LARSEN & TOUBRO LIMITEDPAGE NO.- 1 OF 5
DATE:-03.11.07
MSQ (EPCC-1) UPGADATION
PROJECT REV.NO.- 0
PROCEDURE FOR POST WELD HEAT
TREATMENT
PROCEDURE NO.-LT/MSQ/P/PWHT/010
CONTENTS:
1.0 PURPOSE
2.0 REFERENCE DOCUMENT
3.0 PWHT
4.0 EQUIPMENTS MATERIALS
5.0 INSPECTION
6.0 SAFETY
APPROVED BY L & T REVIEWED / APPROVED BY JACOBS
-
7/27/2019 23376514-10-PROCEDURE-FOR-PWHT.pdf
2/5
LARSEN & TOUBRO LIMITEDPAGE NO.- 2 OF 5
DATE:-03.11.07
MSQ (EPCC-1) UPGADATION
PROJECT REV.NO.- 0
PROCEDURE FOR POST WELD HEAT
TREATMENT
PROCEDURE NO.-LT/MSQ/P/PWHT/010
1.0 PURPOSE:
This procedure provides information; method and control for Post Weld Heat
Treatment (PWHT) of AG/UG piping at IOCL Panipat Refinery MSQ Project.
2.0 REFERENCE DOCUMENT:
ASME B 31.3 (Latest revision)
ABS Spec. SW-231 Approved WPS
Approved Welding specification charts
3.0 POST WELD HEAT TREATMENT (PWHT)
3.1 The Heat Treatment is performed by electrical resistance heating coils or by induction.
Heating elements of NI-Cr wire of suitable gauge, insulated with porcelain beads, shall
be wrapped all round the weld portion and heated electrically. The method is by
locally heating a circumferential band including the entire weld and adjacent area of
base metal.
3.2 Heating elements are wrapped with an overlap of 75mm either side of weld with
sufficient mineral wool to shield the heat. Heat is controlled by varying the electrical
energy manually and / or using timer control. Width of the heating band shall be six
times the wall thickness of thickest part for girth butt welds.
3.3 Width of the insulation shall be 12 times the thickness of thickest part.
3.4 Care shall be taken so that exposed pipe surface temperature shall not exceed 50% of
the peak temperature or 400 C whichever is minimum.
3.5 Weld joints shall be free from grease, oil, etc. prior to PWHT.
3.6 Before PWHT, Line No. & Joint No., dia, type of joint, Recorder No., Calibration
date, Starting time and date etc. shall be written on the SR chart, duly signed and
sealed by L&T QC Engineer. After completion of PWHT , recorders shall be opened
presence of L&T QC Engineer and charts verified with joints for PWHT.
3.7 PWHT shall be carried out at a temperature range as given below.
APPROVED BY L & T REVIEWED / APPROVED BY JACOBS
-
7/27/2019 23376514-10-PROCEDURE-FOR-PWHT.pdf
3/5
LARSEN & TOUBRO LIMITEDPAGE NO.- 3 OF 5
DATE:-03.11.07
MSQ (EPCC-1) UPGADATION
PROJECT REV.NO.- 0
PROCEDURE FOR POST WELD HEAT
TREATMENT
PROCEDURE NO.-LT/MSQ/P/PWHT/010
Description To be Followed at site Requirement as per ASME B 31.3
Heating Rate 150 10 200 C / Hr Max.
Cooling Rate 150 10 200 C / Hr Max.
Holding Temperature 620 10 593 C to 649 C
Holding Time1 hr / 25mm
(Minimum 1hr)1 hr / 25mm (Minimum 1hr)
3.8 HEATING AND COOLING RATES
3.8.1 Heating and cooling rate shall be as per 3.7 above.
3.8.2 Whenever not specified, the heating rate above 300 C, and cooling rate after soaking
up to 300 C , shall be followed.
3.8.3 Controlled heating shall be started from 300 C and controlled cooling shall be up to
300 C
3.8.4 Corrective action should be adopted during power interruption and shall be decided on
case to case basis.
3.8.5 HOLDING TIME
3.8.6 Holding / Soaking time shall be as per 3.7 above.
3.8.7 The following guidelines shall be used to determine the thickness and subsequent
selection of the soaking time of PWHT.
For butt welds, the thickness shall be the thickness of the material at the weld.
For fillet welds, the thickness shall be the throat thickness.
For branch welds, the thickness shall be governed as per relevant clauses of B
31.3 For combination of different welds in a component, the maximum in the
definition given above shall govern.
3.9 HARDNESS TEST
3.9.1 Maximum hardness value of welds after PWHT shall be as per specification.
APPROVED BY L & T REVIEWED / APPROVED BY JACOBS
-
7/27/2019 23376514-10-PROCEDURE-FOR-PWHT.pdf
4/5
LARSEN & TOUBRO LIMITEDPAGE NO.- 4 OF 5
DATE:-03.11.07
MSQ (EPCC-1) UPGADATION
PROJECT REV.NO.- 0
PROCEDURE FOR POST WELD HEAT
TREATMENT
PROCEDURE NO.-LT/MSQ/P/PWHT/010
3.9.2 Hardness testing shall be carried out using Portable Telebrinell / Poldi / or any PMC
approved harness tester.
3.9.3 Whenever hardness value is more than 200 BHN, re-PWHT shall be carried out as per
this procedure.
3.9.4 Hardness Value after PWHT shall be recorded for each weld in the approved format.
LT/PNCP/AU/PWHT-HARD/006
3.9.5 One hardness test per weld shall be performed on weld metal and Heat affected zone.
3.10 NUMBER OF THERMOCOUPLES
SIZE OF PIPENO OF
THERMOCOUPLES
POSITION OF
THERMOCOUPLES
Up to 4 dia One Bottom
Above 4 8 dia Two Top and bottom (180 apart)
Above 8 24 dia Three 120 apart
Above 24 dia Four 90 apart
4.0 EQUIPEMENTS / MATERIALS
4.1 TEMPERATURE RECORDERS
The recorders shall be six-pointer suitable for 1000C & 1200C range, having
continuous recording chart having copper lead with colour dots. Each recording
instrument will give information and immediate indication of a thermocouple open
circuit condition. Calibration certificate for each recorder shall be available for review.
Revalidation of calibration shall be carried out at site once in every 6 months.
4.2 TEMPERATURE CONTROL SYSTEMThe temperature control system shall guarantee a post weld heat treatment within the
limits of the specification.
4.3 THERMOCOUPLES EXTENSION CABLE
Copper constantan compensating cables shall be used. The Copper lead (+ve) shall be
connected to the Chromel Conductor (non-magnetic) and the Nickel Lead (-ve) shall
be connected to the Alumel Conductor (magnetic)
APPROVED BY L & T REVIEWED / APPROVED BY JACOBS
-
7/27/2019 23376514-10-PROCEDURE-FOR-PWHT.pdf
5/5
LARSEN & TOUBRO LIMITEDPAGE NO.- 5 OF 5
DATE:-03.11.07
MSQ (EPCC-1) UPGADATION
PROJECT REV.NO.- 0
PROCEDURE FOR POST WELD HEAT
TREATMENT
PROCEDURE NO.-LT/MSQ/P/PWHT/010
4.4 THERMAL INSULATION
The insulation consists of mineral wool, wrapped around heating elements. The
insulation shall extend a minimum distance of 150mm beyond the outer edges of
heated band. The total insulation covering will be such as to provide minimum heat
loss.
4.5 THERCOUPLE
All thermocouples shall be of the Chromel Vs. Alumel type, type K . thermocouples
shall be fixed using Capacitor discharge Method. Calibration reports of thermocouples
shall be submitted for review prior to start of work.
5.0 INSPECTION & DOCEMENTATION
Documents shall be maintained in format No. LT/MSQ/PWHT-HARD/024
6.0 SAFETY
All safety precautions shall be taken as per safety requirements of the project. Proper
permit shall be obtained as required, prior to start of job.