7 slip form construction

Upload: sivaram-kottali

Post on 06-Jul-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/18/2019 7 Slip Form Construction

    1/11

    2/1

    COLLEGE OF ARCHITECTURE AND PLANNING

    Department of Architecture and Building Sciences

    Dr. Mohammed Ghonim

    7. SLIP-FORM CONSTRUCTION

    ARCH 436Contem porary Building Construction Met hods

    Lecture Objectives

    Upon completion of this lecture, the student will be able to:

    1. Explain the concept of slip-form construction.

    2. Discuss the advantages of slip-form construction.

    3. List the types of slip-forming.

    4. Describe the construction process of slip-forming.

  • 8/18/2019 7 Slip Form Construction

    2/11

    2/1

    Lecture Content

    •   Introduction.

    •   Historical Brief.

    •   Advantages of Slip-form Construction.

    •   Types of Slip-form Construction.

    •   Vertical Slip-form.

    •   Horizontal Slip-form.

    •   The Benefits of Tilt-up Construction.

    •   Applications of Slip-form Construction.

    •   The Slip-form Rig.

    •   Structural Concerns.

    •   Construction Sequence.

    •   Tapered Slip-forming.

    •   Jump Form.

    Introduction

    Slip form construction, or continuously formed construction, is a construction method in

    which concrete is poured into a continuously moving form.

    Basically, this method involves the continuous placing of concrete in a shallow mold having

    the same plan as the building to be constructed. This rigid mold, or "slip-form" as it is called,

    forms the working deck which is jacked slowly upwards at a controlled rate until the required

    elevation is reached.

    KAFD, Riyadh, KSA

  • 8/18/2019 7 Slip Form Construction

    3/11

    2/1

    Introduction

    Slip-form Technique is one of the most productive techniques for construction of High-rise

    structures like communication towers, chimneys, bridge piers, silos etc. Vertical Slip forming

    allows concrete to be erected as a monolithic or a joint-less structure, while reducing overall

    project duration. Slipform paving has enabled concrete road pavements, airport aprons,taxiways, runways, canal lining etc. Slip-form Technique has also been successfully applied

    to various structures including offshore drilling platforms and nuclear facilities etc.

    Historical Brief 

    The slip forming technique was in use by the early 20th century for building silos and grain

    elevators. James MacDonald, of MacDonald Engineering of Chicago was the pioneer in

    utilizing slip form concrete for construction. His concept of placing circular bins in clusters

    was patented, with photographs and illustrations, contained in a 1907 book, “The Design Of 

    Walls,Bins,And Grain Elevators”.

    The technique was introduced to residential and commercial buildings in the late 1960s.[2]

    One of Its first uses in high-rise buildings the United States was on the shear wall supported

    apartment building at Turk & Eddy Streets in San Francisco, CA, in 1962, built by the San

    Francisco office of MacDonald Engineering. The first notable use of the method in a

    residential/retail business was the Skylon Tower in Niagara Falls, Ontario, which was

    completed in 1965. Another unusual structure was the tapered buttress structures for the

    Sheraton Waikiki Hotel in Honolulu, Hawaii, in 1969. Another shear wall supported structure

    was the Casa Del Mar Condominium on Key Biscayne, Miami, FL in 1970.

    Skylon Tower, 1965 Sheraton Waikiki, 1969 Casa Del Mar,1970

  • 8/18/2019 7 Slip Form Construction

    4/11

    2/1

    Types of Slip-form Construction

    1- Vertical Slip-form

    In vertical slip forming, the concrete formmay be surrounded by a platform on which

    workers stand, placing steel reinforcing

    rods into the concrete and ensuring a

    smooth pour. Together, the concrete form

    and working platform are raised by means

    of hydraulic jacks. Generally, the slip-form

    rises at a rate which permits the concrete to

    harden by the time it emerges from the

    bottom of the form.

    Types of Slip-form Construction

    2- Horizontal Slip-form

    In horizontal slip forming for pavement and traffic

    separation walls, concrete is cast, vibrated, worked, and

    settled in place while the form itself slowly moves

    ahead. This method was initially devised and utilized

    in Interstate Highway construction initiated during the

    1950s.

  • 8/18/2019 7 Slip Form Construction

    5/11

    2/1

    The Benefits of Tilt-up Construction

    Factor Description

    1. Time   High production rates can be

    achieved by careful planning of construction process.

    2. Durability   Better concrete; a joint less andwatertight structure.

    3. Cost   Slip forms showed cost advantagesfor more than 20 stories and larger 

    than 600 m2 formed area per floor.

    4. Maintenance   Availability of the different workingplatforms in the formwork system

    allows the exposed concrete at thebottom of the rising formwork to be

    finished, making it an integral part of 

    the construction process.

    5. Flexibility   Certain formwork systems permitconstruction of tapered cores and

    towers.

    6. Labor    Slip form systems require a few buthighly skilled workers.

    7. Machinery   Slip form construction minimizescrane use.

    Applications of Slip-form Construction

    Slip-form construction is used for tall structures, such as towers, buildings, and dams, as well

    as horizontal structures, such as roadway barriers. It enables continuous, non-interrupted,

    cast-in-place joint-less concrete structures which have superior performance characteristics

    over construction methods using discrete form elements. Slip forming relies on the quick-

    setting properties of concrete, and requires a balance between quick-setting capacity and

    workability.

       I  n  n   C  a  n  a   l ,   G  e  r  m  a  n  y

    Capital Gate Tower, Abu Dhabi

       K   i  n  g   A   b   d  u   l  -   A  z   i  z   A   i  r  p  o  r   t

  • 8/18/2019 7 Slip Form Construction

    6/11

    2/1

    The Slip-form Rig

    The slip form rig includes three

    working levels, or decks as follows:

    1. The uppermost deck is used to

    install vertical reinforcing steel

    and to facilitate placement of the

    concrete .

    2. The middle deck is the main

    working platform. It provides the

    locations where gates, ladder 

    platforms, and maintenance

    decks are formed. Usually ,the

    middle deck supports the

    hydraulic lifting system as well

    as provides an area where

    reinforcing steel is assembled

    and concrete is poured and

    vibrated .

    3. The lower deck provides access

    to the newly exposed concreteso that surface finishing

    processes can be completed and

    design specifications can be

    met.

    Structural Concerns

    It is necessary to use a low slump concrete in slip forming processes where the formwork is

    moved horizontally in order for the slab or pavement to retain its shape as the paving machine

    advances. Presently, slip form pavements use "high early strength" concrete, which achieves

    the required strength in approximately 12 hours, as compared to conventional concrete which

    requires 5-14 days. The water content of this type of concrete is lower than it is for standard

    material, resulting in improved strength as well as improved resistance to the permeation of 

    salt, thereby increasing the finished concrete’s resistance to deterioration from chloride ions.

  • 8/18/2019 7 Slip Form Construction

    7/11

    2/1

    Construction Sequence

    1. The formwork and the access platform are

    assembled on the ground.

    2. The assembly is raised using hydraulic jacks which are mounted on strategically

    located steel frames to lift the formwork as

    the concrete is poured into the forms.

    3. As the formwork rises continuously,

    continuous concrete and rebar supply are

    needed until the operation is finished.

    4. As the formwork is raised, reinforcement is

    held in the correct position using guides,

    horizontal reinforcement is tied to the

    vertical reinforcement.

    5. Concrete is poured into the forms in layers

    of approximately 200 mm. The setting

    rates of concrete are constantly monitored

    to ensure that it is matched with the speedat which the forms are raised. The jacks lift

    the form approximately 25mm per stroke

    generally producing a slip-forming rate of 

    300 mm per hour.

    6. Slipforming can be performed on either 

    a continuous basis (i.e. 24 hours per 

    day), or a discontinuous basis (i.e.

    pouring to a predetermined height

    usually within one working day) .

    7. Blockouts for doors and windows can

    be formed with either timber or steel.

    These are in-stalled as the slipform

    proceeds and can be stripped from the

    trailing decks .

    8. Recesses are made to host the

    connections between the beams, slabs

    and the slipform walls

    9. When the formed concrete is exposedfrom the bottom of the steel form

    panels it can be sponged or treated if 

    required .

    10. At the end of the operation the

    formwork is removed using a crane, the

    entire process is thoroughly inspected

    and highly controlled

    Construction Sequence

  • 8/18/2019 7 Slip Form Construction

    8/11

    2/1

    Construction Sequence

    Slip forming relies on the quick-setting properties of concrete, and requires a balance

    between quick-setting capacity and workability. Concrete needs to be workable enough to

    be placed into the form and consolidated via vibration. This strength is needed because the

    freshly set concrete must not only permit the form to "slip" passed the concrete withoutdisturbing it, but also support the pressure of the new concrete as well as resist collapse

    caused by the vibration of the compaction machinery.

    Tapered Slip-forming

    Slip-forming is also used in the construction of conical chimneys, cooling towers, piers and

    other tall concrete structures involving constant or changing thicknesses in walls, diameters

    and/or shapes

    A form is used with sections which overlap so that one gradually slides over the other. This is

    commonly done in chimney construction but it is not satisfactory for architectural concrete

    because the lap shows.

    While the tapered slip-forming process is similar to that used on the standard slip-forming, it

    requires greater attention, contractor experience and expertise ensures the success of such

    projects.

  • 8/18/2019 7 Slip Form Construction

    9/11

    2/1

    Jump Form

    Another but similar method that is in use for this type of construction is the “jump form

    method”. In this method the form work jumps up to the next layer after the bottom layer is

    cast. The concrete pouring is not continuous as in the slip-form method.

    Jump forms climb in steps following each concrete pour. This type of construction is more

    suited to high rise building cores where there are regular floors and joints will not be seen.

    Jump Form

    Another jump form system consists of either fixed diameter or 

    adjustable diameter form sets. Our form set permits diameters

    from 9 ft. to 110 ft. and varying wall thickness. The jump form is

    a fullydecked work platform which is self-contained and sets up

    in days.

    In this jump form construction each ring of forms is 4 ft. tall.

    Three rings of forms are stacked on top of each other. After the

    top 4 feet of form is poured, the bottom section is removed and

    vertically jumped to the new top and then prepared for the next

    pour. This repetitive process of pouring and jumping up the

    lower set of forms continues until the structure is topped out.

  • 8/18/2019 7 Slip Form Construction

    10/11

    2/1

    Summary

    •   Slip form construction is a construction method

    in which concrete is poured into a continuously

    moving form.

    •   There are two types of slip-forms; vertical and

    horizontal.

    •   Slip-form construction consumes very less time

    but requires careful planning of construction

    process to achieve high production rates.

    •   Due to continuous concrete pouring in slip-form

    construction it produces better concrete joint

    less and watertight structures.

    •   Slip form systems require a few but highly skilled

    workforce.

    •   Slip-forming is also used in the construction of 

    tapered structures involving changing

    thicknesses in walls, diameters and/or shapes.

    •   Another but similar method that is in use for this

    type of construction is the “jump form method”.

    In this method the form work jumps up to the

    next layer after the bottom layer is cast. The

    concrete pouring is not continuous as in the slip-

    form method.

    References

    •   Allen, EA. (2009) “Fundamentals of building construction materials and methods”, John Wiley & Sons.

    •   Ching, Francis (2008) “Building Construction Illustrated”, John Wiley & Sons.

    •   Crompton, Richard (1992) “Tilt-up construction”, University of Florida.

    •   Mehta, Madan et. al. (2013) “Building Construction”, Pearson, USA.

    •   Zayed, Tarek et. al. (2008) Slip-Form Application to Concrete Structures, ASCE.

    •   http://en.wikipedia.org.

    •   http://youtube.com

  • 8/18/2019 7 Slip Form Construction

    11/11

    2/1

    Lecture Activity

    Each student is required to prepare a brief but informative internet-based research about one of the topics

    related to this lecture (Slip-form Construction); i.e., new developments, successive and local case studies or 

    important details. The research should be presented in only one A4 sheet.