    Jackson County2014 2018

    Capital Improvement Program

    County Commissioners

    William Tusa, District One - Chair

    Kim Hummel, District Four - Vice-Chair

    Gary Willink, District Two

    Rosemary Schultz, District Three

    David Henkels, District Five

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    2/59

    This page intentionally left blank

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    3/59

    Jackson County2014 2018

    Capital Improvement Program

    Contents

    SECTION 1Overview of Process and Debt Policy

    SECTION 2Affidavit of Public Hearing NoticeCounty Board Resolution

    SECTION 3Limits to Indebtedness

    Underlying, Overlapping and Direct Debt DeterminationCombined Debt Service ScheduleCategory Summary by DepartmentProjects by Category and DepartmentProjects by Year and PriorityFunding Source SummaryChart: Revenue Sources All Departments 2014 OnlyChart: Revenue Sources All Departments 2014 2018Projects by Funding SourceProjects and Funding Sources by Department #1Projects and Funding Sources by Department #2Property Tax DetailWind Production Tax Revenue

    SECTION 4Coordinators & Information Systems Projects

    SECTION 5Highway Projects

    SECTION 6Parks, Planning and Zoning Projects

    SECTION 7Sheriffs Department Projects

    SECTION 8Veterans Services Department Projects

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    4/59

    August 14, 2012

    Jackson CountyCapital Improvement Program Policy

    Overview

    The J ackson County Capital Improvement Program (CIP) is a comprehensive document that detailsprojects and equipment purchases that are anticipated over the next five years, as well as the anticipatedsources of funding. The annual review process allows the County to reassess the capital needs of thecounty in light of changing financial conditions, goals and priorities. The adopted CIP is the result ofcareful planning and decision-making by County officials and reflects the County Boards policy directionon major public improvements.

    The capital improvement planning process provides the following benefits:

    1. The Countys capital improvements are organized, reviewed and presented in a systematic formatthat coordinates projects, costs and revenue sources between departments and agencies.

    2. The CIP planning process forces County officials to look ahead and see what the needs of the Countywill be and plan for future projects, while taking into consideration internal and external factors suchas changing population and availability of funds.

    3. The establishment of policy guidelines regarding the desired annual levels of capital improvementinvestments and the means of funding them allow for more efficient and effective management ofavailable resources.

    4. A CIP helps distribute costs more equitably over a longer period of time, while enhancingopportunities for utilization of non-local dollars through better planning.

    Defini tion of Capital Improvements

    For the purposes of the J ackson County Capital Improvement Program, capital improvements are definedas having a minimum value and/or useful life as follows:

    Highway Improvements - $100,000 and a useful life of at least ten (10) yearsIncludes construction and re-construction

    Buildings/Facilities - $50,000 ora useful life of at least ten (10) years

    Major Equipment - $50,000 and a useful life of at least three (3) years

    Vehicles - $15,000

    Criteria

    In conformance with Minnesota Statutes Chapter 373.40 subdivision 3, each project in the CapitalImprovement Program must consider the following eight criteria:

    1. The condition of the countys existing infrastructure, including the projected need for repair orreplacement;

    2. The likely demand for the improvement;3. The estimated cost of the improvement;4. The available public resources;5. The level of overlapping debt in the county;6. The relative benefits and costs of alternative uses of the funds;7. Operating costs of the proposed improvements; and8. Alternatives for providing services more efficiently through shared facilities with other counties or local

    government units.

    Jackson County 2014 - 2018 Capital Improvement Program Page 1

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    5/59

    August 14, 2012

    Structure of CIP CommitteeThe CIP Committee is responsible for reviewing departmental requests, prioritizing the projects andmaking recommendations to the County Board regarding the content of the CIP on an annual basis. TheCIP Committee will be appointed annually by the County Board with the following membership:

    Two County Commissioners (typically Vice Chair and next Vice Chair)

    County Auditor/Treasurer County Coordinator

    County Highway Engineer

    Three Department Heads appointed to staggered, three year terms.(Note Initial appointment will be for a one year, two year and three year term each)

    Capital Improvement Program Summary of Process

    The CIP planning process will be conducted in J anuary through J une of each year. The following is ageneral summary of the planning process:

    Distributes capital improvement request forms to Departmentsand coordinates planning process

    Prioritizes departmental needs and prepares justification for thedepartmental requests

    Review departmental requests, assure conformance with CountyMission Statement and Statement of Values, prioritize capital

    needs and determine content of CIP

    Give preliminary approval of CIP

    Presentation of CIP and gathering public input

    Adoption of CIP

    Coordinator

    Department Heads

    CIP Committee

    County Board

    Public Hearing

    County Board

    Jackson County 2014 - 2018 Capital Improvement Program Page 2

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    6/59

    August 14, 2012

    Evaluation and Ranking of Projects

    The CIP Committee will evaluate and categorize each proposed project as follows:

    Urgent Cannot be postponed; needed for essential service; partially completed project;maintenance of minimum safety or mandated by state or federal law.

    Necessary Should be carried out to meet needs of current programs at existing levels, orreplacement of unsatisfactory facility.

    Desirable Needed for proper expansion of existing program or department. Can wait until funds areavailable.

    Deferrable Needed for ideal operation but cannot yet be recommended for action. Can bepostponed without lessening of service.

    Projects will be prioritized within each category.

    Debt Policy

    The County strives to keep its level of indebtedness to a minimum. However, it is often necessary andappropriate to use debt as a means of financing projects that will ultimately benefit the citizens of J acksonCounty. A debt policy provides guidance to all participants in the capital improvement process by spellingout the policy objectives of the County and the acceptable parameters of debt issuance andmanagement.

    J ackson County will consider all means available for financing capital improvement projects. This mayinclude the following sources:

    County tax dollars

    Wind production tax revenue

    Funds from federal sources

    Funds from state sources, such as state highway aides Local municipal government cost sharing

    Fees and other revenues

    Transfers from other funds

    Bonding

    Other sources of income

    The following guidelines will be followed when project requests are evaluated and funding decisions aremade:

    1. The County will maintain its ability to support current debt and incur additional debt at minimalinterest rates and in the amounts required for infrastructure and other capital assets withoutendangering the ability of the County to finance essential services.

    2. Debt will be used sparingly and only after other means of financing are fully investigated.3. No debt which becomes an obligation of the County or any of its agencies will be issued for a

    term longer than the reasonably expected useful life of the asset being funded, but in no event forlonger than 30 years for real property or 5 year for equipment.

    4. The proceeds of all debt issues will be expended in compliance with all applicable state andfederal laws and rules and in conformity with all covenants of the issue. Such laws, rules, andcovenants will be strictly construed.

    5. No debt will be issued to fund normal operations of the County or any of its agencies. This doesnot exclude the possibility of issuing Tax Anticipation Notes as a financial and investmentstrategy.

    6. Debt will not be issued in excess of any statutory limit.

    Jackson County 2014 - 2018 Capital Improvement Program Page 3

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    7/59

    August 14, 2012

    7. Property tax supported debt, including capital notes, will not be issued beyond the point whereannual debt service levy demands exceed 10% of the operating budget.

    8. When considering additional tax supported debt, the County will consider the total level of debt forall taxing jurisdictions and the effect additional debt will have on the tax dollars paid by thetaxpayers of J ackson County.

    9. The County will avoid, where possible, the issuance of general obligation debt by utilizingavailable funds, reserves, and revenue bonds or other types of issues.

    Jackson County 2014 - 2018 Capital Improvement Program Page 4

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    8/59

    Jackson County2014-2018 Capital Improvement Program

    Limits to Indebtedness

    Legal Debt LimitMinnesota Statute 475.53 sub. 1 limits the total net debt to 3% of the Taxable Market Value

    2013 Taxable Market Value $2,848,713,100

    Legal Debt Limitation x 3%

    Maximum Legal Debt Limit $85,461,393

    Less: Outstanding Debt Subject to Limitations ($3,530,000) ** Does not include $14,260,000

    Legal Debt Margin $81,931,393 G.O. CIP debt funded in 2013.

    Maximum Annual Debt Service fo r CIP Bonds

    Minnesota Statute 373.40 limits the annual debt service for principal and interest on Capital

    Improvement Bonds to .12% of the Taxable Market Value per year.

    2013 Taxable Market Value $2,848,713,100

    CIP Debt Service Limitation 0.12%

    Maximum Annual Debt Service/CIP Levy $3,418,456

    Less: Existing CIP Debt Service Levy ($290,338)

    CIP Debt Service Margin $3,128,118

    Debt Ratio

    J ackson County Debt Policy #7 limits the Total Property Tax supported debt service levy to

    10% of the total budget.

    2013 Budget $18,100,841Debt Service Limitation x 10%

    Maximum Annual Debt Service $1,810,084

    Less: Existing Debt Service Levy ($567,533)

    Debt Service Margin $1,242,551

    Jackson County 2014 - 2018 Capital Improvement Program Page 5

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    9/59

    Jackson County2014-2018 Capital Improvement Program

    Underlying, Overlapping and Direct Debt Determination

    Taxing Unit

    Total Payable

    2013 Market

    Value

    Total Payable

    2013 Net Tax

    Capacity

    Total G.O. Debt **

    as of 1-1-2013

    Net Tax Capacity

    within Jackson

    County

    Net Tax Capacity

    % within Jackson

    County

    Debt Applicable toNet Tax Capacity

    within Jackson

    County

    County of J ackson $2,351,930,300 $20,290,239 $3,530,000 $20,290,239 100.00% $3,530,000

    Cities:

    Alpha $1,757,400 $20,561 $40,579 $20,561 100.00% $40,579

    Heron Lake $17,792,600 $218,434 $560,000 $218,434 100.00% $560,000

    J ackson $119,531,500 $1,510,702 $7,511,800 $1,510,702 100.00% $7,511,800

    Lakefield $49,964,000 $560,701 $1,610,000 $560,701 100.00% $1,610,000

    Okabena $3,825,800 $40,116 $0 $40,116 100.00% $0

    Wilder $2,258,900 $24,299 $36,420 $24,299 100.00% $36,420

    Schools:

    Mt. Lake #173 $517,749,000 $4,466,367 $0 $558,462 12.50% $0

    Windom #177 $731,986,700 $6,747,625 $10,900,000 $1,793,131 26.57% $2,896,130

    HL/Okabena #330 $413,285,800 $3,898,485 $2,400,000 $3,424,527 87.84% $2,108,160

    Brewster #513 $290,303,300 $2,367,206 $0 $803,847 33.96% $0

    Round Lake #516 $198,432,800 $1,691,443 $0 $699,124 41.33% $0

    MCW #2448 $1,054,089,300 $10,245,261 $390,000 $58,209 0.57% $2,223

    J ackson CC #2895 $1,481,387,800 $12,966,659 $12,090,000 $12,952,939 99.89% $12,076,701

    % of Benefits

    within Jackson

    County

    Debt Applicable to

    Benefits in J ackson

    County

    Drainage Bonds $180,000 81.59% $146,862

    Total Debt $39,248,799 $30,518,875

    ** Does not include GO Revenue or Revenue Debt

    Jackson County 2014 - 2018 Capital Improvement Program Page 6

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    10/59

    Jackson County

    2014-2018 Capital Improvement Program

    Combined Debt Service Schedule

    Year

    Heron Lk Water

    Pipe Project -

    GO Water

    Revenue Bonds

    Heron Lk Water

    Trmnt Project - GO

    Water Revenue

    Bonds (Refunding

    2011A)

    RRRW Phase II

    - GO Water

    Revenue Bonds

    Total Revenue

    Bonds

    Street

    Reconstruction

    Bond 2008A

    Total Non-CIP

    Bonds/Notes

    CIP Bond

    2008A

    CIP

    Refunding

    Bond 2009B

    C

    2014 $163,500 $430,731 $122,200 $716,431 $266,735 $266,735 $29,780 $245,908

    2015 $166,625 $442,031 $124,825 $733,481 $263,685 $263,685 $33,905 $247,203

    2016 $164,200 $446,738 $122,213 $733,150 $264,755 $264,755 $37,765 $252,703

    2017 $161,500 $459,825 $119,600 $740,925 $265,200 $265,200 $36,400 $257,453

    2018 $163,525 $476,525 $121,988 $762,038 $0 $201,403

    2019 $331,625 $119,138 $450,763 $0 $206,303

    2020 $339,000 $116,288 $455,288 $0 $210,543

    2021 $350,200 $118,438 $468,638 $0 $214,178

    2022 $115,350 $115,350 $0 $212,278

    2023 $112,263 $112,263 $0

    2024 $114,175 $114,175 $0

    2025 $115,850 $115,850

    2026 $117,288 $117,288

    2027 $118,488 $118,488

    2028 $119,450 $119,450

    2029 $120,175 $120,175

    2030 $125,663 $125,663

    2031 $125,675 $125,675

    2032 $120,450 $120,450

    2033 $115,225 $115,225

    2034

    2035

    2036

    2037

    2038

    Jackson County 2014 - 2018 Capital Improvement Program

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    11/59

    Capital Improvement Program

    Jackson County, Minnesota

    CATEGORY SUMMARY BY DEPARTMENT

    thru2014 2018

    Total2014 2015 2016 2017 2018Department

    Category Future

    Coordinator/Information Sys

    Buildings 1,150,000 40,000 1,190,000

    Computer/Commun Equip 67,300 81,500 67,200 50,600 69,900 336,500

    67,300 81,500 1,217,200 90,600 69,900 1,526,500Department Total

    Highway Department

    Highway: Bridge Construction 930,000 550,000 810,000 2,290,000

    Highway: Road Construction 3,575,000 2,643,000 3,048,000 1,520,000 1,592,000 12,378,000

    Highway: Trail Construction 198,000 198,000

    Land 500,000 500,000

    Vehicles:Auto/Trucks 140,000 347,000 350,000 51,500 22,000 910,500

    Vehicles:Highway Maintenance 405,000 700,000 257,000 230,000 235,000 1,827,000

    5,050,000 4,740,000 4,663,000 1,801,500 1,849,000 18,103,500Department Total

    Planning & Environmental Svs

    Vehicles:Auto/Trucks 30,000 30,000

    30,000 30,000Department Total

    Sheriff

    Vehicles:Auto/Trucks 65,000 66,600 68,200 69,800 71,400 341,000

    65,000 66,600 68,200 69,800 71,400 341,000Department Total

    Veterans Services

    Vehicles:Auto/Trucks 27,000 27,000

    27,000 27,000Department Total

    5,182,300 4,915,100 5,978,400 1,961,900 1,990,300 20,028,000GRAND TOTAL

    Jackson County 2014 - 2018 Capital Improvement Program Page 8

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    12/59

    Capital Improvement Program

    Jackson County, Minnesota

    PROJECTS BY CATEGORY AND DEPARTMENT

    2014 2018thru

    Total2014 2015 2016 2017 2018Department

    Category Future

    Coordinator/Information Sys

    Bui ld ings

    1,150,000 1,150,000Government Center East

    40,000 40,000Courthouse Roof

    1,150,000 40,000 1,190,000 Category Sub-Total

    Computer /Commun Equ ip

    42,000 42,000 42,000 42,000 42,000 210,000IS Equipment Replacement

    25,300 39,500 25,200 8,600 27,900 126,500Copier Replacement

    67,300 81,500 67,200 50,600 69,900 336,500 Category Sub-Total

    67,300 81,500 1,217,200 90,600 69,900 1,526,500Department Total:

    Highway Department

    Bui ld ings

    County Maintenance Facilities: Jackson & Lakefield

    Category Sub-Total

    Highway: Bridge Construct ion

    450,000 160,000 470,000 1,080,000County Bridge Replacement Program

    480,000 390,000 340,000 1,210,000Township Bridge Replacement Program

    930,000 550,000 810,000 2,290,000 Category Sub-Total

    Highway: Road Construct ion

    190,000 200,000 210,000 220,000 230,000 1,050,000Sealcoat Program

    1,575,000 383,000 1,188,000 1,250,000 1,312,000 5,708,000Overlay Program

    50,000 50,000Purchase of Storage/Staging Sites

    10,000 10,000 20,000Section Corner Reestablishment

    50,000 50,000 50,000 50,000 200,000CR 70 - Regrade

    CSAH 29 - Widening

    1,800,000 1,800,000CSAH 29 - Base & Wear

    1,550,000 1,600,000 3,150,000CSAH 29 - Reconstruction

    400,000 400,000CSAH 23 - Petersburg Intersections

    3,575,000 2,643,000 3,048,000 1,520,000 1,592,000 12,378,000 Category Sub-Total

    Highway: Trai l Construct ion

    198,000 198,000Trail - Ft. Belmont Trail

    198,000 198,000 Category Sub-Total

    Land

    500,000 500,000Gravel Pit Purchase

    500,000 500,000 Category Sub-Total

    Jackson County 2014 - 2018 Capital Improvement Program Page 9

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    13/59

    Total2014 2015 2016 2017 2018

    Department

    Category Future

    Vehic les:Auto/Trucks

    40,000 25,000 26,000 21,500 22,000 134,500Jackson County Passenger Vehicles

    30,000 30,000 31,000 91,000Engineering & Maintenance Supervisor Pickup Fleet

    202,000 136,000 338,000Ditch Equipment

    70,000 90,000 30,000 30,000 220,000Maintenance Pickup Fleet

    127,000 127,000Unit 23 - Sign Truck

    140,000 347,000 350,000 51,500 22,000 910,500 Category Sub-Total

    Vehic les:Highw ay Maintenance

    215,000 220,000 225,000 230,000 235,000 1,125,000 2,690,000Tandem Fleet

    260,000 260,000 970,000Motor Grader Fleet

    220,000 220,000Unit 52 - Oshkosh w/Sno Go

    190,000 190,000Unit 61 - Loader

    32,000 32,000Unit 64 - 873 Bobcat

    405,000 700,000 257,000 230,000 235,000 1,827,000 3,660,000Category Sub-Total

    5,050,000 4,740,000 4,663,000 1,801,500 1,849,000 18,103,500 3,660,000Department Total:

    Planning & Environmental Svs

    Park Impro vements

    Loon Lake Trails Phase III

    Category Sub-Total

    Vehic les:Auto/Trucks

    Ford Utility Truck

    30,000 30,000Ford F-250 Pickup

    30,000 30,000 Category Sub-Total

    30,000 30,000Department Total:

    SheriffVehic les:Auto/Trucks

    65,000 66,600 68,200 69,800 71,400 341,000Squad Car Replacement Program

    65,000 66,600 68,200 69,800 71,400 341,000 Category Sub-Total

    65,000 66,600 68,200 69,800 71,400 341,000Department Total:

    Veterans Services

    Vehic les:Auto/Trucks

    27,000 27,000Veterans Van

    27,000 27,000 Category Sub-Total

    27,000 27,000

    Department Total:

    5,182,300 4,915,100 5,978,400 1,961,900 1,990,300 20,028,000 3,660,000GRAND TOTAL

    Jackson County 2014 - 2018 Capital Improvement Program Page 10

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    14/59

    Capital Improvement Program

    Jackson County, Minnesota

    PROJECTS BY YEAR & PRIORITY

    2014 2018thru

    Project Name Department Project # Priority Project Cost

    2014

    Priori ty 1 Urgent

    08-HWY-BRCTYCounty Bridge Replacement Program 1 450,000Highway Department

    09-HWY-BRTWPTownship Bridge Replacement Program 1 480,000Highway Department

    09-HWY-TNDMSTandem Fleet 1 215,000Highway Department

    12-HWY-29-43CSAH 29 - Base & Wear 1 1,800,000Highway Department

    05-SHRF-037Squad Car Replacement Program 1 65,000Sheriff

    3,010,000Total for: Priority 1

    Pri ori ty 2 Necessary

    01-IS-002IS Equipment Replacement 2 42,000Coordinator/Information Sys

    07-IS-003Copier Replacement 2 25,300Coordinator/Information Sys

    05-HWY-SEALSealcoat Program 2 190,000Highway Department

    06-JC-FLEETJackson County Passenger Vehicles 2 40,000Highway Department

    07-HWY-OVRLYOverlay Program 2 1,575,000Highway Department

    08-HWY-SURSection Corner Reestablishment 2 10,000Highway Department

    09-HWY-EFLTEngineering & Maintenance Supervisor Pickup Fleet 2 30,000Highway Department

    10-HWY-MFLTMaintenance Pickup Fleet 2 70,000Highway Department

    13-HWY-061Unit 61 - Loader 2 190,000Highway Department

    2,172,300Total for: Priority 2

    5,182,300Total for 2014

    2015

    Priori ty 1 Urgent

    08-HWY-BRCTYCounty Bridge Replacement Program 1 160,000Highway Department

    09-HWY-BRTWPTownship Bridge Replacement Program 1 390,000Highway Department

    09-HWY-TNDMSTandem Fleet 1 220,000Highway Department

    12-HWY-045Motor Grader Fleet 1 260,000Highway Department

    13-HWY-29-01CSAH 29 - Reconstruction 1 1,550,000Highway Department

    14-HWY-23-21CSAH 23 - Petersburg Intersections 1 400,000Highway Department

    05-SHRF-037Squad Car Replacement Program 1 66,600Sheriff

    3,046,600Total for: Priority 1

    Pri ori ty 2 Necessary01-IS-002IS Equipment Replacement 2 42,000Coordinator/Information Sys

    07-IS-003Copier Replacement 2 39,500Coordinator/Information Sys

    05-HWY-SEALSealcoat Program 2 200,000Highway Department

    06-JC-FLEETJackson County Passenger Vehicles 2 25,000Highway Department

    07-HWY-OVRLYOverlay Program 2 383,000Highway Department

    08-HWY-SURSection Corner Reestablishment 2 10,000Highway Department

    09-HWY-EFLTEngineering & Maintenance Supervisor Pickup Fleet 2 30,000Highway Department

    10-HWY-DFLTDitch Equipment 2 202,000Highway Department

    10-HWY-MFLTMaintenance Pickup Fleet 2 90,000Highway Department

    Jackson County 2014 - 2018 Capital Improvement Program Page 11

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    15/59

    Project Name Department Project # Priority Project Cost

    10-HWY-PITGravel Pit Purchase 2 500,000Highway Department

    12-HWY-052Unit 52 - Oshkosh w/Sno Go 2 220,000Highway Department

    09-VSO-01Veterans Van 2 27,000Veterans Services

    1,768,500Total for: Priority 2

    Priori ty 3 Desir eable

    08-HWY--PROPPurchase of Storage/Staging Sites 3 50,000Highway Department

    09-HWY-70-01CR 70 - Regrade 3 50,000Highway Department

    100,000Total for: Priority 3

    4,915,100Total for 2015

    2016

    Priori ty 1 Urgent

    08-HWY-BRCTYCounty Bridge Replacement Program 1 470,000Highway Department

    09-HWY-BRTWPTownship Bridge Replacement Program 1 340,000Highway Department

    09-HWY-TNDMSTandem Fleet 1 225,000Highway Department

    13-HWY-29-01CSAH 29 - Reconstruction 1 1,600,000Highway Department

    05-SHRF-037Squad Car Replacement Program 1 68,200Sheriff

    2,703,200Total for: Priority 1

    Pri ori ty 2 Necessary

    01-IS-002IS Equipment Replacement 2 42,000Coordinator/Information Sys

    07-IS-003Copier Replacement 2 25,200Coordinator/Information Sys

    13-COORD-006Government Center East 2 1,150,000Coordinator/Information Sys

    05-HWY-SEALSealcoat Program 2 210,000Highway Department

    06-JC-FLEETJackson County Passenger Vehicles 2 26,000Highway Department

    07-HWY-OVRLYOverlay Program 2 1,188,000Highway Department

    09-HWY-EFLTEngineering & Maintenance Supervisor Pickup Fleet 2 31,000Highway Department

    10-HWY-DFLTDitch Equipment 2 136,000Highway Department

    10-HWY-MFLTMaintenance Pickup Fleet 2 30,000Highway Department

    11-HWY-FTBELTrail - Ft. Belmont Trail 2 198,000Highway Department

    14-P&E-010Ford F-250 Pickup 2 30,000Planning & Environmental Svs

    3,066,200Total for: Priority 2

    Priori ty 3 Desir eable

    09-HWY-70-01CR 70 - Regrade 3 50,000Highway Department

    16-HWY-023Unit 23 - Sign Truck 3 127,000Highway Department

    16-HWY-064Unit 64 - 873 Bobcat 3 32,000Highway Department

    209,000Total for: Priority 3

    5,978,400Total for 2016

    2017

    Priori ty 1 Urgent09-HWY-TNDMSTandem Fleet 1 230,000Highway Department

    05-SHRF-037Squad Car Replacement Program 1 69,800Sheriff

    299,800Total for: Priority 1

    Pri ori ty 2 Necessary

    01-IS-002IS Equipment Replacement 2 42,000Coordinator/Information Sys

    07-IS-003Copier Replacement 2 8,600Coordinator/Information Sys

    17-COORD-005Courthouse Roof 2 40,000Coordinator/Information Sys

    05-HWY-SEALSealcoat Program 2 220,000Highway Department

    Jackson County 2014 - 2018 Capital Improvement Program Page 12

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    16/59

    Project Name Department Project # Priority Project Cost

    06-JC-FLEETJackson County Passenger Vehicles 2 21,500Highway Department

    07-HWY-OVRLYOverlay Program 2 1,250,000Highway Department

    10-HWY-MFLTMaintenance Pickup Fleet 2 30,000Highway Department

    1,612,100Total for: Priority 2

    Priori ty 3 Desir eable

    09-HWY-70-01CR 70 - Regrade 3 50,000Highway Department

    50,000Total for: Priority 3

    1,961,900Total for 2017

    2018

    Priori ty 1 Urgent

    09-HWY-TNDMSTandem Fleet 1 235,000Highway Department

    05-SHRF-037Squad Car Replacement Program 1 71,400Sheriff

    306,400Total for: Priority 1

    Pri ori ty 2 Necessary

    01-IS-002IS Equipment Replacement 2 42,000Coordinator/Information Sys

    07-IS-003Copier Replacement 2 27,900Coordinator/Information Sys05-HWY-SEALSealcoat Program 2 230,000Highway Department

    06-JC-FLEETJackson County Passenger Vehicles 2 22,000Highway Department

    07-HWY-OVRLYOverlay Program 2 1,312,000Highway Department

    1,633,900Total for: Priority 2

    Priori ty 3 Desir eable

    09-HWY-70-01CR 70 - Regrade 3 50,000Highway Department

    50,000Total for: Priority 3

    1,990,300Total for 2018

    GRAND TOTAL 20,028,000

    Jackson County 2014 - 2018 Capital Improvement Program Page 13

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    17/59

    Capital Improvement Program

    Jackson County, Minnesota

    FUNDING SOURCE SUMMARY

    2014 thru 2018

    TotalSource 2014 2015 2016 2017 2018

    Ditches 338,000202,000 136,000

    Energy Program 1,100,0001,100,000

    Federal Funds 1,662,0001,520,000 142,000

    Intergrated Fund 20,00010,000 10,000

    IS Equipment 327,90067,300 81,500 67,200 42,000 69,900

    Local (City) Contribution 43,00043,000

    Local (Township) 80,00020,000 40,000 20,000

    Property Tax 3,473,000720,000 1,441,600 625,200 374,800 311,400

    Recorder's Equipment Fund 8,6008,600

    Road and Bridge Reserves 383,000383,000

    State Aid 10,925,0002,495,000 2,200,000 3,218,000 1,470,000 1,542,000

    State Bridge Bonds 530,000170,000 110,000 250,000

    Town Bridge 810,000140,000 350,000 320,000

    Vehicle Replacement Fund 134,50040,000 25,000 26,000 21,500 22,000

    5,182,300 4,843,100 5,947,400 1,916,900 1,945,300 19,835,000GRAND TOTAL

    Jackson County 2014 - 2018 Capital Improvement Program Page 14

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    18/59

    State Aid50%

    Federal30% Other

    0%

    Revenue Sources - All Departments 201

    Jackson County 2014 - 2018 Capital Improvement Program

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    19/59

    Town Bridge4%

    Federal8%

    State Bridge Bonds

    3%

    Other2%

    Property Tax19%

    Local1%

    State A55%

    Reserves

    3%Energy Program5%

    Revenue Sources - All Departments 2014

    Jackson County 2014 - 2018 Capital Improvement Program

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    20/59

    Capital Improvement Program

    Jackson County, Minnesota

    PROJECTS BY FUNDING SOURCE

    2014 2018thru

    TotalSource Project# Priority 2014 2015 2016 2017 2018

    Ditches

    10-HWY-DFLT 338,000202,000 136,000Ditch Equipment 2

    338,0002 02 ,0 00 13 6,0 00Ditches Total

    Energy Program

    13-COORD-006 1,100,0001,100,000Government Center East 2

    1,100,0001,100,000Energy Program Total

    Federal Funds

    09-HWY-BRTWP 320,000320,000Township Bridge Replacement Program 1

    11-HWY-FTBEL 142,000142,000Trail - Ft. Belmont Trail 2

    12-HWY-29-43 1,200,0001,200,000CSAH 29 - Base & Wear 1

    1,662,0001,520,000 142,000Federal Funds Total

    Intergrated Fund

    08-HWY-SUR 20,00010,000 10,000Section Corner Reestablishment 2

    20,00010,000 10,000Intergrated Fund Total

    IS Equipment

    01-IS-002 210,00042,000 42,000 42,000 42,000 42,000IS Equipment Replacement 2

    07-IS-003 117,90025,300 39,500 25,200 27,900Copier Replacement 2

    327,90067,300 81,500 67,200 42,000 69,900IS Equipment Total

    Local (City) Contribution

    11-HWY-FTBEL 43,00043,000Trail - Ft. Belmont Trail 2

    43,00043,000Local (City) Contribution Total

    Local (Township)

    09-HWY-BRTWP 80,00020,000 40,000 20,000Township Bridge Replacement Program 1

    80,00020,000 40,000 20,000Local (Township) Total

    Property Tax

    05-SHRF-037 341,00065,000 66,600 68,200 69,800 71,400Squad Car Replacement Program 1

    08-HWY-BRCTY 150,000150,000County Bridge Replacement Program 1

    08-HWY--PROP 50,00050,000Purchase of Storage/Staging Sites 3

    Jackson County 2014 - 2018 Capital Improvement Program Page 17

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    21/59

    TotalSource Project# Priority 2014 2015 2016 2017 2018

    09-HWY-EFLT 91,00030,000 30,000 31,000Engineering & Maintenance Supervisor Pickup Fleet 2

    09-HWY-TNDMS 1,125,000215,000 220,000 225,000 230,000 235,000Tandem Fleet 1

    09-VSO-01 20,0005,000 5,000 5,000 5,000Veterans Van 2

    10-HWY-MFLT 220,00070,000 90,000 30,000 30,000Maintenance Pickup Fleet 2

    10-HWY-PIT 500,000500,000Gravel Pit Purchase 2

    11-HWY-FTBEL 27,00027,000Trail - Ft. Belmont Trail 2

    12-HWY-045 260,000260,000Motor Grader Fleet 1

    12-HWY-052 220,000220,000Unit 52 - Oshkosh w/Sno Go 2

    13-COORD-006 50,00050,000Government Center East 2

    13-HWY-061 190,000190,000Unit 61 - Loader 2

    14-P&E-010 30,00030,000Ford F-250 Pickup 2

    16-HWY-023 127,000127,000Unit 23 - Sign Truck 3

    16-HWY-064 32,00032,000Unit 64 - 873 Bobcat 3

    17-COORD-005 40,00040,000Courthouse Roof 2

    3,473,000720,000 1,441,600 625,200 374,800 311,400Property Tax Total

    Recorder's Equipment Fund

    07-IS-003 8,6008,600Copier Replacement 2

    8,6008,600Recorder's Equipment Fund Total

    Road and Bridge Reserves

    07-HWY-OVRLY 383,000383,000Overlay Program 2

    383,000383,000Road and Bridge Reserves Total

    State Aid

    05-HWY-SEAL 1,050,000190,000 200,000 210,000 220,000 230,000Sealcoat Program 2

    07-HWY-OVRLY 5,325,0001,575,000 1,188,000 1,250,000 1,312,000Overlay Program 2

    08-HWY-BRCTY 460,000130,000 110,000 220,000County Bridge Replacement Program 1

    12-HWY-29-43 600,000600,000CSAH 29 - Base & Wear 1

    13-HWY-29-01 3,090,0001,490,000 1,600,000CSAH 29 - Reconstruction 1

    14-HWY-23-21 400,000400,000CSAH 23 - Petersburg Intersections 1

    10,925,0002,495,000 2,200,000 3,218,000 1,470,000 1,542,000State Aid Total

    State Bridge Bonds

    08-HWY-BRCTY 470,000170,000 50,000 250,000County Bridge Replacement Program 1

    13-HWY-29-01 60,00060,000CSAH 29 - Reconstruction 1

    530,000170,000 110,000 250,000State Bridge Bonds Total

    Town Bridge

    09-HWY-BRTWP 810,000140,000 350,000 320,000Township Bridge Replacement Program 1

    810,000140,000 350,000 320,000Town Bridge Total

    Vehicle Replacement Fund

    06-JC-FLEET 134,50040,000 25,000 26,000 21,500 22,000Jackson County Passenger Vehicles 2

    134,50040,000 25,000 26,000 21,500 22,000Vehicle Replacement Fund Total

    Jackson County 2014 - 2018 Capital Improvement Program Page 18

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    22/59

    TotalSource Project# Priority 2014 2015 2016 2017 2018

    19,835,0005,182,300 4,843,100 5,947,400 1,916,900 1,945,300GRAND TOTAL

    Jackson County 2014 - 2018 Capital Improvement Program Page 19

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    23/59

    Capital Improvement Program

    Jackson County, Minnesota

    PROJECTS & FUNDING SOURCES BY DEPARTMENT

    2014 2018thru

    Total2014 2015 2016 2017 2018Department Project# Priority

    Coordinator/Information Sys

    1,100,0001,100,000Energy Program

    327,90067,300 81,500 67,200 42,000 69,900I S Equipment90,00050,000 40,000Property Tax

    8,6008,600Recorder' s Equipment Fund

    1,526,50067,300 81,500 1,217,200 90,600 69,900Coordinator /Information Sys Total

    01-IS-002 210,00042,000 42,000 42,000 42,000 42,000IS Equipment Replacement 2

    07-IS-003 126,50025,300 39,500 25,200 8,600 27,900Copier Replacement 2

    13-COORD-006 1,150,0001,150,000Government Center East 2

    17-COORD-005 40,00040,000Courthouse Roof 2

    1,526,50067,300 81,500 1,217,200 90,600 69,900Coordinator/Information Sys Total

    Highway Department

    05-HWY-SEAL 1,050,000190,000 200,000 210,000 220,000 230,000Sealcoat Program 2

    06-JC-FLEET 134,50040,000 25,000 26,000 21,500 22,000Jackson County Passenger Vehicles 2

    07-HWY-OVRLY 5,708,0001,575,000 383,000 1,188,000 1,250,000 1,312,000Overlay Program 2

    08-HWY-BRCTY 1,080,000450,000 160,000 470,000County Bridge Replacement Program 108-HWY--PROP 50,00050,000Purchase of Storage/Staging Sites 3

    08-HWY-SUR 20,00010,000 10,000Section Corner Reestablishment 2

    09-HWY-70-01 200,00050,000 50,000 50,000 50,000CR 70 - Regrade 3

    09-HWY-BRTWP 1,210,000480,000 390,000 340,000Township Bridge Replacement Program 1

    09-HWY-EFLT 91,00030,000 30,000 31,000Engineering & Maintenance Supervisor Pickup Fleet 2

    09-HWY-TNDMS 1,125,000215,000 220,000 225,000 230,000 235,000Tandem Fleet 1

    10-HWY-DFLT 338,000202,000 136,000Ditch Equipment 2

    10-HWY-MFLT 220,00070,000 90,000 30,000 30,000Maintenance Pickup Fleet 2

    10-HWY-PIT 500,000500,000Gravel Pit Purchase 2

    11-HWY-FTBEL 198,000198,000Trail - Ft. Belmont Trail 2

    12-HWY-045 260,000260,000Motor Grader Fleet 1

    12-HWY-052 220,000220,000Unit 52 - Oshkosh w/Sno Go 2

    12-HWY-29-43 1,800,0001,800,000CSAH 29 - Base & Wear 1

    13-HWY-061 190,000190,000Unit 61 - Loader 2

    13-HWY-29-01 3,150,0001,550,000 1,600,000CSAH 29 - Reconstruction 1

    14-HWY-23-21 400,000400,000CSAH 23 - Petersburg Intersections 1

    16-HWY-023 127,000127,000Unit 23 - Sign Truck 3

    Jackson County 2014 - 2018 Capital Improvement Program Page 20

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    24/59

    Total2014 2015 2016 2017 2018Department Project# Priority

    338,000202,000 136,000Ditches

    1,662,0001,520,000 142,000Federal Funds

    20,00010,000 10,000I ntergrated Fund

    43,00043,000Local (City) Contribution

    80,00020,000 40,000 20,000Local (Township)

    2,992,000655,000 1,370,000 472,000 260,000 235,000Property Tax

    383,000383,000Road and Bridge Reserves

    10,925,0002,495,000 2,200,000 3,218,000 1,470,000 1,542,000State Aid

    530,000170,000 110,000 250,000State Br idge Bonds

    810,000140,000 350,000 320,000Town Bridge

    134,50040,000 25,000 26,000 21,500 22,000Vehicl e Replacement Fund

    17,917,5005,050,000 4,690,000 4,627,000 1,751,500 1,799,000Hi ghway Department Total

    16-HWY-064 32,00032,000Unit 64 - 873 Bobcat 3

    18,103,5005,050,000 4,740,000 4,663,000 1,801,500 1,849,000Highway Department Total

    Planning & Environmental Svs

    30,00030,000Property Tax

    30,00030,000Planning & Environmental Svs Total

    14-P&E-010 30,00030,000Ford F-250 Pickup 2

    30,00030,000Planning & Environmental Svs Total

    Sheriff

    341,00065,000 66,600 68,200 69,800 71,400Property Tax

    341,00065,000 66,600 68,200 69,800 71,400Sheri ff Total

    05-SHRF-037 341,00065,000 66,600 68,200 69,800 71,400Squad Car Replacement Program 1

    341,00065,000 66,600 68,200 69,800 71,400Sheriff Total

    Veterans Services

    20,0005,000 5,000 5,000 5,000Property Tax

    20,0005,000 5,000 5,000 5,000Veterans Servi ces Total

    09-VSO-01 27,00027,000Veterans Van 2

    27,00027,000Veterans Services Total

    Jackson County 2014 - 2018 Capital Improvement Program Page 21

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    25/59

    Total2014 2015 2016 2017 2018Department Project# Priority

    20,028,0005,182,300 4,915,100 5,978,400 1,961,900 1,990,300Grand Total

    Jackson County 2014 - 2018 Capital Improvement Program Page 22

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    26/59

    Capital Improvement Program

    Jackson County, Minnesota

    PROJECTS & FUNDING SOURCES BY DEPARTMENT

    2014 2018thru

    Total2014 2015 2016 2017 2018Department Project# Priority

    Coordinator/Information Sys

    01-IS-002 210,00042,000 42,000 42,000 42,000 42,000IS Equipment Replacement 2

    IS Equipment 42,000 42,000 42,000 42,000 42,000 210,000

    07-IS-003 126,50025,300 39,500 25,200 8,600 27,900Copier Replacement 2

    IS Equipment 25,300 39,500 25,200 27,900 117,900

    Recorder's Equipment Fund 8,600 8,600

    13-COORD-006 1,150,0001,150,000Government Center East 2

    Energy Program 1,100,000 1,100,000

    Property Tax 50,000 50,000

    17-COORD-005 40,00040,000Courthouse Roof 2

    Property Tax 40,000 40,000

    1,526,50067,300 81,500 1,217,200 90,600 69,900Coordinator/Information Sys Total

    Highway Department

    05-HWY-SEAL 1,050,000190,000 200,000 210,000 220,000 230,000Sealcoat Program 2

    State Aid 190,000 200,000 210,000 220,000 230,000 1,050,000

    06-JC-FLEET 134,50040,000 25,000 26,000 21,500 22,000Jackson County Passenger Vehicles 2

    Vehicle Replacement Fund 40,000 25,000 26,000 21,500 22,000 134,500

    07-HWY-OVRLY 5,708,0001,575,000 383,000 1,188,000 1,250,000 1,312,000Overlay Program 2

    Road and Bridge Reserves 383,000 383,000

    State Aid 1,575,000 1,188,000 1,250,000 1,312,000 5,325,000

    08-HWY-BRCTY 1,080,000450,000 160,000 470,000County Bridge Replacement Program 1

    Property Tax 150,000 150,000

    State Aid 130,000 110,000 220,000 460,000

    State Bridge Bonds 170,000 50,000 250,000 470,000

    08-HWY--PROP 50,00050,000Purchase of Storage/Staging Sites 3

    Property Tax 50,000 50,000

    08-HWY-SUR 20,00010,000 10,000Section Corner Reestablishment 2

    Intergrated Fund 10,000 10,000 20,000

    09-HWY-70-01 200,00050,000 50,000 50,000 50,000CR 70 - Regrade 3

    09-HWY-BRTWP 1,210,000480,000 390,000 340,000Township Bridge Replacement Program 1

    Federal Funds 320,000 320,000

    Local (Township) 20,000 40,000 20,000 80,000Town Bridge 140,000 350,000 320,000 810,000

    09-HWY-EFLT 91,00030,000 30,000 31,000Engineering & Maintenance Supervisor Pickup Fleet 2

    Property Tax 30,000 30,000 31,000 91,000

    09-HWY-TNDMS 1,125,000215,000 220,000 225,000 230,000 235,000Tandem Fleet 1

    Property Tax 215,000 220,000 225,000 230,000 235,000 1,125,000

    10-HWY-DFLT 338,000202,000 136,000Ditch Equipment 2

    Ditches 202,000 136,000 338,000

    Jackson County 2014 - 2018 Capital Improvement Program Page 23

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    27/59

    Total2014 2015 2016 2017 2018Department Project# Priority

    10-HWY-MFLT 220,00070,000 90,000 30,000 30,000Maintenance Pickup Fleet 2

    Property Tax 70,000 90,000 30,000 30,000 220,000

    10-HWY-PIT 500,000500,000Gravel Pit Purchase 2

    Property Tax 500,000 500,000

    11-HWY-FTBEL 198,000198,000Trail - Ft. Belmont Trail 2

    Federal Funds 142,000 142,000

    Local (City) Contribution 43,000 43,000

    Property Tax 27,000 27,000

    12-HWY-045 260,000260,000Motor Grader Fleet 1

    Property Tax 260,000 260,000

    12-HWY-052 220,000220,000Unit 52 - Oshkosh w/Sno Go 2

    Property Tax 220,000 220,000

    12-HWY-29-43 1,800,0001,800,000CSAH 29 - Base & Wear 1

    Federal Funds 1,200,000 1,200,000

    State Aid 600,000 600,000

    13-HWY-061 190,000190,000Unit 61 - Loader 2

    Property Tax 190,000 190,000

    13-HWY-29-01 3,150,0001,550,000 1,600,000CSAH 29 - Reconstruction 1

    State Aid 1,490,000 1,600,000 3,090,000

    State Bridge Bonds 60,000 60,000

    14-HWY-23-21 400,000400,000CSAH 23 - Petersburg Intersections 1

    State Aid 400,000 400,000

    16-HWY-023 127,000127,000Unit 23 - Sign Truck 3

    Property Tax 127,000 127,000

    16-HWY-064 32,00032,000Unit 64 - 873 Bobcat 3

    Property Tax 32,000 32,000

    18,103,5005,050,000 4,740,000 4,663,000 1,801,500 1,849,000Highway Department Total

    Planning & Environmental Svs

    14-P&E-010 30,00030,000Ford F-250 Pickup 2

    Property Tax 30,000 30,000

    30,00030,000Planning & Environmental Svs Total

    Sheriff

    05-SHRF-037 341,00065,000 66,600 68,200 69,800 71,400Squad Car Replacement Program 1

    Property Tax 65,000 66,600 68,200 69,800 71,400 341,000

    341,00065,000 66,600 68,200 69,800 71,400Sheriff Total

    Veterans Services

    09-VSO-01 27,00027,000Veterans Van 2

    Property Tax 5,000 5,000 5,000 5,000 20,000

    27,00027,000Veterans Services Total

    GRAND TOTAL 20,028,0005,182,300 4,915,100 5,978,400 1,961,900 1,990,300

    Jackson County 2014 - 2018 Capital Improvement Program Page 24

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    28/59

    Jackson County2014 - 2018 Capital Improvement Program

    Property Tax Detail

    2014 2015 2016 2017 2018Coordinator/Information Systems $67,300 $81,500 $117,200 $82,000 $69,900

    Highway $655,000 $1,370,000 $472,000 $260,000 $235,000

    Planning & Env. Services $0 $0 $30,000 $0 $0

    Sheriff $65,000 $66,600 $68,200 $69,800 $71,400

    Veterans Services $0 $5,000 $5,000 $5,000 $5,000

    Total $787,300 $1,523,100 $692,400 $416,800 $381,300

    $0

    $200,000

    $400,000

    $600,000

    $800,000

    $1,000,000

    $1,200,000

    $1,400,000

    $1,600,000

    2014 2015 2016 2017 2018

    Property

    Tax

    Year

    Tax Levy for CIP Projects

    Jackson County 2014 - 2018 Capital Improvement Program Page 25

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    29/59

    Wind Production Tax Revenue

    $350,000

    $609,193

    $185,248

    2014

    Tax Relief

    Bond Payments

    Available for Capital

    Improvements

    $350,000

    $602,613

    $191,828

    2015

    Jackson County 2014 - 2018 Capital Improvement Program

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    30/59

    Capital Improvement Program

    Jackson County, Minnesota Contact IS Supervisor

    2014 2018thruDepartment Coordinator/Information Sys

    Description

    3 - 5 year replacement cycle of personal computers and servers.

    Project # 01-IS-002

    Priority 2 Necessary

    Justification

    1) Computer software and operating systems are continually being revised to add new functionality and features. Each revision of the software

    requires more resources or processing power from the computers that run them.

    2) The three to five year rotation will allow the County to continue to utilize new technology to better serve the citizens of Jackson County.

    3) Regular replacement will help keep repair and maintenance to a minimum which reduces user downtime.

    Budget Impact/Other

    Useful Life 3 - 5 YearsProject Name IS Equipment Replacement Category Computer/Commun Equip

    Type Equipment

    Ongoing Project yes

    Dept. Priority Necessary

    Total2014 2015 2016 2017 2018Expenditures

    210,00042,000 42,000 42,000 42,000 42,000Equip/Vehicles/Furnishings

    42,000 42,000 42,000 42,000 42,000 210,000Total

    Total2014 2015 2016 2017 2018Funding Sources

    210,00042,000 42,000 42,000 42,000 42,000IS Equipment

    42,000 42,000 42,000 42,000 42,000 210,000Total

    Jackson County 2014 - 2018 Capital Improvement Program Page 27

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    31/59

    Capital Improvement Program

    Jackson County, Minnesota Contact IS Supervisor

    2014 2018thruDepartment Coordinator/Information Sys

    Description

    5 year replacement cycle for county multifunction (copy) machines.

    Project # 07-IS-003

    Priority 2 Necessary

    Justification

    1) Machines traditionally referred to as copiers have evolved into multifunction machines that in addtion to copying also print, scan, fax, and store

    documents. As such, these machines are relied on heavily for all of these functions in all county departments.

    2) A five year replacement cycle will allow the County to continue to utilize new technology to better serve the citizens of Jackson County.

    3) Regular replacement will help keep repair and maintenance to a minimum which will reduce machine downtime.

    Budget Impact/Other

    Useful Life 5 yearsProject Name Copier Replacement Category Computer/Commun Equip

    Type Equipment

    Ongoing Project yes

    Dept. Priority Necessary

    Total2014 2015 2016 2017 2018Expenditures

    126,50025,300 39,500 25,200 8,600 27,900Equip/Vehicles/Furnishings

    25,300 39,500 25,200 8,600 27,900 126,500Total

    Total2014 2015 2016 2017 2018Funding Sources

    117,90025,300 39,500 25,200 27,900IS Equipment

    8,6008,600Recorder's Equipment Fund

    25,300 39,500 25,200 8,600 27,900 126,500Total

    Jackson County 2014 - 2018 Capital Improvement Program Page 28

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    32/59

    Capital Improvement Program

    Jackson County, Minnesota Contact County Coordinator

    2014 2018thruDepartment Coordinator/Information Sys

    Description

    The Building Committee for the Government Center East (1962) Building met and identified improvements to the building that should be made in

    order to continue to utilize this building for the next 15 to 25 years, or until funds are available to complete an addition to the Government Center

    West building. Two of the projects, new roof and window replacements, were authorized in 2012, to be funded through current wind tax revenues.

    Minor remodeling and HVAC upgrades would be completed as funding becomes available.

    Project # 13-COORD-006

    Priority 2 Necessary

    Justification

    With new wind tax revenues earmarked for the new Highway Maintenance Facility, it will be several years before the County is able to set aside

    funds to complete the second and possible third phase of the Government Center Project, which included at least one addition to the new

    Government Center West building to accommodate the departments now located in the Government Center East building. Therefore, some basic

    improvements must be made to the existing facility to make it "livable" for the next 15-20 years. One of two energy programs - PBEEP or GESP -

    may be an alternative to fund the HVAC upgrade, but further assessment will be necessary.

    Budget Impact/Other

    Useful Life 20 yearsProject Name Government Center East Category Buildings

    Type Improvement

    Ongoing Project

    Dept. Priority Necessary

    Total2014 2015 2016 2017 2018Expenditures

    230,000230,000Professional Services

    920,000920,000Construction/Maintenance

    1,150,000 1,150,000Total

    Total2014 2015 2016 2017 2018Funding Sources

    1,100,0001,100,000Energy Program

    50,00050,000Property Tax

    1,150,000 1,150,000

    Total

    Jackson County 2014 - 2018 Capital Improvement Program Page 29

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    33/59

    Capital Improvement Program

    Jackson County, Minnesota Contact County Coordinator

    2014 2018thruDepartment Coordinator/Information Sys

    Description

    Roof was last replaced in 1992 and has a useful life around 25 years.

    Project # 17-COORD-005

    Priority 2 Necessary

    Justification

    This is a normal building lifecycle maintenance item. Failure to replace the roof will result in leaks that could create other damage to the building

    and contents. It is especially important that the Courthouse roof be maintained to avoid leaks which could damage the murals in the dome and

    Courtroom.

    Budget Impact/Other

    Useful Life 25 yearsProject Name Courthouse Roof Category Buildings

    Type Maintenance

    Ongoing Project

    Dept. Priority Necessary

    Total2014 2015 2016 2017 2018Expenditures

    40,00040,000Construction/Maintenance

    40,000 40,000Total

    Total2014 2015 2016 2017 2018Funding Sources

    40,00040,000Property Tax

    40,000 40,000Total

    Jackson County 2014 - 2018 Capital Improvement Program Page 30

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    34/59

    Capital Improvement Program

    Jackson County, Minnesota Contact Highway Engineer

    2014 2018thruDepartment Highway Department

    Description

    The Highway Department's Goal is to Sealcoat approximately 20 - 30 miles of roadway per year

    Sealcoating involves spraying oil (approximately 0.2 gallons/SY) and then applying a layer of pea-rock or rock chips over the oil. The rock is then

    imbedded in the oil with the use of rollers.

    Sometime within the same construction season, the Highway Department applies a Fog Seal to the seal coated surface. This additional seal locks

    down the rock even greater.

    Project # 05-HWY-SEAL

    Priority 2 Necessary

    Justification

    Studies have shown that sealcoating roads help the Pavement Quality Index (PQI) and extends the live of roadways. Sealcoating roads keeps

    moisture out of the pavement and protects the original bituminous material from premature aging caused by Ultra-Violet light.

    Budget Impact/Other

    Useful Life 10 yearsProject Name Sealcoat Program Category Highway: Road Construction

    Type Maintenance

    Ongoing Project yes

    Dept. Priority Necessary

    Total2014 2015 2016 2017 2018Expenditures

    1,050,000190,000 200,000 210,000 220,000 230,000Construction/Maintenance

    190,000 200,000 210,000 220,000 230,000 1,050,000Total

    Total2014 2015 2016 2017 2018Funding Sources

    1,050,000190,000 200,000 210,000 220,000 230,000State Aid

    190,000 200,000 210,000 220,000 230,000 1,050,000Total

    Jackson County 2014 - 2018 Capital Improvement Program Page 31

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    35/59

    Capital Improvement Program

    Jackson County, Minnesota Contact Highway Engineer

    2014 2018thruDepartment Highway Department

    Description

    Passenger Vehicle Fleet

    Replacement Schedule

    2009 - Chevy Impala #930-738

    2010 - Dodge Caravan #587-BWN

    2011 - Blue Impala #679-GBL (No vans on State Contract)

    2012 - Planning & Zoning Van became part of fleet - $23,118 Dodge Grand Caravan

    2013 - Replace '09 Silver Impala

    2014 - Replace '11 Blue Impala

    2014 - Replace '09 Courthouse Impala

    2015 - Replace '10 Dodge Caravan

    2016 - Replace P&Z Van

    2017 - Replace '13 Car

    2018 - Replace '14 Car

    Project # 06-JC-FLEET

    Priority 2 Necessary

    Justification

    In order to save Jackson County money the JCHD manages the passenger fleet vehicles instead of leasing throught the State of Minnesota.

    Budget Impact/Other

    Useful Life 3 - 5 YearsProject Name Jackson County Passenger Vehicles Category Vehicles:Auto/Trucks

    Type Equipment

    Ongoing Project yes

    Dept. Priority Necessary

    Total2014 2015 2016 2017 2018Expenditures

    134,50040,000 25,000 26,000 21,500 22,000Equip/Vehicles/Furnishings

    40,000 25,000 26,000 21,500 22,000 134,500Total

    Total2014 2015 2016 2017 2018Funding Sources

    134,50040,000 25,000 26,000 21,500 22,000Vehicle Replacement Fund

    40,000 25,000 26,000 21,500 22,000 134,500Total

    Jackson County 2014 - 2018 Capital Improvement Program Page 32

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    36/59

    Capital Improvement Program

    Jackson County, Minnesota Contact Highway Engineer

    2014 2018thruDepartment Highway Department

    Description

    2012 - CSAH 16 - from CSAH 19 to TH 71 (3 miles)

    CSAH 19 - from CSAH 14 to CSAH 16 (2 miles)

    CSAH 30 - from TH 71 to CSAH 29 (5 miles)

    CSAH 16 - from TH 71 to CSAH 29 (6 miles)

    2013 - CSAH 13 - from TH 60 to Cottonwood Co. Line (1.8 miles)

    CSAH 20 - from TH 60 to CSAH 7 (2.25 miles)

    CSAH 22 - from TH 71 to Martin County Line (7 miles)

    2014 - CSAH 3 - from CSAH 4 to CSAH 32 (5 miles)

    CSAH 4 - from S. Jct CSAH 4 to TH 86 (8 miles)

    CSAH 5 - from Iowa State Line to CSAH 4 ( 4.5 miles)

    2015 - CSAH 29 - from I-90 to CSAH 22 (4.5 miles)

    2016 - Project Scoping in progress

    2017 - Projects not yet Scoped2018 - Projects not yet Scoped

    Project # 07-HWY-OVRLY

    Priority 2 Necessary

    Justification

    Overlaying roads is part of the lifecycle of a road. The Highway Department's Goal is to Overlay approximately 10 - 15 miles of roadway per

    year. A typical overlay project involves placing an additional 1 1/2" of bituminous and corresponding shouldering.

    Budget Impact/Other

    Useful Life 15 yearsProject Name Overlay Program Category Highway: Road Construction

    Type Maintenance

    Ongoing Project yes

    Dept. Priority Necessary

    Total2014 2015 2016 2017 2018Expenditures

    5,708,0001,575,000 383,000 1,188,000 1,250,000 1,312,000Construction/Maintenance

    1,575,000 383,000 1,188,000 1,250,000 1,312,000 5,708,000Total

    Total2014 2015 2016 2017 2018Funding Sources

    383,000383,000Road and Bridge Reserves

    5,325,0001,575,000 1,188,000 1,250,000 1,312,000State Aid

    1,575,000 383,000 1,188,000 1,250,000 1,312,000 5,708,000Total

    Jackson County 2014 - 2018 Capital Improvement Program Page 33

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    37/59

    Capital Improvement Program

    Jackson County, Minnesota Contact Highway Engineer

    2014 2018thruDepartment Highway Department

    Description

    The goal of the highway department is to replace at least four bridges per year. On average, two of these bridges will be on County owned

    bridges.

    2013 - BR 7173 - CSAH 4 (1.7 miles west of TH 86)

    2014 - BR 776 - CR 83 - (0.75 miles north of CSAH 16)

    - BR 32504 - CSAH 5 - (1.2 miles north of IOWA line)

    2015 - BR 88992 - CSAH 9 (4 miles north of CSAH 4)

    2016 - BR 6444 - CSAH 24 - (1.5 miles west of CR 82)

    2017 - Dependent upon bridge safety inspections.

    2018 - Dependent upon bridge safety inspections.

    Project # 08-HWY-BRCTY

    Priority 1 Urgent

    Justification

    The Highway Department conducts annual bridge safety inspections. From these inspections, bridges are programmed for replacement. All of the

    bridges are structurally deficit. Repairs have been made on some of the bridges to "buy" time until funding can be secured. State Bridge Bondingis only available in even numbered years.

    Budget Impact/Other

    Useful Life 50 yearsProject Name County Bridge Replacement Program Category Highway: Bridge Construction

    Type Improvement

    Ongoing Project yes

    Dept. Priority Urgent

    Total2014 2015 2016 2017 2018Expenditures

    140,00050,000 20,000 70,000Professional Services

    940,000400,000 140,000 400,000Construction/Maintenance

    450,000 160,000 470,000 1,080,000Total

    Total2014 2015 2016 2017 2018Funding Sources

    150,000150,000Property Tax460,000130,000 110,000 220,000State Aid

    470,000170,000 50,000 250,000State Bridge Bonds

    450,000 160,000 470,000 1,080,000Total

    Jackson County 2014 - 2018 Capital Improvement Program Page 34

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    38/59

    Capital Improvement Program

    Jackson County, Minnesota Contact Highway Engineer

    2014 2018thruDepartment Highway Department

    Description

    Purchase of land for the storage of material needed for roadway maintenance.

    2013 - Pursuing Kimball Twp location (Necessary)

    Approximately 7 acres

    2014 - Pursuing Sioux Valley Twp location (Desirable)

    Approximatley 5 acres

    Project # 08-HWY--PROP

    Priority 3 Desireable

    Justification

    In 2006 and 2007 the Highway Department has spent over $30,000 for the staging site for the CSAH 34 project. The Highway Department has

    experienced similar costs on previous projects.

    The JCHD will have decreased maintenance costs and increased efficiency if storage sites are located through-out the county.

    Budget Impact/Other

    Useful Life 40 yearsProject Name Purchase of Storage/Staging Sites Category Highway: Road Construction

    Type Improvement

    Ongoing Project

    Dept. Priority Desirable

    Total2014 2015 2016 2017 2018Expenditures

    50,00050,000Property/Land Acquisition

    50,000 50,000Total

    Prior

    50,000

    Total

    Total2014 2015 2016 2017 2018Funding Sources

    50,00050,000Property Tax

    50,000 50,000Total

    Prior

    50,000

    Total

    Jackson County 2014 - 2018 Capital Improvement Program Page 35

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    39/59

    Capital Improvement Program

    Jackson County, Minnesota Contact Highway Engineer

    2014 2018thruDepartment Highway Department

    Description

    See attached.

    Project # 08-HWY-SHOP

    Priority 1 Urgent

    Justification

    Block and motar crumbling, buildings in need of extensive repair. Floor drains outlet to nearby stream - Not EPA approved. No drain field for

    septic system. Non-insulated, low ceiling height in parts and storage tunnels. Main building not set up for efficient maintenance shop. No

    exhaust system for air quality - Not EPA approved. No approved welding bay. Many expensive pieces of equipment are stored outside. Building

    electrical service is undersized. Low efficiency heating system. Inadequate space for office area, parts storage, equipment, tool storage. Overhead

    hoist will not pass inspections. Overhead oil rack not structurally rated. Non-efficient vehicle servicing. Plows have to be left outside andtherefore have to be hooked up every snow plowing morning. This results in a loss of 20 minutes per truck per snowplowing morning.

    2009 - New Emergency Standby Generator

    Would be sized to meet future requirements

    Budget Impact/Other

    Bond payments would be made from wind production tax revenues, and from lease payments or cost share from the City of Jackson for their share

    of the Jackson facility.

    In 2017, existing CIP/Street Improvement bonds will be paid off. Those payments could then be used towards the CIP Bonds issued for this

    project.

    THE FOLLOWING BUDGET IMPACT IS BASED ON CURRENT RATES AND ESTIMATES, AND IS FOR ILLUSTRATIVE PURPOSES

    ONLY.

    Useful Life 40 yearsProject Name County Maintenance Facilities: Jackson & Lakefield Category Buildings

    Type Improvement

    Ongoing Project

    Dept. Priority Urgent

    Prior

    14,549,195

    Total

    Prior

    14,549,195

    Total

    TotalBudget Items2014 2015 2016 2017 2018

    2,610,000870,000 870,000 870,000CIP Payments

    -810,000-270,000 -270,000 -270,000Lease Income

    600,000 600,000 600,000 1,800,000Total

    Jackson County 2014 - 2018 Capital Improvement Program Page 36

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    40/59

    Capital Improvement Program

    Jackson County, Minnesota Contact Highway Engineer

    2014 2018thruDepartment Highway Department

    Description

    Reestablishment of Section corners with reference to GPS coordinates.

    Project # 08-HWY-SUR

    Priority 2 Necessary

    Justification

    Original section corners were established pre 1900. Many no longer exist. Cost to the individual land owner would be decreased if accurate GPS

    referenced section corners would be developed. A section corner grid would improve the accuracy of the GIS basemap.

    Budget Impact/Other

    Useful Life 50 yearsProject Name Section Corner Reestablishment Category Highway: Road Construction

    Type Maintenance

    Ongoing Project

    Dept. Priority Necessary

    Total2014 2015 2016 2017 2018Expenditures

    20,00010,000 10,000Professional Services

    10,000 10,000 20,000Total

    Prior

    80,000

    Total

    Total2014 2015 2016 2017 2018Funding Sources

    20,00010,000 10,000Intergrated Fund

    10,000 10,000 20,000Total

    Prior

    100,000

    Total

    Jackson County 2014 - 2018 Capital Improvement Program Page 37

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    41/59

    Capital Improvement Program

    Jackson County, Minnesota Contact Highway Engineer

    2014 2018thruDepartment Highway Department

    Description

    C.P. 32-670-01

    CR 70 From TH 86 to CSAH 17 (4 miles)

    Roadway Regrade

    Project # 09-HWY-70-01

    Priority 3 Desireable

    Justification

    The purpose of this project is to raise the grade of the roadway and eliminate inherent snow drifting problem areas.

    Funding was included in 2005 budget. Funds have been placed in reserve. Project has been delayed due to CSAH 34 (06-HWY-34-15) project

    Budget Impact/Other

    Useful Life 25 yearsProject Name CR 70 - Regrade Category Highway: Road Construction

    Type Improvement

    Ongoing Project

    Dept. Priority Desirable

    Total2014 2015 2016 2017 2018Expenditures

    200,00050,000 50,000 50,000 50,000Construction/Maintenance

    50,000 50,000 50,000 50,000 200,000Total

    Prior

    200,000

    Total

    Jackson County 2014 - 2018 Capital Improvement Program Page 38

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    42/59

    Capital Improvement Program

    Jackson County, Minnesota Contact Highway Engineer

    2014 2018thruDepartment Highway Department

    Description

    The goal of the highway department is to replace at least four bridges per year. On average, two of these bridges will be Township owned bridges.

    2013 - Rost - L9312 - SAP 32-599-97 - $200,000

    - Enterprise - L5198 - SAP 32-599-96 - $350,000

    - Round Lake - L5231 - SAP 32-599-80 - $120,000

    2014 - Alba - 2628 - SP 32-599-89 - $350,000

    2015 - Petersburg - 1706 - SAP 32-599-98 - $150,000

    - Kimbal - 2809 - SAP 32-599-95 - $150,000

    2016 - Sioux Valley - L9542 - SAP 32-599-99 - $150,000

    2017 - Dependent upon bridge safety inspections.

    2018 - Dependent upon bridge safety inspections.

    Project # 09-HWY-BRTWP

    Priority 1 Urgent

    Justification

    The Highway Department conducts annual bridge safety inspections. From these inspections, bridges are programmed for replacement.

    Budget Impact/Other

    Useful Life 50 yearsProject Name Township Bridge Replacement Program Category Highway: Bridge Construction

    Type Improvement

    Ongoing Project yes

    Dept. Priority Urgent

    Total2014 2015 2016 2017 2018Expenditures

    180,00080,000 60,000 40,000Professional Services

    1,030,000400,000 330,000 300,000Construction/Maintenance

    480,000 390,000 340,000 1,210,000Total

    Total2014 2015 2016 2017 2018Funding Sources320,000320,000Federal Funds

    80,00020,000 40,000 20,000Local (Township)

    810,000140,000 350,000 320,000Town Bridge

    480,000 390,000 340,000 1,210,000Total

    Jackson County 2014 - 2018 Capital Improvement Program Page 39

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    43/59

    Capital Improvement Program

    Jackson County, Minnesota Contact Highway Engineer

    2014 2018thruDepartment Highway Department

    Description

    Engineering & Maintenance Supervisor Pickup Fleet

    Replacement Schedule (Based upon 10 year life)

    2011 - Unit 12 - 2000 Chevrolet 2500 Reg Cab (Unit 5 to Maintenance)

    2012 - Unit 9 - 2001 Ford F350 4x4

    2013 - Unit 1 - 2002 Chevrolet 2500 (+3 year)

    2014 - Unit 7 - 2001 Ford Explorer (+4 year)

    2015 - Unit 8 - 2006 Chevrolet Crew Cab

    2016 - Unit 5 - 2008 Chevrolet Crew Cab

    Project # 09-HWY-EFLT

    Priority 2 Necessary

    Justification

    The JCHD is changing the approach on how the Maintenance Supervisor and Engineering Department vehicles are replaced.

    In the past, the Maintenance Supervisor's vehilce was replaced every 3 to 4 years due to high mileage. Whereas, the Engineering Department

    vehicles were replaced approximately every 12 years due to a slow accumulation of miles.JCHD is rotating the Maintenance Supervisor's vehicle into the Engineering Department once it reaches 60,000 miles (estimated to be every 2 to 3

    years). The Engineering Department will then run the vehicle for approximately 7 to 8 years more.

    Budget Impact/Other

    Useful Life 10 yearsProject Name Engineering & Maintenance Supervisor Pickup Fleet Category Vehicles:Auto/Trucks

    Type Equipment

    Ongoing Project yes

    Dept. Priority Necessary

    Total2014 2015 2016 2017 2018Expenditures

    91,00030,000 30,000 31,000Equip/Vehicles/Furnishings

    30,000 30,000 31,000 91,000Total

    Total2014 2015 2016 2017 2018Funding Sources

    91,00030,000 30,000 31,000Property Tax

    30,000 30,000 31,000 91,000Total

    Jackson County 2014 - 2018 Capital Improvement Program Page 40

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    44/59

    Capital Improvement Program

    Jackson County, Minnesota Contact Highway Engineer

    2014 2018thruDepartment Highway Department

    Description

    Snow Plow Fleet (Tandem Axle & Osh Kosh)

    Replacement Schedule (Based upon 10 year life)

    2010 - Unit 32 - 2000 Sterling Tandem - New transmission 2010

    2011 - Unit 30 - 2000 Sterling Tandem

    2012 - Unit 21- 1995 Ford Single Axle - Replace with Tandem

    2013 - Unit 27 - 2001 Sterling Tandem

    2014 - Unit 55 - 1996 OshKosh Single Axle - Replace with Tandem

    2015 - Unit 26 - 2003 Tandem

    2016 - Unit 20 - 2005 Tandem

    2017 - Unit 24 - 2006 Tandem

    2018 - Unit 25 - 2007 Tandem

    2019 - Unit 33 - 2007 Tandem

    2020 - Unit 34 - 2009 Tandem

    Project # 09-HWY-TNDMS

    Priority 1 Urgent

    Justification

    Scheduled Replacement

    Backbone of Highway Department used daily.

    Units have 300,000+ miles. A main goal is to rotate the equipment before costs of repairs are nonrecoverable.

    Budget Impact/Other

    Useful Life 10 yearsProject Name Tandem Fleet Category Vehicles:Highway Maintenanc

    Type Equipment

    Ongoing Project yes

    Dept. Priority Urgent

    Total2014 2015 2016 2017 2018Expenditures

    1,125,000215,000 220,000 225,000 230,000 235,000Equip/Vehicles/Furnishings

    215,000 220,000 225,000 230,000 235,000 1,125,000Total

    Total2014 2015 2016 2017 2018Funding Sources

    1,125,000215,000 220,000 225,000 230,000 235,000Property Tax

    215,000 220,000 225,000 230,000 235,000 1,125,000Total

    Jackson County 2014 - 2018 Capital Improvement Program Page 41

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    45/59

    Capital Improvement Program

    Jackson County, Minnesota Contact Highway Engineer

    2014 2018thruDepartment Highway Department

    Description

    Ditch Department Pickup Fleet

    Replacement Schedule (Based upon 10 year life)

    2011 - Unit 17 -1998 Ford F350 (+3 years)

    2012 - Unit 18 - 2008 Ford F350 (Totaled in Accident)

    2013 - Unit 16 - 2002 Chevrolet 3500

    2015 - Unit 63 - 1994 Caterpillar 320 Excavator

    2016 - Unit 79 - 2000 Caterpillar Loader/Backhoe

    Project # 10-HWY-DFLT

    Priority 2 Necessary

    Justification

    Equipment used daily by the ditch crew.

    Budget Impact/Other

    Useful Life 10 yearsProject Name Ditch Equipment Category Vehicles:Auto/Trucks

    Type Equipment

    Ongoing Project yes

    Dept. Priority Necessary

    Total2014 2015 2016 2017 2018Expenditures

    338,000202,000 136,000Equip/Vehicles/Furnishings

    202,000 136,000 338,000Total

    Total2014 2015 2016 2017 2018Funding Sources

    338,000202,000 136,000Ditches

    202,000 136,000 338,000Total

    Jackson County 2014 - 2018 Capital Improvement Program Page 42

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    46/59

    Capital Improvement Program

    Jackson County, Minnesota Contact Highway Engineer

    2014 2018thruDepartment Highway Department

    Description

    Maintenance Pickup Fleet

    Replacement Schedule (Based upon 10 year life)

    2013 - Unit 2 - 2001 Dodge - Mechanics' Truck

    2014 - Unit 11 - 2007 Dodge 3500 - Road Groom PU (replace at 5 yr due to extreme use)

    2014 - Unit 4 - 2002 Chevrolet 3/4 Ton Crew Cab (+1 year)

    2015 - Unit 5 - 2009 Chevrolet 1/2 Ton Crew Cab (old Maint. Super PU)

    2015 - Unit 19 - 2001 Ford 350 Crew Cab

    2015 - Unit 10 - 2005 Chevrolet 3/4 Ton Crew Cab

    2016 - Unit 15 - 2005 Chevrolet 3/4 Ton Crew Cab

    2017 - Unit 6 - 2006 Chevrolet 3/4 Ton Crew Cab

    Project # 10-HWY-MFLT

    Priority 2 Necessary

    Justification

    Budget Impact/Other

    Useful Life 10 yearsProject Name Maintenance Pickup Fleet Category Vehicles:Auto/Trucks

    Type Equipment

    Ongoing Project yes

    Dept. Priority Necessary

    Total2014 2015 2016 2017 2018Expenditures

    220,00070,000 90,000 30,000 30,000Equip/Vehicles/Furnishings

    70,000 90,000 30,000 30,000 220,000Total

    Total2014 2015 2016 2017 2018Funding Sources

    220,00070,000 90,000 30,000 30,000Property Tax70,000 90,000 30,000 30,000 220,000Total

    Jackson County 2014 - 2018 Capital Improvement Program Page 43

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    47/59

    Capital Improvement Program

    Jackson County, Minnesota Contact Highway Engineer

    2014 2018thruDepartment Highway Department

    Description

    Gravel Pit purchase in/with Cottonwood County

    Land exchange with the Department of Natural Resourses to acquire approximately 60+ acres of existing DNR land suspected to have large

    quantity of gravel.

    Project # 10-HWY-PIT

    Priority 2 Necessary

    Justification

    The Highway department currently purchases gravel from various individuals that own gravel pits in the SW portion of Cottonwoood County.

    The Highway Department will continue to have gravel needs in the NW portion of the county for years to come. A gravel pit purchase would "lock

    up" a long term gravel supply for Jackson and Cottonwood Counties for approximately 20 to 30 years.

    A preliminary cost savings of $825,000 is projected.

    Budget Impact/Other

    Useful Life 25 yearsProject Name Gravel Pit Purchase Category Land

    Type Maintenance

    Ongoing Project

    Dept. Priority Necessary

    Total2014 2015 2016 2017 2018Expenditures

    500,000500,000Property/Land Acquisition

    500,000 500,000Total

    Total2014 2015 2016 2017 2018Funding Sources

    500,000500,000Property Tax

    500,000 500,000Total

    Jackson County 2014 - 2018 Capital Improvement Program Page 44

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    48/59

    Capital Improvement Program

    Jackson County, Minnesota Contact Highway Engineer

    2014 2018thruDepartment Highway Department

    Description

    S.P. 32-090-03

    The Fort Belmont Trail (Phase III City of Jackson Trails) will include construction of approximately 1.5 miles of trail. This trail will connect

    with the existing Des Moines River Trail, completed in the summer of 2005, as well as Riverside Elementary with Jacksons Historical Fort

    Belmont attraction. The trail will run adjacent to State Highway 71 from the Des Moines River Trail and north to Fort Belmont using the outer

    edge of existing state highway right-of-way. Fort Belmont will serve as an additional trail head to the City of Jackson trail system. The trail will

    also traverse past the city golf course and hotel making it exceptionally visible to those traveling through Jackson. A future phase will include a

    connection from the Fort Belmont Trail to Kilen Woods State Park.

    Project # 11-HWY-FTBEL

    Priority 2 Necessary

    Justification

    If Trail is in-place, the Department of Transportation will design the bridge on Trunk Highway 71 over the Des Moines river to accommodate a 10'

    wide trail ($120,000).

    Budget Impact/Other

    Useful Life 25 yearsProject Name Trail - Ft. Belmont Trail Category Highway: Trail Construction

    Type Improvement

    Ongoing Project

    Dept. Priority Necessary

    Total2014 2015 2016 2017 2018Expenditures

    13,00013,000Professional Services

    8,0008,000Property/Land Acquisition

    177,000177,000Construction/Maintenance

    198,000 198,000Total

    Prior

    14,000

    Total

    Total2014 2015 2016 2017 2018Funding Sources

    142,000142,000Federal Funds

    43,00043,000Local (City) Contribution

    27,00027,000Property Tax

    212,000 212,000Total

    Jackson County 2014 - 2018 Capital Improvement Program Page 45

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    49/59

    Capital Improvement Program

    Jackson County, Minnesota Contact Highway Engineer

    2014 2018thruDepartment Highway Department

    Description

    Motor Grader Fleet

    Replacement Schedule (Based upon 16 year life)

    2015 - Unit 45 - 1999 Caterpillar 140H (2010 hours = 11,500+)

    2019 - Unit 40 - 2004 Caterpillar 140H (2010 hours = 8,000+)

    2024 - Unit 41 - 2008 Caterpillar 140M (2010 hours = 2,000+)

    2032 - Unit 43 - 2012 Caterpillar 160M

    Project # 12-HWY-045

    Priority 1 Urgent

    Justification

    Scheduled Replacement

    State Aid replacement schedule = 12yr

    Used daily for:

    Snow Plowing

    Gravel Road MaintenanceUnits have over 12,000 hours at replacement

    Budget Impact/Other

    Useful Life 12 yearsProject Name Motor Grader Fleet Category Vehicles:Highway Maintenanc

    Type Equipment

    Ongoing Project

    Dept. Priority Urgent

    Total2014 2015 2016 2017 2018Expenditures

    260,000260,000Equip/Vehicles/Furnishings

    260,000 260,000Total

    Total2014 2015 2016 2017 2018Funding Sources

    260,000260,000Property Tax

    260,000 260,000Total

    Jackson County 2014 - 2018 Capital Improvement Program Page 46

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    50/59

    Capital Improvement Program

    Jackson County, Minnesota Contact Highway Engineer

    2014 2018thruDepartment Highway Department

    Description

    Unit 52 - Replacement

    Truck, Oshkosh w/Sno Go

    Unit 59 - Replacement

    Sno Go, NP-3D Rotary

    Project # 12-HWY-052

    Priority 2 Necessary

    Justification

    Scheduled replacement - 2005

    Replace units 52 with a wheel type loader. Update unit 59 to a better unit for snow removal. Savings of approximately $160,000. This purchase

    will be further evaluated with the merger of City and County Maintenance Forces at the same location. The City also has a loader blower of the

    same vintage of the County's loader blower.

    Budget Impact/Other

    Useful Life 25 yearsProject Name Unit 52 - Oshkosh w/Sno Go Category Vehicles:Highway Maintenanc

    Type Equipment

    Ongoing Project

    Dept. Priority Necessary

    Total2014 2015 2016 2017 2018Expenditures

    220,000220,000Equip/Vehicles/Furnishings

    220,000 220,000Total

    Total2014 2015 2016 2017 2018Funding Sources

    220,000220,000Property Tax

    220,000 220,000Total

    Jackson County 2014 - 2018 Capital Improvement Program Page 47

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    51/59

    Capital Improvement Program

    Jackson County, Minnesota Contact Highway Engineer

    2014 2018thruDepartment Highway Department

    Description

    S.A.P. 32-629-43

    CSAH 29 from CSAH 8 to CSAH 34 (6 miles)

    Full Depth Reclamation - Bituminous Base, Wear, and Aggregate Shouldering

    Project # 12-HWY-29-43

    Priority 1 Urgent

    Justification

    This project places the bituminous surface and aggregate shouldering on a previous year grading project (S.A.P. 32-629-01).

    Budget Impact/Other

    Useful Life 25 yearsProject Name CSAH 29 - Base & Wear Category Highway: Road Construction

    Type Improvement

    Ongoing Project

    Dept. Priority Urgent

    Total2014 2015 2016 2017 2018Expenditures

    1,800,0001,800,000Construction/Maintenance

    1,800,000 1,800,000Total

    Total2014 2015 2016 2017 2018Funding Sources

    1,200,0001,200,000Federal Funds

    600,000600,000State Aid

    1,800,000 1,800,000Total

    Jackson County 2014 - 2018 Capital Improvement Program Page 48

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    52/59

    Capital Improvement Program

    Jackson County, Minnesota Contact Highway Engineer

    2014 2018thruDepartment Highway Department

    Description

    Unit 61 - Replace Front end Loader

    Front end type Loader, Caterpillar 928F, 1995 model

    Project # 13-HWY-061

    Priority 2 Necessary

    Justification

    SA replacement schedule = 12years

    Loader is 18 years old.

    Loader is used almost daily, year round.

    The replacement of this unit will be further evaluated with the City and County shared facility.

    Budget Impact/Other

    Useful Life 12 yearsProject Name Unit 61 - Loader Category Vehicles:Highway Maintenanc

    Type Equipment

    Ongoing Project

    Dept. Priority Necessary

    Total2014 2015 2016 2017 2018Expenditures

    190,000190,000Equip/Vehicles/Furnishings

    190,000 190,000Total

    Total2014 2015 2016 2017 2018Funding Sources

    190,000190,000Property Tax

    190,000 190,000Total

    Jackson County 2014 - 2018 Capital Improvement Program Page 49

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    53/59

    Capital Improvement Program

    Jackson County, Minnesota Contact Highway Engineer

    2014 2018thruDepartment Highway Department

    Description

    On CSAH 29 from Iowa Line to CSAH 8 (4.8 miles)

    2015 - S.A.P.32-629-39, -40, & -41

    Widening of existing roadway grade, construction of 4:1 inslopes, widening of existing ditches, and flattening of backslopes.

    S.A.P. 32-629-02

    Replace Br 89007 - Sufficiency Rating - 58.0

    2016 - S.A.P. 32-629-44

    Full Depth Reclamation

    Project # 13-HWY-29-01

    Priority 1 Urgent

    Justification

    Roadway is well past its useful life. Extensive heavy commercial traffic has decreased life of roadway.

    Bridge is structurally deficient. Bridge exists within the limits of SAP 32-29-01.

    Utilizing FDR will save approximately $70,000 per mile.

    Budget Impact/Other

    Useful Life 25 yearsProject Name CSAH 29 - Reconstruction Category Highway: Road Construction

    Type Improvement

    Ongoing Project

    Dept. Priority Urgent

    Total2014 2015 2016 2017 2018Expenditures

    3,150,0001,550,000 1,600,000Construction/Maintenance

    1,550,000 1,600,000 3,150,000Total

    Total2014 2015 2016 2017 2018Funding Sources

    3,090,0001,490,000 1,600,000State Aid

    60,00060,000State Bridge Bonds

    1,550,000 1,600,000 3,150,000Total

    Jackson County 2014 - 2018 Capital Improvement Program Page 50

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    54/59

    Capital Improvement Program

    Jackson County, Minnesota Contact Highway Engineer

    2014 2018thruDepartment Highway Department

    Description

    S.A.P. 32-623-21

    CSAH 23 and CSAH 4 Intersections in Petersburg and South of Petersburg

    Project # 14-HWY-23-21

    Priority 1 Urgent

    Justification

    Budget Impact/Other

    Useful Life 25 yearsProject Name CSAH 23 - Petersburg Intersections Category Highway: Road Construction

    Type Improvement

    Ongoing Project

    Dept. Priority Urgent

    Total2014 2015 2016 2017 2018Expenditures

    400,000400,000Construction/Maintenance

    400,000 400,000Total

    Total2014 2015 2016 2017 2018Funding Sources

    400,000400,000State Aid

    400,000 400,000Total

    Jackson County 2014 - 2018 Capital Improvement Program Page 51

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    55/59

    Capital Improvement Program

    Jackson County, Minnesota Contact Highway Engineer

    2014 2018thruDepartment Highway Department

    Description

    Unit 23 - Replacement

    Sign Truck, Sterling Acterra w/Maintener Box, 2001 model.

    Used for majority of sign maintenance and replacement throughout the County.

    Project # 16-HWY-023

    Priority 3 Desireable

    Justification

    Scheduled Replacement

    Main vehicle for Sign Maintenance, used daily.

    A main goal is to rotate the equipment before costs of repairs are nonrecoverable.

    Budget Impact/Other

    Useful Life 15 yearsProject Name Unit 23 - Sign Truck Category Vehicles:Auto/Trucks

    Type Equipment

    Ongoing Project

    Dept. Priority Desirable

    Total2014 2015 2016 2017 2018Expenditures

    127,000127,000Equip/Vehicles/Furnishings

    127,000 127,000Total

    Total2014 2015 2016 2017 2018Funding Sources

    127,000127,000Property Tax

    127,000 127,000Total

    Jackson County 2014 - 2018 Capital Improvement Program Page 52

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    56/59

    Capital Improvement Program

    Jackson County, Minnesota Contact Highway Engineer

    2014 2018thruDepartment Highway Department

    Description

    Unit 64 - Replacement

    Skid Steer Loader, 2000 model

    Project # 16-HWY-064

    Priority 3 Desireable

    Justification

    Scheduled Replacement

    Used frequently for:

    Ditch Repair

    Highway Repair

    Snow Removal in JCHD parking lotJCHD has two of these type of units (other unit 62). Intent is to have replacement of the two units be five to six years apart.

    The replacement of this unit will be evaluated with the merger of City and County at one location.

    State Aid recommended replacement 10yrs

    Budget Impact/Other

    Useful Life 12 yearsProject Name Unit 64 - 873 Bobcat Category Vehicles:Highway Maintenanc

    Type Equipment

    Ongoing Project

    Dept. Priority Desirable

    Total2014 2015 2016 2017 2018Expenditures

    32,00032,000Equip/Vehicles/Furnishings

    32,000 32,000Total

    Total2014 2015 2016 2017 2018Funding Sources

    32,00032,000Property Tax

    32,000 32,000Total

    Jackson County 2014 - 2018 Capital Improvement Program Page 53

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    57/59

    Capital Improvement Program

    Jackson County, Minnesota Contact Planning & Env Svs Director

    2014 2018thruDepartment Planning & Environmental Sv

    Description

    Existing pickup is a 2008 F-250

    Project # 14-P&E-010

    Priority 2 Necessary

    Justification

    This truck is the primary park pickup and needs to be capable of pulling equipment, etc.

    Budget Impact/OtherDelay in purchase can result in additional maintenance costs.

    Useful Life 6 yearsProject Name Ford F-250 Pickup Category Vehicles:Auto/Trucks

    Type Equipment

    Ongoing Project

    Dept. Priority Necessary

    Total2014 2015 2016 2017 2018Expenditures

    30,00030,000Equip/Vehicles/Furnishings

    30,000 30,000Total

    Total2014 2015 2016 2017 2018Funding Sources

    30,00030,000Property Tax

    30,000 30,000Total

    Jackson County 2014 - 2018 Capital Improvement Program Page 54

    DRAFT

  • 8/22/2019 2014-2018 Jackson County Capital Improvement Program

    58/59

    Capital Improvement Program

    Jackson County, Minnesota Contact Sheriff

    2014 2018thruDepartment Sheriff

    Description

    Replace Sheriff squad cars in a five (5) year rotation program. The Sheriff's department has eight (8) squad cars and one utility pick-up. The

    program is to replace two (2) v