Endorsed and ranked at 2 nd EWG meeting 2015 Endorsed and ranked at 1st EWG meeting 2016 Project Session 1, 2016 APEC Secretariat Deadline: ~ February Concept Notes to be distributed to Expert Groups/Task Force at least 4 weeks in advance of second 2015 EWG meeting. - Concept Notes to be distributed to EWG 2 weeks in advance of second 2015 EWG meeting. - Concept Notes to be endorsed and ranked by group at second 2015 EWG meeting. Project Session 2, 2016 APEC Secretariat Deadline: ~ July Concept Notes to be distributed to Expert Groups/Task Force at least 4 weeks in advance of the first 2016 EWG meeting. - Concept Notes to be distributed to EWG 2 weeks in advance of the first 2016 meeting. - Concept Notes to be endorsed and ranked by group at the first 2016 EWG meeting. 3

TRANSCRIPT

Page 1: 49 th EWG Meeting, Gyeongju, Korea June 22-26, 2015

APEC Energy Working Group (EWG) Project

Process49th EWG Meeting, Gyeongju, Korea

June 22-26, 2015

Page 2: 49 th EWG Meeting, Gyeongju, Korea June 22-26, 2015

2

Need to clarify and streamline project proposal process

Seek to ensure proposals are closely aligned with the EWG Strategic Plan and priorities and guidance from Ministers and Leaders

Will clarify process for: ◦ Concept note (CN) endorsement, co-

sponsorship and submission, and◦ Final proposal and quality assessment

framework (QAF) review.

Revision to EWG Project Process

Page 3: 49 th EWG Meeting, Gyeongju, Korea June 22-26, 2015

3

New Project Approval Timeline

Endorsed and ranked at 2nd EWG meeting 2015

Endorsed and ranked at 1st EWG meeting 2016

Project Session 1, 2016APEC Secretariat Deadline:

~ February 2016

- Concept Notes to be distributed to Expert Groups/Task Force at least 4 weeks in advance of second 2015 EWG meeting.

- Concept Notes to be distributed to EWG 2 weeks in advance of second 2015 EWG meeting.

- Concept Notes to be endorsed and ranked by group at second 2015 EWG meeting.

Project Session 2, 2016APEC Secretariat Deadline:

~ July 2016

- Concept Notes to be distributed to Expert Groups/Task Force at least 4 weeks in advance of the first 2016 EWG meeting.

- Concept Notes to be distributed to EWG 2 weeks in advance of the first 2016 meeting.

- Concept Notes to be endorsed and ranked by group at the first 2016 EWG meeting.

Page 4: 49 th EWG Meeting, Gyeongju, Korea June 22-26, 2015

4

POs must obtain at least two co-sponsors ◦ Co-sponsorship must be conveyed in writing through

the economy’s EWG or Expert Group (EG)/Task Force (TF) representative (PO to provide a copy with the CN)

◦ Self-funded projects must also obtain at least two co-sponsors.

Once co-sponsors are obtained, PO submits CN through the sponsoring economy’s EG or TF member to relevant EG/TF Chair at least four weeks before the EWG meeting.◦ Chair will circulate group of proposals to EG or TF

members for review and endorsement.

Concept Note Development

Page 5: 49 th EWG Meeting, Gyeongju, Korea June 22-26, 2015

5

EG/TF members should ensure that CNs: ◦ match goals contained in EWG Strategic Plan, ◦ address gaps not already addressed, and ◦ support Energy Ministers’ and Leaders’ goals and

priorities. Note: only if a project does not fit with the

responsibilities of a specific EG/TF or is cross-cutting, may it be submitted directly to the EWG for review. ◦ PO must explain to EWG Secretariat why the project is

being submitted directly to the EWG rather than through an EG/TF.

Expert Group/Task Force Review

Page 6: 49 th EWG Meeting, Gyeongju, Korea June 22-26, 2015

6

Once approved by EG or TF, submit to EWG for endorsement◦ EG/TF Chair will forward CN to EWG Secretariat, with

copy to APEC Secretariat, confirming EG/TF approval.◦ EWG Secretariat will circulate CN to EWG members

for endorsement.◦ No changes to the CN are permitted after circulation

unless these are required by members for endorsement.

◦ Note: unless projects are submitted at least two weeks before an EWG meeting, they will not be considered for endorsement.

Concept Note Submission to EWG

Page 7: 49 th EWG Meeting, Gyeongju, Korea June 22-26, 2015

7

EWG Secretariat will submit CNs to EWG Members 2 weeks before the relevant EWG meeting.

EWG members will discuss and rank EWG CNs at relevant EWG meeting, ensuring projects are aligned with the EWG Strategic Plan and Energy Ministers’ and Leaders’ goals and priorities.

Once endorsed by EWG, EWG Secretariat will submit CNs to APEC Secretariat.◦ EGs and POs should not submit CNs directly.

Note: EWG Members are encouraged to share EWG ranking with their SOM representatives.

EWG Technical Review

Page 8: 49 th EWG Meeting, Gyeongju, Korea June 22-26, 2015

8

The APEC Secretariat will review CNs received from the EWG Secretariat for compliance with the Guidebook for APEC Projects.◦ Compliant CNs received by the Final Submission Deadline will be

referred to the SOM Steering Committee on ECOTECH (SCE) for consideration.

◦ Non-compliant CNs will be referred back to the PO and sponsoring economy representative for amendment.

◦ If non-compliant CNs are corrected and re-submitted prior to the Final Submission Deadline they will be referred to SCE for consideration.

The APEC Secretariat will inform EWG members (including EG/TF Chairs) of the final list of CNs referred to SCE, as ranked by the EWG.

CN Submission to APEC Secretariat

Page 9: 49 th EWG Meeting, Gyeongju, Korea June 22-26, 2015

9

If approved in principle for funding, APEC Secretariat will notify PO and request a full project proposal and QAF.◦ APEC Secretariat will also notify EWG members of the full list of

CNs approved in principle for funding. Once QAF is completed by at least 2 economies,

PO submits the project proposal and Consolidated QAF document directly to APEC Secretariat with copy to EWG Secretariat.◦ Any member economy, including co-sponsoring economies, may

contribute to a QAF.◦ Note: QAF requests for any economy must go through the

economy’s EWG or Expert Group/Task Force representative.

Final Proposal and QAF

Page 10: 49 th EWG Meeting, Gyeongju, Korea June 22-26, 2015

10

APEC Secretariat submits the Project Proposal and Consolidated QAF to all EWG members (including EG/TF Chairs) for review and endorsement. ◦ Expert Group/Task Force Chairs circulate to their groups.

After the Project Proposal is endorsed by EWG, the APEC Secretariat will proceed with the formal assessment of the endorsed document and referral for approval.

The APEC Secretariat will inform all EWG members (including EG/TF Chairs) of the final list of Project Proposals approved by the Budget and Management Committee.◦ Expert Group/Task Force Chairs circulate to their groups.

Final Proposal and QAF (cont.)

Page 11: 49 th EWG Meeting, Gyeongju, Korea June 22-26, 2015

Questions?