35 kw load bank installation - multiquip inc · 35 kw load bank installation ... 13 dc control...

16
DCA125SSJU4i — LOAD BANK INSTRUCTIONS P/N EE58886 — REV. #0 (09/14/15) — PAGE 1 DCA125SSJU4i 35 kW Load Bank Installation The following instructions are intended to assist the user in the installation of the 35 kW Load Bank for use on the DCA125SSJU4i generators. Please read all assembly instructions before installing load bank. REQUIRED TOOLS PARTS Verify that all parts are accounted for. See Figure 1 and Table 1. Figure 1. Power Balance Kit (DCA125SSJU4i) WORK SAFELY! Only a qualified service technician with proper training should perform this installation. Follow all shop safety rules when performing this installation. PREPARATION 1. Make sure generator is turned off and engine is cool. A1 A2 A3 A4 A5 A6 A12 A11 A10 A9 A8 A7 R1 R2 R3 R4 R5 R6 R12 R11 A10 R9 R8 R7 PATENT PENDING Engine Started Shutdown Pre-Alarm Series 800 Controller Alarm Acknowledge Screen Change Program/ Exit Option ECU HARDWARE INSTRUCTIONS 22 18 37 17 16 20 21 19 36 35 34 28 27 25 26 15 23 24 9 10 8 7 11 12 14 13 1 6 3 2 3 4 5 38 29 30 31 33 32 Ratchet Set Flat/Phillips Screwdrivers Wire Cutters Power Drill 2-Inch Chassis Punch 2. Place the generator in an area free of dirt and debris. Make sure it is on secure level ground with chock blocks underneath each wheel to prevent the generator from rolling. Table 1. Power Balance Kit Item No. Part No. Description QTY. Remarks 1 MQP- PB125J4i KIT, POWER BALANCE, 35kW 1 Includes Items 2-38 2 EE58500 Cover, Roof, 35 kW Resistor 1 3 EE58362 Cover Plate, 2-Row Resistor 2 4 1/4-20 Rivet-Nut 4 5 EE58708 Bracket Bottom, Contactor Box 12"X14" 1 6 EE58707 Bracket Top, Contactor Box 12"X14" 1 7 EE58501 Resistor Assy., 35 kW 1 8 EE58673 2" Rubber Grommet 1 9 Load Bank Split Loom, 3/4" X 114" 126" Included With #10 10 EE58704 Load Bank Wire Harness, 8 AWG. 1 7 Wires 11 EE58868 Power Wires (UVW/4 AWG) GND/8 AWG. 1 4 Wires 12 UVW-GND Split Loom, 1.0" X 54" 1 Included With #11 13 DC Control Split, Loom, 3/8" X 54" 1 Included With #14 14 EE58893 DC Control Wires, 16 AWG. 1 6 Wires 15 EE58703 Contactor Assy., 35 kW 1 16 EE57143 Decal Power Balance, 5.4” X 1.5” 1 17 EE57145 Decal Patent Pending, 2.70” X 0.55” 1 18 ECU835 ECU Module 1 19 6mm X 15M Screw 21 20 6mm X 15M Lock Washer 21 21 6mm X 15M Flat Washer 21 22 EE58886 Work Instructions, Power Balance 1 23 EE58370 Tailpipe Extension, 3" Dia. X 13" SS 1 24 EE16745 Clamp, U-Style, 3" Zinc 1 25 M8 X 15 Bolt 1 26 3/8" Lock Washer 1 27 3/8" Flat Washer 1 28 G-Clamp 1-1/4" With 3/8" Hole 1 29 1/4-20 X 1 Bolt 2 30 1/4" Lock Washer 2 31 1/4" Flat Washer 4 32 1/4" Nut 2 33 G-Clamp 1" With 1/4" Hole 2 34 Fuse, 10 AMP (AGC10) 1 Included With #35 35 303110 Fuse Holder, In-Line, 10 AMP 1 36 Tie Wrap, #4 6 37 Tie Wrap, #6 10 38 Tie Wrap, #8 10

Upload: vuongkhanh

Post on 18-May-2018

223 views

Category:

Documents


1 download

TRANSCRIPT

DCA125SSJU4i — LOAD BANK INSTRUCTIONS P/N EE58886 — REV. #0 (09/14/15) — PAGE 1

DCA125SSJU4i 35 kW Load Bank Installation

The following instructions are intended to assist the user in the installation of the 35 kW Load Bank for use on the DCA125SSJU4i generators. Please read all assembly instructions before installing load bank.REQUIRED TOOLS

PARTS

Verify that all parts are accounted for. See Figure 1 and Table 1.

Figure 1. Power Balance Kit (DCA125SSJU4i)

WORK SAFELY!

Only a qualified service technician with proper training should perform this installation. Follow all shop safety rules when performing this installation.

PREPARATION

1. Make sure generator is turned off and engine is cool.

A1

A2

A3

A4

A5

A6A12

A11

A10

A9

A8

A7

R1

R2

R3

R4

R5

R6R12

R11

A10

R9

R8

R7

PATENT PENDING

Engine Started

Shutdown

Pre-Alarm

Series 800 Controller

AlarmAcknowledge

ScreenChange

Program/Exit

Option

ECU

HARDWARE

INSTRUCTIONS

2218

37

17

1620

21

19

36

35

34

28

27

25

26

15

23

24

9

10

8

7

11

12

14

13

1

6 32

34

5

382930

31

33 32

�Ratchet Set

� Flat/Phillips Screwdrivers

�Wire Cutters

�Power Drill

� 2-Inch Chassis Punch

2. Place the generator in an area free of dirt and debris. Make sure it is on secure level ground with chock blocks underneath each wheel to prevent the generator from rolling.

Table 1. Power Balance Kit

Item No. Part No. Description QTY. Remarks

1MQP-

PB125J4iKIT, POWER BALANCE, 35kW 1 Includes Items 2-38

2 EE58500 Cover, Roof, 35 kW Resistor 1

3 EE58362 Cover Plate, 2-Row Resistor 2

4 1/4-20 Rivet-Nut 4

5 EE58708 Bracket Bottom, Contactor Box 12"X14" 1

6 EE58707 Bracket Top, Contactor Box 12"X14" 1

7 EE58501 Resistor Assy., 35 kW 1

8 EE58673 2" Rubber Grommet 1

9 Load Bank Split Loom, 3/4" X 114" 126" Included With #10

10 EE58704 Load Bank Wire Harness, 8 AWG. 1 7 Wires

11 EE58868 Power Wires (UVW/4 AWG) GND/8 AWG. 1 4 Wires

12 UVW-GND Split Loom, 1.0" X 54" 1 Included With #11

13 DC Control Split, Loom, 3/8" X 54" 1 Included With #14

14 EE58893 DC Control Wires, 16 AWG. 1 6 Wires

15 EE58703 Contactor Assy., 35 kW 1

16 EE57143 Decal Power Balance, 5.4” X 1.5” 1

17 EE57145 Decal Patent Pending, 2.70” X 0.55” 1

18 ECU835 ECU Module 1

19 6mm X 15M Screw 21

20 6mm X 15M Lock Washer 21

21 6mm X 15M Flat Washer 21

22 EE58886 Work Instructions, Power Balance 1

23 EE58370 Tailpipe Extension, 3" Dia. X 13" SS 1

24 EE16745 Clamp, U-Style, 3" Zinc 1

25 M8 X 15 Bolt 1

26 3/8" Lock Washer 1

27 3/8" Flat Washer 1

28 G-Clamp 1-1/4" With 3/8" Hole 1

29 1/4-20 X 1 Bolt 2

30 1/4" Lock Washer 2

31 1/4" Flat Washer 4

32 1/4" Nut 2

33 G-Clamp 1" With 1/4" Hole 2

34 Fuse, 10 AMP (AGC10) 1 Included With #35

35 303110 Fuse Holder, In-Line, 10 AMP 1

36 Tie Wrap, #4 6

37 Tie Wrap, #6 10

38 Tie Wrap, #8 10

DCA125SSJU4i — LOAD BANK INSTRUCTIONS P/N EE58886 — REV. #0 (09/14/15) — PAGE 2

FRONT PANEL REMOVAL (TOW SIDE)

1. Disconnect negative battery cable from the battery.

2. Locate the generator front panel as shown in Figure 2.

3. Remove the 12 screws (Figure 2 ) that secure the front panel to the cabinet housing.

Figure 2. Front Panel/Exhaust Cover Removal

4. Remove front panel, set aside where it will not get damaged.

FRONT FRAME EXHAUST COVER REMOVAL

1. Remove the 10 screws that secure the exhaust cover (Figure 2) to cabinet housing.

2. Retain mounting hardware.

3. Discard front frame exhaust cover.

FRONTPANEL

EXHAUSTCOVER

CABINETHOUSING

DISCARD

MOUNTINGHARWARE

WHISPERWATT

MOUNTINGHARWARE

MUFFLER TAIL PIPE EXTENSION INSTALLATION

1. Locate muffler tail pipe extension (P/N EE58370).

2. Place the flanged end over the existing muffler pipe section as shown in Figure 3.

Figure 3. Tail Pipe Extension

3. Secure tail pipe extension with U-Clamp (P/N EE16745).

GROMMET INSTALLATION

1. Using a chassis punch or equivalent tool, cut a 2-inch diameter hole into the front frame cabinet sheet metal as shown in (Figure 4).

Figure 4. 2-Inch Diameter Hole Cut-Out

2. Remove any sharp edges from the hole opening.

3. Insert 2-inch diameter rubber grommet (P/N EE58673) into hole opening.

MUFFLER

TAIL PIPEEXTENSION

U-CLAMP

DCA125SSJU4i — LOAD BANK INSTRUCTIONS P/N EE58886 — REV. #0 (09/14/15) — PAGE 3

CONTACTOR SUPPORT BRACKETS INSTALLATION 1. Two contactor support brackets (top/bottom) need to

be attached to the backside (rear) of the control box (Figure 5). These support brackets must be installed in order to support the contactor J-box

Figure 5. Contactor Box Mounting Brackets

Top Contactor Box Support Bracket

2. Locate the top contactor support bracket P/N EE58707.

3. Align center hole on top contactor support bracket as shown in Figure 5 with the top right pilot hole located on the rear of the control box.

4. Using a pencil or scribe mark the left and right bottom hole opening on the bracket.

5. Next, using a 1/4" drill bit, drill a 1/4" diameter hole previously marked (step 4) into the control box.

Bottom Contactor Support Bracket

1. Locate the bottom contactor support bracket P/N EE58708.

2. Align center hole on bottom contactor support bracket as shown in Figure 5 with the bottom right pilot hole located on the rear of the control box.

3. Using a pencil or scribe mark the left and right bottom hole opening on the bracket.

NOTICE

Use extreme caution when drilling. Verify that components and wiring on the opposite side of control box do not come in contact with drill bit.

4. Next, using a 1/4" drill bit, drill a 1/4" diameter hole previously marked (step 3) into the control box.

5. Remove all shavings and debris from inside the control box due to drilling.

1/4-20 POP RIVET-NUT INSTALLATION1. Insert (install) four 1/4-20 pop rivet-nuts into the

previously drilled holes. Tap rivets (Figure 6) lightly with a rubber mallot to insert into control box.

Figure 6. Pop Rivet Installation

CONTACTOR SUPPORT BRACKETS INSTALLATION1. Using four 6MM screws with flat and lock washers,

attached the top and bottom contactor support brackets to the rear of the control box as shown in Figure 7.

Figure 7. Top And Bottom Contactor Support Bracket Mounting

DCA125SSJU4i — LOAD BANK INSTRUCTIONS P/N EE58886 — REV. #0 (09/14/15) — PAGE 4

CONTACTOR J-BOX INSTALLATION P/N EE583641. Using four 6MM screws with flat and lock washers,

install Contactor J-Box (P/N EE58703), Figure 8 onto top and bottom contactor support brackets.

Figure 8. Contactor J-Box Mounting

RESISTOR LOAD BANK WIRING

There are seven BLACK wires that need to be connected to Resistor Load Bank P/N (EE58501). Six of the wires are to be connected to the 12 resistors located inside the load bank, the remaining wire will be connected to chassis ground.

Connect the six 8 AWG. resistor load wires and ground wire as follows:

1. Place the Resistor Load Bank with the Side-A facing as shown in Figure 9.

Figure 9. Load Bank Connections

2. Insert these seven wires into the 9.5' Load Bank split-loom harness (P/N EE58704).

3. Once the wires have been inserted into the load bank split-loom harness secure using tie-wraps.

4. Next, attach the six wires to the Resistor Load Bank as referenced in Figure 9 and Table 2. Please reference the labeling and length of each wire.

5. To prevent arcing, tighten all nuts securely.

A1

A2

A3

A4

A5

A6A12

A11

A10

A9

A8

A7

R1

R2

R3

R4

R5

R6R12

R11

A10

R9

R8

R7

T3 T2 T1

CONTACTORK2

CONTACTOR J-BOX P/N EE58703

SIDE A

RESISTOR LOAD BANK P/N EE58501

COVER ROOF ASSY. P/N EE58500

8 AWG 14”.1”

8 AWG 14’.0”

8 AWG 13’.6

8 AWG 13’.3”

8 AWG 13’.0”

8 AWG 13’.8”

8 AWG 12’.6”

SIDE B

GND. T3 T2 T1

CONTACTORK1

Table 2. Resistor Load Bank Wiring

Resistor/GND.Load Bank Position

Wire Length (ft.) Black 10 AWG

R1 A1 13.0

R3 A3 13.8

R5 A5 14.0

R7 A7 14.1

R9 A9 13.6

R11 A11 13.3

GND GND Screw 12.6

DCA125SSJU4i — LOAD BANK INSTRUCTIONS P/N EE58886 — REV. #0 (09/14/15) — PAGE 5

SECURING LOAD BANK SPLIT LOOM HARNESS

1. Drill two 1/4" diameter holes into the Resistor Assembly housing P/N EE58501 as shown in Figure 10.

Figure 10. Securing Load Bank Split-Loom Harness

2. Next, install two 1" X 1/4" hole G-Clamps onto resistor assembly housing using 1/4-20 bolt, 1/4" lock washer, 1/4" flat washer and 1/4-20 nut as referenced in Figure 10.

RO O F C OV E R / R E S I S TO R L OA D BA N K INSTALLATION

Use the procedure below to mount the Resistor Load Bank (P/N EE58501) into the Roof Cover (P/N EE58500).

1. Lift the Resistor Load Bank (Figure 11) upward and align mounting ear holes with flange bracket holes on Roof Cover.

2. Secure Resistor Load Bank to Roof Cover using three 6MM hex head screws. The fourth 6MM screw is for the GND. wire.

NOTICE

Some resistor frames have 1/4" holes pre-drilled. If your unit does not have pre-drilled holes, then drilling will be required.

Figure 11. Roof Cover/Resistor Load Bank Installation

3. Connect the ground wire to the Resistor Load Bank as referenced in (Figure 11).

4. Using 6MM screw (12) with lock washers and flat washers (Figure 12), install Cover Plate (P/N EE58362) onto A and B sides of Roof Cover (P/N EE58500).

Figure 12. Cover Plate Mounting

A1

A2

A3

A4

A5

A6A12

A11

A10

A9

A8

A7

R1

R2

R3

R4

R5

R6R12

R11

A10

R9

R8

R7

SIDE A

RESISTOR LOAD BANK P/N EE58501

ROOF COVER P/N EE58500

GND. WIRETERMINAL

RING

1

4

2

3

6MMSCREW

COVER ROOF ASSY. P/N EE58500

COVER PLATE (2) ASSY. P/N EE58362

6MM MOUNTINGSCREW (12)

WITH LOCK/FLATWASHERS

SIDE A

SIDE B

DCA125SSJU4i — LOAD BANK INSTRUCTIONS P/N EE58886 — REV. #0 (09/14/15) — PAGE 6

5. Place and align the Roof Cover (P/N EE58500) on top of cabinet housing as shown in Figure 13.

Figure 13. Roof Cover Mounting

6. Use the mounting hardware removed in the "Front Frame Exhaust Cover", step 2 to secure the Roof Cover to the cabinet housing.

7. Tighten all screws securely.

RESISTOR LOAD BANK WIRE HARNESS ROUTING

1. There should now be seven wires connected to the Resistor Load Bank.

2. Next, install one 1" X 3/8" hole G-Clamp onto the overflow tank using 1/4-20 bolt, 1/4" lock washer, 1/4" flat washer and 1/4-20 nut as shown in Figure

3. Route the load bank split-loom harness (Figure 14) through the 2-inch rubber grommet on the front frame of the cabinet and G-Clamp located on the overflow tank.

ROOF COVER P/N EE58500

CABINET HOUSING

MOUNTING HARDWARE

6MMSCREW

6MM X 15FLAT

WASHER

6MM X 15LOCK

WASHER

Figure 14. Load Bank Split-Loom Harness Routing

4. Next, continue routing the split-loom harness through the front cable connector bushing on the Contactor J-Box.

5. Position the six 8 AWG. load bank wires near contactors K1 and K2.

6. Position the BLACK ground wire (Figure 14) near the Contactor J-Box ground point.

CONTACTOR J-BOX WIRING

There are two contactors (K1/K2) that require wiring via the Resistor Load Bank. Connect the six wires to the contactors as shown below:

1. Connect the six black wires coming from the Resistor Load Bank to the K1 and K2 contactors as shown in Table 3 and Figure 15. Tighen all wires to 40 in. lbs. (4.52 N.m).

2. Attach the BLACK 8 AWG. ground wire to the Contactor J-Box ground point. Tighten ground wire to 40 in. lbs. (4.52 N.m).

K2

K1

OVERFLOW TANK

3/4” X 114”SPLIT-LOOM

HARNESS

CONTACTORJ-BOX

P/N EE58703

CONNECT TORESISTOR LOAD BANK

FRONT FRAMECABINET

GND.POINT

6 WIRES

CONTACTORS

2-INCHRUBBER

GROMMET

CONNECTORBUSHING

INSTALL1” X 3/8” HOLE

G-CLAMP

DCA125SSJU4i — LOAD BANK INSTRUCTIONS P/N EE58886 — REV. #0 (09/14/15) — PAGE 7

Figure 15. Contactor Wiring

FUSE WIRE HARNESS ROUTING

There is a fuse block located inside the Contactor J-Box that contains three 100 amp fuses (F1, F2 and F3). Position load wires to the fuse block as follows:

1. Insert four RED, BLACK, BLUE and GREEN wires into the 54-inch fuse block split-loom harness (EE58868) as shown in Figure 16.

2. Once the wires have been inserted into the split-loom harness. Secure using tie-wraps.

3. Next, continue routing the split-loom harness through the rear cable connector bushing on the Contactor J-Box.

K2 K1

A3

T3 T2 T1 T3 T2 T1

A11

A7A9

A1A5

Table 3. Contactor J-Box WiringLoad Bank Position Contactor (K1/K2)

A1 K1-T1A5 K1-T2A9 K1-T3A7 K2-T1A11 K2-T2A3 K2-T3

GND GND Screw

4. Position the 3 fuse wires (Figure 16) near the fuse block. If necessary, secure wiring with tie-wraps.

5. Position the GREEN ground wire near the Contactor J-Box ground point.

Figure 16. Fuse Connections

FUSE WIRE CONNECTIONS (UVW AND GND.)

1. Connect the three 4 AWG. RED, BLACK, BLUE wires to the load side of the fuse block as shown in Figure 16 and Table 4.

2. Tighten the nut securing the load wires to the fuse block to 60 in. lbs. (6.78 N.m)

3. Connect the GREEN 8 AWG. ground wire to the Contactor J-Box ground point as shown in Figure 16 and Table 4. Tighten ground wire nut to 40 in. lbs. (4.52 N.m).

CONNECTORBUSHING

FUSE BLOCKSPLIT-LOOM

HARNESSP/N EE58868

ROUTE TO OUTPUT TERMINAL PANEL(REAR, UVW-GND)

3 WIRES

FUSE BLOCK

CONTACTORJ-BOX

FUSEBLOCK

F1

GND.POINT

F2 F3

BLUEREDBLK

GRN.

Table 4. Fuse Wiring Connections (UVW)

Fuse Color (Phase)Wire Length (ft.)

8 AWGF1 BLUE (W) 4F2 BLACK (V) 4F3 RED (U) 4

DCA125SSJU4i — LOAD BANK INSTRUCTIONS P/N EE58886 — REV. #0 (09/14/15) — PAGE 8

OUTPUT TERMINAL PANEL ENCLOSURE REMOVAL

1. Remove the four screws as shown in Figure 17 that secure the output terminal enclosure to the cabinet frame.

Figure 17. Output Terminal Panel Enclosure Removal

2. Lift and remove the enclosure from the output terminal panel. Set the enclosure aside.

OUTPUT TERMINAL PANEL (UVW-GND.) WIRE CONNECTIONS

1. Connect the three 4 AWG. RED, BLACK, BLUE wires and GREEN 8 AWG wire to the rear of the ouput terminal panel as shown in Figure 17 and Table 5.

REMOVESCREW

4 PLACES

OUTPUT TERMINALPANEL ENCLOSURE

OUTPUT TERMINALPANEL REAR

UVWO

TO FUSEBLOCK

1-INCH DIA., 54-INCHSPLIT-LOOM HARNESS

F1F2

F3

RED

BLK

BLUE

GREEN

4 AWG3 PLACES

GND.

8 AWG

Table 5. UVW-GND Output Terminal WiringFunction Color

U REDV BLACKW BLUEO1 N/A

GND. GREEN1Terminals O and GND. are bonded

2. Once all four wires have been securely connected to the rear of the output terminal panel, re-install output terminal panel enclosure.

DC CONTROL SPLIT LOOM HARNESS (CONTACTOR J-BOX SIDE)

There are four wires, (P/N EE58893) that need to be connected to the Contactor J-Box. Connect the wires as shown below.

1. Insert the 4 wires into the 3/8", 54-inch DC Control split-loom harness (P/N EE58893).

2. Once the wires have been inserted into the split-loom harness secure using tie-wraps.

3. One side of this harness (Figure 18) has 4 wires with the insulation stripped back 1/2-inch. The other side has 1 terminal ring and 1 male spade lug attached to the wires. The remaining 2 wires have the the insulation stripped back 1/2-inch.

Figure 18. DC Control Split Loom Harness

4. Route the split-loom harness through the front right cable connector bushing on the Contactor J-Box. Be sure to route only the stripped wires up to the J-Box not the terminal ring/male spade lug side.

5. Connect the four wires to the Contactor J-Box as shown in Figure 19 and Table 6.

Table 6. DC Control Wiring

ColorContactor J-Box

TerminalDestination

BROWN TB1-1 ECU Pin-57RED/WHT TB1-2 10 AMP FuseGREEN TB1-3 Ground (Ctrl. Bx.)

YEL/WHT TB1-4 ECU Pin-13

DCA125SSJU4i — LOAD BANK INSTRUCTIONS P/N EE58886 — REV. #0 (09/14/15) — PAGE 9

Figure 19. DC Control Wiring (TB1)

ECU 830 MODULE REMOVAL

1. Loosen the two panel release knobs (Figure 20) that secure the Control Panel to the cabinet frame.

Figure 20. Control Panel

2. Once the release knobs have been loosened, gently lower the control panel. The backside of the ECU 830 control module is now accessible.

3. Remove all wiring connected to the existing ECU 830 control module.

TB1

1

2

3

4

4

4

2

3

1

3

4

4

DC CONTROL3/8” SPLIT-LOOM

HARNESS P/N EE58893BRN

CONTACTORJ-BOX

ALL WIRES 16 AWG.

5 5

1

2

3

4

4

4

2

3

1

3

4

5

5 6

4-WIRES

TO CONTROL BOX., ECU

RED/WHT

GRN

YEL/WHT

4. Next, remove the four screws (Figure 21) that secure the existing ECU 830 control module to the Control Panel.

Figure 21. ECU 830 Module Removal

5. Discard the existing ECU 830 Module.

NEW ECU 835 MODULE INSTALLATION

1. Place the new ECU 835 module onto the Control Panel Secure module using the hardware as referenced in step 4 "ECU 830 Module Removal".

2. Re-connect wiring that was removed in step 3 "ECU 830 Module Removal". Reference Table 7.

ECU830

RETAININGNUT (4)

Table 7. ECU 835 Wire ConnectionsPin Number Wire Color Quantity

3 Green 14 Red/Orange 15 White 16 Brown 18 White 18 White 19 Black 19 Black 112 Pink 113 Yellow/White 114 Black/Red 116 Red 137 White 138 Black 157 Brown 158 Red/Yellow 1

DCA125SSJU4i — LOAD BANK INSTRUCTIONS P/N EE58886 — REV. #0 (09/14/15) — PAGE 10

DC CONTROL SPLIT LOOM HARNESS (ECU, VOLTAGE SELECTOR SWITCH, ECU AND CONTROL BOX SIDE

1. Continue routing the free end of the DC Control split-loom harness through the bottom access hole (Figure 22) on the Control Box.

Figure 22. DC Control Split-Loom Harness

2. Connect the YELLOW/WHITE, and BROWN wires to the ECU module (pins 13, and 57 respectively) as shown in Figure 22 and Table 6.

3. Next, connect the RED wire with the terminal ring to pin 42 on the Voltage Selector Switch.

4. Connect the other end of the RED wire to pin 16 on the ECU module.

5. Place a RED/YELLOW jumper wire between pins 4 and 58 on the ECU module.

6. Connect the GREEN wire with the terminal ring to the Control Box ground point.

DC CONTROLSPLIT-LOOM

HARNESSP/N EE58893

VOLTAGE SELECTOR

SWITCH

TERMINAL42

GND.

4-PIN

TERMINAL

BLOCK 4

CONTROL BOX

YELLOW/WHITE

BROWN

FROM TB1CONTACTOR

J-BOX

ADD IN-LINE

FUSE 10 AMP

31 2

ECU 835

PIN-57

PIN-13

GRN

ACCESS

HOLE

PIN-16

PIN-58

PIN-4

JUMPERWIRE

RED/YEL

BLK

RED

RED/WHT

B+

IN-LINE FUSE INSTALLATION

Reference Figure 22.

1. Insert a 10 AMP fuse into the fuse holder (P/N 303110).

2. Connect one end of the fuse holder wire (Figure 22) to the 4-pin terminal block located at the rear of the Control Box to terminal 4 (bottom).

3. Next, crimp a female spade connector onto the other end of fuse holder wire.

4. Insert the female spade connector end of the fuse holder wire into the RED/WHITE wire (B+) with the male spade connector.

5. Once the wiring has been completed, raise the Control Panel back onto the cabinet frame and secure by turning the release knobs clockwise.

DECAL PLACEMENT

1. Place Power Balance decal (P/N EE57143) onto Control Panel as shown in Figure 23.

2. Next, place Patent Pending decal (P/N EE57145) onto Control Panel as shown in Figure 23.

Figure 23. Decal Placement

3. Reconnect battery.

DCA125SSJU4i — LOAD BANK INSTRUCTIONS P/N EE58886 — REV. #0 (09/14/15) — PAGE 11

TESTING

Once the Load Bank is installed and ready to test, the ECU 835 Controller must first be updated with the latest firmware to support Load Bank operation.

1. Obtain ECU 835 firmware file 0-0-12-0 JD 0-2-0-14.pfw and load to a USB flash drive.

2. Place ECU 835 into “Test Mode”. Test mode is achieved by pressing and holding the hour check button (Figure 24).

Figure 24. Hour Check Button

3. Next, place the Auto-Off/Reset Manual Switch (Figure 25) in the manual position.

Figure 25. Auto-Off/Reset Manual Switch (Manual Position)

4. Release the hour check button. Once in test mode, log onto the ECU835 with the MQ Password.

5. Next, go to advanced options and select upgrade firmware.

6. Select browse for file, and then select the file from the USB. Once selected proceed with the onscreen instructions to complete the firmware update.

NOTICE

The firmware file must be in the main directory (no subfolders). Insert the flash drive into the USB port on the back of the ECU835 controller.

HOUR CHECKBUTTON

AUTO MANUAL

OFF/RESET

7. Once the update is completed, log back on to the ECU835 with the MQ password. Go to customer options then go to load bank settings.

8. Verify and change settings to match the settings shown in Table 8. Use the “Set To” column values.

9. There are two set points that will need to be temporarily set at low values for testing purposes. Once testing is completed, set the Low Load Delay and High Load Trip Reset settings back to the “Set To” column as referenced in Table 8.

10. For testing, use the parameters listed below:

� Low Load Delay, set to 2 minutes.

�High Load Trip Reset, set to 1 minute.

11. The following test equipment will be required to complete the testing:

�A stopwatch to confirm load bank is operating at the correct intervals.

�External load bank capable of full load in each voltage position.

�An ammeter to verify current in each voltage mode.

12. Connect the battery terminals and prime the fuel system. Check that oil, coolant and DEF fluid levels are satisfactory.

13. Verify the main circuit breaker is placed in the ON position.

14. Place the voltage selector switch (Figure 26) in the 3ø-240/139 position.

Figure 26. Voltage Selector Switch 3Ø-240/139 Position

DCA125SSJU4i — LOAD BANK INSTRUCTIONS P/N EE58886 — REV. #0 (09/14/15) — PAGE 12

15. Connect an external load bank to the output terminal panel as shown in Figure 27 and set up for selected voltage mode.

Figure 27. External Load Bank

16. Place ammeter clamp around Line 1 (L1) on the main circuit breaker.

Figure 28. Attaching Ammeter Clamp

3-PHASE

L1

MAIN CIRCUITBREAKER

AMMETERCLAMP

L3

L2

Low Load Delay

1. Start the genset and run at no load.

2. Using the voltage regulator adjustment knob, adjust voltage for 3ø-240V

Figure 29. Voltmeter/VR

3. Start stopwatch.

4. The genset should run without the load bank engaging for the time set for “Low Load Delay”. The test value should be 2 min, so after 2 min (may only take one min) the load bank should automatically turn ON.

5. A powered on Load Bank is indicated by a small “L” on the front screen of the ECU835 (Load Bank On). You should also hear an audible change in the engine load.

6. On line 1 of the main circuit breaker (Figure 28), the current measured at the ammeter should be approximately 84A with the voltage selector switch set at 3Ø-240V position without additional load from the external load bank. The internal load bank should stay on indefinitely.

DECREASEINCREASE

300

0

100240

600

400500

VOLTMETER

VOLTAGE REGULATORADJUSTMENT KNOB

DCA125SSJU4i — LOAD BANK INSTRUCTIONS P/N EE58886 — REV. #0 (09/14/15) — PAGE 13

High Load Level

The next step will test to verify that the internal load bank turns off if a high load level is reached.

1. With the genset still running and the internal load bank on, begin applying load from the external load bank and add load steps equal to a value of approximately 40% of rated load (40 kW) for a 125 kVA genset.

2. The internal load bank should remain on. Run for a couple of minutes and then in one additional step, apply an additional 25 kW step from the external load bank.

3. This should be enough load to exceed the “High Load Trip” set point and drop out the internal load bank. This can be verified by a small “T” on the front display of the ECU835 (Torque Exceeded).

4. The “T” should remain for the duration of the “High Load Reset” (60 seconds for test). Once the ECU timer has elapsed, the “T” will go away.

5. The ECU control module is now verifying if the load is above the acceptable load setting (50%) which it should be while at 80% external load. The internal load bank should not attempt to reengage.

6. Remove the external load bank and begin a new stopwatch sequence.

7. After the (Low Load Delay) timer elapses (approximately 2 minutes for test), the internal load bank should come back on. This completes the test for this voltage position.

Using the same procedure repeat for 3ø-480V and 1ø 240V.

480V Position Load Bank Testing

For 3ø-480V, the load bank line current should be about half of what was measured in the 3ø-240V mode, approximately 42A. Add 40kW step then an additional 40 kW step to trip on High Load Trip.

240V Position Load Bank Testing

1. For 1ø-240V, the load bank line current should be about 73A. This will only be on L1 and L3 when in single phase mode.

2. Add 195 amps to trip on High Load Trip, usually a 85 kW step on a 3ø load bank.

3. As mentioned earlier once testing is completed, set the Low Load Delay and High Load Trip Reset settings back to the values as shown in the “Set To” column. Reference Table 8.

� Low Load Delay set back to 10 min.

�High Load Trip Reset set back to 600 Seconds.

DCA125SSJU4i — LOAD BANK INSTRUCTIONS P/N EE58886 — REV. #0 (09/14/15) — PAGE 14

Table 8. ECU 835/840 MQ Customer Settings (Load Bank)DCA125 JDT4 Interim

Firmware Version 0-0-12-0 JD 0-2-0-14.pfw

Menu Set Point Name DefaultSet To: Value

Unit of Measure

Load Bank Settings

Load Bank Enable 1 1 1=ON 0=OFFLow Load Trip 45 50 % Torque

Sufficient Load Trip 45 50 % TorqueHigh Load Trip 80 92 % Torque

Alt Low Load Trip 45 45 % TorqueAlt Sufficient Load Trip 45 45 % Torque

Alt High Load Trip 80 65 % TorqueLow DOC in Temp C 300 300 °CLow Load Delay Min 10 10 Min

Regen Low Load Delay 10 0 SecLoad Bank Dwell Min 0 60 Min

High Load Second Trip 0.1 0.1 SecHigh Load Second Reset 60 600 Sec

Idle in Load Enable 0 0 1=ON 0=OFFIdle in Load PA 3 3 SecIdle in Load SD 60 60 Sec

Excessive Idle Enable 0 0 1=ON 0=OFFExcessive Idle PA 10 10 MinExcessive Idle SD 15 15 Min

Load Bank 2

DPF TCON High Temp C 1700 1700 °CDPF TCON High Temp Dwell M 1 1 Min

DPF TCON Low Temp C -200 -200 °CDPF TCON Low Temp Dewll M 1 1 Min

H Enable 0 0 1=ON 0=OFFH Count 1 1

TDR Cycle Enable 0 0 1=ON 0=OFFTDR Insuff Load Min 120 120 Min

TDR Loadbank On Min 90 90 MinFault Detect. Enable Second 30 5 5 Sec

Enable Load Always On 0 1 1=ON 0=OFFIdle > Rated Reenable Sec 5 5 Sec

DCA125SSJU4i — LOAD BANK INSTRUCTIONS P/N EE58886 — REV. #0 (09/14/15) — PAGE 15

NOTES

DCA125SSJU4i 35 kW Load Bank Installation

Your Local Dealer is:

HERE’S HOW TO GET HELPPLEASE HAVE THE MODEL AND SERIAL

NUMBER ON-HAND WHEN CALLING

© COPYRIGHT 2015, MULTIQUIP INC.

Multiquip Inc , the MQ logo are registered trademarks of Multiquip Inc. and may not be used, reproduced, or altered without written permission. All other trademarks are the property of their respective owners and used with permission.

This manual MUST accompany the equipment at all times. This manual is considered a permanent part of the equipment and should remain with the unit if resold.

The information and specifi cations included in this publication were in effect at the time of approval for printing. Illustrations, descriptions, references and technical data contained in this manual are for guidance only and may not be considered as binding. Multiquip Inc. reserves the right to discontinue or change specifi cations, design or the information published in this publication at any time without notice and without incurring any obligations.

UNITED STATES Multiquip Corporate Offi ce MQ Parts Department

18910 Wilmington Ave.Carson, CA 90746 Contact : [email protected]

Tel. (800) 421-1244Fax (310) 537-3927

800-427-1244310-537-3700

Fax: 800-672-7877Fax: 310-637-3284

Service Department Warranty Department

800-421-1244310-537-3700

Fax: 310-537-4259 800-421-1244310-537-3700

Fax: 310-943-2249

Technical Assistance

800-478-1244 Fax: 310-943-2238

CANADA UNITED KINGDOM

Multiquip Multiquip (UK) Limited Head Offi ce

4110 Industriel Boul.Laval, Quebec, Canada H7L 6V3 Contact : [email protected]

Tel: (450) 625-2244Tel: (877) 963-4411Fax: (450) 625-8664

Unit 2, Northpoint Industrial Estate, Globe Lane,Dukinfi eld, Cheshire SK16 4UJ Contact : [email protected]

Tel: 0161 339 2223Fax: 0161 339 3226