2014 Construction Program
District 8
Hamilton
ClintonButler Warren
PrebleGreene
LebanonLebanon
Hamilton
ClintonButler Warren
PrebleGreene
ClermontClermont
The cover: This year’s cover features construction at the U.S. 50/Sixth Street Expressway Improvement project.
Project Hamilton County I-75/Hopple Street Interchange Improvement
Description Reconstruction and improvement of the I-75/Hopple Street Interchange. Four lanes of traffic to be maintained in each direction. More info on project at http://www.dot.state.oh.us/districts/D08/MillCreekEx press/ Construction Cost $90.8 millionCounty HamiltonPID 76257Start March 2013Est. End June 2016
Inside:The construction program for each county is represented by a map as well as a page listing of projects, each of which has a map locator number. Projects in red represent bridge/culvert work; those in green show road resurfacing projects; those in blue represent section improvement, safety and enhancement projects, and those in purple show major construction projects.
2014 Ohio Construction Fast Facts
• ODOT’s 2014 construction program includes 936 dif-ferent projects throughout the state, totaling $2.5 billion.
• $1.5 billion in roadway resurfacing projects. • 84 interstate safety upgrades • 30 bridges repaired or replaced as part of the new
County Bridge Program worth $14 million.• By unlocking the revenue potential of our Ohio Turn-
pike asset, the Ohio Jobs and Transportation Plan isfundingmultiplephasesoffiveprojectsthatwillbegin or continue this year, including:
◦ ConstructionofCleveland’seastbound George V. Voinovich Bridge◦ Interstate75highwayreconstructionthrough Wood and Hancock counties◦ ReconstructionofStateRoute57inLorainCounty◦ WideningofInterstate271inSummitCounty◦ ConstructionofCleveland’sOpportunityCorridor
2014 Construction Season Highlights for District 8
Other large projects beginning or continuing this year include:• ConstructionofanewinterchangeatInterstate71
andMartinLutherKingBlvd.inCincinnati’s“Up-town” area
• ModernizationofInterstate75throughDayton• ReconstructionoftheinterchangeatU.S.Route23
andInterstate270innorthernFranklinCounty
Project Clermont County I-275/SR 32 Interchange Improvement
Description Reconstruction of I-275/SR 32 interchange to add capacity and eliminate access point conflicts to improve safety and traffic flow on SR 32 and the I-275/SR 32 and Eastgate Blvd. interchanges. More info on project at http://easterncorridor.org/projects/sr-32-eastgate/sr-32- eastgate-project-overview Construction Cost $31.9 million County ClermontPID 76289Start July 2013Est. End Oct. 2015
Project I-71 Jeremiah Morrow Bridge Replacement
Description Replacement of the two Jeremiah Morrow spans over the Little Miami River. First span opened to northbound I-71 traffic November 2013. Work is proceeding on construction of second span. Additional information on http://www.omniproservices.com/jeremiah-morrow-bridge-replacement-project.html Construction Cost $88.1 million County WarrenPID 22950Start August 2010Est. End May 2016
Project Hamilton County I-71 at Martin Luther King Drive
Description Provide a full movement interchange at I-71 and Martin Luther King Drive while maintaining existing connections to William Howard Taft and McMillan roads. Provide north and southbound auxiliary lanes and capacity improve- ments. Traffic will be maintained. Construction Cost $80.8 millionCounty HamiltonPID 77628Start July 2014Est. End June 2017
Project Waldvogel Viaduct and Sixth Street Expressway Improvement
Description Removal of Waldvogel Memorial Viaduct, including four ramps to Elberon and Warsaw avenues. Replacement of structures for the four ramps to Elberon and Warsaw and replacement of structures for the connection to the Sixth Street Expressway. Removal and replacement of roadways for the required portions of River Road, Elberon Avenue, Warsaw Avenue, State Avenue, Evans Street and Maryland Avenue. One lane of U.S. 50 traffic maintained in each direction. Construction Cost $54.9 millionCounty HamiltonPID 20082Start July 2011Est. End May 2015
2014 District 8 Construction Program
4 BUTLER COUNTY
BUTLER COUNTY
2014 District 8 Construction Program
5
Map No. PID No. Location Work Type Construction Dates Cost 1 81769 U.S.27,cityofOxford Widening March 2014 to June 2016 $7,566,360
2 88722 SR63 Trafficmanagementsystem-signalization Sept.2013toJuly2014 $947,875
3 88780 WayneMadisonRoad Minor widening May to Nov. 2014 $612,346
4 87098 SR747atUnionCentre Turn lane addition; pavement repair May to Nov. 2014 $2,942,000
1 75686 SR177 Drainage improvement April to Nov. 2014 $2,710,8312 97207 SR129 Culvert March to May 2014 $109,2443 89731 Hueston Woods BridgeRepair April to Nov. 2014 $676,9694 84615 SR126,SR4,U.S.127,I-75 Culvert replacement/repair ApriltoSept.2014 $1,472,346
5 90943 SR73atSR4 Drainage improvement Nov. 2013 to April 2014 $93,699
6 88206 U.S.27 StabilizeIndianCreek Aug. 2014 to June 2015 $1,045,000
1 79390 SR4/122 Urbanpaving-cityofMiddletown July to Nov. 2014 $544,960
Local let projectsYankee Road Bridge deck replacementApril 2014 to April 2015
Roachester-Osceola Road Bridge deck replacementMarch to May 2014
Cincinnati Dayton Road WideningMarch to Aug. 2014
Lakota SchoolsSafe Routes to SchoolMay to July 2014
Hamilton Safe Routes to SchoolJune to Oct. 2014
Hamilton SchoolsNatural gas stationJune 2014 to Feb. 2015
Liberty Fairfield Road WideningJune to Oct 2014
Mauds Hughes Bridge replacementJuly to Nov. 2014
2014 District 8 Construction Program
CLERMONT COUNTY 6
Map No. PID No. Location Work Type Construction Dates Cost
1 76289 I-275atSR32 Interchangereconstruction Oct. 2013 to Oct. 2015 $31,990,699
2 92502 Eastgate Blvd Bridge InterchangereconstructiontoSR32
March 2013 to Oct. 2014 $9,039,295
1 92917 U.S.50eastofDryRunRd. Widen shoulder JunetoSept.2014 $98,000
2 87761 SR28eastofBranchHillGuinea Pike
Turn lane addition Aug.2014toSept.2015 $3,577,000
3 81425 SR125atMt.Carmel Intersectionimprovement June 2013 to Aug. 2014 $3,465,003
4 89910 SR125atBachBuxton Intersectionimprovement March to Oct. 2014 $387,965
5 85233 SR125atSR132 Intersectionimprovement JunetoSept.2014 $1,067,000
6 92578 SR133 Sliderepair April to Aug. 2014 $419,810
1 85135 U.S.50 Bridge repair resurfacing April to Oct. 2014 $4,680,608
2014 District 8 Construction Program
7 CLERMONT COUNTY
Local let projects
CR 116 Covered bridge repair Nov. 2013 to Nov. 2014
Clough Pike Widening June 2013 to Aug. 2014
Jackson PikeBridge deck replacementJune to Dec. 2014
Various routesPavement markingsJune to July 2104
Various routesGuardrail replacementJune to Sept. 2014
2014 District 8 Construction Program
CLINTON COUNTY 8
Map No. PID No. Location Work Type Construction Dates Cost
1 87156 U.S.68 Culvert reconstruction May to July 2014 $506,958
1 87061 I-71/SR380 Four-laneresurfacing/bridgerehab March 2013 to July 2014 $8,887,743
2 87093 SR28 Resurfacing Sept.2013toMay2014 $3,675,000
3 96651 U.S.22 Resurfacing Aug. to Nov. 2014 $1,707,000
Map No PID No. Location Work Type Construction Dates Cost1 95272 SR444/DaytonYellowSprings Intersectionimprovement May 2014 to Oct. 2015 $356,000
2 88770 U.S.68/KinseyRoad Intersectionimprovement JunetoSept.2014 $258,000
1 84238 I-675 Pedestrian/cyclist bridge June 2014 to May 2015 $2,850,000
2 89731 JohnBryanStatePark BridgeRepair June to Nov. 2014 $676,9691 77920 I-675 Resurfacing March 2014 to Oct. 2015 $16,267,610
2 88792 U.S.42/68 Urbanpaving-Xenia April to Nov. 2014 $1,302,1713 95678 SR444 Urbanpaving-Fairborn June to Oct. 2014 $133,000
2014 District 8 Construction Program
9 GREENE COUNTY
Local let projects
Fairborn Signals update June to Dec. 2014
Xenia Streetscape April to July 2014
Hanes RoadBridge replacementApril to July 2014
Grange Hall RoadLandscaping April to July 2014
2014 District 8 Construction Program
11 HAMILTON COUNTY
10 HAMILTON COUNTY
Map No. PID No. Location Work Type Construction Dates Cost1 82278 I-75atMitchellAvenue Reconstruction June2011toSept.2014 $54,649,065
2 82284 I-74atBeekmanStreet Interchangereconstruction Jan.2012toSept.2014 $13,069,483
3 76257 I-75/HoppleStreet Interchangereconstruction March 2013 to June 2016 $90,790,431
4 82283 I-75/RailAmerica Railbridgereplacement July2013toSept.2015 $18,055,153
5 82286 I-75betweenMitchelltoSR562 Reconstruction/widening July2014toJune2017 $3,400,000
6 20082 U.S.50 Bridge replacement/widening July 2011 to Oct. 2014 $54,923,975
7 82976 I-275atI-74 MajorRehabilitation Jan. 2014 to Nov. 2015 $27,993,562
8 77628 I-71atMartinLutherKing NewInterchange June2014toJune2017 $80,808,083
1 87098 SR126 Bridge rehabilitation April to Oct. 2014 $3,147,600
2 94476 I-275 Culvert repair June to Aug. 2014 $201,000
1 92785 MiamiWhitewaterForest Parking lot resurfacing June to Nov. 2014 $289,671
2 84495 I-75,EvendaletoI-275 Resurfacing Aug. to Nov. 2014 $4,400,000
2014 District 8 Construction Program
11 HAMILTON COUNTY
2014 District 8 Construction Program
13
Map No. PIDNo. Location Work Type Construction Dates Cost
1 83077 I-71atPfeiffer IntersectionImprovement Jan. 2013 to June 2014 $3,139,393
2 85874 Clough Pike Turn lane addition, signals, sidewalks
March to Aug. 2014 $2,484,042
3 94628 I-71atSR126 IntersectionImprovement MarchtoSept.2014 $3,049,130
4 86797 U.S.127,CresttoCranbrook
Intersectionimprovement ApriltoSept.2014 $980,000
5 83078 U.S.27atEastMiamiRiverRoad
Intersectionimprovement June 2014 to June 2015 $2,120,000
6 92555 U.S.27atI-275 Widening June to Oct. 2014 $2,336,000
7 94293 SR747,Glendale Signals June to Aug. 2014 $59,000
8 96973 U.S.127,SundaletoSR126 Pedestrian signal upgrade July to Nov. 2014 $63,000
9 86895 ReadingRoad,Kemperto Crescentville
turn lane addition/ signals, intersection improvement
July 2014 to July 2015 $2,900,000
10 91466 I-275/U.S.22 Turn lane addition at ramp Aug. to Nov. 2014 $114,000
11 86764 Euclid and Thomas roads, Madeira
SafeRoutestoSchools Aug. 2014 to Oct. 2015 $322,000
12 89182 U.S.22/SR3 Turn lane addition/signals Aug to Nov. 2014 $516,000
13 97537 Cincinnati area interstate Freewayservicepatrol/511sign installation
April to July 2014 $82,175
12 HAMILTON COUNTY
Local letprojects
Westwood Northern Blvd.ResurfacingApril to Nov. 2014
U.S. 50, CincinnatiUrban pavingMay to Nov. 2014
Central ParkwayBikewayJune to Sept. 2014
U.S. 50 Section improvementJune 2014 to March 2015
2014 District 8 Construction Program
Map No. PID No. Location Work Type Construction Dates Cost
1 86136 SR121,SR732 CulvertReplacements MaytoSept.2014 $829,073
1 97724 I-70 Pavement repairs Aug. to Oct. 2014 $300,000
PREBLE COUNTY 13
Local let projectSeven Mile RoadBridge repair Jan. to Aug. 2014
2014 District 8 Construction Program
WARREN COUNTY 14
Map No. PID No. Location Work Type Construction Dates Cost
1 22950 I-71/JeremiahMorrow Bridge replacement June 2010 to May 2016 $88,133,160
2 87401 I-71/MasonMontgomery Northbound loop ramp March 2014 to Oct. 2015 $7,402,950
1 93938 I-71/Mason-Montgomery Intersectionimprovement Aug.2013toSept.2014 $1,138,711
2 87399 I-71/Mason-Montgomery Interchangereconstruction Sept.2013toNov.2014 $1,595,755
3 92040 I-71/SR73 New ramp ApriltoSept.2014 $2,456,114
4 92926 I-75/SR122 Interchangelandscaping July to Oct. 2014 $1,007,000
1 88798 I-71 Bridge repair Oct. 2013 to July 2014 $535,306
2 87128 SR48 Bridge repair March to Aug. 2014 $1,039,785
1 92105 U.S.42 Pavement reconstruction Oct. 2013 to Nov. 2014 $13,851,867
2 82962 I-71,HamiltonCountylinetoSR741 Preventative maintenance May to Nov. 2014 $879,000
3 95749 LytleFivePointsRoad Resurfacing June to Aug. 2014 $420,000
2014 District 8 Construction Program
15 WARREN COUNTY
Local let projects
Mason-Montgomery/Bethany Road Roundabout June 2013 to June 2014
SR 123 Lebanon Connector new alignment June 2013 to Oct. 2014
LM&M railroad Improvements/rehabMay to Aug. 2014
Roachester-OsceolaRoadBridge deck replacement March to May 2014
Towne Blvd.Widening/resurfacing/enhancementsApril to Nov. 2014
11
PID No. Location Work Type Construction Dates Cost87019 District Highway lighting June 2012 to June 2014 $2,107,077
87024 District Signals June 2013 to June 2015 $1,617,61794602 District Guardrail repair/upgrade Nov. 2013 to Nov. 2015 $2,044,65596444 District Micro-surface friction treatment May to Aug. 2014 $1,819,38087028 District Highway lighting Sept.2014toAug.2015 $1,600,00087029 District SignUpgrade Sept.2014toSept.2015 $3,000,00084517 District Bridge sealing Oct.2014toFeb.2015 $771,00084530 District Bridge maintenance May to Nov. 2014 $2,300,00087026 District Pavement Marking April 2014 to April 2015 $2,248,382
87304 District Pavement resurfacing Aug. to Nov. 2014 $988,000
84475 District Crack sealing May to Nov. 2014 $284,29582963 District Crack sealing May to Nov. 2014 $279,60284478 District Preventative maintenance March to May 2014 $961,220
16DISTRICT
2014 District 8 Construction Program
11www.Ohgo.com