PMP Prep – Integration Slide 1

DAY 1

PROJECT INTEGRATION

MANAGEMENT

Page 2: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 2/590

AGENDAAGENDA 

Day 1

PMP Exam Prep Introduction

Project Management Framework 

*Project Life Cycle & Organisation

Project Management Processes

Project INTEGRATION Management

  DAY 2 

Project SCOPE ManagementProject TIME Management

Project COST Management

Project QUALITY Management

  DAY 3

Project COMMUNICATION Management

Project HUMAN RESOURCE Management

Project RISK Management

Project PROCUREMENT Management

DAY 4

Professional & Social Responsibility

REVISION & QUIZ

Page 3: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 3/590

MAJOR PROJECTMAJOR PROJECTDOCUMENTSDOCUMENTS

Before we begin Integration, let's summarize theproject's major documents:

Major Project Documents - generated by the project

• Project Charter  – formally authorizes a project or a phaseand documents initial requirements that satisfy thestakeholder’s needs and expectations. (never changes)

• Project Management Plan – documents the actionsnecessary to define, prepare, integrate, and coordinate allsubsidiary management plans (changes a lot)

PMP Prep - Integration Slide 2

ALL are formallyapproved

Page 4: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 4/590

MAJOR PROJECTMAJOR PROJECTDOCUMENTSDOCUMENTS

Other Project Documents (or Systems) Used by the Project

 These systems could include tools, techniques, methodologies, resources(i.e. templates), procedures, documentation, tracking systems, approvallevels, etc.

Project Management Information System(PMIS)

 • an information system, consisting of the tools and techniques used togather, integrate, and disseminate the outputs of project managementprocesses.

• It is used by project management team to support all aspects of theproject from initiating through closing, and can include both manual andautomated systems.

PMP Prep - Integration Slide 3

Page 5: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 5/590

MAJOR PROJECTMAJOR PROJECT

DOCUMENTSDOCUMENTS  Configuration Management System

It is a sub-system of the overall PMIS. It is a collection of formal documented proceduresused to apply technical and administrative direction and surveillance to:

- identify and document the functional and physical characteristics of aproduct, result, service, or component;

- control any changes to such characteristics;- record & report each changes and its implementation status; and- support the audit of the products, results, or components to verify conformance torequirements

- it includes the documentation, tracking systems, and defined approval levelsnecessary for authorizing and controlling changes.

Change Control System - is a collection of formal documented procedures thatdefine how deliverables and documentation are controlled, changed and approvedIn most application areas CCS is a subset of the configuration management system.

PMP Prep - Integration Slide 4

Page 6: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 6/590

PROJECT INTEGRATIONPROJECT INTEGRATION

MANAGEMENTMANAGEMENT

Coordinate all knowledge areaprocesses

WHAT DOES THE INTEGRATION KNOWLEDGE AREA DO?• It's about the entire project - processes & activities needed to

identify, define, combine, unify, and coordinate the variousprocesses and project management activities within the projectmanagement process groups

• Projects start and close here.• Project plan is made here.• Product, service or result is made here.

 

PMP Prep - Integration Slide 5

Page 7: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 7/590

PROJECT INTEGRATIONPROJECT INTEGRATION

MANAGEMENTMANAGEMENT

 

The integrative nature of projects and project managementcan be understood by thinking of other types of activitiesperformed while completing a project. Examples of someactivities performed by the PM team are:

•  Analyze and understand the scope. This includes the project andproduct requirements, criteria, assumptions, constraints, and other influences related to a project, and how each will be managed or addressed within the project.

• Understand how to take the identified information and then transform itinto a project management plan using a structured approach as

described in PMBOK Guide.• Perform activities to produce project deliverables.• Measure and monitor all aspects of the project’s progress and take

appropriate action to meet project objectives.

PMP Prep – Integration Slide 6

Page 8: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 8/590

INTEGRATION PROCESSESINTEGRATION PROCESSES

INTEGRATION PROCESS DEFINITIONS 4.1 Develop Project Charter 

• that formally authorizes a project or a project phase.

4.2 Develop Project Management Plan• the process of documenting the actions necessary to define,prepare, integrate, and coordinate all subsidiary plan.

 

4.3 Direct & Manage Project Execution• the process of performing the work defined in the project

management plan to achieve the project’s objectives. 

PMP Prep – Integration Slide 7

Page 9: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 9/590

INTEGRATION PROCESSESINTEGRATION PROCESSES

4.5 Monitor & Control Project Work• The process of tracking, reviewing, and regulating the progress to

meet the performance objectives defined in the projectmanagement plan.

4.6 Perform Integrated Change Control• Review all change requests, approve changes, and manage

changes to the deliverables, organizational process assets, projectdocuments, and the project management plan.

4.7 Close Project or Phase• Finalize all activities across all Project Management Process Groups

to formally complete the project or phase. 

PMP Prep – Integration Slide 8

Page 10: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 10/590

INTEGRATION PROCESSESINTEGRATION PROCESSES

PMP Prep – Integration Slide 9

PROCESSES BY PROCESS GROUPInitiating Planning Executing Monitoring and

controllingClosing

4.1 DevelopProject

Charter 

4.3 DevelopProject

ManagementPlan

4.4 Direct andManageProject

Execution

4.5 Monitorand Control

Project work

4.7 CloseProject or

Phase

4.6 Perform

IntegratedChangeControl

Page 11: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 11/590

What should a project charter address?

• Project purpose or justification, • Measurable project objectives and related success criteria,• High-level requirements,

• High-level project description,• High-level risks,• Summary milestone schedule,• Summary budget,• Project approval requirements,• Assigned project manager, responsibility, and authority level, and• Name and authority of the sponsor or other person(s) authorizing the

project charter.

PMP Prep – Integration Slide 10

PROJECT CHARTERPROJECT CHARTER

Formallyauthorizes

a project (never changes)

Page 12: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 12/590

DEVELOP PROJECTDEVELOP PROJECTCHARTERCHARTER 

PMP Prep – Integration Slide 11

Inputs• Project statement of work• Business Case• Contract

• Enterpriseenvironmental

factor• Organizational process

assets

Outputs

• Project Charter

Tools & Techniques

• Expert judgement

Page 13: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 13/590

  INPUTSContract (when applicable)• A contract from the customer’s acquiring organization is an input if theproject is being done for an external customer.

 

Project Statement of Work• Narrative description of products or services to be supplied by the

project• For internal projects, the project initiator or sponsor provides the

statement of work based on business needs, products or servicerequirements.

• For external projects, the SOW can be received from the customer aspart of a bid document, for example, request for proposal, request for information, request for bid, or as part of a contract.

PMP Prep – Integration Slide 12

DEVELOP PROJECT CHARTER-DEVELOP PROJECT CHARTER-

INPUTSINPUTS

Page 14: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 14/590

DEVELOP PROJECTDEVELOP PROJECT

CHARTER-INPUTSCHARTER-INPUTSThe SOW references:

• Business need - an organization’s business need can be based on neededtraining, market demand, technological advance, legal requirement, or governmental standard

• Product scope description – documents the product requirements andcharacteristics of the product or service that the project will be undertaken tocreate

• Strategic plan -all projects should support the organization's strategic goals.The strategic plan of the performing organization should be considered as afactor when making project selection decisions.

PMP Prep – Integration Slide 13

Page 15: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 15/590

DEVELOP PROJECTDEVELOP PROJECTCHARTER-INPUTSCHARTER-INPUTS

Business Case:• Business case or similar document provides the necessary information from abusiness standpoint to determine whether or not the project is worth the requiredinvestment.

• Typically the business need and the cost-benefit analysis are contained in thebusiness case to justify the project.

• For external project, the requesting organization or customer may write thebusiness case.

• Business case is created as a result of one or more of the following:

- Market demand

- Organizational need

- Customer request

- Technological advance

- Legal requirement

- Ecological impacts

- Social need

PMP Prep – Integration Slide 14

DEVELOP PROJECT CHARTERDEVELOP PROJECT CHARTER

Page 16: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 16/590

Enterprise Environmental Factors

• Governmental or industry standards 

• Organization Infrastructure, and

• Marketplace conditions

DEVELOP PROJECT CHARTER-DEVELOP PROJECT CHARTER-

INPUTSINPUTS

These are examplesand not specific to

Project Charter – aninput to all

knowledge areas

DEVELOP PROJECT CHARTERDEVELOP PROJECT CHARTER

Page 17: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 17/590

Organizational Process Assets 

• Organizational standard processes, policies, and standardized processdefinitions for use in the organization;

• Templates (e.g. project charter template); and

• Historical information and lessons learned knowledge base.

DEVELOP PROJECT CHARTER-DEVELOP PROJECT CHARTER-

INPUTSINPUTSNot specific to

project Charter  – an input to allknowledge

areas

Page 18: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 18/590

DEVELOP PROJECTDEVELOP PROJECT

CHARTER- T & TCHARTER- T & TExpert Judgement

It is available from many sources, including:

• Other units within the organization,

• Consultants,

• Stakeholders, including customers or sponsors,

• Professional and technical associations,

• Industry groups,

• Subject matter experts, and

• Project management office (PMO)

PMP Prep – Integration Slide 17

Page 19: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 19/590

TOOLS & TECHNIQUES 

Project Selection Methods 

• Mostly financial considerations are used.• Project selection is generally the responsibility of Portfolio Managers,

Steering Committees. In smaller companies, Presidents and Vice-Presidents

These methods generally fall into one of two broad categories:• Benefit measurement methods that are comparative approaches,

scoring models, benefit contribution, or economic models.

• Mathematical models that use linear, nonlinear, dynamic, integer, or multi-objective programming algorithms

PMP Prep – Integration Slide 18

DEVELOP PROJECTDEVELOP PROJECTCHARTER-T & TCHARTER-T & T

Page 20: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 20/590

Weighted Scoring Model (benefit measurement method)

 A systematic process for selecting projects based on criteria (example on nextslide)

• First, decide on a list of criteria used for project selection• Assign weights (percentages) to each so that they add up to 100%•   Assign scores to each for each project•  Multiply scores by weights to get total weighted scores for each

project•  Highest weighted score wins

Note: Also used for selecting contractors/sellers (Procurement)

PMP Prep – Integration Slide 19

DEVELOP PROJECTDEVELOP PROJECTCHARTER-T & TCHARTER-T & T

Page 21: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 21/590

DEVELOP PROJECTDEVELOP PROJECTCHARTER-T & TCHARTER-T & T

PMP Prep – Integration Slide 20

Page 22: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 22/590

Other Benefit Measurement Methods:

Cash Flow Techniques 

a) Payback Period  

• Length of time it will take to get back the initial investment• Time value of money is ignored here, i.e. no interest, so this is

the least precise of the cash flow techniques

Example:

Initial Investment (P) = $200,000Cash Inflow (C) =$25,000 I quarter for 3 yearsn = # of periodsPayback period (n) = P/C= $ 200,000 I $25,000 = 8 quarters or two years

PMP Prep – Integration Slide 21

DEVELOP PROJECTDEVELOP PROJECTCHARTER- T&TCHARTER- T&T

Page 23: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 23/590

b) Discounted Cash Flow (or Net Present Value method)Calculates the present worth of future money (called netpresent value)

Example -Which project is worth more?

Project X expects to make $250K 1 year from nowProject Y expects to make $300K 2 years from now

i= 12% (or 0.12)

Given this formula, calculate present value & pick one.PV = FV/ (1 +i)n or FV = PV(1 +i)n 

Where FV is future value, PV is present value, n is number of periods , i is

interest rateProject X, PV=250/1.12= 223.2 ; Project Y, PV=300/(1.12)2 = 239.2

Project Y is worth more.

PMP Prep – Integration Slide 22

DEVELOP PROJECTDEVELOP PROJECTCHARTER- T&TCHARTER- T&T

Page 24: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 24/590

Net Present ValueCalculates the expected net value of a project in today's money

To do this, discount all anticipated cash inflows and outflows to thepresent day

If Interest (i) = 12% & Initial Investment (P) = $20,000, what's the NPV of this? NPV=Total of all PVs-P

PMP Pre –Inte ration Slide 23

DEVELOP PROJECTDEVELOP PROJECTCHARTER- T&TCHARTER- T&T

Page 25: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 25/590

Question

 You're managing a software project for a manufacturingcompany. A new computer, which costs $50,000 includingshipping and installation, will speed up the development

process and cause a gross savings of $100,000 after one yearof purchase of the computer.

Assuming an interest rate of 10% per annum, what's the NPV of the savings ?

A. $90,000B. $40,909C. $45,555D. $91,110

DEVELOP PROJECTDEVELOP PROJECTCHARTER- T&TCHARTER- T&T

Page 26: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 26/590

Answer is B 

 You know:FV of the investment == $100,000i = 10% or 0.1n= 1 (year)

P (initial investment) == $50,000

NPV =PVc - P (initial investment), we need all the PV's (in this problem onlyone).

Since PV=FV/(1 +i)n Or, PV= $100,000/ (1 + 0.1 )1 = $90,909.09 ( is the present value )

Therefore, NPV = $90,909 -$50,000 == $40,909

PMP Prep – Integration Slide 25

DEVELOP PROJECTDEVELOP PROJECTCHARTER- T&TCHARTER- T&T

Page 27: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 27/590

 

Accounting Terms 

Sunk Cost (Incurred Cost):• In project selection method, when comparing projects for continuity,

costs already incurred should be considered as sunk costs and should

not be taken in to account in any calculation 

Opportunity Cost :• The cost of the opportunity that you picked• What did you give up (your cost) for the project you selected?• The amount you would have made if you picked the project with the

next best NPV (expected value in today's money)• Opportunity cost is always the second best alternative (doesn't take

the third or subsequent projects into account)

PMP Prep - Integration Slide 26

DEVELOP PROJECTDEVELOP PROJECTCHARTER- T&TCHARTER- T&T

Page 28: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 28/590

Internal Rate of Return (IRR)

• IRR is the interest rate when NPV equals zero (0) • Net present value of all cash inflows (revenue) and outflows(investments) are the same

• Choose projects with highest IRR

PMP Prep - Integration Slide 27

DEVELOP PROJECTDEVELOP PROJECTCHARTER- T&TCHARTER- T&T

Page 29: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 29/590

Question

Four projects are being considered.

 A. NPV is negative, its IRR is 16%, and its payback period is 13 months.

B. NPV is positive, its IRR is 14%, and its payback period is 2 months.C. NPV is negative, its IRR is 9%, and its payback period is 16 months.D. NPV is positive, its IRR is 16%, and its payback period is 18 months.

Which project should you choose if financial consideration is important?

PMP Prep - Integration Slide 28

DEVELOP PROJECTDEVELOP PROJECTCHARTER- T&TCHARTER- T&T

Page 30: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 30/590

 Answer is D.

If IRR is greater than 0 and NPV is positive, you shouldn't give payback periodmuch consideration as its the least precise calculation. Don't select projects A or C with negative NPV. Project D has a higher IRR than Project B and should be

chosen, even though Project B has a shorter payback period.

Consideration in order of priority:

1. IRR (highest positive)

2. NPV (highest positive)

3. Payback period (shortest)

PMP Prep - Integration Slide 29

DEVELOP PROJECTDEVELOP PROJECTCHARTER- T&TCHARTER- T&T

Page 31: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 31/590

2. Project Management Methodology • Defines a set of project management process groups, their related

processes and the related control functions that are consolidated andcombined into a functioning unified whole.

3. Project Management Information System (PMIS)

4. Expert Judgment• Expert judgment is often used to assess inputs used to make the

Project Charter • Available from many sources, including:• Other departments in your organization• Consultants• Stakeholders• Professional or technical associations and industry groups, i.e. PMI

 PMP Prep - Integration Slide 30

DEVELOP PROJECTDEVELOP PROJECTCHARTER- T&TCHARTER- T&T

Page 32: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 32/590

OUTPUT

 

Project Charter 

PMP Prep - Integration Slide 31

DEVELOP PROJECT CHARTER -DEVELOP PROJECT CHARTER -

OUTPUTSOUTPUTS

Page 33: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 33/590

INTEGRATION PROCESSESINTEGRATION PROCESSES

PMP Prep – Integration Slide 32

PROCESSES BY PROCESS GROUPInitiating Planning Executing Monitoring

andcontrolling

Closing

4.1 Develop

Project

Charter

4.2 DevelopProject

ManagementPlan

4.3 Directand Manage

ProjectExecution

4.4 Monitorand Control

Project work

4.6 CloseProject

4.5 PerformIntegrated

ChangeControl

Page 34: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 34/590

INTEGRATION PROCESSESINTEGRATION PROCESSES

PMP Prep – Integration Slide 38

PROCESSES BY PROCESS GROUPInitiating Planning Executing Monitoring

andcontrolling

Closing

4.1 Develop

Project

Charter

4.2 DevelopProject

ManagementPlan

4.3 Directand Manage

ProjectExecution

4.4 Monitorand Control

Project work

4.6 CloseProject

4.5Integrated

ChangeControl

Page 35: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 35/590

What’s in a Project Management Plan? 

•  Documents/defines 'how' a project is executed, monitored andcontrolled

• Generally includes subsidiary management plans & other planning documents

• May be summary or detailed plan (changes often)

• Formally approved

• Updates are approved through the Integrated Change Controlprocess and implemented in the Direct and Manage ProjectExecution process

PMP Prep - Integration Slide 39

PROJECT MANAGEMENTPROJECT MANAGEMENTPLANPLAN

Page 36: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 36/590

Specifically the plan includes:

• Which processes have been selected• Level of implementation of each of the processes (how thorough

each should be)• Which inputs, tools & techniques and outputs are to be used for 

each process• How processes will be used, their dependencies & interactions• How work will be executed• How changes will be monitored & controlled• How configuration management will be performed• How baseline integrity will be maintained (i.e. approved budget or 

schedule )• Stakeholder communication needs & techniques to be used• Project life cycle (if needed for phases)• Key management reviews

PMP Prep - Integration Slide 40

PROJECT MANAGEMENTPROJECT MANAGEMENTPLANPLAN

Page 37: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 37/590

Subsidiary management plans (if required), such as: 

• Scope

• Schedule

• Cost

• Quality

• Process Improvement (in Quality)

• Staffing

• Communication

• Risk• Procurement

PMP Prep - Integration Slide 41

PROJECT MANAGEMENTPROJECT MANAGEMENTPLANPLAN

Page 38: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 38/590

Other components, such as:

•  Milestone list

• Resource calendar 

• Schedule baseline

• Quality baseline

• Risk register  

All these give explicit details of 'how' to produce the requirement(s)

PMP Prep - Integration Slide 42

PROJECT MANAGEMENTPROJECT MANAGEMENTPLANPLAN

Page 39: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 39/590

DEVELOP PROJECTDEVELOP PROJECT

MANAGEMENT PLANMANAGEMENT PLAN 

PMP Prep – Integration Slide 43

Inputs• Project Charter  • Output from Planning

processes• Enterprise environmental

factor • Organizational process

assets

Outputs

• Project management

Plan

TOOLS &Techniques

• Expert judgement

Page 40: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 40/590

INPUTS

• Project Charter 

• Output from Plannning Processes

• Enterprise Environmental Factors

• Organizational Process Assets

PMP Prep - Integration Slide 44

DEVELOP PROJECTDEVELOP PROJECT

MANAGEMENT PLANMANAGEMENT PLAN

Page 41: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 41/590

TOOLS & TECHNIQUES

•Expert Judgment

PMP Prep - Integration Slide 45

DEVELOP PROJECTDEVELOP PROJECT

MANAGEMENT PLANMANAGEMENT PLAN

Page 42: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 42/590

OUTPUT

PMP Prep - Integration Slide 46

DEVELOP PROJECTDEVELOP PROJECT

MANAGEMENT PLANMANAGEMENT PLAN

  Project Management Plan

Page 43: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 43/590

INTEGRATION PROCESSESINTEGRATION PROCESSES

PMP Prep – Integration Slide 47

PROCESSES BY PROCESS GROUPInitiating Planning Executing Monitoring

andcontrolling

Closing

4.1 Develop

Project

Charter

4.2 DevelopProject

ManagementPlan

4.3 Directand Manage

ProjectExecution

4.4 Monitorand Control

Project work

4.6 CloseProject

4.5Integrated

ChangeControl

Page 44: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 44/590

WHAT HAPPENS DURING PROJECT EXECUTION? 

•  PM and the project team to perform multiple actions to execute the

project management plan to accomplish the work defined in the

project scope statement.

• Some actions create the project's product, service or result while

other actions manage the whole of the project in an integrated

manner 

•  Some actions include:

• Perform activities to accomplish project objectives•  Expend effort and spend funds to accomplish project objectives• Staff, train & manage project team members

• Obtain quotations, bids, offers, or proposals as appropriate

Select sellers

……continued

PMP Prep - Inte ration Slide 48

DIRECT AND MANAGE PROJECTDIRECT AND MANAGE PROJECT

EXECUTIONEXECUTION

Page 45: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 45/590

 • Obtain, manage & use resources including materials, tools,

equipments and facilities

• Implement the planned methods and standards

• Create, control, verify & validate project deliverables

• Manage risks & implement risk response activities

• Manage sellers

• Adapt approved changes into project scope, plans & environment

• Establish & manage project communication channels both external

& internal to the project team

• Collect project data and report cost, schedule, technical & quality

• progress, and status information to facilitate forecasting• Collect & document lessons learned, and implement approved

process improvement activities

PMP Prep - Integration Slide 49

DIRECT AND MANAGE PROJECTDIRECT AND MANAGE PROJECT

EXECUTIONEXECUTION

Page 46: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 46/590

DIRECT AND MANAGE PROJECTDIRECT AND MANAGE PROJECT

EXECUTIONEXECUTION 

PMP Prep – Integration Slide 50

Inputs• Project management plan

• Approved change requests• Enterprise Environmentalfactors•Organisational process Assets

Outputs• Deliverables•Work performance information

•Change requests• Project management planupdates• Project document updates

TOOLS &Techniques

• Expert judgement • Project management

Information system

Page 47: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 47/590

INPUTS

• Project Management Plan

Enterprise Environmental factors : The enterprise environmental factors

that can influence the direct and manage project execution process include:•Organizational, company or customer culture/structure,

•Infrastructure (existing facilities and capital equipment)

•Personnel administration(hiring and firing guidelines),

• stakeholder risk tolerances,

•Project management information system•Organizational Process assets: standardized guidelines and workinstructions, communication requirements defining allowed communicationmedia, record retention, and security requirements, project files from prior projects(e.g. scope, cost, schedule etc), issue and defect management databasecontaining historical issues and defect status, its control, resolutions and

actions.

DIRECT AND MANAGE PROJECTDIRECT AND MANAGE PROJECT

EXECUTIONEXECUTION

Page 48: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 48/590

• Approved Change Request

They are documented, authorized changes to expand or contractproject scope. They can also modify policies, project managementplans, procedures, costs or budgets, or revise schedules. They arescheduled for implementation by the project team.

PMP Prep - Integration Slide 52

DIRECT AND MANAGE PROJECTDIRECT AND MANAGE PROJECT

EXECUTIONEXECUTION

Page 49: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 49/590

TOOLS & TECHNIQUES

•Expert Judgement•Project Management Information System (PMIS)

PMP Prep - Integration Slide 53

DIRECT AND MANAGE PROJECTDIRECT AND MANAGE PROJECTEXECUTION-T&TEXECUTION-T&T

Page 50: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 50/590

  OUTPUTS• Deliverables

 Any unique & verifiable product, result or capability to perform a

service that is identified in the project management planning

documentation, and must be produced and provided to

complete the project

• Change Request

When issues are found while project work is being performed, change requestsare issued which may modify project policies and procedures, project scope,

project cost or budget, project schedule or quality. Other change requests cover needed preventive or corrective actions to forestall negative impacts later in theproject. Request for a change can be direct or indirect, externally or internallyinitiated, can be optional or legally/contractually mandated.

 PMP Prep - Integration Slide 54

DIRECT AND MANAGE PROJECT EXECUTION-DIRECT AND MANAGE PROJECT EXECUTION-OUTPUTOUTPUT

Page 51: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 51/590

OUTPUTS

Work Performance InformationInformation on status of project activities being performed to accomplish

the project work. Includes:

• Schedule progress showing status information

•Deliverables that have been completed and those not completed• Schedule activities that have started and those that have been

finished

• Extent to which quality standards are being met

• Costs authorized and incurred

• Estimates to complete the schedule activities that have started• Percent physically complete of the in-progress schedule activities

• Documented lessons learned posted to the lessons learned

knowledge base

• Resource utilization detail

PMP Prep - Integration Slide 55

DIRECT AND MANAGE PROJECT EXECUTION-DIRECT AND MANAGE PROJECT EXECUTION-OUTPUTOUTPUT

Page 52: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 52/590

Project Management updatesElements of the project management plan that may be updated include:

Requirements(Scope) management plan, Schedule management plan, costmanagement plan, human resource management plan, quality managementplan, communications management plan, risk management plan, procurementsmanagement plan, project baselines

Project Document updatesProject documents that may be updated include but are not limited to:

• Requirements documents

• Projects log (issues, assumptions)

• Risk register and• Stakeholder register 

PMP Prep - Integration Slide 56

DIRECT AND MANAGE PROJECT EXECUTION-DIRECT AND MANAGE PROJECT EXECUTION-OUTPUTOUTPUT

Page 53: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 53/590

INTEGRATION PROCESSESINTEGRATION PROCESSES

PMP Prep – Integration Slide 57

PROCESSES BY PROCESS GROUPInitiating Planning Executing Monitoring

andcontrolling

Closing

4.1 Develop

Project

Charter

4.2 DevelopProject

ManagementPlan

4.3 Directand Manage

ProjectExecution

4.4 Monitor and Control

Project work

4.6 CloseProject

4.5Integrated

ChangeControl

MONITOR AND CONTROLMONITOR AND CONTROL

Page 54: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 54/590

WHAT HAPPENS DURING MONITOR & CONTROL PROJECT WORK?

•  Monitor project processes associated with initiating, planning, executing &closing.Corrective or preventive actions are taken to control the project performance.Monitoring is an aspect of project management performed throughout theproject.

•  This process is concerned with:• Comparing actual project performance against the project management plan• Assessing performance to determine whether any corrective or preventiveactions are indicated, then recommending those actions as necessary

• Analyzing, tracking, and monitoring project risks to make sure the risks areidentified, their status is reported, and that appropriate risk response plans

are being executed• Maintaining an accurate, timely information base concerning the project’sproduct (s) and their associated documentation through project completion

• Providing information to support status reporting, progress measurement, andforecasting

• Providing forecasts to update current cost and current schedule information• Monitoring implementation of approved changes when and as they occur 

-

MONITOR AND CONTROLMONITOR AND CONTROL

PROJECT WORK PROJECT WORK 

MONITOR AND CONTROLMONITOR AND CONTROL

Page 55: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 55/590

MONITOR AND CONTROLMONITOR AND CONTROL

PROJECT WORK PROJECT WORK  

PMP Prep – Integration Slide 59

Inputs

• Project management plan• performance reports•Enterprise environmentalfactors• Organizational process assets

Outputs• Change Requests• Project Management Plan updates• Project documents updates

TOOLS &Techniques

•Expert judgement

MONITOR AND CONTROL PROJECT

Page 56: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 56/590

INPUTS •  Project Management Plan

• Performance reports

•Enterprise environmental factors

•Organizational process assets

PMP Prep - Integration Slide 60

MONITOR AND CONTROL PROJECTMONITOR AND CONTROL PROJECTWORK - INPUTSWORK - INPUTS

MONITOR AND CONTROL PROJECTMONITOR AND CONTROL PROJECT

Page 57: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 57/590

TOOLS & TECHNIQUES 

• Expert Judgment

PMP Prep - Integration Slide 61

MONITOR AND CONTROL PROJECTMONITOR AND CONTROL PROJECTWORK – T&TWORK – T&T

O O CO O O C O

Page 58: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 58/590

  OUTPUTSChange requests

• Recommended Corrective Actions

Corrective actions are recommended to bring expected future project

performance into conformance with the project management plan

• Recommended Preventive Actions Preventive actions are recommended to reduce the probability of 

negative consequences associated with project risk

• Recommended Defect Repair 

Some defects, which are found during the quality inspection and audit

process, are recommended for correction

Project Management plan updates

Project Documents updates

PMP Prep - Integration Slide 62

MONITOR AND CONTROL PROJECT WORK MONITOR AND CONTROL PROJECT WORK - OUTPUTS- OUTPUTS

Page 59: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 59/590

INTEGRATION PROCESSESINTEGRATION PROCESSES

PMP Prep – Integration Slide 63

PROCESSES BY PROCESS GROUPInitiating Planning Executing Monitoring

andcontrolling

Closing

4.1 Develop

Project

Charter

4.2 DevelopProject

ManagementPlan

4.3 Directand Manage

ProjectExecution

4.4 Monitorand Control

Project work

4.6 CloseProject

4.5 IntegratedChangeControl

INTEGRATED CHANGEINTEGRATED CHANGE

Page 60: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 60/590

WHAT HAPPENS DURING INTEGRATED CHANGE CONTROL? •  During the entire project, this process ensures that the project

management plan, project scope statement, and other deliverablesmust be maintained by carefully and continuously managingchanges, either by rejecting changes or by approving changes so thatthose approved changes are incorporated into a revised baseline.

•  ICC process includes the following:• Identify if a change needs to occur or has occurred• Influence the factors that circumvent ICC so that only approved

changes are implemented• Review, approve & then manage change requests• Review and approve all recommended corrective and preventativeactions

• Control & update scope, cost, budget, schedule & qualityrequirements, based on approved changes, by coordinating acrossentire project, i.e. a schedule change may affect risk

PMP Prep - Integration Slide 64

INTEGRATED CHANGEINTEGRATED CHANGECONTROLCONTROL

INTEGRATED CHANGEINTEGRATED CHANGE

Page 61: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 61/590

 • Document impact of requested changes• Validate defect repairs• Control project quality (in a coordinated fashion)•  Some configuration management activities included here are:

• Configuration Identification -product details (to the level needed) are

defined, verified & labeled; changes are managed & accountabilityis maintained

• Configuration Status Accounting -capturing, storing & accessingconfiguration information

• Configuration Verification & Auditing -compare performance &.functional requirements defined in the configuration documentation

with reality• Large organizations have Change Control Boards (CCB) to authorize

changes (their roles & responsibilities should be clearly documentedhere)

PMP Prep – Integration Slide 65

INTEGRATED CHANGEINTEGRATED CHANGECONTROLCONTROL

INTEGRATED CHANGEINTEGRATED CHANGE

Page 62: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 62/590

INTEGRATED CHANGEINTEGRATED CHANGECONTROLCONTROL 

PMP Prep – Integration Slide 66

Inputs• Project management plan• Requested changes•Work performance information• Recommended preventive actions• Recommended corrective actions• Recommended defect repair • Deliverables

Outputs•  Approved change requests• Rejected change requests• Project management plan (updates)• Project scope statement (updates)

• Requested changes• Approved preventive actions• Approved corrective actions• Approved defect repair • Validated defect repair • Deliverables

TOOLS &Techniques• Project management

methodology• Project management

Information system• Expert judgement

INTEGRATED CHANGEINTEGRATED CHANGE

Page 63: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 63/590

• Project Management Plan

• Requested Changes Work Performance Information

• Recommended Preventive Actions

• Recommended Corrective Actions

• Recommended Defect Repair 

•Deliverables

•  Change Approved change Req. Implemented

• Request Project Mgmt. plan updated Change

• Scope statement updated Request

PMP Prep - Integration Slide 67

INTEGRATED CHANGEINTEGRATED CHANGE

CONTROL-T&TCONTROL-T&T

23Differen

tProcess

IntegratedChangeControl

(Monitoring &Controlling

)

Direct &ManageProject

Execution

(Executing)

INTEGRATED CHANGEINTEGRATED CHANGE

Page 64: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 64/590

TOOLS & TECHNIQUES

 • Project Management Methodology 

It defines a process that aids a project management team inimplementing ICC for the project

• Project Management Information System (PMIS)

• Expert Judgment

PMP Prep - Integration Slide 68

INTEGRATED CHANGEINTEGRATED CHANGE

CONTROL-T&TCONTROL-T&T

INTEGRATED CHANGE CONTROLINTEGRATED CHANGE CONTROL

Page 65: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 65/590

OUTPUTS

 Approved Change Requests

Rejected Change Requests

Project Management Plan (Updates)

Project Scope Statement (Updates)

Approved Corrective Actions

Approved Preventive Actions

Approved Defect Repair 

Validated Defect Repair 

Deliverables

PMP Prep - Integration Slide 69

INTEGRATED CHANGE CONTROL-INTEGRATED CHANGE CONTROL-

OUTPUTOUTPUT

Page 66: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 66/590

INTEGRATION PROCESSESINTEGRATION PROCESSES

PMP Prep – Integration Slide 70

PROCESSES BY PROCESS GROUPInitiating Planning Executing Monitoring

andcontrolling

Closing

4.1 Develop

Project

Charter

4.3 DevelopProject

ManagementPlan

4.4 Directand Manage

ProjectExecution

4.5 Monitorand Control

Project work

4.7 CloseProject

4.2 DevelopPreliminary

Project ScopeStatement

4.6Integrated

ChangeControl

Page 67: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 67/590

  WHAT HAPPENS DURING PROJECT CLOSURE?

• Finalize all activities completed across all process groups to formallyclose the project or project phase

• Transfer completed or cancelled project as appropriate

• Establish procedures to coordinate activities needed to verify anddocument the project deliverables, to coordinate and interact toformalize acceptance of those deliverables by the customer or sponsor 

• Investigate and document the reasons for actions taken if a project isterminated before completion

CLOSE PROJECTCLOSE PROJECT

Page 68: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 68/590

PROCEDURES TO PERFORM CLOSURE ACTIVITIES

Administrative Closure Procedures • integrated activities needed to collect project records• analyze project success or failure• gather lessons learned• archive project information for future use by organization

Contract Closure Procedures (from Procurement)• closing all contracts• product verification (confirm if all work is completed correctly and

satisfactorily)• Administrative closure (update & archive contract records)

PMP Prep - Integration Slide 72

CLOSE PROJECTCLOSE PROJECT

Page 69: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 69/590

CLOSE PROJECTCLOSE PROJECT 

PMP Prep – Integration Slide 73

Inputs

• Project management plan• Contract documentation• Enterprise environmental factors• Organizational process assets• Work performance information• Deliverables

  Outputs

•  Administrative closure

procedure• Contract closure procedure• Final product, service or result• Organizational process assets

(updates)

Tools &Techniques• Project management

methodology• Project management

Information system• Expert judgement

Page 70: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 70/590

INPUTS

• Project Management Plan

• Contract DocumentationIncludes contract itself, as well as changes to the contract andother documentation (such as the technical approach, product

description, acceptance criteria)

• Enterprise Environmental Factors e.g. governmentregulations

•Organizational Process Assets e.g. formal sign off forms

• Work Performance Information e.g. all invoices from procurement

• Deliverables

PMP Prep - Integration Slide 74

CLOSE PROJECTCLOSE PROJECT

Page 71: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 71/590

TOOLS & TECHNIQUES

• Project Management Methodology

• Project Management Information System (PMIS)

• Expert Judgment

PMP Prep - Integration Slide 75

CLOSE PROJECT-T&TCLOSE PROJECT-T&T

CLOSE PROJECT -CLOSE PROJECT -

Page 72: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 72/590

OUTPUTS

• Administrative Closure Procedure

• Contract Closure Procedure

• Final Product, Service, or ResultFormal acceptance/handover of the final product, service or result

Receipt of formal statement that contract terms have been met

PMP Prep - Integration Slide 76

CLOSE PROJECT CLOSE PROJECT OUTPUTSOUTPUTS

CLOSE PROJECT -CLOSE PROJECT -

Page 73: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 73/590

• Organizational Process Assets (updates)• Formal Acceptance Documentation

  Formal confirmation from customer/sponsor that requirements &

specifications of product, service or result have been met

• Project Files

  Documentation resulting from the project’s activities 

• Project Closer Documents

  Formal documentation indicating completion of project &

transfer of completed project deliverables to others, such as

an operations group

• Historical Information

  Historical information & lesson learned information are

transferred to the lessons learned knowledge base for use by

future projects

PMP Prep – Integration Slide 77

CLOSE PROJECT CLOSE PROJECT OUTPUTSOUTPUTS

S Q S O

Page 74: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 74/590

Question

Which of the following describes configuration management?

 A. it ensures that the description of a project’s product is correct &complete

B. a set of tools, techniques, methodologies, resources & proceduresused to manage products

C. the set of procedures developed to ensure that the project designcriteria are met

D. a mechanism to record budget & schedule variances

PMP Prep - Integration Slide 78

SAMPLE EXAM QUESTIONSAMPLE EXAM QUESTION

SAMPLE EXAM QUESTION

Page 75: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 75/590

B is correct.

Configuration Management System -It's a collection of formal documentedprocedures used to apply technical and administrative direction and surveillanceto: identify and document the functional and physical characteristics of a

product, result, service, or component; control any changes to suchcharacteristics; record and report each change and its implementation status;and support the audit of the products, results or components to verifyconformance to requirements. –

See PMBOK, p.354.

In other words -Procedures to manage (mostly control change)characteristics of something (like a procedure document, user guide)

PMP Prep - Integration Slide 79

SAMPLE EXAM QUESTIONSAMPLE EXAM QUESTION

SAMPLE EXAM QUESTION

Page 76: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 76/590

Question

Project A had an initial investment of $4 million, out of which $2 millionhas already been spent.

 A new Project B needs $1.5 million to complete and will meet the sameobjectives as Project A.

Which project should you select? You can only pick one.

PMP Prep - Integration Slide 80

SAMPLE EXAM QUESTIONSAMPLE EXAM QUESTION

S Q S OSAMPLE EXAM QUESTION

Page 77: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 77/590

Answer 

Choose Project B.

Project A has already spent $2 million (sunk cost). To complete, it needs $2million more out of $4 million total.Project B needs $1.5 million to complete, which is less that the $2 millionneeded to complete Project A.

Therefore, selecting Project B is better because $l.5M is less than $2M.

PMP Prep - Integration Slide 81

SAMPLE EXAM QUESTIONSAMPLE EXAM QUESTION

SAMPLE EXAM QUESTIONSAMPLE EXAM QUESTION

Page 78: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 78/590

Question

Three projects are being considered: Project A has a NPV of $5 millionProject B has a NPV of $3 million Project C has a NPV of $2 million

What is the opportunity cost if Project A is selected?

 A -$5 millionB -$3 millionC -$2 millionD -$0

PMP Prep - Integration Slide 82

SAMPLE EXAM QUESTIONSAMPLE EXAM QUESTION

SAMPLE EXAM QUESTIONSAMPLE EXAM QUESTION

Page 79: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 79/590

Answer 

B - $3 million.

Opportunity cost is the cost of giving up the next best option.

If you choose Project A, you loose the opportunity to make Project B'spotential profit (NPV), which is $3 million.

PMP Prep - Integration Slide 83

SAMPLE EXAM QUESTIONSAMPLE EXAM QUESTION

Q ti ?Q ti ?

Page 80: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 80/590

Questions?Questions?

PMP Prep - Integration Slide 84

Page 81: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 81/590

  This page is Left Blank intentionally

 

Page 82: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 82/590

  This page is Left Blank intentionally

 

Page 83: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 83/590

  This page is Left Blank intentionally

 

Page 84: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 84/590

DAY 1

 

PMP Prep – Scope Slide 1

DAY 2

  CHAPTER 5

PROJECT SCOPE MANAGEMENT

AGENDAAGENDA

Page 85: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 85/590

AGENDAAGENDA 

Day 1PMP Exam Prep IntroductionProject Management Framework 

*Project Life Cycle & OrganisationProject Management Processes

Project INTEGRATION Management

  DAY 2 Project SCOPE ManagementProject TIME ManagementProject COST ManagementProject QUALITY Management  DAY 3Project COMMUNICATION Management

Project HUMAN RESOURCE ManagementProject RISK Management

Project PROCUREMENT ManagementDAY 4

Professional & Social ResponsibilityREVISION & QUIZ

PROJECT SCOPEPROJECT SCOPE

Page 86: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 86/590

JJMANAGEMENTMANAGEMENT

What does the scope knowledge areado?

• It includes the processes required to ensure  that the project

includes all  the work required and only the work required tocomplete the project successfully.

• Managing the project scope is primarily concerned with definingand controlling what is and is not included in the project.

•Project Scope Management defines and controls all the of workincluded and not included in the plan.

• It Makes sure that every one agrees with the scope.

PROJECT SCOPEPROJECT SCOPE

Page 87: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 87/590

JJMANAGEMENTMANAGEMENT

Project Scope Management includes the following processes:

• Collect Requirements

• Define Scope

• Create WBS• Verify Scope

• Control Scope

PMP Prep – Scope Slide 3

PROJECT SCOPEPROJECT SCOPE

Page 88: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 88/590

JJMANAGEMENTMANAGEMENT

In the project context, the term scope can refer to: Product Scope 

- Features & functions that characterize a product, service or result,and/or 

Project Scope - Work that needs to be accomplished to deliver a product, service or 

result with the specified features and functions.

The processes used to manage project scope, as well as the supportingtools and techniques, vary by application area and are usually defined aspart of the project life cycle.

Scope baseline includes 3 things:- Approved Detailed Project Scope statement

- Associated work breakdown structure- WBS dictionary 

PMP Prep – Scope Slide 4

SCOPE PROCESSESSCOPE PROCESSES

Page 89: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 89/590

SCOPE PROCESSESSCOPE PROCESSES

SCOPE PROCESS DEFINITIONS 

5. 1 Collect Requirements- Collect Requirements is the process of defining and

documentingstakeholders’ needs to meet the project objectives.

- The project’s success is directly influenced by the care taken in

capturing and managing project and product requirements.- Requirements include the quantified and documented needs andexpectations of the sponsor, customer, and other stakeholders.

- the requirements need to be elicited, analyzed, and recorded inenough detail to be measured once project execution begins.

- Collecting requirements is defining and managing customer 

expectations.- Requirements become the foundation of the WBS.- Cost, schedule, and quality planning are all built upon these

requirements.- The development of requirements begins with an analysis of the

information contained in the project charter and stakeholder register.

  –

SCOPE PROCESSESSCOPE PROCESSES

Page 90: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 90/590

SCOPE PROCESSESSCOPE PROCESSES

5.2 Define Scope• It is the process of developing a detailed description of the project and

product.

5.3 Create WBS• Subdivide major project deliverables into smaller, more

manageable components

5.4 Verify Scope• Formal acceptance of completed project deliverables, i.e. a signed

document

5.5 Control Scope• Control changes to the project scope

 

PMP Prep – Scope Slide 6

SCOPE PROCESSESSCOPE PROCESSES

Page 91: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 91/590

SCOPE PROCESSESSCOPE PROCESSES

Process by process group

Planning Monitoring andControlling

5.1Collect

Requirements

5.4Verify Scope

5.2

Define Scope

5.5

Control Scope

5.3

Create WBS

Page 92: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 92/590

COLLECT REQUIREMENTSCOLLECT REQUIREMENTS

Page 93: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 93/590

COLLECT REQUIREMENTSCOLLECT REQUIREMENTS

 PMP Prep – Scope Slide 9

INPUTS• Project charter

• Stakeholder register

OUTPUTS• Requirements

documentation•  Requirements

Management Plan•  Requirements

traceability matrix

TOOLS &TECHNIQUES

• Interviews• Focus groups

• Facilitated workshops• Group creativity techniques

• Group decision makingtechniques

• Questionnaires and surveys• observations• Prototypes

COLLECT REQUIREMENTSCOLLECT REQUIREMENTS

Page 94: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 94/590

- INPUTS- INPUTSINPUTS

1. Project Charter 

2. Stakeholder Register   It is used to identify stakeholders that can provide information ondetailed project and product requirements (Stakeholder register isdescribed in Sec 10.1)

COLLECT REQUIREMENTSCOLLECT REQUIREMENTS

Page 95: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 95/590

-T&T-T&T

COLLECT REQUIREMENTSCOLLECT REQUIREMENTS

Page 96: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 96/590

– T&T– T&TTOOLS & TECHNIQUES 

1. Interviews

2. Focus groups Focus groups bring together prequalified stakeholders and subjectmatter experts to learn about their expectations and attitudes about a

proposed product, service, or result. A trained moderator guides thegroup through an interactive discussion, designed to be moreconversational than one-on-one interview.

3. Facilitated Workshops 

4. Group Creativity Techniques- Brainstorming

- Nominal group technique- The Delhi Technique- Idea/mind mapping- Affinity diagram

PMP Prep – Scope Slide 12

COLLECT REQUIREMENTSCOLLECT REQUIREMENTS

Page 97: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 97/590

– T&T– T&T

TOOLS & TECHNIQUES 5. Group Decision Making Techniques - Unanimity- Majority- Plurality (the largest block in a group)- Dictatorship

  6. Questionnaires and Surveys

7. Observations

8. Prototypes

  Prototyping is a method of obtaining early feedback onrequirements

by providing a working model of the expected product beforeactually building it.

COLLECT REQUIREMENTS -COLLECT REQUIREMENTS -

Page 98: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 98/590

OUTPUTSOUTPUTS

OUTPUTS

• Requirements Documentation  (Read Sec. 5.1.3.1, page 109)

• Requirements Management Plan(Read Sec. 5.1.3.2, page 110)

PMP Prep – Scope Slide 14

COLLECT REQUIREMENTS -COLLECT REQUIREMENTS -

Page 99: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 99/590

OUTPUTSOUTPUTSOUTPUTS

• Requirements Traceability Matrix  Traceability matrix is a table that links requirements to their origin and

traces them throughout the project life cycle. It provides a structure for managing changes to the product scope. The process includes, but notlimited to tracing:

- Requirements to business needs, opportunities, goals, and objectives;- Requirements to project objectives;- Requirements to project scope/WBS deliverables;- Requirements to product design;

- Requirements to product development;- Requirements to test strategy and test scenarios; and- High-level requirements to more detailed requirements

PMP Prep – Scope Slide 15

SCOPE PROCESSESSCOPE PROCESSES

Page 100: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 100/590

SCOPE PROCESSESSCOPE PROCESSES

Process by process group

PMP Prep – Scope Slide 16

Planning Monitoring andControlling

5.1

Collect Requirements 

5.4

Verify Scope

5.2

Define Scope 

5.5

Control Scope

5.3

Create WBS

DEFINE SCOPEDEFINE SCOPE

Page 101: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 101/590

DEFINE SCOPEDEFINE SCOPE

What happens in Define Scope?

•  Define Scope is the process of developing a detailed description of the project and product.

• The preparation of a detailed project scope statement is critical toproject success and builds upon the major deliverables, assumptions,

andconstraints that are documented during project initiation.

• During planning, the project scope is defined and described withgreater specificity as more information about the project is known.

• Existing risks, assumptions and constraints are analyzed for completeness

DEFINE SCOPEDEFINE SCOPE

Page 102: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 102/590

DEFINE SCOPEDEFINE SCOPE

 PMP Prep – Scope Slide 18

INPUTS•  Project charter • Requirements documentation• Organizational process assets

OUTPUTS

• Project scope statement• Project document updates

TOOLS & TECHNIQUES

• Expert judgement• Product analysis

• Alternative identification• Facilitated workshops

DEFINE SCOPE - INPUTSDEFINE SCOPE - INPUTS

Page 103: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 103/590

DEFINE SCOPE - INPUTSDEFINE SCOPE - INPUTS

INPUTS• Project Charter 

High-level project description and product characteristics 

• Requirements documentation  Described in Sec. 5.1.3.1 

• Organizational process Assets

PMP Prep – Scope Slide 19

DEFINE SCOPE – T & TDEFINE SCOPE – T & T

Page 104: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 104/590

DEFINE SCOPE – T & TDEFINE SCOPE – T & T

TOOLS & TECHNIQUESExpert Judgment

• Expert judgment is often used to analyze the information needed todevelop the project scope statement.

Product Analysis

• Differs by application area (translates product objectives into tangibledeliverables and requirements).

• Includes techniques such as product breakdown, systems analysis,systems engineering , value engineering, and value analysis.

PMP Prep – Scope Slide 20

DEFINE SCOPE– T&TDEFINE SCOPE– T&T

Page 105: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 105/590

DEFINE SCOPE– T&TDEFINE SCOPE T&T

Alternatives Identification

• Technique used to generate different approaches to execute &perform project work.

• Common techniques are brainstorming (group shares impulseideas & gains ideas from each other) & lateral thinking (consider several points of view)

Facilitated Workshops 

• Read Section 5.1.2.3

PMP Prep – Scope Slide 21

DEFINE SCOPE - OUTPUTSDEFINE SCOPE - OUTPUTS

Page 106: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 106/590

DEFINE SCOPE - OUTPUTSDEFINE SCOPE OUTPUTS 

1) Project Scope Statement

• It describes in detail the project deliverables & work required to createthe deliverables.

• It defines what work will be performed & what work is excluded –determines how well the PM team can control the overall project scope –in turn can determine how well the PM team can plan, manage & controlexecution of the project

• It includes, either directly or by reference to other documents (must readpage 115 of PMBOK thoroughly)

 

PMP Prep – Scope Slide 22

Page 107: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 107/590

DEFINE SCOPE - OUTPUTSDEFINE SCOPE - OUTPUTS 

The detailed project scope statement includes, either directly, or by reference toother documents, the following:

• Product scope description

• Progressively elaborated characteristics of project's product, service or resultdescribed in the project charter and requirements documentation.

• Product acceptance criteria 

Process and criteria for accepting completed products

• Project deliverables

Product or service of the project, and supplementary results, such asproject management reports & documentation

PMP Prep – Scope Slide 23

DEFINE SCOPE - OUTPUTSDEFINE SCOPE - OUTPUTS

Page 108: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 108/590

DEFINE SCOPE OUTPUTSDEFINE SCOPE OUTPUTS

• Project exclusionsGenerally identifies what is excluded as from the project (must stateexplicitly)

• Project constraints - Restriction or limitation of the project scope that limit team’s option e.g.

pre-defined budget; imposed dates or schedule milestones etc.- Projects performed under contract generally have contractual provisions

• Project assumptions- Factors, that for planning purposes, are considered true, real or certain. -- Generally involve a degree of risk

PMP Prep – Scope Slide 24

DEFINE SCOPE - OUTPUTSDEFINE SCOPE - OUTPUTS

Page 109: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 109/590

DEFINE SCOPE OUTPUTSDEFINE SCOPE OUTPUTS

2) Project Document Updates

  Documents that may be updated

include, but not limited to :

- Stakeholder register - Requirements documentation

- Requirements traceability matrix 

PMP Prep – Scope Slide 25

DEFINE SCOPE - OUTPUTSDEFINE SCOPE - OUTPUTS

Page 110: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 110/590

DEFINE SCOPE OUTPUTSDEFINE SCOPE OUTPUTS

Question

My company is researching on “clean energy on cleantransportation”. As the Project Manager, which of thefollowing is a valid assumption?

A. Project scope is to develop an alternative energy source or electric drive for Off-road vehicles.

B. Project has to be completed in 24 monthsC. Cost of the project is $ 17mD. Gas will become a scarce commodity after 20 years

PMP Prep – Scope Slide 26

DEFINE SCOPE - OUTPUTSDEFINE SCOPE - OUTPUTS

Page 111: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 111/590

DEFINE SCOPE OUTPUTSDEFINE SCOPE OUTPUTS

Answer : D

 Assumptions are factors that are considered true, real or certain(PM needs to make assumptions at every stage of the project)

Constraints are limitations or restrictions. (given in Project Charter)

D is the only assumption; all the others are

constraints.

SCOPE PROCESSESSCOPE PROCESSES

Page 112: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 112/590

SCOPE PROCESSESSCOPE PROCESSES

Process by process group

PMP Prep – Scope Slide 28

Planning Monitoring andControlling

5.1

Collect Requirements 

5.4

Verify Scope

5.2

Define Scope

5.5

Control Scope

5.3

Create WBS

CREATE WBSCREATE WBS

Page 113: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 113/590

CREATE WBSCREATE WBS

WHAT'S A WORK BREAKDOWN STRUCTURE?

 • Deliverable-oriented hierarchy of decomposed work to be done bythe project team.

• Organizes & defines the total scope of the project.

 • Subdivides the project work into smaller, more manageable piecesof work.

(refer to figure 5-7 in page117 of PMBOK)

PMP Prep – Scope Slide 29

CREATE WBSCREATE WBS

Page 114: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 114/590

CREATE WBSCREATE WBS

PMP Prep – Scope Slide 30

INPUTS• Project scope statement

• Requirementsdocumentation

• Organizational processassets

OUTPUTS• WBS

• WBS dictionary• Scope baseline

• Project document updates 

TOOLS & TECHNIQUES• Decomposition

CREATE WBS - INPUTSCREATE WBS - INPUTS

Page 115: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 115/590

CREATE WBS INPUTSCREATE WBS INPUTS

INPUTS

• Project Scope Statement

• Requirements Documentation

• Organizational Process Assets

CREATE WBS – T&TCREATE WBS – T&T

Page 116: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 116/590

CREATE WBS T&TTOOLS & TECHNIQUES

Decomposition

• Decomposition is sub-division of project deliverables into smaller, moremanageable components. Decomposition involves the following activities:

• Decomposition may not be possible for a deliverable or sub-project thatwill be accomplished far into the future.

• PM team waits until the deliverable or sub-project is clarified so thedetails of WBS can be developed. This technique is called “ Rolling WavePlanning”.

(Read page 118)

PMP Prep – Scope Slide 32

CREATE WBS – DefinitionsCREATE WBS – Definitions

Page 117: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 117/590

• Work Package – a deliverable at lowest level of WBS with a groupof activities, which are used in Activity Definition as schedulabletasks (may be further decomposed)

• Planning package – Future deliverables or subprojects that can’tbe decomposed

PMP Prep – Scope Slide 33

CREATE WBSCREATE WBS

Page 118: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 118/590

CREATE WBS

  Decomposition process involves:

• Identifying the deliverables and related work

• Structuring and organizing the WBS

• Decomposing the upper WBS levels into lower level detailed

components.• Develop & Assign identification codes to each WBS component

(code of account)

• Verifying that the degree of decomposition of the work is

necessary and sufficient

PMP Prep – Scope Slide 34

APPROACHES TO DEVELOPAPPROACHES TO DEVELOP

SWBS

Page 119: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 119/590

WBSWBS

• Using guidelines: Some organizations, like the DOD,provide guidelines for preparing WBSs

• The analogy approach: It often helps to review WBSs of 

similar projects

• The top-down approach: Start with the largest items of theproject and keep breaking them down

• The bottoms-up approach: Start with the detailed tasksand roll them up

PMP Prep – Scope Slide 35

CREATE WBSCREATE WBS

Page 120: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 120/590

PMP Prep – Scope Slide 36

Sample Intranet WBS Organized by Product

SAMPLE INTRANET WBSSAMPLE INTRANET WBS

ORGANIZED BY PHASEORGANIZED BY PHASE

Page 121: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 121/590

ORGANIZED BY PHASEORGANIZED BY PHASE

PMP Prep – Scope Slide 37

CREATE WBSCREATE WBS

Page 122: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 122/590

Basic principles for creating a WBS:

 1. A unit of work should appear at only one place in the WBS.

2. The work content of a WBS item is the sum of the WBS items below it.

3. A WBS item is the responsibility of only one individual, even thoughmany people may be working on it.

4. The WBS must be consistent with the way in which work is actually going

to be performed; it should serve the project team first and other purposesonly if practical.

5. Project team members should be involved in developing the WBS toensure consistency and buy-in.

6. Each WBS item must be documented to ensure accurate understandingof the scope of work included and not included in that item.

7. The WBS must be a flexible tool to accommodate inevitable changeswhile properly maintaining control of the work content in the projectaccording to the scope statement.

PMP Prep – Scope Slide 38

CREATE WBS - DefinitionsCREATE WBS - Definitions

Page 123: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 123/590

Code of Accounts -Uniquely identifies each element (box)of the WBS

MS Project, Visio etc. can generate Code of Accounts.

Chart of Accounts -Coding structure used by the

performing organization to report financial information bycategory, i.e. labour or supplies. It's generally as given inGeneral Ledger.

Control Account -A management control point placed in a

WBS element where scope, cost & schedule can be tracked.Also used for planning when work packages are notplanned yet. Documented in a Control Account Plan.

CREATE WBS- OUTPUTSCREATE WBS- OUTPUTS

Page 124: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 124/590

OUTPUTS

Work Breakdown StructureThe WBS should not be confused with other break-down structure used topresent project information. Some of them used in other application/knowledge areas include:

• Organizational Breakdown Structure (OBS): depiction of project by

departments, units or teams

• Bill Of Material (BOM): tabulation of physical assemblies, subassemblies

and components

• Risk Breakdown Structure (RBS): depiction of identified project risks

arranged by risk category

• Resource Breakdown Structure (RBS): depiction of project resources bytype

PMP Prep – Scope Slide 40

CREATE WBS- OUTPUTSCREATE WBS- OUTPUTS

Page 125: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 125/590

WBS Dictionary

• Document that details each WBS component• It includes:

• Code of account identifier 

• a statement of work with defined deliverables• Responsible organization• List of schedule milestone

• It could include:

• Contract information• Quality requirements• Technical references• List of associated activities/interdependencies• Resources required• Cost estimate

CREATE WBS- OUTPUTSCREATE WBS- OUTPUTS

Page 126: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 126/590

 

Scope Baseline - The approved detailed “Project ScopeStatement” and its associated WBS & WBS Dictionary.

 

Project Document Updates

 

SCOPE PROCESSESSCOPE PROCESSES

Page 127: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 127/590

Process by process group

PMP Prep – Scope Slide 43

Planning Monitoring andControlling

5.1

Collect Requirements 

5.4

Verify Scope

5.2

Define Scope

5.5

Control Scope

5.3

Create WBS

VERIFY SCOPEVERIFY SCOPE

Page 128: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 128/590

HOW DO WE VERIFY SCOPE? 

•  Getting the stakeholders' formal acceptance of completed or updatedscope & deliverables, i.e. the WBS or the software you delivered

• If a project terminates early, project scope verification should be donenext to establish & document the level & extent of completion.

• Scope verification is concerned with acceptance of deliverables, Whilequality control is concerned with quality of deliverables

•  Quality control is generally performed before scope verification but canbe performed in parallel as well 

• It's unethical to ignore Scope Verification because it adds risk to meetingthe customer's needs (see PMP Code of Conduct)

PMP Prep – Scope Slide 44

VERIFY SCOPEVERIFY SCOPE

Page 129: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 129/590

 PMP Prep – Scope Slide 45

INPUTS• Project scope

statement• WBS dictionary

• Project scopemanagement plan• Deliverables

OUTPUTS• Accepted

deliverables• Requested

changes

• Recommendedcorrectiveactions

TOOLS &TECHNIQUES

• Inspection

VERIFY SCOPE - INPUTSVERIFY SCOPE - INPUTS

Page 130: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 130/590

INPUTSProject Scope Statement -

WBS Dictionary  -

Project Scope Management Plan  -

Deliverables  - partially or fully completed & are an output of the Direct &Manage Project Execution

PMP Prep – Scope Slide 46

VERIFY SCOPE – T&TVERIFY SCOPE – T&T

Page 131: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 131/590

TOOLS & TECHNIQUES

Inspection

• Measuring, examining, and verifying to determine whether work or 

deliverables meet requirements and product acceptance criteria.

• Inspections are also called reviews, product reviews, audits andwalkthroughs.

VERIFY SCOPE - OUTPUTSVERIFY SCOPE - OUTPUTS

Page 132: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 132/590

OUTPUTSAccepted Deliverables

• Documents those completed deliverables that have beenaccepted.

• Documents those completed deliverables that have not beenaccepted, along with the reasons for non-acceptance.

• Includes supporting documentation received from customer or sponsor and acknowledging stakeholders acceptance of theproject’s deliverables.

Requested Changes -

Recommended Corrective Actions –

PMP Prep – Scope Slide 48

SCOPE PROCESSESSCOPE PROCESSES

Page 133: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 133/590

Process by process group

PMP Prep – Scope Slide 49

Planning Monitoring andControlling

5.1

Collect Requirements 

5.4

Verify Scope

5.2

Define Scope

5.5

Control Scope

5.3

Create WBS

CONTROL SCOPECONTROL SCOPE

Page 134: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 134/590

WHAT HAPPENS DURING CONTROL SCOPE ?(Change is inevitable)

• Influencing the factor that create project scope changes

• Controlling the impact of those changes

• Assures all requested changes and recommended corrective actionsare processed through the project Integrated Change Controlprocess

• Project scope control is used to manage the actual changes whenthey occur& integrated with other control processes

Note: Uncontrolled changes are often referred to as project scopecreep

PMP Prep – Scope Slide 50

CONTROL SCOPECONTROL SCOPE

Page 135: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 135/590

 

PMP Prep – Scope Slide 51

INPUTS• Project scope statement

• Work breakdown structure• WBS dictionary• Project scope

management plan• Performance reports

• Approved change requests• Work performance

information

OUTPUTS• Project scope statement

(updates)• WBS (updates)

• WBS dictionary (updates)• Scope baseline (updates)

• Requested changes•Recommended corrective action• Organizational process assets

(updates)• Project management Plan

(updates)

TOOLS & TECHNIQUES

• Change control system• Variance analysis

• Replanning• Configurationmanagement

system

CONTROL SCOPE - INPUTSCONTROL SCOPE - INPUTS

Page 136: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 136/590

INPUTSProject Scope Statement -

Work Breakdown Structure  -

WBS Directory  -

Project Scope Management Plan  -

Performance Reports  -• Performance reports provide information on project work performance,

such as interim deliverables that have been completed

Approved Change Requests -

Work Performance Information –

PMP Prep – Scope Slide 52

CONTROL SCOPE – T&TCONTROL SCOPE – T&T

Page 137: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 137/590

TOOLS & TECHNIQUES

Change Control System

Documented in project scope management plan, defines the procedures bywhich the project scope or product scope can be changed.

Variance Analysis

• Project performance measurements are used to assess the magnitude of variation. Important aspects of scope control include determining cause of variance to scope baseline and deciding whether corrective action is

required.• Time & cost areas (to come) use a mathematical technique called earned

value analysis.

PMP Prep – Scope Slide 53

CONTROL SCOPE – T&TCONTROL SCOPE – T&T

Page 138: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 138/590

Re-planning –

• Approved change requests can require modifications to the:

• WBS• WBS dictionary

• Project Scope Statement• Project Scope Management Plan• Other components of Project Management Plan

• Configuration Management System

Provides procedures for the status of the deliverables, and assures thatrequested changes to the project scope & product scope are thoroughlyconsidered & documented before being processed through ICC process.

PMP Pre – Sco e Slide 54

CONTROL SCOPE -CONTROL SCOPE -OUTPUTSOUTPUTS

Page 139: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 139/590

OUTPUTSOUTPUTSOUTPUTS

Project Scope Statement (updates) -

Work Breakdown Structure (updates)  -

WBS Dictionary (Updates)  -

Scope Baseline (Updates) -

Requested Changes  -

Recommended Corrective Actions  -

Organizational Process Assets (Updates)  -

Project Management Plan (Updates)  -

PMP Prep – Scope Slide 55

SAMPLE EXAM QUESTIONSAMPLE EXAM QUESTION

Page 140: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 140/590

Question

You're the project manager for an advertising campaign. Thestakeholders, including the client, approved your completed WBS.Later, after some of the artwork has been printed, the client wantsto add a registered trademark symbol, which will cost a

considerable amount of money. The client says that your company'ssalesperson, prior to signoff on the WBS, promised this featurewould be included. Who should pay for the change?

 A. Your company managing the project

B. Both the client and your company should pay part of the costC. The change should not be implemented

D. The client

PMP Prep – Scope Slide 56

SAMPLE EXAM QUESTIONSAMPLE EXAM QUESTION

Page 141: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 141/590

Answer - D

Because signing of the WBS constitutes an agreement betweenyour company managing the project and the client, the client shouldpay. Work that is not specified in the WBS is not part of the projectscope.

In reality, this is sometimes not the case. Companies will frequentlydo work that is outside the project scope in order to ensure thegoodwill of the client.

 Also note that if the WBS had been done with a milestonedeliverable for signing of the artwork before printing (scopeverification), this could have been avoided.

PMP Prep – Scope Slide 57

Questions?Questions?

Page 142: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 142/590

PMP Prep – Scope Slide 58

Page 143: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 143/590

  This page is Left Blank intentionally

 

Page 144: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 144/590

 PMP Prep – Time Slide 1 

DAY 3

CHAPTER 6

PROJECT TIMEMANAGEMENT

AGENDAAGENDA

Page 145: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 145/590

 

Day 1  DAY 4  PMP Exam Prep Introduction Project QUALITY  Management

Project Management Framework  Project RISK  Management

*Introduction Project HUMANRESOURCE Management

*Project Life Cycle & OrganisationProject Management Processes

  DAY 2  DAY 5  Project INTEGRATION Management ProjectPROCUREMENT Management

Project SCOPE Management Professional & SocialResponsibility

DAY 3 DAY 6  Project TIME Management REVISION & QUIZ

Project COST Management

PROJECT TIMEPROJECT TIMEMANAGEMENTMANAGEMENT

Page 146: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 146/590

MANAGEMENTMANAGEMENT  WHAT DOES THE TIME MANAGEMENT AREA ATTAIN?

 

• Manages the project schedule to ensure timely

completion of the project

• Utilizes the Schedule Management Plan from the

Develop Project Management Plan process

PMP Prep – Time Slide 2

TIME PROCESSESTIME PROCESSES

Page 147: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 147/590

DEFINITIONS : TIME PROCESSES 

6.1 Define Activities 

• Identifying the specific actions to be performed to produce project deliverables

(at the lowest level in the WBS, which is called the work package).

6.2 Sequence Activities

• Identifying & documenting relationships among the project activities.

6.3 Estimate Activity Resources 

• Estimate the type & quantities of material, people, equipment, or supplies

required to perform each activity.

PMP Prep – Time Slide 3

TIME PROCESSESTIME PROCESSES

Page 148: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 148/590

6.4 Estimate Activity Durations • Estimate the number of work periods needed to complete individual activities

with estimated resources.

6.5 Develop Schedule

• Analyze activity sequences, durations, resource requirements, and scheduleconstraints to create the project schedule.(The five processes above could be viewed as a single process in small projects)

6.6 Control Schedule• Monitor the status of the project to update project progress and managing

changes to the schedule baseline.

PMP Prep – Time Slide 4

TIME PROCESSESTIME PROCESSES

Page 149: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 149/590

PMP Prep – Time Slide 5

PLANNING MONITORING & CONTROLLING

6.1 Define Activities 6.6 Control Schedule

6.2 Sequence Activities

6.3 Estimate Activity Resources

6.4 Estimate Activity Durations

6.5 Develop Schedule

DEFINE ACTIVITIESDEFINE ACTIVITIESWHAT HAPPENS IN DEFINE ACTIVITIES?

Page 150: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 150/590

  WHAT HAPPENS IN DEFINE ACTIVITIES?

•  Identifies the specific actions to be performed to produce the project deliverables. TheCreate WBS process identifies the deliverables at the lowest level in the WorkBreakdown Structure (WBS), the work package.

•  Decompose the work packages into smaller components called activities that representthe work necessary to complete the work package.

•  Differentiate between a work package and an activity?• A work package is a deliverable as a result of work•  An activity is an action that produces a deliverable alone or together with other 

activities

• Activities provide a basis for estimating, scheduling, executing, and

monitoring & controlling the project work.

• Implicit in this process is defining and planning the schedule activities such that theproject objectives will be met.

PMP Prep – Time Slide 6

DEFINE ACTIVITIESDEFINE ACTIVITIES

Page 151: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 151/590

 

PMP Prep – Time Slide 7

• Scope baseline• Enterprise environmental factors• Organizational process assets

OUTPUTS• Activity list

• Activity

attributes• Milestone list

TOOLS & TECHNIQUES• Decomposition• Rolling wave planning

• Templates• Expert judgement

DEFINE ACTIVITIES -DEFINE ACTIVITIES -INPUTSINPUTS

Page 152: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 152/590

INPUTSU S

• Scope Baseline

• Enterprise Environmental Factors

• Organizational Process Assets  - Existing formal and informal activity planning-related policies, procedures,

and guidelines, such as scheduling methodology, that are considered indeveloping the activity definitions, and

- Lessons-learned knowledge base containing historical informationregarding activities lists used by previous similar projects.

 

PMP Prep – Time Slide 8

DEFINE ACTIVITIES – T&TDEFINE ACTIVITIES – T&T

Page 153: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 153/590

  TOOLS & TECHNIQUES 

Decomposition

• Subdivides work packages into smaller, more manageable components calledactivities. Activities represent the effort needed to complete a work package.

 Rolling Wave Planning 

• Rolling wave planning is a form of progressive elaboration planning, where

• Work in near term is planned in detail• Work in future is planned at a higher level of WBS

  Therefore, work can exist at various levels of detail depending on where it is in the project life cycle.For example, during early strategic planning, when information is less defined, work

packages may be decomposed to the milestone level. As more is known about theupcoming events in the near term it can be decomposed into activities.

PMP Prep – Time Slide 9

DEFINE ACTIVITIES– T&TDEFINE ACTIVITIES– T&T

Page 154: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 154/590

Templates•  A standard activity list or a portion of an activity from a

previous project is often used as a template for a new

project.

• Templates are also used to identify typical schedulemilestones.

Expert Judgment• Experts - experienced and skilled in developing detailed

project scope statements, the WBS, and project schedules

can provide expertise in defining activities

PMP Prep – Time Slide 10

DEFINE ACTIVITIES -DEFINE ACTIVITIES -OUTPUTSOUTPUTS

OUTPUTS

Page 155: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 155/590

OU U SOUTPUTS

Activity List

•The activity list is a comprehensive list of all schedule activities required on the project.•The activity list includes the activity identifier and a scope of work description for eachactivity in sufficient detail to ensure that project team members understand what work isrequired to be completed.

Activity Attributes• Multiple components associated with each activity that evolve over time.

During the initial stages of the project they include:- Activity ID, WBS ID, and Activity Name

  and when completed may include- Activity codes, activity description- Predecessor activities, successor activities, logical relationships- Leads & lags

- Resource requirements- Imposed dates, constraints & assumptions- Person or company responsible for executing the work- Geographic area or place where the work has to be performed- Activity type such as level of effort, discrete effort, and apportioned effort

PMP Prep – Time Slide 11

DEFINE ACTIVITIES -DEFINE ACTIVITIES -OUTPUTSOUTPUTS

OUTPUTS

Page 156: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 156/590

OUTPUTS

Activity Attributes (Contd.)• Activity attributes are used for schedule development and for 

selecting, ordering, and sorting the planned schedule activities invarious ways within reports. The number of attributes varies byapplication area.

Milestone List• A milestone is a significant point or event in the project.

Its type that could be either: • Mandatory (required by contract or law)• Optional (based upon project requirements or historicalinformation)

PMP Prep – Time Slide 12

TIME PROCESSESTIME PROCESSES

Page 157: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 157/590

PMP Prep – Time Slide 13

PLANNING MONITORING & CONTROLLING

6.1 Define Activities 6.6 Control Schedule

6.2 Sequence Activities

6.3 Estimate Activity Resources

6.4 Estimate Activity Durations

6.5 Develop Schedule

SEQUENCE ACTIVITIESSEQUENCE ACTIVITIES

Page 158: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 158/590

WHAT HAPPENS IN SEQUENCE ACTIVITIES?

• Identifies & documents logical relationship among the projectactivities.

 • Every activity and milestone except the first and last are connected to

at least one predecessor and one successor.

• Defines precedence relationships and leads & lags to supportdevelopment of a realistic & achievable project schedule.

• Sequencing can be performed by using project management software or byusing manual or automated techniques.

PMP Prep – Time Slide 14

SEQUENCE ACTIVITIESSEQUENCE ACTIVITIES

Page 159: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 159/590

 

PMP Prep – Time Slide 15

INPUTS• Activity list

• Activity attributes

• Milestone list• Project scope statement• Organizational process assets 

OUTPUTS• Project schedule

network diagrams

• Project documentupdates

TOOLS & TECHNIQUES• Precedence diagramming

method (PDM)• Dependency determination

• Applying leads & lags• Schedule network

templates

SEQUENCE ACTIVITIESSEQUENCE ACTIVITIES

Page 160: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 160/590

 

INPUTS

 

• Activity List

• Activity Attributes

• Milestone List

•  Project Scope Statement

• Organizational Process Assets

PMP Prep-Time Slide 16

SEQUENCE ACTIVITIESSEQUENCE ACTIVITIESTools &Techniques

Page 161: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 161/590

  Tools &Techniques

1) Precedence Diagramming Method (PDM)• Method of constructing a Project schedule network diagram that uses

• Rectangles or boxes (called nodes) to represent activities• Arrows show dependencies

This method is also called activity-on-node (AON)

 

PMP Prep – Time Slide 17

SEQUENCE ACTIVITIES -SEQUENCE ACTIVITIES -T&TT&T

Types of Predecessor

Page 162: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 162/590

Types of Predecessor 

Finish-to-Start  –Successor activity can not start until the predecessor activityis completed

Activity A Predecessor  Activity B Successor 

e.g. Trouser can not be stitched till the linen is cut.

Finish-to-Finish – Completion of successor activity depends uponcompletion of predecessor activity. Hence two tasks must finish at the sametime

e.g. – ‘Wiring Inspection’ can’t finish until ‘House Wiring” is completed.

 

Predecessor Activity A

Successor Activity B

PMP Prep – Time Slide 18

SEQUENCE ACTIVITIES -SEQUENCE ACTIVITIES -T&TT&T

Page 163: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 163/590

Start-to-Start -Start of successor activity depends upon start of thepredecessor activity

e.g. start canvassing only after candidature is announced by the ElectionCommission.

Predecessor Activity ASuccessor Activity B

Start-to-Finish  – Completion of successor activity depends upon start of thepredecessor activity

e.g. – To pass PMP exams, you have to start reading PMBOK

Predecessor Activity ASuccessor Activity B

PMP Prep – Time Slide 19

SEQUENCE ACTIVITIES -SEQUENCE ACTIVITIES -T&TT&T

Page 164: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 164/590

Read just for knowledge

 Arrow Diagramming Method (ADM) ADM uses arrows to represent activities & connects to nodes to show their dependencies

• Also called activity-on-arrow (AOA)

• Used in teaching ‘Schedule Network Theory’

• Uses only finish-to-start dependencies and is not as

prevalent as PDM

• Can require "dummy" relationships (dummy activities)

(broken lines) that have zero value for duration

• Uses more than one time estimate.

PMP Prep – Time Slide 20

SEQUENCE ACTIVITIES -SEQUENCE ACTIVITIES -T&TT&T

Page 165: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 165/590

2) Dependency Determination 

Three types of dependencies are used

• Mandatory dependencies (sometimes called hard logic)

• Inherent in the nature of the work e.g. before basement 1st floor 

• Discretionary dependencies (preferred, preferential or soft logic)• Sometimes required in unusual aspect of the project

• PM team decides based on knowledge, best practices & exp.

• External dependencies 

Relationship between project & non-project activities, i.e. dependent on

delivery of computers before the software development can start

PMP Prep – Time Slide 21

SEQUENCE ACTIVITIES -SEQUENCE ACTIVITIES -T&TT&T

Page 166: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 166/590

 

3) Applying Leads & Lags

  A lead allows the following activity start before the previousone

is finished.

• Start painting the bedroom before all the rooms are constructed.• Lead is overlap between activities

A lag allows a delay in the next activity.

• Staff joined but training to commence after 15 days (a lag of 15 days)• Lag is waiting time between activities.

SEQUENCE ACTIVITIES -SEQUENCE ACTIVITIES -T&TT&T

Page 167: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 167/590

4) Schedule Network Templates 

• Standardized project schedule network diagram templates can be

used to expedite the preparation of networks

• Portions of a project schedule network diagram are often referred as‘sub network’ or ‘fragment network’

• Useful for identical deliverables, as in different floors of a multi-storied

building

PMP Pre – Time Slide 23

SEQUENCE ACTIVITIES -SEQUENCE ACTIVITIES -OUTPUTSOUTPUTS

Page 168: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 168/590

OUTPUTS 1) Project Schedule Network Diagrams • Schematic displays of project schedule activities and logical relationships

among dependencies

• A short narrative describing the approach used to sequence the activities. Anyunusual activity sequences within the network are fully described in the

narrative (during schedule updates, you'll need to remember)

2) Project Document UpdatesProject documents that may be updated include, but not limited to:

  Activity lists

Activity attributes

Risk register 

PMP Prep – Time Slide 24

TIME PROCESSESTIME PROCESSES

Page 169: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 169/590

PMP Prep – Time Slide 25

PLANNING MONITORING & CONTROLLING

6.1 Define Activities 6.6 Control Schedule

6.2 Sequence Activities

6.3 Estimate Activity Resources

6.4 Estimate Activity Durations

6.5 Develop Schedule

ESTIMATE ACTIVITY ESTIMATE ACTIVITY RESOURCESRESOURCES

Page 170: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 170/590

WHAT IS IN “ESTIMATE ACTIVITY RESOURCES”? 

•  Estimate Activity Resources is the process of estimating the type and

quantities of material, people, equipment, or supplies required to

perform each activity. 

• For example. a construction project team will need to be familiar with

local building codes. Such knowledge is often readily available from local

sellers. However, if the local labor pool lacks experience with unusual or 

specialized construction techniques, the additional cost for a consultant might

be the most effective way to secure knowledge of the local building codes.

PMP Prep – Time Slide 26

ESTIMATE ACTIVITY ESTIMATE ACTIVITY RESOURCESRESOURCES

Page 171: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 171/590

 

PMP Prep – Time Slide 27

INPUTS

• Activity list• Activity attributes

• Resource calendars• Enterprise environmental factors

• Organizational process assets

OUTPUTS• Activity resource

requirements

• Resource breakdownstructure

• Project document updates

TOOLS & TECHNIQUES• Expert judgment

• Alternative analysis• Published estimating data

• Bottom-up estimating• Project management software

ESTIMATE ACTIVITY RESOURCESESTIMATE ACTIVITY RESOURCES

- INPUTS- INPUTSINPUTS

Page 172: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 172/590

INPUTS• Activity List

• Activity Attributes

• Resource Calendars

The composite resource calendar includes the availability,

capabilities, and skills of human resources 

- Which resources (people, equipment, material) are potentially available.- Estimate resource types, i.e. senior vs. junior engineer at different phase of 

the project (e.g. during early phases of an Engineering Design Project-Junior 

engineer is fine but at later stages experienced engineers will be required).

- Consider geographical location & when they will be available.

 

• Enterprise Environmental Factors

• Organizational Process Assets

PMP Prep – Time Slide 28

ESTIMATE ACTIVITY RESOURCESESTIMATE ACTIVITY RESOURCES – T&T– T&T

Page 173: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 173/590

Expert Judgment Experts access the resource-related inputs in planning & estimating

Alternatives AnalysisMany schedule activities have alternative methods of accomplishment. Theyinclude:• Using various levels of resource capability or skills

• Using different sizes or types of machines or tools, e.g.automated or  manual

• Make-or-buy decisions regarding the resources (whether tooutside contracting is cheaper than hiring)

PMP Prep – Time Slide 29

ESTIMATE ACTIVITY ESTIMATE ACTIVITY 

RESOURCESRESOURCES – T&T– T&T

Page 174: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 174/590

 Published Estimating Data

Some companies publish production rate and unit cost of resources for different trades, material & equipment within countries, various info

published by PMI for its members

Bottom-up Estimating

• For accuracy, the work within schedule activity is decomposed into moredetail• Each activity is then totalled into overall project

• Schedule activities may or may not have dependencies betweenthem that can affect the application and use of resources.

Project Management Software Sophisticated software help plan, organize and manage resource pools &

develop resource estimates.

PMP Prep-Time Slide 30

 ESTIMATE ACTIVITY RESOURCESESTIMATE ACTIVITY RESOURCES

- OUTPUTS- OUTPUTS

Page 175: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 175/590

Activity Resource Requirements 

• Identification & description of types & quantities of 

resources required for each schedule activity

• Added up to determine estimated resources for eachwork package

• Schedule activity forms basis of estimate & determines

type, availability and quantity of resources used

• Schedule Development process determines when

resources are needed

PMP Prep – Time Slide 31

 ESTIMATE ACTIVITY RESOURCESESTIMATE ACTIVITY RESOURCES

- OUTPUTS- OUTPUTS

Page 176: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 176/590

Resource Breakdown Structure (RBS)

Is hierarchical structure of identified resources by

(i) Resource category, and (ii) Resource type

Project Document Updates

•  Activity list,

• Activity attributes,

• Resource calendars.

PMP Prep – Time Slide 32

TIME PROCESSESTIME PROCESSES

Page 177: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 177/590

PMP Prep – Time Slide 33

PLANNING MONITORING & CONTROLLING

6.1 Define Activities 6.6 Control Schedule

6.2 Sequence Activities

6.3 Estimate Activity Resources

6.4 Estimate Activity Durations 

6.5 Develop Schedule

ESTIMATE ACTIVITY DURATIONSESTIMATE ACTIVITY DURATIONS

WHAT IS THERE IN ESTIMATE ACTIVITY DURATION?

Page 178: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 178/590

WHAT IS THERE IN ESTIMATE ACTIVITY DURATION?

The process of approximating the number of work periods needed to complete individualactivities with estimated resources. The process uses information on:

• Activity scope of work

• Required resource types, estimated resource quantities &

resource calendars.

The duration estimate is:

• progressively elaborated• the process considers the quality & availability of the input data

• All data and assumption that support duration estimating are documented for each

estimate of activity duration.

Most project management software for scheduling will handle this situation by using aproject calendar and alternative work-period resource calendars that are usually identifiedby resources that require specific work-periods. In addition to the sequencing logic, theactivities will be performed according to the project calendar and appropriate resourcecalendars.

PMP Prep – Time Slide 34

ESTIMATE ACTIVITY DURATIONSESTIMATE ACTIVITY DURATIONS

Page 179: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 179/590

 

PMP Prep – Time Slide 35

INPUTS• Activity list

• Activity attributes• Activity resource requirements

• Resource calendars• Project scope statement

• Enterprise environmental factors• Organizational process assets

 

OUTPUTS• Activity duration estimates

• Project document updates

TOOLS & TECHNIQUES• Expert judgment

• Analogous estimating• Parametric estimating• Three-point estimates

• Reserve analysis

ESTIMATE ACTIVITY DURATIONS - INPUTSESTIMATE ACTIVITY DURATIONS - INPUTS

INPUTS

Page 180: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 180/590

  INPUTS

Activity List

Activity Attributes

Activity Resource Requirements

Resource Calendars

Project Scope Statement

Enterprise Environmental Factors

Organizational Process Assets

PMP Prep – Time Slide 36

ESTIMATE ACTIVITY DURATIONS – T&TESTIMATE ACTIVITY DURATIONS – T&T

Expert Judgment

Page 181: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 181/590

Expert Judgment

Analogous Estimating

• An estimate that's based on the duration of previous, similar schedule activity

as the basis for estimating duration of a future schedule activity.

• It uses historical information & expert judgement.

• It is most reliable when the previous activities are similar in fact and not just in

appearance, and the project team members preparing the estimates have the

needed expertise (A form of a top-down estimate)

PMP Prep – Time Slide 37 

ESTIMATE ACTIVITY DURATIONS – T&TESTIMATE ACTIVITY DURATIONS – T&T

Parametric Estimating

Page 182: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 182/590

Estimates activity durations quantitatively by multiplying the quantity of work tobe performed by the productivity rate.Basically uses some measurable parameter that changes the same way as costdoes

Three – Point Estimates

The accuracy of the activity estimate can be improved by consideringestimation uncertainty and risk. This concept originated with theProgram Evaluation and Review Technique (PERT). PERT uses threeestimates to define an approximate range for an activity’s duration:

The three estimates are Optimistic, Pessimistic & Most Likely. PERT

analysis calculates an Expected activity duration using a weightedaverage of the these three estimates:

Weighted average = {Optimistic + (4* Most likely) + Pessimistic} / 6

PMP Prep – Time Slide 38 

ESTIMATE ACTIVITY DURATIONS – T&TESTIMATE ACTIVITY DURATIONS – T&T

Reserve Analysis (read 6 4 2 5 page 151)

Page 183: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 183/590

Reserve Analysis (read 6.4.2.5, page 151)

• Project teams can choose to incorporate additional time referred to as

contingency reserve or time reserves or buffers

• Can be applied to overall project schedule or at a point in the schedule asrecognition of project risk

• They are planned provisions to mitigate the impact of variance in cost or 

schedule (takes care of risk in cost & time)

PMP Prep – Time Slide 39 

ESTIMATE ACTIVITY DURATIONS – OUTPUTSESTIMATE ACTIVITY DURATIONS – OUTPUTS

OUTPUTS

Page 184: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 184/590

OU U S

Activity Duration Estimates

• Quantitative assessments of the likely number of work periods

required to complete a schedule activity

• Estimates should include some indication of the range of 

possible results, I.e. 2 weeks +/-2 days to indicate that schedule

activity will take at least eight days and no more than 12 days

(assume 5 day week)

 Project Document Updates 

PMP Prep – Time Slide 40 

TIME PROCESSESTIME PROCESSES

Page 185: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 185/590

PMP Prep – Time Slide 41

PLANNING MONITORING & CONTROLLING

6.1 Define Activities 6.6 Control Schedule

6.2 Sequence Activities

6.3 Estimate Activity Resources

6.4 Estimate Activity Durations

6.5 Develop Schedule 

DEVELOP SCHEDULEDEVELOP SCHEDULE

HOW DO YOU DEVELOP A SCHEDULE ?

Page 186: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 186/590

HOW DO YOU DEVELOP A SCHEDULE ?

• Develop Schedule is the process of analysing activity sequences, durations,resource requirements, and schedule constraints to create the project schedule.

•Determine planned start & finish dates for all project activities

• Schedule development is iterative (repeats in cycles) & continues throughoutthe project to modify duration & resource estimates as the:

• Work progresses• Project Management Plan changes• the nature of risk events evolves

• The schedule baseline (developed at the beginning of the project) is used totrack work progress and variance.

PMP Prep – Time Slide 42

DEVELOP SCHEDULEDEVELOP SCHEDULE

TOOLS & TECHNIQUES• Schedule network analysis

Page 187: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 187/590

 

PMP Prep – Time Slide 43

INPUTS• Activity list

• Activity attributes• Project schedule network

diagrams

• Activity resource requirements• Resource calendars• Activity duration estimates

• Project scope statement• Enterprise environmental factors

• Organizational process assets

OUTPUTS• Project schedule• Schedule baseline

• Schedule data• Project document updates

 Schedule network analysis• Critical path method

• Critical chain method• Resource levelling

• What-if scenario analysis• Applying leads and lags• Schedule compression

• Scheduling tool

DEVELOP SCHEDULE - INPUTSDEVELOP SCHEDULE - INPUTS

INPUTS 

Page 188: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 188/590

Activity List

Activity Attributes

Project Schedule Network Diagrams

Activity Resource Requirements

Resource Calendars

Activity Duration Estimates

Project Scope Statement

Enterprise Environmental Factors

Organizational Process Assets

• e.g. Scheduling methodology, and project calendar 

PMP Pre – Time Slide 44

 DEVELOP SCHEDULE – T&TDEVELOP SCHEDULE – T&T

TOOLS & TECHNIQUES

Page 189: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 189/590

  TOOLS & TECHNIQUES

 

1) Schedule Network Analysis• Generates the project schedule with early and late start and finish dates

using:• Critical path method• Critical chain method

• What-if analysis & resource levelling

• Schedule compression or analysis2) Critical Path Method (CPM ) – Read page 154-155

• Series (or path) of activities through the network diagram thatdetermines the soonest time a project can finish

• Calculates the theoretical early start and finish dates, and late start andfinish dates, for all activities without regard for any resource limitations, by

performing a forward and backward pass analysis through the schedulenetwork.• longest path through the network diagram

• they have either zero or negative total float.• Networks can have multiple near critical paths.

• the schedule activities on critical path are called critical activities

PMP Prep – Time Slide 45 

 DEVELOP SCHEDULE – T&TDEVELOP SCHEDULE – T&T

TOOLS & TECHNIQUES

Page 190: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 190/590

  TOOLS & TECHNIQUES

  3) Critical Chain Method (Read page 155)

• Critical chain is a schedule network analysis technique that modifies the

project schedule to account for limited resources.

• The critical chain method adds duration buffers that are non-work

schedule activities to manage uncertainty. One buffer, placed at the end of 

the critical chain, is known as the project buffer and protects the target

finish date from slippage along the critical chain.

 PMP Prep – Time Slide 46 

 DEVELOP SCHEDULE – T&TDEVELOP SCHEDULE – T&T

TOOLS & TECHNIQUES

Page 191: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 191/590

  TOOLS & TECHNIQUES

4) Resource Levelling •  After using critical path to analyse your schedule, you may need to

address:• Resource usage that needs to be kept at a constant level, e.g. a technician utilized for 

120 hours for one week is better utilized at 40 hours a week for 3 weeks• Activities that need to be performed to meet specified delivery dates

• to address the situation where shared or critical required resources are only available atcertain times and in limited quantities

• Resource levelling often results in: •  A longer project duration

• Allocating scarce resources to critical path activities• Using overtime or multiple shifts

• Methods to increase resource productivity like different technology or machines

• Can cause the original critical path to change• A cost increase, but staff cost may decrease if overtime is eliminated

• Produces a resource-limited or resource-constrained schedule• Reverse resource allocation scheduling is done from project end.

PMP Prep – Time Slide 47

 DEVELOP SCHEDULE – T&TDEVELOP SCHEDULE – T&T

TOOLS & TECHNIQUES

Page 192: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 192/590

  TOOLS & TECHNIQUES

5) What-If Scenario Analysis•  Creates a schedule model, then computes different scenarios (simulations) if X

happens; assess the feasibility of the project schedule under adverse conditions.• The most common technique is Monte Carlo Analysis (read Section 11.4.2.2)

6) Applying Leads and Lags 

7) Schedule Compression

• Shortens project schedule without changing the project scope to meet schedule

constraints, imposed dates, or other schedule objectives.

• Crashing –addition of more resources on the critical path to complete the projectearlier (generally increases cost).

• Fast tracking  - activities or phases that normally would be done in sequence areperformed in parallel; can require work to be performed without detailed info. & can

increase risk.8) Scheduling Tool•  Automated scheduling tools expedite the scheduling process by generating start and finishdates based on the inputs of activities, network diagrams, resources and activity durations. Ascheduling tool can be used in conjunction with other project mgmt. Software applications as

well as manual methods.

PMP Prep – Time Slide 48

DEVELOP SCHEDULE – T&TDEVELOP SCHEDULE – T&T 

Consider the following diagram of activities (time is given in days)

Page 193: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 193/590

Consider the following diagram of activities (time is given in days)

1. How many paths are on this network diagram?

2. How long is each path in days?

3. Which is the critical path?

4. What is the least amount of time needed to finish this project?

PMP Prep – Time Slide 49

DEVELOP SCHEDULE – T&TDEVELOP SCHEDULE – T&T

PERT (Problem)

Page 194: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 194/590

( ob e )

What's the expected time to complete an activity given these

times?

Optimistic = 15 min. Most Likely =30 min. Pessimistic = 60 min.

Weighted Average (Expected) Time using PERT calculations:{Optimistic + ( 4 x Most Likely) + Pessimistic} divided by 6 

 Answer: (15 + 120 + 60) /6 = 32.5 min

 

PMP Prep – Time Slide 50

DEVELOP SCHEDULE – T&TDEVELOP SCHEDULE – T&T

Page 195: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 195/590

 

PMP Prep – Time Slide 51

DEVELOP SCHEDULE – T&TDEVELOP SCHEDULE – T&T

Page 196: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 196/590

Schedule Exercise -Draw a network diagram based on this information toanswer these questions.

Task A can start immediately & is estimated at 3 weeks

Task B can start after Task A is completed & is estimated at 3 weeks

Task C can start after Task A is completed & is estimated at 6 weeks

Task D can start after Task B is completed & is estimated at 8 weeksTask E can start after Tasks C & 0 are finished & IS estimated at 4 weeks

1. How long is the critical path?

2. What's the float of Task C?_______ and Task B?

3, What's the total float (between all nodes) of the path with the longest float?

 

PMP Prep – Time Slide 52

DEVELOP SCHEDULE – T&TDEVELOP SCHEDULE – T&T

Page 197: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 197/590

PMP Prep – Time Slide 53

DEVELOP SCHEDULE – T&TDEVELOP SCHEDULE – T&T

More Exercise Questions

Page 198: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 198/590

More Exercise Questions

4. If Task C changes to 10 weeks, how will the schedule dates be affected?

5. Task F, which is estimated at 11 weeks, has been added to the project. Itmust be completed before Task E & after Task C. The customer is concerned

that this will add an additional 11 weeks to the elapsed time of the project. Howmany weeks will be added?

(Assume question 4 above didn't happen.)

PMP Prep – Time Slide 54

DEVELOP SCHEDULE – T&TDEVELOP SCHEDULE – T&T

Page 199: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 199/590

 

Exercise Answers 4 & 5

4. No effect . Task C is on a path with a 5 week total float so addinganother 4 weeks will still leave 1 week of total float on its path.

5. Task F is added to a path with a 5 week float. Adding this 11week activity will use up all 5 of the float weeks and delay theproject by an additional 6 weeks. The critical path will move to thebottom with a 6 week float on the top path.

PMP Prep – Time Slide 55

 DEVELOP SCHEDULE – OUTPUTSDEVELOP SCHEDULE – OUTPUTS

 OUTPUTS

Page 200: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 200/590

1) Project Schedule• Includes at least a planned start date & planned finish

date for each schedule activity.

• Project Schedule can be presented in summary form,

called master or milestone schedule, or presented in

detail.• More often presented graphically using following

formats:

• Project Schedule Network Diagrams (These diagrams

can be presented in the activity-on-node diagram

format or in a time-scaled schedule network diagram

format (see Figure 6-10, p.150), sometimes called a

logic bar chart.

PMP Prep – Time Slide 56

DEVELOP SCHEDULE – OUTPUTSDEVELOP SCHEDULE – OUTPUTS

Page 201: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 201/590

• Milestone Charts•  Bar chart with only scheduled start or completion dates of major 

deliverables and key external interfaces (see Fig. 6-14, p.158 top

milestone schedule)

• In milestone chart activities have zero duration

• Bar Charts• Gantt Charts with bars representing activities show activity start and end

dates & expected durations

• For control & management communication, more comprehensive

summary activity, (see Fig. 6-14, p.158 middle summary schedule)

sometime referred to as a hammock activity, is used between milestones

or across multiple interdependent work packages

 

PMP Prep – Time Slide 57

DEVELOP SCHEDULE – OUTPUTSDEVELOP SCHEDULE – OUTPUTS

• Project schedule network diagrams (see Fig. 6-7 and Fig. 6-14)

Page 202: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 202/590

2) Schedule Baseline

• Accepted & approved schedule

3) Schedule Data 

4) Project Document Updates

- Activity resource requirements

- Activity attributes

- Calendar - Risk register 

PMP Prep Time Slide 58

TIME PROCESSESTIME PROCESSES

Page 203: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 203/590

PMP Prep – Time Slide 59

PLANNING MONITORING & CONTROLLING

6.1 Define Activities 6.6 Control Schedule 

6.2 Sequence Activities

6.3 Estimate Activity Resources

6.4 Estimate Activity Durations

6.5 Develop Schedule

CONTROL SCHEDULECONTROL SCHEDULE 

Page 204: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 204/590

WHAT HAPPENS IN CONTROL SCHEDULE?

• Schedule control is concerned with:

• Determining the current status of the project schedule

• Influencing the factors that create schedule changes

• Determining that the project schedule has changed• Managing the actual changes as they occur 

Schedule Control is a portion of Integrated Change Control process

PMP Prep Time Slide 60

CONTROL SCHEDULECONTROL SCHEDULE

TOOLS & TECHNIQUESP f i

Page 205: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 205/590

 

PMP Prep Time Slide 61

INPUTS

• Project management plan• Project schedule

• Work performance information• Organizational process assets 

OUTPUTS

• Work performance measurements• Organizational process assets updates

• Change requests• Project management plan updates

• Project document updates

• Performance reviews

• Variance analysis• Project management software

• Resource levelling• What-if scenario analysis• Adjusting leads and lags• Schedule compression

• Scheduling tool

CONTROL SCHEDULE - INPUTSCONTROL SCHEDULE - INPUTS

Page 206: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 206/590

INPUTSProject Management Plan

• It describes how the schedule will be managed and controlled, for example:

• Format of your schedule; rules for use of MS Project

• How and how often is the schedule updated

• Rules for authorizing schedule changes• Mechanisms for detecting schedule changes

• How is time estimating done

• The schedule baseline is used to compare with actual results to determine if a

change, corrective action, or preventive action is necessary.

Project Schedule

Work Performance Information

Organizational Process Assets

 PMP Prep – Time Slide 62

CONTROL SCHEDULE – T&TCONTROL SCHEDULE – T&T

Page 207: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 207/590

Performance ReviewsPerformance reviews measure, compare, and analyse schedule performancesuch as actual start and finish dates, percent complete, and remaining durationfor work in progress.

If earned value mgmt.(EVM) is utilized the schedule variance (SV) and scheduleperformance index (SPI) are used to assess the magnitude of schedule

variations (read page 162)

Variance Analysis

• Compare target vs. actual/forecast start and finished dates provides useful

information for the detection of deviations and for the implementation of 

corrective actions in case of delays.

PMP Prep – Time Slide 63

CONTROL SCHEDULE – T&TCONTROL SCHEDULE – T&T

Page 208: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 208/590

Project Management SoftwareResource Leveling

What-If Scenario Analysis

Adjusting Leads and Lags

Schedule Compression

Scheduling Tool

PMP Prep – Time Slide 64

CONTROL SCHEDULE – OUTPUTSCONTROL SCHEDULE – OUTPUTS

Page 209: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 209/590

OUTPUTS

• Work Performance Measurements

• Organizational Process Assets Updates

• Change Requests• Project Management Plan Updates 

• Project Document Updates

PMP Prep – Time Slide 65

SAMPLE EXAM QUESTIONSAMPLE EXAM QUESTION

Question 1

Page 210: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 210/590

Mathematical analysis often produces a preliminary schedule that show peaksand valleys in the resource requirements. Resource levelling can take care of this and may result in all the following except:

 A. Increase project duration

B. Increase in productivity by using different technologies and/or machinery

C. Reduction in many project costs, but may not be human resource cost

D. Utilization of weekends, extended hours or multiple shifts

Answer 1

C is the correct answer. See PMBOK, p.147

PMP Prep – Time Slide 66

SAMPLE EXAM QUESTIONSAMPLE EXAM QUESTION

Question 2 TASK PrecedingActivity

Estimate inMonths

Page 211: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 211/590

What is the length of thecritical path?

 A. 12

B. 10

C. 11

D. 14

PMP Prep – Time Slide 67

Activity Months

Start - 0

 A Start 3

B A 4

C Start 2

E C 5

D Start 7

E D 1

END B 3

END E 4

SAMPLE EXAM QUESTIONSAMPLE EXAM QUESTION

Page 212: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 212/590

PMP Prep – Time Slide 68

SAMPLE EXAM QUESTIONSAMPLE EXAM QUESTION

 

Page 213: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 213/590

PMP Prep – Time Slide 69

Page 214: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 214/590

Questions?Questions?

Page 215: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 215/590

PMP Prep – Time Slide 71

 

DAY 1

DAY 

Page 216: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 216/590

 

PMP Prep – Cost Slide 1

3

  CHAPTER 7

  PROJECT COST MANAGEMENT

AGENDAAGENDA 

Day 1 DAY 4

Page 217: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 217/590

Day 1  DAY 4

  PMP Exam Prep Introduction Project QUALITY  Management

Project Management Framework  Project RISK  Management

*Introduction Project HUMANRESOURCE Management

*Project Life Cycle & OrganisationProject Management Processes

  DAY 2  DAY 5  Project INTEGRATION Management ProjectPROCUREMENT Management

Project SCOPE Management Professional & Social

Responsibility

DAY 3 DAY 6  Project TIME Management REVISION & QUIZ

Project COST Management

PROJECT COSTPROJECT COSTMANAGEMENTMANAGEMENT

WHAT DOES THE COST KNOWLEDGE AREA INCLUDE?

Page 218: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 218/590

WHAT DOES THE COST KNOWLEDGE AREA INCLUDE?

• Processes involved in estimating, budgeting, and controlling costsso that the project can be completed within the approved budget.

• Primarily concerned with resource costs of schedule activities.

• The work involved in performing the three processes of Project CostMgmt. is preceded by a planning effort of the project mgmt. team.This planning effort is the part of the Develop Project Mgmt. Plan

process, which produces a cost management plan that sets out theformat and establishes the criteria for planning, structuring,

estimating, budgeting, and controlling project costs.

PMP Prep – Cost Slide 2

PROJECT COSTPROJECT COSTMANAGEMENTMANAGEMENT

WHAT DOES THE COST KNOWLEDGE AREA INCLUDE?

Page 219: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 219/590

WHAT DOES THE COST KNOWLEDGE AREA INCLUDE?

• The cost management processes and their associated tools andtechniques are usually selected during the project life cycle

definition (read Sec. 2.1), and are documented in the cost mgmt.plan.

Life Cycle Costing• It is defined as the cost of using, maintaining & supporting the

product, service or result of the project, but it's not part of theproject's budget (will get many questions on life cycle costing).

• Uses the Cost Management Plan (which is a part of the ProjectManagement Plan)

PMP Prep – Cost Slide 3

PROJECT COSTPROJECT COSTMANAGEMENTMANAGEMENT

Types of Costs : Let us illustrate using an example: Seminar

Page 220: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 220/590

Types of Costs : Let us illustrate using an example: Seminar 

• Fixed- rent of the seminar room is a fixed cost

• Variable – cost of food to participants varies with number of participants

• Direct – hiring of PA system for the seminar 

• indirect – cost of electricity of the venue is shared by all the other users

PMP Prep – Cost Slide 4

 COST PROCESSESCOST PROCESSES

COST PROCESS DEFINITIONS

Page 221: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 221/590

7.1 Estimate Costs• Develop cost approximations of all monetary resources needed to

complete project activities.

7.2 Determine Budget

• Aggregating the estimated costs of individual activities or work packagesto establish an authorized cost baseline.

7.3 Control Costs• The process of monitoring the status of the project to update the project

budget and managing changes to the cost baseline.

In smaller projects, Cost Estimating & Cost Budgeting can be one single process

PMP Prep – Cost Slide 5

COST PROCESSESCOST PROCESSES

Processes by process

Page 222: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 222/590

groupPlanning Monitoring and

controlling

7.1

Estimate Costs

7.3

Control Costs

7.2

Determine Budget

ESTIMATE COSTSESTIMATE COSTS

HOW DO YOU ESTIMATE COSTS?

Page 223: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 223/590

Get a cost approximation of the monetary resources needed tocomplete each schedule activity

Resources should include:

• Labour & services

• Materials, equipment & facilities

• Information technology• Inflation, cost contingency reserves

• Cost estimates are generally expressed in units of currency (or 

hours)

• Possible causes of variations should be considered (risk)

• Accuracy should increase as project progresses• Some organizations have formally trained project cost estimators

PMP Prep – Cost Slide 7

ESTIMATE COSTSESTIMATE COSTS

Salient Features:

Page 224: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 224/590

• Cost estimating includes identifying and considering various

costing alternatives

• Cost estimates are expressed in units of currency

• Cost estimates are normally refined during the course of the

project. The accuracy of a project estimate will increase asthe project progresses through the project life cycle.

• A project in initial phase could have a rough order of 

magnitude (ROM) estimate in the range of -50 to +50%.

• Later in the project, as more info. Is known, estimates could

narrow to a range -10 to +10%.

PMP Prep – Cost Slide 8

ESTIMATE COSTSESTIMATE COSTS

TOOLS &TECHNIQUES

• Expert judgement

Page 225: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 225/590

 

PMP Prep – Cost Slide 9

INPUTSScope baseline

• Project schedule

• Human resource plan• Risk register  

• Enterprise environmentalfactors

• Organizational process assets

OUTPUTS• Activity cost

estimates•Basis of estimates

•Projectdocument

updates

pe judge e

• Analogous estimating

• Parametric estimating• Bottom-up estimating• Three-point estimates

• Reserve analysis• Cost of quality

• Project managementestimating software

• Vendor bid analysis

ESTIMATE COSTS -ESTIMATE COSTS -INPUTSINPUTS

INPUTS

Scope Baseline

Page 226: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 226/590

Scope Baseline• Scope statement• Work breakdown structure• WBS dictionary

Project Schedule The type and quantity of resources and the amount of time which those resources

are applied to complete the work of the project are major factors in determining theproject cost. Schedule activity resources and their respective durations are used askey inputs to this process.

Human Resource PlanThe following are necessary components for developing the project cost estimates • Project staffing attributes

• Personnel rates• Related rewards/recognition

PMP Prep – Cost Slide 10

ESTIMATE COSTS -ESTIMATE COSTS -INPUTSINPUTS

INPUTS

Risk Register

Page 227: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 227/590

Risk Register The risk register should be reviewed to consider risk mitigation costs

Enterprise Environmental FactorsThe cost estimating process considers• Marketplace conditions• Commercial databases

Organizational Process Assets• Cost estimating policies, procedures & guidelines• Cost estimating templates• Historical information• Project files

• Project team knowledge• Lesson learned

PMP Prep – Cost Slide 11

ESTIMATE COSTS – T&TESTIMATE COSTS – T&T

TOOLS & TECHNIQUES

Page 228: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 228/590

Expert Judgment

Analogous EstimatingUsing actual cost of previous, similar projects as the basis for costing

current project. This method is less costly than other techniques, but is lessaccurate. Most reliable when previous projects are similar.

PMP Prep – Cost Slide 12

ESTIMATE COSTS – T&TESTIMATE COSTS – T&T

Parametric Estimating

Page 229: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 229/590

Uses statistical relationship between historical data and other variables( e.g. required labour hours, square footage in construction etc.)

Bottom-up EstimatingEstimating the cost of individual work packages or schedule activities withthe lowest level of detail. This detailed cost is then summarized or "rolled

up" to higher levels for reporting and tracking purposes. More accurate than Analogous Estimating.

Three-Point EstimatesPERT uses three estimates to define an approximate range for an activity’scost as under:

 {Optimistic + (4 * Most Likely) + Pessimistic} / 6

PMP Prep – Cost Slide 13

ESTIMATE COSTS – T&TESTIMATE COSTS – T&TReserve Analysis• Cost estimate may include “Contingency Reserve” (or contingency allowances) to

account for cost uncertainty

Page 230: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 230/590

account for cost uncertainty.

• PM's discretion to deal with anticipated, but not certain events ("known

unknowns"). These events are part of the project scope and cost baselines.

• Contingency reserve may be a percentage of the estimated cost.

• A schedule reserve can be a zero duration activity.

Cost of QualityCan also be used to prepare the schedule activity cost estimate (see section 8.1.2.2in PMBOK)

PMP Prep – Cost Slide 14

Cost of Quality“Quality-Costs”

Cost of Good

Quality

Cost of 

Poor Quality

Appraisal

Costs

Prevention

Costs

InternalFailureCosts

ExternalFaliureCost

ESTIMATE COSTS – T&TESTIMATE COSTS – T&T

Page 231: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 231/590

Project Management Estimating SoftwareCost estimating software applications, computerized spreadsheets,simulation and statistical tools are becoming more widely acceptedto assist with cost estimating.

Vendor Bid Analysis Analyse vendor bids to determine price of individual products.

PMP Prep – Cost Slide 15

ESTIMATE COSTS -ESTIMATE COSTS -OUTPUTSOUTPUTS

Page 232: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 232/590

Activity Cost EstimatesQuantitative (numerical) assessment of the likely costs of theresources required to complete schedule activities. This includes,but not limited to, labour, materials, equipment, services, facilities,information technology and special categories such as an inflation

allowance or cost contingency reserve.

PMP Prep – Cost Slide 16

ESTIMATE COSTS -ESTIMATE COSTS -OUTPUTSOUTPUTS

Basis of Estimates- The amount and type of additional details supporting schedule

Page 233: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 233/590

activity cost estimate vary by application area.

- Supporting detail for activity cost estimate vary by application area.Supporting detail for activity cost may include:

• Documentation of the basis of the estimate,• Documentation of all assumptions made,

• Documentation of any known constraints,• Range of estimates {e.g.$ 10K (-10% / + 10%) or 

between $9K and $11K}• Indication of the confidence level of the final estimate

Project Document UpdatesProject documents that may be updated include, but are not limited to, therisk register.

PMP Prep – Cost Slide 17

COST PROCESSESCOST PROCESSES

Processes by process

Page 234: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 234/590

groupPlanning Monitoring and

controlling

7.1

Estimate Costs 

7.3

Control Costs

7.2

Determine Budget 

 DETERMINEDETERMINE BUDGETBUDGET

WHAT HAPPENS IN DETERMINE BUDGET?

Page 235: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 235/590

• Aggregating the estimated costs of individual schedule activities or workpackages to establish a total cost baseline for measuring performance.It establishes the Project's funding requirements.

• Remember that the project scope statement provides only the summarybudget.

 

PMP Prep – Cost Slide 19

 DETERMINEDETERMINE BUDGETBUDGET

TOOLS &TECHNIQUES

Page 236: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 236/590

 

PMP Prep – Cost Slide 20 

INPUTS• Activity cost estimates

• Basis of estimates• Scope baseline

• Project schedule

• Resource calendars• Contracts

• Organizational processassets

OUTPUTS• Cost Performance baseline

• Project fundingrequirements

• Project document updates 

Q• Cost aggregation• Reserve analysis• Expert judgment

• Historical relationship• Funding limit reconciliation

DETERMINEDETERMINE BUDGETBUDGET -- INPUTSINPUTS

INPUTS

Page 237: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 237/590

Activity cost estimates

Basis of estimates

Scope baseline

Project Schedule

Resource Calendars

Contracts

Organizational process assets

PMP Prep – Cost Slide 21

DETERMINEDETERMINE BUDGETBUDGET -- T&TT&T

TOOLS & TECHNIQUESCost Aggregation

Page 238: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 238/590

• Cost estimates of all activities in each work package are aggregated in accordancewith the WBS.

• Total all work packages for higher component levels of WBS,such as “control accounts” & get the entire project total expectedbudget by period.

 Reserve AnalysisEstablishes contingency reserves, such as the management contingencyreserve, that are allowance for “unknown unknowns” risks identified in riskregister. PM needs approval for using such reserves. They are not part of project cost baseline, but are included in the budget for the project.

• Review your reserves through the project to ensure you have the right amount• Contingency reserves (spare funds) allow for unplanned, but potentially required

changes that may result from identified risks (to cost baseline)• Management reserves account for "unknown unknowns":

a) Included in performing organization's management budgetb) Not included in project budget, cost baseline or earned value calculations

PMP Pre – Cost Slide 22

DETERMINEDETERMINE BUDGETBUDGET -- T&TT&T

Expert Judgement

Page 239: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 239/590

Historical Relationship

 Any historical relationships that result in parametric estimates or analogousestimates involve the use of project characteristics (parameters) to developmathematical models to predict total project costs. Such models can besimple (e.g., residential home construction is based on a certain cost per 

square foot of space) or complex (e.g., one model of software developmentcosting uses multiple separate adjustment factors, each of which hasnumerous points within it).

PMP Prep – Cost Slide 23

DETERMINEDETERMINE BUDGETBUDGET – T&T– T&T

Tools & Techniques 

Page 240: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 240/590

Funding Limit Reconciliation

• The expenditure of funds should be reconciled with any funding

limits on the commitment of funds for the project.

• A variance between funding limits and the planned expenditures

will sometimes necessitate the rescheduling of work to level out

the rate of expenditures. This can be accomplished by placing

imposed date constraints for work into the project schedule.

PMP Prep – Cost Slide 24

Page 241: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 241/590

DETERMINEDETERMINE BUDGET – OUTPUTSBUDGET – OUTPUTS

OUTPUTS 

Page 242: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 242/590

Project Funding Requirements • Get funding requirements, total & by period (e.g. annual or quarterly) and

derived from cost baseline, which can exceed (usually by a margin) toallow for either early progress or cost overruns

• Funding usually occurs in incremental amounts, not continuous, appears

as a step graph (see Figure 7-6, p.178)• Total required funds is cost baseline plus management contingency

reserve

Project Document Plan Updates 

• Risk register,• Cost estimates, and• Project schedule

PMP Prep – Cost Slide 26

COST PROCESSESCOST PROCESSES

Processes by process

Page 243: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 243/590

groupPlanning Monitoring and

controlling

7.1

Estimate Costs 

7.3

Control Costs

7.2

Determine Budget

CONTROL COSTSCONTROL COSTS

WHAT SHOULD YOU DO IN CONTROL COSTS? 

Page 244: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 244/590

• Influencing the factors that create changes to the cost baseline,• Ensure that all change requests are acted on in a timely manner,• Manage the actual changes when and as they occur,• Make sure that cost expenditures don't exceed authorized funding (by

period & in total) for the project,

• Monitor cost performance to isolate and understand variances fromapproved cost baselines,

• Monitor work performance against funds expended,• Prevent unapproved changes from being included in the reported cost or 

resource usage,• Inform appropriate stakeholders of approved changes and associated

cost, and• Act to bring expected cost overruns within acceptable limits

PMP Prep – Cost Slide 28

CONTROL COSTSCONTROL COSTS

TOOLS & TECHNIQUES• Earned value mgmt.

• Forecasting

Page 245: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 245/590

 

PMP Prep – Cost Slide 29

INPUTS• Project management plan

• Project funding requirements• Work performance information

• Organizational process assets

OUTPUTS• Work performance measurements

• Budget forecasts• Organizational process assets updates

• Change requests•

Project management plan updates• Project document updates

• To-complete performanceindex

• Performance reviews• Variance analysis

• Cost change control system• Project management software

CONTROL COSTS - INPUTSCONTROL COSTS - INPUTS

Page 246: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 246/590

 INPUTS• Project Management Plan

- Cost Performance Baseline- Cost Mgmt. Plan

 • Project Funding Requirements

• Work Performance Information

• Organizational Process Assets

 

PMP Prep – Cost Slide 30

CONTROL COSTS - T&TCONTROL COSTS - T&T

TOOLS & TECHNIQUESCost Change Control System

Page 247: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 247/590

Performance Measurement Analysis

• An important part of cost control is to determine:- Cause of variance- Magnitude of a variance

- Decide if variance requires corrective action• Performance measurement techniques (called EVT) help to assess the

magnitude of any variances that will invariably occur.• Earned Value Technique (EVT) compares the value of the budgeted cost

of work performed (earned) at the original allocated budget amount to both- the budgeted cost of work scheduled (planned)

- to the actual cost of work performed (actual)This technique is especially useful for cost control, resource management& production .

PMP Prep – Cost Slide 31

CONTROL COSTS - T&TCONTROL COSTS - T&TEarned Value Management

Page 248: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 248/590

• Earned value mgmt. (EVM) in its various forms is a commonlyused method of performance measurements.

• It integrates project scope, cost, and schedule measures to help theproject mgmt. team assess and measure project performance and

progress.

• It is a project mgmt. technique that requires the formation of an integratedbaseline against which performance can be measured for the duration of the project.

• The principles of EVM can be applied to all projects, in any industry.

PMP Prep – Cost Slide 32

CONTROL COSTS - T&TCONTROL COSTS - T&TEarned Value Management (Contd.)

Page 249: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 249/590

• EVM) develops and monitors three key dimensions for each workpackage and control account:

- Planned Value (PV): budgeted cost for the work scheduled (inplanned time) to be completed

- Earned Value (EV): budgeted amount for work actuallycompleted

 - Actual Cost (AC): actual money spent in finishing the work

(actual cost)

PMP Prep – Cost Slide 33

CONTROL COSTS - T&TCONTROL COSTS - T&T

For example,

Page 250: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 250/590

You've hired a man to paint your house. It should take 3 months & you'llpay him $2,700 ($900/mo.). Paint is estimated at $3,600. After, one month,he's completed 20% of the work, but used 40% of the paint, therefore the:

PV = {( $2,700 + $3,600) / 3 } = $2,100

EV = 20% of $6,300 = $1,260

 AC = $900 + 40% of $3,600 = $ 900 + $1,440 = $2,340

PMP Prep – Cost Slide 34

CONTROL COSTS - T&TCONTROL COSTS - T&T

EV= 1,260 PV= 2,100 AC=2,340

(S Fi 7 9 183)

Page 251: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 251/590

(See Figure 7-9, p.183)

Cost Variance (CV) (sometimes called burn rate)= EV - AC= $1,260 -$2,340 = -$1,080 (over budget)CV%=CV/EV (many a time asked in exam)

Schedule Variance (SV) = EV-PV=$1,260 -$2,100 = -$840 (behind schedule)SV%=SV/PV (many a time asked in exam)

PMP Prep – Cost Slide 35

CONTROL COSTS - T&TCONTROL COSTS - T&TEV= 1,260 PV= 2,100 AC=2,340

C t P f I d (CPI) C t ffi i ti ( t t d l i )

Page 252: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 252/590

Cost Performance Index (CPI) -Cost efficiency ratio (cost trend analysis)CPI = EV / AC = $1,260/ $2,340 = 0.54

CPI < 1 -over budget

CPI> 1 -under budget

This is the ratio of what you expected to spend for the work you've earned(done) to what you really spent for it.

Schedule Performance Index (SPI) -Schedule efficiency ratio (schedule

trend)

SPI = EV / PV = $1,260/ $2,100 = 0.6

SPI < 1 -behind scheduleSPI > 1 ahead of schedule This is the ratio of what you planned on doing

to what you really did.

PMP Prep – Cost Slide 36

CONTROL COSTS - T&TCONTROL COSTS - T&T

Page 253: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 253/590

PMP Prep – Cost Slide 37

CONTROL COSTS - T&TCONTROL COSTS - T&T

Forecasting: Predicts or estimates future values of Estimate to

Complete (ETC) and Estimate at Completion (EAC) 

Page 254: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 254/590

The earned value technique parameters are:

Budget At Completion (BAC) : total of all PV's (project's total costbaseline) = PVc (also called Cumulative Planned Value)

Project Cost Variance (CV) - After project is complete, difference

between budget at completion (total project budget) & actualamount spent

CV = BAC- AC 

Variance at Completion (VAC) - Before project is complete,difference between budget at completion (total project budget) &

estimate at completion (now that project is underway)VAC = BAC –EAC

PMP Prep – Cost Slide 38

CONTROL COSTS - T&TCONTROL COSTS - T&TEstimate to Complete (ETC) - Expected cost to finish all theremaining work

Page 255: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 255/590

ETC based on new estimate  – Revised (New) estimate for the workremaining (uses standard estimating techniques) because originalestimate was flawed, e.g. in a project installing the latest version of Primavera on 500 computers, the team though initially had expectedcurrent hardware would be okay, found that 20% of the computers requireupgrading; thus a revised new estimate.

ETC based on atypical variances –PM team expectations are thatsimilar variances will not occur in future.

  ETC = BAC-EV

ETC based on typical variances – This approach is used when

current variances are seen as typical of future variances (is expectedto occur in future as well).  ETC = (BAC -EV)/ CPI (factors in CPI for trend)

PMP Prep – Cost Slide 39

CONTROL COSTS - T&TCONTROL COSTS - T&TEstimate at Completion (EAC) - Most likely total cost of the project(or activity) based on performance to date (often called latest

revised estimate)

Page 256: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 256/590

revised estimate)

EAC using a new estimate - Actual costs to date plus newestimate for the remaining work. Used when original estimate wasflawed or no longer relevant.

EAC = AC + ETC (doesn't rely on original budget BAC)

EAC using remaining budget - Similar variances not expected tooccur in future (atypical)

EAC =AC + BAC -EV

EAC using CPI - Similar variances are expected to occur (istypical)

EAC =AC +(BAC-EV)/CPI

CONTROL COSTS - T&TCONTROL COSTS - T&TTo-complete Performance Index (TCPI) –

The to complete performance index (TCPI) is the calculated

Page 257: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 257/590

The to-complete performance index (TCPI) is the calculatedprojection of cost performance that must be achieved on theremaining work to meet a specified management goal, such as theBAC or the EAC. If it becomes obvious that the BAC is no longer viable, the project manager develops a forecasted estimate atcompletion (EAC). Once approved, the EAC effectively supersedesthe BAC as the cost performance goal.Equation for the TCPI based on the BAC:

TCPI = (BAC-EV) / (BAC-AC)

The TCPI is conceptually displayed in Fig 7-10. The equation for theTCPI is shown in the lower left as the work remaining (defined as

the BAC minus EV) divided by the funds remaining (which can beeither the BAC minus the AC, or the EAC minus AC).

PMP Prep – Cost Slide 41

CONTROL COSTS - T&TCONTROL COSTS - T&TTo-complete Performance Index(TCPI) – Contd.

If the cumulative CPI falls below the baseline plan (as shown in Fig 7 6) all

Page 258: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 258/590

If the cumulative CPI falls below the baseline plan (as shown in Fig.7-6), allfuture work of the project will need to immediately be performed in therange of the TCPI (BAC) (as reflected in the top line of Fig.7-6) to staywithin the authorized BAC. Whether this level of performance is achievableis a judgment call based on a number of considerations, including risks,schedule, and technical performance.

Once the mgmt. acknowledges that the BAC is no longer attainable, theproject manager will prepare a new estimate at completion (EAC) for thework, and once approved, the project will work to the new EAC value. Thislevel of performance is displayed as the TCPI (EAC) line. The equation for the TCPI based on the EAC: 

TCPI = (BAC - EV) / (EAC – AC) 

PMP Prep – Cost Slide 42

CONTROL COSTS - T&TCONTROL COSTS - T&T

Performance ReviewsCompare cost performance over time, schedule activities or work packagesoverrunning & under running budget (planned value) and estimated funds

Page 259: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 259/590

overrunning & under running budget (planned value), and estimated fundsneeded to complete work in progress.

If EVM is being used, the following information is determined:

• Variance analysis -Compares actual to planned or expected

cost and schedule variances are the most frequently analyzed.

• Trend analysis - Examines performance over time to determine if 

performance is improving or deteriorating. Graphical analysis techniques

are valuable for understanding performance to date and for comparison to

future performance goals in the form of BAC versus EAC and completion

dates.

• Earned value performance – EVM compares the baseline plan to actual

schedule and cost performance.

PMP Prep – Cost Slide 43

CONTROL COSTS - T&TCONTROL COSTS - T&T

Variance Analysis 

• Cost performance measurements (CV CPI) are used to assess the

Page 260: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 260/590

• Cost performance measurements (CV,CPI) are used to assess the

magnitude of variation to the original cost baseline.

• Important aspects of project cost control include determining the

cause and degree of variance relative to the cost performance

baseline (section 7.2.3.1) and deciding whether corrective or 

preventive action is required.

•The % range of acceptable variances will tend to decrease as more

work is accomplished. The larger % variances allowed at the start of 

the project can decrease as the project nears completion. .

Project Management SoftwarePMS is often used to monitor the three EVM dimensions (PV, EV, and AC),to display graphical trends, and to forecast a range of possible final results. 

PMP Prep – Cost Slide 44

CONTROL COSTS -CONTROL COSTS -OUTPUTSOUTPUTSOUTPUTS

• Work Performance Measurements

Page 261: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 261/590

• Work Performance Measurements• Budget Forecasts

• Organizational Process Assets Updates -

• Change Requests –

• Project Management Plan Updates -

- Cost performance baseline

• Project document Updates

- Cost estimates

- Basis of estimates 

PMP Prep – Cost Slide 45

DEPRECIATIONDEPRECIATION

Straight Line Depreciation (SLD)

• Equal amount of depreciation is taken out each period (year)

Example below shows depreciation for 5 years where:

Page 262: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 262/590

Example below shows depreciation for 5 years where:

Depreciable value is $140,000 (purchase price) - $40,000 (salvage Value) = $100,000

Depreciation each year is $100,000 / 5 years = $20,000/year 

 

PMP Prep – Cost Slide 46

Purchase

Price

Salvage

Value

 Year Depreciati

on

Depreciated

Balance

$ 140,000 $40,000 0 0 $100,000

1 $20,000 $80,000

2 $20,000 $60,000

3 $20,000 $40,000

4 $20,000 $20,000

5 $20,000 0

DEPRECIATIONDEPRECIATION

Double Declining Balance (DDB)

• Depreciation taken out each period (year) by double straight line depreciation

• Usually applied on the initial purchase price (don’t subtract salvage value)

Page 263: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 263/590

• Usually, applied on the initial purchase price (don t subtract salvage value)

Example below shows depreciation for 5 years where:

Depreciation for 1st year is $140,000 / 5 years x 2 = $56,000 (or 40% of $140,000)

Depreciation for 2nd year is $84,000 / 5 years x 2 = $33,600 (or 40% of $84,000)

 

PMP Prep – Cost Slide 47

Purchase Price Depreciation % Year Depreciation Depreciated Balance

$ 140,000 0 0 $140,000

40% 1 $56,000 $84,000

40% 2 $33,600 $50,400

40% 3 $20,160 $30,240

40% 4 $12,096 $18,144

40% 5 $7,257 $10,886(Salvage)

DEPRECIATIONDEPRECIATION

Sum of Years Digits Depreciation (SYD)• Accelerated depreciation amount taken out each period (year) based on year’s digits

Example below shows depreciation for 5 years where sum of years’ digits = 1+2+3+4+5 = 15

Page 264: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 264/590

Example below shows depreciation for 5 years where sum of years digits 1 2 3 4 5 15Depreciation factor for 1st year is 5 (reverse order of years) / 15 (sum of years)

Multiply factor by original balance to get depreciation for that year 

Depreciation for 1st year is 5/15 x $100,000 = $33,333, 2nd year is 4/15 x $100,000 = $26,667

Purchase

Price

Salvage

Value

Depreciation

Factor

 Year Depreciatio

n

Depreciate

d Balance

$140,000 $40,000 0 0 $100,000

5/15 1 $33,333 $66,667

4/15 2 $26,667 $40,000

3/15 3 $20,000 $20,000

2/15 4 $13,000 $6,667

1/15 5 $6,667 0

CONTROL COSTS -CONTROL COSTS -EARNED VALUEEARNED VALUE

Performance Measurement Baseline

  Current

Page 265: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 265/590

PMP Prep – Cost Slide 49

  PV EV AC

 January 0 0 0

February 2500 3600 6000

March 8000 8000 8000

April 13000 10000 8000

May 42000 38000 48000

 June 62000

 July 70000

CONTROL COSTS - COSTCONTROL COSTS - COSTVARIANCEVARIANCE

From the last chart, we have these values and can make thesecalculations:

PV $42 000 EV = $38 000 AC = $48 000

Page 266: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 266/590

PV $42,000 EV = $38,000 AC = $48,000

Comparing original amount budgeted for work that's done (EV) tothe amount spent to produce that work (AC), we can get costvariance (CV) as follows:

CV (= EV -AC ) = $38,000 -$48,000 = -$10,000 (> spent thanplanned)

Comparing original amount budgeted for work that's done (EV) to

the amount budgeted for that work In the plan (PV), we can getschedule variance (SV) as follows:

SV (= EV -PV ) = $38,000 -$42,000 = -$4,000 «work than planned)

PMP Prep – Cost Slide 50

CONTROL COSTS - OTHERCONTROL COSTS - OTHERCALCULATIONSCALCULATIONS

CPI ( = EV / AC ) = $38,000/ $48,000 = 0.79

$0 79 worth of work was done for each $1 00 spent

Page 267: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 267/590

$0.79 worth of work was done for each $1.00 spent

SPI(= EV/PV) =$38,000/ $42,000 =0.90

$0.90 worth of work was done for each $1.00 worth of work planned

ETC ( = BAC -EV) = $70,700 -$38,000 = $32,700EAC ( = AC+BAC-EV) = $48,000 + $70,700 -$38,000 = $80,700

VAC ( = BAC -EAC) = $70,700-$80,700 =-$10,000

Project will exceed planned budget by $10,000

PMP Prep – Cost Slide 51

CONTROL COSTS - SAMPLE COSTCONTROL COSTS - SAMPLE COSTPROBLEMPROBLEM

More Calculations (slight possibility that these will be on the exam)

Page 268: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 268/590

PMP Prep – Cost Slide 52

Given

BAC = $40K EV = $20K PV = $28K AC = $26K 

Calculate

% of work Scheduled% of Budget Spent

% of Work AccomplishedTo Complete

Performance Index(TCPI)CV%SV%

CONTROL COSTSCONTROL COSTS - SAMPLE- SAMPLESOLUTIONSOLUTION 

More Calculations

Page 269: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 269/590

More Calculations

Answers

% of Work Scheduled

% of Budget Spent

% of Work AccomplishedTCPI

CV%SV%

PV/ BAC = $28K/ $40K = 0.7 or 70%

AC/ BAC = $26K / $40K = 0.65 or 65%

EV / BAC =$20K / $40K = 0.5 or 50%(BAC-EV)/( BAC - AC) =

($40K -$20K) / ( $40K -$26K) = 1.43

CV / EV =($20K -$26K ) / $20K =0.3 or 30%SV/ PV =( $20-$28)/$28K =0.28 or 28%

PMP Prep – Cost Slide 53

CONTROL COSTS - EARNED VALUECONTROL COSTS - EARNED VALUEEXAMPLESEXAMPLES

FOR BUDGET

Page 270: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 270/590

PMP Prep – Cost Slide 54

If CPI < 1 EV < AC Over Budget

If CPI > 1 EV > AC Under Budget

FOR SCHEDULE

IF SPI < 1 EV < PV Behind Schedule

IF SPI > 1 EV > PV Ahead of Schedule

CONTROL COSTSCONTROL COSTS - CASE 1

PV = $1,860

EV = $1,860

AC = $1 860

Page 271: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 271/590

AC = $1,860

PMP Prep – Cost Slide 55

This is the idealsituation,

Where everythinggoes

According to plan

CONTROL COSTSCONTROL COSTS - CASE 2SCHEDULE

CASE 2 SCHEDULE

PV = $1,900 Here we see $400 worth of

Page 272: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 272/590

PV $1,900EV = $1,500

AC = $1,700

SV = EV-PV = -$400

SV% = SV/ PV = -0.21 or -21%

PMP Prep – Cost Slide 56

Here we see $400 worth of work is behind schedule inbeing completed. We are

21% behind where weplanned to be.

CONTROL COSTSCONTROL COSTS - CASE 2COST

PV= $1,900

EV= $1,500

AC= $1,700

Page 273: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 273/590

AC $1,700

CV = EV-AC = -$200 

CV% = CV I EV = -0.13 or -13%

PMP Prep – Cost Slide 57

Also, we see “Actuals” (AC)exceed “Earned” (EV)

$1,500 worth of work wasaccomplished, However; it

cost $1,700 to do so. Wehave a $200 cost overrun(13% over budget)

 CONTROL COSTSCONTROL COSTS - CASE 2 INDICES

PV = $1,900

EV = $1,500

AC = $1,700

This means only 79 centsth f k d f

Page 274: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 274/590

C $ , 00

SPI = EV I PV = $0.79

CPI= EV I AC = $0.88

Case 2 is the worst case where all

performance indicators are negative.

 PMP Prep – Cost Slide 58

s ea s o y 9 ce tsworth of work was done for 

each $1.00 of workplanned, and only 88 centsworth of work was actually

done for each $1.00 spent.

 CONTROL COSTSCONTROL COSTS - CASE 3 INDICES

PV= $2,600 

EV= $2,400

Page 275: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 275/590

EV $2,400 

AC= $2,200 

SV= -$200 SV% = - 8%

SPI= 0.92 

PMP Prep – Cost Slide 59

This is bad news. Our work efficiencyis a bit low. We are getting only 92

cents of work done per dollar. We arebehind schedule.

CONTROL COSTS – CASE 3CONTROL COSTS – CASE 3INDICESINDICES

PV = $2,600

EV = $2,400

AC = $2,200

This is good news as we are under 

Page 276: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 276/590

$ ,

CV = $200 

CV% = 8%CPI = 1.09

SPI = EV/PV = 2400/2600 = 0.92

Case 3 is under budget, but behind schedule.

 PMP Prep – Cost Slide 60

gbudget. We are getting $1.09 worth of 

work done for each $1.00 spent.

Questions?Questions?

Page 277: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 277/590

PMP Prep – Cost Slide 61

  This page is Left Blank intentionally

Page 278: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 278/590

 

  This page is Left Blank intentionally

Page 279: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 279/590

 

DAY 3

Page 280: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 280/590

 PMP Prep – Communications Slide 1

CHAPTER 10

PROJECTCOMMUNICATIONS

MANAGEMENT

AGENDAAGENDA 

Day 1  DAY 4

  PMP Exam Prep Introduction Project QUALITY  Management

Page 281: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 281/590

Project Management Framework  Project RISK  Management

*Introduction Project HUMANRESOURCE Management

*Project Life Cycle & Organisation

Project Management Processes

  DAY 2  DAY 5  Project INTEGRATION Management ProjectPROCUREMENT Management

Project SCOPE Management Professional & SocialResponsibility

DAY 3 DAY 6  Project TIME Management REVISION & QUIZ

Project COST Management

PROJECT COMMUNICATIONSPROJECT COMMUNICATIONS

MANAGEMENTMANAGEMENT WHAT DOES THE COMMUNICATIONS KNOWLEDGE AREA DO?

 • It employs the processes required to ensure timely and appropriate

Page 282: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 282/590

 It employs the processes required to ensure timely and appropriategeneration, collection, distribution, storage retrieval, and ultimate

disposition of project information

• These processes provide the critical links among people & informationthat are necessary for successful communications.

• Project managers spend the majority of their time communicating with teammembers and other project stakeholders, whether they are internal or 

external to the organization.

Effectively deals with stakeholders' information needs. 

PMP Prep – Communications Slide 2

COMMUNICATION SKILLSCOMMUNICATION SKILLS

COMMUNICATION SKILLS

•  Most communication skills are common for general mgmt. and projectmgmt., such as, but not limited to:

Page 283: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 283/590

g

• Listening actively and effectively,• Questioning, probing ideas and situations to ensure better 

understanding,• Educating to increase team’s knowledge so that they can be more

effective,•  Fact-finding to identify or confirm information,• Setting and managing expectations,• Persuading a person or organization to perform an action,• Negotiating to achieve mutually acceptable agreements between

parties,• Resolving conflict to prevent disruptive impacts, and• Summarizing, recaping, and identifying the next steps.

PMP Prep – Communications Slide 3

COMMUNICATION MODELSCOMMUNICATION MODELSCOMMUNICATION MODELS

• See Fig 10-8, p.255 for a basic two-person model of communications (how ideas or information are sent & received between two parties)

• Key components of model include:

Page 284: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 284/590

 •  Encode: translate thoughts or ideas into a language that is understood by

others•  Message & feedback-message: the output of encoding•  Medium: the method used to convey the message, e.g. email, fax•  Noise:  anything that interferes with transmission and understanding of 

the message (e.g. distance)

•  Decode: to translate the message back into meaningful thoughts or ideas

• Inherent in the model is an action to acknowledge a message.• Acknowledgement means that the receiver signals receipt of the message, but notnecessarily in agreement with the message.

• Another action is response to a message, which means that the receiver has

decoded, understands, and is replying to the message.• Sender is responsible for making information clear & complete so that the receiver can receive it correctly & confirming that it is understood properly

• Receiver is responsible for making sure that information is received in itsentirety & correctly understood

PMP Prep – Communications Slide 4

COMMUNICATION METHODSCOMMUNICATION METHODSThere are several communication methods used to share information among projectstakeholders. These methods can be broadly classified into:

• Interactive communication

Between two or more parties performing a multidirectional exchange of 

information. It is the most efficient way to ensure a common

Page 285: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 285/590

understanding by all participants on specified topics, and includes

meetings, phone calls, video conferencing, etc.

•  Push communication

Sent to specific recipients who need to know the information. This

ensures that the information is distributed but does not certify that itactually reached or was understood by the intended audience. Push

communication includes letters, memos, reports, emails, faxes, voice

mails, press releases etc.

•  Pull communication

  Used for very large volumes of information, or for very large audiences, that

requires the recipients to access the communication content at their own

discretion. These methods include intranet sites, e-learning, and knowledge

repositories, etc.

PMP Prep – Communications Slide 5

COMMUNICATIONSCOMMUNICATIONSPROCESSPROCESS

  COMMUNICATIONS PROCESS DEFINITIONS10.1 Identify Stakeholders

• Identify all people or organizations impacted by the project, anddocumenting relevant

Page 286: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 286/590

ginformation regarding their interests, involvement, and impact on

project success.10.2 Plan Communications• The process of determining the project stakeholder informationneeds and

defining a communication approach. 10.3 Distribute Information• The process of making relevant information available to projectstakeholders as

planned.10.4 Manage Stakeholders Expectations• The process of communicating and working with stakeholders tomeet their needs and addressing issues as they occur.10.5 Report Performance • The process of collecting and distributing performanceinformation, including status reports, progress measurements, andforecasts.

COMMUNICATIONSCOMMUNICATIONSPROCESSESPROCESSES

PROCESSES BY PROCESS GROUP

 

Page 287: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 287/590

PMP Prep – Communications Slide 7

INITIATING PLANNING EXECUTING MONITORING &CONTROLLING

10.1

IdentifyStakeholders

10.2 Plan

Communications

10.2

DistributeInformation

10.3

ReportPerformance

10.3 ManageStakeholders

Expectations

IDENTIFY STAKEHOLDERSIDENTIFY STAKEHOLDERS

 WHAT HAPPENS IN IDENTIFY STAKEHOLDERS? 

•  It is the process of identifying all people or organizations impacted by the

project, and documenting relevant information regarding their interests,involvement and impact on project success

Page 288: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 288/590

involvement, and impact on project success

• Project stakeholders are persons and organizations such as customers,sponsors, the performing organization, and the public that are activelyinvolved in the project, or whose interests may be positively or negativelyaffected by the execution or completion of the project. They may also

exertinfluence over the project and its deliverables.

• Stakeholders may be at different levels within the organization and maypossess different authority levels, or may be external to the performingorganization for the project (Section 2.3 identifies various types of projectstakeholders.

IDENTIFY STAKEHOLDERSIDENTIFY STAKEHOLDERS

TOOLS & TECHNIQUES• Stakeholder analysis

Page 289: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 289/590

PMP Prep – Communications Slide 9

INPUTS• Project Charter 

• Procurement documents• Enterprise environmental factors• Organizational process assets

OUTPUTS• Stakeholder register • Stakeholder  mgmt. 

strategy 

 Stakeholder analysis• Expert judgement

 

IDENTIFY STAKEHOLDERS -IDENTIFY STAKEHOLDERS -INPUTSINPUTS

INPUTS

• Project Charter 

Page 290: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 290/590

• Procurement Documents • Enterprise Environmental Factors  i.e. company culture and structure, and Governmental or industry

standards

• Organizational Process Assetsi.e. stakeholder register templates, lessons learned from previous

projects, and stakeholder registers from previous projects.

 

PMP Prep – Communications Slide 10

IDENTIFY STAKEHOLDERS –IDENTIFY STAKEHOLDERS –T&TT&T

TOOLS & TECHNIQUES

• Stakeholder Analysis

Page 291: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 291/590

  Follows a number of steps (read page 248 to 250)

• Expert Judgement

PMP Prep – Communications Slide 11

IDENTIFY STAKEHOLDERS –IDENTIFY STAKEHOLDERS –OUTPUTSOUTPUTS

OUTPUTS

Stakeholder Register 

Page 292: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 292/590

This contains all details related to the identifiedstakeholders including, but not limited to:• Identification information

(Name, position, location, role in the project , contact info.)

• Assessment information(major requirements., main expectations, potential influence in theproject, phase in the life cycle with the most interest; and

• Stakeholder classification

  (internal/external, supporter/neutral/resistor, etc.)

PMP Prep – Communications Slide 12

IDENTIFY STAKEHOLDERS –IDENTIFY STAKEHOLDERS –OUTPUTSOUTPUTS

OUTPUTS

Stakeholder Management StrategyThe stakeholder management strategy defines an approach to

Page 293: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 293/590

The stakeholder management strategy defines an approach toincrease the support and minimize negative impacts of stakeholdersthroughout the entire project life cycle. It includes elements such as:• Key stakeholders who can significantly impactthe project,

• Level of participation in the project desired for eachidentified stakeholder, and

• Stakeholder groups and their management (as groups) A common way of representing the stakeholder management strategyis a stakeholder analysis matrix. An example of a blank matrix with

column headers is provided in Fig. 10-5 (page 251)

PMP Prep – Communications Slide 13

COMMUNICATIONCOMMUNICATIONPROCESSESPROCESSES

PROCESSES BY PROCESS GROUP

 INITIATING PLANNING EXECUTING MONITORING &

Page 294: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 294/590

PMP Prep – Communications Slide 14

INITIATING PLANNING EXECUTING MONITORING &CONTROLLING

10.1

IdentifyStakeholders

10.2 Plan

Communications

10.2

DistributeInformation

10.3

ReportPerformance

10.3 ManageStakeholdersExpectations

PLAN COMMUNICATIONSPLAN COMMUNICATIONS 

WHAT HAPPENS IN PLAN COMMUNICATIONS?

• Plan communications is the process of determining the project

Page 295: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 295/590

p g p jstakeholder information needs and defining a communicationapproach (see fig. 10-7, the Data Flow diagram)

• Who needs - what, when; how the needs will be fulfilled and by whom

• Identifying the information needs of the stakeholders and determining asuitable means of meeting those needs are important factors for projectsuccess.

• Improper communication planning will lead to problems such as delay in message

delivery, communication of sensitive information to the wrong audience, or lack of communication to some of the required stakeholders.

 

PMP Prep – Communications Slide 15

PLAN COMMUNICATIONSPLAN COMMUNICATIONS

TOOLS & TECHNIQUES

• Communication requirementanalysis

Page 296: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 296/590

PMP Prep – Communications Slide 16

INPUTS

• Stakeholder register • Stakeholder management strategy• Enterprise environmental factors

• Organizational process assets

OUTPUTS

• Communicationsmanagement plan

• Project document

updates

• Communication technology• Communication models• Communication methods

 

PLAN COMMUNICATIONSPLAN COMMUNICATIONS --INPUTSINPUTS

INPUTS 

Page 297: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 297/590

• Stakeholder Register   Section 10.1.3.1

• Stakeholder Management Strategy  Section 10.1.3.2

• Enterprise Environmental Factors

• Organizational Process Assets

 

PMP Prep – Communications Slide 17

PLAN COMMUNICATIONS –PLAN COMMUNICATIONS –T&TT&T

TOOLS & TECHNIQUESCOMMUNICATION REQUIREMENT S ANALYSIS

• Determine total information needs of project stakeholders

Page 298: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 298/590

• Combine the type & format of information needed with an analysis of thevalue of that information (e.g. all information that contributes to projectsuccess or prevents failure)

• Number of communication channels is, n ( n -1 ) / 2 (remember for exam)

where n = number of stakeholders

• How many potential channels of communication are there in a projectwith

21 stakeholders? __________ 

 

PMP Pre – Communic tion Slide 18

PLAN COMMUNICATIONS –PLAN COMMUNICATIONS –T&TT&T

COMMUNICATIONS TECHNOLOGYMethodologies used to transfer information among stakeholders can vary significantly, e.g. email,text messaging, etc.

Communications technology factors that can affect the project

Page 299: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 299/590

Communications technology factors that can affect the projectinclude:

•  Urgency of the need for information – Is project success dependent upon

having frequently updated information available on a moment’s notice, or 

would regularly issued written reports suffice?•  Availability of technology - Are existing systems appropriate, or do the

project needs warrant change needed?

•  Expected project staffing - Are proposed communications systems

compatible with the experience & expertise of project participants, or is

extensive training and learning required?

•  Length of the project - Is the available technology likely to change before

the project is over?

•  Project environment - Does the team meet and operate on a face-to-face or 

in a virtual environment?

 –

PLAN COMMUNICATIONS –PLAN COMMUNICATIONS –T&TT&T

• COMMUNICATION MODELS• See Fig 10-8, p.255 for a basic two-person model of communications (how ideas or 

information are sent & received between two parties)• Key components of model include:

Page 300: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 300/590

 Key components of model include: 

•  Encode: translate thoughts or ideas into a language that is understood byothers

•  Message & feedback-message: the output of encoding•  Medium: the method used to convey the message, e.g. email, fax

•  Noise:  anything that interferes with transmission and understanding of the message (e.g. distance)•  Decode: to translate the message back into meaningful thoughts or 

ideas

• Inherent in the model is an action to acknowledge a message.• Acknowledgement means that the receiver signals receipt of the message, but notnecessarily in agreement with the message.

• Another action is response to a message, which means that the receiver hasdecoded, understands, and is replying to the message.

• Sender is responsible for making information clear & complete so that the receiver can receive it correctly & confirming that it is understood properly

• Receiver is responsible for making sure that information is received in itsentirety & correctly understood

PMP Pre – Communications Slide 20

PLAN COMMUNICATIONS –PLAN COMMUNICATIONS –T&TT&T

COMMUNICATION METHODSThere are several communication methods used to share information among projectstakeholders. These methods can be broadly classified into:

• Interactive communicationBetween two or more parties performing a multidirectional exchange of 

Page 301: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 301/590

p p g ginformation. It is the most efficient way to ensure a commonunderstanding by all participants on specified topics, and includesmeetings, phone calls, video conferencing, etc.

•  Push communication

Sent to specific recipients who need to know the information. Thisensures that the information is distributed but does not certify that itactually reached or was understood by the intended audience. Pushcommunication includes letters, memos, reports, emails, faxes, voicemails, press releases etc.

•  Pull communication  Used for very large volumes of information, or for very large audiences, that

requires the recipients to access the communication content at their owndiscretion. These methods include intranet sites, e-learning, and knowledgerepositories, etc.

 PMP Prep – Communications Slide 21

PLAN COMMUNICATIONS –PLAN COMMUNICATIONS –T&TT&T

COMMUNICATION METHODSThere are several communication methods used to share information among projectstakeholders. These methods can be broadly classified into:

• Interactive communicationBetween two or more parties performing a multidirectional exchange of 

Page 302: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 302/590

p p g ginformation. It is the most efficient way to ensure a commonunderstanding by all participants on specified topics, and includesmeetings, phone calls, video conferencing, etc.

•  Push communication

Sent to specific recipients who need to know the information. Thisensures that the information is distributed but does not certify that itactually reached or was understood by the intended audience. Pushcommunication includes letters, memos, reports, emails, faxes, voicemails, press releases etc.

•  Pull communication  Used for very large volumes of information, or for very large audiences, that

requires the recipients to access the communication content at their owndiscretion. These methods include intranet sites, e-learning, and knowledgerepositories, etc.

 PMP Prep – Communications Slide 22

PLAN COMMUNICATIONS –PLAN COMMUNICATIONS –OUTPUTSOUTPUTS

OUTPUTS

COMMUNICATIONS MANAGEMENT PLAN is a subsidiary plan of theProject Management Plan that provides: 

Page 303: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 303/590

• Stakeholder communication requirements;• Information to be communicated (includes format, content & level of 

detail);• Reason for the distribution of that information;• Time frame and frequency for the distribution of required information;• Person responsible for communicating the information• Person responsible for authorizing release of confidential information;• Person/groups who will receive the information;• Methods or technologies used to convey the information, such as

memos, email, and/or press releases;

PMP Prep – Communications Slide 23

PLAN COMMUNICATIONS –PLAN COMMUNICATIONS –OUTPUTSOUTPUTS

OUTPUTSCOMMUNICATIONS MANAGEMENT PLAN (contd.)

• Resources allocated for communication activities, including time and budget;

E l ti id tif i ti f & th t h i f

Page 304: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 304/590

• Escalation process – identifying time frames & the management chain for escalation of issues;

• Method for updating and refining the communications management plan as projectprogresses and develops;

• Glossary of common terminology;

• Flow charts of the information flow in the project, workflows with possible sequenceof authorization, list of reports, and meeting plans, etc.; and

• Communication constraints, usually derived from specific legislation or regulation,

technology, and organizational policies, etc. 

PLAN COMMUNICATIONS -PLAN COMMUNICATIONS -OUTPUTSOUTPUTS

OUTPUTS

Project Document Updates

Page 305: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 305/590

Project documents that may be updated include but are not limited to:

• Project schedule• Stakeholder register 

• Stakeholder management strategy

COMMUNICATIONSCOMMUNICATIONSPROCESSESPROCESSES

PROCESSES BY PROCESS GROUP

 INITIATING PLANNING EXECUTING MONITORING &

Page 306: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 306/590

PMP Prep – Communications Slide 26

INITIATING PLANNING EXECUTING MONITORING &CONTROLLING

10.1

IdentifyStakeholders

10.2 Plan

Communications

10.2

DistributeInformation

10.3

ReportPerformance

10.3 ManageStakeholdersExpectations

DISTRIBUTEDISTRIBUTEINFORMATIONINFORMATION

  WHAT HAPPENS IN DISTRIBUTE INFORMATION?M ki i f ti il bl t j t t k h ld

Page 307: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 307/590

• Making information available to project stakeholders asplanned (see Fig. 10-10, page 259, Data Flow Diagram

• It is performed throughout the entire project life cycle and in

all management processes.

• The focus is mainly in the execution process, which includesimplementing the communications management plan, as wellas responding to unexpected requests for information.

 

PMP Prep – Communications Slide 27

DISTRIBUTEDISTRIBUTEINFORMATIONINFORMATION

TOOLS & TECHNIQUES

•Communications methods

• Information distribution tools 

Page 308: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 308/590

PMP Prep – Communications Slide 28

INPUTS

• Project management plan• Performance reports

• Organizational process assets

OUTPUTS

• Organizational processassets updates)

• Requested changes

DISTRIBUTEDISTRIBUTEINFORMATIONINFORMATION - INPUTS- INPUTS

INPUTS • Project management plan

Page 309: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 309/590

• Project management plan  Section 10.2.3.1 contains the communications management plan.

• Performance reportsPerformance reports are used to distribute project performance and status

information, should be made available prior to project meetings, and should be asprecise and current as possible.

• Organizational Process Assets  The organizational process assets that can influence the Distribute Information

process include, but are not limited to

- Policies, procedures, and guidelines regarding information distribution - Templates, and- Historical information and lessons learned

PMP Prep – Communications Slide 29

DISTRIBUTEDISTRIBUTEINFORMATION– T&TINFORMATION– T&T

Tools & Techniques

Communications Methods

Page 310: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 310/590

Individual and group meetings, video and audio conferences, computer chats, andother remote communications methods are used to distribute information.

Information Distribution Tools

• Hard-copy document distribution, manual filing systems, press releases, andshared-access electronic databases;

• Electronic communication and conferencing tools, such as email, fax, voice mail,telephone, video and web conferencing, websites and web publishing; and

• Electronic tools for project management, such as web interfaces to scheduling andproject mgmt. Software, meeting and virtual office support software, portals, andcollaborative work mgmt. Tools.

PMP Prep – Communications Slide 30

DISTRIBUTE INFORMATION –DISTRIBUTE INFORMATION –OUTPUTSOUTPUTS

Outputs

Organization Process Assets Updates

Page 311: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 311/590

• Stakeholder notifications• Project reports• Project presentations

• Project records• Feedback from stakeholders• Lessons learned documentation

Requested Changes

PMP Prep – Communications Slide 31

COMMUNICATIONSCOMMUNICATIONSPROCESSESPROCESSES

PROCESSES BY PROCESS GROUP

 INITIATING PLANNING EXECUTING MONITORING &

Page 312: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 312/590

PMP Prep – Communications Slide 32

CONTROLLING

10.1Identify Stakeholders

10.2 PlanCommunications

10.2Distribute

Information

10.3Report

Performance

10.3 ManageStakeholdersExpectations

MANAGE STAKEHOLDERSMANAGE STAKEHOLDERSEXPECTATIONSEXPECTATIONS

  WHAT HAPPENS IN MANAGE STAKEHOLDERSEXPECTATIONS?

Page 313: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 313/590

• It is the process of communicating and working withstakeholders to meet their needs and addressing issues asthey occur ( see Fig. 10-1.20, page 262, Data Flow Diagram)

• It involves communication activities directed towards projectstakeholders to influence their expectations, addressconcerns, and resolve issues (read page 261)

PMP Prep – Communications Slide 33

MANAGE STAKEHOLDERSMANAGE STAKEHOLDERSEXPECTATIONSEXPECTATIONS

TOOLS & TECHNIQUES• Communications methods

• Interpersonal skills• Management skills

Page 314: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 314/590

PMP Prep – Communications Slide 34

INPUTS• Stakeholder register

• Stakeholder mgmt. strategy• Project management plan

• Issue log• Change log

• Organizational process assets

 

OUTPUTS• Organizational process

assets updates• Change requests

• Project mgmt. plan

updates• Project documentupdates

MANAGE STAKEHOLDERS EXPECTATIONS - INPUTSMANAGE STAKEHOLDERS EXPECTATIONS - INPUTS

  Inputs

• Stakeholder register 

• Stakeholder management strategy

Page 315: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 315/590

• Stakeholder management strategy   An understanding of stakeholder goals and objectives is used to determine a

strategy to manage stakeholder expectations (see Section 10.1.3.2)

• Project mgmt. plan

• Issue log  It is used to document and monitor the resolution of issues.

•  Change log

It is used to document changes that occur during a project. These changes andtheir impact to the project in terms of time, cost, and risk,

• Organizational process assets

 PMP Prep – Communications Slide 35

MANAGE STAKEHOLDERS EXPECTATIONS - T&TMANAGE STAKEHOLDERS EXPECTATIONS - T&T

Tools & Techniques

• Communication Methods

Page 316: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 316/590

• Interpersonal Skills  Building trust, resolving conflict, active listening, and public speaking

• Management Skills Issue log  Presentation skills, Negotiating, Writing skills, and public speaking

MANAGE STAKEHOLDERS EXPECTATIONS - OUTPUTSMANAGE STAKEHOLDERS EXPECTATIONS - OUTPUTS

Outputs

•  Organizational Process Assets Updates

Page 317: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 317/590

• Change Requests

• Project Mgmt. Plan Updates

• Project Document Updates

PMP Prep – Communications Slide 37

COMMUNICATIONSCOMMUNICATIONSPROCESSESPROCESSES

PROCESSES BY PROCESS GROUP

 INITIATING PLANNING EXECUTING MONITORING &

CONTROLLING

Page 318: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 318/590

PMP Prep – Communications Slide 38

CONTROLLING

10.1Identify Stakeholders

10.2 PlanCommunications

10.2Distribute

Information

10.3Report

Performance

10.3 ManageStakeholders

Expectations

REPORT PERFORMANCEREPORT PERFORMANCE

What ‘Report Performance’ process do?

Report performance is the process of collecting and distributing performance

Page 319: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 319/590

p p p g g pinformation, including status reports, progress measurements, and forecasts (seeFig, 10-14, Data Flow Diagram) The process involves the periodic collection andanalysis of baseline versus actual data to understand and communicate the projectprogress and performance as well as to forecast the project results.

Performance reports need to provide information at an appropriate level for eachaudience.

PMP Prep – Communications Slide 39

REPORT PERFORMANCEREPORT PERFORMANCE

TOOLS & TECHNIQUES

• Variance analysis• Forecasting methods• Communication methods

Page 320: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 320/590

PMP Prep – Communications Slide 40

INPUTS• Project management plan

• Work performance information• Work performance measurements

• Budget forecasts• Quality control measurements

• Organizational processassets

 

OUTPUTS• Performance reports

• Organizational processassets updates

• Change Requests• 

Communication methods• Reporting systems

REPORT PERFORMANCE -REPORT PERFORMANCE -INPUTSINPUTS

INPUTS

• Project Management Plan

Page 321: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 321/590

• Work Performance Information 

e.g. completion status of the deliverables and what has been accomplished

is collected as part of project execution, and is fed into the PerformanceReporting process

• Work Performance Measurements

• Budget Forecasts

• Organizational Process Assets

REPORT PERFORMANCE -REPORT PERFORMANCE -T&TT&T

TOOLS & TECHNIQUES

• Variance AnalysisIt is an after-the-fact look at what caused a difference between the

Page 322: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 322/590

baseline and the actual performance.

 

• Forecasting Methods

  It is the process of predicting future project performance based onactual performance to date. Forecasting methods may be

classified in different categories:

- Time series methods

- Causal/econometric methods

- Judgmental methods- Other methods (include simulation, probabilistic forecasting, and

ensemble forecasting)

 PMP Prep – Communications Slide 42

REPORT PERFORMANCE -REPORT PERFORMANCE -T&TT&T

• Communication Methods

Exchange and analyze information about the project progress andperformance. The project manager generally uses a push communication

technique

Page 323: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 323/590

technique.

• Reporting Systems

Standard tool for the project manager to capture, store, and distribute

information to stakeholders.

 PMP Prep – Communications Slide 43

REPORT PERFORMANCE -REPORT PERFORMANCE -OUTPUTSOUTPUTS

OUTPUTS Performance Reports

- Organize & summarize project performance information from all areas

- Results of any analysis are compared with performance measurementbaseline

- Report should provide the status & progress information and the level of

Page 324: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 324/590

- Report should provide the status & progress information, and the level of detail required by various stakeholders, as documented in thecommunications management plan

Common formats for performance reports include: • Bar charts• S-curves• Histograms (bar graph where bar widths are proportional to variable

classes & bar heights proportional to class frequencies)• Tables•  Variance analysis

• Earned value analysis data is often included• Forecast data

See Fig. 10-15, page 271- Tabular Performance Report Sample

PMP Prep – Communications Slide 44

REPORT PERFORMANCE -REPORT PERFORMANCE -OUTPUTSOUTPUTS

• Organizational Process Assets Updates

• Change Requests

Page 325: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 325/590

Change Requests- Analysis of project performance often generates change requests

PMP Prep – Communications Slide 45

SAMPLE EXAM QUESTIONSAMPLE EXAM QUESTION

Question

Some common formats of performance reports are:

Page 326: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 326/590

Some common formats of performance reports are:

 A.S-curves, histograms, WBS

B.S-curves, precedence network diagrams, histogramsC.Bar charts, S-curves, histograms

D.Bar charts, earned value analysis, histograms

PMP Prep – Communications Slide 46

SAMPLE EXAM QUESTIONSAMPLE EXAM QUESTION

Answer-C is the correct answer.

Page 327: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 327/590

 A - WBS does not report performance. It is a deliverable-orientedhierarchical decomposition of the work to be executed by the project teamto accomplish the project objectives and create the required deliverables.

B - A precedence network diagram does not report performance. A networkdiagram presents the project schedule in a format that demonstrates logicalrelationships between project activities.

D - Earned value analysis is a technique, not a report.

PMP Prep – Communications Slide 47

Questions?Questions?

Page 328: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 328/590

 PMP Prep – Communications Slide 48

  This page is Left Blank intentionally

 

Page 329: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 329/590

  This page is Left Blank intentionally

 

Page 330: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 330/590

  This page is Left Blank intentionally

 

Page 331: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 331/590

DAY 4

CHAPTER 8

Page 332: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 332/590

 PMP Prep – Quality Slide 1

CHAPTER 8

PROJECT QUALITY MANAGEMENT

AGENDAAGENDA 

Day 1  DAY 4  PMP Exam Prep Introduction Project QUALITY  

ManagementProject Management Framework  Project RISK  

Management

Page 333: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 333/590

*Introduction Project HUMANRESOURCE Management

*Project Life Cycle & OrganisationProject Management Processes

  DAY 2  DAY 5  Project INTEGRATION Management ProjectPROCUREMENT Management

Project SCOPE Management Professional & SocialResponsibility

DAY 3 DAY 6  Project TIME Management REVISION & QUIZ

Project COST Management

WHAT’S PROJECT QUALITY WHAT’S PROJECT QUALITY MANAGEMENT?MANAGEMENT?

WHAT’S PROJECT QUALITY MANAGEMENT?

Project Quality Management processes include all the activities of the

Page 334: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 334/590

performing organization that determine quality policies, objectives, andresponsibilities so that the project satisfy the needs for which it wasundertaken. It implements the quality management system through the

policy, procedures, and processes of quality planning, quality assurance,and quality control, with continuous process improvement activitiesconducted throughout, as appropriate.

PMP Prep – Quality Slide 2

PROJECT QUALITY PROJECT QUALITY MANAGEMENT?MANAGEMENT?

  WHAT DO THE QUALITY EXPERTS SAY ABOUTQUALITY?

Page 335: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 335/590

• Quality is "the degree to which a set of characteristics fulfil

requirements"

• Quality should be planned, designed & built-in as the integralpart of the process.

QUALITY MANAGEMENTQUALITY MANAGEMENTAPPROACHAPPROACH

PMl's QUALITY MANAGEMENT APPROACH

1. Uses standards established by:a) International Organization for Standardization (ISO)

b) Total Quality Management (TQM)

Page 336: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 336/590

PMP Prep - Quality Slide 4

ISO

b) Total Quality Management (TQM)c) Six Sigma Cost of Quality (COQ)

d) Continuous Improvement2. Addresses quality of the project & the product of the project

3. Because projects are temporary, the cost for product quality is oftenborne by the acquiring organization, especially defect prevention &

appraisal.

TQM COQ

Modern quality management complements project management. For example, both disciplines recognize the importance of:

• Customer Satisfaction: understanding, evaluating, defining, andmanaging combination of:• conformance to requirements (the project must produce what it said it

QUALITY MANAGEMENTQUALITY MANAGEMENTAPPROACHAPPROACH

Page 337: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 337/590

would produce), and• fitness for use (the product or service must satisfy real needs)

• Prevention Over Inspection: The cost of preventing mistakes is generallymuch less than the cost of correcting them, as revealed by inspection

• Management Responsibility: Management must provide resourcesneeded to meet quality levels and thus succeed

• Continuous Improvement: The plan-do-check-act cycle is the basis for quality improvement (as defined by Shewhart and modified by Deming) 

PMP Prep – Quality Slide 5

QUALITY versus GRADE• Quality and Grade are not the same.

• Grade is a category (or rank) that distinguishes items having the samefunctional use but different technical characteristics, e.g. a product with lotsof features and benefits is generally considered a high grade product, but

QUALITY VS GRADEQUALITY VS GRADE

Page 338: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 338/590

 

still can be of poor quality.

• Quality is a degree measuring fitness for use, e.g. a high quality product

will meet the specs and satisfy the real purpose, but may have limitedfeatures (or, grade).

• For example, software of high quality has no bugs, but may be low gradebecause it has limited features (such as Microsoft Calculator).

• Low quality is always a problem, low grade may not be.

• PM and his team are responsible for determining and delivering therequired levels of both quality and grade.

PMP Prep – Quality Slide 6

QUALITY PHILOSOPHIES

W. Edwards Deming • Workers need to be shown “what acceptable Quality is”

QUALITY PHILOSPHIESQUALITY PHILOSPHIES

Page 339: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 339/590

p y• Quality is a Management problem• Improve Leadership, drive out fear • Improve constantly and forever (continuous improvement)

• Started the TQM movement

Dr. Joseph Juran• Fitness to Use/Conformance• Quality & Grade• Trilogy: Quality Improvement, Planning & Control

PMP Prep – Quality Slide 7

QUALITY PHILOSPHIESQUALITY PHILOSPHIES

Phillip Crosby • Quality is ‘Free’

• ‘Right’ the First Time• Prevention is the ‘Key’

• Zero Defects

Page 340: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 340/590

Zero Defects

Kaizen Method or Technologies• Continuous improvement in small increments (continuous improvement

of people first, then products & services• Overall improvement, in life at work, the well-being

• Kaizen is a Japanese word that means gradual continuousimprovement

PMP Prep – Quality Slide 8

The International Organization for Standardization

• ISO 9001 is a quality standard that checks on the systems used by anorganization

• Quality Management System (QMS) is a systematic approach used

What’s A PMP?What’s A PMP?

ISOISO

Page 341: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 341/590

• Quality Management System (QMS) is a systematic approach usedto plan, manage and continually improve the quality of anorganization's products or services. It's a framework that directs and

ensures that controls are in place to achieve success in managementof a business.

• See www.iso.orgISO 14001 defines Environment standardOHSAS 18001 defines Health & Safety standard

PMP Prep – Quality Slide 9

QUALITY PROCESS DEFINITIONS

8.1 Plan Quality

• The process of identifying quality requirements and/or standards for the project & product, and documenting how the project willdemonstrate compliance.

What’s A PMP?What’s A PMP?

QUALITY PROCESSESQUALITY PROCESSES

Page 342: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 342/590

p

8.2 Perform Quality Assurance• The process of auditing the quality requirements and the results from

quality control measurements to ensure appropriate quality standardsand operational definitions are used

8.3 Perform Quality Control

• The process of monitoring and recording results of executing the

quality activities to assess performance and recommend necessarychanges.See Figure 8-3, p.193 for plan quality data flow diagram 

PMP Prep – Quality Slide 10

PROCESSES BY PROCESS GROUP

QUALITY PROCESSESQUALITY PROCESSES

Planning Executing Monitoring &

Page 343: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 343/590

PMP Prep – Quality Slide 11

Controlling

8.1

Plan Quality

8.2

Perform QualityAssurance

8.3

Perform QualityControl

PLAN QUALITY PLAN QUALITY 

WHAT YOU DO IN PLAN QUALITY?

•  The process of identifying quality requirements and/or standards for the

project & product and documenting how the project will demonstrate

Page 344: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 344/590

project & product, and documenting how the project will demonstratecompliance.

• Quality planning should be performed in parallel with the other projectplanning processes. For example, proposed changes in the product to

meet identified quality standards may require cost or scheduleadjustments and a detailed risk analysis of the impact to plans.

• The quality planning techniques discussed here are those mostfrequently used on projects. There are many others that may be usefulon certain projects or in some application areas.

PLAN QUALITY PLAN QUALITY 

TOOLS & TECHNIQUES• Cost-benefit analysis

•Cost of Quality• Control charts

• Benchmarking• Design of experiments

Page 345: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 345/590

 

PMP Prep – Quality Slide 13

INPUTS• Scope baseline

• Stakeholder register • Cost performance baseline

• Schedule baseline• Risk register • Enterprise environmental factors

• Organizational process assets

 

OUTPUTS• Quality management plan

• Quality metrics• Quality checklists

• Process improvement plan• Project document updates

• Statistical sampling• Flowcharting

• Proprietary quality mgmt.methodologies

• Additional quality planning tools

PLAN QUALITY -INPUTSPLAN QUALITY -INPUTS  INPUTS1. Scope Baseline

- Scope statement

- WBS

- WBS Dictionary

Page 346: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 346/590

2. Stakeholder Register 

It identifies stakeholders with a particular interest in, or impact on, quality.

3. Cost Performance Baseline

It documents the accepted schedule performance measures including

start and finish dates.

4. Schedule Baseline

It documents the accepted schedule performance measures includingstart and finish dates

PMP Prep – Quality Slide 14

PLAN QUALITY-INPUTSPLAN QUALITY-INPUTS

INPUTS

5. Risk Register   The risk register contains information on threats and

opportunities that may impact quality requirements

Page 347: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 347/590

pp y p q y q

6. Enterprise Environmental FactorsGovernmental agency regulations, rules, standards, and guidelines

specific to the application area may affect the project

7. Organizational Process AssetsOrganizational quality policies, procedures and guidelines, historicaldatabases and lessons learned from previous projects specific to theapplication area may affect the project

PMP Prep – Quality Slide 15

PLAN QUALITY – T&TPLAN QUALITY – T&T

TOOLS & TECHNIQUES

• Cost-Benefit Analysis

Q f ff

Page 348: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 348/590

• Quality planning must consider cost-benefit tradeoffs.

• The primary benefit of meeting quality requirements is less rework,

which means higher productivity, lower costs, and increasedstakeholder satisfaction.

• The primary cost of meeting quality requirements is the expenseassociated with Project Quality Management activities.

PMP Pre – Qualit Slide 16

PLAN QUALITY – T&TPLAN QUALITY – T&T•  Cost of Quality (COQ)

• Quality costs are the total costs incurred by investment in preventing non-conformance to requirements, appraising the product or service

for conformance to requirements, and failing to meet requirements(rework). Failure cost are categorized into internal or external (Failurecosts are also called cost of poor quality).

Page 349: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 349/590

y)

•  Examples of :Cost of Conformance

  Prevention - training, surveys, using a quality system, planning,recruiting quality staff, etc. Appraisal  - testing, inspecting, auditing, etc.Cost of non-conformance Internal - rework, rejects, etc.

External - warranty, recall, repairs, handling complaints, legal issues,loss of goodwill, etc.

PMP Prep – Quality Slide 17

PLAN QUALITY – T&TPLAN QUALITY – T&T

Control Charts

• Control charts are used to determine whether or not a process is stable or has predictable performance.

Page 350: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 350/590

p p

• They reflect the maximum and minimum values allowed.

• Control charts are used to monitor various types of output variables

• See Fig. 8-5 & Fig. 8-6(Page 196-197) – Read thoroughly

PMP Prep – Quality Slide 18

PLAN QUALITY – T&TPLAN QUALITY – T&T 

•Benchmarking• Comparing actual or planned project practices to those of other 

projects to generate ideas for improvement and to provide a basisby which to measure performance

• Design of Experiments

Page 351: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 351/590

• Design of Experiments• Statistical method that helps identify which factors may influence

specific variables of a product or process under development or 

production.• The most important aspect of this technique is that it provides a

statistical framework for systematically changing all of the important factors

• For example, automotive designers use this technique to determinewhich combinations of suspensions and tires will produce the most

desirable ride characteristics at a reasonable cost

PMP Prep – Quality Slide 19

PLAN QUALITY – T&TPLAN QUALITY – T&TStatistical Sampling• Statistical sampling involves choosing part of a population of 

interest for inspection• There is a substantial body of knowledge on statistical sampling.

In some application areas it may be necessary for the PM teamto be familiar with a variety of sampling techniques to assure the

Page 352: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 352/590

to be familiar with a variety of sampling techniques to assure thesample selected actually represents the population of interest.

Flowcharting• Graphical representation of a process showing the relationships

among process steps. Flowcharts show activities, decisionpoints, and the order of processing

• See Fig. 8-7 in Page 199.

PMP Prep – Quality Slide 20

PLAN QUALITY – T&TPLAN QUALITY – T&T

Proprietary Quality Mgmt. Methodologies

• These include Six Sigma, Lean Six Sigma, Quality FunctionDeployment, CMMI, etc.

Page 353: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 353/590

Additional Quality Planning ToolsThese include brainstorming, affinity diagrams, force fieldanalysis*, nominal group techniques, matrix diagrams,and prioritisation matrices.

* Identifies forces and factors, both restraining and driving,effecting the solution of an issue so that the positives canbe reinforced and negatives reduced or eliminated.

PMP Prep – Quality Slide 21

PLAN QUALITY – T&TPLAN QUALITY – T&T

  Quality Management Plan

• Describes how the PM team will implement the performing organization'squality policy (Quality management plan is a component or a subsidiaryplan of the project management plan).

Page 354: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 354/590

• Provides input to the overall Project Management Plan and mustaddress quality assurance, quality control and continuous processimprovement for the project.

• Quality management plan may be formal or informal, highly detailed or broadly framed, based on the requirement of the project.

• Should include efforts at the front end of the project to ensure thatearlier decisions (e.g. on concepts, designs, and tests) are correctThese efforts should be performed through an independent peer review and not include persons that worked on the material being

reviewed.

PMP Prep – Quality Slide 22

PLAN QUALITY – OUTPUTSPLAN QUALITY – OUTPUTS Quality Metrics

• A metric is an operational definition that describes, in very specific

terms, what something is and how the quality control processmeasures it.• Very specific (actual) measurable values to be met by a process,

activity or work result

Page 355: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 355/590

activity or work result.• For example, it is not enough to say that meeting the planned

schedule dates is a measurement of management quality. The PM

team must also indicate whether every activity must start on timeor only finish on time and whether individual activities will bemeasured, or only certain deliverables and if so, which ones.

• Quality metrics are used both in QA & QC processes.

Quality Checklists 

• Structured tool used by both QA and QC to verify a set of requiredsteps have been performed (usually component specific)

PMP Prep – Quality Slide 23

PLAN QUALITY – T&TPLAN QUALITY – T&T 

Process Improvement Plan

• It is subsidiary of the project management plan.• Details the steps for analysing processes that will facilitate the

identification of waste, error & non-value added activity, thusincreasing customer value

Page 356: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 356/590

increasing customer value.

• Examples of such steps are:

• Process boundaries: describes the purpose, start, and end of processes, their inputs & outputs, data required and the owner and stakeholder of the processes.

• Process configuration: a flowchart of processes to facilitateanalysis with interfaces identified

• Process metrics

• Targets for improved performance

PMP Prep – Quality Slide 24

PLAN QUALITY – T&TPLAN QUALITY – T&T

 Project Document Updates

Project documents that may be updated include but are not limited to:

Page 357: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 357/590

Project documents that may be updated include, but are not limited to:

• Stakeholder register, and

• Responsibility Assignment Matrix (Section 9.1.2.1)

PROCESSES BY PROCESS GROUP

QUALITY PROCESSESQUALITY PROCESSES

Planning Executing Monitoring &Controlling

Page 358: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 358/590

PMP Prep – Quality Slide 26

Controlling

8.1

Plan Quality

8.2

Perform QualityAssurance

8.3

Perform QualityControl

PERFORM QUALITY PERFORM QUALITY ASSURANCEASSURANCEHOW SHOULD YOU PERFORM QUALITYASSURANCE?

•  Quality assurance (QA) is application of planned, systematic qualityactivities to ensure the project will employ all processes needed tomeet requirements

Page 359: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 359/590

q

• QA uses the Process Improvement Plan to make project processes

better 

• A quality assurance department, or similar organization, oftenoversees quality assurance activities.

• QA also provides an umbrella for another important quality activity,

continuous process improvement (CPI). CPI provides an iterativemeans for improving the quality of all processes (improves in smallsteps over time)

PMP Prep – Quality Slide 27

PERFORM QUALITY PERFORM QUALITY ASSURANCEASSURANCE

TOOLS &TECHNIQUES

•  Plan Quality and Perform &Quality control tools &

techniques• Quality audits

Page 360: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 360/590

 

PMP Prep – Quality Slide 28

INPUTS• Project management plan

• Quality metrics• Work performance information• Quality control measurement

OUTPUTS• Organizational process

assets updates• Change requests

• Project management plan

(updates)• Project document updates

Q y• Process analysis

PERFORM QUALITY ASSURANCE-PERFORM QUALITY ASSURANCE-INPUTSINPUTS

INPUTS • Project Management Plan

• Quality Metrics

Page 361: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 361/590

• Quality Metrics

• Work performance information

• Quality Control MeasurementsQC measurements are the results of quality control activities thatis fed back to the QA process for use in re-evaluating andanalysing the quality standards and processes of the performing

organization

PMP Prep – Quality Slide 29 

PERFORM QUALITY PERFORM QUALITY ASSURANCE-T&TASSURANCE-T&TTOOLS &TECHNIQUES

• Plan Quality and Perform Quality Control tools and techniquesTools & techniques from Plan Quality and Perform Quality Control, discussed

in Section 8.1.2 and Section 8.3.2 (can also be used for that Quality Assurance activities.

• Quality Audits

Page 362: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 362/590

 Quality Audits• A structured, independent review to determine whether projectactivities comply with organizational & project policies, processes,

& procedures•The objective of a quality audit is to identify inefficient andineffective policies, processes, and procedures in use on theproject.• May be scheduled or at random• May be carried out by properly trained in-house auditors or thirdparties

• Quality audits confirm that approved change requests, correctiveactions, defect repairs & preventive actions are being implemented

PMP Prep – Quality Slide 30

PERFORM QUALITY PERFORM QUALITY ASSURANCE-T&TASSURANCE-T&T• Process Analysis

• Follows the steps outlined in the Process Improvement Plan toidentify needed improvements from an organizational and technicalstandpoint

• Examines problems & constraints experienced and non value

Page 363: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 363/590

• Examines problems & constraints experienced and non-value-added activities identified during process operation

• Uses root cause analysis, a specific technique to analyse a

problem/situation, determine the underlying causes that lead toit, and create preventive actions for similar problems

PERFORM QUALITY ASSURANCE-PERFORM QUALITY ASSURANCE-OUTPUTSOUTPUTS  OUTPUTS

• Organizational Process Assets Updatese.g. quality standards

• Change Requests 

Page 364: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 364/590

• Project Management Plan Updates- Quality mgmt. plan

- Schedule mgmt. plan- Cost mgmt. plan

• Project Document Updates- Quality audit reports- Training plans- Process documentation

PMP Prep – Quality Slide 32

PROCESSES BY PROCESS GROUP

QUALITY PROCESSESQUALITY PROCESSES

Planning Executing Monitoring &Controlling

Page 365: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 365/590

PMP Prep – Quality Slide 33

Controlling

8.1

Quality Planning

8.2

Perform QualityAssurance

8.3

Perform QualityControl

PERFORM QUALITY CONTROLHOW DO YOU PERFORM QUALITY CONTROL?

• Use the Quality Management Plan to monitor specific project resultsto determine whether they comply with relevant quality standards(metrics) for both project & product quality

Page 366: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 366/590

(metrics) for both project & product quality

• Identify ways to eliminate causes of unsatisfactory results.

• It should be performed throughout the project

• QC is performed by a Quality Control Department

•The PM team should have a working knowledge of statistical qualitycontrol, especially sampling & probability

PERFORM QUALITY PERFORM QUALITY CONTROLCONTROL

TOOLS &TECHNIQUES

• Cause and effect diagram• Control charts

• Flowcharting• Histogram• Pareto chart

• Run chart• Scatter diagram

Page 367: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 367/590

 

PMP Prep – Quality Slide 35

INPUTS• Project management plan

• Quality metrics• Quality checklists

• Work performance information• Approved change requests• Deliverables

• Organizational process assets

OUTPUTS• Quality control measurements

• Validated changes• Validated deliverables

• Organization process assets updates

• Change Requests• Project management plan updates

• Project document updates

Scatter diagram• Statistical sampling

• Inspection• Approved change requests review

PERFORM QUALITY CONTROLKnow the difference between:

Prevention (keeping errors out of the process); Inspection (keepingerrors out of the hands of the customer)

Attribute sampling (result conforms, or it doesn't); Variables sampling( the result is rated on a continuous scale that measures the degree of

Page 368: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 368/590

( the result is rated on a continuous scale that measures the degree of conformity); Statistical sampling (measures only a percentage of items,e.g. 5 out of every 100)

 Special causes (unusual events); Common or random causes (normalprocess variation) Tolerances (the result is acceptable if it falls within range specified bytolerance); Control limits (the process is in control if the result fallswithin the control limits)

PMP Prep – Quality Slide 36

PERFORM QUALITY CONTROL-INPUTS

INPUTS

 

•Project Management Plan•Quality Metrics•Quality Checklists

Page 369: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 369/590

•Work Performance Information•Approved Change Requests

•Deliverables•Organizational Process Assets

PMP Prep – Quality Slide 37

PERFORM QUALITY CONTROL-T&TTOOLS & TECHNIQUES

• Cause and Effect Diagram• Also called Ishikawa (inventor) or fishbone diagrams• Below is an example to show how various factors might be linked

to potential problems or effects

Page 370: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 370/590

p p

PMP Prep – Quality Slide 38

PERFORM QUALITY PERFORM QUALITY CONTROL-T&TCONTROL-T&T • Control Charts (See Figure 8-5 & 8-6, p.196-7)

• Shows whether or not a process is stable or has predictable performance over a period of time

• Stable or Predictable – normal (no action required)

Page 371: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 371/590

Stable or Predictable – normal (no action required)• Out of control – process is subject to special cause variation

and (needs to be fixed) 

• used for repetitive activities like manufacturing

• a graphic display of the interaction of process variables on aprocess ( Are the process variables within acceptable limits?)

 

PMP Prep – Quality Slide 39

PERFORM QUALITY PERFORM QUALITY CONTROL-T&TCONTROL-T&T

• A process is out of control if the values are:

  • widely fluctuating values (outside the control limits set)• suddenly jumps or shifts• gradually increasing variation (trend)

Page 372: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 372/590

g y g ( )

‘Rule of Seven' which is when 7 values in a row are all below or all

above the mean or increase/decrease in direction

• For processes outside acceptable limits, the process shouldbe adjusted ( the upper & lower limits are usually set at +/-3sigma, where sigma is standard deviation)

PMP Prep – Quality Slide 40

PERFORM QUALITY PERFORM QUALITY CONTROL-T&TCONTROL-T&T• Flowcharting

• Helps to analyse how problem occur 

• A flowchart is a graphical representation of a process

Page 373: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 373/590

• There are many styles, but all flowcharts activities,decision points, and the order of processing

• See Figure 8-8, an example of a process flowchart for design reviews

PERFORM QUALITY PERFORM QUALITY CONTROL-T&TCONTROL-T&T • Histogram  - A bar chart showing a distribution of variables

- Each column represents an attribute or characteristicso that one can compare two or more things

- Height of each column represents the frequency (or amount) of a

Page 374: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 374/590

characteristic 

PMP Prep – Quality Slide 42

PERFORM QUALITY PERFORM QUALITY CONTROL-T&TCONTROL-T&T Pareto Chart 

• A Pareto chart is a specific type of histogram, ordered byfrequency of occurrence

• The Pareto technique is used primarily to identify and evaluatef i i

Page 375: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 375/590

nonconformities• In Pareto diagrams, rank ordering is used to guide corrective action

• The project team should take action to fix that problem first, whichare causing the greatest number of defects

• Pareto diagrams are conceptually related to Pareto’s Law, whichholds that a small number of causes will typically produce a largemajority of the problems or defects

• Pareto's Law is commonly referred as the 80/20 principle, where80 percent of the problems are due to 20 percent of the causes

PERFORM QUALITY PERFORM QUALITY CONTROL-T&TCONTROL-T&T

Page 376: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 376/590

PMP Prep – Quality Slide 44

PERFORM QUALITY PERFORM QUALITY CONTROL-T&TCONTROL-T&TRun Chart • A run chart shows the history and pattern of variation• A run chart is a line graph that shows data points plotted in order in

which they occur (over time)

• Run charts show trends in a process over time, variation over time,or declines or improvements in a process over time

• Trend analysis is performed using run charts• Trend analysis is using mathematical techniques to forecast future

Page 377: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 377/590

Trend analysis is using mathematical techniques to forecast futureoutcomes based on historical results

• Trend analysis is often used to monitor technical performance;

project cost & schedule performance.

 Scatter Diagram • Shows the pattern of relationship between two variables• This tool allows the quality team to study and identify the possible

relationships between changes observed in two variables• The closer the points are to a diagonal line, the more closely they'rerelated

PMP Prep – Quality Slide 45

PERFORM QUALITY PERFORM QUALITY CONTROL-T&TCONTROL-T&T• Statistical Sampling

• Involves choosing part of a population of interest for inspection(For example, select 10 widgets at random out of 100)

• Inspection• Examination of a work product to determine if it conforms to

standards

Page 378: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 378/590

standards• Generally, the results of an inspection include measurements• Inspection can be conducted at any level, for example, the results of 

a single activity can be inspected, or final product of the project canbe inspected

• Inspections are also called reviews, peer reviews, audits, andwalkthroughs

• Approved Change Requests Review• All approved change requests should be reviewed to verify that they

were implemented as approved.

PMP Prep – Quality Slide 46

PERFORM QUALITY CONTROL-PERFORM QUALITY CONTROL-

OUTPUTSOUTPUTS

OUTPUTS

• Quality Control Measurements• Quality control measurements are documented results of 

lit t l ti iti i th f t ifi d d i lit

Page 379: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 379/590

quality control activities in the format specified during qualityplanning.

• Validated Changes • Any changed or repaired items are inspected & will be either accepted or rejected before notification of the decision isprovided. The rejected items may require rework. 

PMP Prep – Quality Slide 47

PERFORM QUALITY CONTROL-PERFORM QUALITY CONTROL-OUTPUTSOUTPUTS

•  Validated Deliverables

• Organizational Process Assets Updates• Completed checklists• Lessons learned documentation i e causes of variances

Page 380: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 380/590

• Lessons learned documentation, i.e. causes of variances,reasoning behind the corrective action chosen 

•  Change Requests

• Project Mgmt. Plan Updates

• Project Document Updates

PMP Pre – Qualit Slide 48

STANDARD DEVIATION-STANDARD DEVIATION-Slide 1Slide 1Accuracy Measurement 

Standard deviations from the mean (or average):+/-1 (on both sides of the mean) = 68.3% : (1sigma)+/-2 =95.5% : (2 sigma)+/-3 =99.7% : (3 sigma)

Page 381: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 381/590

+/-6 =99.9% : (6 sigma)

Sigma andStandardDeviationare the same

PMP Prep – Quality Slide 49

STANDARD DEVIATION-STANDARD DEVIATION-Slide2Slide2Formulas:

Mean (u)/Average = (sum the data, and then divide by the number of items)= 31 / 6 = 5.17

Page 382: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 382/590

Variance (a 2) - how spread out a distribution of data is (bothsides of mean)

 =E ( ( x - u ) 2) -where x is, each sample data, i.e. 4.9 on then -1

next slide and n is the number of samples (6)

= 0.2334 =0.04668

6-1

PMP Prep – Quality Slide 50

STATISTICAL STANDARDSTATISTICAL STANDARDDEVIATIONDEVIATION

Page 383: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 383/590

PMP Prep – Quality Slide 51

STATISTICAL STANDARDSTATISTICAL STANDARDDEVIATIONDEVIATION

Page 384: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 384/590

PMP Prep – Quality Slide 52

SAMPLE EXAM QUESTIONSAMPLE EXAM QUESTION

Question

All the following are true about 'Quality' and 'Grade' except:

 A. A low quality product may be of high gradeB A low grade product may be of high quality

Page 385: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 385/590

B. A low grade product may be of high qualityC. It is a problem if either the product is low grade or low quality

D. Grade is a rank given to entities having the same functionalusebut different technical characteristics

SAMPLE EXAM QUESTIONSAMPLE EXAM QUESTIONThe answer is C.

Quality is "the degree to which a set of inherent characteristics fulfilrequirements".

Grade is a category assigned to products or services having the same

Page 386: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 386/590

functional use but different technical characteristics.

Low quality is always a problem, low grade may not be.PMBOK, p.18D.

 PMP Prep – Quality Slide 54

Questions?Questions?

Page 387: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 387/590

PMP Prep – Quality Slide 55

DAY 4

CHAPTER 9

Page 388: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 388/590

 PMP Prep – HR Slide 1

PROJECT HUMAN RESOURCEMANAGEMENT

AGENDAAGENDA 

Day 1  DAY 3  PMP Exam Prep Introduction Project TIME Management

Project Management Framework Project COST Management*Introduction Project

COMMUNICATION Management*Project Life Cycle & Organisation

P j t M t P

Page 389: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 389/590

Project Management Processes

  DAY 2  DAY 4  Project INTEGRATION Management Project QUALITY  Management

Project SCOPE Management Project RISK Management

Project HUMANRESOURCE Management

  DAY 5 Project

PROCUREMENT ManagementProfessional & Social

PROJECT HUMAN RESOURCEPROJECT HUMAN RESOURCEMANAGEMENTMANAGEMENT WHAT DOES THE HUMAN RESOURCE KNOWLEDGE AREA DO? 

Organize & manage the project team (also referred to as project staff)

• The project team comprises of the people who have assigned roles andresponsibilities for completing the project (who report directly or indirectly to the Project Manager and perform the project work).

• Team members should be involved in much of the project’s planning and

Page 390: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 390/590

p j p gdecision-making.

• Early involvement of team members adds expertise during the planningprocess and strengthens commitment to the project.

• The Project Management Team is a subset of the project team and isresponsible for project management activities such as planning,controlling, and closing.

• Project sponsor works with project management team , typically

assisting with matters such as project funding , clarifying scopequestions , and influencing other in order to benefit the project.

PMP Prep – HR Slide 2

HUMAN RESOURCEHUMAN RESOURCEPROCESSESPROCESSES

HUMAN RESOURCE PROCESS DEFINITIONS 

9.1 Develop Human Resource Plan

• Identifying & documenting project roles, responsibilities & reportingrelationships, as well as creating the Staffing Management Plan

9.2 Acquire Project TeamObt i l d d t l t th j t

Page 391: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 391/590

• Obtain people needed to complete the project

9.3 Develop Project Team• Improve competencies & interaction of team members to enhance

project performance

9.4 Manage Project Team• Track team member performance, provide feedback, resolve issues &

coordinate changes to enhance project performance

See Figure 9-3, p.218 for human resource plan data flow diagram

PMP Prep – HR Slide 3

HUMAN RESOURCEHUMAN RESOURCEPROCESSESPROCESSESProcesses by process group

Planning Executing

9.1

Develop Human ResourcePlan

9.2

Acquire Project Team

Page 392: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 392/590

PMP Prep – HR Slide 4

9.3

Develop Project Team

9.4

Manage Project Team

DEVELOP HUMANDEVELOP HUMANRESOURCE PLANRESOURCE PLAN

WHAT DOES ‘DEVELOP HUMAN RESOURCE

PLAN’ DO?

• Identifies & documents project roles, responsibilities, and requiredskills reporting relationships and

Page 393: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 393/590

skills, reporting relationships, and

• Creates a staffing management plan• can include how & when project team members will be acquired(the persons can be from inside or outside the performing org.)

• criteria for releasing them from the project• Identification of training needs• Plans for recognition & rewards

• Compliance considerations (e.g. labour laws), safety issues (e.g.workman's safety

DEVELOP HUMANDEVELOP HUMANRESOURCE PLANRESOURCE PLAN

TOOLS & TECHNIQUES• Organization charts &

position descriptions• Networking

• Organizational theory

Page 394: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 394/590

 

PMP Prep – HR Slide 6

INPUTS• Activity resource

requirements• Enterprise environmental factors• Organizational process assets

OUTPUTSHuman Resource Plan

DEVELOP HUMAN RESOURCE PLANDEVELOP HUMAN RESOURCE PLAN

- INPUTS- INPUTS

   Activity Resource Requirements

  The preliminary requirements regarding the required people and

competencies for the project team members are progressivelyelaborated as part of human resource planning process (Section

Page 395: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 395/590

elaborated as part of human resource planning process (Section

6.3.3.1 of PMBOK)

PMP Prep – HR Slide 7

DEVELOP HUMAN RESOURCEDEVELOP HUMAN RESOURCEPLAN - INPUTSPLAN - INPUTS

Enterprise Environmental Factors

The enterprise environmental factors (section 1.8) that caninfluence the Develop Human Resource Plan process include, butare not limited to:

Page 396: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 396/590

• Organizational culture and structure,

• Existing human resources,• Personnel administration policies, and• Marketplace conditions

PMP Prep – HR Slide 8

DEVELOP HUMAN RESOURCEDEVELOP HUMAN RESOURCEPLAN - INPUTSPLAN - INPUTS

Organizational Process Assets

• Organizational standard processes and policies andstandardized role descriptions,

Page 397: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 397/590

p , 

• Templates for organizational charts and positiondescriptions, and

• Historical information on organizational structures

that have worked in previous projects

PMP Prep – HR Slide 9

DEVELOP HUMAN RESOURCEDEVELOP HUMAN RESOURCE

PLAN – T&TPLAN – T&T

TOOLS & TECHNIQUES

Organization Charts & Position DescriptionsUsed to ensure each work package has an unambiguous owner & that allteam members have a clear understanding of their roles & responsibilities(See Figure 9-4, p.205 shows three different types of chart)

Page 398: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 398/590

Hierarchical- type charts

Organizational breakdown structure (OBS) - looks similar to WBS,but is broken down by organisation’s existing departments, units or teams

Resource breakdown structure (RBS)  – another hierarchical chartbroken down by types of resources, e.g. welders, graphic designers, etc.

RBS can help tracking project costs, and can be aligned with theorganization’s accounting system (RBS can contain resource categoriesother than human resources).

PMP Prep – HR Slide 10

DEVELOP HUMAN RESOURCEDEVELOP HUMAN RESOURCE

PLAN – T&TPLAN – T&T

Matrix-based charts 

Responsibility assignment matrix (RAM) is used to shows connectionsbetween work & people. See Figure 9-5, p.206, is a type of RAM called aRACI chart (responsible, accountable, consult, inform)

Text-oriented formats

Page 399: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 399/590

Detailed job or position descriptions; documents that provide informationsuch as responsibilities, authority, competencies, and qualifications; etc.

Other sections of the project management planSome responsibilities related to managing the project are listed andexplained in other sections of the project management plan. For example,the risk register lists risk owners, the communication plan lists teammembers responsible for communication activities.

PMP Prep – HR Slide 11

DEVELOP HUMAN RESOURCEDEVELOP HUMAN RESOURCE

PLAN – T&TPLAN – T&T

Networking

•Informal interaction with others is an effective way to understandpolitical & interpersonal factors that will impact the effectiveness of staffing options

• Include proactive correspondence, luncheon meetings, informalconversations, and trade conferences

Page 400: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 400/590

conversations, and trade conferences

Organizational Theory

• Provides information regarding the ways people, teams &organizational units behave.

• Helps managing people & groups; includes motivational theories

PMP Prep – HR Slide 12

DEVELOP HUMAN RESOURCE PLAN –DEVELOP HUMAN RESOURCE PLAN –

OUTPUTSOUTPUTSOUTPUTS

Roles & Responsibilities

List include:Role  – the label describing the portion of a project for which a person isaccountable; examples of project roles are business analyst, electricalengineer, testing coordinator, etc.

Page 401: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 401/590

 Authority – The right to apply project resources, make decisions & signapprovals (members work best with authority matching their 

responsibility)

Responsibility   – The work that a project team member is expected toperform in order to complete the project activitiesCompetency – The skill & capacity needed to complete project activities

Project Organization ChartsGraphic display of project team members & their reporting relationships

PMP Prep – HR Slide 13

DEVELOP HUMAN RESOURCE PLAN –DEVELOP HUMAN RESOURCE PLAN –

OUTPUTSOUTPUTSStaffing Management Plan

• Describes when & how human resource requirements will be met

• May be tied with Procurement processes• Includes: 

• Staff acquisition  – from internal/external contracted sources; needto work in a central location or can they work from distant locations

Page 402: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 402/590

to work in a central location or can they work from distant locations,costs associated with each level of expertise , HR department’s

assistance to project management team, etc.

• Timetable - describes necessary time frames for project teammembers, either individually or collectively, as well as whenacquisition activities such as recruiting should start. One tool for charting human resources is a resource histogram (see Fig 9-6)

PMP Prep – HR Slide 14

RESOURCE HISTOGRAMRESOURCE HISTOGRAM

Page 403: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 403/590

 PMP Prep – HR Slide 15

DEVELOP HUMAN RESOURCE PLAN –DEVELOP HUMAN RESOURCE PLAN –

OUTPUTSOUTPUTSStaffing Management Plan (contd.)

Staff Release plan - method & timing of releasing team members

Training Needs  – If the team members to be assigned are not expectedto have the required competencies, a training plan can be developed aspart of the project. The plan can also include ways to help team membersobtain certifications that would support their ability to benefit the project

Page 404: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 404/590

pp y p j

Recognition & rewards - criteria for recognition and rewards areplanned; awarded as part of the Develop Project Team process

Compliance - Government regulations, union contracts & HR policies

Safety – policies & procedures that protect team members from safety

hazards

PMP Prep – HR Slide 16

HUMAN RESOURCEHUMAN RESOURCE

PROCESSESPROCESSESProcesses by process group

Planning Executing

9.1

Develop Human Resource Plan9.2

Acquire Project Team

Page 405: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 405/590

PMP Prep – HR Slide 17

9.3

Develop Project Team

9.4

Manage Project Team

ACQUIRE PROJECT TEAMACQUIRE PROJECT TEAM

HOW SHOULD YOU ACQUIRE YOUR PROJECT TEAM? 

•  A project team can be acquired by :

• Pre-assignment (known in advance)• Negotiation (staff assignments are negotiated on many projects

Page 406: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 406/590

inside the performing organization)

• Acquisition (from outside the performing organization)• Virtual Teams (groups of people with a shared goal, placed atdifferent locations)

• Project Manager may or may not have control over whichmembers are selected 

PMP Prep – HR Slide 18

ACQUIRE PROJECT TEAMACQUIRE PROJECT TEAM

TOOLS & TECHNIQUES• Pre-assignment

• Negotiation• Acquisition

• Virtual teams

Page 407: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 407/590

 

INPUTS• Project mgmt. plan• Enterprise environmental

factors• Organizational process

assets

OUTPUTS• Project Staff assignments

• Resource calendars• Project management plan

(updates)

ACQUIRE PROJECT TEAM-ACQUIRE PROJECT TEAM-

INPUTSINPUTS

INPUTS

Project Management Plan

Enterprise Environmental Factors • Project team members are drawn from all available sources, both

internal & external• When PM team is able to influence or direct staff assignments,

h t i ti t id i l d

Page 408: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 408/590

characteristics to consider include:

• Availability (Who is available & when they're available?)•  Ability (What competencies do they possess?)•  Experience (Do people have similar experience? Have they done

it well? )•  Interests (Are people interested in working on this project?)•  Cost (How much will each team member be paid?)

PMP Prep – HR Slide 20

ACQUIRE PROJECT TEAM-ACQUIRE PROJECT TEAM-

INPUTSINPUTS Organizational Process Assets

HR department (policies, guidelines, or procedures governingstaff assignments)

Page 409: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 409/590

 

PMP Prep – HR Slide 21

ACQUIRE PROJECT TEAM-ACQUIRE PROJECT TEAM-

T&TT&T

TOOLS & TECHNIQUES

Pre-AssignmentSpecific people may be promised as part of a competitive proposal, if theproject is dependent on expertise of particular persons. Some staff assignments are defined within the Project Charter 

Page 410: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 410/590

NegotiationPM team uses their influencing skills to obtain staff members from withinthe performing organisation. May need to negotiate with

• Functional managers• Other project management teams

PMP Prep – HR Slide 22

ACQUIRE PROJECT TEAM-ACQUIRE PROJECT TEAM-T&TT&T

Acquisition• Required services can be acquired from outside sources when the

performing organization lacks in-house staff.

Virtual Teams• People with a shared goal who perform with little or no face to face

meetings

Page 411: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 411/590

• Benefit from e-mail & video conferencing; must plan communicationscarefully

• Virtual team format makes it possible to:• Form teams from widespread geographic areas• Add special expertise to a project team, even though the expert is

not in the same geographic area• Incorporate employees who work from home offices

• Form teams of people who work different shifts or hours• Include people with mobility handicaps• Move forward with projects otherwise ignored due to travel

expenses PMP Prep – HR Slide 23

ACQUIRE PROJECT TEAM-ACQUIRE PROJECT TEAM-OUTPUTSOUTPUTS

OUTPUTSProject Staff Assignments• Project is staffed when appropriate people are assigned to work on it• Documentation can include a project team directory, memos to

team members, and names inserted into other parts of projectmanagement plan (such as organization charts & schedules)

Page 412: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 412/590

Resource Calendars

• Documents the time periods (or calendar) each project teammember can work on the project

• Creating a reliable final schedule depends on having a goodunderstanding of each person’s schedule conflicts, includingvacation time and commitments to other projects

Project Management Plan (Updates)• Elements of project mgmt. plan that may be updated include, but are

not limited to the human resources plan

PMP Prep – HR Slide 24

HUMAN RESOURCEHUMAN RESOURCEPROCESSESPROCESSES

Processes by process group

Planning Executing

9.1

Develop Human ResourcePlan

9.2

Acquire Project Team

9 3

Page 413: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 413/590

PMP Prep – HR Slide 25

9.3

Develop Project Team9.4

Manage Project Team

DEVELOP PROJECT TEAMDEVELOP PROJECT TEAMHOW DO YOU DEVELOP YOUR PROJECT TEAM?

Improve the competencies and interaction of team members to enhanceproject performance. Objectives include:

a) Improve skills of team members in order to increase their ability tocomplete project activities

b) Improve feelings of trust & cohesiveness among team members so as

Page 414: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 414/590

b) Improve feelings of trust & cohesiveness among team members so asto raise their productivity through greater team-work

c) Develop the team early to realize greater benefits

Examples of effective teamwork:• Assisting each other when workloads are unbalanced• Communicating in ways that fit individual preferences

• Sharing information & resources

PMP Prep – HR Slide 26

DEVELOP PROJECT TEAMDEVELOP PROJECT TEAM

TOOLS & TECHNIQUES• Interpersonal skills

• Training• Team Building Activities

• Ground Rules• Co-location

• Recognition and rewards

Page 415: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 415/590

 

PMP Prep – HR Slide 27

INPUTS• Project staff assignments• Project management plan

• Resource calendars

OUTPUTS• Team Performance

Assessment • Enterprise environmental

factors updates

DEVELOP PROJECT TEAM-DEVELOP PROJECT TEAM-INPUTSINPUTS

INPUTS

Project Staff Assignments

Project Management Plan

Page 416: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 416/590

Resource Calendars

PMP Prep – HR Slide 28

DEVELOP PROJECT TEAM-DEVELOP PROJECT TEAM-T&TT&T

TOOLS & TECHNIQUES 

Interpersonal Skills

Interpersonal skills, sometimes known as "soft skills" are particularlyimportant to team development. Understanding the sentiments of teammembers, anticipating their actions, acknowledging their concerns andfollowing up on their issues can greatly reduce problems and increasecooperation.Skills such as: empathy influence creativity group facilitation are

Page 417: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 417/590

Skills such as: empathy, influence, creativity, group facilitation arevaluable assets when managing the project team

Training Activities designed to enhance the competencies of the project teammembers. Example of training methods include:Classroom, online, computer-based, on-the-job training from another project team member, mentoring, and coaching from other team

members (Training includes diversity/cultural training as well)

PMP Prep – HR Slide 29

DEVELOP PROJECT TEAM-DEVELOP PROJECT TEAM-T&TT&T

Team-Building Activities• Could be

• a ten minute agenda item in a status review meeting• an off-site, professionally facilitated experience designed to

improve interpersonal relationships• some group activities, although not specifically designed for team

building, like developing a WBS (can increase team cohesiveness) 

E i f l i i & i i i

Page 418: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 418/590

• Encourage informal communication & activities

• Team building strategies are particularly valuable when teammembers operate from remote locations• Five stages of team development (explained later)

Ground Rules• Establish clear expectations regarding acceptable behaviour by

project team members to decrease misunderstandings & increase

productivity

PMP Prep – HR Slide 30

DEVELOP PROJECT TEAM-DEVELOP PROJECT TEAM-T&TT&T

Co-Location• Placing many or all of the most active team members in the same

physical location enhances their ability to perform as a team

• Can be temporary, only at strategically important times in the project• Co-location strategy can include a meeting room ("war room") with

electronic communication devices and other conveniences thatenhance communication and a sense of community

 Recognition and Rewards

Page 419: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 419/590

g• The original plans concerning ways to reward people are developed

during Human Resource Planning.• Process involves recognizing & rewarding only desirable behaviour,

e.g. need to work overtime because of poor planning should not berewarded (undesirable behaviour)

• Win-lose (zero sum) rewards that only limited number of project teammembers can achieve, e.g. employee of the month etc. (can hurt team

cohesiveness)• Rewarding win-win behaviour that everyone can achieve tends to

increase support among team members

PMP Prep – HR Slide 31

DEVELOP PROJECT TEAM-DEVELOP PROJECT TEAM-OUTPUTSOUTPUTS

OUTPUTS

Team Performance Assessment

Informal or formal evaluation of a team's effectiveness can includeindicators like:• Improvements in skills that allow a person to perform assigned

activities more effectively

Page 420: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 420/590

activities more effectively• Improvement in competencies and sentiments that help team

perform better as a group• Reduced staff turnover rate

Enterprise Environmental Factors Updates

PMP Prep – HR Slide 32

TYPES OF POWERPower is the potential ability to influence behaviour to get peopleto do things they would not normally do.

Types of Power  

Legitimate (Formal) -based on actual or perceived position e.g. boss or boss‘s spouse

Coercive based on fear of punishment (normally used as the last resort)

Page 421: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 421/590

Coercive-based on fear of punishment (normally used as the last resort)

Reward -based on reward possibility (great to use). To be effective,rewards should be based on activities & performance under a person'scontrol. Must have a clear criteria with a planned system of evaluation.Must be awarded in public.

Expert –Exert power based on your expertise or knowledge (great to

use)

Referent - Ability to influence other through charisma

PMP Prep – HR Slide 33

Page 422: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 422/590

TYPE OF ROLES PLAYED BY PROJECT TEAMTYPE OF ROLES PLAYED BY PROJECT TEAMMEMBERSMEMBERS

Supportive  Destructive

Initiators Aggressor  

Information Seekers Dominator  

Information Givers Devil’s Advocate

Encouragers Topic Jumper

Page 423: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 423/590

 PMP Prep – HR Slide 35

Encouragers Topic Jumper  

Clarifiers Recognition Seeker 

Harmonizers Withdrawer  

Consensus Takers Blocker 

Gate Keepers

MANAGEMENT STYLESMANAGEMENT STYLESAutocratic Management by authority vs Consensus

Good For Weakness

Mature, well-defined projects Limits staff bye-in leading to low morale

When quick decisions are needed Possible arbitrary decision

Page 424: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 424/590

 PMP Prep – HR Slide 36

Laissez-Faire – Meaning “to let do”- Minimal or no interference by authority

Good For Weakness

Innovative projects Confusion about project objectives

Projects with high morale, self-motivated staff – promotes creativity Inability to make decisions

MASLOW’S HIERARCHY OF NEED

Page 425: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 425/590

 PMP Prep – HR Slide 37

MANAGEMENT THEORIES

MANAGEMENT THEORIES 

McGregor's Theory

Theory X• Workers viewed as inherently self-centred, lazy

T diti l i f t t d

Page 426: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 426/590

• Traditional view of management; top-down .

• Managers control & micromanage the workers

Theory Y• People will perform their best if they are properly motivated• Workers viewed as willing & eager to accept responsibility• Managers create environment that aids workers in achieving goals

PMP Prep – HR Slide 38

MANAGEMENT THEORIES

Page 427: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 427/590

 PMP Prep – HR Slide 39

MANAGEMENT THEORIESMANAGEMENT THEORIESHYGIENE FACTORS

•  Absence of proper hygiene factors are linked to dissatisfactionat the work-place. Examples of Hygiene factor are:

• company policies & job security• pay, remuneration, salaries• working conditions• supervision

Page 428: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 428/590

supervision

 MOTIVATING FACTORS

•  When they exist, team members have a good time at their place of work. It includes,

• sense of achievement & recognition for things done

• opportunity for growth & advancement• responsibility & stimulating work

PMP Prep – HR Slide 40

HUMAN RESOURCEHUMAN RESOURCEPROCESSESPROCESSES

Processes by process group

Planning Executing

9.1Develop Human Resource

Plan

9.2Acquire Project Team

9.3

Page 429: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 429/590

PMP Prep – HR Slide 41

Develop Project Team9.4

Manage ProjectTeam

MANAGE PROJECT TEAMMANAGE PROJECT TEAM

HOW SHOULD YOU MANAGE YOUR PROJECT TEAM?

• Track & appraise team member performance• Provide feedback• Observe team behaviour, manage conflict & resolve issues• Coordinate changes to enhance project performance• As a result of managing the project team, staffing management plan

Page 430: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 430/590

is updated, change requests are submitted, issues are resolved, input

is given to organizational performance appraisals, and lessonslearned are added to the organization’s database.

• Management of the project team is complicated when teammembers are accountable to both a functional manager and theproject manager within a matrix organization

• Effective management of this dual reporting is often a critical

success factor for the project, and is generally the responsibility of the project manager 

PMP Prep – HR Slide 42

MANAGE PROJECT TEAMMANAGE PROJECT TEAM

TOOLS & TECHNIQUES• Observation & conversation

•Project performanceappraisals

• Conflict management• Issue log

• Interpersonal skills

Page 431: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 431/590

 

 –

INPUTS• Project staff assignments• Project management plan

• Team performance assessment• Work performance information

• Performance reports

• Organizational processassets

OUTPUTS• Enterprise environmental

factors updates• Organization process assets

(updates)• Change Requests

• Project management plan(updates)

FORMS OFCOMMUNICATION

 

Form of Communicati

on

Characteristics

Examples

Written Formal• Precise• Transmitted

throughmedium

of correspondence

• Project charter, Scope statement,

project plan, WBS, project status• Complex issues• Contract related communication

Page 432: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 432/590

Written informal • Emails, notes, memos, letters• Regular communication withteam member

Oral Formal • High degree of flexibility

• Personalcontact,

group meetingsortelephone

• Presentations, Speeches• Negotiations, conflict resolution

Oral Informal • Conversation with team members• Pro ect meetin s

MANAGE PROJECT TEAM –INPUTS

 

•  Project staff assignments

• Project Management Plan

• Team performance assessments

• Performance Reports

Page 433: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 433/590

• Organizational Process Assets

PMP Prep – HR Slide 45

MANAGE PROJECT TEAM –T&T

 Observation and Conversation

• Stay in touch with the work & attitudes of project team members• The PM team members monitors indicators such as :

• progress toward project deliverables• accomplishments that are source of pride for team members• interpersonal issues

Page 434: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 434/590

Issue Log

 As issues arise in course of managing the project team, a writtenlog can document persons responsible for resolving specificissues by a target date

PMP Prep – HR Slide 46

MANAGE PROJECT TEAM –T&T

TOOLS & TECHNIQUES

Project Performance Appraisals

•  Need for formal or informal appraisals depends on length andcomplexity of project, organizational policy, labour contractrequirements, and the amount and quality of regular communication

• Evaluation information can be gathered from people who interactwith project team members using 360-degree feedback principles

Page 435: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 435/590

(where feedback is provided to the person being evaluated from many

sources, including superiors, peers & subordinates)

• Objectives for conducting performance appraisals include:• Re-clarification of roles & responsibilities• Structured time for team members receive positive feedback in what

might otherwise be a hectic environment• Discovery of unknown or unresolved issues• Development of individual training plans• Establishment of specific goals for future time period

PMP Prep – HR Slide 47

MANAGE PROJECT TEAM –T&T

Conflict Management• Successful conflict management results in greater productivity and

positive working relationships

• Common sources of conflict include scarce resources, schedulingpriorities & personal working styles

• Conflict reduction techniques include team ground rules, groupnorms, and solid project management practices, like communicationplanning & role definition

Page 436: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 436/590

• Differences of opinion can be healthy, can lead to increased creativity

and better decision-making, if managed properly

When the differences become a negative factor: • project team members are initially responsible for solving their own

conflicts• if escalates, then PM should help facilitate a satisfactory resolution• conflicts should be addressed early, usually in private, using a direct

& collaborative approach

PMP Prep – HR Slide 48

MANAGE PROJECT TEAM –T&T

Conflict Resolution Techniques 

•  Forcing (Win/lose) - one person forces solution on the other parties

•  Smoothing (accommodating) (lose/lose) - attempts are made tomake conflict appear less important than it is

Page 437: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 437/590

•  Compromise (negotiating) (neutral/neutral) - each party gives up

something to reach a solution

•  Withdrawal (avoiding) (lose/lose) - one party gives up & refuses todiscuss the conflict, which is probably the worst technique

•  Confrontation (collaboration/problem solving) (win/win) - the onlytrue and best solution -a fact finding mission results in somepossible solutions which are chosen from

PMP Prep – HR Slide 49

MANAGE PROJECT TEAM

– T&TIssue Log

  Issues arise in course of managing project team. A written log documents

and helps monitor who is responsible for resolving specific issues by atarget date. Issue resolution addresses obstacles that can block the teamfrom achieving its goals.

I t l Skill

Page 438: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 438/590

Interpersonal Skills

  Project managers uses combination of technical, human, andconceptual skills to analyze situations and interact appropriatelywith team members. This aids PM capitalizing on the strengths of allteam members (read Appendix F in PMBOK).

PMP Prep – HR Slide 50

MANAGE PROJECT TEAM –OUTPUTS

OUTPUTS

Enterprise Environmental Factors UpdatesEEF that may require updates as a result of the Manage

Project Team process include, but are not limited to:Input to organizational performance appraisals, and

Personnel skill updates

  Organizational Process Assets (Updates)

Organizational process assets that may require updates as a

Page 439: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 439/590

Organizational process assets that may require updates as a

result of the Manage Project Team process include, but arenot limited to:- Historical information and lessons learned documentation

- Template, and

- Organizational standard processes

PMP Prep – HR Slide 51

MANAGE PROJECT TEAM –OUTPUTS

 

Change Requests

• Staffing changes, whether by choice or by uncontrollable events

Project Management plan (Updates)

Page 440: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 440/590

Project Management plan (Updates)

• Updates to Staffing Management Plan – they include new roles,training, reward decisions

 PMP Pre – HR Slide 52

HUMAN RESOURCE QUIZHUMAN RESOURCE QUIZQuiz

You're the Project Manager for a one-year construction project.The project is a quarter done and your team consists of six sellersand 25 company employees. To understand who is responsiblefor what work, you would look at the:

A Resource histograms

Page 441: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 441/590

 A. Resource histograms

B. Bar chartC. Responsibility assignment matrixD. Project organization chart

PMP Prep – HR Slide 53

HUMAN RESOURCE QUIZHUMAN RESOURCE QUIZ

Answer 

C is the answer.

The responsibility assignment matrix maps who will do what work.The resource histogram show the number of resources used in

Page 442: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 442/590

geach time period. The bar chart, in its pure form, shows onlyactivity and calendar dates. An organizational chart shows whoreports to whom.

PMP Prep – HR Slide 54

Questions?Questions?

Page 443: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 443/590

PMP Prep – HR Slide 55

DAY 4

CHAPTER 11

Page 444: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 444/590

 PMP Prep – Risk Slide 1

PROJECT RISK MANAGEMENT

AGENDAAGENDA 

Day 1  DAY 4  PMP Exam Prep Introduction Project QUALITY  Management

Project Management Framework  Project RISK  Management

*Introduction Project HUMANRESOURCE Management

*Project Life Cycle & OrganisationProject Management Processes

Page 445: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 445/590

j g

  DAY 2  DAY 5  Project INTEGRATION Management ProjectPROCUREMENT Management

Project SCOPE Management Professional & SocialResponsibility

DAY 3 DAY 6  Project TIME Management REVISION & QUIZ

Project COST Management

PROJECT RISK PROJECT RISK MANAGEMENTMANAGEMENT

 WHAT DOES THE RISK KNOWLEDGE AREA DO?

• Risk management planning, identification, analysis,responses, and monitoring & control on a project

• The objectives of Project Risk management are to increasethe probability & impact of positive events (opportunities),

Page 446: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 446/590

p y p p ( pp )

and decrease the probability & impact of events adverse tothe project (threats)

PMP Prep – Risk Slide 2

PROJECT RISK PROJECT RISK MANAGEMENTMANAGEMENT

What is project risk? • Uncertain event or condition that, if it occurs, has a positive or a negative

effect on at least one project objective (i.e. time, cost, scope, or quality)

Positive effect is an opportunityNegative effect is a threat

Known risks

Page 447: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 447/590

Known risks 

• Those that are identified and can be proactively managed & analyzed

Unknown risks (unknown knowns & unknown unknowns)• Cannot be proactively managed

PMP Prep – Risk Slide 3

PROJECT RISK PROJECT RISK MANAGEMENTMANAGEMENT

• Look for risks caused by things like poor project management,dependency on uncontrollable external resources, concurrentmultiple projects, etc.

• Accept risks if they're in balance with a possible reward

• Communicate about risk information openly & honestly

Page 448: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 448/590

• Provide risk responses in line with the organization's perceivedbalance between risk-taking &risk-avoidance

• To be successful, an organization should be committed toaddressing the management of risk proactively & consistentlythroughout the project

PMP Prep – Risk Slide 4

RISK PROCESSESRISK PROCESSESRISK PROCESS DEFINITIONS 

11.1 Plan Risk Management

• Process of deciding how to approach and conduct (plan & execute) therisk management activities for a project.

11.2 Identify Risks• Determine which threats/opportunities might affect the project &

Page 449: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 449/590

document their details

11.3 Perform Qualitative Risk Analysis• Assess each risk's chance of occurring & probable impact to get a

prioritized list of risks requiring more analysis or action

PMP Prep – Risk Slide 5

RISK PROCESSESRISK PROCESSES11.4 Perform Quantitative Risk Analysis• Numerically analyze identified risks' effect on overall project objectives

11.5 Plan Risk Responses• Analyze risks and make a plan of actions & options to enhance

opportunities & reduce threats to project objectives

11 6 Monitor & Control Risks

Page 450: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 450/590

11.6 Monitor & Control Risks

• Track identified & residual risks, identify new risks, execute risk responseplans & evaluate their effectiveness

• See Figure 11-20, p.309 for Risks data flow diagram

PMP Prep – Risk Slide 6

RISK PROCESSESRISK PROCESSESProcesses by process group

Planning Monitoring and controlling

11.1

Plan Risk Management

11.6

Monitor and Control Risks

11.2

Identify Risks

11.3

Page 451: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 451/590

PMP Prep – Risk Slide 7

Perform Qualitative RiskAnalysis

11.4

Perform Quantitative RiskAnalysis

11.5

Plan Risk Responses

PLAN RISK MANAGEMENTPLAN RISK MANAGEMENTHOW DO YOU PLAN FOR RISK?

 

• Establish an agreed-upon approach for conducting risk

management activities & evaluating risk

• Ensure that the level, type, and visibility of risk management arecommensurate with both risk and importance of the project to theorganization

Page 452: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 452/590

• Provide sufficient resources and time for risk managementactivities

• Planning Risk management should be completed early duringproject planning, since it is crucial to successfully performing theother processes

PMP Prep – Risk Slide 8

PLAN RISK MANAGEMENTPLAN RISK MANAGEMENT

INPUTS• Project scope statement

TOOLS &TECHNIQUES

• Planningmeeting &

analysis

Page 453: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 453/590

PMP Prep – Risk Slide 9

• Project scope statement

• Cost mgmt. plan• Schedule mgmt. plan

• Communications mgmt. plan• Enterprise environmental

factors• Organizational process

assets

OUTPUTS

• Risk management plan

PLAN RISK MANAGEMENT-PLAN RISK MANAGEMENT-INPUTSINPUTS

INPUTS 

Project Scope Statement (sec 5.2.3.1)

Cost Management Plan (sec 7.0)

Page 454: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 454/590

Schedule Management Plan (sec 6.0)

Communications Management Plan (sec 10.2.3.1)

PMP Prep – Risk Slide 10

PLAN RISK MANAGEMENT-PLAN RISK MANAGEMENT-

INPUTSINPUTSEnterprise Environmental Factors•  Attitudes towards risk and the risk tolerance of organizations and

people involved in the project will influence the project managementplan.

Organizational Process Assets

O i ti h d fi d h t i k

Page 455: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 455/590

• Organizations may have predefined approaches to riskmanagement such as categories, common definitions of concepts &terms, standard templates, roles & responsibilities, and authoritylevels for decision- making.

PMP Prep – Risk Slide 11

PLAN RISK MANAGEMENTPLAN RISK MANAGEMENT-T & T-T & T

TOOLS & TECHNIQUES

Planning Meetings and Analysis

•  Project teams hold planning meetings to develop the risk management

plan (attendees may include the project manager, selected project team

members and stakeholders)

Page 456: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 456/590

• Develop risk cost elements (e.g. contingency reserves) and scheduleactivities (e.g. risk status meetings or buffer time) for inclusion in the

project budget and schedule

• Assign risk responsibilities

• Develop general organizational templates for risk categories and

definitions (e.g. risk levels, types)

PMP Prep – Risk Slide 12 Powered by POeT Solvers Limited

PLAN RISK MANAGEMENTPLAN RISK MANAGEMENT

-OUTPUTS-OUTPUTSRisk Management Plan 

•  Describes how risk management will be structured & performedon the project

•  It includes:

• Methodology – defines the approaches, tools, & data sources thatmay be used to perform risk management on the project

Page 457: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 457/590

• Roles & responsibilities - defines the lead, support, & riskmanagement team membership for each type of activity in the riskmanagement plan, assigns people to these roles, and clarifies their responsibilities

• Budgeting – assigns resources & estimates costs needed for riskmanagement for inclusion in the project cost baseline

PMP Prep – Risk Slide 13 Powered by POeT Solvers Limited

PLAN RISK MANAGEMENT-PLAN RISK MANAGEMENT-

OUTPUTSOUTPUTS•  Timing

Defines when & how often the risk management process will beperformed throughout the project life cycle, and establishes riskmanagement activities to be included in the project schedule.

• Risk categories • Provides a structure that ensures a comprehensive process of 

systematically identifying risk to a consistent level of detail &contributes to the effectiveness and quality of Risk Identification 

• An organization can use a previously prepared categorization of

Page 458: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 458/590

• An organization can use a previously prepared categorization of typical risks.

• A Risk Breakdown Structure (RBS) (not a Resource BreakdownStructure, which is also RBS) is one approach to providing such astructure (see fig.11-4, page 244)

• Revised stakeholders' tolerances - Stakeholders tolerances may berevised in risk management planning process

PMP Prep – Risk Slide 14 Powered by POeT Solvers Limited

PLAN RISK MANAGEMENT-PLAN RISK MANAGEMENT-

OUTPUTSOUTPUTS

  Definitions of risk probability & impact

• The impact scale reflects significance of impact, either negative for threats or positive for opportunities, on each project objective if arisk occurs.

• Impact scales are specific to the objective potentially impacted, type

Page 459: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 459/590

p p j p y p , yp

& size of the project, organization’s strategies and financial state,and the organization’s sensitivity to particular impacts. 

• See fig. 11-5 in page 281 

PMP Prep – Risk Slide 15 Powered by POeT Solvers Limited

PLAN RISK MANAGEMENT-PLAN RISK MANAGEMENT-

OUTPUTSOUTPUTS• Relative scales (also called ordinal scale) for impact are rankordered descriptors such as low, medium, high, very high reflectingimpact in increasing order.

• Alternatively, numeric scales (also called cardinal scales) assignvalues to these impacts. The values may be

• Linear (e.g. 1, 3, 5, 7, 9) or,• Non-linear (e.g. 1, 2,4, 8) – non-linear scales may represent organization’s

desire to avoid high-impact threats or exploit high impact opportunities, even if theyhave relatively low probability

Risk impact-Proj Objective 1 2 3 4

Linear – Risk Value totalis 40

Risk Impact-P j Obj ti 1 2 4 8

Non-Linear – Risk value is 63

Page 460: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 460/590

Note: The figures in the box are probability of a risk impacting an objective

Proj. Objective

 Time 3 1

Cost 4

Scope 5

Quality

2

3 8 9 20

Proj. Objective 1 2 4 8

 Time 3 1

Cost 4

Scope 5

Quality 2

3 8 12 40

PLAN RISK MANAGEMENT-PLAN RISK MANAGEMENT-

OUTPUTSOUTPUTS• Probability & impact matrix 

• Risks are prioritized by their potential impact on project multiplied by

their possibility of occurring, e.g. 10% x $800 = $80 risk value

• See Figure 11-5, p.245 for a sample impact scale (relative &numerical)

• See Figure 11-8, p.252 for a Probability & Impact Matrix look-up table

where you can look up your impact (bottom row) multiplied by your 

determined probability (left column) and get a rating which can be

Page 461: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 461/590

measured against other projects in your companyReporting formats 

Describes the content & format of risk register (list of risks with details)

Tracking 

Documents how all facets of risk activities will be recorded for the

benefit of current project, future needs, and lessons learned.

PMP Prep – Risk Slide 17 Powered by POeT Solvers Limited

RISK PROCESSESRISK PROCESSESProcesses by process group

Planning Monitoring and controlling

11.1Plan Risk Management 

11.6Monitor and Control Risks

11.2

Identify Risks

Page 462: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 462/590

 –

11.3Perform Qualitative Risk

Analysis

11.4

Perform Quantitative Risk

Analysis

11.5

Plan Risk Responses

IDENTIFY RISKSIDENTIFY RISKS  WHAT HAPPENS IN IDENTIFY RISKS?

• Identify Risks determines which risks might affect the project &documents their characteristics

• Participants in identify risk activities can include the following, whereappropriate: project manager, project team members, risk managementteam (if assigned), risk experts from outside, customers, end-users,stakeholders, etc.

Page 463: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 463/590

•  All project personnel should be encouraged to identify risks.

• Identify risks - is an iterative process because:

 – Risk events may happen, which may cause new risks – Status of identified risks may change

 – New risks may occur 

 

PMP Prep – Risk Slide 19 Powered by POeT Solvers Limited

IDENTIFY IDENTIFY  RISKSRISKS 

INPUTS• Risk management plan

• Activity cost estimatesA ti it d ti ti t

TOOLS &TECHNIQUES

• Documentationreviews

• Information gathering

techniques• Checklist analysis• Assumptions analysis

• Diagrammingtechniques

• SWOT analysis

Page 464: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 464/590

PMP Prep – Risk Slide 20 Powered by POeT Solvers Limited

• Activity duration estimates• Scope baseline

• Stakeholder register • Cost mgmt. plan

• Schedule mgmt. plan• Quality mgmt. plan• Project documents

• Enterprise environmental

factors• Organizational process

assets 

OUTPUTS• Risk register

• Expert judgement

IDENTIFY IDENTIFY  RISKS - INPUTSRISKS - INPUTSINPUTS

• Risk Management Plan

• Activity cost estimates

• Activity time estimates

• Activity duration estimates

Page 465: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 465/590

• Scope baseline

• Stakeholder register 

PMP Prep – Risk Slide 21 Powered by POeT Solvers Limited

IDENTIFY IDENTIFY  RISKS - INPUTSRISKS - INPUTS

• Cost mgmt. plan

• Schedule mgmt. plan

• Quality mgmt. plan

• Project documents

• Enterprise Environmental Factors

Page 466: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 466/590

• Organizational Process Assets

PMP Prep – Risk Slide 22 Powered by POeT Solvers Limited

IDENTIFY IDENTIFY  RISKS – T&TRISKS – T&T

TOOLS & TECHNIQUES

Documentation Reviews

Structured review of project documentation including plans,

assumptions, prior project files, and other information to ensure

Page 467: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 467/590

•  Quality of the plans

• Consistency between those plans and with the project requirements

and assumptions

PMP Prep – Risk Slide 23 Powered by POeT Solvers Limited

IDENTIFY IDENTIFY  RISKS – T&TRISKS – T&TInformation Gathering Techniques

Brainstorming -a group creativity technique to share impulsive ideas & getnew ideas from each other to build on

Delphi technique -experts take part in an anonymous questionnaire so asnot to influence each other, then their ideas are shared for more input

Interviewing -meeting a person to draw out facts & statements

Page 468: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 468/590

Root cause identification -examine underlying causes for a risk

PMP Prep – Risk Slide 24

IDENTIFY IDENTIFY  RISKS – T&TRISKS – T&TChecklist Analysis 

• Checklist are developed based on historical information & knowledge

• Impossible to build an exhaustive one

• Get sample checklists or Questionnaires commercially or from theinternet

Assumptions Analysis

• Are assumptions still valid? It identifies risks to the project from

inaccuracy, inconsistency, or incompleteness of assumptions.

Page 469: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 469/590

Diagramming Techniques• Cause-and-effect diagrams (also called Ishikawa or fishbone diagrams)

• System or process flow charts

• Influence diagrams (What affects What) – It is a graphical

representation of situation showing causal influences, time ordering of 

events, and other relationships among variables and outcomes.

  PMP Prep – Risk Slide 25

IDENTIFY IDENTIFY  RISKS – T&TRISKS – T&T

SWOT Analysis

• The technique examines the project from each of the SWOT

(strengths, weaknesses, opportunities, and threats)perspectives to increase the breadth of identified risks byincluding internally generated risks

• SWOT analysis also examines the degree to which

Page 470: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 470/590

organizational strengths offset threats and opportunities thatmay serve to overcome weaknesses.

Expert Judgement

PMP Prep – Risk Slide 26

IDENTIFY IDENTIFY  RISKS –RISKS –

OUTPUTSOUTPUTS  Risk Register 

The primary outputs of Identify Risks are the initial entries into the riskregister. The risk register ultimately contains the outcomes of the other risks mgmt. processes as they are conducted, resulting in an increase inthe level and type of information contained in the risk register over time.The preparation of risk register begins with

Page 471: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 471/590

• List of identified risks• List of potential responses

PMP Prep – Risk Slide 27

RISK PROCESSESRISK PROCESSESProcesses by process group

Planning Monitoring and controlling

11.1

Plan Risk Management 

11.6

Monitor and Control Risks

11.2

Identify Risks

11.3

Perform Qualitative Risk

Page 472: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 472/590

PMP Prep – Risk Slide 28

Perform Qualitative Risk Analysis

11.4

Perform Quantitative RiskAnalysis

11.5

Plan Risk Responses

QUALITATIVE RISK QUALITATIVE RISK 

ANALYSISANALYSIS HOW DO YOU PERFORM QUALITATIVE RISK ANALYSIS?

• Prioritize identified risks for further action, such as Quantitative Risk Analysis or Risk Response Planning

• Organizations can improve the project’s performance effectively byfocusing on high-priority risks

• Assess the priority of identified risks using their probability of occurring

Page 473: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 473/590

Assess the priority of identified risks using their probability of occurring,the corresponding impact on project objectives if the risks do occur 

• Also use factors such as time frame & risk tolerance of the projectconstraints of cost, schedule, scope & quality

PMP Prep – Risk Slide 29

PERFORM QUALITATIVE RISK PERFORM QUALITATIVE RISK 

ANALYSISANALYSIS

INPUTS

TOOLS &TECHNIQUES

• Risk probability andimpact

assessment• Probability and impact

matrix• Risk data quality

assessment• Risk categorization

• Risk urgency

Page 474: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 474/590

 

PMP Prep – Risk Slide 30

• Risk register• Risk management plan

• Project scope statement• Organizational process

assets

OUTPUTS• Risk register

(updates)

assessment• Expert judgement

PERFORM QUALITATIVE RISK PERFORM QUALITATIVE RISK 

ANALYSIS-INPUTSANALYSIS-INPUTSINPUTS

Risk Register 

Risk Management Plan

Project Scope Statement

Page 475: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 475/590

Organizational Process Assets

PMP Prep – Risk Slide 31

PERFORM QUALITATIVE RISK PERFORM QUALITATIVE RISK 

ANALYSIS - T&TANALYSIS - T&T TOOLS & TECHNIQUES

Risk Probability & Impact Assessment

• It investigates the likelihood that each specific risk will occur • Risk impact assessment investigates the potential effect on a project

objective such as time, cost, scope, or quality, including both negativeeffect for threats and positive effects for opportunities.

• The level of probability for each risk and its impact on each objective isevaluated during the interview or meeting with experts or keystakeholders

Page 476: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 476/590

Probability & Impact Matrix

Risk Data Quality Assessment • Risk analysis requires accurate & unbiased data• Examine the degree to which the data about the risk is useful• Examine the degree to which the risk is understood

• Examine the risk data for accuracy, quality, reliability, & integrity

PMP Prep – Risk Slide 32

PERFORM QUALITATIVE RISK PERFORM QUALITATIVE RISK 

ANALYSIS – T&TANALYSIS – T&T TOOLS & TECHNIQUES

Risk Categorization 

• Risks to the project can be categorized by sources of risk (e.g. using theRBS)

Risk Urgency Assessment

• Risks requiring near-term responses may be considered more urgent to

Page 477: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 477/590

address. 

Expert Judgement

• Expert judgement is required to assess the probability and impact of each risk to determine itslocation in the matrix shown in Fig. 11-10 (page 293)

PMP Prep – Risk Slide 33

RISK PROCESSESRISK PROCESSESProcesses by process group

Planning Monitoring and controlling

11.1

Plan Risk Management 

11.6

Monitor and Control Risks

11.2

Identify Risks

11.3

Perform Qualitative Risk

Page 478: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 478/590

PMP Prep – Risk Slide 34

QAnalysis

11.4

Perform Quantitative Risk Analysis

11.5

Plan Risk Responses

PERFORM QUANTITATIVE RISK PERFORM QUANTITATIVE RISK 

ANALYSISANALYSIS HOW DO YOU PERFORM QUANTITATIVE RISK ANALYSIS? 

•   Analyze priority risks (identified in Qualitative Risk Analysis)

• Analyzes the effect of those risk events and assigns a numerical

(quantitative) rating to those risks• It also presents a quantitative approach to making decisions in the

presence of uncertainty

• The process uses techniques such as Monte Carlo simulation & decision

tree analysis to:

Page 479: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 479/590

Quantify possible outcomes for the project and their probabilities• Assess probability of achieving specific project objectives

• Identify risks requiring the most attention

• Identify cost, schedule & scope targets in the light of risk

• Make best decisions when conditions or outcomes are uncertain

• Experienced risk managers sometime perform it directly after Identify Risk

PMP Prep – Risk Slide 35

PERFORM QUANTITATIVE RISK PERFORM QUANTITATIVE RISK 

ANALYSISANALYSIS 

INPUTS

TOOLS & TECHNIQUES• Data gathering &

representationtechniques

•Quantitative risk analysis&

modeling techniques• Expert judgment

Page 480: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 480/590

PMP Prep – Risk Slide 36

• Risk register• Risk mgmt. plan• Cost mgmt. plan

• Schedule mgmt. plan• Organizationalprocess assets

OUTPUTS• Risk register

(updates)

PERFORM QUANTITATIVE RISK PERFORM QUANTITATIVE RISK 

ANALYSIS-INPUTSANALYSIS-INPUTSINPUTS 

Risk Register 

Risk Management Plan

Cost Management Plan

Page 481: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 481/590

Schedule Management Plan

Organizational Process Assets 

PMP Prep – Risk Slide 37

PERFORM QUANTITATIVE RISK PERFORM QUANTITATIVE RISK 

ANALYSIS – T&TANALYSIS – T&T

TOOLS & TECHNIQUES 

Data Gathering & Representation Techniques   Interviewing:

- The info. needed depends upon type of probability

distributions that will be used, e.g. three-point estimates for some

commonly used distributions, and the mean & standard deviation

for others

Page 482: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 482/590

- Documenting the rationale of the risk ranges is an importantcomponent of risk interview

  Probability distributions (beta and triangular) see Figure 11-14, p.298

PMP Prep – Risk Slide 38

PERFORM QUANTITATIVE RISK PERFORM QUANTITATIVE RISK 

ANALYSIS -T & TANALYSIS -T & TQuantitative Risk Analysis & Modeling Techniques

Commonly used techniques include:

• Sensitivity Analysis

Which risks have the most potential impact on the project ( tornado diagram is

used- will definitely get question in exam)

• Expected Monetary Value (EMV) Analysis 

• Calculates average outcome from a group of conditional values when their 

future has events that may or may not occur 

(Will definitely get question in exam)

Page 483: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 483/590

• Multiply each possible impact by its probability (risk value), uses decision tree•  Decision Tree diagram (see Fig. 11-15, page 299)

• Modeling & Simulation 

• Models that translate uncertainties at a detailed level into their potential

impact

• Typically uses Monte Carlo technique

• Better for cost or schedule risk than EMV because EMV is subject to misuse

PMP Prep – Risk Slide 39

PERFORM QUANTITATIVE RISK PERFORM QUANTITATIVE RISK 

ANALYSIS -T & TANALYSIS -T & TExpert Judgement

• It is required to identify potential cost and schedule impacts, to

evaluate probability, and to define inputs (such as probabilitydistributions) into the tools

• It also comes into play in the interpretation of the data. Expertsshould be able to identify the weaknesses of the tools as well as

Page 484: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 484/590

their relative strengths.

• Experts may determine when a specific tool may or may not bemore appropriate given the organization’s capabilities and culture.

PMP Prep – Risk Slide 40

QUANTITATIVE RISK ANALYSIS -QUANTITATIVE RISK ANALYSIS -

OUTPUTOUTPUTOUTPUT

Risk Register (updates)

• Probabilistic analysis of the project

• Probability of achieving cost and time objectives

Page 485: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 485/590

• Prioritized list of quantified risks

• Trends in quantitative risk analysis results

PMP Prep – Risk Slide 41

RISK PROCESSESRISK PROCESSESProcesses by process group

Planning Monitoring and controlling

11.1

Plan Risk Management 

11.6

Monitor and Control Risks

11.2

Identify Risks

11.3

Perform Qualitative Riskl i

Page 486: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 486/590

PMP Prep – Risk Slide 42

Analysis

11.4

Perform Quantitative RiskAnalysis

11.5

Plan Risk Responses

PLAN RISK RESPONSESPLAN RISK RESPONSES

HOW DO YOU PLAN RISK RESPONSES?

• Develop options & determine actions to enhance

opportunities and reduce threats

• Risk responses must be:

• Appropriate to the significance of the risk

C ff

Page 487: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 487/590

• Cost effective• Timely

• Realistic

• Within the project context

• Agreed upon by all parties involved

• Owned by a responsible person

PMP Prep – Risk Slide 43

PLAN RISK RESPONSESPLAN RISK RESPONSES

INPUTS

OUTPUTS• Risk register

( d t )

TOOLS & TECHNIQUES• Strategies for negative

risks orthreats

• Strategies for positiverisks or

opportunities• Contingent response

strategies• Expert judgement

Page 488: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 488/590

 

PMP Prep – Risk Slide 44

INPUTS•Risk register

•Risk managementplan

 

(updates)• Risk-related contract

decisions• Project management

plan

(updates)• Project document

updates

PLAN RISK RESPONSES -PLAN RISK RESPONSES -

INPUTSINPUTS

  INPUTS

Risk Register 

Risk Management Plan

Page 489: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 489/590

PMP Prep – Risk Slide 45

PLAN RISK RESPONSES –PLAN RISK RESPONSES –

T&TT&TTOOLS & TECHNIQUES

Strategies for Negative Risks or Threats

Avoid  – Changing the Project Management Plan to eliminate a potential

risk

For example: 

•  Avoid a scope risk by changing to a less "bleeding edge" technology,

TD b k l t th th j t b f

Page 490: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 490/590

e.g. TD bank lost three months on a project because of unprovensoftware

• Avoid a cost risk by properly doing Activity Resource Estimating

• Avoid a resource risk by removing its requirement

PMP Prep – Risk Slide 46

PLAN RISK RESPONSES –PLAN RISK RESPONSES –

T&TT&T• Transfer - To third party

• Generally involves payment to the party taking on the risk e.g.

procurement of a critical item, For example: 

• Transfer a scope risk by employing a contractor 

T f h d l i k b h i fl d i f N

Page 491: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 491/590

•  Transfer schedule risk by purchasing flood insurance for a NewOrleans project

•  Transfer a resource risk by purchasing on-site warranty

PLAN RISK RESPONSES–PLAN RISK RESPONSES–

T&TT&T•  Mitigate -Reduce impact of an adverse risk/or reduction in the

probabilityFor example:

• Mitigate a scope risk by building a prototype

• Mitigate a resource risk by cross-training a team member • Mitigate a schedule risk by using a pool of temporary workers, e.g.

Departmental Stores/Malls use lots of part-time workers

• Accept 

U d b it' ld ibl t li i t ll th t f j t

Page 492: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 492/590

• Used because it's seldom possible to eliminate all threats from a project• Actively decide not to change project plan to deal with a risk• Passive acceptance requires no action, leaving the project team

to deal with the threats or opportunities as they occur • Active acceptance establishes a contingency reserve or strategy

PMP Prep – Risk Slide 48

PLAN RISK RESPONSES –PLAN RISK RESPONSES –

T&TT&T  Strategies for Positive Risks or Opportunities

• Exploit - Eliminates the uncertainty associated with a particular 

upside risk by making the opportunity will definitely happen

e.g. hiring more talented resources to the project to reduce the

completion time

"T t k d t f" "T k b t f“

Page 493: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 493/590

"To take advantage of" or "To make best use of“

PMP Prep – Risk Slide 49

PLAN RISK RESPONSES–PLAN RISK RESPONSES–

T&TT&T• Share - Share responsibility and accountability to get best chanceof seizing an opportunitye.g. risk sharing partnerships or joint ventures

• Enhance - Modify the "size“ of an opportunity by increasingprobability and/or positive impacts by identifying & maximizing keydrivers.e.g. a sales opportunity may make a higher profit if a volumediscount is offered

Accept

Page 494: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 494/590

• Accept 

 Accepting an opportunity is being willing to take advantage of it if it comes along,butnot actively pursuing it.

 

PMP Prep – Risk Slide 50

PLAN RISK RESPONSES –PLAN RISK RESPONSES –

T&TT&TContingent Response Strategy

• Respond only if certain event occurs and there's sufficient warning

to implement the plan. Examples of events that trigger contingency

response

•  missing intermediate milestones

t f h d

Page 495: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 495/590

• cost of resource has gone down• gaining high priority with a supplier 

should be defined and tracked

PMP Prep – Risk Slide 51

PLAN RISK RESPONSES –PLAN RISK RESPONSES –

T&TT&TExpert Judgement

Input from knowledgeable parties pertaining to the actionsbe taken on a specific and defined risk.

Page 496: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 496/590

PMP Prep – Risk Slide 52

PLAN RISK RESPONSESPLAN RISK RESPONSES --

OUTPUTSOUTPUTS• Risk Register (Updates)  The risk register is developed in Identify Risk, and is updated

during Perform Qualitative Risk Analysis & Perform Quantitative

Risk Analysis In Plan risk responses, appropriate responses are chosen,

agreed upon, and included in the risk register   Components of risk register (read page 305 & 306)

  a) Residual risks - risk that are expected to remain after 

planned responses have been taken as well as those that

Page 497: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 497/590

planned responses have been taken as well as those thathave been deliberately accepted

b) Secondary risks -new risk that arise as a direct outcome of 

implementing a risk response.

PMP Prep – Risk Slide 53

PLAN RISK RESPONSESPLAN RISK RESPONSES --

OUTPUTSOUTPUTS

Risk-Related Contractual Agreements

Such as agreements for insurance, services, and other items asappropriate, can be prepared to specify each party’s responsibilityfor specific risks, should they occur.

Page 498: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 498/590

PMP Pre – Risk Slide 54

Page 499: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 499/590

RISK PROCESSESRISK PROCESSESProcesses by process group

Planning Monitoring and controlling

11.1

Plan Risk Management 

11.6

Monitor and Control Risks 

11.2

Identify Risks

11.3

Perform Qualitative Risk

Page 500: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 500/590

PMP Prep – Risk Slide 56

Perform Qualitative RiskAnalysis

11.4

Perform Quantitative RiskAnalysis

11.5Plan Risk Responses

MONITOR AND CONTROLMONITOR AND CONTROL

RISK RISK WHAT HAPPENS IN MONITOR AND CONTROL RISK?

•   Identify, analyze & plan for new or changed risks

• keep track of the identified risks and those on the watch list• reanalyze existing risks

• Monitor trigger conditions for contingency plan

• Monitor residual & secondary risks

• Review the execution of risk responses while evaluating their 

effectiveness

Page 501: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 501/590

effectiveness.

• Monitor & Control Risk process applies techniques, such as

variance and trend analysis, which require the use of 

performance data generated during project execution

PMP Prep – Risk Slide 57

MONITOR AND CONTROL RISK MONITOR AND CONTROL RISK   Other purposes of Monitor & Control Risk are to determine if:

• Mid-course correction needed to handle the risk appropriately Projectassumptions are still valid

• Risk, as assessed, has changed from its prior state, with analysis of trends

• Proper risk management policies & procedures are being followed

• Contingency reserves of cost or schedule should be modified in line withthe risk of the project

Page 502: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 502/590

• Monitor & Control Risk can involve choosing alternative strategies,executing a contingency or fallback plan, taking corrective action &modifying the project management plan

• Receive periodic reports from risk response owner on the effectiveness of 

the plan, and any unanticipated effects.

PMP Prep – Risk Slide 58

MONITOR AND CONTROLMONITOR AND CONTROL

RISK RISK 

INPUTS

• Risk registerOUTPUTS

• Risk register (updates)

TOOLS & TECHNIQUES• Risk reassessment

• Risk audits• Variance and trend

analysis• Technical performancemeasurement

• Reserve analysis• Status meetings

Page 503: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 503/590

 

PMP Prep – Scope Slide 59

• Risk register• Risk 

managementplan

• Work performance

information• Performancereports

• Risk register (updates)• Org. process assets

(updates)• Change Requests

• Project management plan

(updates)• Project document updates

 MONITOR AND CONTROL RISK -MONITOR AND CONTROL RISK -

INPUTSINPUTSINPUTS

Risk Register 

Project Management Plan

Work Performance Information

Performance Reports

Page 504: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 504/590

Performance Reports

PMP Prep – Risk Slide 60

MONITOR AND CONTROL RISK MONITOR AND CONTROL RISK 

– T&T– T&T  TOOLS & TECHNIQUESRisk Reassessment• Risk Monitoring & Control often requires identification of new risks & re-assessment of risks

•Risk reassessment should be regularly scheduled & should be an agendaitem at project team status meetings

Risk Audits• Examine & document the effectiveness of risk responses in dealing with

identified risks and their root causes, as well as the effectiveness of the riskmanagement process

Page 505: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 505/590

Variance and Trend Analysis• Earned value analysis & trend analysis may be used to monitor overall projectperformance. Outcomes from these analyses may forecast potential deviation of theproject at completion from cost and schedule targets

• Deviation from baseline plan may indicate the potential impact of threats or opportunities

PMP Prep – Risk Slide 61

MONITOR AND CONTROL RISK MONITOR AND CONTROL RISK 

– T&T– T&TTechnical Performance Measurement• Compares technical accomplishment during project execution to the

plan’s schedule of technical achievement

Reserve Analysis• Compares the amount of contingency reserves remaining to the amount of 

risk remaining at any time in the project, to determine if the remainingreserve is adequate

Status Meetings

Page 506: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 506/590

Status Meetings • Risk management can be an agenda item in periodic status meetings to

proactively manage risk

PMP Prep – Risk Slide 62

MONITOR AND CONTROL RISK -MONITOR AND CONTROL RISK -

OUTPUTSOUTPUTS

Risk Register (Updates)

Organizational Process Assets (Updates)

Change Requests

Project Management Plan (Updates)

Project Document (Updates)

Page 507: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 507/590

Project Document (Updates)

(Read page 311 & 312)

 

PMP Prep – Risk Slide 63

SAMPLE EXAM QUESTIONSAMPLE EXAM QUESTIONExercise

Give examples of three risks with a response plan for each.

Schedule - _____________________________________________

______________________________________________________

Cost -

Page 508: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 508/590

Cost ________________________________________________________________________________________________________

Scope- _________________________________________________

_______________________________________________________

 PMP Prep – Risk Slide 64

SAMPLE EXAM QUESTIONSAMPLE EXAM QUESTIONExercise

What’s the difference between:

Passive acceptance & active acceptance?____________________

_______________________________________________________

S d & id l i k ?

Page 509: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 509/590

Secondary & residual risks?_______________________________________________________________________________________

Management reserve & contingency reserve?_________________

_______________________________________________________

Questions?Questions?

Page 510: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 510/590

PMP Prep – Risk Slide 66

  This page is Left Blank intentionally

 

Page 511: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 511/590

 DAY 1

DAY 5

 

CHAPTER 12

PROJECT PROCUREMENT

Page 512: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 512/590

 PMP Prep – Procurement Slide 1

PROJECT PROCUREMENTMANAGEMENT

AGENDAAGENDA 

Day 1  DAY 4  PMP Exam Prep Introduction Project QUALITY  Management

Project Management Framework  Project RISK  Management*Introduction Project HUMAN

RESOURCE Management*Project Life Cycle & Organisation

Project Management Processes

  DAY 2  DAY 5Project INTEGRATION Management Project

Page 513: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 513/590

5  Project INTEGRATION Management ProjectPROCUREMENT Management

Project SCOPE Management Professional & SocialResponsibility

DAY 3 DAY 6  Project TIME Management REVISION & QUIZ

Project COST Management

PROJECT PROCUREMENTPROJECT PROCUREMENT

MANAGEMENTMANAGEMENTWHAT DOES THE PROCUREMENT

KNOWLEDGE AREA DO? • Purchases or acquires products, services or results needed to perform

project work (internal or external to the performing organization)• PMI uses the terms Buyer & Seller very often. Buyer is normally the

performing organization. Sellers can be Contractors, Sub-contractors,

Service providers, Suppliers/Vendors.

• Buyer can also be clients, customers, contractors, or purchasers.

• It is important to understand the situation/context and accordingly

Page 514: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 514/590

p g yinterpret – who is a Buyer or Seller.

• A Seller may consider delivering you their own project (which may be a

a subproject to you.

• If required, seek early assistance from Specialists in contracting,

purchasing within the legal framework (so as to be fair to both).

PROJECT PROCUREMENTPROJECT PROCUREMENT

MANAGEMENTMANAGEMENTContracts• Contracts are formal. Also named as Agreements, Subcontracts, or 

Purchase orders. Letters of intent are not considered as Contract.

• Contract is defined as an agreement between competent parties, for valid (effective, well-grounded, logical and producing desired results )consideration, to accomplish a lawful purpose with clearly definedterms.

• Contracts are a method of transferring risk for a fees (a strategy used in

Risk Response Planning).

Page 515: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 515/590

p g)

• If internal to the Project Team’s organization, a non-contractual formalagreement is prepared in form of an MOU (with other departments).

• PM team should prepare a tailor-made contract based on specific

project needs.

• PM must know the contents of the contract & the purpose.PMP Prep – Procurement Slide 3

PROJECT PROCUREMENTPROJECT PROCUREMENT

MANAGEMENTMANAGEMENT

PROCUREMENT PROCESSDEFINITIONS 

12.1 Plan Procurements

• Make a Procurement Management Plan: that defines What, When &

How to buy goods and services for the Project. Then, prepare a SOW  

defining the purchase needs.

12.2 Conduct Procurements

Page 516: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 516/590

• Document the requirements (for products, services & results from

outside the project organization)

• Identify potential Sellers

12.3 Administer Procurements

• Obtain Information, Quotes, Bids, Offers or Proposals

PROCUREMENT PROCESSESPROCUREMENT PROCESSES

 • Review the Offers; Select the best out of the potential Sellers;Negotiate a written Contract.

• Manage the Contract & contract changes; the relationshipsbetween Buyer and Seller.

• Review & document the Seller performance.• Manage contractual relationship with outside Buyer of the

Project.

Page 517: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 517/590

j

12.4 Close Procurements

• Complete & settle each contract 

• See the Process flow diagram in page 273.

 PMP Prep – Procurement Slide 5

PROCUREMENT PROCESSESPROCUREMENT PROCESSES

Planning  Executing Monitoring and

controlling

Closing

12.1

PlanProcurement

s

12.2

ConductProcurement

s

12.3

AdministerProcurement

s

12.4

CloseProcurement

s

Page 518: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 518/590

 

PMP Prep – Procurement Slide 6

PLAN PROCUREMENTSHOW DO WE PLAN PROCUREMENTS?

 Identify which project needs that can best be:•  project needs which can be, must be, met by acquiring products, services or 

results outside the Project organization.• accomplished by the project team during project execution.

The process •  involves consideration of whether, how, what, how much & when to

acquire.

• includes reviewing the risks involved in each make or buy decision.• includes reviewing the type of contract planned to be used with

Page 519: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 519/590

includes reviewing the type of contract planned to be used withrespect to mitigating or transferring risks to the Seller.

PMP Prep – Procurement Slide 7

PLAN PROCUREMENTSPLAN PROCUREMENTS

INPUTS• Scope baseline

• Requirements documentation

• Teaming agreements• Risk register

OUTPUTS

• Procurement

TOOLS & TECHNIQUES

•  Make-or-buy analysis

• Expert judgement• Contract types

Page 520: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 520/590

 

PMP Prep – Procurement Slide 8

• Risk register • Risk-related contract decisions• Activity resource requirements

• Project schedule• Activity cost estimates

• Cost performance baseline

• Enterprise environmental factors• Organizational Process assets

 

management plan• Procurement statements of work

• Make-or-buy decisions• Procurement documents• Source selection criteria

• Change requests

PLAN PROCUREMENTSINPUTS 

Enterprise Environmental Factors

• Marketplace conditions: what products, services & results are available,

at what prices, under what terms & conditions.• If the performing organization does not have a purchasing or contracting

group, then project team will have to supply both resources & expertise

to perform all procurement activities.

Organizational Process Assets 

• Formal & informal procurement-related policies, procedures, forms,

Page 521: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 521/590

guidelines & management systems that are considered in developing

Procurement Management Plan & selecting contract types to be used.

• Existing organisation policies frequently constrain procurement

decisions. Though many a times those policies are devised based on

lessons learned from past projects.

PMP Prep – Procurement Slide 9

PLAN PROCUREMENTS - INPUTS

Scope Baseline

The scope baseline describes the need, justification, requirements,and current boundaries for the project. It consists of the following

components: • Scope statement : It contains the product scope description, service

description, the list of deliverables, and acceptance criteria, as well as

important information regarding technical issues or concerns that could

impact cost estimating. Examples of constraints are required delivery

dates, available skilled resources, and organizational policies.

Page 522: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 522/590

, , g p

• Work Breakdown Structure

• WBS Dictionary

PMP Prep – Procurement Slide 10

PLAN PROCUREMENTS -

INPUTSRequirements Documentation

Requirements documentation may include:• Important information about project requirements that is considered

during planning procurements. 

• Requirements with contractual and legal implications that may include

health, safety, security, performance, environmental, insurance,

intellectual property rights, equal employment opportunity, licenses,d

Page 523: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 523/590

and

permits – all of which are considered when planning for procurements.

PLAN PROCUREMENTS -

INPUTS Teaming Agreements:

• Legal contractual agreements between two ormore entities to form a partnership or jointventure, or some other arrangement as defined bythe parties.

• The agreement defines buyer-seller roles for eachparty.

• Whenever the new business opportunity ends, theteaming agreement also ends.

Page 524: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 524/590

g g• When teaming agreement is in effect, the planning

process for the project is significantly impacted.• When teaming agreement is in place on a project,

the roles of buyer and seller are predetermined,and such issues as scope of work, competitionrequirements, and other critical issues aregenerally predefined.

PLAN PROCUREMENTS -

INPUTSRisk Register (Section 11.2.3.1)Risk-Related Contract Decisions

• They include agreements including insurance,bonding, services, and other items as appropriate,that are prepared to specify each party’sresponsibility for specific risks. 

Activity Resource Requirements (Section

6.3.3.1)P j S h d l

Page 525: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 525/590

6.3.3.1)Project Schedule

Activity Cost Estimates• Cost estimates developed by the procuring activity

are used to evaluate the reasonableness of thebids or proposals received from potential sellers 

PLAN PROCUREMENTS -

INPUTSCost Performance Baseline (Section 7.2.3.1)

Enterprise Environmental FactorsEEF that can influence the Plan Procurements process include,

but are not limited to:

• Marketplace conditions;

• Products, services, and results that are available in the

marketplace;S ppliers incl ding past performance or rep tation

Page 526: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 526/590

• Suppliers, including past performance or reputation;

•  Typical terms and conditions for products, services, andresults or for the specific industry; and

• Unique local requirements.

PLAN PROCUREMENTS -

INPUTSOrganizational Process AssetsOPA that influence the Plan Procurement process

include, but

are not limited to:

• Formal Procurement policies, procedures, andguidelines.

• Management systems that are considered in

Page 527: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 527/590

Management systems that are considered indeveloping the procurement management planand selecting the contract types to be used.

• An established multi-tier supplier system of pre-qualified sellers based on prior experience.

PLAN PROCUREMENTS -T&T

  TOOLS & TECHNIQUESExpert Judgment

Make or Buy Analysis

 Price is not the only consideration. Also consider:

• Exposure of proprietary information• Difficulty in defining deliverables and communicating externally• Is this work your core competency?• Work you want to do in parallel

Page 528: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 528/590

• Amount of change contemplated• Time to manage several procurement processes/find sellers• Skills available within your team/company and their moral if you

outsource

• Special resource requirement-time duration for training, learning curveetc.

PLAN PROCUREMENTS -T&T

Questions on Make or Buy decisions: can include buy or leasequestions like this.

It costs $300/day to lease an item. It would cost $2000 plus $100/day onmaintenance to buy it. When will lease and purchase costs be equal (inDays)?

Lease cost = $300/day Investment =$2000 + $100/day

D = # of days when purchase & lease costs will be equal

Page 529: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 529/590

 $300D =$2000 + $100D ( No. of days)

$300D -$100D = $2000 + $100D -$100D (subtract $100D from bothsides)

$200D = $2000

D = 10 i.e. 10 days 

PLAN PROCUREMENTS -T&T

Page 530: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 530/590

PMP Prep – Procurement Slide 14

CONTRACT TYPESCONTRACT TYPES  Contract Types

FIXED-PRICE (FP) CONTRACTS 

Firm Fixed Price Contracts (FFP)

• Seller to complete the job within a fixed total price.

• The Product has to be well defined ( both seller & buyer are at risk )

Fixed Price Plus Incentive Fee -FPIF• Seller completes ithin a fi ed total price pl s an e tra incenti e for

Page 531: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 531/590

• Seller completes within a fixed total price, plus an extra incentive for 

meeting or exceeding certain objectives

e.g. fixed price of $100,000 + $25,000 for completing by a target date

PMP Prep – Procurement Slide 15

CONTRACT TYPESCONTRACT TYPESFixed Price Incentive Fee Contracts (FPIF)

• Incentive is based on sellers performance

tied to achieving agreed to metrics.

• Typically such financial incentives arerelated to cost, schedule, or technical

performance of the seller

Page 532: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 532/590

p• In FPIF contracts, a price ceiling is set, and

all costs above the price ceiling are theresponsibility of the seller, who isobligated to complete the work.

CONTRACT TYPESCONTRACT TYPESFixed price with Economic Price AdjustmentContracts (FP-EPA)

• The contract type is used whenever the seller’sperformance period spans a considerable period of years, as is desired with many long-termrelationships.

• It is Fixed price contract, but with a special

provision allowing for pre-defined finaladjustments to the contract price due to changed

Page 533: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 533/590

j p gconditions, such as inflation changes, or costincreases (or decreases) for specific commodities.

• The EPA clause must relate to some reliablefinancial index which is used to precisely adjustthe final price. The FP-EPA contract is intended toprotect both buyer and seller from externalconditions beyond their control.

CONTRACT TYPESCONTRACT TYPESCOST-REIMBURSABLE (CR) CONTRACTS • Involves payment (reimbursement) to the seller for seller's actual costs,

plus a fee typically representing seller profit• May also include financial incentive clauses whenever the seller 

exceeds, or falls below, defined objectives such as costs, schedule, or technical performance targets.

• Three or more common types in use are as given below:

Cost Plus Fixed Fee –CPFF

•  Buyer pays all costs plus a fixed fee• Cost over runs will not increase the fixed fee

Page 534: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 534/590

Cost over runs will not increase the fixed fee• e.g. cost of $100,000 + fixed fee of $15,000 (as profit)

PMP Prep – Procurement Slide 16

CONTRACT TYPESCONTRACT TYPESCost Plus Incentive Fee -CPIF 

•  Buyer pays all costs plus an incentive to beat some criteria• Criteria might be a cost or time target with a certain formula• e.g. cost of $100,000 + a pre-determined fee $5000 as

incentive for early delivery 

Cost Plus Award Fee contracts (CPAF)•  The seller is reimbursed for all legitimate costs, but the majority

of the fee is only earned based on the satisfaction of certainbroad subjective performance criteria defined and incorporated

Page 535: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 535/590

broad subjective performance criteria defined and incorporatedinto the contract.

• The determination of fee is based solely on the subjectivedetermination of seller performance by the buyer, and is

generally not subject to appeals.

PMP Prep – Procurement Slide 17

CONTRACT TYPESCONTRACT TYPESTIME & MATERIAL (T&M) CONTRACTS

• Hybrid type of contractual agreement that contains aspects of both

cost-reimbursable & fixed-price contracts.

 • The full value of the agreement and the exact quantity of items to be

delivered is not known when the agreement is made (like a cost

reimbursement contract)

• Based upon unit rates or hourly rates as preset by the Buyer & Seller for a specific resource category (like a fixed-price contract)

Page 536: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 536/590

p g y ( p )

PMP Prep – Procurement Slide 18

CONTRACT TYPESCONTRACT TYPES 

Question

Contract cost is estimated to be $210,000 and a fee of $10 ,000 is offeredto the supplier for completing the contract on or before time.

If the contractor beats the cost, both the buyer and the seller will sharethe savings at 40:60 ratio.

If the actual cost of the work comes out to $180,000, what will the

Page 537: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 537/590

Seller get if the contract is completed before time?

PMP Prep – Procurement Slide 19

CONTRACT TYPESCONTRACT TYPES

ANSWER:

Target cost" $210,000Seller's fee" $10,000

Sharing ratio = 40% buyer / 60% seller 

seller Actual cost" $180,000

Cost savings = $210,000 -$180,000 = $30,000Seller's profit = $10,000 + ( $30,000 X 60% ) = $28,000

Page 538: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 538/590

p $ , ( $3 , % ) $ ,

Final price to buyer = $180,000 + $28,000 = $208,000

PMP Prep – Procurement Slide 20

CONTRACT TYPESCONTRACT TYPES

Page 539: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 539/590

PMP Prep – Procurement Slide 21

CONTRACT TYPESCONTRACT TYPES

  Spectrum of Risk• Contract type should be chosen based on the degree of risk (do you

know what will it cost to deliver?)• Risk increases if scope is not well defined. So defining the scope better 

will get you a better contract with less risk for all.• Risk can affect any/or all of them - time, cost, quality & scope

Contracts - buyer on high risk• Buyer pays for what it costs to deliver 

If costs go up, buyer's price increases, but seller's costs are always

covered.

Page 540: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 540/590

Contracts - seller on high risk• Buyer pays for agreed price no matter what it costs to deliver 

If costs go up, seller has to absorb them, but buyer has fixed price &isn't affected.

PMP Prep – Procurement Slide 22

PROCUREMENT DOCUMENTSPROCUREMENT DOCUMENTS

Procurement Documents 

RFP (Request for Proposal or Request for Tender) - requests a price anddetails on how the work will be carried out, time frame, who will do it,biography of the team, company experience, etc.

IFB (Invitation for Bid or Request for Bid) -requests one price for all thework.

Request for Quote (RFQ) -requests a price quote per item, on hourly or per unit basis

Page 541: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 541/590

per unit basis.

PMP Prep – Procurement Slide 23

PLAN PROCUREMENTS -PLAN PROCUREMENTS -

OUTPUTSOUTPUTS 

Procurement Management Plan

•  Describes how the procurement processes will be managed from

developing procurement documentation through contract closure• The procurement management plan can include guidance for:

• Types of contracts to be used;

• Risk management issues;

• Whether independent estimates will be used and if they are needed

as evaluation criteria;

• Those actions the PM team can take unilaterally if the performing

Page 542: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 542/590

• Those actions the PM team can take unilaterally, if the performing

organization has a prescribed procurement, contracting, or 

purchasing department;

• Standardized procurement documents, if they are needed;

PMP Prep – Procurement Slide 24

PLAN PROCUREMENTS -PLAN PROCUREMENTS -

OUTPUTSOUTPUTSProcurement Management Plan

(Contd.)

• Managing multiple suppliers;

• Coordinating procurement with other project

aspects, such as scheduling and performancereporting;

Page 543: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 543/590

p g;

• Handling the required lead times

• Handling the make-or-buy decisions, etc.

 

PLAN PROCUREMENTS -PLAN PROCUREMENTS -

OUTPUTSOUTPUTSProcurement Statements of Work• Describes the procurement item in sufficient detail to allow prospective

sellers to determine if they are capable of providing the item.• Written to be clear, complete & concise.• Information included in a contract SOW can include specifications,

quantity desired quality levels, performance data, period of performance,work location & other requirements.

• Include description of any collateral services required, i.e. performancereporting or post-project operational support for the procured item.

• Contract SOW can be revised as required as it moves through theprocurement process until incorporated into signed contract. Seller mayl dif th SOW b ti ffi i t h l

Page 544: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 544/590

also modify the SOW by suggesting more efficient approach or a lesscostly product than that originally specified.

Make-or-Buy Decisions

PMP Prep – Procurement Slide 25

PLAN PROCUREMENTS -PLAN PROCUREMENTS -

OUTPUTSOUTPUTSProcurement Documents

• Used to seek proposals from prospective sellers e.g.

RFP/RFQ/IFB etc.• Terms such as bid, tender or quotation are generally used when

the seller selection decision will be based on price;• RFP is used when other considerations such as technical

capability or technical approach are paramount)

• These documents include,- Procurement SOW

Page 545: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 545/590

- Any required contractual provisions- With government contracting, some or all of the content andstructure of procurement documents can be defined byregulation.

PLAN PROCUREMENTS -PLAN PROCUREMENTS -

OUTPUTSOUTPUTSSource Selection Criteria• Selection Criteria are often included as a part of the procurement solicitation

documents. Such criteria are developed and used to rate or score seller proposals,and can be objective or subjective (the proposed Project Manager should be a

Certified PMP) or subjective (previous experience on similar projects)• Other selection criteria to support an assessment of a complex products, services, or results may include:

  Understanding of need Overall or life-cycle cost Technical capability Risk

Management approach Technical Approach

Page 546: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 546/590

Warranty Financial capacity Production capacity and interest Business size & type Past performance of sellers References Intellectual property rights Proprietary rights

PROCUREMENT PROCESSESPROCUREMENT PROCESSES

PROCESSES BY PROCESS GROUP 

Planning Executing Monitoring and

controlling

Closing

12.1

PlanProcurement

s

12.2

Conduct

Procurements

12.3

Administer

Procurements

12.4

Close

Procurements

Page 547: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 547/590

PMP Prep – Procurement Slide 26

s  s s s

 

CONDUCT PROCUREMENTSCONDUCT PROCUREMENTS

  WHAT HAPPENS IN CONDUCT PROCUREMENTS?

• Conduct Procurements is the process of obtaining Seller responses, selecting a seller, andawarding a contract (see Figures 12-4 and 12-5 in page 329 of PMBOK)

• In this process, the team will receive bids or proposals and will apply previously definedselection criteria to select one or more sellers who are qualified to perform the work andacceptable as a seller.

• On major procurement items, overall process of requesting responses from sellers andevaluating those responses can be repeated.

• A short list of qualified sellers can be established based on a preliminary proposal. A moredetailed evaluation can then be conducted based on a more specific and comprehensiverequirements document requested from the sellers on the short list. In addition, tools and

Page 548: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 548/590

q qtechniques described here can be used alone or in combination to select sellers. For example, a weighting system can be used to:

- Select a single seller that will be asked to sign a standard contract, and- Establish a negotiating sequence by ranking all proposals by the weighted evaluation

scores assigned to each proposal.

PMP Prep – Procurement Slide 27

CONDUCTCONDUCT

PROCUREMENTSPROCUREMENTS

INPUTS• Project management plan

• Procurement documents• Source selection criteria

Q lifi d ll li t

OUTPUTS• Selected sellers

• Procurement contract award

TOOLS & TECHNIQUES

• Bidder conferences• Proposal evaluation

techniques• Independent estimates

• Expert judgement• Advertising

• Internet Research• Procurement negotiations

Page 549: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 549/590

PMP Prep – Procurement Slide 28

• Qualified seller list• Seller proposals

• Project documents• Make-or-buy decisions• Teaming agreements

• Organizational process assets

• Procurement contract award• Resource calendars

• Change requests• Project Mgmt. Plan (updates)• Project document (updates)

CONDUCT PROCUREMENTS -CONDUCT PROCUREMENTS -

INPUTSINPUTSINPUTS

•  Project Management Plan• Procurement documents• Source selection criteria• Qualified seller list• Seller proposals

• Project documents• Make or Buy Decisions

Page 550: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 550/590

• Make-or-Buy Decisions• Teaming agreements• Organizational process assets

 PMP Prep – Procurement Slide 29

CONDUCTCONDUCT

PROCUREMENTS – T&TPROCUREMENTS – T&T1) Bidder Conferences

Meeting with all prospective sellers and buyers

prior to submittal of a bid or proposal (Read page331)

2) Proposal Evaluation Techniques

  On complex procurements, where source selectionwill be made based on seller responses to previouslydefined eighted criteria a formal e al ation re ie

Page 551: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 551/590

defined weighted criteria, a formal evaluation reviewprocess will be defined by the buyer’s procurementpolicies. The evaluation committee will make their selection for approval by management prior to theaward.

 PMP Prep – Procurement Slide 30

CONDUCTCONDUCT

PROCUREMENTS – T&TPROCUREMENTS – T&T

3) Independent Estimates

4) Expert Judgment5) Advertising 

6) Internet Search

Page 552: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 552/590

PMP Prep – Procurement Slide 31

CONDUCTCONDUCT

PROCUREMENTS – T&TPROCUREMENTS – T&T7) Procurement NegotiationsClarifies the structure & requirements of the contract so that mutualagreement can be reached prior to signing the contract.

Subjects covered include:• Responsibilities & authorities• Applicable terms & law• Technical & business management approaches• Proprietary rights

• Contract financing• Technical solution

Page 553: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 553/590

• Overall schedule• Payments• Price

CONDUCT PROCUREMENTS –CONDUCT PROCUREMENTS –

OutputsOutputsSelected Sellers

• Those sellers who have been judged to be

in a competitive range based upon theoutcome of the proposal or bid evaluation,and

• Who have negotiated a draft contract thatwill become the actual contract when an

Page 554: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 554/590

award is made.

• Final approval of all high-value, high-risk

procurements will generally requireorganizational senior mgmt. approval prior

CONDUCT PROCUREMENTS –CONDUCT PROCUREMENTS –

OutputsOutputsProcurement Contract Award

• A procurement contract is awarded to eachselected seller.

• The contract can be in the form of simple purchaseorder or a complex document.

• Regardless of the document’s complexity, acontract is a mutually binding legal agreement

that obligates the seller to provide the specifiedproducts, services, or results, and obligates the

Page 555: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 555/590

p , , , gbuyer to compensate the seller.

• A contract is a legal relationship subject to remedyin the courts.

CONDUCT PROCUREMENTSCONDUCT PROCUREMENTS

– Outputs– Outputs• The major components in a contract document will

vary, but will sometimes include the following;

- Statement of work or deliverables,

- Schedule baseline,

- Performance reporting,

- Period of performance,

- Roles and responsibilities,

- Seller’s place of performance,

Page 556: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 556/590

- Pricing,

- Payment terms,

- Place of delivery

CONDUCT PROCUREMENTSCONDUCT PROCUREMENTS

– Outputs– Outputs- Inspection and acceptance criteria,- Warranty,- Product support,

- Limitation of liability,- Fees and retainage,- Penalties- Incentives,- Insurance and performance bonds,

- Subordinate subcontractor approvals,- Change request handling, andTermination and alternative dispute resolution (ADR)

Page 557: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 557/590

- Termination and alternative dispute resolution (ADR)mechanisms. The ADR method can be decided in

advance as a part of the procurement award.

PROCUREMENT PROCESSESPROCUREMENT PROCESSES

PROCESSES BY PROCESS GROUP 

Planning Executing Monitoring and

controlling

Closing

12.1

Plan

Procurement

s

12.2

Conduct

Procurements

12.3

Administer

Procurements

12.4

Close

Procurements

Page 558: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 558/590

PMP Prep – Procurement Slide 33

 

ADMINISTER PROCUREMENTADMINISTER PROCUREMENT

HOW DO WE ADMINISTERPROCUREMENT?

• It is the process of managing procurement relationships,monitoring contract performance, and making changes andcorrections as needed (see Figures 12-6 and 12-7 in page 336).

• Both the buyer and the seller will administer the procurement

contract for similar purposes.

• Each must ensure that both parties meet their contractual

Page 559: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 559/590

• Each must ensure that both parties meet their contractualobligations and that their own legal rights are protected.

PMP Prep – Procurement Slide 34

ADMINISTERADMINISTER

PROCUREMENTPROCUREMENT• The Administer Procurements process ensures that the seller’s performance

meets procurement requirements and that the buyer performs according to theterms of the legal contract.

 

• The legal nature of the contractual relationship makes it imperative that the projectmanagement team is aware of the legal implications of actions taken whenadministering any procurement.

• Due to varying org. structures, many organizations treat contract administration asan administrative function separate from the project organization. While aprocurement administrator may be on the project team, this individual typicallyreports to a supervisor from a different department. This is usually true if theperforming organization is also the seller of the project to an external customer.

Page 560: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 560/590

 

ADMINISTERADMINISTER

PROCUREMENTPROCUREMENT

INPUTS• Procurementdocuments

OUTPUTS

TOOLS & TECHNIQUES

• Contract change control system

• Procurement performance

reviews• Inspections & audits• Performance reporting

• Payment systems• Claims administration

• Records management system

Page 561: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 561/590

PMP Prep – Procurement Slide 35

documents• Project management plan

• Contract• Performance reports

• Approved change requests• Work performance information 

• Procurementdocumentation

• Organizational process assets(updates)

• Change requests• Project Mgmt. Plan (updates)

ADMINISTER PROCUREMENT-ADMINISTER PROCUREMENT-

INPUTSINPUTS1) Procurement Documents2) Project mgmt. plan

3) Contract4) Performance reports5) Approved change requests6) Work performance information

Page 562: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 562/590

PMP Prep – Procurement Slide 36 

ADMINISTER PROCUREMENT-ADMINISTER PROCUREMENT-

T&TT&T  TOOLS & TECHNIQUES

Contract change control system

•  Defines the process to modify a contract• Includes paperwork, tracking systems, dispute

resolution procedures & approval levels necessaryfor authorizing changes, i.e. work authorization

system

P t f i

Page 563: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 563/590

Procurement performance reviews

PMP Prep – Procurement Slide 37

ADMINISTERADMINISTER

PROCUREMENT- T&TPROCUREMENT- T&TInspections and audits

•Required by the buyer & supported bythe seller as specified in contractdocumentation.

• If authorized by contract, someinspections and audit teams can

Page 564: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 564/590

include buyer procurement personnel.

ADMINISTERADMINISTER

PROCUREMENT- T&TPROCUREMENT- T&T• Performance Reporting

How effectively the seller is achieving

contractual objectives

• Payment systems

Payments to the seller are typically

processed by the accounts payable systemof the buyer after certification of satisfactory

Page 565: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 565/590

of the buyer after certification of satisfactorywork by an authorized person on the projectteam. Strictly as per terms of contract.

ADMINISTERADMINISTER

PROCUREMENT- T&TPROCUREMENT- T&T• Claims administration  Contested changes and potential constructive

changes are those requested changes where thebuyer and seller cannot reach an agreement oncompensation for the change, or cannot agree that achange has occurred. These contested changes arevariously called claims, disputes, or appeals.Preferred method of claims/dispute settlement is

through negotiation.• Records management system

Page 566: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 566/590

  It is used by the PM to manage contract andprocurement documentation and records (it is a partof PMIS, section 4.3.2.2)

ADMINISTER PROCUREMENT-ADMINISTER PROCUREMENT-

OUTPUTSOUTPUTS  OUTPUTS

1) Procurement documentation 

It includes, but not limited to, the procurement

contract with all supporting schedules, requestedunapproved contract changes, and approved changerequests. It also includes any seller-developedtechnical documentation and other work performanceinformation such as deliverables, seller performance

reports, warranties, financial documents includinginvoices and payment records, and the result of contract-related inspections

Page 567: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 567/590

contract related inspections.

PMP Prep – Procurement Slide 38

 

ADMINISTER PROCUREMENT-ADMINISTER PROCUREMENT-

OUTPUTSOUTPUTS2) Organizational Process Assets

(updates) – Read page 340

3) Change Requests

4) Project Mgmt. Plan (updates)- Procurement mgmt. plan

Page 568: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 568/590

Procurement mgmt. plan- Baseline schedule (must be updated to reflectthe current expectations

PROCUREMENT PROCESSESPROCUREMENT PROCESSES

PROCESSES BY PROCESS GROUP 

Planning Executing Monitorin

g andcontrolling

Closing

12.1

PlanProcurement

s

12.2

ConductProcurement

s

12.3

AdministerProcurement

s

12.4

CloseProcurement

s

Page 569: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 569/590

PMP Prep – Procurement Slide 39

 

CLOSE PROCUREMENTSCLOSE PROCUREMENTS

WHAT HAPPENS IN CLOSEPROCUREMENTS?

• Close procurements process supports the close project process• Verifies that all work and deliverables were acceptable

• Administrative activities, such as update records to reflect final

results and archive them for future use

• In multi-phase projects, the terms of a contract may only apply to a

given phase of the project.• Unresolved claims may be subject to litigation after close procurements.

• Contract terms & conditions can prescribe specific procedures for

Page 570: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 570/590

• Contract terms & conditions can prescribe specific procedures for 

close procurements.

• Early termination of a contract is a special case of close procurements

& can happen when the buyer & seller mutually agree or when there's

contract default

PMP Prep – Procurement Slide 59

CLOSE PROCUREMENTSCLOSE PROCUREMENTS

INPUTS

• Procurement management plan

OUTPUTS

• Closed procurements

TOOLS & TECHNIQUES• Procurement audits

• Negotiated settlements

• Records management system

Page 571: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 571/590

 

PMP Prep – Procurement Slide 60

g p• Procurement documentation

 

• Closed procurements• Organizational process assets

(updates) 

CLOSE PROCUREMENTS -CLOSE PROCUREMENTS -

INPUTSINPUTS

  INPUTS

•  Procurement Management Plan• Procurement Documentation

Page 572: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 572/590

PMP Prep – Procurement Slide 61

CLOSE PROCUREMENTS – T&TCLOSE PROCUREMENTS – T&T

  TOOLS & TECHNIQUES Procurement Audits• Structured review of all the procurementprocess from Plan Procurement processthrough Administer Procurements

• Objective is to identify successes & failures

that warrant recognition in the preparationand administration of other procurement

Page 573: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 573/590

contracts on the project, or on other projectwithin the performing organization.

 PMP Prep – Procurement Slide 62

CLOSE PROCUREMENTS –CLOSE PROCUREMENTS –

T&TT&TNegotiated Settlements• In all procurement relationships the final equitable settlement

of all outstanding issues, claims, and disputes by negotiation

is a primary goal.

• Whenever settlement cannot be achieved through directnegotiation, some form of alternative dispute resolution (ADR)including mediation or arbitration may be explored.

• When all else fails, litigation in the courts is the least desirableoption.

Records Management System (see section12 3 2 7)

Page 574: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 574/590

Records Management System (see section12.3.2.7)

CLOSE PROCUREMENTS -CLOSE PROCUREMENTS -

OUTPUTSOUTPUTSOUTPUTS

Closed Procurements• The buyer, usually through the authorized procurement

administrator, provides the seller with formal written notice that

the contract has been completed

Organizational Process Assets (Updates) •  Procurement file -a complete set of indexed records• Deliverable acceptance (or rejection)

Page 575: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 575/590

  Deliverable acceptance (or rejection)

• Lessons learned documentation 

PMP Prep – Procurement Slide 63

SAMPLE EXAM QUESTIONSAMPLE EXAM QUESTION

  Question

All the following are true statements about 'Just In Time

Manufacturing' except:

 A. It emphasizes waste reduction.B. It eliminates costs related to material handling, storage,

paperwork and inspection.

C. It emphasizes short-term relationships with suppliers that last

until the delivery is received.

Page 576: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 576/590

D. It reduces inventory to zero or the re-order level.

PMP Prep – Procurement Slide 64

SAMPLE EXAM QUESTIONSAMPLE EXAM QUESTION

Answer - C

 All are true except C.  Amongst the true one’s - But the best answer would be D (for exam).

Just-in-time manufacturing is a process where inventory is

delivered to the factory by suppliers only when it's needed.

Page 577: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 577/590

PMP Prep – Procurement Slide 65

Questions?Questions?

Page 578: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 578/590

PMP Prep – Procurement Slide 66

  This page is Left Blank intentionally

 

Page 579: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 579/590

 

DAY 5

PROFESSIONAL & SOCIALRESPONSIBILITY

Page 580: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 580/590

PMP Prep – Responsibilities Slide 1

AGENDAAGENDA 

Day 1  DAY 4  PMP Exam Prep Introduction Project QUALITY  Management

Project Management Framework  Project RISK  

Management*Introduction Project HUMAN

RESOURCE Management*Project Life Cycle & Organisation

Project Management Processes

  DAY 2  DAY 5  Project INTEGRATION Management ProjectPROCUREMENT Management

Project SCOPE Management Professional & Social

Page 581: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 581/590

j gResponsibility

DAY 3 DAY 6  Project TIME Management REVISION & QUIZ

Project COST Management

PROFESSIONALPROFESSIONAL

RESPONSIBILITY RESPONSIBILITY Responsibilities to the Profession

Compliance with all organizational (PMI) rules & policies

Candidate/Certificant Professional Practice

Advancement of the Profession

Responsibilities to Customers & the Public

Qualifications, experience & performance of professional services

Conflict of interest situations & other prohibited professional conduct

Administration of Code of Conduct

B b i PMP t bid b thi d f d t

Page 582: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 582/590

• By becoming PMP, you agree to abide by this code of conduct.

• PMI reserves the right to suspend or revoke the credentials of any PMP

who is determined to have committed a violation of this code.

PMP Prep – Responsibilities Slide 2

RESPONSIBILITIES TO THERESPONSIBILITIES TO THE

PROFESSIONPROFESSIONCOMPLIANCE WITH ALL ORGANIZATIONAL (PMI) RULES & POLICIES 

• Provide accurate and truthful information directly or indirectly related

to all aspects of PMI Certification Program

• Responsibility to report violations of the PMP Code of Professional

Conduct by individuals in the field of project management

• Responsibility to cooperate with PMl concerning ethics violations and

the collection of related information

Page 583: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 583/590

• Responsibility to disclose to clients, customers, owners or contractors,

significant circumstances that could be construed as a conflict of 

interest or an appearance of impropriety

PMP Prep – Responsibilities Slide 3

RESPONSIBILITIES TO THERESPONSIBILITIES TO THE

PROFESSIONPROFESSIONCANDIDATE/CERTIFICANT PROFESSIONAL PRACTICE  Responsibility to provide accurate, truthful advertising and

representations concerning qualifications, experience andperformance of services

Responsibility to comply with applicable laws, regulations and ethicalstandards governing professional practice in the state/province and/or country when interacting with PMI and when providing projectmanagement services

Responsibility to act in an honest & ethical manner when interacting

with PMI and when providing PM services (another word for ethical ismoral & the dictionary description of ethical is 'Being in accordancewith the accepted principles of right & wrong that govern the conduct

Page 584: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 584/590

with the accepted principles of right & wrong that govern the conductof a profession')

Responsibility to maintain and respect the confidentiality of the contentsof the PMP credential exam.

PMP Prep – Responsibilities Slide 4

RESPONSIBILITIES TO THERESPONSIBILITIES TO THE

PROFESSIONPROFESSIONADVANCEMENT OF THE PROFESSION

• Responsibility to recognize & respect intellectual property developed

or owned by others, and to otherwise act in an accurate, truthful and

complete manner, including all activities related to professional work

and research.

• Responsibility to support & disseminate the PMP Code of Professional

Conduct to other PMI certificants.

Page 585: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 585/590

PMP Prep – Responsibilities Slide 5

RESPONSIBILITIES TO CUSTOMERRESPONSIBILITIES TO CUSTOMER

AND PUBLICAND PUBLICQUALIFICATIONS, EXPERIENCE & PERFORMANCE OFPROFESSIONAL SERVICES

• Provide accurate & truthful representations to the public in

advertising, public statements and in the preparations of estimates,concerning costs, services & expected results

• Maintain & satisfy the scope & objectives of professional services,

unless otherwise directed by the customer 

• Maintain & respect the confidentiality of sensitive information

obtained in the course of professional activities or otherwise where a

Page 586: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 586/590

obtained in the course of professional activities or otherwise where a

clear obligation exists

PMP Prep – Responsibilities Slide 6

RESPONSIBILITIES TO CUSTOMERRESPONSIBILITIES TO CUSTOMER

AND PUBLICAND PUBLICCONFLICT OF INTEREST SITUATIONS & OTHERPROHIBITED PROFESSIONAL CONDUCT

• Ensure that a conflict of interest does not compromise legitimate

interests of a client or influence/interfere with your professional judgments

• (Don't make/participate in a decision if there's an opportunity to

further your own interests or those of an associate, friend or family

member)

• Refrain from offering or accepting inappropriate payments gifts or

Page 587: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 587/590

Refrain from offering  or accepting inappropriate payments, gifts or 

compensation for personal gain unless in conformity with applicable

laws & customs of the country where PM services are being provided

PMP Prep – Responsibilities Slide 7

ADMINISTRATION OF CODE OFADMINISTRATION OF CODE OF

CONDUCTCONDUCTADMINISTRATION OF CODE OF CONDUCT

• By becoming a PMP, you agree to abide by this Code of Conduct

• PMI reserves the right to suspend or revoke the credential of any

PMP who is determined to have committed a violation of thisCode

Page 588: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 588/590

SUMMARY SUMMARY 

 

• Truthfully report information about your PMP status & PM experience.

• You're responsible for the integrity of the PM process, the product &

yourself.

• Avoid putting your own personal gain above project objectives.

• Abide by laws, rules, & regulations of the country you're working in.

• Report instances that might appear to be a conflict of interest. It's

Page 589: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 589/590

always better to inform others of an apparent conflict than to have it

discovered later & your methods called into question.

• Deal with problems.

PMP Prep – Responsibilities Slide 9

SUMMARY SUMMARY 

•  Always strive to maintain honesty in project reporting.

• Respect the use of confidential information and intellectual property &

always verify who has permission to access it & when disclosures are

required.

• Balance the needs & interests of stakeholders with project objectives.

• Respect and understand cultural differences & don't impose your 

beliefs on others.

Page 590: 56445815-PMP

7/31/2019 56445815-PMP

http://slidepdf.com/reader/full/56445815-pmp 590/590

• Culture shock is when you find yourself in a different cultural

environment than you're familiar with. Diversity training can help

project team members with relationship management techniquesabout cultural & ethnic differences.

PMP Prep – Responsibilities Slide 10

Questions?Questions?