    BUREAU VERITAS MARINE DIVISION

    PORT STATE CONTROLInspection Preparation

    Checklist

    Accommodations

    This Check list is issued to assist you to check the maintenancecondition of the ship in the light of possible port state control

    inspection.

    It does not in any way replace or cover the scope of classand/or statutory surveys carried out by Bureau Veritas, the flagstate or by Bureau Veritas on behalf of the flag state.

    It is not exhaustive and contains those items which according tothe information in Bureau Veritas possession are morefrequently inspected and/or found defective during port statecontrol inspections. It is given for guidance only.

  • 7/29/2019 5 - Checklist for PSC inspections - Accommodations.pdf

    2/3

    Accommodations

    1. Fire doors

    Examination of manual and automatic fire doors and verification of theirworking condition and able to close tight

    Verification that fire doors are self closing and self latching, ensure self closingdoors have no hold back arrangements fitted other than those that can beremotely released e.g. magnetic

    2. Fire fighting equipment

    Examination of the fire-fighting appliances, with working test as far asnecessary and practicable

    Examination of the hydrants, hoses, spanners and nozzles and confirmationthat they are at their respective locations

    Examination of the international shore connection and confirmation that it islocated as shown on the Fire Control Plan

    Verification that the connection bolts dimensions is as per regulation and mustbe stored next to the connection. The correct joint must also be available at

    the location as should correct size spanner

    Confirmation that the fire fighter's outfits are complete (correct number of suitsare available) and in satisfactory condition

    Confirmation that the cylinders, including the spare cylinders, of any self-contained breathing apparatus are suitably charged

    3. Fire control plan

    Confirmation that the fire-control plans are permanently exhibited, or,alternatively, that emergency booklets containing information dealing with firefighting are available on board

    Confirmation that a duplicate copy of the fire-control plans (or booklet) isavailable in a prominently marked enclosure, external to the ship's deckhouse

  • 7/29/2019 5 - Checklist for PSC inspections - Accommodations.pdf

    3/3

    4. Signs, indications (weather tight doors, fire detectors, fire

    dampers,ventilation)

    All in place and as required

    5. Emergency lighting and batteries

    Tests of emergency lighting, transitional emergency lighting andsupplementary emergency lighting

    Verification that batteries are fully charged

    6. Alarms and PA Systems

    Tests of general emergency alarms & signals, operational alarms and publicaddress systems functioning and clearly audible in all areas

    7. Sanitary facilities

    Equipment in place, clean and functioning correctly

    Hot water available at wash areas and in the galley

    Living facilities adequate for conditions, ample bed covers etc

    Living areas clean and hygienic