    Estimate Line Detail

    Estimate: 2009-2 - Process Plant ProjectCurrency: AED-United Arab Emirates-Dirham

    Item Description Quantity UOM Rate ManHrs Labor Equip Job Mat Perm Mat Mech Elec Eq Sub/Plug Total Cost

    12100000EXCAVATION (GRAVEL & SOIL)

    Including surfacing & compacyion 95%7,868.73 m3 1,617 11,379 20,088 260,000 291,467

    0.21 1.45 2.55 33.04 37.04

    000030 EXCAVATION (GRAVEL & SOIL)Including surfacing & compacyion 95% 7,081.86 m3 435 5,075 20,088 25,163

    0.06 0.72 2.84 3.55

    Prod=24.42 m3/hour, 0.061MH/m3, 16.28 m3/MH, 290.00 hour

    Excavate & Load 1.5 CY (Cat 325) Backhoe 1.00 EA 86.77

    Equipment Operator Foreman 0.5 13.00 1,885

    Backhoe Operator 1.0 11.00 3,190

    Excavator, Komatsu 1.0 62.56 18,142

    Pick-up Double Cabin 0.5 13.42 1,946

    000040EXCAVATION (GRAVEL & SOIL)

    Including surfacing & compacyion 95%786.87 m3 1,182 6,304 6,304

    1.50 8.01 8.01

    Prod=3.99 m3/hour, 1.502MH/m3, 0.67 m3/MH, 197.00 hour

    Excavate Loam by Hand 1.00 EA 32

    Leadman Labour 1.0 7.00 1,379

    Labourer 5.0 5.00 4,925

    000050 Wellpoint Dewatering 200mm (8") Pump 1.00 LS 260,000 260,000

    260,000.00 260,000.00

    Well Point Dewatering 1.0 LS 260,000.00 260,000

    12100010 BACKFILLING & COMPACTIONw/imported soil, 50mm sieve 100% passing, #200 sieve 0~20

    passing, LL=Max.35, PL=Max.12

    3,429.75 m3 1,350 11,880 37,101 96,033 145,014

    0.39 3.46 10.82 28.00 42.28

    000010

    BACKFILLING & COMPACTIO

    w/imported soil, 50mm sieve 100% passing, #200 sieve 0~20

    passing, LL=Max.35, PL=Max.1

    3,429.75 m3 1,350 11,880 37,101 96,033 145,014

    0.39 3.46 10.82 28.00 42.28

    Prod=12.70 m3/hour, 0.394MH/m3, 2.54 m3/MH, 270.00 hour

    Place Granular Backfill with 2.7 CY Loader 1.00 EA 181.41

    Equipment Operator Foreman 1.0 13.00 3,510

    Loader Operator 1.0 11.00 2,970

    Packer Operator 1.0 10.00 2,700Labourer 2.0 5.00 2,700

    Loader, 966f 1.0 62.44 16,859

    Jumping Jack Tamper 1.0 3.78 1,021

    22" Smooth Drum Manual (Bomag 55) 1.0 10.00 2,700

    Roller 1 Steel Drum 1.0 47.77 12,898

    Pick-up Double Cabin 1.0 13.42 3,623

    BACKFILLING & COMPACTION

    w/imported soil, 50mm sieve 100% passing, #200 sieve 0~20

    passing, LL=Max.35, PL=Max.12 3,429.8 m3 28.00 96,033

    12100020 BACKFILLING & COMPACTION 6,073.74 m3 2,391 21,038 65,702 170,065 256,805

    0.39 3.46 10.82 28.00 42.28

    000010 BACKFILLING & COMPACTION 6,073.74 m3 2,391 21,038 65,702 170,065 256,805

    0.39 3.46 10.82 28.00 42.28

  • 8/10/2019 52- Process Plant Buildings Estimate Detail

    2/35

    08/11/2009 2:45:17 PM Page No 2 of 35

    Item Description Quantity UOM Rate ManHrs Labor Equip Job Mat Perm Mat Mech Elec Eq Sub/Plug Total Cost

    Prod=12.70 m3/hour, 0.394MH/m3, 2.54 m3/MH, 478.14 hour

    Place Granular Backfill with 2.7 CY Loader 1.00 EA 181.41

    Equipment Operator Foreman 1.0 13.00 6,216

    Loader Operator 1.0 11.00 5,260

    Packer Operator 1.0 10.00 4,781Labourer 2.0 5.00 4,781

    Loader, 966f 1.0 62.44 29,855

    Jumping Jack Tamper 1.0 3.78 1,807

    22" Smooth Drum Manual (Bomag 55) 1.0 10.00 4,781

    Roller 1 Steel Drum 1.0 47.77 22,841

    Pick-up Double Cabin 1.0 13.42 6,417

    BACKFILLING & COMPACTION

    w/imported soil, 50mm sieve 100% passing, #200 sieve 0~20passing, LL=Max.35, PL=Max.12 6,073.7 m3 28.00 170,065

    12100030DISPOSAL (10KM)

    Unfactored soil, Disposal area(10km far)1,403.14 m3 175 1,754 7,117 8,871

    0.13 1.25 5.07 6.32

    000010 Disposal,Machine,0-10km ( Distance ) 1,403.14 m3 175 1,754 7,117 8,871

    0.13 1.25 5.07 6.32

    Prod=8.00 m3/hour, 0.125MH/m3, 8.00 m3/MH, 175.39 hour

    DISPOSAL (10KM)Unfactored soil, Disposal area(10km far)

    1.00 EA 50.58

    Highway Truck Driver 1.0 10.00 1,754

    Dump Truck 1.0 40.58 7,117

    12100040GRAVEL COMPACT.Aggregate base course,THK=150mm

    784.39 m3 314 2,275 6,840 47,063 56,178

    0.40 2.90 8.72 60.00 71.62

    000010 GRAVEL COMPACT.Aggregate base course,THK=150mm 784.39 m3 314 2,275 6,840 47,063 56,178

    0.40 2.90 8.72 60.00 71.62

    Prod=10.00 m3/hour, 0.400MH/m3, 2.50 m3/MH, 78.44 hour

    Place Granular Base under Concrete Slab with D3 Dozer 1.00 EA 116.2

    Dozer Operator 1.0 11.00 863

    Leadman Civil 1.0 8.00 628

    Labourer 2.0 5.00 784

    Dozer, D8N 1.0 77.20 6,055

    22" Smooth Drum Manual (Bomag 55) 1.0 10.00 784

    Aggregate base course,THK=150mm 784.4 m3 60.00 47,063

    12100050 Imported sand for sand bedding(w/Soil compaction underneath the

    i

    1,148.85 m3 161 1,356 7,820 32,168 41,343

    0.14 1.18 6.81 28.00 35.99

    000010 Imported sand for sand bedding(w/Soil compaction underneath the

    i

    1,148.85 m3 161 1,356 7,820 32,168 41,343

    0.14 1.18 6.81 28.00 35.99

    Prod=50.00 m3/hour, 0.140MH/m3, 7.14 m3/MH, 22.98 hour

    Place Sand Bedding, per m3 1.00 EA 399.33

    Equipment Operator Foreman 1.0 13.00 299

    Backhoe Operator 1.0 11.00 253

    Loader Operator 1.0 11.00 253

    Labour Foreman 1.0 9.00 207Labourer 3.0 5.00 345

    Loader, 966f 1.0 62.44 1,435

    Backhoe/Loader 1.0 34.41 791

  • 8/10/2019 52- Process Plant Buildings Estimate Detail

    3/35

    08/11/2009 2:45:17 PM Page No 3 of 35

    Item Description Quantity UOM Rate ManHrs Labor Equip Job Mat Perm Mat Mech Elec Eq Sub/Plug Total Cost

    Dump Truck 6.0 40.58 5,594

    Sand Bedding 1,148.9 m3 28.00 32,168

    12100060LAYING PE FILMFLOOR.(0.25MMX1PLIES)

    6,907.93 m2 205 1,746 13,968 15,714

    0.03 0.25 2.02 2.27

    000010 LAYING PE FILMFLOOR.(0.25MMX1PLIES) 6,907.93 m2 205 1,746 13,968 15,714

    0.03 0.25 2.02 2.27

    1/4" (6 mm) Polyethelene 6,983.9 m2 2.00 13,968

    Carpenter Foreman 1.0 12.00 616

    Carpenter 2.0 8.00 821

    Carpenter Helper 1.0 6.00 308

    12100070GRAVEL PAVING

    THK=100927.08 m2 139 1,147 1,543 4,079 6,770

    0.15 1.24 1.66 4.40 7.30

    000010GRAVEL PAVING

    THK=10092.71 m3 139 1,147 1,543 4,079 6,770

    1.50 12.37 16.65 44.00 73.02

    Prod=2.67 m3/hour, 1.500MH/m3, 0.67 m3/MH, 34.77 hour

    Backfilling with Compaction 1.00 EA 77.39

    Loader Operator 1.0 11.00 382

    Leadhand 1.0 12.00 417

    Labourer 2.0 5.00 348

    Backhoe/Loader 1.0 34.41 1,196

    Jumping Jack Tamper 1.0 3.78 131

    22" Smooth Drum Manual (Bomag 55) 1.0 6.20 216

    Granular Backfill 102.0 m3 40.00 4,079

    12100080

    . .

    Havy duty expanded metal mesh - Hot dip galvanized(including Fence

    l ~

    923.95 m 1,007 8,562 8,394 383,439 400,395

    1.09 9.27 9.09 415.00 433.35

    000010

    . .

    Havy duty expanded metal mesh - Hot dip galvanized(including Fence

    l ~

    923.95 m 1,007 8,562 8,394 383,439 400,395

    1.09 9.27 9.09 415.00 433.35

    Prod=5.50 m/hour, 1.090MH/m, 0.92 m/MH, 167.88 hour

    Install Chainlink Fence 2400mm (8 FT) 1.00 EA 101

    Auger Operator 1.0 12.00 2,015

    Labour Foreman 1.0 9.00 1,511

    Labourer 2.0 5.00 1,679

    Carpenter Foreman 1.0 12.00 2,015

    Carpenter 1.0 8.00 1,343

    Truck Mounted Post Hole Auger 1.0 50.00 8,394

    FENCE (P.V.C COATING)Havy duty expanded metal mesh - Hot dip galvanized(including Fence

    Door),removable, 8~12 gage 13mm Max.gap 924.0 m 415.00 383,439

    12210000FORM (PLYWOOD)

    above ground12,326.21 m2 35,644 267,086 107,048 443,744 817,877

    2.89 21.67 8.68 36.00 66.35

    000010FORM (PLYWOOD)above ground

    12,326.21 m2 35,644 267,086 107,048 443,744 817,877

    2.89 21.67 8.68 36.00 66.35

    Prod=2.67 m2/hour, 1.174MH/m2, 0.85 m2/MH, 1,542.75 hour

    Fabricate Light Formwork 1.00 EA 46.09

    Formsetter Foreman 0.1 14.00 2,808

    Formsetter 2.0 8.00 24,684

  • 8/10/2019 52- Process Plant Buildings Estimate Detail

    4/35

    08/11/2009 2:45:17 PM Page No 4 of 35

    Item Description Quantity UOM Rate ManHrs Labor Equip Job Mat Perm Mat Mech Elec Eq Sub/Plug Total Cost

    Formsetter Helper 1.0 6.00 9,257

    Generator, 10-30 kva 1.0 6.65 10,259

    Dyna truck, 2.5 ton 1.0 15.62 24,098

    Prod=2.45 m2/hour, 2.500MH/m2, 0.40 m2/MH, 5,027.00 hour

    Set Strip Footing Forms 1.00 EA 60.28

    Formsetter Foreman 0.1 14.00 9,149

    Formsetter 4.0 8.00 160,864

    Formsetter Helper 2.0 6.00 60,324

    Generator, 10-30 kva 1.0 6.65 33,430

    Dyna truck, 2.5 ton 0.5 15.62 39,261

    Form Work Materials 12,326.2 m2 36.00 443,744

    12210010FORM (PLYWOOD)

    for U/G concrete3,897.14 m2 11,270 84,444 33,845 140,297 258,586

    2.89 21.67 8.68 36.00 66.35

    000010FORM (PLYWOOD)

    for U/G concrete3,897.14 m2 11,270 84,444 33,845 140,297 258,586

    2.89 21.67 8.68 36.00 66.35

    Prod=2.67 m2/hour, 1.174MH/m2, 0.85 m2/MH, 487.77 hour

    Fabricate Light Formwork 1.00 EA 46.09

    Formsetter Foreman 0.1 14.00 888

    Formsetter 2.0 8.00 7,804

    Formsetter Helper 1.0 6.00 2,927

    Generator, 10-30 kva 1.0 6.65 3,244

    Dyna truck, 2.5 ton 1.0 15.62 7,619

    Prod=2.45 m2/hour, 2.500MH/m2, 0.40 m2/MH, 1,589.37 hour

    Set Strip Footing Forms 1.00 EA 60.28

    Formsetter Foreman 0.1 14.00 2,893Formsetter 4.0 8.00 50,860

    Formsetter Helper 2.0 6.00 19,072

    Generator, 10-30 kva 1.0 6.65 10,569

    Dyna truck, 2.5 ton 0.5 15.62 12,413

    Form Work Materials 3,897.1 m2 36.00 140,297

    12220000 For U/G Plain Con'c.,ASTM 17MPa,ASTM C150 TYPE I minimum

    i

    317.49 m3 317 1,746 540 75,721 78,007

    1.00 5.50 1.70 238.50 245.70

    000010 For U/G Plain Con'c.,ASTM 17MPa,ASTM C150 TYPE I minimum

    i

    317.49 m3 317 1,746 540 75,721 78,007

    1.00 5.50 1.70 238.50 245.70

    Prod=8.00 m3/hour, 1.000MH/m3, 1.00 m3/MH, 39.69 hour

    Place Lean Concrete direct from truck 1.00 EA 57.6

    Labour Foreman 1.0 9.00 357

    Concrete Labourer 4.0 5.00 794

    Vibrator Operator 2.0 5.00 397

    Concrete Spotter 1.0 5.00 198

    Daihatsu pickup, 3 ton 1.0 13.60 540

    2,000 PSI (15 MPA) Readymix Concrete 336.5 m3 225.00 75,721

    12220010For A/G RC,ASTM 35MPa,ASTM C150 TYPE I + Micro silica Fume 6%

    Minimum Cement Content 364kg/cm3 Max W/C Ratio 0.4, Calcium1,703.25 m3 122,634 572,241 694,875

    72.00 335.97 407.97

    000010 For A/G RC,ASTM 35MPa,ASTM C150 TYPE I + Micro silica Fume 6%Minimum Cement Content 364kg/cm3 Max W/C Ratio 0.4, Calcium

    1,703.25 m3 122,634 572,241 694,875

    72.00 335.97 407.97

    Concrete coating as per APCS-10 5,109.8 m2 24.00 122,634

  • 8/10/2019 52- Process Plant Buildings Estimate Detail

    5/35

    08/11/2009 2:45:17 PM Page No 5 of 35

    Item Description Quantity UOM Rate ManHrs Labor Equip Job Mat Perm Mat Mech Elec Eq Sub/Plug Total Cost

    5,000 PSI (35 MPA) Readymix Concrete 1,805.4 m3 315.00 568,715

    Curing Agent 5,109.8 m2 0.69 3,526

    12220020For U/G RC,ASTM 35MPa,ASTM C150 TYPE I + Micro silica 6%Minimum Cement Content 364kg/cm3 Max W/C Ratio 0.4, Caicium

    2,797.70 m3 201,434 939,943 1,141,378

    72.00 335.97 407.97

    000010 For U/G RC,ASTM 35MPa,ASTM C150 TYPE I + Micro silica 6%Minimum Cement Content 364kg/cm3 Max W/C Ratio 0.4, Caicium 2,797.70 m3 201,434 939,943 1,141,378

    72.00 335.97 407.97

    Concrete coating as per APCS-10 8,393.1 m2 24.00 201,434

    5,000 PSI (35 MPA) Readymix Concrete 2,965.6 m3 315.00 934,152

    Curing Agent 8,393.1 m2 0.69 5,791

    12220030 CON'C POURING ( PUMPCAR) 1,703.25 m3 3,626 23,614 7,525 31,138

    2.13 13.86 4.42 18.28

    000010 CON'C POURING ( PUMPCAR) 1,703.25 m3 3,407 21,196 7,525 28,721

    2.00 12.44 4.42 16.86

    Prod=4.50 m3/hour, 2.000MH/m3, 0.50 m3/MH, 378.50 hour

    Place Concrete for Buildings with Crane 1.00 EA 75.88

    Labour Foreman 1.0 9.00 3,407

    Labourer 2.0 5.00 3,785

    Concrete Labourer 3.0 5.00 5,678

    Truck Spotter 1.0 6.00 2,271

    Mason 2.0 8.00 6,056

    Concrete Vibrator 1.0 3.00 1,136

    Generator, 55-131kw 1.0 16.88 6,389

    000020 Apply Concrete Curing Agent 5,109.75 m2 220 2,418 2,418

    0.04 0.47 0.47Prod=46.50 m2/hour, 0.043MH/m2, 23.25 m2/MH, 109.89 hour

    Apply Concrete Curing Agent 1.00 EA 22

    Cement Finisher 2.0 11.00 2,418

    12220040CON'C POURING (REMICON)

    for U/G Concrete3,115.19 m3 5,425 35,262 6,967 42,229

    1.74 11.32 2.24 13.56

    000010CON'C POURING (REMICON)

    for U/G Concrete3,115.19 m3 3,154 19,626 6,967 26,593

    1.01 6.30 2.24 8.54

    Prod=8.89 m3/hour, 1.013MH/m3, 0.99 m3/MH, 350.46 hour

    Place Concrete for Buildings with Crane 1.00 EA 75.88

    Labour Foreman 1.0 9.00 3,154

    Labourer 2.0 5.00 3,505

    Concrete Labourer 3.0 5.00 5,257

    Truck Spotter 1.0 6.00 2,103

    Mason 2.0 8.00 5,607

    Concrete Vibrator 1.0 3.00 1,051

    Generator, 55-131kw 1.0 16.88 5,916

    000020 Apply Concrete Curing Agent 9,345.57 m2 402 4,422 4,422

    0.04 0.47 0.47Prod=46.50 m2/hour, 0.043MH/m2, 23.25 m2/MH, 200.98 hour

  • 8/10/2019 52- Process Plant Buildings Estimate Detail

    6/35

    08/11/2009 2:45:17 PM Page No 6 of 35

    Item Description Quantity UOM Rate ManHrs Labor Equip Job Mat Perm Mat Mech Elec Eq Sub/Plug Total Cost

    Apply Concrete Curing Agent 1.00 EA 22

    Cement Finisher 2.0 11.00 4,422

    000030 Bituminous Coating 9,345.57 m2 1,869 11,215 11,215

    0.20 1.20 1.20Prod=20.00 m2/hour, 0.200MH/m2, 5.00 m2/MH, 467.28 hour

    Bituminous Coating 1.00 EA 24

    Labour Foreman 1.0 9.00 4,206

    Labourer 3.0 5.00 7,009

    12230000RE-BAR 1Dia.10~32mm,ASTM A615/A615M Grade 60, Uncoated

    438.84 ton 1,217,781 1,217,781

    2,775.00 2,775.00

    000010RE-BAR 1

    Dia.10~32mm,ASTM A615/A615M Grade 60, Uncoated438.84 ton 1,217,781 1,217,781

    2,775.00 2,775.00

    Supply Uncoated Reinforcing Steel 460.8 t 2,500.00 1,151,955Rebar Tie Wire 6,582.6 kg 10.00 65,826

    12230010

    -

    Dia.10~32,ASTM A615 Grade 60, Fusion bonded epoxy

    i i ~ i

    153.24 ton 586,143 586,143

    3,825.00 3,825.00

    000010

    -

    Dia.10~32,ASTM A615 Grade 60, Fusion bonded epoxyi i ~ i

    153.24 ton 586,143 586,143

    3,825.00 3,825.00

    Supply Epoxy Coated Reinforcing Steel 160.9 t 3,500.00 563,157

    Rebar Tie Wire 2,298.6 kg 10.00 22,986

    12230020 RE-BAR MANUFACTURING AND FITTING 592.08 ton 11,223 89,786 16,962 106,748

    18.96 151.64 28.65 180.29

    000010 RE-BAR MANUFACTURING AND FITTING 592.08 ton 11,223 89,786 16,962 106,748

    18.96 151.64 28.65 180.29

    Prod=3.33 t/hour, 0.900MH/t, 1.11 t/MH, 177.62 hour

    Handle Reinforcing Steel 1.00 EA 47.18

    Crane Operator Class-A 1.0 12.00 2,131

    Steel Fixer Helper 2.0 6.00 2,131

    5 Ton Boomtruck 1.0 23.18 4,117

    Prod=0.72 t/hour, 18.056MH/t, 0.06 t/MH, 822.33 hour

    Place Reinforcing Steel 1.00 EA 119.62

    Steel Fixer Foreman 1.0 12.00 9,868

    Steel Fixer 10.0 8.00 65,787

    Steel Fixer Helper 2.0 6.00 9,868

    Dyna truck, 2.5 ton 1.0 15.62 12,845

    12300000 (ASTM C129,TYPE?),Including solid concrete fill,12mm vertical

    i l i i i i i l i l

    66.36 m2 93 774 83 4,977 5,834

    1.40 11.67 1.25 75.00 87.91

    000010 (ASTM C129,TYPE?),Including solid concrete fill,12mm vertical

    i l i i i i i l i l

    66.36 m2 93 774 83 4,977 5,834

    1.40 11.67 1.25 75.00 87.91

    Prod=4.29 m2/hour, 1.400MH/m2, 0.71 m2/MH, 15.48 hour

    Lay Concrete Block, 150mm (6") Thick 1.00 EA 55.34

  • 8/10/2019 52- Process Plant Buildings Estimate Detail

    7/35

    08/11/2009 2:45:17 PM Page No 7 of 35

    Item Description Quantity UOM Rate ManHrs Labor Equip Job Mat Perm Mat Mech Elec Eq Sub/Plug Total Cost

    Mason Foreman 1.0 12.00 186

    Mason 4.0 8.00 495

    Mason Helper 1.0 6.00 93

    Cement Mixer 1.0 5.34 83

    6 CONCRETE BLOCK WORK

    (ASTM C129,TYPE?),Including solid concrete fill,12mm vertical

    reinforcement & tooled finish(Min. 2hr. fire rated) including block mesh 66.4 m2 75.00 4,977

    12300010 (ASTM C129,TYPE?),Including solid concrete fill,12mm vertical

    i l i i i i i l i l

    647.52 m2 1,230 10,252 1,095 58,277 69,624

    1.90 15.83 1.69 90.00 107.52

    000010 (ASTM C129,TYPE?),Including solid concrete fill,12mm vertical

    i l i i i i i l i l

    647.52 m2 1,230 10,252 1,095 58,277 69,624

    1.90 15.83 1.69 90.00 107.52

    Prod=3.16 m2/hour, 1.900MH/m2, 0.53 m2/MH, 205.05 hour

    Lay Concrete Block, 150mm (8") Thick 1.00 EA 55.34

    Mason Foreman 1.0 12.00 2,461

    Mason 4.0 8.00 6,562

    Mason Helper 1.0 6.00 1,230Cement Mixer 1.0 5.34 1,095

    8 CONCRETE BLOCK WORK

    (ASTM C129,TYPE?),Including solid concrete fill,12mm vertical

    reinforcement & tooled finish(Min. 2hr. fire rated) including block mesh 647.5 m2 90.00 58,277

    12300020 (ASTM C129,TYPE?),Including solid concrete fill,12mm verticali l i i i i i l i l

    1,800.00 m2 4,320 36,000 3,845 198,000 237,845

    2.40 20.00 2.14 110.00 132.14

    000010 (ASTM C129,TYPE?),Including solid concrete fill,12mm verticali l i i i i i l i l

    1,800.00 m2 4,320 36,000 3,845 198,000 237,845

    2.40 20.00 2.14 110.00 132.14

    Prod=2.50 m2/hour, 2.400MH/m2, 0.42 m2/MH, 720.00 hour

    Lay Concrete Block, 150mm (10") Thick 1.00 EA 55.34

    Mason Foreman 1.0 12.00 8,640

    Mason 4.0 8.00 23,040

    Mason Helper 1.0 6.00 4,320

    Cement Mixer 1.0 5.34 3,845

    10 CONCRETE BLOCK WORK(ASTM C129,TYPE?),Including solid concrete fill,12mm vertical

    reinforcement & tooled finish(Min. 2hr. fire rated) including block mesh 1,800.0 m2 110.00 198,000

    12300030LINTEL FAB.& INSTALL

    PC Lintel, 250 x 300mm11.50 m 43 308 113 706 1,127

    3.75 26.77 9.80 61.38 97.96

    000010 CON'C POURING (REMICON)for U/G Concrete

    11.50 m3 12 72 26 292 390

    1.01 6.30 2.24 25.38 33.92

    Prod=8.89 m3/hour, 1.013MH/m3, 0.99 m3/MH, 1.29 hour

    LINTEL FAB.& INSTALLPC Lintel, 250 x 300mm

    1.00 EA 75.88

    Labour Foreman 1.0 9.00 12

    Labourer 2.0 5.00 13

    Concrete Labourer 3.0 5.00 19

    Truck Spotter 1.0 6.00 8

    Mason 2.0 8.00 21

    Concrete Vibrator 1.0 3.00 4

    Generator, 55-131kw 1.0 16.88 22

    5,000 PSI (35 MPA) Readymix Concrete 0.9 m3 315.00 287

    Curing Agent 6.9 m2 0.69 5

  • 8/10/2019 52- Process Plant Buildings Estimate Detail

    8/35

    08/11/2009 2:45:17 PM Page No 8 of 35

    Item Description Quantity UOM Rate ManHrs Labor Equip Job Mat Perm Mat Mech Elec Eq Sub/Plug Total Cost

    000010FORM (PLYWOOD)

    above ground2.30 m2 31 235 87 414 736

    13.67 102.37 37.84 180.00 320.20

    Prod=2.67 m2/hour, 1.174MH/m2, 0.85 m2/MH, 0.86 hour

    Fabricate Light Formwork 1.00 EA 46.09

    Formsetter Foreman 0.1 14.00 2

    Formsetter 2.0 8.00 14

    Formsetter Helper 1.0 6.00 5

    Generator, 10-30 kva 1.0 6.65 6

    Dyna truck, 2.5 ton 1.0 15.62 13

    Prod=2.45 m2/hour, 2.500MH/m2, 0.40 m2/MH, 4.69 hour

    Set Strip Footing Forms 1.00 EA 60.28

    Formsetter Foreman 0.1 14.00 9

    Formsetter 4.0 8.00 150

    Formsetter Helper 2.0 6.00 56

    Generator, 10-30 kva 1.0 6.65 31

    Dyna truck, 2.5 ton 0.5 15.62 37Form Work Materials 11.5 m2 36.00 414

    12300040RE-BARDia.10~32mm,ASTM A615/A615M Grade 60, Uncoated

    17.94 ton 340 2,721 514 68,621 71,855

    18.96 151.64 28.65 3,825.00 4,005.29

    000010 RE-BAR MANUFACTURING AND FITTING 17.94 ton 340 2,721 514 3,234

    18.96 151.64 28.65 180.29

    Prod=3.33 t/hour, 0.900MH/t, 1.11 t/MH, 5.38 hour

    Handle Reinforcing Steel 1.00 EA 47.18

    Crane Operator Class-A 1.0 12.00 65Steel Fixer Helper 2.0 6.00 65

    5 Ton Boomtruck 1.0 23.18 125

    Prod=0.72 t/hour, 18.056MH/t, 0.06 t/MH, 24.92 hour

    Place Reinforcing Steel 1.00 EA 119.62

    Steel Fixer Foreman 1.0 12.00 299

    Steel Fixer 10.0 8.00 1,993

    Steel Fixer Helper 2.0 6.00 299

    Dyna truck, 2.5 ton 1.0 15.62 389

    000010

    -

    Dia.10~32,ASTM A615 Grade 60, Fusion bonded epoxyi i ~ i

    17.94 ton 68,621 68,621

    3,825.00 3,825.00Supply Epoxy Coated Reinforcing Steel 18.8 t 3,500.00 65,930

    Rebar Tie Wire 269.1 kg 10.00 2,691

    12300050GRANITE

    T=50(W=450)96.88 m2 123 1,042 76,293 77,335

    1.26 10.75 787.50 798.25

    000010GRANITE

    T=50(W=450)96.88 m2 123 1,042 76,293 77,335

    1.26 10.75 787.50 798.25

    Prod=3.16 m2/hour, 1.265MH/m2, 0.79 m2/MH, 30.63 hour

    GRANITE

    T=50(W=450)

    1.00 EA 34

    Tile Layer Foreman 1.0 12.00 368

    Tile Layer 2.0 8.00 490

    Tile Layer Helper 1.0 6.00 184

  • 8/10/2019 52- Process Plant Buildings Estimate Detail

    9/35

    08/11/2009 2:45:17 PM Page No 9 of 35

    Item Description Quantity UOM Rate ManHrs Labor Equip Job Mat Perm Mat Mech Elec Eq Sub/Plug Total Cost

    Granite Tile 101.7 m2 750.00 76,293

    12410000ANCHOR BOLT

    M25~M35, Hot Dip Galvanized276.00 EA 414 2,760 39,976 42,736

    1.50 10.00 144.84 154.84

    000010ANCHOR BOLT

    M25~M35, Hot Dip Galvanized276.00 EA 414 2,760 39,976 42,736

    1.50 10.00 144.84 154.84

    Prod=2.00 ea/hour, 1.500MH/ea, 0.67 ea/MH, 138.00 hour

    Set Large Anchor Bolts 1.00 EA 20

    Carpenter 1.0 8.00 1,104

    Carpenter Helper 2.0 6.00 1,656

    Anchor Bolts, M25 - M35 281.5 ea 142.00 39,976

    12410010ANCHOR BOLT

    hot dip galvarnize396.00 EA 594 3,960 57,357 61,317

    1.50 10.00 144.84 154.84

    000010ANCHOR BOLT

    hot dip galvarnize396.00 EA 594 3,960 57,357 61,317

    1.50 10.00 144.84 154.84

    Prod=2.00 ea/hour, 1.500MH/ea, 0.67 ea/MH, 198.00 hour

    Set Large Anchor Bolts 1.00 EA 20

    Carpenter 1.0 8.00 1,584

    Carpenter Helper 2.0 6.00 2,376

    Anchor Bolts, M25 - M35 403.9 ea 142.00 57,357

    12420000INSERT PLATEASTM A36

    10.35 ton 1,335 12,517 28,619 53,820 94,956

    129.00 1,209.37 2,765.11 5,200.00 9,174.49

    000010 INSERT PLATEASTM A36 10.35 t 1,335 12,517 28,619 53,820 94,956

    129.00 1,209.37 2,765.11 5,200.00 9,174.49

    Prod=0.06 t/hour, 129.000MH/t, 0.01 t/MH, 166.89 hour

    INSERT PLATEASTM A36

    1.00 EA 246.48

    Crane Operator Class-A 1.0 12.00 2,003

    Steel Fabrication Foreman 1.0 14.00 2,337

    Steel Fabricator 3.0 9.00 4,506

    Steel Fabricator Helper 2.0 6.00 2,003

    Rigger III 1.0 10.00 1,669

    400 Amp Diesel Welder 1.0 10.68 1,782

    Acetylene Cutting Torch 1.0 1.98 330

    Telescopic Boom Mobile Crane, 70 Ton 1.0 158.82 26,506ASTM A36 10.4 t 5,200.00 53,820

    12420010MISC. STEEL

    hot dip galvanized material42.80 ton 275,837 275,837

    6,444.80 6,444.80

    000010MISC. STEEL

    hot dip galvanized material42.80 ton 275,837 275,837

    6,444.80 6,444.80

    hot dip galvanized material 45.4 ton 6,080.00 275,837

    12420020 FAB. & INSTALL. OF MISC. STEEL 42.80 ton 7,447 69,818 159,631 229,448

    174.00 1,631.25 3,729.69 5,360.94000010 FAB. & INSTALL. OF MISC. STEEL 42.80 ton 7,447 69,818 159,631 229,448

    174.00 1,631.25 3,729.69 5,360.94

  • 8/10/2019 52- Process Plant Buildings Estimate Detail

    10/35

    08/11/2009 2:45:17 PM Page No 10 of 35

    Item Description Quantity UOM Rate ManHrs Labor Equip Job Mat Perm Mat Mech Elec Eq Sub/Plug Total Cost

    Prod=0.05 t/hour, 174.000MH/t, 0.01 t/MH, 930.90 hour

    FAB. & INSTALL. OF MISC. STEEL 1.00 EA 246.48

    Crane Operator Class-A 1.0 12.00 11,171

    Steel Fabrication Foreman 1.0 14.00 13,033

    Steel Fabricator 3.0 9.00 25,134

    Steel Fabricator Helper 2.0 6.00 11,171

    Rigger III 1.0 10.00 9,309

    400 Amp Diesel Welder 1.0 10.68 9,942

    Acetylene Cutting Torch 1.0 1.98 1,843

    Telescopic Boom Mobile Crane, 70 Ton 1.0 158.82 147,846

    12430000 AL. MOULDING 464.58 m 259 2,287 546 50,083 52,916

    0.56 4.92 1.18 107.80 113.90

    000010 AL. MOULDING 1.89 t 259 2,287 546 50,083 52,916

    137.00 1,210.17 289.07 26,498.76 27,997.99

    Prod=0.04 t/hour, 137.000MH/t, 0.01 t/MH, 43.16 hour

    AL. MOULDING 1.00 EA 65.66

    Steel Fabrication Foreman 1.0 14.00 604

    Steel Fabricator 3.0 9.00 1,165

    Steel Fabricator Helper 2.0 6.00 518

    400 Amp Diesel Welder 1.0 10.68 461

    Acetylene Cutting Torch 1.0 1.98 85

    AL. MOULDING 492.5 m 101.70 50,083

    12430010 SETTING NON-SLIP 115.63 m 41 363 87 11,194 11,643

    0.36 3.14 0.75 96.81 100.70

    000010 SETTING NON-SLIP 0.30 t 41 363 87 11,194 11,643

    137.00 1,210.17 289.07 37,312.00 38,811.24

    Prod=0.04 t/hour, 137.000MH/t, 0.01 t/MH, 6.85 hour

    SETTING NON-SLIP 1.00 EA 65.66

    Steel Fabrication Foreman 1.0 14.00 96

    Steel Fabricator 3.0 9.00 185

    Steel Fabricator Helper 2.0 6.00 82

    400 Amp Diesel Welder 1.0 10.68 73

    Acetylene Cutting Torch 1.0 1.98 14

    SETTING NON-SLIP 0.3 t 35,200.00 11,194

    12440000 GROUTMin.35MPa(7 days) : ASTM C1107

    8.26 m3 1,239 13,629 11,842 25,471

    150.00 1,650.00 1,433.68 3,083.68

    Prod=0.01 m3/hour, 150.000MH/m3, 0.01 m3/MH, 619.50 hour

    Non-shrink Grout 1.00 EA 22

    Cement Finisher 2.0 11.00 13,629

    Non-Shrink Grout 657.9 Bag 18.00 11,842

    12511000l. i i il l l

    140Gm/m2 Seperation layer+insulation : Thk=50 Extruded polystyrene

    = il

    1,376.70 m2 148,684 148,684

    108.00 108.00

    000010

    l. emen eig eig iles or ravel mm lya

    140Gm/m2 Seperation layer+insulation : Thk=50 Extruded polystyrene= il

    1,376.70 m2 148,684 148,684

    108.00 108.00

    Waterproofing works 1,376.7 m2 108.00 148,684

  • 8/10/2019 52- Process Plant Buildings Estimate Detail

    11/35

    08/11/2009 2:45:17 PM Page No 11 of 35

    Item Description Quantity UOM Rate ManHrs Labor Equip Job Mat Perm Mat Mech Elec Eq Sub/Plug Total Cost

    12511010SHEET-APPLIED MEMBRANE WATERPROOFING

    PU Waterproof Membrane1,460.50 m2 157,734 157,734

    108.00 108.00

    000010SHEET-APPLIED MEMBRANE WATERPROOFINGPU Waterproof Membrane

    1,460.50 m2 157,734 157,734

    108.00 108.00

    Waterproofing works 1,460.5 m2 108.00 157,734

    12511020WATERPROOF MORTAR

    For wall,T=30257.92 m2 387 3,288 9,027 12,316

    1.50 12.75 35.00 47.75

    000010WATERPROOF MORTAR

    For wall,T=30257.92 m2 387 3,288 9,027 12,316

    1.50 12.75 35.00 47.75

    Prod=2.67 m2/hour, 1.500MH/m2, 0.67 m2/MH, 96.72 hour

    WATERPROOF MORTARFor wall,T=30

    1.00 EA 34

    Carpenter Foreman 1.0 12.00 1,161

    Carpenter 2.0 8.00 1,548Carpenter Helper 1.0 6.00 580

    For wall,T=30 257.9 m2 35.00 9,027

    12511030 WATERPROOF MORTAR 385.66 m2 578 4,917 15,426 20,344

    1.50 12.75 40.00 52.75

    000010 WATERPROOF MORTAR 385.66 m2 578 4,917 15,426 20,344

    1.50 12.75 40.00 52.75

    Prod=2.67 m2/hour, 1.500MH/m2, 0.67 m2/MH, 144.62 hour

    WATERPROOF MORTAR 1.00 EA 34

    Carpenter Foreman 1.0 12.00 1,735

    Carpenter 2.0 8.00 2,314

    Carpenter Helper 1.0 6.00 868

    WATERPROOF MORTAR 385.7 m2 40.00 15,426

    12511040LIQUID WATERPROOFING

    For floor & Wall28.52 m2 11 97 3,993 4,090

    0.40 3.40 140.00 143.40

    Prod=10.00 m2/hour, 0.400MH/m2, 2.50 m2/MH, 2.85 hour

    LIQUID WATERPROOFINGFor floor & Wall

    1.00 EA 34

    Carpenter Foreman 1.0 12.00 34

    Carpenter 2.0 8.00 46Carpenter Helper 1.0 6.00 17

    For floor & Wall 28.5 m2 140.00 3,993

    12511050 Waterproof gypsum board(For wall), Waterproof plywood 9t + 331.20 m2 450 3,200 49,680 52,880

    1.36 9.66 150.00 159.66

    000010 Waterproof gypsum board(For wall), Waterproof plywood 9t + 331.20 m2 450 3,200 49,680 52,880

    1.36 9.66 150.00 159.66

    Prod=6.62 m2/hour, 1.359MH/m2, 0.74 m2/MH, 50.00 hour

    Waterproof gypsum board(For wall), Waterproof plywood 9t + 1.00 EA 64

    Labourer 4.0 5.00 1,000

    Carpenter Foreman 1.0 12.00 600

    Carpenter 4.0 8.00 1,600

  • 8/10/2019 52- Process Plant Buildings Estimate Detail

    12/35

    08/11/2009 2:45:17 PM Page No 12 of 35

    Item Description Quantity UOM Rate ManHrs Labor Equip Job Mat Perm Mat Mech Elec Eq Sub/Plug Total Cost

    WATERPROOF PROTECTION BOARD

    Waterproof gypsum board(For wall), Waterproof plywood 9t +

    Waterproofed gypsumboard 9t 331.2 m2 150.00 49,680

    12512000CAULKINGAround Doors & Windows

    700.00 m 210 1,680 19,600 21,280

    0.30 2.40 28.00 30.40

    000010CAULKINGAround Doors & Windows

    700.00 m 210 1,680 19,600 21,280

    0.30 2.40 28.00 30.40

    Prod=3.33 m/hour, 0.300MH/m, 3.33 m/MH, 210.00 hour

    Apply Joint Cauking 1.00 EA 8

    Carpenter 1.0 8.00 1,680

    Around Doors & Windows 700.0 m 28.00 19,600

    12512010 CONTROL JOINT 255.30 m 135 1,078 8,042 9,120

    0.53 4.22 31.50 35.72

    000010 CONTROL JOINT 255.30 m 112 899 7,148 8,047

    0.44 3.52 28.00 31.52

    Prod=2.27 m/hour, 0.440MH/m, 2.27 m/MH, 112.33 hour

    Apply Joint Sealant 1.00 EA 8

    Carpenter 1.0 8.00 899

    Apply Joint Sealant 255.3 m 28.00 7,148

    000020 CONTROL JOINT 255.30 m 22 180 894 1,073

    0.09 0.70 3.50 4.20

    Prod=11.36 m/hour, 0.088MH/m, 11.36 m/MH, 22.47 hour

    Install Backer Rod 1.00 EA 8

    Carpenter 1.0 8.00 180

    Install Backer Rod 255.3 m 3.50 894

    12512020WATER DRIP

    Water stop40.25 m 24 193 3,019 3,212

    0.60 4.80 75.00 79.80

    000010WATER DRIP

    Water stop40.25 m 24 193 3,019 3,212

    0.60 4.80 75.00 79.80

    8" (200 mm) Waterstop 40.3 m 75.00 3,019

    Formsetter 2.0 8.00 193

    12520000ROCK WOOL

    Wall (T=50)1,926.25 m2 240 2,040 24,271 26,311

    0.12 1.06 12.60 13.66

    000010ROCK WOOL

    Wall (T=50)1,926.25 m2 240 2,040 24,271 26,311

    0.12 1.06 12.60 13.66

    Prod=32.10 m2/hour, 0.125MH/m2, 8.03 m2/MH, 60.00 hour

    Install Wool Batt Insulation 1.00 EA 34

    Carpenter Foreman 1.0 12.00 720

    Carpenter 2.0 8.00 960

    Carpenter Helper 1.0 6.00 360

    Wall (T=50) 2,022.6 m2 12.00 24,271

  • 8/10/2019 52- Process Plant Buildings Estimate Detail

    13/35

    08/11/2009 2:45:17 PM Page No 13 of 35

    Item Description Quantity UOM Rate ManHrs Labor Equip Job Mat Perm Mat Mech Elec Eq Sub/Plug Total Cost

    12530000 EXPANSION JOINT/CAULKING 602.80 m 318 2,546 18,988 21,534

    0.53 4.22 31.50 35.72

    000010 EXPANSION JOINT/CAULKING 602.80 m 318 2,546 18,988 21,534

    0.53 4.22 31.50 35.72

    Prod=11.36 m/hour, 0.088MH/m, 11.36 m/MH, 53.05 hour

    Install Backer Rod 1.00 EA 8

    Carpenter 1.0 8.00 424

    Prod=2.27 m/hour, 0.440MH/m, 2.27 m/MH, 265.23 hour

    Apply Joint Sealant 1.00 EA 8

    Carpenter 1.0 8.00 2,122

    Install Backer Rod 602.8 m 3.50 2,110

    Apply Joint Sealant 602.8 m 28.00 16,878

    12610000

    i . . l li i i i - l i l

    painting/Accessories/Grouting for the frames(If necessory),

    i l ll l i

    9.00 EA 140 1,010 20,160 21,170

    15.56 112.22 2,240.00 2,352.22

    000010

    ize . x . eel o or on lig weig par i ion- n clu ing l y

    painting/Accessories/Grouting for the frames(If necessory),

    i l ll l i

    9.00 EA 100 700 20,160 20,860

    11.11 77.78 2,240.00 2,317.78

    Prod=0.23 ea/hour, 8.889MH/ea, 0.11 ea/MH, 40.00 hour

    Install Metal Door Frame 1.00 EA 14

    Carpenter 1.0 8.00 320

    Carpenter Helper 1.0 6.00 240

    Prod=0.90 ea/hour, 2.222MH/ea, 0.45 ea/MH, 10.00 hour

    Kick Plates 1.00 EA 14

    Carpenter 1.0 8.00 80

    Carpenter Helper 1.0 6.00 60

    Prod=0.90 ea/hour, 0.000MH/ea, 0.00 ea/MH, 0.00 hour

    Door Closures 1.00 EA 14

    Carpenter 1.0 8.00 0

    Carpenter Helper 1.0 6.00 0

    STEEL DOOR(Size 0.8x2.1) Steel door on lightweight partition-Including Alkyd

    painting/Accessories/Grouting for the frames(If necessory),

    10mmTHK.(ext.)/3mmTHK(int.) Cold rolled sheet door leaf(Both sides)

    & 100x65x2 Door frame 9.0 EA 2,240.00 20,160

    000020 Paint Door & Frame (Primer + 2 coats) 9.00 EA 40 310 310

    4.44 34.44 34.44

    Prod=0.90 ea/hour, 4.444MH/ea, 0.23 ea/MH, 10.00 hour

    Paint Door & Frame (Primer + 2 coats) 1.00 EA 31

    Painter Foreman 1.0 11.00 110

    Painter 2.0 7.00 140

    Painter Helper 1.0 6.00 60

    Paint Door & Frame (Primer + 2 coats) 9.0 EA 0.00 0

    12610010(Size 1.0x2.2) Including Alkyd painting/Accessories/Grouting for the

    frames(if necessary). 45mm thick, grade2, heavy dyty, model2,27.00 EA 475 3,426 83,160 86,586

    17.59 126.90 3,080.00 3,206.90

  • 8/10/2019 52- Process Plant Buildings Estimate Detail

    14/35

    08/11/2009 2:45:17 PM Page No 14 of 35

    Item Description Quantity UOM Rate ManHrs Labor Equip Job Mat Perm Mat Mech Elec Eq Sub/Plug Total Cost

    000010(Size 1.0x2.2) Including Alkyd painting/Accessories/Grouting for the

    frames(if necessary). 45mm thick, grade2, heavy dyty, model2,27.00 EA 340 2,380 83,160 85,540

    12.59 88.15 3,080.00 3,168.15

    Prod=0.18 ea/hour, 11.111MH/ea, 0.09 ea/MH, 150.00 hour

    Install Metal Door Frame 1.00 EA 14

    Carpenter 1.0 8.00 1,200

    Carpenter Helper 1.0 6.00 900

    Prod=1.35 ea/hour, 1.482MH/ea, 0.68 ea/MH, 20.00 hour

    Kick Plates 1.00 EA 14

    Carpenter 1.0 8.00 160

    Carpenter Helper 1.0 6.00 120

    Prod=0.90 ea/hour, 0.000MH/ea, 0.00 ea/MH, 0.00 hour

    Door Closures 1.00 EA 14

    Carpenter 1.0 8.00 0

    Carpenter Helper 1.0 6.00 0STEEL DOOR

    (Size 1.0x2.2) Including Alkyd painting/Accessories/Grouting for the

    frames(if necessary). 45mm thick, grade2, heavy dyty, model2,

    seamless design 1.5mm thick colorolled steel sheet faces 27.0 EA 3,080.00 83,160

    000020 Paint Door & Frame (Primer + 2 coats) 27.00 EA 135 1,046 1,046

    5.00 38.75 38.75

    Prod=0.80 ea/hour, 5.000MH/ea, 0.20 ea/MH, 33.75 hour

    Paint Door & Frame (Primer + 2 coats) 1.00 EA 31

    Painter Foreman 1.0 11.00 371

    Painter 2.0 7.00 473

    Painter Helper 1.0 6.00 203

    Paint Door & Frame (Primer + 2 coats) 27.0 EA 0.00 0

    12610020(Size 1.1x2.2) Including Alkyd painting/Accessories/Grouting for the

    frames(if necessary). 45mm thick, grade2, heavy dyty, model2,7.00 EA 131 940 23,716 24,656

    18.65 134.31 3,388.00 3,522.31

    000010(Size 1.1x2.2) Including Alkyd painting/Accessories/Grouting for the

    frames(if necessary). 45mm thick, grade2, heavy dyty, model2,7.00 EA 96 669 23,716 24,385

    13.65 95.56 3,388.00 3,483.56

    Prod=0.18 ea/hour, 11.429MH/ea, 0.09 ea/MH, 40.00 hour

    Install Metal Door Frame 1.00 EA 14

    Carpenter 1.0 8.00 320

    Carpenter Helper 1.0 6.00 240

    Prod=0.90 ea/hour, 2.222MH/ea, 0.45 ea/MH, 7.78 hour

    Kick Plates 1.00 EA 14

    Carpenter 1.0 8.00 62

    Carpenter Helper 1.0 6.00 47

    Prod=0.70 ea/hour, 0.000MH/ea, 0.00 ea/MH, 0.00 hour

    Door Closures 1.00 EA 14

    Carpenter 1.0 8.00 0

    Carpenter Helper 1.0 6.00 0

  • 8/10/2019 52- Process Plant Buildings Estimate Detail

    15/35

    08/11/2009 2:45:17 PM Page No 15 of 35

    Item Description Quantity UOM Rate ManHrs Labor Equip Job Mat Perm Mat Mech Elec Eq Sub/Plug Total Cost

    STEEL DOOR

    (Size 1.1x2.2) Including Alkyd painting/Accessories/Grouting for the

    frames(if necessary). 45mm thick, grade2, heavy dyty, model2,

    seamless design 1.5mm thick colorolled steel sheet faces 7.0 EA 3,388.00 23,716

    000020 Paint Door & Frame (Primer + 2 coats) 7.00 EA 35 271 271

    5.00 38.75 38.75

    Prod=0.80 ea/hour, 5.000MH/ea, 0.20 ea/MH, 8.75 hour

    Paint Door & Frame (Primer + 2 coats) 1.00 EA 31

    Painter Foreman 1.0 11.00 96

    Painter 2.0 7.00 123

    Painter Helper 1.0 6.00 53

    Paint Door & Frame (Primer + 2 coats) 7.0 EA 0.00 0

    12610030(Size 1.8x2.4)Including Alkyd painting/Accessories/Grouting for the

    frames(if necessary),45mm thick,grade?,Heavy duty,model2,seamless2.00 EA 84 621 12,096 12,717

    42.22 310.56 6,048.00 6,358.56

    000010 (Size 1.8x2.4)Including Alkyd painting/Accessories/Grouting for theframes(if necessary),45mm thick,grade?,Heavy duty,model2,seamless 2.00 EA 44 311 12,096 12,407

    22.22 155.56 6,048.00 6,203.56

    Prod=0.10 ea/hour, 20.000MH/ea, 0.05 ea/MH, 20.00 hour

    Install Metal Door Frame 1.00 EA 14

    Carpenter 1.0 8.00 160

    Carpenter Helper 1.0 6.00 120

    Prod=0.90 ea/hour, 2.222MH/ea, 0.45 ea/MH, 2.22 hour

    Kick Plates 1.00 EA 14

    Carpenter 1.0 8.00 18

    Carpenter Helper 1.0 6.00 13

    Prod=0.90 ea/hour, 0.000MH/ea, 0.00 ea/MH, 0.00 hour

    Door Closures 1.00 EA 14

    Carpenter 1.0 8.00 0

    Carpenter Helper 1.0 6.00 0

    STEEL DOOR(Size 1.8x2.4)Including Alkyd painting/Accessories/Grouting for the

    frames(if necessary),45mm thick,grade?,Heavy duty,model2,seamless

    design 1.5mm thick cold rolled steel sheet faces 2.0 EA 6,048.00 12,096

    000020 Paint Door & Frame (Primer + 2 coats) 2.00 EA 40 310 310

    20.00 155.00 155.00

    Prod=0.20 ea/hour, 20.000MH/ea, 0.05 ea/MH, 10.00 hour

    Paint Door & Frame (Primer + 2 coats) 1.00 EA 31

    Painter Foreman 1.0 11.00 110

    Painter 2.0 7.00 140

    Painter Helper 1.0 6.00 60

    Paint Door & Frame (Primer + 2 coats) 2.0 EA 0.00 0

    12610040(Size 2.2x2.6) Including Alkyd painting/Accessories/Grouting for the

    frames(if necessary). 45mm thick, grade2, heavy dyty, model2,2.00 EA 104 776 16,016 16,792

    52.22 388.06 8,008.00 8,396.06

    000010 (Size 2.2x2.6) Including Alkyd painting/Accessories/Grouting for theframes(if necessary). 45mm thick, grade2, heavy dyty, model2,

    2.00 EA 44 311 16,016 16,327

    22.22 155.56 8,008.00 8,163.56

  • 8/10/2019 52- Process Plant Buildings Estimate Detail

    16/35

    08/11/2009 2:45:17 PM Page No 16 of 35

    Item Description Quantity UOM Rate ManHrs Labor Equip Job Mat Perm Mat Mech Elec Eq Sub/Plug Total Cost

    Prod=0.10 ea/hour, 20.000MH/ea, 0.05 ea/MH, 20.00 hour

    Install Metal Door Frame 1.00 EA 14

    Carpenter 1.0 8.00 160

    Carpenter Helper 1.0 6.00 120

    Prod=0.90 ea/hour, 2.222MH/ea, 0.45 ea/MH, 2.22 hour

    Kick Plates 1.00 EA 14

    Carpenter 1.0 8.00 18

    Carpenter Helper 1.0 6.00 13

    Prod=0.90 ea/hour, 0.000MH/ea, 0.00 ea/MH, 0.00 hour

    Door Closures 1.00 EA 14

    Carpenter 1.0 8.00 0

    Carpenter Helper 1.0 6.00 0

    STEEL DOOR

    (Size 2.2x2.6) Including Alkyd painting/Accessories/Grouting for the

    frames(if necessary). 45mm thick, grade2, heavy dyty, model2,seamless design 1.5mm thick colorolled steel sheet faces 2.0 EA 8,008.00 16,016

    000020 Paint Door & Frame (Primer + 2 coats) 2.00 EA 60 465 465

    30.00 232.50 232.50

    Prod=0.13 ea/hour, 30.000MH/ea, 0.03 ea/MH, 15.00 hour

    Paint Door & Frame (Primer + 2 coats) 1.00 EA 31

    Painter Foreman 1.0 11.00 165

    Painter 2.0 7.00 210

    Painter Helper 1.0 6.00 90

    Paint Door & Frame (Primer + 2 coats) 2.0 EA 0.00 0

    12610050(Size 2.7x3.1) Including Alkyd painting/Accessories/Grouting for the

    frames(if necessary). 45mm thick, grade2, heavy dyty, model2,2.00 EA 144 1,071 23,436 24,507

    72.22 535.56 11,718.00 12,253.56

    000010(Size 2.7x3.1) Including Alkyd painting/Accessories/Grouting for the

    frames(if necessary). 45mm thick, grade2, heavy dyty, model2,2.00 EA 64 451 23,436 23,887

    32.22 225.56 11,718.00 11,943.56

    Prod=0.07 ea/hour, 30.000MH/ea, 0.03 ea/MH, 30.00 hour

    Install Metal Door Frame 1.00 EA 14

    Carpenter 1.0 8.00 240

    Carpenter Helper 1.0 6.00 180

    Prod=0.90 ea/hour, 2.222MH/ea, 0.45 ea/MH, 2.22 hour

    Kick Plates 1.00 EA 14

    Carpenter 1.0 8.00 18

    Carpenter Helper 1.0 6.00 13

    Prod=0.90 ea/hour, 0.000MH/ea, 0.00 ea/MH, 0.00 hour

    Door Closures 1.00 EA 14

    Carpenter 1.0 8.00 0

    Carpenter Helper 1.0 6.00 0

    STEEL DOOR

    (Size 2.7x3.1) Including Alkyd painting/Accessories/Grouting for the

    frames(if necessary). 45mm thick, grade2, heavy dyty, model2,seamless design 1.5mm thick colorolled steel sheet faces 2.0 EA 11,718.00 23,436

  • 8/10/2019 52- Process Plant Buildings Estimate Detail

    17/35

    08/11/2009 2:45:17 PM Page No 17 of 35

    Item Description Quantity UOM Rate ManHrs Labor Equip Job Mat Perm Mat Mech Elec Eq Sub/Plug Total Cost

    000020 Paint Door & Frame (Primer + 2 coats) 2.00 EA 80 620 620

    40.00 310.00 310.00

    Prod=0.10 ea/hour, 40.000MH/ea, 0.03 ea/MH, 20.00 hour

    Paint Door & Frame (Primer + 2 coats) 1.00 EA 31

    Painter Foreman 1.0 11.00 220

    Painter 2.0 7.00 280

    Painter Helper 1.0 6.00 120

    Paint Door & Frame (Primer + 2 coats) 2.0 EA 0.00 0

    12620000TEMPERED GLASS DOOR

    1.8*2.1 W/ACCESSORIES1.00 EA 25 210 9,450 9,660

    25.00 210.00 9,450.00 9,660.00

    000010TEMPERED GLASS DOOR

    1.8*2.1 W/ACCESSORIES1.00 EA 25 210 9,450 9,660

    25.00 210.00 9,450.00 9,660.00

    Prod=0.76 m2/hour, 6.614MH/m2, 0.15 m2/MH, 5.00 hour

    TEMPERED GLASS DOOR1.8*2.1 W/ACCESSORIES

    1.00 EA 42

    Glazier Foreman 1.0 12.00 60

    Glazier 3.0 8.00 120

    Glazier Helper 1.0 6.00 30

    1.8*2.1 W/ACCESSORIES 1.0 EA 9,450.00 9,450

    12620010TEMPERED GLASS DOOR2.0 X 2.4 W/ACCESORRIES

    1.00 EA 75 630 12,000 12,630

    75.00 630.00 12,000.00 12,630.00

    000010TEMPERED GLASS DOOR2.0 X 2.4 W/ACCESORRIES

    1.00 EA 75 630 12,000 12,630

    75.00 630.00 12,000.00 12,630.00

    Prod=0.32 m2/hour, 15.625MH/m2, 0.06 m2/MH, 15.00 hour

    TEMPERED GLASS DOOR2.0 X 2.4 W/ACCESORRIES

    1.00 EA 42

    Glazier Foreman 1.0 12.00 180

    Glazier 3.0 8.00 360

    Glazier Helper 1.0 6.00 90

    2.0 X 2.4 W/ACCESORRIES 1.0 EA 12,000.00 12,000

    12620020TEMPERED GLASS DOOR

    1.8 X 2.7 W/ACCESSORIES2.00 EA 100 840 24,300 25,140

    50.00 420.00 12,150.00 12,570.00

    000010TEMPERED GLASS DOOR

    1.8 X 2.7 W/ACCESSORIES2.00 EA 100 840 24,300 25,140

    50.00 420.00 12,150.00 12,570.00

    Prod=0.49 m2/hour, 10.288MH/m2, 0.10 m2/MH, 20.00 hour

    TEMPERED GLASS DOOR1.80 X 2.7 W/ACCESORRIES

    1.00 EA 42

    Glazier Foreman 1.0 12.00 240

    Glazier 3.0 8.00 480

    Glazier Helper 1.0 6.00 120

    1.8 X 2.7 W/ACCESSORIES 2.0 EA 12,150.00 24,300

    12630000 (Size 1.0x2.2) Resisting against 2ton/m2(suction),including door

    i

    3.00 EA 320 2,660 60,000 62,660

    106.67 886.67 20,000.00 20,886.67

    000010 (Size 1.0x2.2) Resisting against 2ton/m2(suction),including doori

    3.00 EA 240 2,040 60,000 62,040

    80.00 680.00 20,000.00 20,680.00

  • 8/10/2019 52- Process Plant Buildings Estimate Detail

    18/35

    08/11/2009 2:45:17 PM Page No 18 of 35

    Item Description Quantity UOM Rate ManHrs Labor Equip Job Mat Perm Mat Mech Elec Eq Sub/Plug Total Cost

    Prod=0.05 ea/hour, 80.000MH/ea, 0.01 ea/MH, 60.00 hour

    (Size 1.0x2.2) Resisting against 2ton/m2(suction),including door 1.00 EA 34

    Carpenter Foreman 1.0 12.00 720

    Carpenter 2.0 8.00 960

    Carpenter Helper 1.0 6.00 360

    BLAST RESISTANT DOOR(Size 1.0x2.2) Resisting against 2ton/m2(suction),including door

    accessories 3.0 EA 20,000.00 60,000

    000020 Paint Door & Frame (Primer + 2 coats) 3.00 EA 80 620 620

    26.67 206.67 206.67

    Prod=0.15 ea/hour, 26.667MH/ea, 0.04 ea/MH, 20.00 hour

    Paint Door & Frame (Primer + 2 coats) 1.00 EA 31

    Painter Foreman 1.0 11.00 220

    Painter 2.0 7.00 280

    Painter Helper 1.0 6.00 120Paint Door & Frame (Primer + 2 coats) 3.0 EA 0.00 0

    12630010 (Size 2.0x2.4) Resisting against 2ton/m2(suction),including doori

    1.00 EA 180 1,485 75,000 76,485

    180.00 1,485.00 75,000.00 76,485.00

    000010 (Size 2.0x2.4) Resisting against 2ton/m2(suction),including door

    i

    1.00 EA 120 1,020 75,000 76,020

    120.00 1,020.00 75,000.00 76,020.00

    Prod=0.03 ea/hour, 120.000MH/ea, 0.01 ea/MH, 30.00 hour

    (Size 2.0x2.4) Resisting against 2ton/m2(suction),including door 1.00 EA 34

    Carpenter Foreman 1.0 12.00 360

    Carpenter 2.0 8.00 480Carpenter Helper 1.0 6.00 180

    BLAST RESISTANT DOOR

    (Size 2.0x2.4) Resisting against 2ton/m2(suction),including door

    accessories 1.0 EA 75,000.00 75,000

    000020 Paint Door & Frame (Primer + 2 coats) 1.00 EA 60 465 465

    60.00 465.00 465.00

    Prod=0.07 ea/hour, 60.000MH/ea, 0.02 ea/MH, 15.00 hour

    Paint Door & Frame (Primer + 2 coats) 1.00 EA 31

    Painter Foreman 1.0 11.00 165Painter 2.0 7.00 210

    Painter Helper 1.0 6.00 90

    Paint Door & Frame (Primer + 2 coats) 1.0 EA 0.00 0

    12640000 3 keys for each door, 3 keys for each building, 3 keys for each group, 3 61.00 EA 200 1,400 57,950 59,350

    3.28 22.95 950.00 972.95

    000010 3 keys for each door, 3 keys for each building, 3 keys for each group, 3 61.00 EA 200 1,400 57,950 59,350

    3.28 22.95 950.00 972.95

    Prod=0.61 ea/hour, 3.279MH/ea, 0.31 ea/MH, 100.00 hour

    Lock Set Standard 1.00 EA 14Carpenter 1.0 8.00 800

    Carpenter Helper 1.0 6.00 600

  • 8/10/2019 52- Process Plant Buildings Estimate Detail

    19/35

    08/11/2009 2:45:17 PM Page No 19 of 35

    Item Description Quantity UOM Rate ManHrs Labor Equip Job Mat Perm Mat Mech Elec Eq Sub/Plug Total Cost

    LOCK SET

    3 keys for each door, 3 keys for each building, 3 keys for each group, 3

    keys for master 61.0 EA 950.00 57,950

    12640010DOOR CLOSERFOR GENERAL USE K-1630, for Heavy duty steel door"

    61.00 EA 136 949 36,600 37,549

    2.22 15.56 600.00 615.56

    000010 DOOR CLOSERFOR GENERAL USE K-1630, for Heavy duty steel door"

    61.00 EA 136 949 36,600 37,549

    2.22 15.56 600.00 615.56

    Prod=0.90 ea/hour, 2.222MH/ea, 0.45 ea/MH, 67.78 hour

    Door Closures 1.00 EA 14

    Carpenter 1.0 8.00 542

    Carpenter Helper 1.0 6.00 407

    DOOR CLOSER

    FOR GENERAL USE K-1630, for Heavy duty steel door" 61.0 EA 600.00 36,600

    12640020DOOR STOP

    FOR OPERATED FRICTION DOOR HOLDER61.00 EA 49 342 3,660 4,002

    0.80 5.60 60.00 65.60

    000010DOOR STOP

    FOR OPERATED FRICTION DOOR HOLDER61.00 EA 49 342 3,660 4,002

    0.80 5.60 60.00 65.60

    Prod=2.50 ea/hour, 0.800MH/ea, 1.25 ea/MH, 24.40 hour

    Door Stops 1.00 EA 14

    Carpenter 1.0 8.00 195

    Carpenter Helper 1.0 6.00 146

    Door Stops 61.0 EA 60.00 3,660

    12640030

    PANIC DEVICE

    Stainless steel 18.00 EA 90 630 180,000 180,6305.00 35.00 10,000.00 10,035.00

    000010PANIC DEVICE

    Stainless steel18.00 EA 90 630 180,000 180,630

    5.00 35.00 10,000.00 10,035.00

    Prod=0.40 ea/hour, 5.000MH/ea, 0.20 ea/MH, 45.00 hour

    PANIC DEVICEStainless steel

    1.00 EA 14

    Carpenter 1.0 8.00 360

    Carpenter Helper 1.0 6.00 270

    Stainless steel 18.0 EA 10,000.00 180,000

    12640040 PIVOT HINGE 7.00 SET 20 140 3,500 3,640

    2.86 20.00 500.00 520.00

    000010 PIVOT HINGE 7.00 SET 20 140 3,500 3,640

    2.86 20.00 500.00 520.00

    Prod=0.70 ea/hour, 2.857MH/ea, 0.35 ea/MH, 10.00 hour

    PIVOT HINGE 1.00 EA 14

    Carpenter 1.0 8.00 80

    Carpenter Helper 1.0 6.00 60

    PIVOT HINGE 7.0 SET 500.00 3,500

    12640050 DOOR KNOB 1.00 EA 3 23 950 973

    3.28 22.95 950.00 972.95

  • 8/10/2019 52- Process Plant Buildings Estimate Detail

    20/35

    08/11/2009 2:45:17 PM Page No 20 of 35

    Item Description Quantity UOM Rate ManHrs Labor Equip Job Mat Perm Mat Mech Elec Eq Sub/Plug Total Cost

    000010 DOOR KNOB 1.00 EA 3 23 950 973

    3.28 22.95 950.00 972.95

    Prod=0.61 ea/hour, 3.279MH/ea, 0.31 ea/MH, 1.64 hour

    Lock Set Standard 1.00 EA 14

    Carpenter 1.0 8.00 13Carpenter Helper 1.0 6.00 10

    DOOR KNOB 1.0 EA 950.00 950

    12650000

    .

    (Size 0.9x1.8) Including accessories Extruded aluminum complying

    i ll

    2.00 EA 20 140 8,100 8,240

    10.00 70.00 4,050.00 4,120.00

    000010

    .

    (Size 0.9x1.8) Including accessories Extruded aluminum complying

    i ll

    2.00 EA 20 140 8,100 8,240

    10.00 70.00 4,050.00 4,120.00

    Prod=0.32 m2/hour, 6.173MH/m2, 0.16 m2/MH, 10.00 hour

    Install Aluminum Window 1.00 EA 14

    Carpenter 1.0 8.00 80

    Carpenter Helper 1.0 6.00 60

    AL. WINDOW/FRAME

    (Size 0.9x1.8) Including accessories Extruded aluminum complying

    with ASTM B221 alloy 6063-T 2.0 EA 4,050.00 8,100

    12650010

    .

    (Size 0.9x12) Including accessories Extruded aluminum complying withll

    13.00 EA 1,400 9,800 351,000 360,800

    107.69 753.85 27,000.00 27,753.85

    000010.

    (Size 0.9x12) Including accessories Extruded aluminum complying with

    ll

    13.00 EA 1,400 9,800 351,000 360,800

    107.69 753.85 27,000.00 27,753.85

    Prod=0.20 m2/hour, 9.972MH/m2, 0.10 m2/MH, 700.00 hour

    Install Aluminum Window 1.00 EA 14

    Carpenter 1.0 8.00 5,600

    Carpenter Helper 1.0 6.00 4,200

    AL. WINDOW/FRAME

    (Size 0.9x12) Including accessories Extruded aluminum complying withASTM B221 alloy 6063-T5 13.0 EA 27,000.00 351,000

    12650020

    .

    (Size 1.2x0.6) Including accessories Extruded aluminum complying

    i ll

    1.00 EA 10 70 1,800 1,870

    10.00 70.00 1,800.00 1,870.00

    000010

    .

    (Size 1.2x0.6) Including accessories Extruded aluminum complying

    i ll

    1.00 EA 10 70 1,800 1,870

    10.00 70.00 1,800.00 1,870.00

    Prod=0.14 m2/hour, 13.889MH/m2, 0.07 m2/MH, 5.00 hour

    Install Aluminum Window 1.00 EA 14

    Carpenter 1.0 8.00 40

    Carpenter Helper 1.0 6.00 30

    AL. WINDOW/FRAME

    (Size 1.2x0.6) Including accessories Extruded aluminum complying

    with ASTM B221 alloy 6063-T 1.0 EA 1,800.00 1,800

    12650030

    .

    (Size 0.9x12) Including accessories Extruded aluminum complying with

    ll

    3.00 EA 323 2,262 81,000 83,262

    107.69 753.85 27,000.00 27,753.85

    000010

    .

    (Size 0.9x12) Including accessories Extruded aluminum complying with

    ll

    3.00 EA 323 2,262 81,000 83,262

  • 8/10/2019 52- Process Plant Buildings Estimate Detail

    21/35

    08/11/2009 2:45:17 PM Page No 21 of 35

    Item Description Quantity UOM Rate ManHrs Labor Equip Job Mat Perm Mat Mech Elec Eq Sub/Plug Total Cost

    107.69 753.85 27,000.00 27,753.85

    Prod=0.20 m2/hour, 9.972MH/m2, 0.10 m2/MH, 161.54 hour

    Install Aluminum Window 1.00 EA 14

    Carpenter 1.0 8.00 1,292

    Carpenter Helper 1.0 6.00 969

    AL. WINDOW/FRAME(Size 0.9x12) Including accessories Extruded aluminum complying with

    ASTM B221 alloy 6063-T5 3.0 EA 27,000.00 81,000

    12650040

    .

    (Size 1.2x1.5) Including accessories Extruded aluminum complying

    i ll

    3.00 EA 30 210 13,500 13,710

    10.00 70.00 4,500.00 4,570.00

    000010

    .

    (Size 1.2x1.5) Including accessories Extruded aluminum complying

    i ll

    3.00 EA 30 210 13,500 13,710

    10.00 70.00 4,500.00 4,570.00

    Prod=0.36 m2/hour, 5.556MH/m2, 0.18 m2/MH, 15.00 hour

    Install Aluminum Window 1.00 EA 14

    Carpenter 1.0 8.00 120

    Carpenter Helper 1.0 6.00 90

    AL. WINDOW/FRAME

    (Size 1.2x1.5) Including accessories Extruded aluminum complying

    with ASTM B221 alloy 6063-T 3.0 EA 4,500.00 13,500

    12650050

    .

    (Size 1.2x3.0) Including accessories Extruded aluminum complyingi ll

    3.00 EA 60 420 27,000 27,420

    20.00 140.00 9,000.00 9,140.00

    000010.

    (Size 1.2x3.0) Including accessories Extruded aluminum complying

    i ll

    3.00 EA 60 420 27,000 27,420

    20.00 140.00 9,000.00 9,140.00

    Prod=0.36 m2/hour, 5.556MH/m2, 0.18 m2/MH, 30.00 hour

    Install Aluminum Window 1.00 EA 14

    Carpenter 1.0 8.00 240

    Carpenter Helper 1.0 6.00 180

    AL. WINDOW/FRAME

    (Size 1.2x3.0) Including accessories Extruded aluminum complyingwith ASTM B221 alloy 6063-T 3.0 EA 9,000.00 27,000

    12650060

    .

    (Size 2.0x1.5) Including accessories Extruded aluminum complying

    i ll

    2.00 EA 54 378 15,000 15,378

    27.00 189.00 7,500.00 7,689.00

    000010

    .

    (Size 2.0x1.5) Including accessories Extruded aluminum complying

    i ll

    2.00 EA 54 378 15,000 15,378

    27.00 189.00 7,500.00 7,689.00

    Prod=0.22 m2/hour, 9.000MH/m2, 0.11 m2/MH, 27.00 hour

    Install Aluminum Window 1.00 EA 14

    Carpenter 1.0 8.00 216

    Carpenter Helper 1.0 6.00 162

    AL. WINDOW/FRAME

    (Size 2.0x1.5) Including accessories Extruded aluminum complying

    with ASTM B221 alloy 6063-T 2.0 EA 7,500.00 15,000

    12650070

    .

    (Size 0.9x3.0) Including accessories Extruded aluminum complying

    i ll

    2.00 EA 50 350 13,500 13,850

    25.00 175.00 6,750.00 6,925.00

    000010

    .

    (Size 0.9x3.0) Including accessories Extruded aluminum complyingi ll

    2.00 EA 50 350 13,500 13,850

  • 8/10/2019 52- Process Plant Buildings Estimate Detail

    22/35

    08/11/2009 2:45:17 PM Page No 22 of 35

    Item Description Quantity UOM Rate ManHrs Labor Equip Job Mat Perm Mat Mech Elec Eq Sub/Plug Total Cost

    25.00 175.00 6,750.00 6,925.00

    Prod=0.22 m2/hour, 9.259MH/m2, 0.11 m2/MH, 25.00 hour

    Install Aluminum Window 1.00 EA 14

    Carpenter 1.0 8.00 200

    Carpenter Helper 1.0 6.00 150

    AL. WINDOW/FRAME(Size 0.9x3.0) Including accessories Extruded aluminum complying

    with ASTM B221 alloy 6063-T 2.0 EA 6,750.00 13,500

    12650080

    .

    (Size 1.2x4.0) Including accessories Extruded aluminum complying

    i ll

    3.00 EA 80 560 36,000 36,560

    26.67 186.67 12,000.00 12,186.67

    000010

    .

    (Size 1.2x4.0) Including accessories Extruded aluminum complying

    i ll

    3.00 EA 80 560 36,000 36,560

    26.67 186.67 12,000.00 12,186.67

    Prod=0.36 m2/hour, 5.556MH/m2, 0.18 m2/MH, 40.00 hour

    Install Aluminum Window 1.00 EA 14

    Carpenter 1.0 8.00 320

    Carpenter Helper 1.0 6.00 240

    AL. WINDOW/FRAME

    (Size 1.2x4.0) Including accessories Extruded aluminum complying

    with ASTM B221 alloy 6063-T 3.0 EA 12,000.00 36,000

    12650090

    .

    (Size 0.9x6.0) Including accessories Extruded aluminum complyingi ll

    4.00 EA 180 1,260 54,000 55,260

    45.00 315.00 13,500.00 13,815.00

    000010.

    (Size 0.9x6.0) Including accessories Extruded aluminum complying

    i ll

    4.00 EA 180 1,260 54,000 55,260

    45.00 315.00 13,500.00 13,815.00

    Prod=0.24 m2/hour, 8.333MH/m2, 0.12 m2/MH, 90.00 hour

    Install Aluminum Window 1.00 EA 14

    Carpenter 1.0 8.00 720

    Carpenter Helper 1.0 6.00 540

    AL. WINDOW/FRAME

    (Size 0.9x6.0) Including accessories Extruded aluminum complyingwith ASTM B221 alloy 6063-T 4.0 EA 13,500.00 54,000

    12660000CLEAR GLASS

    Type I,Class 1, Quality Q4223.97 m2 500 4,200 201,573 205,773

    2.23 18.75 900.00 918.75

    000010CLEAR GLASS

    Type I,Class 1, Quality Q4223.97 m2 500 4,200 201,573 205,773

    2.23 18.75 900.00 918.75

    Prod=2.24 m2/hour, 2.232MH/m2, 0.45 m2/MH, 100.00 hour

    CLEAR GLASSType I,Class 1, Quality Q4

    1.00 EA 42

    Glazier Foreman 1.0 12.00 1,200

    Glazier 3.0 8.00 2,400

    Glazier Helper 1.0 6.00 600

    Type I,Class 1, Quality Q4 224.0 m2 900.00 201,573

    12660010PAIR GLASS

    Tempered Glass 6T + Air space 13T + Clear Glass 6T16.39 m2 50 420 40,975 41,395

    3.05 25.63 2,500.00 2,525.63

    000010 PAIR GLASSTempered Glass 6T + Air space 13T + Clear Glass 6T

    16.39 m2 50 420 40,975 41,395

    3.05 25.63 2,500.00 2,525.63

  • 8/10/2019 52- Process Plant Buildings Estimate Detail

    23/35

    08/11/2009 2:45:17 PM Page No 23 of 35

    Item Description Quantity UOM Rate ManHrs Labor Equip Job Mat Perm Mat Mech Elec Eq Sub/Plug Total Cost

    Prod=1.64 m2/hour, 3.051MH/m2, 0.33 m2/MH, 10.00 hour

    PAIR GLASSTempered Glass 6T + Air space 13T + Clear Glass 6T

    1.00 EA 42

    Glazier Foreman 1.0 12.00 120

    Glazier 3.0 8.00 240

    Glazier Helper 1.0 6.00 60

    Tempered Glass 6T + Air space 13T + Clear Glass 6T 16.4 m2 2,500.00 40,975

    12660020WIRED GLASS

    T=83.04 m2 10 84 3,648 3,732

    3.29 27.63 1,200.00 1,227.63

    000010WIRED GLASS

    T=83.04 m2 10 84 3,648 3,732

    3.29 27.63 1,200.00 1,227.63

    000010PAIR GLASS

    Tempered Glass 6T + Air space 13T + Clear Glass 6T3.04 m2 10 84 3,648 3,732

    3.29 27.63 1,200.00 1,227.63

    Prod=1.52 m2/hour, 3.290MH/m2, 0.30 m2/MH, 2.00 hour

    PAIR GLASSTempered Glass 6T + Air space 13T + Clear Glass 6T 1.00 EA 42

    Glazier Foreman 1.0 12.00 24

    Glazier 3.0 8.00 48

    Glazier Helper 1.0 6.00 12

    T=8 3.0 m2 1,200.00 3,648

    12660030 TEMPERED GLASS 13.70 m2 42 351 24,660 25,011

    3.05 25.63 1,800.00 1,825.63

    000010 TEMPERED GLASS 13.70 m2 42 351 24,660 25,011

    3.05 25.63 1,800.00 1,825.63

    Prod=1.64 m2/hour, 3.051MH/m2, 0.33 m2/MH, 8.36 hour

    TEMPERED GLASS 1.00 EA 42

    Glazier Foreman 1.0 12.00 100

    Glazier 3.0 8.00 201

    Glazier Helper 1.0 6.00 50

    TEMPERED GLASS 13.7 m2 1,800.00 24,660

    12660040DAMP PROOFING MIRROR

    For toilet8.19 m2 20 168 4,095 4,263

    2.44 20.51 500.00 520.51

    000010DAMP PROOFING MIRROR

    For toilet8.19 m2 20 168 4,095 4,263

    2.44 20.51 500.00 520.51Prod=2.05 m2/hour, 2.442MH/m2, 0.41 m2/MH, 4.00 hour

    DAMP PROOFING MIRRORFor toilet

    1.00 EA 42

    Glazier Foreman 1.0 12.00 48

    Glazier 3.0 8.00 96

    Glazier Helper 1.0 6.00 24

    For toilet 8.2 m2 500.00 4,095

    12670000SHUTTER (ELECTRICAL)

    (Size 1.8x2.5) Steel, Galv.1.00 EA 80 680 8,065 8,745

    80.00 680.00 8,065.00 8,745.00

    000010

    SHUTTER (ELECTRICAL)

    (Size 1.8x2.5) Steel, Galv. 1.00 EA 80 680 8,065 8,74580.00 680.00 8,065.00 8,745.00

  • 8/10/2019 52- Process Plant Buildings Estimate Detail

    24/35

    08/11/2009 2:45:17 PM Page No 24 of 35

    Item Description Quantity UOM Rate ManHrs Labor Equip Job Mat Perm Mat Mech Elec Eq Sub/Plug Total Cost

    Prod=0.05 ea/hour, 80.000MH/ea, 0.01 ea/MH, 20.00 hour

    Vertical Lift Door 1.00 EA 34

    Carpenter Foreman 1.0 12.00 240

    Carpenter 2.0 8.00 320

    Carpenter Helper 1.0 6.00 120

    (Size 1.8x2.5) Steel, Galv. 1.0 EA 8,065.00 8,065

    12670010SHUTTER (ELECTRICAL)

    3.0x3.5 (Steel Galvanized)4.00 EA 360 3,060 75,272 78,332

    90.00 765.00 18,818.00 19,583.00

    000010SHUTTER (ELECTRICAL)

    3.0x3.5 (Steel Galvanized)4.00 EA 360 3,060 75,272 78,332

    90.00 765.00 18,818.00 19,583.00

    Prod=0.04 ea/hour, 90.000MH/ea, 0.01 ea/MH, 90.00 hour

    Vertical Lift Door 1.00 EA 34

    Carpenter Foreman 1.0 12.00 1,080

    Carpenter 2.0 8.00 1,440

    Carpenter Helper 1.0 6.00 540

    3.0x3.5 (Steel Galvanized) 4.0 EA 18,818.00 75,272

    12670020SHUTTER (ELECTRICAL)

    3.0x3.5 (Steel Galvanized)1.00 EA 90 765 18,818 19,583

    90.00 765.00 18,818.00 19,583.00

    000010SHUTTER (ELECTRICAL)3.0x3.5 (Steel Galvanized)

    1.00 EA 90 765 18,818 19,583

    90.00 765.00 18,818.00 19,583.00

    Prod=0.04 ea/hour, 90.000MH/ea, 0.01 ea/MH, 22.50 hour

    Vertical Lift Door 1.00 EA 34

    Carpenter Foreman 1.0 12.00 270Carpenter 2.0 8.00 360

    Carpenter Helper 1.0 6.00 135

    3.0x3.5 (Steel Galvanized) 1.0 EA 18,818.00 18,818

    12670030SHUTTER (ELECTRICAL)

    (Size 4.0x4.0) Steel, Galv.5.00 EA 720 6,120 143,375 149,495

    144.00 1,224.00 28,675.00 29,899.00

    Prod=0.03 ea/hour, 144.000MH/ea, 0.01 ea/MH, 180.00 hour

    Vertical Lift Door 1.00 EA 34

    Carpenter Foreman 1.0 12.00 2,160

    Carpenter 2.0 8.00 2,880Carpenter Helper 1.0 6.00 1,080

    (Size 4.0x4.0) Steel, Galv. 5.0 EA 28,675.00 143,375

    12680000LOUVER(AL)

    (Size 1.2x1.2) Including accessories36.00 EA 280 1,960 129,600 131,560

    7.78 54.44 3,600.00 3,654.44

    000010LOUVER(AL)

    (Size 1.2x1.2) Including accessories36.00 EA 280 1,960 129,600 131,560

    7.78 54.44 3,600.00 3,654.44

    Prod=0.37 m2/hour, 5.401MH/m2, 0.19 m2/MH, 140.00 hour

    Install Aluminum Window 1.00 EA 14

    Carpenter 1.0 8.00 1,120Carpenter Helper 1.0 6.00 840

    (Size 1.2x1.2) Including accessories 36.0 EA 3,600.00 129,600

  • 8/10/2019 52- Process Plant Buildings Estimate Detail

    25/35

  • 8/10/2019 52- Process Plant Buildings Estimate Detail

    26/35

    08/11/2009 2:45:17 PM Page No 26 of 35

    Item Description Quantity UOM Rate ManHrs Labor Equip Job Mat Perm Mat Mech Elec Eq Sub/Plug Total Cost

    Install Metal Studs 20-25 ga 600 (24") c-c 1.00 EA 34

    Carpenter Foreman 1.0 12.00 1,404

    Carpenter 2.0 8.00 1,871

    Carpenter Helper 1.0 6.00 702

    Install Metal Studs 20-25 ga 600 (24") c-c 2,196.5 m2 20.00 43,930

    12720010 GYPSUM BOARD 41.90 m2 25 210 4,268 4,477

    0.59 5.01 101.85 106.86

    00001016mm,for wall,including 22 gage steel stud frame(64) & runner & bead& sealant on the other side of the steel framed metal sheet wall

    41.90 m2 11 90 2,860 2,949

    0.25 2.14 68.25 70.39

    Prod=15.87 m2/hour, 0.252MH/m2, 3.97 m2/MH, 2.64 hour

    Drywall to Walls 15mm (5/8") Taped & Finished 1.00 EA 34

    Carpenter Foreman 1.0 12.00 32

    Carpenter 2.0 8.00 42

    Carpenter Helper 1.0 6.00 16

    GYPSUM BOARD 44.0 m2 65.00 2,860

    000020 Install Metal Studs 20-25 ga 600 (24") c-c 41.90 m2 9 76 880 956

    0.21 1.81 21.00 22.81

    Prod=18.78 m2/hour, 0.213MH/m2, 4.69 m2/MH, 2.23 hour

    Install Metal Studs 20-25 ga 600 (24") c-c 1.00 EA 34

    Carpenter Foreman 1.0 12.00 27

    Carpenter 2.0 8.00 36

    Carpenter Helper 1.0 6.00 13

    Install Metal Studs 20-25 ga 600 (24") c-c 44.0 m2 20.00 880

    000030 ROCK WOOLWall (T=50)

    41.90 m2 5 44 528 572

    0.12 1.06 12.60 13.66

    Prod=32.10 m2/hour, 0.125MH/m2, 8.03 m2/MH, 1.31 hour

    Install Wool Batt Insulation 1.00 EA 34

    Carpenter Foreman 1.0 12.00 16

    Carpenter 2.0 8.00 21

    Carpenter Helper 1.0 6.00 8

    Wall (T=50) 44.0 m2 12.00 528

    12720020 GYPSUM PARTITION 7.04 m2 4 35 673 708

    0.59 5.01 95.60 100.61

    000010 GYPSUM PARTITION 7.04 m2 2 15 444 459

    0.25 2.14 63.00 65.14

    Prod=15.87 m2/hour, 0.252MH/m2, 3.97 m2/MH, 0.44 hour

    Drywall to Walls 15mm (5/8") Taped & Finished 1.00 EA 34

    Carpenter Foreman 1.0 12.00 5

    Carpenter 2.0 8.00 7

    Carpenter Helper 1.0 6.00 3

    GYPSUM PARTITION 7.4 m2 60.00 444

    000020 Install Metal Studs 20-25 ga 600 (24") c-c 7.04 m2 1 13 141 154

    0.21 1.81 20.00 21.81

  • 8/10/2019 52- Process Plant Buildings Estimate Detail

    27/35

    08/11/2009 2:45:17 PM Page No 27 of 35

    Item Description Quantity UOM Rate ManHrs Labor Equip Job Mat Perm Mat Mech Elec Eq Sub/Plug Total Cost

    Prod=18.78 m2/hour, 0.213MH/m2, 4.69 m2/MH, 0.37 hour

    Install Metal Studs 20-25 ga 600 (24") c-c 1.00 EA 34

    Carpenter Foreman 1.0 12.00 4

    Carpenter 2.0 8.00 6

    Carpenter Helper 1.0 6.00 2

    Install Metal Studs 20-25 ga 600 (24") c-c 7.0 m2 20.00 141

    000030ROCK WOOL

    Wall (T=50)7.04 m2 1 7 89 96

    0.12 1.06 12.60 13.66

    Prod=32.10 m2/hour, 0.125MH/m2, 8.03 m2/MH, 0.22 hour

    Install Wool Batt Insulation 1.00 EA 34

    Carpenter Foreman 1.0 12.00 3

    Carpenter 2.0 8.00 4

    Carpenter Helper 1.0 6.00 1

    Wall (T=50) 7.4 m2 12.00 89

    12730000 Heavy duty expanded metal mesh - Hot dip galvanized(excluding the

    l l ~

    187.22 m2 231 1,619 117,949 119,567

    1.24 8.65 630.00 638.65

    000010 Heavy duty expanded metal mesh - Hot dip galvanized(excluding the

    l l ~

    187.22 m2 231 1,619 117,949 119,567

    1.24 8.65 630.00 638.65

    Prod=1.62 ea/hour, 1.235MH/ea, 0.81 ea/MH, 115.61 hour

    Heavy duty expanded metal mesh - Hot dip galvanized(excluding the

    ~1.00 EA 14

    Carpenter 1.0 8.00 925

    Carpenter Helper 1.0 6.00 694

    METAL LATH

    Heavy duty expanded metal mesh - Hot dip galvanized(excluding thesteel frames),removable, 8~12 gage 13mm Max.gap 196.6 m2 600.00 117,949

    12730010 CEMENT MORTAR 1,522.98 m2 2,132 17,768 1,898 33,506 53,171

    1.40 11.67 1.25 22.00 34.91

    000010 CEMENT MORTAR 1,522.98 m2 2,132 17,768 1,898 33,506 53,171

    1.40 11.67 1.25 22.00 34.91

    Prod=4.29 m2/hour, 1.400MH/m2, 0.71 m2/MH, 355.36 hour

    CEMENT MORTAR 1.00 EA 55.34

    Mason Foreman 1.0 12.00 4,264

    Mason 4.0 8.00 11,372

    Mason Helper 1.0 6.00 2,132

    Cement Mixer 1.0 5.34 1,898

    , Floor 60mm 1,523.0 m2 22.00 33,506

    12730020 CEMENT MORTAR 4,408.77 m2 6,172 51,436 5,493 5,175 17,217 79,321

    1.40 11.67 1.25 1.17 3.91 17.99

    000010 CEMENT MORTAR 4,408.77 m2 6,172 51,436 5,493 5,175 17,217 79,321

    1.40 11.67 1.25 1.17 3.91 17.99

    Prod=4.29 m2/hour, 1.400MH/m2, 0.71 m2/MH, 1,028.71 hour

    CEMENT MORTAR 1.00 EA 55.34

    Mason Foreman 1.0 12.00 12,345

  • 8/10/2019 52- Process Plant Buildings Estimate Detail

    28/35

    08/11/2009 2:45:17 PM Page No 28 of 35

    Item Description Quantity UOM Rate ManHrs Labor Equip Job Mat Perm Mat Mech Elec Eq Sub/Plug Total Cost

    Mason 4.0 8.00 32,919

    Mason Helper 1.0 6.00 6,172

    Cement Mixer 1.0 5.34 5,493

    Clean sand for plastering 184.8 m3 28.00 5,175

    Cement Bag (40 kg) portland type 10 1,012.8 Bag 17.00 17,217

    12730030 CEMENT MORTAR 2,415.71 m2 3,382 28,183 3,010 2,835 9,434 43,463

    1.40 11.67 1.25 1.17 3.91 17.99

    000010 CEMENT MORTAR 2,415.71 m2 3,382 28,183 3,010 2,835 9,434 43,463

    1.40 11.67 1.25 1.17 3.91 17.99

    Prod=4.29 m2/hour, 1.400MH/m2, 0.71 m2/MH, 563.67 hour

    CEMENT MORTAR 1.00 EA 55.34

    Mason Foreman 1.0 12.00 6,764

    Mason 4.0 8.00 18,037

    Mason Helper 1.0 6.00 3,382

    Cement Mixer 1.0 5.34 3,010

    Clean sand for plastering 101.3 m3 28.00 2,835

    Cement Bag (40 kg) portland type 10 554.9 Bag 17.00 9,434

    12730040LEVELLING MORTAR

    For roof963.60 m2 1,156 9,636 23,126 32,762

    1.20 10.00 24.00 34.00

    000010LEVELLING MORTAR

    For roof963.60 m2 1,156 9,636 23,126 32,762

    1.20 10.00 24.00 34.00

    Prod=5.00 m2/hour, 1.200MH/m2, 0.83 m2/MH, 192.72 hour

    CEMENT MORTAR 1.00 EA 50

    Mason Foreman 1.0 12.00 2,313

    Mason 4.0 8.00 6,167Mason Helper 1.0 6.00 1,156

    For roof 963.6 m2 24.00 23,126

    12730050 STEEL TROWEL FINISH 1,944.42 m2 194 2,136 2,282 7,593 12,011

    0.10 1.10 1.17 3.91 6.18

    000010 STEEL TROWEL FINISH 1,944.42 m2 194 2,136 2,282 7,593 12,011

    0.10 1.10 1.17 3.91 6.18

    Prod=20.03 m2/hour, 0.100MH/m2, 10.01 m2/MH, 97.08 hour

    Finish Concrete with Trowel 1.00 EA 22

    Cement Finisher 2.0 11.00 2,136

    Clean sand for topping 81.5 m3 28.00 2,282

    Cement Bag (40 kg) portland type 10 446.7 Bag 17.00 7,593

    12730060 Metallic,aggregate dry-shake floor hardener(including water soluble

    i i ili i i

    752.25 m2 150 1,705 201 22,568 24,473

    0.20 2.27 0.27 30.00 32.53

    000010 Metallic,aggregate dry-shake floor hardener(including water soluble

    i i ili i i

    752.25 m2 150 1,705 201 22,568 24,473

    0.20 2.27 0.27 30.00 32.53

    Prod=15.00 m2/hour, 0.200MH/m2, 5.00 m2/MH, 50.15 hour

    Power Finish Concrete & Apply Hardener 1.00 EA 38

    Cement Finisher Foreman 1.0 12.00 602

    Cement Finisher 2.0 11.00 1,103

  • 8/10/2019 52- Process Plant Buildings Estimate Detail

    29/35

    08/11/2009 2:45:17 PM Page No 29 of 35

    Item Description Quantity UOM Rate ManHrs Labor Equip Job Mat Perm Mat Mech Elec Eq Sub/Plug Total Cost

    Concrete Power Trowel-Walker 1.0 4.00 201

    HARDENER

    Metallic,aggregate dry-shake floor hardener(including water solubleinorganic silicate based compound finish) 752.3 m2 30.00 22,568

    12730070 MORTAR GROUTING AROUND WINDOW FRAME 38.64 m 12 98 966 1,064

    0.32 2.53 25.00 27.53000010 MORTAR GROUTING AROUND WINDOW FRAME 38.64 m2 12 98 966 1,064

    0.32 2.53 25.00 27.53

    Prod=3.16 m/hour, 0.316MH/m, 3.16 m/MH, 12.22 hour

    MORTAR GROUTING AROUND WINDOW FRAME 1.00 EA 8

    Mason 1.0 8.00 98

    MORTAR GROUTING AROUND WINDOW FRAME 38.6 Lm 25.00 966

    12740000 15x600x600 - For ceiling,including paint including the 2% of the spare

    i l l

    888.95 m2 189 1,609 65,338 66,947

    0.21 1.81 73.50 75.31

    000010 15x600x600 - For ceiling,including paint including the 2% of the spare

    i l l

    888.95 m2 189 1,609 65,338 66,947

    0.21 1.81 73.50 75.31

    Prod=18.78 m2/hour, 0.213MH/m2, 4.69 m2/MH, 47.34 hour

    AcousticCeiling Boards 1.00 EA 34

    Carpenter Foreman 1.0 12.00 568

    Carpenter 2.0 8.00 757

    Carpenter Helper 1.0 6.00 284

    ACOUSTIC BOARD15x600x600 - For ceiling,including paint including the 2% of the spare

    material supply 933.4 m2 70.00 65,338

    12740010CEILING SYSTEM 2

    Lightweight ceiling frame - T bar407.10 m2 20 173 6,412 6,585

    0.05 0.43 15.75 16.18

    000010CEILING SYSTEM 2Lightweight ceiling frame - T bar

    407.10 m2 20 173 6,412 6,585

    0.05 0.43 15.75 16.18

    Prod=80.00 m2/hour, 0.050MH/m2, 20.00 m2/MH, 5.09 hour

    T-Bar Suspension System 1.00 EA 34

    Carpenter Foreman 1.0 12.00 61

    Carpenter 2.0 8.00 81

    Carpenter Helper 1.0 6.00 31

    Lightweight ceiling frame - T bar 427.5 m2 15.00 6,412

    12740020CEILING SYSTEM 2

    Lightweight ceiling frame - M bar481.85 m2 24 205 10,119 10,324

    0.05 0.43 21.00 21.43

    000010CEILING SYSTEM 2

    Lightweight ceiling frame - M bar481.85 m2 24 205 10,119 10,324

    0.05 0.43 21.00 21.43

    Prod=80.00 m2/hour, 0.050MH/m2, 20.00 m2/MH, 6.02 hour

    T-Bar Suspension System 1.00 EA 34

    Carpenter Foreman 1.0 12.00 72

    Carpenter 2.0 8.00 96Carpenter Helper 1.0 6.00 36

    Lightweight ceiling frame - M bar 505.9 m2 20.00 10,119

  • 8/10/2019 52- Process Plant Buildings Estimate Detail

    30/35

    08/11/2009 2:45:17 PM Page No 30 of 35

    Item Description Quantity UOM Rate ManHrs Labor Equip Job Mat Perm Mat Mech Elec Eq Sub/Plug Total Cost

    12750000CARPET TILE

    Modular carpet tile43.70 m2 14 117 2,202 2,320

    0.32 2.69 50.40 53.09

    000010CARPET TILEModular carpet tile

    43.70 m2 14 117 2,202 2,320

    0.32 2.69 50.40 53.09

    Prod=12.66 m2/hour, 0.316MH/m2, 3.17 m2/MH, 3.45 hour

    Gluedown Carpet 1.00 EA 34

    Carpet Layer Foreman 1.0 12.00 41

    Carpet Layer 2.0 8.00 55

    Carpet Layer Helper 1.0 6.00 21

    Modular carpet tile 45.9 m2 48.00 2,202

    12750010Rubber tile finish(H=600) - Galvanized steel frame filled with cement

    grout H=600mm,including accessories & anchor bolt including the 2%354.20 m2 172,495 172,495

    487.00 487.00

    000010Rubber tile finish(H=600) - Galvanized steel frame filled with cement

    grout H=600mm,including accessories & anchor bolt including the 2%354.20 m2 172,495 172,495

    487.00 487.00

    ACCESS FLOOR

    Rubber tile finish(H=600) - Galvanized steel frame filled with cementgrout H=600mm,including accessories & anchor bolt including the 2%

    of the spare material supply 354.2 m2 487.00 172,495

    12750020 BASE BOARD VINYL (H=100) 597.10 m 215 1,824 25,078 26,902

    0.36 3.05 42.00 45.05

    000010 BASE BOARD VINYL (H=100) 597.10 m 215 1,824 25,078 26,902

    0.36 3.05 42.00 45.05

    Prod=11.13 m/hour, 0.359MH/m, 2.78 m/MH, 53.64 hour

    BASE BOARD VINYL (H=100) 1.00 EA 34

    Tile Layer Foreman 1.0 12.00 644

    Tile Layer 2.0 8.00 858

    Tile Layer Helper 1.0 6.00 322

    BASE BOARD VINYL (H=100) 627.0 m 40.00 25,078

    12760000On gypsum board - Fenomastic 04 flat emulsion w/Fenomastic 20

    semi Gloss emulsion finish coat Acrylic emulsion Paint conforming to2,196.50 m2 6,240 48,360 76,878 125,238

    2.84 22.02 35.00 57.02

    000010On gypsum board - Fenomastic 04 flat emulsion w/Fenomastic 20

    semi Gloss emulsion finish coat Acrylic emulsion Paint conforming to2,196.50 m2 6,240 48,360 76,878 125,238

    2.84 22.02 35.00 57.02

    Prod=1.41 m2/hour, 2.841MH/m2, 0.35 m2/MH, 1,560.00 hour

    ACRYLIC PAINTDOOR & WINDOW, Polyamide, Oil Paint 2 Plies

    1.00 EA 31

    Painter Foreman 1.0 11.00 17,160

    Painter 2.0 7.00 21,840

    Painter Helper 1.0 6.00 9,360

    DOOR & WINDOW, Polyamide, Oil Paint 2 Plies 2,196.5 m2 35.00 76,878

    12760010ACRYLIC PAINT

    DOOR & WINDOW, Polyamide, Oil Paint 2 Plies697.04 m2 2,080 16,120 24,396 40,516

    2.98 23.13 35.00 58.13

    000010ACRYLIC PAINT

    DOOR & WINDOW, Polyamide, Oil Paint 2 Plies

    697.04 m2 2,080 16,120 24,396 40,516

    2.98 23.13 35.00 58.13

  • 8/10/2019 52- Process Plant Buildings Estimate Detail

    31/35

  • 8/10/2019 52- Process Plant Buildings Estimate Detail

    32/35

    08/11/2009 2:45:17 PM Page No 32 of 35

    Item Description Quantity UOM Rate ManHrs Labor Equip Job Mat Perm Mat Mech Elec Eq Sub/Plug Total Cost

    000010 Block filler & Fenomastic 04 flat emulsion Acrylic emulsion paint

    i i i l i

    2,415.71 m2 6,863 53,186 72,471 125,658

    2.84 22.02 30.00 52.02

    Prod=1.41 m2/hour, 2.841MH/m2, 0.35 m2/MH, 1,715.69 hour

    Block filler & Fenomastic 04 flat emulsion Acrylic emulsion paint 1.00 EA 31

    Painter Foreman 1.0 11.00 18,873Painter 2.0 7.00 24,020

    Painter Helper 1.0 6.00 10,294

    ACRYLIC PAINT

    Block filler & Fenomastic 04 flat emulsion Acrylic emulsion paint

    cinforming to SASO SSA 470 for Exterior emulsion 2,415.7 m2 30.00 72,471

    12760060EPOXY COATINGT=0.2mm Dust-proofing

    24.15 m2 20 220 845 1,065

    0.83 9.11 35.00 44.11

    000010EPOXY COATING

    T=0.2mm Dust-proofing24.15 m2 20 220 845 1,065

    0.83 9.11 35.00 44.11

    Prod=2.42 m2/hour, 0.828MH/m2, 1.21 m2/MH, 10.00 hourEPOXY COATINGT=0.2mm Dust-proofing

    1.00 EA 22

    Cement Finisher 2.0 11.00 220

    T=0.2mm Dust-proofing 24.2 m2 35.00 845

    12760070EPOXY COATING

    T=0.2mm Dust-proofing4,396.40 m2 3,641 40,050 153,874 193,924

    0.83 9.11 35.00 44.11

    000010EPOXY COATING

    T=0.2mm Dust-proofing4,396.40 m2 3,641 40,050 153,874 193,924

    0.83 9.11 35.00 44.11

    Prod=2.42 m2/hour, 0.828MH/m2, 1.21 m2/MH, 1,820.46 hour

    EPOXY COATINGT=0.2mm Dust-proofing

    1.00 EA 22

    Cement Finisher 2.0 11.00 40,050

    T=0.2mm Dust-proofing 4,396.4 m2 35.00 153,874

    12760080EPOXY COATING

    T=0.2mm For dust-proofing, under access floor279.45 m2 266 2,928 9,781 12,708

    0.95 10.48 35.00 45.48

    000010EPOXY COATING

    T=0.2mm For dust-proofing, under access floor279.45 m2 266 2,928 9,781 12,708

    0.95 10.48 35.00 45.48

    Prod=2.10 m2/hour, 0.952MH/m2, 1.05 m2/MH, 133.07 hour

    EPOXY COATINGT=0.2mm For dust-proofing, under access floor

    1.00 EA 22

    Cement Finisher 2.0 11.00 2,928

    T=0.2mm For dust-proofing, under access floor 279.5 m2 35.00 9,781

    12760090 Coaltar Epoxy,for U/G RC Surface,400micro (250mic.x 2plys) 5,252.81 m2 3,400 37,400 168,090 205,490

    0.65 7.12 32.00 39.12

    000010 Coaltar Epoxy,for U/G RC Surface,400micro (250mic.x 2plys) 5,252.81 m2 3,400 37,400 168,090 205,490

    0.65 7.12 32.00 39.12

    Prod=3.09 m2/hour, 0.647MH/m2, 1.54 m2/MH, 1,700.00 hour

    Coaltar Epoxy,for U/G RC Surface,400micro (250mic.x 2plys) 1.00 EA 22

    Cement Finisher 2.0 11.00 37,400

    It Description Quantity UOM Rate ManHrs Labor Equip Job Mat Perm Mat Mech Elec Eq Sub/Plug Total Cost

  • 8/10/2019 52- Process Plant Buildings Estimate Detail

    33/35

    08/11/2009 2:45:17 PM Page No 33 of 35

    Item Description Quantity UOM Rate ManHrs Labor Equip Job Mat Perm Mat Mech Elec Eq Sub/Plug Total Cost

    Coaltar Epoxy,for U/G RC Surface,400micro (250mic.x 2plys) 5,252.8 m2 32.00 168,090

    12760100URETHANE COATING

    One Pack Moisture cured, 500micro 1 Ply769.43 m2 539 5,925 30,777 36,702

    0.70 7.70 40.00 47.70

    000010URETHANE COATING

    One Pack Moisture cured, 500micro 1 Ply769.43 m2 539 5,925 30,777 36,702

    0.70 7.70 40.00 47.70Prod=2.86 m2/hour, 0.700MH/m2, 1.43 m2/MH, 269.30 hour

    URETHANE COATINGOne Pack Moisture cured, 500micro 1 Ply

    1.00 EA 22

    Cement Finisher 2.0 11.00 5,925

    One Pack Moisture cured, 500micro 1 Ply 769.4 m2 40.00 30,777

    12760110VINYL TILE

    Resilient Vinyl Tile,300x300x3T,Homogenious type350.68 m2 186 1,580 18,411 19,991

    0.53 4.51 52.50 57.01

    000010VINYL TILE

    Resilient Vinyl Tile,300x300x3T,Homogenious type350.68 m2 186 1,580 18,411 19,991

    0.53 4.51 52.50 57.01

    Prod=7.55 m2/hour, 0.530MH/m2, 1.89 m2/MH, 46.47 hour

    Resilient Tile 1.00 EA 34

    Tile Layer Foreman 1.0 12.00 558

    Tile Layer 2.0 8.00 743

    Tile Layer Helper 1.0 6.00 279

    Resilient Vinyl Tile,300x300x3T,Homogenious type 368.2 m2 50.00 18,411

    12760120BASE BOARD SELLAMIN PAINTbase board enamel paint(H=100)

    667.87 m 240 2,040 6,679 8,719

    0.36 3.05 10.00 13.05

    000010BASE BOARD SELLAMIN PAINT

    base board enamel paint(H=100)

    667.87 m 240 2,040 6,679 8,719

    0.36 3.05 10.00 13.05

    Prod=11.13 m/hour, 0.359MH/m, 2.78 m/MH, 60.00 hour

    BASE BOARD SELLAMIN PAINTbase board enamel paint(H=100)

    1.00 EA 34

    Tile Layer Foreman 1.0 12.00 720

    Tile Layer 2.0 8.00 960

    Tile Layer Helper 1.0 6.00 360

    base board enamel paint(H=100) 667.9 m 10.00 6,679

    12760130 ARCRLIC PAINT (H=100) 163.30 m 59 499 1,306 1,805

    0.36 3.05 8.00 11.05

    000010 ARCRLIC PAINT (H=100) 163.30 m 59 499 1,306 1,805

    0.36 3.05 8.00 11.05

    Prod=11.13 m/hour, 0.359MH/m, 2.78 m/MH, 14.67 hour

    ARCRLIC PAINT (H=100) 1.00 EA 34

    Tile Layer Foreman 1.0 12.00 176

    Tile Layer 2.0 8.00 235

    Tile Layer Helper 1.0 6.00 88

    ARCRLIC PAINT (H=100) 163.3 m 8.00 1,306

    12760140 BASE BOARD EPOXY PAINT 22.99 m 8 70 276 346

    0.36 3.05 12.00 15.05

    Item Description Quantity UOM Rate ManHrs Labor Equip Job Mat Perm Mat Mech Elec Eq Sub/Plug Total Cost

  • 8/10/2019 52- Process Plant Buildings Estimate Detail

    34/35

    08/11/2009 2:45:17 PM Page No 34 of 35

    Item Description Quantity UOM Rate ManHrs Labor Equip Job Mat Perm Mat Mech Elec Eq Sub/Plug Total Cost

    000010 BASE BOARD EPOXY PAINT 22.99 m 8 70 276 346

    0.36 3.05 12.00 15.05

    Prod=11.13 m/hour, 0.359MH/m, 2.78 m/MH, 2.07 hour

    BASE BOARD EPOXY PAINT 1.00 EA 34

    Tile Layer Foreman 1.0 12.00 25Tile Layer 2.0 8.00 33

    Tile Layer Helper 1.0 6.00 12

    BASE BOARD EPOXY PAINT 23.0 m 12.00 276

    12800000TOILET PARTITION

    Including partition door and accessories6.73 m2 30 300 13,460 13,760

    4.46 44.58 2,000.00 2,044.58

    000010TOILET PARTITION

    Including partition door and accessories6.73 m2 30 300 13,460 13,760

    4.46 44.58 2,000.00 2,044.58

    Prod=0.67 ea/hour, 4.458MH/ea, 0.22 ea/MH, 10.00 hour

    Toilet Partition 1.00 EA 30Specialties Foreman 1.0 12.00 120

    Specialty Tradesman 1.0 10.00 100

    Specialty Helper 1.0 8.00 80

    Including partition door and accessories 6.7 m2 2,000.00 13,460

    12800010 FRP SEPTIC TANK 1.00 EA 19 177 740 20,000 20,917

    18.75 177.08 739.60 20,000.00 20,916.69

    000010 FRP SEPTIC TANK 1.00 EA 19 177 740 20,000 20,917

    18.75 177.08 739.60 20,000.00 20,916.69

    Prod=0.48 ea/hour, 18.750MH/ea, 0.05 ea/MH, 2.08 hour

    FRP SEPTIC TANK 1.00 EA 440.01

    Equipment Operator Foreman 1.0 13.00 27

    Crane Operator Class-A 1.0 12.00 25

    Backhoe Operator 1.0 11.00 23

    Loader Operator 1.0 11.00 23

    Packer Operator 1.0 10.00 21

    Labourer 1.0 5.00 10

    Pipelayer 1.0 7.00 15

    Topman 1.0 6.00 13

    Rigger III 1.0 10.00 21

    Loader, 966f 1.0 62.44 130

    Excavator, Komatsu 1.0 62.56 130

    22" Smooth Drum Manual (Bomag 55) 1.0 10.00 21Roller 1 Steel Drum 1.0 47.77 100

    Telescopic Boom Mobile Crane, 70 Ton 1.0 158.82 331

    Pick-up Double Cabin 1.0 13.42 28

    FRP SEPTIC TANK 1.0 EA 20,000.00 20,000

    12800020 FRP SEPTIC TANK 2.00 EA 38 354 1,479 40,000 41,833

    18.75 177.08 739.60 20,000.00 20,916.69

    000010 FRP SEPTIC TANK 2.00 EA 38 354 1,479 40,000 41,833

    18.75 177.08 739.60 20,000.00 20,916.69

    Prod=0.48 ea/hour, 18.750MH/ea, 0.05 ea/MH, 4.17 hour

    FRP SEPTIC TANK 1.00 EA 440.01

    Item Description Quantity UOM Rate ManHrs Labor Equip Job Mat Perm Mat Mech Elec Eq Sub/Plug Total Cost

  • 8/10/2019 52- Process Plant Buildings Estimate Detail

    35/35

    08/11/2009 2:45:17 PM Page No 35 of 35

    Item Description Quantity UOM Rate ManHrs Labor Equip Job Mat Perm Mat Mech Elec Eq Sub/Plug Total Cost

    Equipment Operator Foreman 1.0 13.00 54

    Crane Operator Class-A 1.0 12.00 50

    Backhoe Operator 1.0 11.00 46

    Loader Operator 1.0 11.00 46

    Packer Operator 1.0 10.00 42

    Labourer 1.0 5.00 21

    Pipelayer 1.0 7.00 29

    Topman 1.0 6.00 25

    Rigger III 1.0 10.00 42

    Loader, 966f 1.0 62.44 260

    Excavator, Komatsu 1.0 62.56 261

    22" Smooth Drum Manual (Bomag 55) 1.0 10.00 42

    Roller 1 Steel Drum 1.0 47.77 199

    Telescopic Boom Mobile Crane, 70 Ton 1.0 158.82 662

    Pick-up Double Cabin 1.0 13.42 56

    FRP SEPTIC TANK 2.0 EA 20,000.00 40,000

    12800030FRP SEPTIC TANK50 PERSON

    1.00 EA 19 177 740 30,000 30,917

    18.75 177.08 739.60 30,000.00 30,916.69

    000010FRP SEPTIC TANK

    50 PERSON1.00 EA 19 177 740 30,000 30,917

    18.75 177.08 739.60 30,000.00 30,916.69

    Prod=0.48 ea/hour, 18.750MH/ea, 0.05 ea/MH, 2.08 hour

    FRP SEPTIC TANK50 PERSON

    1.00 EA 440.01

    Equipment Operator Foreman 1.0 13.00 27

    Crane Operator Class-A 1.0 12.00 25

    Backhoe Operator 1.0 11.00 23

    Loader Operator 1.0 11.00 23

    Packer Operator 1.0 10.00 21

    Labourer 1.0 5.00 10

    Pipelayer 1.0 7.00 15

    Topman 1.0 6.00 13

    Rigger III 1.0 10.00 21

    Loader, 966f 1.0 62.44 130

    Excavator, Komatsu 1.0 62.56 130

    22" Smooth Drum Manual (Bomag 55) 1.0 10.00 21

    Roller 1 Steel Drum 1.0 47.77 100

    Telescopic Boom Mobile Crane, 70 Ton 1.0 158.82 331

    Pick-up Double Cabin 1.0 13.42 28

    50 PERSON 1.0 EA 30,000.00 30,000

    12900000 CURTAIN BOX 11.22 m2 40 340 1,346 1,686

    3.57 30.30 120.00 150.30

    000010 CURTAIN BOX 11.22 m2 40 340 1,346 1,686

    3.57 30.30 120.00 150.30

    Prod=1.12 m2/hour, 3.565MH/m2, 0.28 m2/MH, 10.00 hour

    CURTAIN BOX 1.00 EA 34

    Carpenter Foreman 1.0 12.00 120

    Carpenter 2.0 8.00 160

    Carpenter Helper 1.0 6.00 60

    CURTAIN BOX 11.2 m2 120.00 1,346