© 2014 hdr architecture, inc., all rights reserved.©...

34
© 2016 HDR, Inc., all rights reserved.

Upload: vandat

Post on 24-Mar-2018

214 views

Category:

Documents


1 download

TRANSCRIPT

  • 2014 HDR Architecture, Inc., all rights reserved. 2014 HDR Architecture, Inc., all rights reserved. 2014 HDR Architecture, Inc., all rights reserved. 2014 HDR, Inc., all rights reserved. 2014 HDR, Inc., all rights reserved. 2014 HDR, Inc., all rights reserved. 2016 HDR, Inc., all rights reserved.

  • 2016 HDR, Inc., all rights reserved.

    Grant Creek Restoration & Flood Control Project: 10-year Follow Up

    REPLACE ONE OF THESE IMAGES

    WITH AN ACTUAL PHOTO (SITE

    PHOTO)

    AMFM 2017 Annual Conference March 7th, 2017

  • Project Background

    Design & Construction

    Lessons Learned

    Questions

  • Lower Project Limit at Clark Fork River Floodplain

    Upper Project Limit at I-90

  • Project Background

  • Mullan Trail Subdivision

  • Resulted in lawsuit Homeowners Association implemented a fix

    that experienced groundwater challenges Prompted Missoula County to initiate a

    project through the US Army Corps of Engineers to find a solution

    1997 Flood Event

  • Pre-project analysis showed significant 100-year flood impacts

    Mullan Trail Subdivision 42 homes affected

  • Homes were being flooded

    Pre-1997 flood construction Post-1997 flood construction

  • Aggradation was reducing flood conveyance

  • Culverts were significant barriers to fish passage

  • Severe erosion was occurring

  • Multiple project stakeholders resulted in project challenges!

    City of Missoula State Highway Railroad Airport Area Large Undeveloped

    Ranches Irrigation District Existing

    Developments Interested

    Developers

  • $4.2 M FEMA Pre-disaster Mitigation Grant was acquired by Missoula County for the project!

    SUBMITTED!

    Second Application All Electronic new for

    FEMA Missoula County

    Commitment and Funds Landowner

    Easements/Approvals Mapped Property

    Elevations Supported by Hydrologic

    and Hydraulic Studies Benefit-cost Analysis

    Required

  • Design and Construction - Grant Creek Project Reaches

    Horseshoe Bend

    Upper Grant Creek

    Hiawatha Lake

    Mullan Trail/Prarie Schooner

    Clark Fork Confluence

  • The Creek was filling-in upstream of Highway 10 (West Broadway) Uppper Grant Creek Reach

    Field measurements of the creek bed showed a rise in the bed elevation

    ?

    The creek was losing its flood-carrying capacity

  • Cleaning of channel and culvert removal in Upper Grant Creek reach improved hydraulics and eased aggradation

    Pepsi Co. Culverts... Removed By Mother

    Nature!

  • Fish passage problems at West Broadway were addressed

    Culvert replacement was designed to:

    Reduce Flood Elevation Meet State and Federal Fish

    Passage Criteria

    Rehabilitation of existing culverts was not cost effective Replacing the culvert with natural bottom structures was implemented

    Relative Cumulative Culvert Costs

    Years

    Rel

    ativ

    e C

    osts

    Culvert Replacement Costs

    Culvert Rehabilitation

    Long-Term Cost Savings Strategy

    Chart1

    10010

    10520

    11030

    11540

    12050

    12560

    13070

    13580

    14090

    145100

    150110

    155120

    160130

    165140

    170150

    175160

    180170

    185180

    190190

    195200

    200210

    205220

    210230

    215240

    220270

    225280

    230290

    235300

    240310

    245320

    250330

    255340

    260350

    265360

    270370

    275380

    280390

    285400

    290410

    295420

    300430

    305440

    310450

    315460

    320470

    325480

    330490

    335500

    340510

    345540

    Cumulative Open Bottom Culvert Cost

    Cumulative Baffled Culvert Cost

    Years

    Relative Costs

    Relative Cumulative Culvert Costs

    Sheet1

    11001001010

    251051020

    351101030

    451151040

    551201050

    651251060

    751301070

    851351080

    951401090

    10514510100

    11515010110

    12515510120

    13516010130

    14516510140

    15517010150

    16517510160

    17518010170

    18518510180

    19519010190

    20519510200

    21520010210

    22520510220

    23521010230

    24521510240

    25522030270

    26522510280

    27523010290

    28523510300

    29524010310

    30524510320

    31525010330

    32525510340

    33526010350

    34526510360

    35527010370

    36527510380

    37528010390

    38528510400

    39529010410

    40529510420

    41530010430

    42530510440

    43531010450

    44531510460

    45532010470

    46532510480

    47533010490

    48533510500

    49534010510

    50534530540

    Sheet2

    Sheet3

  • Landowners in Horseshoe Bend Reach not ready to participate in the project

    Horseshoe Bend Unnatural Channel Remains Pruyn Check Dam Remains (10 Year Commitment)

  • Post-project 100-year floodplain Hiawatha Lake and Mullan Trail Reaches

    Hiawatha Lake Reach

    Mullan Trail Reach

  • Analysis of groundwater/surface water interactions at Hiawatha Lake reach were key

    Shallow groundwater contributed to historical Grant Creek flooding!

  • Sand Seams Were Eliminated When Hiawatha Lake Riparian Terrace Was Constructed

  • Addressing irrigation inputs to groundwater in the Hiawatha Lake and Mullan Trail reaches were necessary

    Worked With Active Agriculture Entities to Provide More Flow Control

    Minimized Waste Streams

    Reduced Infiltration Sources

  • Established/Developed Riparian Corridor in the Hiawatha Lake, Mullan Trail and Prairie Schooner Reaches Used locally adapted

    native plant species. Minimized exotic

    plant colonization. Maximized Woody

    Material. Minimized impacts to

    Lower Clark Fork River trout- overflow weir

    Improved waterfowl and other wildlife habitat.

  • Riparian Corridor Was Also Developed With Fish Passage Considerations

    Mullan Trail Earthen Overflow Weir in

    Operation

  • Design and Construction - Grant Creek Project Reaches

    Horseshoe Bend

    Upper Grant Creek

    Hiawatha Lake

    Mullan Trail/Prarie Schooner

    Clark Fork Confluence

  • Channel Modifications in Prairie Schooner Reach Was Limited by Available Right-of-way

  • Channel construction did help landowners in the Mullan Road reach

  • Design and Construction - Grant Creek Project Reaches

    Horseshoe Bend

    Upper Grant Creek

    Hiawatha Lake

    Mullan Trail/Prarie Schooner

    Clark Fork Confluence

  • Peak Flow Bypass engineered solution was required

  • Public Policy failures within governmental entities can happen (FEMA DFIRM mapping was wrong from the start)

    Be Flexible - game changers (Hurricane Katrina) can occur Multiple Stakeholders can shape the final product public outreach is paramount

    Lessons Learned

    DFIRM mapping was INCORRECT, which led to poor decisions

  • Some recommended actions may have to wait (Dougherty Ranch at Horseshoe Bend, Pruyn

    Check Dam, properties west of Mullan Trail subdivision) Natural solutions are preferred, but dont get trapped (Peak flow bypass structure enabled the

    hydraulic solution)

    Lessons Learned (cont.)

  • Surface and groundwater interconnection should be considered (Hiawatha Lake sand seam removal solved the Mullan Trail subdivision groundwater problems)

    Project permitting adds considerable time and complexity

    Lessons Learned (cont.)

  • Questions?

    Slide Number 1Grant Creek Restoration & Flood Control Project: 10-year Follow UpSlide Number 3Slide Number 4Slide Number 5Slide Number 61997 Flood EventPre-project analysis showed significant 100-year flood impactsHomes were being floodedAggradation was reducing flood conveyanceCulverts were significant barriers to fish passageSevere erosion was occurringMultiple project stakeholders resulted in project challenges!$4.2 M FEMA Pre-disaster Mitigation Grant was acquired by Missoula County for the project!Design and Construction - Grant Creek Project ReachesThe Creek was filling-in upstream of Highway 10 (West Broadway) Uppper Grant Creek ReachCleaning of channel and culvert removal in Upper Grant Creek reach improved hydraulics and eased aggradationFish passage problems at West Broadway were addressedLandowners in Horseshoe Bend Reach not ready to participate in the projectPost-project 100-year floodplain Hiawatha Lake and Mullan Trail ReachesAnalysis of groundwater/surface water interactions at Hiawatha Lake reach were key Sand Seams Were Eliminated When Hiawatha Lake Riparian Terrace Was ConstructedAddressing irrigation inputs to groundwater in the Hiawatha Lake and Mullan Trail reaches were necessaryEstablished/Developed Riparian Corridor in the Hiawatha Lake, Mullan Trail and Prairie Schooner ReachesRiparian Corridor Was Also Developed With Fish Passage ConsiderationsDesign and Construction - Grant Creek Project ReachesChannel Modifications in Prairie Schooner Reach Was Limited by Available Right-of-wayChannel construction did help landowners in the Mullan Road reachDesign and Construction - Grant Creek Project ReachesPeak Flow Bypass engineered solution was requiredLessons LearnedLessons Learned (cont.)Lessons Learned (cont.)Questions?