5.3.4 the assonora water supply scheme (1) system development...
TRANSCRIPT
5 - 43
5.3.4 The Assonora Water Supply Scheme (1) System Development Plan a. Expansion of the Treatment Plant The Assonora WTP has a capacity of 42,000m3/day. It currently receives 15,000 m3/day of treated water from the Podocem WTP, which is part of the Sanquelim WSS. It is proposed that an extra 8,000 m3/day of treated water will be supplied from the Podocem WTP to the Assonora WTP until 2012, as shown in Figure 53.16. This will result in a total transmission of 23,000 m3/day of treated water from the Podocem WTP to the Assonora WTP. However, when the expansion of the existing Assonora WTP is completed, the transmission volume from the Podocem WTP will be returned to the current 15,000 m3/day level. The existing plant, constructed in 1968, has a capacity of 12,000 m3/day. It is proposed that this plant be abandoned in 2012, due to its age and because a new plant is expected to be constructed by that time. Although the PWD has a plan of 40,000 m3/day augmentation, it is recommended that the plant capacity be expanded to 50,000 m3/day in 2012, to meet demand from the Assonora WSS.
ExistingPlant II30 MLD(1992)
Treated Waterfrom Podocem
WTP15 MLD
until 2012Present
Ex. Plant I12 MLD(1968)
Treated Waterfrom Podocem
WTP23 MLD
ExistingPlant II
30 MLD(1992)
Ex. Plant I12 MLD(1968)
ExistingPlant II
30 MLD(1992)
Treated Waterfrom Podocem
WTP15 MLD
ProposedPlant
50 MLDAbandoned
aftercompletion of
new plant
Supplementof 8 MLD
fromPodocemWTP until
2012
after 2012
57 MLD
65 MLD
95 MLD
Figure 53.16 Supply Capacity of the Assonora WTP
5 - 44
The relationship between the daily maximum water demand and the supply capacity for the Assonora WSS is shown in Figure 53.17.
0
20,000
40,000
60,000
80,000
100,000
120,000
2005
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
Year
Wat
er Q
uant
ity (m
3 /day
)
Day Maximum Water DemandSupply Capacity
Figure 53.17 Relationship between Daily Maximum Water Demand and Supply Capacity for the Assonora WSS
b. Transmission Plan The proposed transmission plan for the Assonora WSS in 2025 is shown in Figure 53.18.
5 - 45
15.0MLD
Bichilim Taluka
Tiswadi Taluka
Pernem Taluka
Bardez Taluka
Assonora WTP (80MLD)93.7MLD
Podosem WTP90.1MLD
3.7MLD
Figure 53.18 Transmission Plan for the Assonora WSS
(2) Treatment Plant a. Water treatment plant capacity The existing Assonora WTP has a capacity of 42 MLD, excluding the 15 MLD supplied from the Podocem WTP. It is recommended that the existing 12MLD plant, commissioned in 1968, be abandoned in 2012 due to its age. This will reduce the plant capacity from 42 MLD to 30 MLD. The master plan proposes that an extra 50 MLD of new water treatment capacity is required to address water shortages that are expected in 2025. Therefore, the plant capacity will increase from 42 MLD (12 MLD + 30 MLD) to 80 MLD (30 MLD + 50 MLD). According to the Water Resources Department, the water resource availability for the Assonora WTP is 250 MLD from the Tillari Canal, which is enough for the future expansion. b. Proposed Water Treatment process The proposed water treatment process for the new water treatment plant consists of contact aeration, a coagulation basin, flocculation/sedimentation, sand filtration and chlorination. This process was designed with consideration of the raw water quality and existing process conditions (See Figure 53.19).
Figure 53.19 Proposed Water Treatment Process at the Assonora WTP
5 - 46
c. Implementation Schedule The timeline for the implementation schedule of WTP is shown in Table 53.20. Rehabilitation and improvement of the existing water treatment plant will be conducted during Stage I. Installation of chlorine safety equipment, replacement of equipment that has exceeded its design life, and installation of a generator and flow meters will be conducted over this period. It is recommended that a new treatment plant with a capacity of 50 MLD is constructed during Stage I.
Table 53.20 Implementation Schedule for Assonora WTP
Stage Existing Plants New Plants
Stage I Components
- Installation of safety equipment
- Replacement of raw water pumps and
backwash pumps
- Installation of generator and flow
meters
- Modification of coagulation process
Expansion of 50 MLD plant
(3) Transmission System a. Proposed Transmission System To cover the future service areas and to meet the increased demand, the transmission system shown in Figure 53.20 and summarised in Table 53.21 is proposed. Calculations using WaterCAD are attached in Volume IV Appendix M53 Results of Hydraulic Analysis. Table 53.21 Proposed Transmission Mains for the Assonora WSS
Material Diameter (mm) Length (km)
500 5.00
400 4.00
250 7.20
200 6.05
150 10.50
Ductile Iron
100 0.90
Total 33.65
5 - 47
Pernem Taluka
Bardez Taluka
Tiswadi Taluka
Bichilim Taluka
14.3kW x 3 units,100m3 sump
φ400DI, 0.8km
Padi, 300m3
Existing Transmission Mains
Existing Reservoirs
Proposed Transmission Mains
Details of Proposed Transmission Mains
Proposed Reservoirs
Details of Proposed Reservoir, Location & Volume
Details of Proposed Pumping Stations
Legend
Boundary of Taluka
Proposed Proposed Pumping StationsP
Assonora WTP Existing: 30,000 m3/day Proposed: 50,000 m3/day
Advalpal, 300m3
Menkurem, 300m3
Sirigao, 300m3
Madel, 650m3
Power Grid, 150m3
Vinani, 300m3
Bastora, 800m3
Girim, 800m3
Saligao, 800m3
Arpora, 800m3
Assonora MBR, 10,000m3
Dangarwadi, 800m3
φ200DI, 1.7km
φ200DI, 3.3km
φ100DI, 0.9km
φ250DI, 0.5km
φ150DI, 0.5kmφ500DI, 5.0km
φ400DI, 4.0kmφ250DI, 2.9km
φ150DI, 3.7km
φ200DI, 0.35km
φ150DI, 0.4km
φ150DI, 3.6km
φ250DI, 1.5km
φ250DI, 2.3km
φ200DI, 0.7km
φ150DI, 2.3km
Figure 53.20 Proposed Transmission System for the Assonora WSS in 2025
N
S
EW
Not to scale
5 - 48
b. Rehabilitation of the Existing Transmission System The Master Plan recommends the replacement of 30% of old transmission pipes installed before 1975, which is an estimated length of 6.0 km, to secure the transmission system of the Assonora WSS. (4) Reservoirs a. Proposed Reservoirs To supply treated water to an expanded service area, construction of thirteen reservoirs (as listed in Table 53.22) is proposed. Locations and volumes of the proposed reservoirs are shown in Figure 53.20. Table 53.22 List of Reservoirs proposed for the Assonora WSS
Location Capacity (m3) Remarks
Assonora MBR 10,000 addition to the existing reservoir of 10,000 m3
Advalpal 300 -
Menkurem 300 -
Sirigao 300 addition to the existing reservoir of 50 m3
Dangarwadi 800 -
Madel 650 -
Power Grid 150 -
Vinani 300 -
Bastora 800 addition to the existing reservoir of 250 m3
Girim 800 addition to the existing reservoir of 150 m3
Saligao 800 addition to the existing reservoir of 800 m3
Arpora 800 addition to the existing reservoir of 150 m3
Housing Board Porvolim 650
b. Rehabilitation of the Existing Reservoirs The Assonora WSS has 85 reservoirs, as summarised in Table 53.23. A detailed list of the reservoirs is attached in Volume IV Appendix M31 Existing Water Supply System. Table 53.23 also identifies the reservoirs that need to be rehabilitated.
5 - 49
Table 53.23 Number of Existing Reservoirs Number of Reservoirs
Reservoir Volume (m3) Existing to be rehabilitated
2,000 & 3,000 2 0
800 & 650 18 4
250, 300, 350 27 5
150 29 6
100 and less 9 2
Total 85 17
Note: not include the reservoirs at Assonora WTP
(5) Pumping Station a. Proposed Pumping Station According to the Master Plan, the Assonora WSS does not require the construction of new pumping stations. b. Rehabilitation of the Existing Pumping Station The design life of the pumping equipment is assumed to be 15 years. Therefore the pumping equipment in all the existing pumping stations will need to be replaced by 2025. Details are shown in Table 53.24. Table 53.24 Pumping Equipment Replacement Details
Pumping Unit (pump and motor) Name of Station
Rated Output (kW) No. of Units
Mapusa 5.9 3
Socorro 4.7 2
Pundalik Nagar 2.3 3
Porvorim 5.0 3
Torda 10.3 3
P.D.A. Colony 33.4 3
(6) Distribution Pipeline and House Connections a. Proposed Distribution Pipeline and House Connections The proposed length of distribution pipelines was calculated by multiplying the number of house connections to be installed (which reflects the increase in population served) by the unit pipeline length per connection (which is 14.26m as mentioned in section 5.1.2). Table 53.25 shows the proposed number of house connections and length of distribution pipelines.
5 - 50
Table 53.25 Proposed Number of House Connections and Length of Distribution Pipelines in the Assonora WSS (incremental basis)
Year 2007 2008 2009 2010 2011 2012 2013 Distribution Pipeline (m) 16,648 16,941 17,286 17,610 17,966 18,293 18,660
Number of House Connection 1,167 1,188 1,212 1,235 1,260 1,283 1,309
Year 2014 2015 2016 2017 2018 2019 2020 Distribution Pipeline (m) 19,049 19,409 19,806 20,220 20,640 21,064 21,488
Number of House Connection 1,336 1,361 1,389 1,418 1,447 1,477 1,507
Year 2021 2022 2023 2024 2025 Total Distribution Pipeline (m) 21,474 21,930 22,393 22,839 23,336 377,055
Number of House Connection 1,506 1,538 1,570 1,602 1,636 26,442
b. Rehabilitation of the Existing Distribution Pipelines and House Connections The design life of the distribution pipelines is assumed to be 50 years. It is planned that 2 % of the existing 724km of distribution pipelines will be replaced every year. This will total 38 % from 2007 to 2025. As a result, the existing 275 km of distribution pipelines will be replaced with new pipelines during the 19 years from 2007 to 2025. The design life of the water meters at the house connections is assumed to be 10 years. It is planned that all 55,355 existing water meters will be replaced within 10 years. As a result about 116,500 water meters will be replaced during the 19 years from 2007 to 2025. (7) Summary of the Planning The components of the Assonora WSS master plan are summarised in Table 53.26. Figure 53.21 depicts the proposed Assonora WSS in 2025.
5 - 51
Table 53.26 Components of the Assonora WSS Master Plan
Facility Proposed Rehabilitation/ Replacement
Treatment Plant 50,000 m3/day 30,000 m3/day
Transmission Main 41 km 6 km
Reservoir 16 14
Pumping Station 1 2
Distribution Pipeline 377 km 275 km
House Connection 26,442 116,500
5 – 52
Mar
na, 1
50G
LR,
RL=
78.0
,H
WL=
82.0
, LW
L=78
.3Ti
vim
, 300
OH
R,
RL=
51.0
,H
WL=
80.0
, LW
L=76
.0
Acc
oi, 1
50O
HR
,R
L=47
.0,
HW
L=66
.0, L
WL=
63.0
15M
LD T
reat
ed W
ater
from
Pod
ocem
WTP
Ass
onor
a, 3
00G
LR,
RL=
80.0
HW
L=84
.0, L
WL=
80.3
Pirn
a, R
L=41
.0,
50, 1
50, 3
00G
LR,
HW
L=45
.0, L
WL=
41.3
Nad
ora,
50G
LR &
300
GLR
,R
L=48
.0,
HW
L=52
.0, L
WL=
48.3
Rev
ora,
75G
LR &
300
GLR
,R
L=49
.0,
HW
L=53
.0, L
WL=
49.3
Qui
tula
, 50G
LR,
RL=
47.0
,H
WL=
49.5
, LW
L=47
.3
Ald
ona,
50G
LR,
300G
LR, R
L=33
.46,
HW
L=37
.46,
LW
L=33
.76
Kho
rjuem
, 150
GLR
,R
L=29
.1,
HW
L=33
.1, L
WL=
29.4
Lakd
em, 3
00G
LR,
RL=
38.1
5,H
WL=
42.1
5, L
WL=
38.4
5
Moi
ra, 1
50O
HR
,R
L=47
.0,
HW
L=66
.0, L
WL=
63.0
Nac
hino
la, 1
50O
HR
,R
L=48
.45,
HW
L=67
.45,
LW
L=64
.45
Nac
hino
la, 3
00G
LR,
50O
HR,
RL=
25.2
,H
WL=
44.2
, LW
L=41
.2
Pom
burp
a, 1
50G
LR,
RL=
53.1
1,H
WL=
57.1
1, L
WL=
53.4
1
Ecox
im, 1
50G
LR,
RL=
38.1
5,H
WL=
42.1
5, L
WL=
38.4
5
Sala
i,80
0GLR
& 1
50G
LR,
RL=
56.4
2,H
WL=
56.7
2, L
WL=
60.4
2
Ass
agao
, 800
GLR
,R
L=48
.0,
HW
L=52
.0, L
WL=
48.3
Vag
ator
, 800
GLR
,R
L=40
.0,
HW
L=44
.0, L
WL=
40.3
Anj
una,
800
GLR
,R
L=49
.0,
HW
L=53
.0, L
WL=
49.3
Parr
a, 1
50G
LR,
RL=
42.0
,H
WL=
46.0
, LW
L=42
.3
Arp
ora,
RL=
50.0
,15
0GLR
,H
WL=
54.0
, LW
L=50
.3
Oxe
l, 30
0GLR
,R
L=49
.0,
HW
L=53
.0, L
WL=
49.3
Sodi
em, 3
00G
LR,
RL=
51.0
,H
WL=
55.0
, LW
L=51
.3
Cam
urlim
, 300
GLR
,R
L=48
.0,
HW
L=52
.0, L
WL=
48.3
Cuc
helim
, 150
GLR
,R
L=49
.0,
HW
L=53
.0, L
WL=
49.3
Siol
im, 8
00G
LR,
150G
LR, R
L=50
.0,
HW
L=54
.0, L
WL=
50.3
Bas
tora
, 250
GLR
,R
L=46
.0,
HW
L=50
.0, L
WL=
46.3
Uca
ssai
m, 3
00G
LR,
RL=
47.0
,H
WL=
51.0
, LW
L=47
.3
Pedd
em, 3
00O
HR
,R
L=50
.0,
HW
L=69
.0, L
WL=
66.0
Kho
rlim
, 300
GLR
,R
L=78
.0,
HW
L=82
.0, L
WL=
78.3
Ass
agao
, 150
GLR
,R
L=66
.0,
HW
L=70
.0, L
WL=
66.3
Map
usa,
RL=
85.0
300G
LR &
800
GLR
,H
WL=
89.0
, LW
L=85
.3
Map
usa,
2000
GL
R, R
L=7
5.0,
HW
L=7
9.0,
LW
L=7
5.3,
& 8
00G
LR
, RL
=80.
0,H
WL
=84.
0, L
WL
=80.
3
Hou
sing
Boa
rd, R
L=87
.0,
100O
HR
,H
WL=
106.
0, L
WL=
103.
0,30
0OH
R,
HW
L=10
7.0,
LW
L=10
3.0
Sils
aim
, 150
GLR
,R
L=48
.6,
HW
L=52
.6,L
WL=
48.9
Colv
ale,
150
GLR
,R
L=50
.0,
HW
L=54
.0, L
WL=
50.3
Col
vale
, 300
GLR
,R
L=48
.0,
HW
L=52
.0, L
WL=
48.3
Sinq
uelim
,80
0GLR
, RL=
48.0
,H
WL=
??.?
, LW
L=??
.?,
& 1
50G
LR, R
L=30
.0,
HW
L=??
.?, L
WL=
??.?
Can
dolim
, RL=
40.0
,15
0GLR
& 8
00G
LR,
HW
L=44
.0, L
WL=
40.3
Soco
rro, R
L=55
.0,
150O
HR
,H
WL=
74.0
, LW
L=70
.0,
150G
LR &
300
Sum
pH
WL=
59.0
, LW
L=55
.3 Tord
a, R
L=60
.080
0OH
R,
HW
L=84
.0, L
WL=
80.0
,&
300
GLR
, HW
L=64
.0, L
WL=
60.3
Porv
orim
, RL=
58.0
,15
0OH
R,
HW
L=77
.0, L
WL=
73.0
,&
800
GLR
,H
WL=
62.0
, LW
L=58
.0
Pile
rna,
150
GLR
, RL=
50.0
,H
WL=
54.0
, LW
L=50
.3
Alto
-Bet
im,
150G
LR, R
L=55
.0,
HW
L=59
.0, L
WL=
55.3
Pund
alik
Nag
ar, R
L=55
.0,
300O
HR
,H
WL=
74.0
, LW
L=70
.0,
& 3
00G
LR,
HW
L=55
.3, L
WL=
59.0
Secr
etar
iate
Com
plex
0.2M
LD
Ver
em,
250G
LR, R
L=70
.0,
HW
L=74
.0, L
WL=
70.3
Ner
ul,
150G
LR, R
L=55
.0,
HW
L=59
.0, L
WL=
55.3
Cal
angu
te, 8
00G
LR,
RL=
30.0
,H
WL=
34.0
, LW
L=30
.3
Cal
angu
te, 1
50O
HR
,R
L=25
.0,
HW
L=44
.0, L
WL=
40.0
Ass
onor
a M
BR
4×80
0,m
3, 5
,000
m3,
RL=
120.
00
Men
kure
m(P
ropo
sed)
300G
LR
, RL
=42.
0
Adv
alpa
l(Pro
pose
d)30
0GL
R, R
L=48
.0,
Usa
p, R
L=41
.0,
800G
LR,
HW
L=41
.3, L
WL=
45.0
Ass
onor
a W
TP(4
2MLD
)
Ass
onor
a R
iver
Sirig
aoR
L=51
.0,
50G
LR,
HW
L=55
.0, L
WL=
51.3
Cans
a-B
odie
m, 5
0GLR
,R
L=46
.8,
HW
L=49
.3, L
WL=
47.1
Dan
garw
adi(P
ropo
sed)
,80
0GL
R, R
L=6
1.0
Chi
calim
, 150
GLR
,R
L=50
.0,
HW
L=54
.0, L
WL=
50.3
Vin
ani(P
ropo
sed)
,30
0GL
R,R
L=5
0.0
Pow
er G
rid(
Prop
osed
),15
0GL
R,R
L=3
5.0
Ver
la-C
anca
, 150
GLR
,80
0GLR
, RL=
65.0
,H
WL=
69.0
, LW
L=65
.3
Map
usa,
150
OH
R,R
L=85
.0,
HW
L=10
4.0,
LW
L=10
1.0
Gui
rim15
0GLR
, RL=
42.0
, H
WL=
46.0
, LW
L=42
.3,
650O
HR
, RL=
42.0
,H
WL=
71.0
, LW
L=68
.0
Sang
olda
, 300
GR
L,R
L=48
.0,
HW
L=52
.0, L
WL=
48.3
Salig
ao, R
L=48
.0,
800G
LRH
WL=
52.0
, LW
L=48
.3
Map
usa,
RL=
67.0
,65
0GLR
& 6
50G
LR,
HW
L=71
.0, L
WL=
67.3
P.D
.A. C
olon
y,30
00G
LR, R
L=80
.0,
HW
L=84
.0, L
WL=
80.0
25M
LD R
aw W
ater
from
Pod
ocem
Inta
ke (R
aw W
ater
Res
ervo
ir)
LEG
END
Wat
er T
reat
men
t Pla
ntM
BR
(Mas
ter B
alan
cing
Res
ervo
ir)G
LR (G
roun
d Le
vel R
eser
voir)
/OH
R (O
ver H
ead
Res
ervo
ir)Tr
ansm
issi
on M
ain
M
ain
Dia
met
er D
350
mm
Lin
e
Mai
n D
iam
eter
D40
0 m
m L
ine
M
ain
Dia
met
er D
700
mm
Lin
e
Mai
n D
iam
eter
D11
00 m
m L
ine
M
ain
Dia
met
er D
1200
mm
Lin
e (P
umpi
ng M
ain)
M
ain
Dia
met
er D
300
mm
Lin
e (to
Bic
holim
Tal
uka)
P
ropo
sed
Tran
smis
sion
Mai
n
Arp
ora,
RL
=50.
0,80
0GL
R(P
ropo
sed)
Salig
ao, R
L=4
8.0,
800G
LR
(Pro
pose
d)
Bas
tora
,RL
=46.
0,80
0GL
R(P
ropo
sed)
Siri
gao
RL
=51.
0,30
0GL
R(P
ropo
sed)
φ20
0DI,
1.7k
m
φ20
0DI,
3.3k
m
φ1
00D
I, 0.
9km
φ25
0DI,
0.5k
m
φ150DI, 0.5km
φ50
0DI,
5.0km
φ250
DI, 2.9k
m
φ15
0DI,
3.7k
m
φ40
0DI,
4.3k
mφ
200D
I, 0.
35m
φ15
0DI,
0.4k
mφ150DI, 3.6km
φ25
0DI,
1.5km
φ25
0DI,
2.3km
φ15
0DI,
2.3k
m
φ20
0DI,
0.7k
m
Tivi
m ID
C, 1
50O
HR
,R
L=50
.0,
HW
L=69
.0, L
WL=
66.0
Mad
el(P
ropo
sed)
,65
0GL
R, R
L=4
8.0
Vad
dem
, 150
GLR
,R
L=50
.0,
HW
L=54
.0, L
WL=
50.3
Gui
rim
RL
=42.
0, 8
00G
LR
(Pro
pose
d)
Ola
ulim
, 150
GLR
,R
L=66
.0,
HW
L=70
.0, L
WL=
66.3
Hou
sing
Boa
rdPo
rvol
im65
0OH
R(P
ropo
sed)
Ass
onor
a M
BR
(Pro
pose
d)10
,000
GL
R, R
L=1
20.0
,
Figure 53.21 Proposed System for the Assonora Water Supply Scheme in 2025
N S
EW
02
km4
km6
km