6/4/2015 1 2012 IECC (International Energy Conservation Code) Compliance Documentation Career Development Seminar State of Connecticut Office of Education and Data Management June 2015 1 Responsibilities Designer / Design Profession Develop construction documents that comply Provide compliance documentation Building Official Verify compliance of construction documents Inspect as built conditions for compliance Contractors Complete project that functions as intended and is in compliance with the energy code 2 Why Compliance Documentation? Code requirements Facilitates permit review Communicates code compliance and project requirements to: Building officials Contractors and sub contractors Suppliers 3

Upload: others

Post on 18-Jun-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 2012 IECC (International Energy Conservation Code ......2012 IECC (International Energy Conservation Code) Compliance Documentation Career Development Seminar State of Connecticut

6/4/2015

1

2012 IECC(International Energy Conservation Code)

Compliance Documentation

Career Development SeminarState of Connecticut

Office of Education and Data Management

June 2015

1

Responsibilities

• Designer / Design Profession– Develop construction documents that comply

– Provide compliance documentation

• Building Official– Verify compliance of construction documents

– Inspect as built conditions for compliance

• Contractors– Complete project that functions as intended and is

in compliance with the energy code

2

Why Compliance Documentation?

• Code requirements

• Facilitates permit review

• Communicates code compliance and project requirements to:

– Building officials

– Contractors and sub contractors

– Suppliers

3

Page 2: 2012 IECC (International Energy Conservation Code ......2012 IECC (International Energy Conservation Code) Compliance Documentation Career Development Seminar State of Connecticut

6/4/2015

2

Sections R103 & C103Information on construction documents

– Insulation materials and their R-values– Fenestration U-factors and SHGCs– Area-weighted U-factor and SHGC calculations– Mechanical system design criteria– Mechanical and service water heating system and equipment

types, sizes and efficiencies– Economizer description– Equipment and systems controls– Fan motor horsepower (hp) and controls– Duct sealing– Duct and pipe insulation and location– Lighting fixture schedules with wattage and control narrative– Air seal details

4

Compliance DocumentationFor Residential Projects

• Identify the code to be complied with

• Approaches

– Project requirements scattered throughout the plans

– REScheck

– Forms from codes/standards organization

– Forms as developed by designer or design professional

5

Sample Residential Project

6

Page 3: 2012 IECC (International Energy Conservation Code ......2012 IECC (International Energy Conservation Code) Compliance Documentation Career Development Seminar State of Connecticut

6/4/2015

3

Sample Residential Project

First Floor PlanSecond floor above

Cathedral ceiling above

Second floor above

DN

UP

C-1

C-2

C-3 A-1

D-2

C-2 C-4

C-2

D-2

D-4

D-1

7

Sample Residential Project

Second Floor Plan

DN

DH-1

DH-2 DH-2 DH-2 DH-2

DH-1

DH-1

A-2

A-3 A-3

Living Room Below

Garage Below

8

Sample Residential Project

Schedules

9

Page 4: 2012 IECC (International Energy Conservation Code ......2012 IECC (International Energy Conservation Code) Compliance Documentation Career Development Seminar State of Connecticut

6/4/2015

4

Code Requirement

Air Sealing(Mandatory)

10

Sample Residential Project

Wall and Roof/Ceiling Sections

Wall At Cathedral Ceiling

Wall Adjacent ToCathedral Ceiling

Roof Sheathing

Air Space

Plywood

Plywood

Air SpaceRoof Sheathing

Sheetrock

Blocking Panel withVentilation Notch

Wood I-Beam Rafter

Sealant

Sheathing

Siding

SheathingSiding

Air Permeable Water Barrier

2x6 Wood Stud Wall

8” Closed Cell Foam (R-51)Air Barrier & Vapor Retarder

3½” Closed Cell Foam (R-22)Air Barrier & Vapor Retarder

3½” Closed Cell Foam (R-22)Air Barrier & Vapor Retarder

2x6 Wood Stud Wall

SheetrockWood I-Beam Rafter

Air Permeable Water Barrier

11

Sample Residential Project

Wall and Roof/Ceiling Sections

Cathedral & Second Floor Ceiling

Second Floor Ceiling

2x Rafters

Roof Sheathing

Rim Joist

Sealant

2x6 Wood Stud Wall

3½” Closed CellFoam (R-22)Air Barrier & Vapor Retarder

8” Closed Cell Foam (R-51)Air Barrier & Vapor Retarder Plywood

Chase forHVAC Ducts

Sheetrock

Sheetrock

Air Space

Vapor PermeableWater Barrier

Sheathing

12

Page 5: 2012 IECC (International Energy Conservation Code ......2012 IECC (International Energy Conservation Code) Compliance Documentation Career Development Seminar State of Connecticut

6/4/2015

5

Sample Residential Project

Wall Sections

Basement Wall Back Wall Cantilever

Wood Floor Joist

Rim Joist

2x6 Wood Stud Wall

Sealant

Sealant

Concrete Foundation

2x4 Stud Wall

SheetrockSheathing

Siding3½” Closed Cell Foam(R-22) Air Barrier &Vapor Retarder

Sheetrock

Vapor Permeable Water Barrier

2½” Closed CellFoam (R-16)Air Barrier & Vapor Retarder

5” Closed Cell Foam(R-32) Air Barrier &Vapor Retarder

3½” Closed Cell Foam(R-22) Air Barrier &Vapor Retarder

3½” Closed Cell Foam(R-22) Air Barrier &Vapor Retarder

Sealant

Blocking

2x6 Wood Stud Wall

2x6 Wood Stud Wall

Sheetrock

Sheetrock

13

Sample Residential Project

General Envelope Notes

• Fenestration rating certificates are to be left on the product until the leakage test is performed.

• Thermal envelope to be leakage tested after all utility penetrations have been completed and the air barrier and insulation have been installed.

• Verified air leakage rate shall be equal to or less than 3 air changes per hour. Leaks shall be sealed and test shall be repeated until this leakage rate is achieved.

14

Sample Residential Project

Heating and Cooling System Notes

• Heat loss and heat gain calculations to be provided.

• All ducts and piping to be inside the thermal envelope.

• Programmable thermostat to be provide for each zone.

• All ducts and air handlers are to be sealed.

• All piping to have R-3 insulation.

• Fully ducted energy recovery system with minimum 2.8cfm/watt efficiency to be provided.

15

Page 6: 2012 IECC (International Energy Conservation Code ......2012 IECC (International Energy Conservation Code) Compliance Documentation Career Development Seminar State of Connecticut

6/4/2015

6

Sample Residential Project

Other System Notes

• Plumbing system

– Automatic circulating hot water system to be provided.

– All hot water piping to have R-3 insulation.

• Lighting system

– CFL or LED lamps to be installed in all fixtures

16

Sample Residential Project

REScheck

17

Sample Residential Project

REScheck

18

Page 7: 2012 IECC (International Energy Conservation Code ......2012 IECC (International Energy Conservation Code) Compliance Documentation Career Development Seminar State of Connecticut

6/4/2015

7

Sample Residential Project

Heating and Cooling Load Calculations

Heating Load (≤72° Design)

• Conductive heat losses(U × A × ΔT)

• Infiltration heat losses[1.1 × (ACH/60) × vol × ΔT]

• Ventilation heat losses[1.1 × Vent Rate × ΔT × (1- eff)]

Design outdoor air temperature (ASHRAE 90.1-2013)

99.6% 1% db 1% wb

Bridgeport 8° 84° 72°

Hartford 2° 88° 72°

Cooling Load (≥75° Design)

• Conductive heat gains

• Radiation heat gains

• Infiltration heat gains

• Infiltration humidity gains

• Ventilation heat gains

• People heat loads

• People humidity loads

• Equipment loads

• Cooking loads

19

Sample Residential Project

REScheck

20

Sample Residential Project

REScheck

21

Page 8: 2012 IECC (International Energy Conservation Code ......2012 IECC (International Energy Conservation Code) Compliance Documentation Career Development Seminar State of Connecticut

6/4/2015

8

Sample Residential Project

REScheck

22

Sample Residential Project

REScheck

23

Sample Residential Project

REScheck

24

Page 9: 2012 IECC (International Energy Conservation Code ......2012 IECC (International Energy Conservation Code) Compliance Documentation Career Development Seminar State of Connecticut

6/4/2015

9

Sample Residential Project

REScheck

25

Compliance DocumentationFor Commercial Projects

• Identify the code to be complied with

• Approaches– Project requirements scattered throughout the

construction documents

– COMcheck

– AIA Connecticut sample documentation

– Forms from codes/standards organization

– Forms from US Department of Energy

– Forms as developed by designer or design professional

26

Compliance RequirementFor Commercial Projects

• C401.2 Application: comply with ONE of:1. ANSI/ASHRAE/IESNA Standard 90.1-20102. Sections C402 (Envelope), C403 (Mechanical Systems), C404

(Service Water Heating), C405 (Electrical Power and Lighting Systems) AND WITH either Section 406.2 (Efficient HVAC Performance), 406.3 (Efficient Lighting System) or C406.4 (On-site Renewable Energy)

3. Section C407 (Total Building Performance) and all mandatory requirements. Building energy cost shall be ≤85% of standard reference design building.

• C401.2.1 Application to existing buildingAdditions, alterations and repairs shall comply with ONE of:• Sections C402, C403, C404 and C405, or• ANSI/ASHRAE/IESNA Standard 90.1-2010

27

Page 10: 2012 IECC (International Energy Conservation Code ......2012 IECC (International Energy Conservation Code) Compliance Documentation Career Development Seminar State of Connecticut

6/4/2015

10

Sample Commercial Project

First Floor Plan

W-1

W-1

W-1

W-1

W-1

W-1

W-1

W-1

W-1

W-1

W-1 W-1 W-1

W-1 W-1 W-1

W-1W-2 W-2D-1

W-3 W-3D-2

W-4

Partially Conditioned Vestibule

13’-0” Floor to Floor Height9’-0” Floor to Ceiling Height

28

Sample Commercial Project

Second Floor Plan

W-1

W-1 W-1 W-1 W-1 W-1

W-1

W-1

W-1

W-1

W-1

W-1

W-1

W-1

W-1

W-1 W-1 W-1 W-1 W-1

13’-0” Floor to Roof Height9’-0” Floor to Ceiling Height

29

Sample Commercial Project

Sections

Wall Section at Slab Roof Section

Metal Roof Deck

Rigid Board Insulation (R-25)

Roof Membrane

2” Foam Insulation (R-10)to 24” below floor level

Concrete Foundation

Concrete Slab

Sheetrock & Vapor Retarder

6” Metal Stud Wall

6” Fiberglass Insulation (R-19)

Sheathing1½” Foam Insulation (R-7.5)

Air Barrier

Air Space

Brick

Grade

30

Page 11: 2012 IECC (International Energy Conservation Code ......2012 IECC (International Energy Conservation Code) Compliance Documentation Career Development Seminar State of Connecticut

6/4/2015

11

Sample Commercial Project

Envelope Notes/Details

31

Sample Commercial Project

Envelope Notes/Details

• Air barrier shall be continuous over all surfaces.

• Air barrier sealing details for penetrations and fenestration shall be followed.

• Doors in vestibule shall be equipped with self-closing devices

32

Sample Commercial Project

Mechanical Schedules/Notes

33

Page 12: 2012 IECC (International Energy Conservation Code ......2012 IECC (International Energy Conservation Code) Compliance Documentation Career Development Seminar State of Connecticut

6/4/2015

12

Sample Commercial Project

Mechanical Notes/Details

• Heat loss and cooling load calculations are provided.

• Building automation system shall control HVAC system functions and schedule.

• HVAC shall be low-pressure variable-air-volume system with parallel fan powered boxes with hot water coils.

• Perimeter hot water baseboard shall be provided as shown on drawings.

34

Sample Commercial Project

Mechanical Notes/Details

• Ducts, air handlers and filter boxes shall be sealed.

• 2” of insulation with conductivity of 0.27 shall be installed on all heating pipes.

• Air systems and hydronic systems shall be adjusted and balanced.

35

Sample Commercial Project

Mechanical Notes/Details

• Commissioning plan for the mechanical system shall be followed.

• Preliminary commissioning report shall be given to owner’s representative before final inspection by the building official.

• As built drawings including performance data shall be provided.

• Operations manuals and maintenance manuals shall be provided.

36

Page 13: 2012 IECC (International Energy Conservation Code ......2012 IECC (International Energy Conservation Code) Compliance Documentation Career Development Seminar State of Connecticut

6/4/2015

13

Sample Commercial Project

Service Water Schedules/Notes

• ½” insulation with a conductivity of 0.27 shall be installed on hot water pipes between instantaneous water heater and faucet.

37

Sample Commercial Project

Interior Lighting Schedules/Notes/DetailsLightingFixtureSchedule

Thisofficebuildingprojectisdesignedto2012IECCwithefficientlightingsystemefficiencypackageoption(0.85wattspersquarefoot)

ID Description Lamp Ballast Input

No Type Series Type

Ballast

Factor

12x4RecessedIndirectTroffer 2 F32T8HP 800

PremiumElectronic,ProgramStart 0.88 56

2a2x2RecessedIndirectTroffer 2 F17T8HP 800

PremiumElectronic,InstantStart 0.88 30

2b

2x2RecessedIndirect

Troffer 2 F17T8HP 800

PremiumElectronic,

InstantStart 0.88 303 6"Downlight 1 LED16w 16

4 1x4WallMount 1 F32T8HP 800PremiumElectronic,

RapidStart 0.88 28

• Luminaires in conference/meeting rooms, lunch/break rooms private offices, restrooms and storage rooms shall be controlled by occupancy sensors.

• Controls in all other spaces, except corridors, shall allow for manual reduction of lighting load by at least 50 percent.

• Task lighting shall have automatic occupancy sensor controls.

38

Sample Commercial Project

Exterior Lighting Schedules/Notes/Details

• Exterior lighting shall be controlled by an astronomical time switch

39

Page 14: 2012 IECC (International Energy Conservation Code ......2012 IECC (International Energy Conservation Code) Compliance Documentation Career Development Seminar State of Connecticut

6/4/2015

14

Sample Commercial Project

COMcheck Inputs

40

Sample Commercial Project

COMcheck Inputs

41

Sample Commercial Project

COMcheck Inputs

42

Page 15: 2012 IECC (International Energy Conservation Code ......2012 IECC (International Energy Conservation Code) Compliance Documentation Career Development Seminar State of Connecticut

6/4/2015

15

Sample Commercial Project

COMcheck Report

43

Sample Commercial Project

COMcheck Report

44

Sample Commercial Project

COMcheck Report

45

Page 16: 2012 IECC (International Energy Conservation Code ......2012 IECC (International Energy Conservation Code) Compliance Documentation Career Development Seminar State of Connecticut

6/4/2015

16

Sample Commercial Project

COMcheck Report

46

Sample Commercial Project

COMcheck Report

47

Sample Commercial Project

COMcheck Report

48

Page 17: 2012 IECC (International Energy Conservation Code ......2012 IECC (International Energy Conservation Code) Compliance Documentation Career Development Seminar State of Connecticut

6/4/2015

17

Sample Commercial Project

COMcheck Report

49

Sample Commercial Project

COMcheck Report

50

Sample Commercial Project

COMcheck Report

51

Page 18: 2012 IECC (International Energy Conservation Code ......2012 IECC (International Energy Conservation Code) Compliance Documentation Career Development Seminar State of Connecticut

6/4/2015

18

Sample Commercial Project

AIA CT Sample DocumentationASHRAE/IESN

A Values In Values

Standard Simulation For Incorporated

90.1-2010 Proposed Into This

Element Requirement Building Design Design

See the instructions and disclaimer for this spreadsheet. Commercial Values In Values

Chapter 4 [CE] Simulation for Incorporated

2012 IECC Proposed Into This

Element Requirement Building Design Design

Total Building Performance, Annual Energy Cost For Standard

Reference Design

Building

Compliance is demonstrated when the proposed building's energy cost is equal to or less than

85 percent of the standard reference design building's energy cost.For Proposed

Design Building

ASHRAE/IESNA Values

Standard Incorporated

90.1-2010 Into This

Element Requirement Design

52

AIA CT Sample Documentation

53

http://aiact.org/about-aia-connecticut/committees/building-performance-regulations/

Building Performance & RegulationsAIA Connecticut Committees

Sample Commercial Project

AIA CT Sample Documentation

54

Page 19: 2012 IECC (International Energy Conservation Code ......2012 IECC (International Energy Conservation Code) Compliance Documentation Career Development Seminar State of Connecticut

6/4/2015

19

Sample Commercial Project

AIA CT Sample Documentation

55

Sample Commercial Project

AIA CT Sample Documentation

56

Sample Commercial Project

AIA CT Sample Documentation

57

Page 20: 2012 IECC (International Energy Conservation Code ......2012 IECC (International Energy Conservation Code) Compliance Documentation Career Development Seminar State of Connecticut

6/4/2015

20

Sample Commercial Project

AIA CT Sample Documentation

58

Sample Commercial Project

AIA CT Sample Documentation

59

Sample Commercial Project

AIA CT Sample Documentation

60

Page 21: 2012 IECC (International Energy Conservation Code ......2012 IECC (International Energy Conservation Code) Compliance Documentation Career Development Seminar State of Connecticut

6/4/2015

21

Sample Commercial Project

AIA CT Sample Documentation

61

Sample Commercial Project

AIA CT Sample Documentation

62

Further Questionsand/or

Discussions

Thank You!

Frederick F. Wajcs, Jr., P.E.Energy Code Consultant