424 final
TRANSCRIPT
-
8/3/2019 424 Final
1/50
Enhancement of Available TransferCapacity
for
Congestion ManagementIn
Deregulated Power SystemGuided by :
Prof. S. K. JoshiM.S.U. Baroda
Presented byB.P.Pandya , BE(E) IV
Roll No. : 424
-
8/3/2019 424 Final
2/50
Project Theme
Deregulated Electricity Market Open Access
Congestion Management
Available Transfer Capacity
To propose a new set of AC sensitivity referred as ACPower Transfer Congestion Distribution Factor (ACPTCDF)
for 6 bus system.
Calculate ATC of transmission line
Enhancement of ATC using facts devices forcongestion management
-
8/3/2019 424 Final
3/50
Significance of Topic
Conversion of Vertically integrated utilities to Open Accessmarket system
[ May 2003,Indian Electricity Act]
To promote competition through open access among utilities
ATC must be calculated [ ATC posted on OASIS] Because of Open Access, Congestion is prime problem for
power system
Congestion can be managed by Facts devices. Fact devicescan enhance ATC.
So we develop a set of congestion distribution factors in termsof real as well as reactive power
Most sensitive congested line is identified by sensitiveanalysis and ATC calculation
-
8/3/2019 424 Final
4/50
Regulation
Regulation means thatthe Government has set
down laws and rules thatput limits on and definehow a particular industryor company can operate.
-
8/3/2019 424 Final
5/50
Deregulation
Deregulation inpower industry is arestructuring of the
rules andeconomicincentives thatgovernment set upto control and drive
electric powerindustry.
-
8/3/2019 424 Final
6/50
Advantages of Deregulation
The need for regulation changed former verticallyintegrated utility is disaggregated into separatecompanies devoted to each function.
Privatization Cost is expected to drop
Customer focus will improve
Encourages innovation
Power production and retail sales will be competitive,monopoly franchise business
-
8/3/2019 424 Final
7/50
Benefits & Issues involved in Deregulation
Benefits Issues
Improved generation Network Congestion
Planning Efficiency Optimal bidding for Genco
Cheaper electricity due tocompetition and innovation
Transmission pricing
Improved Economy Ancillary Services
ManagementNew jobs for powerengineers
Risk Analysis
-
8/3/2019 424 Final
8/50
Network Congestion
When the producers and consumers of the electricenergy desire to produce and consume in total thatwould cause the transmission system to operate at orbeyond one or more transfer limit, the system is said to
be congested.
Congestion is a consequence of network constraintscharacterizing a finite network capacity that prevent thesimultaneous delivery of power from an associated set ofpower transactions.
-
8/3/2019 424 Final
9/50
Constraints
Thermal limit :- The maximum amount of electrical energythat transmit on transmission line without
overheating.
Voltage limit :- System voltage and change in voltage must
be maintained with the range of acceptable
deviation
Stability limit :- Transmission system capable of survivingdisturbances through the
transient and dynamic period
-
8/3/2019 424 Final
10/50
Graph showing congestion
-
8/3/2019 424 Final
11/50
Objective of Congestion Management
Minimized interference of the transmission network in themarket for electric energy
Secure operation of the power system
Improvement of market efficiency Manage power flow with existing Transmission line
-
8/3/2019 424 Final
12/50
Available Transfer Capacity (ATC)
ATCis a measure of the Transfer Capability Remaining inthe transmission network for further commercial activity*over and above already committed uses
(* while ensuring system security)
Mathematically,ATC = TTC TRM (ETC+CBM)
[In accordance with the recent FERC (Federal Energy Regulatory Commission) Order 888(Promoting Utility Competition Through Open Access, Non discriminatory Transmission service
by Public Utility)& 889(OASIS , Open Access Same time Information system) ,ATC must be calculated for electric utility]
.
-
8/3/2019 424 Final
13/50
ATC = TTC TRM (ETC+CBM)
ETC is the existing transfer commitments
TTC is the maximum amount of power which can betransferred over the network while satisfying all securityconstraints.
TRM is the margin required for uncertainties in the systemconditions.
CBM is the margin reserved by load serving entities forgeneration reliability requirements.
-
8/3/2019 424 Final
14/50
Pre- Contingency Situation
Bart.SE
NrthBarth.
N.E.S. Delaware
Flow 900
Flow 50
Rating 210
ContingencyElement
CONTINGENCY
Flow gate direction
-
8/3/2019 424 Final
15/50
Post contingency situation
N.E.S.Delaware
Flow 0
Flow 212
Rating 210
contingency
50 + 0.18 * 900
Flow gate direction
BartSE
NrthBart
-
8/3/2019 424 Final
16/50
Transfer Capacity on 28/4/2010
Present Status: Transfer Capacity state
1. Congestion charges applicable NO
2. Total transfer capacity(TTC) of NR 4250 MW
3. Available transfer capacity(ATC) of NR 3750 MW
4. IR Schedule 2749 MW
5. IR Actual 2930 MW
6. TTC Violation -1320 MW
7. ATC Violation -820 MW
NORMAL
Transfer capacitystate
1) Normal- NoViolation- colorGreen
2) Alert- ATCViolation- colorYellow
3) Emergency- TTCViolation- colorRed
-
8/3/2019 424 Final
17/50
-
8/3/2019 424 Final
18/50
Role of ISO
ATC is a measure of how much additional electricpower could be transferred.
Each ISO is responsible for monitoring its own regionaltransmission system and calculating ATC for potentially
congested paths.
ATC values would be placed on a website known asOpen Access Same-time Information System (OASIS)operated by ISO.
Anyone wishing to do transaction, would access OASISweb pages and use ATC information available there todetermine if system could accommodate the transaction.
-
8/3/2019 424 Final
19/50
Methods ofATC
Calculation
Using PTCDFand LODF
Optimal powerflow method
Continuationmethod
-
8/3/2019 424 Final
20/50
AC Load flow based Approach
A.C. based approach utilized two sets of sensitivityfactors terms as Real Power Transmission CongestionFactor (PTCDF) & Reactive Power TransmissionCongestion Factor (QTCDF)
Most sensitive transmission line can be found & managethis line with use of FACTS device.
-
8/3/2019 424 Final
21/50
Real Power Transfer Congestion DistributionFactor ( PTCDF)
For ATC determination the MW flow must be allocated toeach line or group of lines in proportion to MW beingtransmitted by each transaction.
A transaction is a specific amount of power that isinjected in to the system at one bus by a generator &removed at the another bus by load.
PTCDF is defined as the change in real power flow (Pij)
in a transmission linek, connected between bus i & j,due to unit change in the power injection(Pn) at bus-n.
-
8/3/2019 424 Final
22/50
QTCDF is defined as the change in reactive power flow
(Qij) in a transmission linek, connected between bus i& j, due to unit change in the reactive powerinjection(Qn) at bus-n
It is also called sensitivity because it relates the amountof one change transaction amount to another change line flow.
1 52 34 76
-
8/3/2019 424 Final
23/50
ATC Calculation using PTCDF
Recognizing new flow on line from bus i to bus j (line k)due to transaction at bus n.
-
8/3/2019 424 Final
24/50
Line Outage Distribution Factor (LODF)
ATC is also limited by the effects of contingencies. The line flows could be used to calculate the effect of
each line outage, then PTCDF applied to find transferlimit.
LODFs & PTCDFs can be combined to calculate thefirst contingency incremental transfer capability, which isthe maximum increase in transaction amount from onebus to another bus.
LODF can be defined as the measure of redistributionbecause of line outage.
1 2 3 4 5 6
-
8/3/2019 424 Final
25/50
ATC using PTCDF & LODF
-
8/3/2019 424 Final
26/50
-
8/3/2019 424 Final
27/50
Congestion Management by FACTS devices
For efficient utilization of the existing network withpenetration of additional power FACTS devices areused.
Effective FACTS based power flow control can beapplied to relieve transmission congestion & Improve thetransfer capability of the network with high penetration ofpower. While voltage security & voltage stabilityconstraint are satisfied & transmission net work can beeffectively utilized.
-
8/3/2019 424 Final
28/50
Principle of Control The inserted series voltage can be regulated to change
the impedance (X) of Transmission line hence powerflow of the line can be controlled.
FACTS is power Electronics based system that providedynamic control of the power transfer parameters
transmission voltage, line impedance & phase angle,active and reactive power when storage becomes viablestorage then they can supply & absorbed active poweras well
Consider unity power factor load, real power transferredis given by
Similarly Reactive power transferred is given by
-
8/3/2019 424 Final
29/50
FACTS Technology and their potential
Definition[3] of FACTS by IEEE as:
Alternating current transmission system incorporatingpower Electronics based & other static controller toenhance controllability and increase power transfercapability
FACTS controller [14] :- It is power electronic-basedsystem and other static equipment that provide control of
one or more AC transmission parameters.
For ATC enhancement the FACTS devices are placedat weak-bus.
-
8/3/2019 424 Final
30/50
FACTS Devices
1. Shunt controller :Adjusting the system voltage by means of shunt
reactive elements is known as shunt compensation.
2. Series Controller :
Adjusting the system voltage by means of series reactiveelements is known as shunt compensation.
3. Combined shunt-series controller (Unified Power FlowController) :-
It provides independent series reactive compensation for
each line bus also transfer real power among the line viad.c. power link (Inter line power flow controller).
Used in multiple line
-
8/3/2019 424 Final
31/50
FACTS DEVICES LOCATION
We look at static considerations here for the placement of FACTSdevices in the power system. The objectives for device placementmay be one of the following:
1. Reduction in the real power loss of a particular line
2. Reduction in the total system real power loss 3. Reduction in the total system reactive power loss
4. Maximum relief of congestion in the system
For the first three objectives, methods based on the sensitivityapproach may be used. If the objective of FACTS device placement
is to provide maximum relief of congestion, the devices may beplaced in the most congested lines .
For ATC enhancement the FACTS devices are placed at weak-bus.
-
8/3/2019 424 Final
32/50
Weak Bus Identification
The basic equations used in N-R Load flow are given below
-
8/3/2019 424 Final
33/50
To obtain real and reactive power sensitivity, the basic load flow equations becomes
(3)
Hence, the real and reactive power sensitivities of the ith
P P
P V
VQ P Q
V
2
4
bus are obtained as
(4)
ii
ii
i
i
i
ii
i
PJ V
V
QJ V
V
..continue
-
8/3/2019 424 Final
34/50
..continue
i
Eq.4 represents the real and reactive power sensitivities of the i-th bus.
deg
, min change in V for variation
in Q-sta
thi i
i i
Q Qalso indicatethe ree of weakness for i bus as being
V V
high becomes low indicating imum
tus of the bus. Thus, being higher,
the degree of weakness of the i-th bus becomes lesser
i
i
Q
V
-
8/3/2019 424 Final
35/50
N
Y
Start
Run Base case Load flow
Form full jacobian except for the SlackBus
Consider Transaction
Identify seller and buyer busesi & j
Compute Line flows
Compute the JacobianInverse
Compute ACPTCDF & LODFusing same transaction
Are alltransaction over
Go to newtransaction
Inject Reactive power withFACTS devices
Calculate AvailabilityTransfer capability & print
Results
End
Flow chart
-
8/3/2019 424 Final
36/50
Results for 6 bus system
(2) Results of basic load flow :
(3) (a) Line flows file : line_flow.txt
From to --- Line flows ---- ------- Line loss--
MW MVar MVA MW MVar
1 2 -18.37627 292.961 293.537 28.955 53.869
1 5 5.30588 95.595 95.742 3.185 1.840
2 1 47.33095 -239.092 243.732 28.955 53.869
2 4 7.66905 -116.081 116.334 6.499 9.378
3 5 0.73076 -36.339 36.346 0.472 -3.1673 6 35.26924 10.639 36.839 0.561 -2.782
4 2 -1.17022 125.459 125.464 6.499 9.378
4 5 34.07616 -51.782 61.988 1.456 -1.199
4 6 67.09406 -3.723 67.197 1.802 -0.302
5 1 -2.12073 -93.755 93.779 3.185 1.840
5 3 -0.25888 33.172 33.173 0.472 -3.1675 4 -32.62039 50.583 60.189 1.456 -1.199
6 3 -34.70777 -13.421 37.212 0.561 -2.782
6 4 -65.29223 3.421 65.382 1.802 -0.302
Total Loss 42.930 57.637
-
8/3/2019 424 Final
37/50
(b) Load flow result :
Load flow bus status (Loadflowbusstatus.txt)
Bus Voltage Angle ------Load------ ---Generation--- Injected
No. Mag. Degree MW Mvar MW Mvar Mvar
1 1.1000 0.0000 70.000 10.000 56.899 398.564 0.0002 0.9000 7.7121 45.000 10.000 100.000 -345.175 0.000
3 1.0000 2.5717 50.000 10.000 86.000 -15.715 0.000
4 1.0000 4.4050 30.000 10.000 130.000 79.937 0.000
5 1.0273 1.7730 35.000 10.000 0.000 0.000 0.000
6 0.9761 1.2120 100.000 10.000 0.000 0.000 0.000
Total 330.000 60.000 372.899 117.611 0.000
-
8/3/2019 424 Final
38/50
Real Power Transmission Congestion Distribution factors (PTCDF) are asunder:
line no from to Real Power Distribution factor
________________________________________________
1 1 2 0.1904
2 1 5 -0.0037
3 2 4 0.3031
4 3 5 0.0815
5 3 6 -0.1026
6 4 5 -0.1509
7 4 6 -0.4593________________________________________________
-
8/3/2019 424 Final
39/50
Weak bus Results are as under :
-----------------------------------------------
Load Bus dq/dv
-----------------------------------------------
5 0.02540466 0.0423613
-----------------------------------------------
Minimum dQ/dV is 0.0254 for bus no 5
Hence bus 5 is weak bus
-
8/3/2019 424 Final
40/50
Reactive power injection from (1 to 50 Mvar) at weak bus for congestion management
Shunt: 1 -> Voltage(Kv) : 1.02679 -> ATC : 31.000 (MW)
Shunt: 2 -> Voltage(Kv) : 1.02705 -> ATC : 33.000 (MW)
Shunt: 3 -> Voltage(Kv) : 1.02732 -> ATC : 36.000 (MW)
Shunt: 4 -> Voltage(Kv) : 1.02758 -> ATC : 38.000 (MW)
Shunt: 5 -> Voltage(Kv) : 1.02785 -> ATC : 39.000 (MW)
Shunt: 6 -> Voltage(Kv) : 1.02811 -> ATC : 35.000 (MW)
Shunt: 7 -> Voltage(Kv) : 1.02837 -> ATC : 32.000 (MW)
Shunt: 8 -> Voltage(Kv) : 1.02864 -> ATC : 29.000 (MW)
Shunt: 9 -> Voltage(Kv) : 1.02890 -> ATC : 26.000 (MW)
Shunt: 10 -> Voltage(Kv) : 1.02916 -> ATC : 23.000 (MW)
Shunt: 11 -> Voltage(Kv) : 1.02943 -> ATC : 20.000 (MW)
Shunt: 12 -> Voltage(Kv) : 1.02969 -> ATC : 16.000 (MW)
Shunt: 13 -> Voltage(Kv) : 1.02995 -> ATC : 13.000 (MW)
Shunt: 14 -> Voltage(Kv) : 1.03022 -> ATC : 10.000 (MW)
Shunt: 15 -> Voltage(Kv) : 1.03048 -> ATC : 6.000 (MW)
Shunt: 16 -> Voltage(Kv) : 1.03074 -> ATC : 3.000 (MW)Shunt: 17 -> Voltage(Kv) : 1.03101 -> ATC : 3.000 (MW)
Shunt: 18 -> Voltage(Kv) : 1.03127 -> ATC : 5.000 (MW)
-
8/3/2019 424 Final
41/50
Shunt: 19 -> Voltage(Kv) : 1.03153 -> ATC : 8.000 (MW)
Shunt: 20 -> Voltage(Kv) : 1.03179 -> ATC : 11.000 (MW)Shunt: 21 -> Voltage(Kv) : 1.03205 -> ATC : 15.000 (MW)Shunt: 22 -> Voltage(Kv) : 1.03232 -> ATC : 18.000 (MW)Shunt: 23 -> Voltage(Kv) : 1.03258 -> ATC : 22.000(MW)Shunt: 24 -> Voltage(Kv) : 1.03284 -> ATC : 25.000 (MW)Shunt: 25 -> Voltage(Kv) : 1.03310 -> ATC : 27.000 (MW)Shunt: 26 -> Voltage(Kv) : 1.03336 -> ATC : 31.000 (MW)Shunt: 27 -> voltage(Kv) : 1.03362 -> ATC : 32.000 (MW)
Shunt: 28 -> Voltage(Kv) : 1.03388 -> ATC : 34.000 (MW)Shunt: 29 -> Voltage(Kv) : 1.03414 -> ATC : 37.000 (MW)Shunt: 30 -> Voltage(Kv) : 1.03440 -> ATC : 37.000 (MW)Shunt: 31 -> Voltage(Kv) : 1.03466 -> ATC : 39.000(MW)Shunt: 32 -> Voltage(Kv) : 1.03492 -> ATC : 37.000 (MW)Shunt: 33 -> Voltage(Kv) : 1.03518 -> ATC : 36.000 (MW)Shunt: 34 -> Voltage(Kv) : 1.03544 -> ATC : 36.000 (MW)
Shunt: 35 -> Voltage(Kv) : 1.03570 -> ATC : 33.000 (MW)Shunt: 36 -> Voltage(Kv) : 1.03596 -> ATC : 32.000 (MW)Shunt: 37 -> Voltage(Kv) : 1.03622 -> ATC : 28.000(MW)Shunt: 38 -> Voltage(Kv) : 1.03648 -> ATC : 26.000 (MW)Shunt: 39 -> Voltage(Kv) : 1.03674 -> ATC : 20.000 (MW)
Shunt: 40 -> Voltage(Kv) : 1.03700 -> ATC : 14.000 (MW)
-
8/3/2019 424 Final
42/50
Shunt: 41 -> Voltage(Kv) : 1.03726 -> ATC : 10.000 (MW)Shunt: 42 -> Voltage(Kv) : 1.03752 -> ATC : 4.000 (MW)Shunt: 43 -> Voltage(Kv) : 1.03777 -> ATC : 2.000 (MW)Shunt: 44 -> Voltage(Kv) : 1.03803 -> ATC : 9.000 (MW)Shunt: 45 -> Voltage(Kv) : 1.03829 -> ATC : 16.000 (MW)
Shunt: 46 -> Voltage(Kv) : 1.03855 -> ATC : 25.000 (MW)
Shunt: 47 -> Voltage(Kv) : 1.03881 -> ATC : 34.00 (MW)
Shunt: 48 -> Voltage(Kv) : 1.03906 -> ATC : 29.00 (MW)Shunt: 49 -> Voltage(Kv) : 1.03932 -> ATC : 21.00 (MW)
Shunt: 50 -> Voltage(Kv) : 1.03958 -> ATC : 12.00 (MW)
_________________________________________________________
Final ATC : 39.0000 (MW) at shunt :5.00 (Mvar) at bus no 5
_________________________________________________________
Program.txt
http://bhargav.txt/http://bhargav.txt/ -
8/3/2019 424 Final
43/50
Result
1 2 3 4 5 6 7-0.4
-0.2
0
0.2
0.4Plot for distribution factor at given Line
Line No.
Distributionfactor
0 5 10 15 20 25 30 35 40 45 500
10
20
30
40
X: 5
Y: 39
Shunt MVar
ATC
-
8/3/2019 424 Final
44/50
Conclusion & Future Scope
It conclude that ATC calculation is very important &mandatory for Open Access in power system inDeregulated Electrical Market .
In future with the help of some optimization techniqueslike genetic algorithm, Particle Swam Optimization, wecan optimized reactive power injection at weak bus.
-
8/3/2019 424 Final
45/50
References1. S.A.Kapharde, Congestion management
2. A.R Abhayankar,prof.S.A.Khaparde Introduction to deregulation in power industry.
3. J.Bailek, Tracing of the Flow of ElectricityIEE Proc-Generation, transmission, Distribution, Vol.143, pp 313-320, July 1996.
4. G.C.Ejebe, j.Tong, J.G.Waight, J.G.Frame, X. Wang & W.F. Tinney Available transfer capabilityCalculations PE-321-PWRS-0-10-97,IEEE transaction on power system,vol-13,No.4 pp 1521 to1527, 1998
5. Mark H. Gravener, Chika Nwankpa, Tai-sim Yeoh , ATC computational issues Proceedings of32nd Hawali International Conference on system Sciences-1999
6. R.D.Christie, B.F.Wollenberg, I.Wangensteen, Transmission management in deregulatedenvironment Proceeding of IEEE, 88, No.2 , pp 449-451, Feb 2000
7. G. Hamoud, Assessment of Available Transfer capability of transmission system:,IEEEtransaction on Power system vol-15, No-1, pp 27-32, February,2000.
8. Mohamed Shaaban, Yaxin Ni, Felix F.Wu, Transfer Capability Computation in Deregulated Powersystems Proceddings of 32nd Hawali International Conference on system Sciences-2000
9. S.N. Singh ,A.K. David, Optimum Location of FACTS devices for congestion management,Electric Power system Research 58 (2001), pp 71-79, 2001.
10. Sarika Kushalani, S.A Khaparde, S.A. Soman, Congestion management in the Emerging Energy
Market Structure,Cigre Regional Meeting on Bulk Power Transmission System Integration inDeveloping countries, pp-VII-16 to 24 New Delhi Nov.2001
-
8/3/2019 424 Final
46/50
11. E.A Leonidaki, N.D.Hatziargyriou, G.A. Manos,A Systematic Approach for Effective Location ofSeries compensation to increased Available Transfer capabilityIEEE , Portio Power techConference , September 2001,Portugal.
12. N. Schnurr and W.H. Wellssow, Determination and Enhancement of the Available TransferCapability in FACTS.IEEE , Portio Power tech Conference , September 2001,Portugal.
13. Ashwani Kumar, S. C. Srivastav , Power Transaction Allocation in a Deregulated Market usingAC Power Transfer Distribution Factors Cigre Regional Meeting on Bulk Power TransmissionSystem Integration in Developing countries, pp-VIII-9 to 17 New Delhi Nov.2001
14. Chen-Ching Liu, Gerald T. Heydt, Abedal-Aty Edris, Impact of FACTS controller on Transfercapability of Power grid,IEEE, 2002, pp 556-261
15. Armando M. Leite da Silva, Fellow, IEEE, Joo Guilherme de Carvalho Costa, Luiz Antnio daFonseca Manso, and George J. Anders, Fellow, IEEE, Transmission Capacity: Availability,Maximum Transfer and ReliabilityIEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 17,NO. 3, AUGUST 2002.
16. Ying Xiao,Y.H.Song,Chen-Ching Liu and Y.Z. Sun, Available Transfer Capability Enhancementusing FACTS Devices,IEEE transaction on power system,vol-18,No.1 pp 305 to 312 , February2003
17. H.Y. Yamina a, S.M. Shahidehpour ,Congestion management coordination in the deregulatedpower market Electric Power Systems Research 65 (2003) 119/127
18. Ashwani Kumar , S.C. Srivastava , S.N. Singh , A zonal congestion management approach using actransmission congestion distribution factors, Electric Power Systems Research 72 (2004) 8593
-
8/3/2019 424 Final
47/50
20. B.Mozafari, A.M.Rajbar, A.R. Shirani & A.Barkeseh,A comprehensive Method forATCcalculation in deregulated power systemIEEE International conference on Electric UtilityDeregulation , Restructuring & Power Technology April 2004 , pp 680 to 685.
21. A Kazemi, H. Andami, FACTS Devices in Deregulated Electric Power system: A Review,international conference on Electric Utility Deregulation, Restructuring and Powertechnologies(DRPT2004), April 2004, Honkong.
22. H. Farahmand, Rasid-Nejad and M. Fotuhi-Firozabad Implement of FACTS Devices for ATC
Enhancement Using RPF techniques,IEEE ,2004, pp 30-3523. Linzhong Yao, Phill Cartwright. Laurent Schimitt, Xiao-Ping Zhang, Congestion Management ofTransmission System Usin FACTSIEEE/PES transmission and Distribution conference andexhibition: Asia and Pacific Dalian, China, 2005
24. Naresh Acharya,N. Mithulananthan, Locating Series FACTS devices for congestion managementin deregulated electricity markets, Electric Power system Research 2332 (2006), pp 1-9.
25. A.S. Nayak and M.A. Pai Congestion management in Restructured Power system using an optimalPower flow Frame work, University of Illinois at Urbana-Champaign
26. K. Bhattacharya, M.H.J.Bollen, J.E.Dalder, Operation of restructured power system,Kulwar
Acadamic Publishers, Boston.27. Wood & Woolen breg , Power generation Operation & control
19. Roberto Mendez and Huge Rudnick, Congestion Management and TransmissionRights in Centralized Electric Markets,IEEE transaction on power system Vol. 19
No.2, pp 889-896, May 2004.
-
8/3/2019 424 Final
48/50
28. Formation of Independent System Operator (ISO) Dr Sanjay GuptaSenior Consultant Energy & Utilities Group Infosys Technologies LimitedBangalore, India
29. N.G. Hingorani, Flexible A.C. transmission IEEE spectrum, April 1993, pp40-45
30. Abhijit chakravarti & Sunita Haldar Power system Analysis.
-
8/3/2019 424 Final
49/50
Reference Websites
www.powerexindia.com
www.iexindia.com
www.pserc.cornell.edu/tcc
www.powergridindia.com www.nldc.in
www.erldc.org
www.wrldc.com
www.spp.org Atc_april2010_powergrid
http://www.powerexindia.com/http://www.powerexindia.com/http://www.powerexindia.com/http://www.powerexindia.com/http://www.powerexindia.com/http://www.iexindia.com/http://www.iexindia.com/http://www.iexindia.com/http://www.pserc.cornell.edu/tcchttp://www.pserc.cornell.edu/tcchttp://www.pserc.cornell.edu/tcchttp://www.powergridindia.com/http://www.powergridindia.com/http://www.powergridindia.com/http://www.nldc.in/http://www.erldc.org/http://www.wrldc.com/http://www.spp.org/http://atc_jan10.xls/http://atc_jan10.xls/http://www.spp.org/http://www.wrldc.com/http://www.erldc.org/http://www.nldc.in/http://www.powergridindia.com/http://www.powergridindia.com/http://www.powergridindia.com/http://www.pserc.cornell.edu/tcchttp://www.pserc.cornell.edu/tcchttp://www.pserc.cornell.edu/tcchttp://www.iexindia.com/http://www.iexindia.com/http://www.iexindia.com/http://www.powerexindia.com/http://www.powerexindia.com/http://www.powerexindia.com/http://www.powerexindia.com/http://www.powerexindia.com/ -
8/3/2019 424 Final
50/50
Thank You