57 - environmentclearance.nic.inl&t hydrocarbon engineering ltd hazid study report page no. : 4...
TRANSCRIPT
L&T HYDROCARBON ENGINEERING LTD
HAZID STUDY REPORT
PAGE No. : 2 of 17
CONTRACT No.: 116029CNT
PROJECT : MB PLATFORM AND
PIPELINE PROJECT
DOC. No.: BGEP-LNTH-P117-MBXX-SA-08-188-0002-D
REV. No. : 0
TABLE OF CONTENTS
1 INTRODUCTION 3
1.1 OBJECTIVE 3
1.2 SCOPE OF THE STUDY 3
1.3 BACKGROUND 4
1.4 EXISTING FACILITIES AND INTERFACE PROJECTS 5
2 DEFINITIONS 6
3 ABBREVIATIONS 7
4 HAZID METHODOLOGY 9
4.1 PREAMBLE 9
4.2 HAZID PROCESS 9
4.3 CONDUCTING THE HAZID SESSIONS 9
4.4 GUIDEWORDS CONSIDERED FOR THE HAZID STUDY 10
5 RECOMMENDATIONS 14
5.1 HAZID STUDY RECOMMENDATIONS 14
6 REFERENCES 16
7 ANNEXURES 17
I. HAZID Attendance Sheet 17
II. HAZID WORKSHEET 17 III. TOR FOR HAZID WORKSHOP 17
L&T HYDROCARBON ENGINEERING LTD
HAZID STUDY REPORT
PAGE No. : 3 of 17
CONTRACT No.: 116029CNT
PROJECT : MB PLATFORM AND
PIPELINE PROJECT
DOC. No.: BGEP-LNTH-P117-MBXX-SA-08-188-0002-D
REV. No. : 0
1 INTRODUCTION
1.1 OBJECTIVE
The objectives of the HAZID study are to:
Identify potential hazards and reasonably foreseeable accident events which could lead to
escalation, injuries to personnel or fatalities, asset damage and environmental impact;
Identify engineering and / or procedural safeguards already incorporated into the design that will
help reduce the likelihood or the severity of consequences related to the identified threat; and
Identify any actions required to help reduce the risk from the threat identified if it is found that the
engineering controls are insufficient relative to the severity of the threat.
1.2 SCOPE OF THE STUDY
The scope of work is to conduct HAZID study for the proposed “MB Platform and Pipeline Project” in
accordance with documents / drawings (such as layout, design basis, PFD, etc.). Facilities include in the
project scope are:
MB Wellhead Platform
Pipelines between MA Platform and MB Platform
Pipelines between MB Platform and PPA Platform
Modifications at MA Platform
Modifications at PPA Platform
L&T HYDROCARBON ENGINEERING LTD
HAZID STUDY REPORT
PAGE No. : 4 of 17
CONTRACT No.: 116029CNT
PROJECT : MB PLATFORM AND
PIPELINE PROJECT
DOC. No.: BGEP-LNTH-P117-MBXX-SA-08-188-0002-D
REV. No. : 0
1.3 BACKGROUND
Oil & Natural Gas Corporation (ONGC), Reliance Industries Ltd (RIL) and BG Exploration and Production
India Limited (BGEPIL) are joint operators of the Panna-Mukta offshore oil & gas production field
situated in the Arabian Sea, off the west coast of India near Mumbai. The Mukta Field is located about
120 kilometres offshore northwest of Mumbai, India.
Following sketch provides overall view of Panna and Mukta field.
The Panna field has eleven wellhead platforms (including PL) and the well fluid is routed to central
Process Processing Platform (PPA). PPA is bridge connected to PA wellhead platform, PQ living quarter
platform and PFP flare platform. Mukta field currently has one platform MA with its well fluids sent to
PPA via PA and processed along with Panna crude.
The MB wellhead platform will have nine (9) production slots in approximately 63 m of water depth. The
Mukta field is located west of the Panna and MB wellhead platform is located approximately 25 km west
of Panna Processing Platform (PPA).
As existing MA-PA pipeline is not operational, it is planned to evacuate MA production through new MB-
PPA pipeline and also MB will supply gas lift to MA.
L&T HYDROCARBON ENGINEERING LTD
HAZID STUDY REPORT
PAGE No. : 5 of 17
CONTRACT No.: 116029CNT
PROJECT : MB PLATFORM AND
PIPELINE PROJECT
DOC. No.: BGEP-LNTH-P117-MBXX-SA-08-188-0002-D
REV. No. : 0
1.4 EXISTING FACILITIES AND INTERFACE PROJECTS
PPA is the main processing platform. The other unmanned wellhead platforms connected to main
processing platform PPA via subsea pipelines are PB, PC, PD, PE, PF, PG, PH, PJ, PL & MA. PA Wellhead
platform is bridge linked to PPA. PQ Platform which is a living quarter is also bridge linked to PPA and
PFP Flare platform is bridge connected to PPA. MB Wellhead platform is a new unmanned platform being
built as part of the MB Platform and Pipeline project and will be connected to PPA via subsea pipelines.
The normal means of access to the MB platform shall primarily be by helicopter and alternatively, in
extremely rare occasions, by supply boat. Operators are not required to be present on the platform to
log any process parameters or perform well tests. This can all be carried out remotely.
Key design features of the new MB wellhead platform are:
It is normally unmanned wellhead platform.
The wellhead platform will be designed for automatic operation with minimum intervention by
operations personnel.
The facility control and safety system is to provide monitoring, control, safe operation and
shutdown functionality of the platform in line with BGEPIL unmanned and minimum facilities
philosophy.
L&T HYDROCARBON ENGINEERING LTD
HAZID STUDY REPORT
PAGE No. : 6 of 17
CONTRACT No.: 116029CNT
PROJECT : MB PLATFORM AND
PIPELINE PROJECT
DOC. No.: BGEP-LNTH-P117-MBXX-SA-08-188-0002-D
REV. No. : 0
2 DEFINITIONS
In this document, the following definitions apply:
Term Definition
Company BGEPIL
Engineering Contractor Larsen & Toubro Limited
Safety Consultant DNV GL
L&T HYDROCARBON ENGINEERING LTD
HAZID STUDY REPORT
PAGE No. : 7 of 17
CONTRACT No.: 116029CNT
PROJECT : MB PLATFORM AND
PIPELINE PROJECT
DOC. No.: BGEP-LNTH-P117-MBXX-SA-08-188-0002-D
REV. No. : 0
3 ABBREVIATIONS
In this document, the following acronyms and abbreviations apply:
Abbreviations Definition
AFP Active Fire Protection
ALARP As Low As Reasonably Practicable
ANSI American National Standard Institute
API American Petroleum Institute
ASME American Society of Mechanical Engineering
BGEPIL BG Exploration and Production India Limited
BS British Standards
CAA Civil Aviation Authority
CR Control Room
DBB Double Block & Bleed
EEMUA Engineering Equipment and Materials Users Association
EIA Environmental Impact Assessment
EMERA Escape, Muster, Evacuation and Rescue Analysis
EMS Environmental Management System
ENVID Environmental (Hazard) Identification
ESD Emergency Shutdown
FERA Fire & Explosion Risk Analysis
FGS Fire and Gas System
FWHP & FWHT Flowing Wellhead Pressure/Temperature
HAZID Hazard Identification Study
HAZOP Hazard and Operability Study
HMI Human Machine Interface
HRA Health Risk Assessment
HSSE Health, Safety, Security & Environment
IALA International Assoc. of Lighthouse Authorities
ICSS Integrated Control and Safety Systems
IDLH Immediately Dangerous to Life or Health
IEC International Electro-technical Commission
IMO International Maritime Organization
IP Institute of Petroleum
IR Infra-Red
IRPA Individual Risk Per Annum
IS Indian Standards
ISO International Standards Organization
LEL Lower Explosive Limit
L&T HYDROCARBON ENGINEERING LTD
HAZID STUDY REPORT
PAGE No. : 8 of 17
CONTRACT No.: 116029CNT
PROJECT : MB PLATFORM AND
PIPELINE PROJECT
DOC. No.: BGEP-LNTH-P117-MBXX-SA-08-188-0002-D
REV. No. : 0
Abbreviations Definition
LED Light-emitting Diode
LP Low Pressure
MAE Major Accident Events
mg/l milligrams / liter
MMSCFD Million Standard Cubic Feet / Day
NFPA National Fire Protection Association
NIOSH National Institute for Occupational Safety and Health
OISD Oil India Safety Directorate
ONGC Oil & Natural Gas Corporation Ltd.
OSHA Occupational Safety and Health Administration
PA Panna A Wellhead Platform
PCS Process Control System
PFP Passive Fire Protection
PH Panna H Wellhead Platform
PJ Panna J Wellhead Platform
PK Panna K Wellhead Platform
PL Panna L Wellhead Platform
PLL Potential Loss of Life
POB Person on Board
PPA Panna Processing Platform
PPM Part Per Million
PQ Panna Living Quarter
PSD Process Shutdown
PSV Pressure Safety Valve
RIL Reliance Industries Ltd
SDV Shutdown Valve
SIMOPS Simultaneous Operations
SIL Safety Integrity Level
SOLAS Safety of Life At Sea
TR Temporary Refuge
UPS Uninterruptible Power Supply
USD Unit Shutdown
UV Ultraviolet
VHF Very High Frequency
WHP Well Head Platform
L&T HYDROCARBON ENGINEERING LTD
HAZID STUDY REPORT
PAGE No. : 9 of 17
CONTRACT No.: 116029CNT
PROJECT : MB PLATFORM AND
PIPELINE PROJECT
DOC. No.: BGEP-LNTH-P117-MBXX-SA-08-188-0002-D
REV. No. : 0
4 HAZID METHODOLOGY
4.1 PREAMBLE
The HAZID study was conducted using the conventional guideword approach. The principle of HAZID is
that accidents occur when operations are conducted under conditions that deviate from the desired
intentions. Therefore, HAZID technique starts by understanding the design intentions of a particular line
or a vessel and finds out meaningful deviations that can occur in the process. The process then is to
understand these deviations and the consequences of these deviations, and detect which of these
consequences will result in a major hazard.
It is used to examine the upcoming MB Platform and Pipeline Project in order to identify and evaluate
problems that may represent risks to personnel or equipment, or prevent efficient operation.
4.2 HAZID PROCESS
The guidewords relevant to MB platform are generated using BG standards. The possible causes are
listed together with the consequences with respect to hazards. The existing protection or safeguard to
reduce the possibility of undesirable deviations occurring or to limit the severity of the consequences
are considered by the team to determine what actions to recommend, if any, to improve the safety of
the process system. All aspects are discussed by the team and recorded in the worksheet.
4.3 CONDUCTING THE HAZID SESSIONS
The guideword was examined systematically by an expert team comprising experienced Process
Engineer, Project Engineer, Instrument, Client(s) Representatives, HSE Engineer/representative, Piping
Engineer, Electrical Engineer, Civil Engineer, Mechanical Engineer, chaired and scribed by DNVGL). The
examination was conducted on the relevant layouts and queries raised systematically on every part of it
to discover how deviations from the intention of the design can occur and determine whether these
deviations can give rise to hazards and whether further protective measures, altered operating
procedures or design changes were required.
The questioning was focused around a number of guide words which were derived from method study
techniques. The guide words ensure that the questions posed to test the integrity of each part of the
design explored every conceivable way in which the operation could deviate from the design intention.
Some of the causes were deemed unlikely and hence the derived consequences could be ignored. Some
of the consequences were noted to be trivial and were not considered further. The potential problems
were then evaluated for existing safeguards and requirement for remedial action. The HAZID team took
note of a fact that immediate solution to a problem was not always obvious and could need further
consideration and clarification.
The HAZID studies were conducted under the presence of a Chairman who launched the questions and
guided the discussions. All decisions taken were recorded by the secretary in the form of worksheets.
L&T HYDROCARBON ENGINEERING LTD
HAZID STUDY REPORT
PAGE No. : 10 of 17
CONTRACT No.: 116029CNT
PROJECT : MB PLATFORM AND
PIPELINE PROJECT
DOC. No.: BGEP-LNTH-P117-MBXX-SA-08-188-0002-D
REV. No. : 0
4.4 GUIDEWORDS CONSIDERED FOR THE HAZID STUDY
The selection of the guideword was made based an understanding of the system, on past experience
and engineering judgment and the operations to be conducted. The relevant guidewords & Hazardous
event considered are summarized below. These have been further expanded during the HAZID session.
List of HAZID study Guidewords
Guideword Hazardous Event Description
Natural and Environmental Hazards
Earth quake
Erosion
Subsidence
Weather
Process Hazards
Drilling
Shallow Gas
Production
Work Over/Wire Line
Wellhead & Process
Start-up/ Shutdown
Process release( un-ignited )
Process release( ignited)
Well Blow out
Effects of one module to another
External to Modules
Flare/ Vent System
Chemical reaction
Overpressure/ Vacuum
Overfill
Corrosion
Erosion
L&T HYDROCARBON ENGINEERING LTD
HAZID STUDY REPORT
PAGE No. : 11 of 17
CONTRACT No.: 116029CNT
PROJECT : MB PLATFORM AND
PIPELINE PROJECT
DOC. No.: BGEP-LNTH-P117-MBXX-SA-08-188-0002-D
REV. No. : 0
Guideword Hazardous Event Description
Pipelines
Pig launchers/ Receivers
Risers
Flow-lines/Pipelines
Utilities
Power - Solar Power
Power - wind Power
Battery
Power - DG set.
Fuel Gas
Plant Air/ Instrument Air
Heating Medium
Refrigerant
Produced Water
Diesel Fuel
Aviation Fuel
Inert Gas
Drains
Other Hazardous Chemicals
Radioactive
Toxic
Asphyxiant
Corrosive
Explosive
Biocide
Impact & Collision
Supply Boats
Standby Boats
Diving Vessels
Well Service Vessels
Drilling Rig
L&T HYDROCARBON ENGINEERING LTD
HAZID STUDY REPORT
PAGE No. : 12 of 17
CONTRACT No.: 116029CNT
PROJECT : MB PLATFORM AND
PIPELINE PROJECT
DOC. No.: BGEP-LNTH-P117-MBXX-SA-08-188-0002-D
REV. No. : 0
Guideword Hazardous Event Description
Flotel
Fishing
Mud-level
Aircraft
Helicopter
Military
Falling Objects
Cranes
Drilling Derrick
Others
Missiles
Rotating machinery disintegration
Explosion due to air ingress into flammable systems
Explosives
Bursting of pressurized system
Structural Design Failure
Foundations
Structure
Flare Tower
Drilling Derrick
Cranes
Joints failure in Jacket
Drawdown
Human Error
Operation
Maintenance
Construction
Mobile/Floating Installation
Foreseen Combined Operation
Loss of Position
Mooring failure
Dynamic positioning system failure
Stability control
L&T HYDROCARBON ENGINEERING LTD
HAZID STUDY REPORT
PAGE No. : 13 of 17
CONTRACT No.: 116029CNT
PROJECT : MB PLATFORM AND
PIPELINE PROJECT
DOC. No.: BGEP-LNTH-P117-MBXX-SA-08-188-0002-D
REV. No. : 0
Guideword Hazardous Event Description
Leg collapse / Punch through
Others
Communication Failure
Power supply failure
Process Control Failure
Diving
Combined Operation
Confined space entry
Adverse weather condition
E & I Evacuation
Vessel Entry
L&T HYDROCARBON ENGINEERING LTD
HAZID STUDY REPORT
PAGE No. : 14 of 17
CONTRACT No.: 116029CNT
PROJECT : MB PLATFORM AND
PIPELINE PROJECT
DOC. No.: BGEP-LNTH-P117-MBXX-SA-08-188-0002-D
REV. No. : 0
5 RECOMMENDATIONS
5.1 HAZID STUDY RECOMMENDATIONS
Below table presents a summary of the recommendations from the HAZID workshop review.
HAZID Study Recommendations
S.No. Action Action By Safety
Priority
1. Facility assessment for MA & PPA to be carried out in view with
project activities. BG
2. HAZCON / Constructability review to recognize the soil
subsidence aspect. L&T Yes
3. Review/ ensure wind speed consideration for different objects
as per design basis through the procurement phase. L&T / BG Yes
4. HAZCON / Constructability/SIMOPS/Drilling review to recognize
the effect of extreme weather. L&T Yes
5. HAZCON / Constructability/SIMOPS to recognize the effect of
extreme weather. L&T Yes
6. Check design of Caisson pump & motor (Physical barriers),
locate start/stop switch at sub-cellar deck. L&T Yes
7. HAZCON & SIMOPS to address the crane operation during
installation. L&T Yes
8. Provision for secondary retention device to be made for light
weight equipment. L&T / BG Yes
9. Review need for lightning arrestor. L&T Yes
10. Review requirement of automatic CO2 system L&T Yes
11. FERA study to establish the requirement for passive fire
protection & explosion protection. L&T Yes
12. EMERA & FERA to confirm adequacy of egress route. L&T Yes
13. Check/ update SOPs for addressing pyrophoric iron. BG Yes
14. Method statement, JSA to be carried out in advance with
appropriate project definition for retrieval & installation. L&T Yes
15. Method statement, JSA to be carried out in advance with
appropriate project definition and preparation of bridging and
interface document.
L&T Yes
16. Method statement, JSA to be carried out in advance with
appropriate project definition L&T Yes
17. HAZCON/Constructability review to address Handling of
radioactive materials. L&T Yes
18. F&G detector layout to be reviewed based on Gas Dispersion L&T Yes
L&T HYDROCARBON ENGINEERING LTD
HAZID STUDY REPORT
PAGE No. : 15 of 17
CONTRACT No.: 116029CNT
PROJECT : MB PLATFORM AND
PIPELINE PROJECT
DOC. No.: BGEP-LNTH-P117-MBXX-SA-08-188-0002-D
REV. No. : 0
S.No. Action Action By Safety
Priority
study. ( For brownfield scope, ensure adequacy for MA & PPA)
19. Check adequacy of safety measures for injected chemicals to
be in line with MSDS. L&T Yes
20. Any diving operation will be carried out by project specific JSA
and the diving vessel confirms to BG standard and marine
assurance requirement.
L&T Yes
21. Dropped object study to cover due to crane / heavy lift
operations envisaged with the facility. Required safety
measures to be identified subsequently.
L&T Yes
22. Ensure VHF is able to cover approximate 25 KM L&T Yes
23. Procedure to facilitate vessel entry L&T Yes
24. E&I room to be provided with internal door release for quick
evacuation L&T Yes
25. Ensure vessel entry and positive isolation is in line with BG
requirement and all internal section are capable of cleaning
and inspection
L&T Yes
During workshop, 25 recommendations were recorded out of which 24 action items are identified as
critical actions which require immediate attention for design.