2015 integrated sustainable building design (isbd) student
TRANSCRIPT
Chris Fazzalare
Architectural Engineering
586-484-2188
Robert Melton
Architectural Engineering
606-231-6317
Kenneth Fitzgerald
Architectural Engineering
248-892-0803
Crystal Smith
Architectural Engineering
607-644-5159
2015 Integrated Sustainable Building Design (ISBD)
Student Design Project Competition
Daniel Faoro
21000 W 10 Mile Road
Southfield, MI 48075
248-204-2856
Mark Driedger
21000 W 10 Mile Road
Southfield, MI 48075
905-580-4820
Faculty Advisors
Lawrence Technological University
INTRO SITE ENCLOSURE PLANS MECHANICAL ELECTRICAL CONSTRUCTION LIFECYCLE
i
EXECUTIVE SUMMARY
Sustainable Sites Water Efficiency Energy Efficiency IEQ Building’s Impact Construction
To initiate the project, a morphology study was performed to develop floor plans in
response to the owner requirements and the climate of Doha, Qatar. Between the four of us,
we each designed at least one alternative for us to choose from to develop further. One of
our goals was to implement precast concrete as the primary structural material in order to
take advantage of the modularity of the system and to utilize the thermal mass of the
material. Once a design was selected, the building enclosure was looked at in more detail to
respond to the extreme heat of the site. Daylighting was one of our concerns when designing
the building and its enclosure. We wanted to ensure maximum daylight entered the building
while limiting the direct solar heat gain to the building.
After the exterior systems were finalized, the HVAC equipment was sized and selected. We
looked at a few different systems that could work well in this climate, and we ultimately
decided to go with a variable refrigerant flow (VRF) system. With this system, a dedicated
outdoor air system (DOAS) will be used to bring in only the outdoor air requirements that
are required by code. This will limit the amount of hot, humid outdoor air the systems need
to condition before supplying the spaces.
Programs used:
Autodesk Revit
Climate Consultant
Green Building Studio
Sefaira
Tally
Trane Trace 700
Visual-3D
INTRO SITE ENCLOSURE PLANS MECHANICAL ELECTRICAL CONSTRUCTION LIFECYCLE
ii
TABLE OF CONTENTS
Sustainable Sites Water Efficiency Energy Efficiency IEQ Building’s Impact Construction
SS WE EE IEQ BI C
Introduction X 1
Location X 2
Sustainable Sites X 3
Bioclimatic Data X 4
Bioclimatic Response X X X 5
Site Plan X X 6
Site Interaction X X 7
Site Water Response X X 8
Site Impact X X 9
Thermal Properties of Enclosure X 10
Enclosure Conductance X X 11
Double Skin Façade System X X X 12
Floor Plans X 13
Basement and First Floor Plans X 14
Second and Third Floor Plans X 15
East-West Section X 16
North-South Section X 17
Mechanical Systems X X 18
HVAC System X 19
General HVAC X 20
Water Efficiency X 21
Lighting Strategies X X 22
Recommended LPD X 23
Lighting Strategy X 24
Implemented LPD X 25
Electrical Control System X 26
Monitoring and Distribution X 27
Photovoltaics X 28
Maintenance and Future Growth X 29
Constructability X 30
Construction and Closing X 31
Lifecycle Analysis X 32
Building Energy Consumption X 33
Works Cited 34
Main Topics
The table of contents
shows the page
number as well as the
judging criteria that is
covered on each page.
The key for the criteria
is as follows:
SS = Sustainable
Sites
WE = Water
Efficiency
EE = Energy
Efficiency
IEQ = Indoor
Environmental
Quality
BI = Building’s
Impact
C = Construction
INTRO SITE ENCLOSURE PLANS MECHANICAL ELECTRICAL CONSTRUCTION LIFECYCLE
1
INTRODUCTION
Main Topics
Educational
Building
97,026 sq. ft.
Education City,
Qatar
Lat: 25.291°
Long: 51.530°
Codes Referenced
Building Description
Location: Qatar
Occupancy: Primary School
Occupancy Number: 1350 students and staff
Water Closets (M): 6
Water Closets (W): 12
Construction Type: Precast
Building Area: 36,276 sq. ft.
Gross Floor Area: 97,026 sq. ft.
Local Area
This project will be located in the Qatar Science & Technology Park, which is part of
Education City in Ar-Rayyan, Qatar. Education City, developed by the Qatar Foundation,
has three main focuses: education, science & research, and community development. The
foundation is also concerned about the environment and sustainability, so this project is
meant to reflect on and build upon their eco-conscious efforts. One of the biggest challenges
Qatar currently faces is the lack of freshwater. Based on information from Doha News,
Qatar heavily depends on desalinization since its reservoirs are almost depleted. Part of the
challenge of this area is to reduce the water demands of the project.
Codes Referenced
The following codes and standards have been referenced for this project:
ASHRAE 55-2013
ASHRAE 62.1-2013
ASHRAE 90.1-2013
ASHRAE 189.1-2014
IBC 2012
National Electric Code 2014
Product Disclaimer
There are specific products and brands mentioned in order to establish a basis of design. The
goal was not to endorse these companies, but to use available products to prove the efficacy
of the design.
INTRO
Sustainable Sites Water Efficiency Energy Efficiency IEQ Building’s Impact Construction
INTRO SITE ENCLOSURE PLANS MECHANICAL ELECTRICAL CONSTRUCTION LIFECYCLE
2
LOCATION
Main Topics
Greenfield Site
Sandstorms may
occur
Latitude &
Longitude:
25.2867° N,
51.5333° E
Since the site has not been developed before, the site is
listed as a “greenfield site” based on the definitions at the
beginning of ASHRAE 189.1-2014. This is an allowable
site as per ASHRAE 189.1-2014 Section 5.3.1.1 because
there are existing services and residencies within half a
mile of its location. Figures 1, 2, and 3 show where the
project is located in relation to the Middle East, Doha,
and Education City.
The occurrence of sandstorms in Qatar is common. The
project was designed with the potential impacts that sand
could have. One of the main concerns for this was the
effect sand would have on the photovoltaic array, but
cleaning the panels will be able to maintain their
efficiency. Sand traps will be used in any air intake to the
building to reduce potential damage to HVAC systems.
Figure 3 - Map of Education City
Figure 2 - Map of Doha
Figure 1 - Map of Middle East
Sustainable Sites Water Efficiency Energy Efficiency IEQ Building’s Impact Construction
INTRO
INTRO SITE ENCLOSURE PLANS MECHANICAL ELECTRICAL CONSTRUCTION LIFECYCLE
3
Sustainable Sites Water Efficiency Energy Efficiency IEQ Building’s Impact Construction
SUSTAINABLE SITES
Main Topics
Solar Studies
Summer Solstice
Max Angle: 88°
Winter Solstice
Max Angle: 42°
SITE
Introduction
Before designing the building or the systems to be implemented, climate and site studies
were performed. The goal of these studies was to understand the conditions in order to
properly design and integrate all the systems that were utilized to ensure a comfortable and
enjoyable experience could be provided to the occupants. The extreme heat of Qatar
influenced the design and required different strategies that are unique to this type of climate.
Substantial shading to the site and to the building itself was one of the focuses of the design
because of these criteria.
Solar Studies
The sun angle chart for Doha, Qatar is shown in Figure 4 and is provided by Sun Earth
Tools. On the summer solstice, the sun rises and sets about 25° north of the east-west axis.
The sun will be almost directly overhead around noon on the summer solstice as well. The
highest altitude the sun reaches on the winter solstice is about 42°. This information aids the
design of the building and site shading and the photovoltaic panels.
Figure 4 - Sun Angle Chart for Doha, Qatar
INTRO SITE ENCLOSURE PLANS MECHANICAL ELECTRICAL CONSTRUCTION LIFECYCLE
4
The annual rainfall for Qatar is about 2.5 inches, per information from The World Bank
Group. Figure 5 shows the average monthly breakdown of rainfall in Qatar from 1990 to
2009. Climate Consultant® software was also used to aid the climate research for the site.
Abu Dhabi was used as a proxy site since information was not available for Qatar
specifically. The design temperatures are shown in Figure 6. It is common for the
temperature to reach 100°F or higher over the summer.
BIOCLIMATIC DATA
Main Topics
Annual Rainfall
2.5 in
Design
Temperatures
Low: 52°F
High: 113°F
Figure 6 - Monthly Design Temperatures for Abu Dhabi
Figure 5 - Rainfall in Qatar
Sustainable Sites Water Efficiency Energy Efficiency IEQ Building’s Impact Construction
SITE
INTRO SITE ENCLOSURE PLANS MECHANICAL ELECTRICAL CONSTRUCTION LIFECYCLE
5
BIOCLIMATIC
RESPONSE
Main Topics
Climate Zone 1
Exterior Shading
Based on information from Degree Days, Doha, Qatar, has 12,496 cooling degree days
(base 50°F) in one year. Using ASHRAE 90.1-2013 Table B1-4, since the CDD50°F is
greater than 9,000, the site is listed as ASHRAE climate zone 1. Figure 7 shows a
psychrometric chart for Abu Dhabi provided by Climate Consultant® software. The
program suggests different strategies to condition the air to create a comfortable indoor
environment for the occupants. The most highly recommended suggestion was to shade the
windows, which could reduce the cooling load required over 2,468 hours in the year. Single-
stage evaporative cooling was another suggested strategy to cool the building. However, the
humidity in Doha varies greatly with potential for extremely high humidity year-round and
the effectiveness of an evaporative cooling system would be questionable and inconsistent.
To strive for consistency, a simpler system using variable refrigerant flow (VRF) units that
can function year-round was selected. The data from Climate Consultant® is based on the
assumption that the building is occupied from 7am to 6pm year-round.
Figure 7 - Bioclimatic Chart
Sustainable Sites Water Efficiency Energy Efficiency IEQ Building’s Impact Construction
SITE
INTRO SITE ENCLOSURE PLANS MECHANICAL ELECTRICAL CONSTRUCTION LIFECYCLE
6
SITE PLAN
Sustainable Sites Water Efficiency Energy Efficiency IEQ Building’s Impact Construction
SITE
1
Main Topics
Drop Off
Main Entrances
Secondary Exits
Carports with
Water Collection
EV Parking
Spaces (6)
Bike Racks
Shaded Green
Path
Water Movement on
Site
Public Transportation
Route
Parking Lot Entrances
and Exits
Porous Concrete
Parking Lot and Walk
Way
INTRO SITE ENCLOSURE PLANS MECHANICAL ELECTRICAL CONSTRUCTION LIFECYCLE
7
SITE INTERACTION
Site Rendering
Bioclimatic Site
Design
Photovoltaic Roof
Heat island
Mitigation
Front Entrance
From Green Strip
Bioclimatic Site
Design
Double Skin
Façade
West Entrance
Front Entrance From
Drop Off Location
Double Skin
Façade
East Entrance
Main Pedestrian
Access
Sustainable Sites Water Efficiency Energy Efficiency IEQ Building’s Impact Construction
SITE
INTRO SITE ENCLOSURE PLANS MECHANICAL ELECTRICAL CONSTRUCTION LIFECYCLE
8
SITE WATER RESPONSE
Sustainable Sites Water Efficiency Energy Efficiency IEQ Building’s Impact Construction
SITE
Main Topics
Roof Top Water
Harvesting
Porous concrete
35,000 Gallons
Subgrade Cistern
Gray Water Reuse
Stormwater Management
As per ASHRAE 189.1-2014 Section 5.3.4, rainwater harvesting and infiltration will be
implemented to mitigate rainwater runoff. The rain that falls on the building roof, 33,610
sq. ft., and the carports, 51,000 sq. ft., will be directed to a cistern used to flush toilets inside
the building. A calculation to determine how much water can be collected using Doha’s 2.5
inches of annual rainfall is shown below. Since Qatar’s freshwater supply is very limited,
this is an important strategy to help reduce the water demands of the building. The large
amount of paved walking and parking areas the site will utilize porous concrete. This will
allow the site to retain its normal infiltration of water on site. Water will pass through the
concrete and into the soil below, reducing the impact of storm water and allowing the site to
absorb more water than a typical asphalt covered site.
Cistern
The building uses more water than can be collected in a one month period of time, 461,953
gallons per month based on Mechanical and Electrical Equipment for Buildings. The cistern
was sized to one month’s typical rain fall during the rainy season, 35,000 gallons. This
would allow the building to significantly reduce storm water run off while not over sizing
the cistern. This cistern would be located below the central courtyard, this will keep the
cistern close to the building and the systems used to maintain it while protecting it from the
forces the building applies on the site. Water collected form the roof and carports will
contain dust and dirt that needs to be removed before storage. A settling tank and series of
filters will be located in the basement to clean the water before it is stored in the cistern. The
collected grey water will be used to flush toilets.
Equation 1 - Annual Rainwater Collection
INTRO SITE ENCLOSURE PLANS MECHANICAL ELECTRICAL CONSTRUCTION LIFECYCLE
9
SITE IMPACT
Sustainable Sites Water Efficiency Energy Efficiency IEQ Building’s Impact Construction
SITE
Main Topics
Native Plants
Light Colored
Materials
Shading
Double Skin
Façade
Heat Dissipation
Raised
Photovoltaic Array
Site Water Use
Native plants have been chosen to provide shade to the site as well as the built environment.
These plants will be compatible with the existing ecosystem and shall be drought tolerant.
Per ASHRAE 189.1-2014 Section 6.3.1.1, greater than 60% of the improved site area is
landscaped with native and adapted plants. These native plants are able to thrive in the
limited rain fall Education City receives and therefore will not increase building’s annual
water usage. Irrigation will not be needed or implemented in the project. Furthermore
natural irrigation of the plants is maximized by grading the site so that water not collected
by the graywater cistern is directed into the green belt located on the south side of the site.
Heat Island Effect
To reduce the gain of heat on the site the following was used: light colored porous concrete,
site shading and a double skin façade system. The light colored concrete reflects light and
absorbs less heat when compared to asphalt. The density of the porous concreate reduces the
material’s ability to absorb large amounts of heat thus it cools off quickly and reduces the
site’s heat island effect. The site utilizes native shade trees and car ports to create shade on
the site and keep it cooler. Native trees will provide shade and some evaporative cooling
through transpiration to reduce site heat gain. Carports will provide more shade and have a
white roof to reflect light and reduce heat absorption. The concrete building will have a
double skin façade system to protect the concrete for direct sunlight and diffuse the heat as
the heated air rises though the façade and out the top of the building. A similar concept is
used on the roof, photovoltaic array raised 7 feet off the roof blocks the roof from direct
sunlight and provides another air space. The layer of air absorbs the heat and is removed
from the building as wind blows over the top of the building. With these systems the
building is able to exceed the percentage of shaded exterior defined by ASHRAE 189.1-
2014 Section 5.3.5.2.
INTRO SITE ENCLOSURE PLANS MECHANICAL ELECTRICAL CONSTRUCTION LIFECYCLE
10
THERMAL PROPERTIES
OF ENCLOSURE
Main Topics
Enclosure
Conductivity
R-28 Selected
Introduction
Careful consideration went into the design of the enclosure. The conductivity of the
enclosure exceeds the values listed in ASHRAE 189.1-2014. The properties of the
fenestrations were also selected to comply with the standard. Due to the extreme heat gain
from the sun in Doha, Qatar, an exterior shading system was implemented. This system
allows control for how much daylight can enter the building to control the lighting load
while limiting direct solar radiation that strikes the building, thus reducing the cooling loads.
Enclosure Thermal Conductivity
In order to determine the ideal R-value for the enclosure, Figure 8 indicates what the heat
gain would be with different R-values. By using the equation for heat gain, Q=UAΔT, and
keeping the area of the enclosure and the difference between indoor and outdoor
temperatures constant, it was demonstrated that an enclosure with an R-value of 28 is both
efficient and economical. Following the law of diminishing returns, after an R-value of 28,
there is less benefit to adding more insulation. After this point, it may be too expensive to
add further insulation.
ENCLOSURE
0
20000
40000
60000
80000
100000
120000
0 20 40 60 80 100 120
Hea
t G
ain
(BTU
H)
R-Value
Wall Heat Gain by R-Value
Wall Gain
Figure 8 - Enclosure Conductivity Comparison
Sustainable Sites Water Efficiency Energy Efficiency IEQ Building’s Impact Construction
R-28
INTRO SITE ENCLOSURE PLANS MECHANICAL ELECTRICAL CONSTRUCTION LIFECYCLE
11
Enclosure Properties
The following table lists the U-values recommended by ASHRAE 189.1-2014 Table E-1 for
different enclosure elements in ASHRAE climate zone 1 compared to the actual
implemented values. The enclosure of the building is primarily constructed of precast
modules with integrated insulation to provide continuous insulation. The recommended
values and the actual implemented values are listed in the table below.
Fenestration Properties
There are requirements for vertical fenestrations given in ASHRAE 189.1-2014 Table E-1
also. The following table summarizes the requirements and the actual values used in the
project. Table E-1 also gives an allowable range of values for the vertical enclosure’s
percent glazing between 0% and 40%. This project has a total wall area of 43064 sq. ft. and
a total fenestration area of 11771 sq. ft., giving a glazing percentage of 27%. This design
meets ASHRAE requirements and allows daylight to enter the enclosed environment. The
center-of-glass U-value for the windows are 0.11.
Table 2 Recommended Implemented Percent Improved
from Baseline
Assembly U-Value 0.45 (max) 0.18 60%
SHGC (E, W, S) 0.25 (max) 0.24 4%
SHGC (N) 0.35 (max) 0.24 31.4%
VT/SHGC 1.10 (min) 1.58 43.6%
ENCLOSURE
CONDUCTANCE
Main Topics
27% Glazing
U-Values:
Wall: 0.035
Roof: 0.026
Floor: 0.035
Window (COG):
0.18
Window (Asm):
0.11
ENCLOSURE
Table 1 Wall Roof Floor
Max Allowable U-Value Conditioned 0.580 0.048 0.322
Semiconditioned 0.580 0.218 0.322
Implemented U-Value Conditioned 0.035 0.026 0.035
Semiconditioned 0.035 0.026 0.035
Conditioned 94.0% 45.8% 89.1% Percent Improved from
Baseline Semiconditioned 94.0% 88.1% 89.1%
Sustainable Sites Water Efficiency Energy Efficiency IEQ Building’s Impact Construction
INTRO SITE ENCLOSURE PLANS MECHANICAL ELECTRICAL CONSTRUCTION LIFECYCLE
12
DOUBLE SKIN FAÇADE
SYSTEM
Sustainable Sites Water Efficiency Energy Efficiency IEQ Building’s Impact Construction
ENCLOSURE
Main Topics
Double Façade
Stainless steel
Panels
Stack Effect
Dynamic Action
Daylight Control
Shading
Exterior Example
Interior Example
Due to Doha Qatar’s location, the building will be
subjected to large amounts of solar radiation
throughout the year. Although this radiation
provides a great amount of daylighting and energy
for the photovoltaic panels, it comes at a high
price. Solar radiation heats the building and
increases the cooling demand of the building.
Increasing the R-value is one way to protect the
building, but another is to protect the building
from ever receiving the heat. To do this a passive
double skin façade system will be implemented.
Double Skin Façade System:
The double skin façade system on the
building is made of a perforate stainless
steel panel as seen on the University of
Potsdam physics building Figure 10. For
this project however it will be offset 2 feet
off the building to create an effective air
space. The 2 feet allows heat to be
absorbed and move up the building in a
stack effect, without transferring large
amounts of energy to the concrete. Cooler
air is pulled in through the façade at
ground level to continuously cool the
building. The dynamic nature of the
façade allows a daylight to be partially
blocked, when needed, or allowed to enter
the building, when desired. Figure 11
shows an interior view of the façade
closed in direct daylight and the lights on
in the class room.
Figure 9 - Double Skin Façade
Wall Section
Figure 10 - U of P, Stainless steel Fa-
Figure 11 - U of P, Interior View
INTRO SITE ENCLOSURE PLANS MECHANICAL ELECTRICAL CONSTRUCTION LIFECYCLE
13
FLOOR PLANS
Main Topics
156,926 SF
Parking Lot
336 Parking
Spaces
6 EV Parking
Spaces
480’ Green Scape
Connection to The
Campus’s Main
Building
920 Roof Rack
Mounted PV
Panels
5 Roof Rack
Mounted Solar
water Heaters
Introduction
To fully integrate the architectural, mechanical, electrical, structural, and construction
systems, the entire building was designed from the ground up instead of using the floor
plans provided by ASHRAE for the competition. The floor plans have been provided in
order to get a visual sense of the spaces and the organization.
Sustainable Sites Water Efficiency Energy Efficiency IEQ Building’s Impact Construction
PLANS
Not to Scale
INTRO SITE ENCLOSURE PLANS MECHANICAL ELECTRICAL CONSTRUCTION LIFECYCLE
14
BASEMENT AND FIRST
FLOOR PLANS
Main Topics
Basement
Substation
EM Generator
(2) DOAS Units
Cistern
Battery Storage
Area Way for
Equipment Removal
First Floor
Outdoor Courtyard
Covered Entrances
and Exits
Workshop Spaces
Admin Offices
Covered Back
Porches
PLANS
Sustainable Sites Water Efficiency Energy Efficiency IEQ Building’s Impact Construction
INTRO SITE ENCLOSURE PLANS MECHANICAL ELECTRICAL CONSTRUCTION LIFECYCLE
15
SECOND AND THIRD
FLOOR PLANS
Main Topics
Second Floor
Classrooms
Roof Top
Compressor Units
Closed Access
Roofs
Open Center
Covered Outdoor
Space, Thermal
Buffer
Third Floor
Classrooms
Open Center
Covered Outdoor
Space, Thermal
Buffer
Semi-covered
Outdoor Space,
North Side of the
Building
PLANS
Sustainable Sites Water Efficiency Energy Efficiency IEQ Building’s Impact Construction
INTRO SITE ENCLOSURE PLANS MECHANICAL ELECTRICAL CONSTRUCTION LIFECYCLE
16
EAST-WEST SECTION
Main Topics
Semi-covered
Rooftop Area
Central Courtyard
Staircases
Fire Exit Doors
Mechanical Room
PV 7’ Above Roof
PLANS
Sustainable Sites Water Efficiency Energy Efficiency IEQ Building’s Impact Construction
East-West Section, Looking North
East-West Paraline Section East-West Paraline Section, Looking North
INTRO SITE ENCLOSURE PLANS MECHANICAL ELECTRICAL CONSTRUCTION LIFECYCLE
17
NORTH-SOUTH
SECTION
Main Topics
Covered Outdoor
Area
Classrooms
Rooftop Units
Library
Shop Space
Battery Storage
Room
PV 7’ Above Roof
PLANS
Sustainable Sites Water Efficiency Energy Efficiency IEQ Building’s Impact Construction
North-South Section, Looking East
North-South Paraline Section, Looking East
INTRO SITE ENCLOSURE PLANS MECHANICAL ELECTRICAL CONSTRUCTION LIFECYCLE
18
MECHANICAL
SYSTEMS
Main Topics
ASHRAE 55
Cooling Loads
ASHRAE 62.1
Ventilation
Requirements
Environmental
Tobacco Smoke
Control
Introduction
To determine what systems should be used in the building, calculations for the cooling loads
were performed first. Then the ventilation requirements were determined to comply with
ASHRAE 62.1. Based on the numbers from these calculations, a system was able to be
selected and implemented in the design. The water efficient design is also discussed by
exploring the fixture choice, rainwater collection and usage, energy dashboard and kiosk
area, annual consumption and the improvements made over baseline, and the onsite
renewable energy.
Cooling Loads
Load analysis for the building was completed using Trane Trace 700®. The required
cooling load for the main building is calculated to be 123.2 tons in order to comply with
ASHRAE 55-2013.
Outdoor Air Requirements
To comply with ASHRAE 62.1-2013 Section 4, a ventilation spreadsheet was developed to
determine the required flow rate of outdoor air for each space depending on area and
occupancy. A sample calculation for a typical classroom is shown below. Using these
calculations for each space, it was found that 20830 CFM of outdoor air was required for the
entire building.
Environmental Tobacco Smoke Control
The recommendations to address environmental tobacco smoke control in ASHRAE 189.1-
2014 Section 8.3.1.4 are to prohibit smoking inside the building and to place designated
smoking areas at least 25 feet away from any entrance, outdoor air intake, and operable
windows. Signs stating these requirements are also required to be posted within 10 feet of
each entrance.
MECHANICAL
Sustainable Sites Water Efficiency Energy Efficiency IEQ Building’s Impact Construction
Equation 2 - Sample Outdoor Air Calculation for a Typical Classroom
INTRO SITE ENCLOSURE PLANS MECHANICAL ELECTRICAL CONSTRUCTION LIFECYCLE
19
HVAC SYSTEM
Sustainable Sites Water Efficiency Energy Efficiency IEQ Building’s Impact Construction
MECHANICAL
Main Topics
(2) DOAS units
Floor mounted
VRFs
Merv 6 Pre-Filter
Merv 11 Main
Filter
Conditioning the Building
Two DOAS units are used to pull fresh air into the building and supply the minimum the
fresh air requirements. The system runs on 100% outdoor air, no mixing occurs since there
is no return air. Each of the DOAS units can handle up to 12,000 CFM, together they
supply the required 20,830 CFM of outdoor air. The refrigerant cooling coil in the DOAS
cools incoming air down to 72°F and dehumidifies the air based on information from the
energy dashboard. The air is then ducted into each room.
Floor mounted Variable Refrigerant Flow (VRF) units located at floor level will provide all
the sensible cooling required for the room. Due to the low distribution of cool air a
stratification will form in the room with warm air near the ceiling and cool air near the floor.
The warmer air will pass through a transfer grill to the lower pressure, semi conditioned
corridor. The corridor will remain just below 80°F, cooled by the transfer of air from
conditioned spaces and some VRF units. These corridor units will only be used when the
corridors exceed 80°F.
From the corridor the air will be ducted back to the mechanical room to pass through an
enthalpy wheel and be relieved to the south facing façade. This façade will take the biggest
amount of solar radiation during the day and the cool relief air will reduce the amount of
solar gain the façade receives.
The System will use sand trap intake louvers to protect the system from sand, Merv 6 filter
to protect against any remaining sand and dust while a Merv 11 will be utilized to filter out
smaller particulate less than 2.5 μm in accordance with ASHRAE 62.1-2013 Section 6.2.1.
The Merv 6 filter will extend the life and effectiveness of the Merv 11 filter.
Figure 12 - Typical Room Supply
INTRO SITE ENCLOSURE PLANS MECHANICAL ELECTRICAL CONSTRUCTION LIFECYCLE
20
GENERAL HVAC
Main Topics
No Duct
Insulation
Required
Pipe Insulation
Fire Protection
Fire Protection
Solar Hot Water
Duct and Pipe Insulation
There are recommendations for duct insulation for cooling-only ducts in ASHRAE 189.1-
2014 Table A-2. Since all of the ductwork is in the ceiling of a conditioned space or a
semiconditioned space, no insulation is required for the ductwork. The piping in the
building will be insulated to comply with ASHRAE 90.1-2013 Table 6.8.3-1 and Table
6.8.3-2.
Workshop Dust
The wood and metal shops share an exhaust system that needs to be filtered. This will be
done with a centrifugal separator located in the separate grounds room adjacent to the shop
rooms. This will remove particulate for the air so it can be safely exhausted.
Fire Protection
According to the National Fire Protection Association (NFPA) standard 72, this building
falls in the type 1a or 1b category. This category does not require buildings to be sprinkled.
However, a sprinkler system will be installed in the wood and metal shops. Common
emergency and fire devices found throughout an educational building include manual pull
stations, smoke detectors, and fire extinguishers. A local distributer located in Doha, can
supply all these necessary fire alarm components.
To comply with the International Building Code (IBC), manual pull stations will be placed
within 5 feet of every exit, as well as within 200 feet of traveling distance from an
occupant’s location. Combination carbon monoxide and smoke detector will be placed
outside of each elevator lobby, each exit, and spaced every 30 feet, while exit signs will be
placed at every exit to highlight egress locations. Speaker strobes will also be placed
throughout the building, such that an alarm signal can be seen and from anywhere in the
building.
Domestic Hot Water
To further offset the energy needs of the building, solar evacuated hot water collectors will
be placed on the roof. Five large panels are used to take incoming utility water at 70 degrees
and raise the temperature to 120 degrees. Utilizing a holding tank in a mechanical room it is
possible to produce all the hot water necessary for the building’s domestic needs.
Sustainable Sites Water Efficiency Energy Efficiency IEQ Building’s Impact Construction
MECHANICAL
INTRO SITE ENCLOSURE PLANS MECHANICAL ELECTRICAL CONSTRUCTION LIFECYCLE
21
WATER EFFICIENCY
Main Topics
Building Water
Use Reduction
Building Water
Consumption
Management
Plumbing Fixtures
The plumbing fixtures in the building were selected to comply with the allowable water
usage rates given in ASHRAE 189.1-2014 Table 6.3.2.1 and reduce the water demands of
the building. The following table shows the different fixtures selected and their water
consumption compared to the recommended values. The low-flow fixtures were
implemented to help reduce the demand of fresh water which is already limited in supply in
Qatar.
Building Water Consumption Management – Energy Dashboard-
Per ASHRAE 189.1 Section 6.3.3.1, both reclaimed and potable water entering and leaving
the building will be monitored utilizing the same dashboard system and compatible
measuring devices as the energy systems. The system will report daily, monthly and yearly
water consumption per floor and per large water usage systems. Data collected will be
stored on the network within the building and will be accessible to the public on demand
through a graphical interface in the main lobby.
Table 3 Water Closet Urinal Lavatory
Allowable Water Usage 1.28 gpf 0.5 gpf 0.5 gpm
Actual Water Usage 1.28 gpf 0 gpf 0.5 gpm
Image
Sustainable Sites Water Efficiency Energy Efficiency IEQ Building’s Impact Construction
MECHANICAL
INTRO SITE ENCLOSURE PLANS MECHANICAL ELECTRICAL CONSTRUCTION LIFECYCLE
22
LIGHTING STRATEGIES
Main Topics
Daylighting
Fiber Optics
Light Pollution
Introduction
This section will explain the energy efficient design by exploring the enclosure, electrical
distribution, lighting and daylighting with achieved lighting power density, control systems,
energy dashboard and kiosk area, annual energy consumption, and the improvements made
over baseline and the final onsite renewable energy. By optimizing the systems and
elements listed above through the application of Green Building Studio by Autodesk, it was
possible to achieve a 90% more energy efficient building over the baseline building model.
Green Building Studio and Sefaira were both used throughout the project to predict the
energy usage of each major system, effectiveness of the exterior envelope, and other
components within the system.
Exterior Lighting
To illuminate the exterior paths, LED luminaires are spaced 30 feet apart. This luminaire
provides a uniform distribution making individuals feel comfortable and safe at night while
reducing the amount of light pollution to the night sky and the surrounding area.
Interior Lighting
To take advantage of the maximum amount of daylight
use in the building, a double skin façade system
composed of folding horizontal metal panels and
windows collectors to channel daylight to interior spaces.
Fiber optic light collectors are also used to introduce
daylight. Rectangular light collectors, as shown below,
will be located in the 2-foot gap between the façade and
wall at the roof. The cables are then run behind the
mullions of the façade panels and into the ceiling plenum of the rooms where needed.
A company in Sweden, manufactures a hybrid fiber optic daylighting device that
incorporates an LED fixture into the system. When the sun does not provide enough output
through the luminaire, the LED turns on and helps aid in the lumen output into the room.
Each fiber optic luminaire will vary in lumen output from the sun depending on the distance
of cable that needs to be run. For example, at 16.5 feet, 1,460 lm will be provided, while at
64 feet, 860 lm will be provided.
ELECTRICAL Figure X
Figure 13 - Fiber Optic Light
Collector
Sustainable Sites Water Efficiency Energy Efficiency IEQ Building’s Impact Construction
INTRO SITE ENCLOSURE PLANS MECHANICAL ELECTRICAL CONSTRUCTION LIFECYCLE
23
RECOMMENDED LPD
Main Topics
Allowable LPD
The lighting power density (LPD) allowed for the building was determined using ASHRAE
90.1-2013 Table 9.6.1 and ASHRAE 189.1-2014 Table 7.4.6.1B. The summary of the
standards’ recommendations are listed in the table below. The final LPD values were
calculated by taking the LPD from 90.1 and multiplying it by the factor from 189.1. If the
space has a room cavity ratio (RCR) greater than the threshold for that type of space, a 20%
increase to the LPD is allowed. For the entire building, an aggregate LPD of 0.94 is allowed.
The calculations were done using a space-by-space method to account for the potential
increase in LPD based on the RCR value.
ELECTRICAL
Table 4 RCR 90.1 LPD (W/ft2) 189.1 Factor Final LPD (W/ft2)
Classroom / Lecture
Hall / Training Room
4 1.24 0.85 1.05
Conference / Meeting /
Multipurpose Room
6 1.23 0.90 1.11
Copy / Print Room 6 0.72 1.00 0.72
Corridor Width<8ft 0.66 0.85 0.56
Computer Room 4 1.71 1.00 1.71
Electrical / Mechanical
Room
6 0.42 1.00 0.42
Lobby 4 0.90 0.95 0.86
Breakroom 4 0.73 0.85 0.62
Office (Enclosed) 8 1.11 0.95 1.05
Office (Open) 4 0.98 0.85 0.83
Restroom 8 0.98 1.00 0.98
Stairwell 10 0.69 1.00 0.69
Storage Room 6 0.63 1.00 0.63
Workshop 6 1.59 1.00 1.59
Sustainable Sites Water Efficiency Energy Efficiency IEQ Building’s Impact Construction
INTRO SITE ENCLOSURE PLANS MECHANICAL ELECTRICAL CONSTRUCTION LIFECYCLE
24
LIGHTING STRATEGY
Main Topics
Implemented LPD
Emergency
Lighting Levels
By incorporating the Parans Hybrid Daylight and LED luminaire, the LPD was reduced
from 0.6 W/ft2 to 0.4 W/ft2.
In a case of emergency, all paths of egress will be illuminated with the minimum code
according to International Building Code. Per the emergency code, emergency lighting will
meet the following:
Minimum footcandle of greater than 0.1 footcandles
Average footcandle of at least 1.0 footcandle
Maximum to Minimum ratio of 40:1 or less
To achieve this, every third light in the corridors would be placed on emergency, as well as
a luminaire outside of each elevator and one on every floor in the stairwells.
ELECTRICAL
Sustainable Sites Water Efficiency Energy Efficiency IEQ Building’s Impact Construction
Figure 14 - LPD Comparison Before (Left) and After (Right) Fiber Optics
INTRO SITE ENCLOSURE PLANS MECHANICAL ELECTRICAL CONSTRUCTION LIFECYCLE
25
IMPLEMENTED LPD
Main Topics
IES Light Level
Recommendations
LED Fixtures
To comply with IES-recommended footcandles per room type, additional electrical lighting
is needed. A dimmable LED 2’x4’ luminaire paired with a photocell reduces the amount of
energy consumed by reducing the amount of lumen output. By using Visual 2012,
calculations were performed to ensure IES-recommended footcandles and ASHRAE 90.1
table 9.6.1 and ASHRAE 189.1 table 7.4.6.1B were met. Below is a table of the results.
ELECTRICAL
Table 5 Recommended
Footcandles
Calculated
Footcandles
Required LPD
(W/ft2)
Calculated
LPD (W/ft2)
Computer Room 30 35.1 1.71 0.4
Corridor 15 15.4 0.56 0.3
Large Classroom 35 35.2 1.05 0.4
Library 30-50 32.3 1.06 0.4
Lounge 20 22.4 0.62 0.4
Metal Shop 100 98.4 1.59 1.2
Office 30 37.1 1.05 0.4
Restroom 15 21.3 0.98 0.4
Small Classroom 35 45.1 1.05 0.8
Storage Room 15 17.9 0.63 0.3
Wood Shop 50 63.9 1.59 0.7
Sustainable Sites Water Efficiency Energy Efficiency IEQ Building’s Impact Construction
INTRO SITE ENCLOSURE PLANS MECHANICAL ELECTRICAL CONSTRUCTION LIFECYCLE
26
ELECTRICAL
CONTROL SYSTEM
Main Topics
Receptacle
Control
Occupancy Sensor
Photo Sensor
Automatic Receptacle and Lighting Control
In order to comply with ASHRAE 90.1 Sections 8.4, 9.4, and 10.4 a receptacle and
luminaire control system is being used. When using this system, an occupancy sensor and
photocell sensor work in tandem to reduce the amount of energy being consumed. A
photocell sensor communicates with the luminaries, to maintain a predetermined footcandle
level, taking into account both natural daylight entering the space as well as the light output
from the luminaires. The system can then dim the luminaires or shut them off completely in
order to maintain lighting levels while saving the most energy possible. After a
predetermined time of no occupancy, the occupancy sensor communicates with the relay
system which shuts off the power to the luminaires and designated outlets. For this system,
entire outlets or individual plugs can be chosen. The system itself also has a master timer.
This timer allows for entire design load circuits within the building to be shut off after the
hours of operation have passed. Override options exist with the master timer which will
sustain power to the circuits in the vicinity of the occupancy sensors detecting motion for an
additional two hours. This override can be triggered as many times as possible for late night
occupants. Figure 15 shows an example of how an office could be connected.
ELECTRICAL
Figure 15 - Control Diagram
Sustainable Sites Water Efficiency Energy Efficiency IEQ Building’s Impact Construction
INTRO SITE ENCLOSURE PLANS MECHANICAL ELECTRICAL CONSTRUCTION LIFECYCLE
27
MONITORING AND
DISTRIBUTION
Main Topics
Public Dashboard
Voltage Drop
Building Energy Consumption Management – Energy Dashboard
Using a “Building Dashboard”, the building will monitor in real time its energy usage and
consumption of all utilities. Per ASHRAE 90.1 Section 8.4 – 8.4.4, both renewable
electrical energy produced on site and grid-tied electrical usage entering and leaving the
building will be monitored utilizing the same dashboard system as the water consumption
equipment. The system will report daily, monthly and yearly electrical consumption per
floor and per large electrical usage systems such as HVAC, interior lighting, exterior
lighting and receptacles. Data collected will be stored on the network within the building
and will be accessible to the public on demand through a graphical interface in the main
lobby. This main public display kiosk not only allows for the education of the building
occupants but allows for the additional possibility of obtaining LEED V4 credit. The public
display of the energy dashboard will also allow for the building to act further as a living
laboratory for its students. This system will give students the ability to recognize where
issues with production and consumption are located within the building and could allow for
students to conduct experiments or adjust / fix the systems and have the results delivered to
them real time via the system extending the building as its own learning tool and class
exercise.
Electrical Distribution and Voltage Drop
Load calculations preformed for square footage and by space type, indicate that the
buildings primary transformer will be a triple rated 1000 kW transformer. This transformer
will be an integral part of a single ended substation located in the basement which will
distribute to each electrical room on each floor. The pieces of the substation will be placed
in the basement through an areaway on the south side of the building. Incoming power will
be provided primarily from utility service and will be supplemented with photovoltaic
panels back-fed to the utility utilizing a central inverter. Distribution will achieve limited
voltage drop by stacking electrical rooms and limiting feeder runs to the minimum length
possible. Per the NEC and ASHRAE 90.1 electrical voltage drop to equipment and
receptacles as well as the branch panels feeding them will be limited to three percent. This
will be accomplished by feeding electrical loads from two separate electrical closets. This
will allow all electrical circuits to be feed from an electrical panel board to its termination
point while staying within 150 lineal feet of wiring for a conventional 20 A circuits utilizing
number 12 wire. Larger wires will be used for larger circuits which also have a large run
length associated with them.
ELECTRICAL
Sustainable Sites Water Efficiency Energy Efficiency IEQ Building’s Impact Construction
INTRO SITE ENCLOSURE PLANS MECHANICAL ELECTRICAL CONSTRUCTION LIFECYCLE
28
PHOTOVOLTAICS
Photovoltaic Panels
As stated in the ASHRAE competition information 5% of the building’s annual usage will
be donated in their equivalent solar panel rating. Based on the procedure found in ASHRAE
189.1 Section 7.4.1.1, the minimum energy needed to be produced by the photovoltaic
system is determined by multiplying 10 kBTU by the gross roof area. Converting to kWh
this gives a minimum of 73,853 kWh annually. Solar irradiance data from NASA was used
to calculate the ideal angle to pitch the PV array. Utilizing this data and taking the average
recommended angles over the spring summer and fall months the optimum angle becomes
13.5 degrees. Utilizing Green Building Studio and 23,000 square feet of the roof area we are
able to provide a system rating of 230 kW that has the ability to produce 352,140 kWh
annually. This far exceeds the minimum requirement for ASHRAE. When compared to the
annual building usage of 547,878 kWh annually, the PV system is able to produce 64% of
the energy needed for the building. Utilizing Solarworld’s Sunfix Plus a variety of mounting
angles can be achieved. Each string will be combine into various combiner boxes placed on
the roof and then sent to a central inverter. The utility scale inverter will then monitor the
power, tying into the utility service and energy dashboard, together the dashboard and the
central inverter will work together to supply energy back to the grid or to the building loads
itself.
Emergency Power
The building will have a 500 kVA emergency natural gas generator for emergency lighting
and emergency systems such as fire alarm as well as the mechanical ventilation and cooling
load. The generator will be located in the basement and will be ventilated as well as
serviceable and removable through the areaway located on the south side of the building.
ELECTRICAL
Sustainable Sites Water Efficiency Energy Efficiency IEQ Building’s Impact Construction
Main Topics
Annual Energy
Consumption:
547,878 kWh
Annual PV
Production:
352,140 kWh
PV Provides 64%
of the Building’s
Energy Needs
13.5° Optimal
Angle
500kVa
Emergency
Generator
INTRO SITE ENCLOSURE PLANS MECHANICAL ELECTRICAL CONSTRUCTION LIFECYCLE
29
MAINTENANCE AND
FUTURE GROWTH
Main Topics
PV Cleaning
Adjustable PV
Angle
Possibilities for
Wind Energy
On-Site Renewable Energy Systems - Solar Array, Wind and Solar Hot water
To improve the efficiencies of the solar panels in this climate, given the possibilities of dust
storms and the resulting shading of the panels, a solar panel cleaning robot will be used. The
“Solarbrush” cleaning robot travels on top of the solar panels and cleans them by traveling
across the array. The only manual work that will be needed is to place the robot on the panel
array and to charge the
robot every 4 hours. This will eliminate the need to manually continually clean the array
and will improve the system efficiency. 920 PV panels will be installed.
There is ample room for walkways for serviceability of the equipment, even though there
are 920 PV panels and 5 solar evacuated hot water collector systems. Although this may
seem like a large quantity, there is still potential for future growth on both separate lower
roof levels for either the hot water collector or solar array panels.
As a future prospect, 4 wind turbines could be added to the site along the entrance drive to
further establish the entry way to the site and building. Upon research of the wind potential
in Education City wind turbines, specifically vertical axis wind turbines, is fair for
producing power. A quick analysis of a vertical axis turbine on a 15-foot pole indicates
roughly 2.3 kWh annually of production. A 4 turbine array would produce 9.2 kWh of
power annually and boost the overall efficiency by almost another percent to 91%. Although
this additional system would not majorly offset our annual electrical usage it would serve as
a learning opportunity for the students attending the technical institute.
ELECTRICAL
Sustainable Sites Water Efficiency Energy Efficiency IEQ Building’s Impact Construction
INTRO SITE ENCLOSURE PLANS MECHANICAL ELECTRICAL CONSTRUCTION LIFECYCLE
30
CONSTRUCTABILITY
Main Topics
Modular
Construction
Construction
Waste
Schedualing and
Time Savings
Modular units are the main structural component to this building. By building with modules,
the building will be more structurally sound. This is mostly due to the fact that each module
needs to be able to withstand the transportation and craning process.
Not only will the building be stronger, but the time of construction is cut nearly in half and
construction waste is significantly reduced. While modules are being produced, foundation
work can be conducted. Since each module is constructed in a controlled environment, there
is no delay caused by weather. Pre-designed modules can be modified to accommodate
mechanical and electrical systems throughout the building. This eliminates the need to drill
holes and cut openings to allow the systems to be distributed on each floor and reduces the
amount of construction waste. However, the waste produced form these modules is the
shrink wrap placed around each module to protect it during transportation, but this waste
can be recycled.
The site must first be excavated for the basement and the cistern. The basement slab and
walls will be placed using machinery but the cistern can be constructed by hand. The cistern
will be built out of a water proof membrane and filled with corrugated pipe that is small
enough to be carried by hand. Once built, its covered and the building slab is placed for the
modules.
To construct this building, trucks will be delivering modules to the site. Once located on the
site, modules are unwrapped and hooked up to the crane. The crane will then place each
module in its designated location. Once in place, the temporary structural installed for
shipping is then removed. As soon as each module is placed, interior construction can then
begin.
CONSTRUCTION
Sustainable Sites Water Efficiency Energy Efficiency IEQ Building’s Impact Construction
Figure 16 - Modular Construction Time Savings
INTRO SITE ENCLOSURE PLANS MECHANICAL ELECTRICAL CONSTRUCTION LIFECYCLE
31
CONSTRUCTION AND
CLOSING
Main Topics
Façade And Fiber
Optic Integration
PV Wiring
Project
Completion
Example Images
After all the modules have been placed, a qualified installer may install the horizontal solar
shading panels. This system depends on stainless steel construction attached to the exterior
of the concrete modules. The panels are small enough that a crane is not required to place
them. Once the solar shading of the second façade has been constructed, the solar optic light
collectors can then be installed. These collectors will be installed between the concrete
modules and the second façade. Fiber optic cables are then run through pre-molded holes in
the modules, and sent to the appropriate rooms.
When the roof has been installed, the PV modules can then be set in place. To install the PV
modules, racks need to be installed first. Next the PV modules can be mounted onto the
racks. After the modules are in installed, each modules is strung together, run to various
combiner boxes, and then connected to the central inverter. From the central inverter, the
conduit carries the power to the panel boards to power equipment in the building.
As per ASHRAE 189.1 section 10.3.1, all tests will be performed before building occupancy
occurs. All warranties, user manuals, maintenance plans, and service plans will also be
turned over to the owner. The maintenance plans would include the mechanical, electrical,
and the PV systems, as well as recommended green cleaning products for the interior of the
building surfaces.
CONSTRUCTION
Sustainable Sites Water Efficiency Energy Efficiency IEQ Building’s Impact Construction
Figure 17 - Installation of Precast Modules Example Figure 18 - Cistern Construction
INTRO SITE ENCLOSURE PLANS MECHANICAL ELECTRICAL CONSTRUCTION LIFECYCLE
32
LIFECYCLE ANALYSIS
Main Topics
Reduction of on
Site Work
Benefits of
Concrete
Tally® Life Cycle
Analysis
When building with modular units, approximately 80% of site construction is removed from
the site and is performed in the manufacturing plant. This significantly reduces the
disruption caused to the site and traffic in the area, as well as increasing site safety.
Concrete has a higher thermal mass and help lower energy costs. Also, concrete has a
natural resistance to fire, mold, and mildew. This lowers the amount of chemicals used in
the building, which in turn reduces the contribution to ozone depletion.
Although we are reducing our concrete construction waste significantly but using precast
modules, there will still be onsite recycling. We may be reducing concrete waste, but there
will still be plastic waste from the modules during transport, as well as inner building waste.
According to Tally, a life cycle analysis Revit plug-in, our building has potential to
contribute to global warming the most during operation. This also holds true for primary
energy demand. This means, out of the four categories, manufacturing, maintenance and
replacement, end of life, and operation, our building will make the most impact during its
longest stage, operation.
LIFECYCLE
Sustainable Sites Water Efficiency Energy Efficiency IEQ Building’s Impact Construction
Figure 19 - Lifecycle Analysis
INTRO SITE ENCLOSURE PLANS MECHANICAL ELECTRICAL CONSTRUCTION LIFECYCLE
33
BUILDING ENERGY
CONSUMPTION
Main Topics
55% Improvement
Over Baseline
Model
Reduction of 181
Tons of CO2 from
Baseline
PV Offsets
Approximately
213 Tons of CO2
Baseline Building Consumption : 999,516 kWh annually
Final Building Consumption after Design alterations : 547,878 kWh annually
45.2% Improvement from Baseline Building
PV System: 920 Panels, 230 kW system, 352,140 kWh Produced Annually
According the energy analysis software Green Building Studio the annual energy usage for
the building will be roughly 547,878 kWh annually. This roughly relates to 331 tons of CO2
when referencing natural gas. This energy consumption is a 45% reduction in annual energy
consumption thanks to the shading and green strategies that we have employed and that are
seen throughout this report.
To further offset the annual energy consumption a total of 920 panels totaling a 230 kW
system and yielding an estimated 352,140 kWh annually. Combining the savings in
consumption from both energy efficient design and from the solar array installed allows our
building to be 90% better than the baseline model of 999,516 kWh. To review more about
the solar panel system. Please review our alternative energy section as well as our
construction sections of this report.
LIFECYCLE
Sustainable Sites Water Efficiency Energy Efficiency IEQ Building’s Impact Construction
Figure 20 - Energy Usage
INTRO SITE ENCLOSURE PLANS MECHANICAL ELECTRICAL CONSTRUCTION LIFECYCLE
34
REFERENCES
"Architects." Architects. Web. 30 Apr. 2015. Armstrong. Web. 30 Apr. 2015. "ASHRAE Codes and Standards." Web. 3 May 2015. <https://www.ashrae.org/standards-
research--technology>. "Building Construction for Schools." Building Construction for Schools. Web. 30 Apr.
2015. "Climate Change Knowledge Portal 2.0." Climate Change Knowledge Portal 2.0. The
World Bank Group, n.d. Web. 08 Apr. 2015. "Colt Sonnenschutz - Bewegliche Klappläden Zur Fassadengestaltung, Lichtlenkung Und
Beschattung." Fassadengestaltung. N.p., n.d. Web. 30 Apr. 2015. "Commercial Bathroom." KOHLER. Web. 29 Apr. 2015. "DELTABEAM." DELTABEAM. N.p., n.d. Web. 30 Apr. 2015. "Donaldson Torit DCE." Donaldson Filters. N.p., n.d. Web. 30 Apr. 2015. "Degree Days.net - Custom Degree Day Data." Heating & Cooling Degree Days. N.p., n.d.
Web. 08 Apr. 2015. Kovessy, Peter. "Qatar Races to Desalinate, Store Water to Meet Nation's Growing Thirst -
Doha News." Doha News. N.p., 20 Mar. 2015. Web. 23 Apr. 2015. "Lutron Electronics, Inc. - Dimmers And Lighting Controls." Lutron Electronics, Inc. -
Dimmers And Lighting Controls. N.p., n.d. Web. 29 Apr. 2015. "Modular Construction." About Commercial Modular Construction. Web. 30 Apr. 2015. "NASA Surface Meteorology and Solar Energy - Location." NASA Surface Meteorology
and Solar Energy - Location. Web. 29 Apr. 2015. "Our Products." Parans. Web. 30 Apr. 2015. "Practicing Architecture." AIA RSS. Web. 30 Apr. 2015. "Professional Lighting Solutions." GE Lighting Europe. Web. 30 Apr. 2015. "Qatar Foundation | About." Qatar Foundation | About. Web. 30 Apr. 2015. "Qatar Solar." Qatar Solar. N.p., n.d. Web. 30 Apr. 2015. "RainSpace Stormwater Management Chambers." RainSpace Stormwater Management
Chambers. N.p., n.d. Web. 30 Apr. 2015. "Smarter Occupants Create Greener Buildings." Building Dashboard. Web. 29 Apr. 2015. "SOLARBRUSH - ROBOTS FOR CLEANER SOLAR ENERGY SOLARBRUSH. N.p.,
n.d. Web. 30 Apr. 2015. "Solar Shading Systems: Delivering Distinctive Architectural Impact and Cutting Energy
Use." Solar Shading. N.p., n.d. Web. 30 Apr. 2015. "Sunmodule Protect." SolarWorld : Sunmodule Plus. N.p., n.d. Web. 30 Apr. 2015. "Sun Position." Calculation of Sun’s Position in the Sky for Each Location on the Earth at
Any Time of Day. N.p., n.d. Web. 23 Apr. 2015. "VRV - Engineering Data Manuals." VRV Systems. N.p., n.d. Web. 30 Apr. 2015. Product Disclaimer There are specific products and brands mentioned in order to establish a basis of design. The
Sustainable Sites Water Efficiency Energy Efficiency IEQ Building’s Impact Construction