of JMA , acting as authorised representative of the Joint Managing Authority for the ENPI CBC
Programme Mediterranean Sea Basin , hereby give assurance that the management and control systems set up for the programme in the course
of the previous year continue to comply with the model approved by the Commission and that they have operated in such a way as to warrant a
reasonable degree of confidence in the correctness of the financial report and in the legality and regularity of the transactions to which it relates.
I hereby declare the following.
1) The revenue and expenditure of the programme with regard to EU funds for the year 2008-2009 is as follows. The balance corresponds to the
aggregated amount of EU funds deposited on the programme's accounts.
ANNUAL FINANCIAL REPORT FOR THE YEAR 2010
* This amount comes from balance of the ENPI bank account (€ 27.987.673,43 which not includes the net interest from 31.10.2010 to
31.12.2010) plus the amount of the Aqaba Branch Office balance which has not been spent (A) less the amount of TA expenditures advanced by
Region of Sardinia (B) and the one advanced by Comunitat Valenciana (C) to be reimbursed.
2) The financial contributions from participating countries at the programme level for the year 2010 are as follows:
3) The EU contribution to projects at the level of commitments and accepted expenditure does not exceed 90%.
1. DECLARATION Page 2
EU contribution to projects (grant amount) 0,00%
EU contribution to accepted expenditure 0,00%
signature: _______________________________________ date: _______________
1. DECLARATION Page 3
0,00 0,00 0,00 0,00 0,00 0,00 0,00
0,00
Project
reference
Project title Beneficiary with
nationality
Partners with
nationality
Duration
[months]
Year of
contract
signature
Start End Total cost
[EUR]
EU grant
[EUR]
EU grant
%
Expenditure
claimed
to date
[EUR]
Expenditure
accepted
to date
[EUR]
EU contribution
to expenditure
accepted to date
[EUR]
Amount paid
to date - EU
funds
[EUR]
Amount
recovered
to date - EU
funds
[EUR]
0,00 0,00 0,00 0,00 0,00 0,00 0,00
0,00 0,00 0,00 0,00 0,00 0,00 0,00
0,00 0,00 0,00 0,00 0,00 0,00 0,00
0,00 0,00 0,00 0,00 0,00 0,00 0,00
0,00 0,00 0,00 0,00 0,00 0,00 0,00
0,00 0,00 0,00 0,00 0,00 0,00 0,00
0,00 0,00 0,00 0,00 0,00 0,00 0,00
0,00 0,00 0,00 0,00 0,00 0,00 0,00
0,00 0,00 0,00 0,00 0,00 0,00 0,00
0,00 0,00 0,00 0,00 0,00 0,00 0,00
0,00 0,00 0,00 0,00 0,00 0,00 0,00
0,00 0,00 0,00 0,00 0,00 0,00 0,00
0,00 0,00 0,00 0,00 0,00 0,00 0,00
PRIORITY <number and name>
PRIORITY <number and name>
MEASURE <number and name>
MEASURE <number and name>
MEASURE <number and name>
MEASURE <number and name>
MEASURE <number and name>
PRIORITY <number and name>
MEASURE <number and name>
MEASURE <number and name>
MEASURE <number and name>
MEASURE <number and name>
MEASURE <number and name>
ANNUAL FINANCIAL REPORT FOR THE YEAR 2010
Amount of grant of contracts of current period
Programme: ENPI CBC Mediterranean Sea Basin
2. PROJECTS
all reporting periods
2. PROJECTS Page 9
Project
reference
Project title Beneficiary with
nationality
Partners with
nationality
Duration
[months]
Year of
contract
signature
Start End Total cost
[EUR]
EU grant
[EUR]
EU grant
%
Expenditure
claimed
to date
[EUR]
Expenditure
accepted
to date
[EUR]
EU contribution
to expenditure
accepted to date
[EUR]
Amount paid
to date - EU
funds
[EUR]
Amount
recovered
to date - EU
funds
[EUR]
0,00 0,00 0,00 0,00 0,00 0,00 0,00
0,00 0,00 0,00 0,00 0,00 0,00 0,00
0,00 0,00 0,00 0,00 0,00 0,00 0,00
0,00 0,00 0,00 0,00 0,00 0,00 0,00
0,00 0,00 0,00 0,00 0,00 0,00 0,00
0,00 0,00 0,00 0,00 0,00 0,00 0,00
0,00 0,00 0,00 0,00 0,00 0,00 0,00
MEASURE <number and name>
MEASURE <number and name>
MEASURE <number and name>
MEASURE <number and name>
MEASURE <number and name>
MEASURE <number and name>
PRIORITY <number and name>
2. PROJECTS Page 10
9.181.352,01 561.266,41 1.572.404,75 1.572.404,75
Description Amount contracted
[lEUR]
Amount paid
in previous reporting periods
[EUR]
Amount paid
in current reporting period
[EUR]
Amount paid
to 31/12/2010
[EUR]
STAFF 5.167.660,63 187.850,86 573.817,60 573.817,60
JMA 1.218.168,13 187.850,86 474.691,44 474.691,44
JTS 2.786.257,50 0,00 55.111,77 55.111,77
Branch office Valencia 731.235,00 0,00 27.267,54 27.267,54
Branch office Aqaba 432.000,00 0,00 16.746,85 16.746,85
TRAVEL & SUBSISTENCE
COSTS
210.249,94 119.830,52 91.800,27 91.800,27
JMA 96.925,51 39.385,84 59.522,26 59.522,26
JTS 12.210,85 0,00 11.932,16 11.932,16
JMC 77.050,11 77.050,11 0,00 0,00
PSC 14.568,24 0,00 14.245,20 14.245,20
Branch office Valencia 7.161,33 3.394,57 3.766,76 3.766,76
Branch office Aqaba 2.333,90 0,00 2.333,90 2.333,90
EQUIPMENT AND SUPPLIES 29.246,18 0,00 29.246,18 29.246,18
JMA 26.933,37 0,00 26.933,37 26.933,37
JTS 0,00 0,00 0,00 0,00
Branch office Valencia 0,00 0,00 0,00 0,00
Branch office Aqaba 2.312,81 0,00 2.312,81 2.312,81
CONSUMABLES 2.984,31 2.874,31 110,13 110,13
JMA 0,00 0,00 0,00 0,00
JTS 0,00 0,00 0,00 0,00
JMC 552,00 552,00 0,00 0,00
Branch office Valencia 2.432,31 2.322,31 110,13 110,13
Branch office Aqaba 0,00 0,00
SUBCONTRACTED
EXPENDITURE
658.255,81 165.319,69 241.833,70 241.833,70
JMA 298.134,75 140.276,75 19.924,10 19.924,10
JTS 81.480,00 0,00 81.480,00 81.480,00
PSC 253.338,52 0,00 140.170,00 140.170,00
Branch office Valencia 25.302,54 25.042,94 259,60 259,60
Branch office Aqaba 0,00 0,00 0,00 0,00
OTHER COSTS 2.995.378,49 59.168,16 544.243,09 544.243,09
JMA 1.845.153,91 7.099,10 544.054,81 544.054,81
JMC 1.150.224,58 52.068,58 156,00 156,00
JTS 0,00 0,00 0,00 0,00
Branch office Valencia 0,00 0,00 0,00 0,00
Branch office Aqaba 0,00 0,48 32,28 32,28
INDIRECT COSTS 117.576,65 26.222,88 91.353,78 91.353,78
JMA 104.981,70 26.222,88 78.758,82 78.758,82
JTS 10.396,68 0,00 10.396,68 10.396,68
Branch office Valencia 2.198,28 0,00 2.198,28 2.198,28
Branch office Aqaba 0,00 0,00 0,00 0,00
all reporting periods
3. TECHNICAL ASSISTANCE (EU FUNDS)
Programme: ENPI CBC Mediterranean Sea Basin
ANNUAL FINANCIAL REPORT FOR THE YEAR 2010
3. TA Page 13