23376491-05-ag-piping.pdf

Upload: aston-martin

Post on 30-Oct-2015

21 views

Category:

Documents


0 download

DESCRIPTION

technical

TRANSCRIPT

  • LARSEN & TOUBRO LIMITEDPAGE NO.- 1 OF 19

    DATE:-01.11.2007MSQ (EPCC-1) UPGADATION PROJECT REV.NO.- 0

    PROCEDURE FOR AG PIPING FABRICATION & ERECTION

    PROCEDURE NO.-LT/MSQ/P/AG/005

    CONTENTS

    1.0 PURPOSE

    2.0 SCOPE

    3.1 STANDARD SPECIFICATIONS &

    NORMAL PRACTICE

    3.2 DEVIATION

    4.0 FABRICATION

    5.0 ERECTION

    6.0 PERFORMANCE OF WELDS & HEAT TREATMENT

    7.0 WELDING CONSUMBALES

    8.0 SHIELDING & PURGING GAS

    9.0 WELDING

    10.0 VISUAL INSPECTION

    11.0 REPAIRS OR REMOVAL OF DEFECT

    12.0 INSPECTION AND TESTING

    13.0 SAFETY

    14.0 DOCUMENTATION

    APPROVED BY L & T REVIEWED / APPROVED BY JACOBS

  • LARSEN & TOUBRO LIMITEDPAGE NO.- 2 OF 19

    DATE:-01.11.2007MSQ (EPCC-1) UPGADATION PROJECT REV.NO.- 0

    PROCEDURE FOR AG PIPING FABRICATION & ERECTION

    PROCEDURE NO.-LT/MSQ/P/AG/005

    1.0 PURPOSE:

    The purpose of this procedure is intended to cover the general requirements

    for the execution of piping, pre-fabrication, assembly and erection of the

    above ground pipe work at site.

    2.0 SCOPE:

    This procedure covers execution, inspection, testing, and method of record

    keeping for fabrication & erection of all above ground piping systems as per

    standard specification and normal practice.

    3.1 CONTROLLING SPECIFICATIONS:

    Approved PMCs standards and specifications Process and instrument diagram.

    Piping materials specification

    Pipe supports standards

    Line list.

    Job specification of non-destructive testing of piping as per Sec V &

    standard spec

    Welding specification for Fabrication of piping (3177-LSS-104)

    Standard specification for Inspection, flushing piping system (3177-

    LSS-106)

    Specification for inspection, flushing & testing of piping

    systems(3177-LSS-106)

    ASME B 31.3 Process Piping

    AME B 31.1 Power Piping

    APPROVED BY L & T REVIEWED / APPROVED BY JACOBS

  • LARSEN & TOUBRO LIMITEDPAGE NO.- 3 OF 19

    DATE:-01.11.2007MSQ (EPCC-1) UPGADATION PROJECT REV.NO.- 0

    PROCEDURE FOR AG PIPING FABRICATION & ERECTION

    PROCEDURE NO.-LT/MSQ/P/AG/005

    ASME Sec VIII code for Unfired Pressure Vessel

    IBR Regulations

    IS : 823 code for Procedure for Manual Metal Are Welding of Mild

    Steel ( For Structural Steel)

    Job specification for colour coding

    3.2 DEVIATIONS

    Where a deviation from the Basis of work and approved job procedure

    described above is required or where the basis of work does not cover a

    particular situation, the matter shall be brought to the notice of owner / PMC

    and work carried out only after obtaining written approval from him in each

    cases.

    4.0 FABRICATION:

    4.1 PIPING MATERIAL

    Pipe, pipefitting, flanges, valves, gaskets, studs bolts etc. used in a given

    piping system shall be strictly as per the Piping Material Specification for

    the Pipe Class specified for that system.

    For the purpose of common understanding the construction job procedure, to

    be submitted by L&T , shall include proposal for

    -Maximizing prefabrication, inspection and testing at fabrication shop with

    minimum field joints

    -Positive material identification, handling, storage & preservation.

    4.2 DIMENSIONAL TOLERANCES

    Dimensional tolerances for piping fabrication shall be as per standard no.

    3177-LSD-1017. To take care of minor variations in the actual location (at

    site) of equipments, inserts, structures etc., field welds shall be provided

    during piping fabrication and an extra length 100 mm & above the dimensions

    APPROVED BY L & T REVIEWED / APPROVED BY JACOBS

  • LARSEN & TOUBRO LIMITEDPAGE NO.- 4 OF 19

    DATE:-01.11.2007MSQ (EPCC-1) UPGADATION PROJECT REV.NO.- 0

    PROCEDURE FOR AG PIPING FABRICATION & ERECTION

    PROCEDURE NO.-LT/MSQ/P/AG/005

    indicated in the drawing may be left on one side of the pipe at each field

    welds.

    4.3 IBR PIPING

    The complete piping work shall be carried out as per Approved for

    Construction drawings and sketches. For piping falling under IBR, necessary

    approval of boiler inspector on the drawings shall be obtained prior to start of

    fabrication and all works shall be carried out as per the requirement of IBR.

    IBR approval to be taken on as built IBR Drg.

    Field welding of weld joint nearest the pumps shall be done only after

    pump and connected piping have been truly aligned.

    4.4 EDGE PREPARATION

    4.4.1 The edges to be welded shall be prepared to meet the joint design requirements by

    any of the following method recommended:

    a) Carbon Steel (C.S.)

    Gas cutting, Machining or grinding methods shall be used. After gas

    cutting, oxides shall be smoothened / removed by chipping and grinding.

    b) Low Alloy Steel (Containing up to 5% Cr)

    Gas cutting, Machining or grinding methods shall be used. After gas

    cutting, machining or grinding shall be carried out on the cut surface.

    c) High Alloy Steel (>5% Cr) & Stainless Steels (S.S), Nickel Alloys

    Plasma cutting, machining or grinding methods shall be used. After plasma

    cutting, cut surface shall be machined or ground smooth.

    4.4.2 SPACING

    )a For pipe wall thickness 5 mm and above, the ends to be welded shall secure

    APPROVED BY L & T REVIEWED / APPROVED BY JACOBS

  • LARSEN & TOUBRO LIMITEDPAGE NO.- 5 OF 19

    DATE:-01.11.2007MSQ (EPCC-1) UPGADATION PROJECT REV.NO.- 0

    PROCEDURE FOR AG PIPING FABRICATION & ERECTION

    PROCEDURE NO.-LT/MSQ/P/AG/005

    in position with the aid of couplers, yokes and C clamps, to maintain

    perfect alignment. Yokes shall be detached after the completion of weld,

    without causing any surface irregularity.

    )b Tacks should be equally spaced. Minimum number of tacks shall be:

    3 tacks - for 21/2 and smaller diameter pipes

    4 tacks - for 3 to 12 diameter pipes

    6 tacks - for 14 and larger diameter pipes

    4.4.3 All piping spools shall be marked / stamped for proper identification like as line no.,

    joints no., welder no., spool no.

    4.4.4 CLEANING

    )a The ends to be welded shall be properly cleaned to remove paint, oil,

    grease, rust, oxides, sand, earth and other foreign matter. The ends shall be

    completely dry before the welding.

    )b On completion of each run, craters, welding irregularities, slag etc., shall be

    removed by the grinding and chiselling. Separate grinding wheels and wire

    brushes should be used for Carbon steels & stainless Steel

    4.5 PIPE JOINTS

    The piping class of each line specifies the type of pipe joints to be adopted. In

    general, joining of line 2 and above in process and utility piping shall be

    accomplished by butt weld. Joining of lines 11/2 and below shall be by socket

    welding / butt welding / thread joints as specified in Piping Material

    Specification.

    Flange joints shall be used at connections to vessels, equipments, valves and

    where required ease of erection and maintenance as indicated in drawings.

    4.6 BUTT WELDED AND SOCKET WELDED PIPING

    Edge preparation, alignment and fit up of piece to be welded, welding, pre

    heating, post heating and heat treatment shall be as described in the welding

    APPROVED BY L & T REVIEWED / APPROVED BY JACOBS

  • LARSEN & TOUBRO LIMITEDPAGE NO.- 6 OF 19

    DATE:-01.11.2007MSQ (EPCC-1) UPGADATION PROJECT REV.NO.- 0

    PROCEDURE FOR AG PIPING FABRICATION & ERECTION

    PROCEDURE NO.-LT/MSQ/P/AG/005

    specification (3177-LSS-104) and NDT specification (18-3177-000-L-02-

    0703-A4).

    4.7 SCREWED PIPING

    In general, galvanized piping shall have threads as per IS: 554 or ANSI B 2.1

    NPT as required matching threads on fittings, valves etc. all other piping shall

    have threads as per ANSI B 2.1, tapered unless specified otherwise.

    4.8 FLANGE CONNETIONS

    All range facings shall be true and perpendicular to the axis of pipe to which

    they are attached. Flanged bolthholes shall straddle the normal centre lines

    unless different orientation is shown in drawing.

    4.9 BRANCH CONNECTIONS

    Branch connections shall be as indicated in the Piping Material Specifications

    for end preparation, alignment; spacing, fit up and welding of branch

    connections refer welding specifications. Templates shall be used wherever

    required to ensure accurate cutting and proper fit up.

    Reinforcement pads shall be provided wherever indicated in drawings /

    specifications / standard and codes etc.

    4.10 BENDING

    Bending of pipe shall be done as per ASME B31.3. Cold bend for lines 1

    and below, with a bend radius of 5 times the nominal diameter shall be used

    as required in place of elbows wherever allowed by piping specifications.

    Bending of pipes 2 and above may be required in some cases like that for

    headers, reactors etc.The competed bend shall have a smooth surface, free

    from cracks, buckles, wrinkles, bulges, flat spot and other serious defect.

    4.11 FORGING AND FORMING

    Forging and forming of small bore fittings like reducing for piping 1 and

    APPROVED BY L & T REVIEWED / APPROVED BY JACOBS

  • LARSEN & TOUBRO LIMITEDPAGE NO.- 7 OF 19

    DATE:-01.11.2007MSQ (EPCC-1) UPGADATION PROJECT REV.NO.- 0

    PROCEDURE FOR AG PIPING FABRICATION & ERECTION

    PROCEDURE NO.-LT/MSQ/P/AG/005

    below, shall be as per ASME B 31.3 / ASME B 31.1.

    4.12 MITRE BENDS AND FABRICATED REDUCERS

    Mitre bends and fabricated reducers shall be governed by the piping material

    specifications. Generally all 90 mitres shall be 4-piece 3-weld types and 45

    mitres shall be 3-piece 2-weld types unless otherwise specified. Reducers

    shall be fabricated as per directions of the PMC.The radiographic

    requirements shall be as per Material Specifications for process and utility

    systems and NDT specification for steam piping under IBR, radiographic

    requirement of IBR shall complied with.

    4.13 CUTTING AND TRIMMING OF STANDARD FITTINGS & PIPES

    Component likes pipes, elbows, couplings, half couplings etc shall be trimmed

    / edge prepared wherever required to meet fabrication and erection

    requirements, as per drawings and instructions of owner / PMC.

    4.14 GALVANISED PIPING

    Galvanised carbon steel piping shall be completely cold worked, so as not to

    damage galvanised surface. This piping involves only threaded joints and

    additional external threading on pipes may be required to be done as per

    requirement. However threading after galvanising should be minimum.

    4.15 JACKETED PIPING

    The jacking shall be done in accordance with approved PMCs or licensors

    approved specification as suggested in Piping Material Specification. Position

    of jump over and nozzles on the Jacket pipes, fittings etc. shall be marked

    according to pipe disposition and those shall be prefabricated to avoid

    damaging of inner pipe and obstruction of Jacket space.

    4.16 SHOP FABRICATION / PREFABRICATION

    The purpose of Shop fabrication or prefabrication is to minimise work during

    APPROVED BY L & T REVIEWED / APPROVED BY JACOBS

  • LARSEN & TOUBRO LIMITEDPAGE NO.- 8 OF 19

    DATE:-01.11.2007MSQ (EPCC-1) UPGADATION PROJECT REV.NO.- 0

    PROCEDURE FOR AG PIPING FABRICATION & ERECTION

    PROCEDURE NO.-LT/MSQ/P/AG/005

    erection to the extent possible. Piping spool after fabrication shall be stacked

    with proper identification marks, so as to facilitate their withdrawal at any

    time erection. During the period all flange (gasket contact faces) and threads

    shall be adequately fabricated by coating with removable rust preventive. Care

    shall also be taken to avoid any physical damage to flange faces and threads.

    4.17 ALIGNMENT

    The pipes to be jointed by welding shall be aligned correctly with existing

    tolerances on diameters, wall thickness and out of roundness and weld gaps.

    The same alignment shall be preserved during welding.

    4.18 LAYOUT, CUTTING & FITTING UP

    )c For laying out headers, tees, laterals and other irregular details, cutting

    template shall be used to ensure accurate cutting and proper fit up.

    )d All cutting shall follow the outline of the templates.

    )e Machine cut bevels to form the welding groove are preferred in carbon

    steel pipe. However, smooth, clean, slag free flame cut bevels is

    acceptable.

    )f Tack welds with full penetration shall be used and shall become the part of

    the finished weld and shall be carried out by qualified welders only.

    )g Defective welds or tack welds with lack of penetration are not acceptable

    and shall be chipped / ground out.

    )h No temporary weld attachment shall be with extended clamps / attachment.

    4.19 CLEANNING OF PIPING

    )a On completion of fabrication, all pipes and fittings shall be cleaned inside

    and outside by suitable means (Mechanical, cleaning tool, wire brush, etc.)

    before erection to ensure that assembly is free from all loosed foreign

    material such as scale, sand, weld, spatter particle, cutting chips etc.

    )b All field fabricated piping shall also be cleaned at the competition of the

    APPROVED BY L & T REVIEWED / APPROVED BY JACOBS

  • LARSEN & TOUBRO LIMITEDPAGE NO.- 9 OF 19

    DATE:-01.11.2007MSQ (EPCC-1) UPGADATION PROJECT REV.NO.- 0

    PROCEDURE FOR AG PIPING FABRICATION & ERECTION

    PROCEDURE NO.-LT/MSQ/P/AG/005

    fabrication. All burrs, welding circles and weld spatters shall be removed

    by any suitable means (Mechanical tools, wire, brush, etc.)

    )c Both shop and field fabricated piping shall be blown out with compressed

    air at the terminated specification of cleannning and capped.

    )d Cleaning requirements for special services, if any, shall be as specified in

    the piping material specifications.

    )e S.S. jacketed piping requiring picking shall be pickled to remove oxidation

    and discolouring due to welding.

    5.0 ERECTION

    5.1 PIPING ROUTING

    Pipe to pipe, pipe to structure / equipments distances / clearance as shown the

    drawings shall be strictly followed as these clearance may be required for the

    expansion of piping / equipment.

    5.2 COLD PULL

    Wherever cold pull is specified, maintain the necessary gap, as indicated in

    the drawing. Stress reliving shall be performed before removing the gadgets

    for old pulling.

    5.3 SLOPES

    Slopes specified for various lines in the drawings / P&ID shall be maintained

    during erection of piping spools.

    5.4 EXPANSION JOINTS / BELLOWS

    5.4.1 Installation of Expansion joints / Bellows shall be installed in accordance with the

    specification and installation drawings.

    5.4.2 Each expansion joints / bellows shall be blown free of dust / foreign matter with

    compressed air or cleaned with a piece of cloth.

    5.4.3 a) For handling and installation of expansion joints, great care shall be taken while

    aligning. An expansion joints shall never be slinged from bellows

    APPROVED BY L & T REVIEWED / APPROVED BY JACOBS

  • LARSEN & TOUBRO LIMITEDPAGE NO.- 10 OF 19

    DATE:-01.11.2007MSQ (EPCC-1) UPGADATION PROJECT REV.NO.- 0

    PROCEDURE FOR AG PIPING FABRICATION & ERECTION

    PROCEDURE NO.-LT/MSQ/P/AG/005

    corrugations / external shrouds, tie-rods, and angles.

    b) An expansion joints / bellows shall preferably be slinged from the end pipes /

    flanges or on the middle pipe.

    5.4.4 a) All expansion joint shall be procured at Installation length, maintained by means

    of shipping rods, angles welded to the flanges or weld ends or by wooden or

    metallic stops.

    b) Expansion joints stop blocks shall be carefully removed after hydrostatic

    testing. Angles welded to the flanges or weld ends shall be trimmed by saw as

    per manufactures instructions and the flanges or weld ends shall be ground

    smooth.

    5.4.5 a) The pipe end sin which the expansions joints is to be installed shall be perfectly

    aligned or shall have specified lateral deflection as noted on the relevant

    drawings.

    b) The pipes ends / flanges shall be spaced at a distance specified in the

    drawings.

    5.4.6 The expansion joints shall be placed between the mating pipe ends / flanges and shall

    be tack welded / bolted. The mating pipes shall again be checked for correct

    alignment.

    5.4.7 Butt-welding shall be carried out at each end of the expansion joint. For flanged

    expansion joints the mating flanges shall be bolted.

    5.4.8 After the expansion joint is installed and shall ensure that the mating pipes and

    expansion joints are in correct alignment and that the pipes are well supported

    and guided.

    5.4.9 The expansion joint shall not have any lateral deflection.

    5.4.10 Precautions

    1) For carrying out welding, earthing lead shall not be attached with the

    expansion joint.

    APPROVED BY L & T REVIEWED / APPROVED BY JACOBS

  • LARSEN & TOUBRO LIMITEDPAGE NO.- 11 OF 19

    DATE:-01.11.2007MSQ (EPCC-1) UPGADATION PROJECT REV.NO.- 0

    PROCEDURE FOR AG PIPING FABRICATION & ERECTION

    PROCEDURE NO.-LT/MSQ/P/AG/005

    2) The expansion bellow shall be protected from arc welds spot and

    welding spatter.

    3) Hydrostatic testing of the system having expansion joints shall be

    performed with shipping lugs in position. These lugs shall be removed

    after testing and certification is over.

    5.5 FLANGE CONNECTIONS

    While fitting up mating flanges, care shall be exercised to properly align he

    pipes and to check the flanges for trueness, so that faces of the flanges can be

    pulled together, without inducing any stresses in the pipes and equipment

    nozzles. Extra care shall be taken for flange connections to pumps, turbines,

    compressors, cold boxes, air coolers etc. the flange connections to these

    equipments shall be checked for misalignment, excessive gap etc. after the

    final alignment of the equipment is over. The welding of flange shall be done

    only after proper alignment of terminal equipment.

    Temporary protective covers shall be retained on all flange connections of

    pumps, turbines, compressors and other similar equipments, until the piping is

    finally connected, so as to avoid any foreign material from entering these

    equipments.

    The assembly of a flange joint shall be done in such a way that the gasket

    between these flanges is uniformly compressed. To achieve this bolt shall be

    tightened in a proper sequence.

    5.6 VENTS AND DRAINS

    High point vents and low point shall be provided as shown in the drawings.

    The details of vents and drains shall be as per piping material specifications /

    jobs standards.

    5.7 VALVES

    Valves shall be installed with spindle / actuator orientation as shown in the

    APPROVED BY L & T REVIEWED / APPROVED BY JACOBS

  • LARSEN & TOUBRO LIMITEDPAGE NO.- 12 OF 19

    DATE:-01.11.2007MSQ (EPCC-1) UPGADATION PROJECT REV.NO.- 0

    PROCEDURE FOR AG PIPING FABRICATION & ERECTION

    PROCEDURE NO.-LT/MSQ/P/AG/005

    layout drawings. Care shall be exercised to ensure that globe valves, check

    valves, and other unidirectional valves are installed with the Flow direction

    arrow on the valve body pointing in the correct direction. If the direction of

    the arrow is not marked on such valves this shall be done in presence of

    Engineer-In-Charge.

    5.8 INSTRUMENTS

    Installation of in-line instruments such as restriction orifices, control valves,

    safety valves, relief valves, rotameter, orifice flange assembly, venturi meters,

    flow meters etc. shall form a part of piping erection work.

    Fabrication and erection of piping up to first block valve / nozzle / flange for

    installation of offline instruments for measurement of level, pressure,

    temperature, flow, etc. shall also form part of piping construction work. The

    limits of piping and instrumentation work will be shown in drawing / standard

    / specifications. Orientations / locations of take-offs for temperature, pressure,

    flow level connections etc. shown in drawing shall be maintained

    Flushing and testing of piping systems which include instruments mentioned

    above and the precautions to be taken are covered in flushing, testing, and

    inspection of piping (3177-LSS-106). Care shall be exercised and adequate

    precautions taken to avoid damage and entry of foreign matter into

    instruments during transportation, installation, testing etc.

    5.9 LINE MOUNTED EQUIPMENTS / ITEMS

    Installation of line mounted items like filters, strainers, steam traps, air traps,

    desuperheaters, ejector, sample coolers, mixers, flame arrestors, sight glasses

    etc. including their supporting arrangement their supporting arrangements

    shall form part of piping erection work.

    5.10 BOLTS AND NUTS

    M/s L & T shall apply molycoat grease mixed with graphite powder (unless

    APPROVED BY L & T REVIEWED / APPROVED BY JACOBS

  • LARSEN & TOUBRO LIMITEDPAGE NO.- 13 OF 19

    DATE:-01.11.2007MSQ (EPCC-1) UPGADATION PROJECT REV.NO.- 0

    PROCEDURE FOR AG PIPING FABRICATION & ERECTION

    PROCEDURE NO.-LT/MSQ/P/AG/005

    otherwise specified in piping classes) all bolts and nuts during storage, after

    erection and wherever flange connections are broken and made-up for any

    purpose whatsoever. M/s L & T shall supply he grease and graphite powder

    without price implication to owner. However wherever bolt tensioning is

    called for the lubricants used shall be as per the bolt tensioning specification

    duly reviewed by PMC.

    5.11 PIPE SUPPORTS

    Pipe supports are designed and located to effectively sustain the weight and

    thermal effects of he piping system and to prevent its vibrations. Location and

    design of pipes supports will be shown in drawings for lines of all sizes. All

    supports provided should be as per the location and type considered during the

    approval of stress analysis reports. If any change of route is to be done, stress

    analysis to be done before carrying out site changes. This is applicable for the

    pipelines identified for stress analysis, for rest of the pipelines; supports

    should be as per drawing.

    No pipe shoe / cradle shall be offset unless specifically shown in the

    drawings.

    Hanger rods shall be installed inclined in a direction opposite to the direction

    in which the pipe moves during expansion.

    Preset rods shall be installed inclined in a direction opposite to the direction in

    which the pipe moves during expansion.

    Preset lock pins of all spring supports shall be removed only after hydrostatic

    testing and insulation is over. The following points shall be checked after

    installation by designer & consultant with the PMC and necessary

    confirmation in writing shall be given certifying that:

    All restrains have been installed correctly.

    Clearances have been maintained as per support drawings

    APPROVED BY L & T REVIEWED / APPROVED BY JACOBS

  • LARSEN & TOUBRO LIMITEDPAGE NO.- 14 OF 19

    DATE:-01.11.2007MSQ (EPCC-1) UPGADATION PROJECT REV.NO.- 0

    PROCEDURE FOR AG PIPING FABRICATION & ERECTION

    PROCEDURE NO.-LT/MSQ/P/AG/005

    Insulation does not restrict thermal expansion

    All temporary tack welds provided during have been fully removed.

    All welded supports have been fully welded.

    Where practicable and except when otherwise shown on the drawings, valve

    stems shall be installed in a vertical direction and shall not be installed with

    below the horizontal axis.

    6.0 PERFORMANCE OF WELDS & HEAT TREATMENT

    6.1 PREHEATING

    a) No welding shall be performed by without preheating the joint 100C when

    the ambient temperature is below 100C.

    b) Preheat will be applied with minimum as specified in welding chart.

    c) Preheating shall be performed using resistance or induction methods.

    Preheating by gas burners, utilising oxy-acetylene or oxy-propane gas

    mixture.

    d) Preheating shall extend uniformly to at least three times the thickness of the

    joint, but not less than 50 mm, on both sides of weld.

    e) Preheating temperature shall be maintained over the whole length of joint

    during welding.

    6.2 POST WELD HEAT TREATMENT

    a) Post weld heat treatment, wherever required for joints between pipes, pipes

    and fittings, pipe body and supports shall be carried out as per welding

    specification chart.

    b) Post weld heat treatment shall be done in a furnace or by using electric

    resistance or induction heating equipment.

    All welding consumable such as electrodes, filler wires, flux and gas shall

    be stored, handled and use in accordance with the manufacturers

    instructions.

    APPROVED BY L & T REVIEWED / APPROVED BY JACOBS

  • LARSEN & TOUBRO LIMITEDPAGE NO.- 15 OF 19

    DATE:-01.11.2007MSQ (EPCC-1) UPGADATION PROJECT REV.NO.- 0

    PROCEDURE FOR AG PIPING FABRICATION & ERECTION

    PROCEDURE NO.-LT/MSQ/P/AG/005

    7.0 WELDING CONSUMBALES

    7.1 The welding electrodes and filler wires used shall be as per approved WPS/ welding

    specification chart and B.T.C. of electrode / filler wire shall be submitted to

    Jacobs for approval.

    7.2 All electrodes shall purchased in sealed containers and stored properly to prevent

    deterioration. The electrode removed from containers shall be kept in holding

    ovens at temperatures recommended by the electrode manufacture. The

    electrode shall handled with care to avoid any damage to the flux covering.

    7.3 All low hydrogen type of electrodes shall be rebaked at 3500C for 1 hours minimum and

    stored in ovens kept at 80-1000C before use.

    7.4 The electrodes, filler wires and flux used shall be free from rust oil, grease, earth and

    other foreign matter, which affect the quality of welding.

    7.5 Tungsten electrodes used shall conform to ASME Sec. II C SFA 5.12 specification.

    7.6 Only Owner/ PMC approved brands of electrodes shall be used.

    8.0 SHIELDING & PURGING GAS:

    8.1 Argon gas with a purity level of 99.995% shall be used for purging.

    8.2 The purging shall be maintained during the root pass and for the first filling pass to

    minimise oxidation on the inner side of the pipe, unless otherwise specified in

    Welding Specification Chart.

    8.3 Initial purging shall be maintained for sufficient period of time so that at least 4-5 times

    the volume between the dams is displaced in order to completely remove the

    entrapped air.

    8.4 Dams, used for conserving inert gas during purging, shall be removed after competition

    of the welding, and shall be accounted for. Wherever, removal of dams is no

    possible after welding, use of watersoluble dams should be made.

    9.0 WELDING

    a) Qualified welders as per approved WPS, welding specification chart and

    APPROVED BY L & T REVIEWED / APPROVED BY JACOBS

  • LARSEN & TOUBRO LIMITEDPAGE NO.- 16 OF 19

    DATE:-01.11.2007MSQ (EPCC-1) UPGADATION PROJECT REV.NO.- 0

    PROCEDURE FOR AG PIPING FABRICATION & ERECTION

    PROCEDURE NO.-LT/MSQ/P/AG/005

    approved drgs, shall carry out all welding.

    b) Welding technique / process followed during welding shall be as per

    approved WPS.

    10.0 VISUAL INSPECTION

    Inspection of all welds shall carried out as per ANSI B 31.3 and specification.

    Finished welds shall be visually inspected for parallel and axial misalignment

    of the work, crack. Inadequate penetration, unrepaired burn-through,

    dimensions, and other surface defects, and it shall present a neat workman like

    appearance. Under cutting adjacent to the final bead on the outside of the pipe

    shall not exceed 0.8 mm in depth of 121/2% of the pipe wall thickness,

    whichever us smaller and the cumulative length shall not be more than 50 mm

    in any continuous 300 mm length or weld.

    11.0 REPAIRS OR REMOVAL OF DEFECT

    Defects, which are not within the acceptable limits, shall be removed from the

    joint completely by chipping or grinding.

    When the whole joint us found unacceptable, the weld and the ends of the

    joints shall be restored according to relevant under fabrication.

    No repair shall be carried out without prior authorisation of the PMC.

    12.0 INSPECTION AND TESTING

    12.1.1 All NDT works like as RT, DPT, and MPT, UT etc.shall be

    carried out by experienced/qualified personnel as per approved job

    procedures.

    12.1.2 The application of above NDT for welding shall be as per

    inspection class mentioned in NDT specification no. 18-3177-000-l-02-0703-

    A4 & approved L&T doc. No.-L&T/MSQ/NDT.SPEC/001

    12.1.3 Welding repairs are unavoidable made on PWHT, and then

    complete PWHT cycle must be repeated with a second heat chart.

    APPROVED BY L & T REVIEWED / APPROVED BY JACOBS

  • LARSEN & TOUBRO LIMITEDPAGE NO.- 17 OF 19

    DATE:-01.11.2007MSQ (EPCC-1) UPGADATION PROJECT REV.NO.- 0

    PROCEDURE FOR AG PIPING FABRICATION & ERECTION

    PROCEDURE NO.-LT/MSQ/P/AG/005

    12.1.4 After PWHT the hardness value on the weld, HAZ and parent

    metal shall be measured both using Poldi type or portable hardness instrument

    wherever PWHT is applicable and hardness requirement shall be as per

    welding specification chart.

    12.1.5 The field Hydro-test pressure shall not be less than the greatest

    of the following:

    11/2 times the maximum sustained operating pressure

    11/2 times the maximum pipeline static pressure

    Sum of the maximum sustained pressure or the maximum pipeline static

    pressure and the maximum calculated surge pressure.

    - the field test pressure shall wherever possible be not less than two

    thirds of the works test pressure and shall be applied and maintained for at

    least four hours.

    - Where he field test pressure is less than two-thirds the works test

    pressure, the period of test shall be increased to at least 24 hours. The test

    pressure shall be gradually raised at the rate of nearly 1.0 kg/cm2/minute.

    12.1.6 All above ground pipes shall be tested for leakages to a

    minimum hydrostatic test pressure of 10 kg/cm2gauge or as per specification.

    12.1.7 The joints of the pipe connecting the testing sections shall be

    100% radiographed.

    12.1.8 TEST MEDIUM

    Construction water shall be generally be used as the testing medium for the

    hydrostatic testing of Piping system.

    12.1.9 CLEANING / FLUSHING

    All system shall be cleaned and flushed free of all dirt, debris or loose foreign

    material after testing.

    12.1.10 TEMPORARY BLINDS

    APPROVED BY L & T REVIEWED / APPROVED BY JACOBS

  • LARSEN & TOUBRO LIMITEDPAGE NO.- 18 OF 19

    DATE:-01.11.2007MSQ (EPCC-1) UPGADATION PROJECT REV.NO.- 0

    PROCEDURE FOR AG PIPING FABRICATION & ERECTION

    PROCEDURE NO.-LT/MSQ/P/AG/005

    Open ends of piping systems such as at pumps or wherever equipment has

    been removed or disconnected prior to hydrostatic testing, or at termination

    point of piping branch connections shall be blinded off by temporary blind

    flange made out of minimum 10 mm hick MS plate.

    12.1.11 VENTING

    All piping systems and equipments shall be properly vented to remove air

    from system during filling or as shown in the drawings.

    12.1.12 PRESSURISING

    Pressure shall be applied by means of suitable test pump, which shall not be

    connected to the system until ready to test. A pressure gauge duly calibrated

    shall be provided at the pump discharge for guidance in bringing the system

    upto pressure. An authorised operator shall attend the pump constantly during

    the test. The pump shall be disconnected after the pressure test is completed.

    The test pressure is to be maintained for sufficient time to permit compete

    inspection of the system under test but in no case shall the time be less than

    ten minutes.

    12.1.13 TEST GAUGES

    Test gauge shall be installed as close as possible to the lowest point in the

    system being tested. Prior to installation, the test gauge shall be checked

    against standard gauge or calibrated with the aid of a dead weight tester.

    12.1.14 DRAINING

    All lines and equipments shall be completely drained after the hydrostatic test

    of a system has been completed. High point vents shall be open prevent

    excessive vacuum and permit complete draining.

    13.0 SAFETY

    13.1 All safe measures shall be observed in welding and cutting and required PPE shall be

    enforced to the job performer.

    APPROVED BY L & T REVIEWED / APPROVED BY JACOBS

  • LARSEN & TOUBRO LIMITEDPAGE NO.- 19 OF 19

    DATE:-01.11.2007MSQ (EPCC-1) UPGADATION PROJECT REV.NO.- 0

    PROCEDURE FOR AG PIPING FABRICATION & ERECTION

    PROCEDURE NO.-LT/MSQ/P/AG/005

    13.2 All Safety & regulatory practices during performance of Radiography work shall be

    observed particularly personal protection from radiation either by distance, or

    time or, shielding, or a suitable combination of all three.

    13.3 During Radiography, also Radiation warning signal either visual or sound or both

    shall be put to keep the unconnected people away to avoid any exposure.

    13.4 During Hydrostatic or Pneumatic testing, people shall be warned by deploying danger

    signal and cordoning the area to avoid any accidental injury.

    14.0 DOCUMENTATION

    All documents shall be prepared and maintained as per approved ITP No. : -

    LT/MSQ/ITP/PIPE/AG/002 Rev. 0 and applicable approved formats as per

    ITP.

    APPROVED BY L & T REVIEWED / APPROVED BY JACOBS

    3.1 CONTROLLING SPECIFICATIONS: