6. fap project showcase april 2015 (final). fap proj… · 16/04/2015  · capital project program...

11
1 Central Arizona Project Finance, Audit, and Power Committee Capital Project Program Report Ryan Johnson April 16, 2015 Agenda o Hydrology Improvements at Centennial Wash (610448) o Discharge Valve Replacement at BRD, PIC, Red(610453) o Elevator System Control/Drive Replacement (610455) o Station Service Battery Charger Replacement (610469) o Trashrake Installation at Mark Wilmer Pumping Plant (610476) 2 FAP Agenda Number 6.

Upload: others

Post on 06-Oct-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 6. FAP Project Showcase April 2015 (FINAL). FAP Proj… · 16/04/2015  · Capital Project Program Report Ryan Johnson April 16, 2015 Agenda o Hydrology Improvements at Centennial

1

Central Arizona ProjectFinance, Audit, and Power Committee

Capital Project Program Report

Ryan JohnsonApril 16, 2015

Agenda

o Hydrology Improvements at Centennial Wash (610448)

o Discharge Valve Replacement at BRD, PIC, Red(610453)

o Elevator System Control/Drive Replacement (610455)

o Station Service Battery Charger Replacement (610469)

o Trashrake Installation at Mark Wilmer Pumping Plant (610476)

2

FAP Agenda Number 6.

Page 2: 6. FAP Project Showcase April 2015 (FINAL). FAP Proj… · 16/04/2015  · Capital Project Program Report Ryan Johnson April 16, 2015 Agenda o Hydrology Improvements at Centennial

2

Hydrology Improvements at Centennial Wash -610448

32010 Storm Flooding, Looking Northeast at Pool 6 Dike

100‐yr, 24‐hr storm event flow model

Centennial Wash Area Overview

Hydrology Improvements at Centennial Wash -610448

Project Scopeo Address exposure to current hydrologyo 8 miles, North-side canal embankment elevation modificationso Increase overchute capacityo Additional flood-water diversion improvements at Centennial Wash Siphon inlet

Design Phaseo Design Consultant: JE Fullero Anticipate to seek Board contract award at May Board Meetingo Notice to Proceed anticipated in May for approximately 6 month design duration

Statuso Hydrology study and assessment phase completed in March 2013o Scope clarification and negotiations complete with JE Fullero 6-month construction duration February – August 2016o Project Close-out 4th Qtr 2016

4

($000) Pre‐2014 2014 2015 2016 Totals Variance

Budget 0  0  273.3  992.1 $1,265.4

(530.3) ‐41.9%Actuals + Forecast 0  0  489.9  1,305.8  $1,795.7 

Page 3: 6. FAP Project Showcase April 2015 (FINAL). FAP Proj… · 16/04/2015  · Capital Project Program Report Ryan Johnson April 16, 2015 Agenda o Hydrology Improvements at Centennial

3

5

Hydrology Improvements at Centennial Wash -610448

2010 Storm Flooding, Looking North at Overchute

CBM HMI Screen6

Hydrology Improvements at Centennial Wash -610448

2010 Storm Flooding, Looking North at Centennial Siphon Inlet

Page 4: 6. FAP Project Showcase April 2015 (FINAL). FAP Proj… · 16/04/2015  · Capital Project Program Report Ryan Johnson April 16, 2015 Agenda o Hydrology Improvements at Centennial

4

Discharge Valve Replacement at Brady, Picacho & Red Rock Pumping Plants - 610453

Project Scopeo Replace nineteen, 54-inch unit discharge valves & hydraulic valve actuator for each o Valve foot support modificationso Controls system

Design Phaseo CAP internal Engineering designo Design provides individual work packages for construction in 2015, 2016, 2017,

respectively

Statuso Pilot project competed October 2013 with Pentair, triple-eccentric butterfly valveo Coatings deficiencies and supplier responsiveness resulted in solicitation for qualified

valve suppliero Reliability completed Failure Modes and Effects Analysis (FMEA) for various valves in

May 2014 o Valve contract awarded to Crispin for 2 butterfly valves at this timeo Anticipate install of 2 valves in 2015, 6 valves in 2016, 10 valves in 2017 during plant

outage windows.

7

($000) Pre‐2014 2014 2015 2016 2017 2018 Totals Variance

Budget 0  563.0  1,969.2  39.4  0  0  2,571.7 

39.5 1.5%Actuals + Forecast 0  40.2  324.0  894.4  1,235.2  38.3 2,532.2 

8

Discharge Valve Replacement at Brady, Picacho & Red Rock Pumping Plants - 610453

Existing Allis Chalmer Discharge Valve on Pedestal

FLOWFLOW

Page 5: 6. FAP Project Showcase April 2015 (FINAL). FAP Proj… · 16/04/2015  · Capital Project Program Report Ryan Johnson April 16, 2015 Agenda o Hydrology Improvements at Centennial

5

9

Discharge Valve Replacement at Brady, Picacho & Red Rock Pumping Plants - 610453

October 2013 Pilot Valve Install at Red Rock Unit 2, Pentair Triple‐eccentric Butterfly Valve 

ActuatorHydraulic Actuator

FLOWFLOW

Project Scopeo Replace elevator controls and equipment, power circuits, HVAC, and fire alarm system

integrationo Address any code-compliance concernso Salt Gila, Brady, Picacho, Little Harquahala, Mark Wilmer Service Bay

Design Phaseo Design Consultant: Caliente Construction / LSW o Notice to Proceed: November 2014o Design Completion: August 2015o Design Phase: $306K

Statuso Project Steering Committee re-prioritized project into two phases based on replacement

priority in November 2013. Second phase is planned for 2019, 2020, and 2021 and includes Bouse, Hassayampa, Mark Wilmer Unit Bay, San Xavier, Brawley, Waddell, Black Mountain, Snyder Hill, and Headquarters Building 2. Budget will be submitted for approval at that time.

o Public solicitation for Statement of Qualifications complete in 2014.o Design 40% completeo Construction phase starts June 2015 (4-5 months per site); limited outage periodo Close-out 1st Quarter 2017

Elevator System Control/Drive Replacement –610455

10

($000) Pre‐2014 2014 2015 2016 2017 2018 2019 Totals Variance

Budget 0  453.0  1,726.7 2,034.1 1,914.1 1,656.1 30.4 7,814.3 3,874.1 49.6%

Actuals + Forecast 0  121.8 1,939.5 1,829.8 49.1 3,940.2 

Page 6: 6. FAP Project Showcase April 2015 (FINAL). FAP Proj… · 16/04/2015  · Capital Project Program Report Ryan Johnson April 16, 2015 Agenda o Hydrology Improvements at Centennial

6

Elevator System Control/Drive Replacement -610455

11Picacho Existing Control Cabinet and CircuitsPicacho Elevator Motor & Drive in Equipment Room

Elevator System Control/Drive Replacement -610455

12

Brady Elevator Shaft Ceiling and Cables, looking up

Brady Elevator Shaft Pit, looking down

Page 7: 6. FAP Project Showcase April 2015 (FINAL). FAP Proj… · 16/04/2015  · Capital Project Program Report Ryan Johnson April 16, 2015 Agenda o Hydrology Improvements at Centennial

7

Station Server Battery Charger Replacement -610469Project Scopeo Replace station service battery chargerso Replace individual protection and metering devices; remote battery monitoringo All 15 Pumping Plants

Design Phaseo Design Consultant: Brown & Caldwello Notice to Proceed: June 2014o Design Complete: December 2014o Design Contract: $167,250

Statuso Design completeo Equipment procurement awarded October 2014; Installation awarded February

2015o Construction Start Date: April 2015 at Black Mountain (2 weeks per site)o Close-out 2nd Qtr 2016

13

($000) Pre‐2014 2014 2015 2016 Totals Variance

Budget 0  637.5  1,388.3 0  2,025.8

280.6 13.9%Actuals + Forecast 0  281.5 1,349.1 114.6  1,745.2 

14Factory Acceptance Testing of New C&D Battery Chargers

Station Service Backup Battery Bank, Typical

Existing Battery Chargers, Typical

New Arga Battery Monitoring Device

Page 8: 6. FAP Project Showcase April 2015 (FINAL). FAP Proj… · 16/04/2015  · Capital Project Program Report Ryan Johnson April 16, 2015 Agenda o Hydrology Improvements at Centennial

8

Trashrake Installation at Mark Wilmer Pumping Plant - 610476

15

Trashrake Installation at Mark Wilmer Pumping Plant - 610476 Project Scopeo Provide an automated trash rake system; address weed and debris loadingo Provide for weed handling and staging improvementso Conveyor systems for weed handling and disposal operations

Design Phaseo Design Consultant: Brown & Caldwello Notice to Proceed: August 2014o Design Complete: May 2015o Design Contract: $457,998

Statuso Completed Weed Removal Study in July 2012o Construction Manager at Risk (CMAR) Selected August 2014: PCLo Prototype Field Testing completed in February 2015o Design 90% completeo Trashrake equipment lead time: June – November 2015;o Construction Phase: January – June 2016o Close-out: 1st Qtr 2017

16

($000) Pre‐2014 2014 2015 2016 2017 Totals Variance

Budget 0  169.2  3,195.1 3,183.3  14.3  6,561.9 

(93.7) ‐1.4%Actuals + Forecast 0  376.0  3,297.1  2,968.3  14.3  6,655.7 

Page 9: 6. FAP Project Showcase April 2015 (FINAL). FAP Proj… · 16/04/2015  · Capital Project Program Report Ryan Johnson April 16, 2015 Agenda o Hydrology Improvements at Centennial

9

Trashrake Installation at Mark Wilmer Pumping Plant - 610476

17Weed Removal & Handling in 2010

Trashrake Installation at Mark Wilmer Pumping Plant - 610476

18Weed Collection Boat

Page 10: 6. FAP Project Showcase April 2015 (FINAL). FAP Proj… · 16/04/2015  · Capital Project Program Report Ryan Johnson April 16, 2015 Agenda o Hydrology Improvements at Centennial

10

Trashrake Installation at Mark Wilmer Pumping Plant - 610476

19

Mark Wilmer Forebay Deck

Mark Wilmer Deck Bulkhead Gate Guides

Trashrake Installation at Mark Wilmer Pumping Plant- 610476

20Mark Wilmer Trashrake Installation, 90% Design

Similar Trashrake Installation at a Florida Water District

Page 11: 6. FAP Project Showcase April 2015 (FINAL). FAP Proj… · 16/04/2015  · Capital Project Program Report Ryan Johnson April 16, 2015 Agenda o Hydrology Improvements at Centennial

11

Questions?

21