document88

60
Construction Environmental Management Plan PROJECT: PORT BOTANY REDEVELOPMENT STAGE 1 CONSTRUCTION OF RAMP D CONTRACT No.: CONTROLLED COPY NO: e-copy DISTRIBUTION LIST OF CONTROLLED COPIES Copy No. Issued to 1 Fulton Hogan Construction Project Director 2 Client Representative Project Authorised Delegate

Upload: muthuswamy77

Post on 17-Jul-2016

216 views

Category:

Documents


0 download

DESCRIPTION

dsfsf

TRANSCRIPT

Page 1: Document88

Construction Environmental Management Plan

PROJECT: PORT BOTANY REDEVELOPMENT STAGE 1

CONSTRUCTION OF RAMP D

CONTRACT No.:

CONTROLLED COPY NO: e-copy

DISTRIBUTION LIST OF CONTROLLED COPIES

Copy No.

Issued to

1 Fulton Hogan Construction Project Director

2 Client Representative Project Authorised Delegate

Page 2: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 3/07/2013 Page 2 of 60

Table of Contents

1. Introduction ...................................................................................................................... 4 1.1. Background .............................................................................................................. 4 1.2. Purpose and Scope ................................................................................................... 4 1.3. Project Overview ...................................................................................................... 4 1.4. Construction phases ................................................................................................. 6 1.4.1. Site Establishment .................................................................................................... 6 1.4.2. Main Construction Works ........................................................................................ 6 1.5. Construction Staging ................................................................................................ 6

2. Construction Environmental Management System Overview ......................................... 7 2.1. Environmental Policy ............................................................................................... 7 2.2. Construction Environmental Management Plan ...................................................... 8 2.3. Issue Specific Sub-Plans............................................................................................ 8 2.4. Environmental Work Method Statements ............................................................... 9 2.5. Internal Permit System............................................................................................. 9

3. Planning .......................................................................................................................... 10 3.1. Environmental Aspects and Impacts ...................................................................... 10 3.2. Statutory Requirements ......................................................................................... 10 3.2.1. Minister’s Conditions of Approval (MCoA) ............................................................ 10 3.2.2. Commonwealth Consent ........................................................................................ 11 3.2.3. The Development Deed ......................................................................................... 11 3.2.4. Green Port Guidelines ............................................................................................ 12 3.2.5. Port Development Code ......................................................................................... 12 3.2.6. Knuckle Management Plan .................................................................................... 12 3.3. Environmental Objectives and Targets .................................................................. 13

4. Implementation and Operation ...................................................................................... 14 4.1. Resources, Roles, Responsibilities and Authority .................................................. 14 4.2. Competence, Training and Awareness .................................................................. 15 4.2.1. Site Induction ......................................................................................................... 15 4.2.2. Environmental Awareness Training ....................................................................... 16 4.2.3. Toolbox Talks .......................................................................................................... 16 4.3. Communication and Consultation ......................................................................... 17 4.3.1. Liaison with Patrick ................................................................................................ 17 4.3.2. Community and Stakeholder Management ........................................................... 17 4.3.3. Managing Cumulative Impacts From Multiple Construction Works ...................... 18 4.3.4. Authority Liaison .................................................................................................... 18 4.3.5. Hours of Work ........................................................................................................ 19 4.4. Emergency Preparedness and Incident Management ........................................... 19

5. Checking Performance .................................................................................................... 20 5.1. Environmental Inspections..................................................................................... 20 5.2. Environmental Monitoring ..................................................................................... 20 5.3. Environmental Nonconformities ............................................................................ 20 5.4. Audits & Reporting ................................................................................................. 20

Page 3: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 3/07/2013 Page 3 of 60

6. Document Control and Records Management .............................................................. 21 7. Review and Improvement of the CEMP .......................................................................... 21 Attachments ............................................................................................................................ 22

Attachment A. Environmental Policy ............................................................................ 22 Attachment B. Environmental Risk Register ................................................................. 24 Attachment C. Summary of MCOA Requirements ........................................................ 25 Attachment D. Summary of EIS Requirements ............................................................. 38 Attachment E. Register of Relevant Legislation............................................................ 46 Attachment F. Environmental Inspection Report ......................................................... 51 Attachment G. Consultation Register ........................................................................... 56

Page 4: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13 Page 4 of 60

1. Introduction

1.1. Background

Patrick Stevedores Operations Pty Ltd (Patrick) operates an international shipping container terminal (Terminal) on the land leased from NSW Ports at Brotherson Dock, Port Botany.

The Terminal loads and unloads containers from ships berthed at the dock and provides a container stacking area for its clients. All containers are ‘in-transit’ and the Terminal facilitates the transfer of goods between the land and sea as well as using trucks and trains to transport containers to customer sites.

The objective of the Port Botany Redevelopment Project (PBRP) is to deliver the infrastructure, change management and associated works to enable transition from a manual terminal operation to a state of the art AutoStrad Terminal achieving best practice safety, productivity, energy efficiency and environmental benefits. The PBRP will be completed in two construction stages as follows:

Stage 1

expansion of the existing container handling facility on reclaimed land, “the Knuckle”, adjacent to the Patrick’s existing container terminal, and

construction of “Ramp D” which extends from the existing Grade Separation Works undertaken by SPC.

Stage 2

upgrading the existing terminal with new truck grids, additional rail and new road access, construction of new administration offices, a control tower and workshop buildings, and

procurement of more eco‐efficient, less noisy plant with reduced lighting requirements for night time operation while being amenable for optimal operation as a result of terminal automation.

The NSW Minister for Planning granted staged development consent in 2005 and 2006 under the Environmental Planning and Assessment Act 1979, subject to a number of Conditions of Approval. This consent has since been subject to thirteen (13) modifications. In addition, the Commonwealth granted consent in 2006 under the Environment Protection and Biodiversity Conservation Act 1999, for aspects of the project relating to migratory birds, such as enhancement of Penrhyn Estuary.

1.2. Purpose and Scope

This Construction Environmental Management Plan (CEMP) is prepared to cover the construction of “Ramp D” only (the Project). The CEMP describes the environmental management processes and controls that Fulton Hogan will apply during construction of the Project.

Fulton Hogan recognises that the project construction activities will result in some adverse impacts on the environment. The purpose of this CEMP is to ensure that such activities are undertaken in an environmentally responsible manner and that any unavoidable adverse impacts on the environment are minimised.

It is designed to satisfy the requirements of Fulton Hogan’s Integrated Management System (IMS) and AS/NZS ISO 14001:2004. This CEMP will be used as a working document to ensure that commitments and obligations included in the Ministers Conditions of Approval (MCoA) and Environmental Impact Statement (EIS) obligations are understood and implemented by all construction staff, including sub-contractors.

1.3. Project Overview

The Project involves the construction of Ramp D which will complement the overall Terminal redevelopment by providing a main entry and exit point to the Patrick container handling facility.

Page 5: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13 Page 5 of 60

Ramp D is a new ramp and bridge structure that will adjoin the recently constructed Penrhyn Road elevated roundabout (part of the Grade Separation Works), and traverse the existing rail line that services the Patrick area of the Port.

The scope of works includes:

demolition of existing buildings and structures, including RCOS building

relocation and modification of underground services such as water, electrical and communications

installation of new services for the new ramp access such as storm water drainage and electrical for street lighting

drilling and constructing piles to provide foundation for the bridge structure

construction of reinforced earth wall embankment and bridge abutment

construction of bridge piers and bridge deck

removal and modification of existing lighting, fencing and barriers on the existing elevated roundabout;

placement of pavement material

installation of traffic islands and kerb and gutter

installation of traffic signage, barriers, fencing and safety screening, and

placement of asphalt pavement and line marking.

Figure 1-1 below shows the project layout and location.

Figure 1-1. Project Layout & Location

Proposed Ramp D

Existing Elevated Roundabout

Ramp A

Limit of Works

Limit of Works

Ramp D Construction Envelope (Indicative)

Page 6: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13 Page 6 of 60

1.4. Construction phases

Works associated with the construction of Ramp D involve the following phases.

1.4.1. Site Establishment

Site establishment activities will include:

assembly of site offices and facilities

temporary utility connections to services, and

installation of drainage, and sediment and erosion controls.

1.4.2. Main Construction Works

Main construction works will commence immediately after completion of site establishment works and will include:

services identification relocation, protection and installation

demolition of existing building and pavements

drainage works including construction of drains and protection works

construction of piling platform and piling works

earthworks and construction of the reinforced earth wall embankment

structural concrete works for bridge pier and deck construction

installation of bridge girders

construction of pavement drainage and installation of services

placement of pavement, kerb and gutter and asphalt works, and

Installation of barriers, road furniture, street lighting, line marking and signage.

1.5. Construction Staging

Work on Ramp D is expected to commence in July 2013 and will take approximately ten months to complete. Indicative construction schedule is shown in Figure 1-2 below.

Figure 1-2: Indicative construction schedule summary

Page 7: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13 Page 7 of 60

2. Construction Environmental Management System Overview

The Construction Environmental Management System (CEMS), consistent with the requirements of AS/NZS ISO 14001:2004 Environmental management systems – requirements with guidance for use, has been developed by Fulton Hogan for the Project. The CEMS consists of this Construction Environmental Management Plan (CEMP), issue specific sub-plans and other supporting documentation. The structure of the CEMS is shown in Figure 2-1 below.

Minister’s Conditions of

ApprovalEIS Obligations and Other

Requirements

Corporate Environmental Management System

Construction Environmental Management Plan

Issue-specific Sub Plans Soil and Water Management Sub-Plan Acid Sulfate Soils Management Sub-Plan Construction Noise Management Sub-Plan Dust Management Sub-Plan Waste Management Sub-Plan

Environmental Work Method Statements Clearing and Grubbing Dewatering Works in Waterways

Environmental Inspections Reports

NCR Reports

Audit Reports Management Reviews

Figure 2-1. Project CEMS structure.

2.1. Environmental Policy

The Commitment to Sustainability in combination with Fulton Hogan’s Mission and General Principles fulfils the requirement of AS/NZ ISO 14001 and defines the Company’s environmental policy.

A copy of Fulton Hogan’s Commitment to Sustainability, and Mission and General Principles, is included in Attachment A.

Page 8: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13 Page 8 of 60

2.2. Construction Environmental Management Plan

This CEMP is a key component of the project-specific CEMS. It describes its main elements and provides references to other relevant plans, procedures and work method statements that together form a systematic approach to managing environmental risks associated with the works.

The CEMP has been prepared to meet the required standards of environmental management during the project implementation. It is a ‘live’ document that will be regularly reviewed and updated to ensure its continuing suitability, adequacy and effectiveness.

The objectives of this CEMP are as follows:

To provide a framework for achieving the requirements of the EIS and MCoA

To describe the systems and processes that will ensure compliance with relevant legal and other requirements

To detail environmental monitoring, reporting and auditing requirements

To outline environmental roles and responsibilities, and

To provide a basis for project induction and environmental awareness training.

This CEMP interfaces with other associated Plans, which together describe the overall management system for the Project.

The CEMP will be forwarded to the Client Representative and relevant authorities for review and comment or approval prior to commencement of construction.

2.3. Issue Specific Sub-Plans

The CEMP includes issue specific sub-plans addressing the key environmental aspects and risks and how they will be managed during construction.

The sub-plans will be forwarded to the Client Representative and relevant authorities for review and comment or approval prior to commencement of construction.

The sub-plans required for the project are shown in the diagram below.

Dust & Air Quality Management Sub-Plan

Soil & Water Management Sub-Plan

Noise & Vibration Management Sub-Plan

Waste & Spoil Management Sub-Plan

ASS Management Sub-Plan

Construction EMP

Fulton Hogan Construction Environmental Management System

Page 9: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13 Page 9 of 60

2.4. Environmental Work Method Statements

Environmental Work Method Statements (EWMSs) will be prepared for all high-risk activities, which include but are not limited to:

Clearing and grubbing

Works in waterways

Dewatering

Management of Acid Sulphate Soils, and

Handling and disposal of contaminated material.

Fulton Hogan will develop EWMSs for the construction phase progressively. Each EWMS will involve a detailed assessment of the environmental risks associated with the proposed activity and may also contain information derived from site specific technical assessments undertaken by expert consultants.

EWMSs will be forwarded to the Client Representative for review prior to commencement of construction. A register of all EWMSs will be maintained.

2.5. Internal Permit System

An internal permits system will be maintained for all high-risk activities to ensure all required approvals are in place and all notification and consultation obligations are met prior to activities commencing.

Each permit will include details of proposed works, justification for the works, measures to reduce impacts, consultation with the Principal’s Authorised Representative (if needed), and signoffs on the permit before release.

The list of internal permits is provided below.

Table 2-1. Internal permits

Type of activity requiring Internal Permit Permit Title

Works in or near waterways Works in Waterways Permit

Dewatering Discharge/Dewatering Permit

Clearing and grubbing Clearing and Grubbing Permit

Works in or near environmentally sensitive areas Permit to Enter

Page 10: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13 Page 10 of 60

3. Planning

3.1. Environmental Aspects and Impacts

The environmental aspects and impacts associated with the works were initially identified and assessed in the Environmental Impact Statement (EIS) and include:

water quality, erosion and sedimentation

acid sulfate soils, and contaminated soils

noise

dust

vegetation and weeds, and

waste disposal.

A summary of the MCOA requirements is included in Attachment C. A summary of the EIS requirements is included in Attachment D.

Fulton Hogan has undertaken a risk assessment of all potential environmental impacts in accordance with its Risk Management Procedure. The results of this risk assessment are recorded in the Environmental Risk Register included in Attachment B.

3.2. Statutory Requirements

A detailed list of legal and other requirements relevant to the Project is included in Attachment E. Any changes to the existing legislation during construction will be noted and this CEMP will be reviewed and amended accordingly.

3.2.1. Minister’s Conditions of Approval (MCoA)

MCoA have been issued as part of the development consent for the entire Port Botany Expansion Project. The consent is currently subject to 13 modifications; however, only three are applicable to the construction of Ramp D. These are shown in Table 3-1 below.

A further modification (number 14) is currently being reviewed by DP&I, and is included in Table 3-1 below.

Table 3-1. List of modifications granted to the original development consent.

Modification Description

Modification 5 MOD-60-9-2008 approved 21 September 2008

Specifies the work times allowable for construction activities that would result in audible noise at any residential premise. Construction outside the specified hours needs to be approved on a case by case basis.

Modification 6 MOD-68-12-2008 approved 12 December 2008

Repeals the conditions contained in Modification 5 provided the construction activities are subject to an environment protection licence issued by the EPA under the POEO Act and the EPA has approved activities to be conducted outside the permitted hours.

Modification 13 (MOD 13) approved 8 February 2013,

Modified the stormwater system for the Patrick ‘knuckle’ area.

Modification 14 (MOD 14) subject to DP&I approval.

Re-assesses vehicle traffic based on required activities for construction of terminal operation infrastructure.

Page 11: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13 Page 11 of 60

3.2.2. Commonwealth Consent

Commonwealth consent was granted for the Port Botany Expansion project under the Environment Protection and Biodiversity Conservation Act 1999. The consent relates to migratory birds that inhabit the Penrhyn Estuary and was granted on 3 January 2006. The approval conditions were modified on 7 December 2012.

SPC prepared a Habitat Enhancement Plan and is responsible for all measures in the consent. Whilst SPC is responsible for all measures in the Commonwealth consent, as defined in the Schedule 10 of the Development Deed, the construction works will be carried out in a manner that will minimise potential impacts from noise and lighting on shorebirds at Penrhyn Estuary.

3.2.3. The Development Deed

The Development Deed between SPC and Patrick comprises the agreed terms under which work can be carried out on the Project. Ramp D works can be carried out within the scope of the original consent so long as the requirements under the “Development Deed” are satisfied. SPC have confirmed that no additional approvals are required for Ramp D related works. A summary of the environmental-related obligations in the Deed relevant to the construction phase is included in Table 3-2 below.

Table 3-2. Summary of environmental obligations.

Section Summary of Environment-Related Deed Obligations Where addressed

2(g) Requirement to comply with the Dust Management Plan Dust & Air Quality Mgmt Sub Plan

3.1 (h)

3.1 (m)

EMP is required to be prepared as per clause 30.18

Condition B1.4 of SPC Existing Development Approval

CEMP

CEMP s4.3.3

5.1 (xi) Project to accept management, control and responsibility for the Site and for risk in connection with Dust Management Plan

Dust & Air Quality Mgmt Sub Plan

7 Requirement to carry all development in accordance with the Applicable Development Approval only

CEMP s3.2.1, Appendix C

9 Compliance with obligation in each Project Document including the CEMP

CEMP s5

10.2 Conditions relating to communication with general public and to participate in community consultation meetings regarding project

CEMP s4.3.2

15.5 Obligations relating to Nuisance, Noise (s.15.5), Rubble (s.15.6) Construction Noise Mgmt Sub-Plan

Waste & Spoil Mgmt Sub Plan

29 Applications to relevant authorities to obtain all approvals necessary to lawfully construct works and in compliance with the CEMP

CEMP s4.3.3

30.1

30.8

Duration to determine consent by SPC

Consultation with Sydney Ports and address comments or suggestions raised by SPC

CEMP s4.3.3

Page 12: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13 Page 12 of 60

Section Summary of Environment-Related Deed Obligations Where addressed

30.16

30.18(i)

Operator must comply with all approvals

CEMP to be consistent with Compliance Schedule, SPC EMP and shall provide details of legal compliance and management of site to minimising environmental impact

31.1 Carry out, construct and complete the works in accordance with the CEMP and Dust Management Plan and in conformity with approvals and requirements of government agencies, NSW and Australian Law and relevant Australian Standards

CEMP s5

Dust & Air Quality Mgmt Sub Plan

37 Environmental Obligations including compliance with Environmental Laws, approval conditions, minimising harm, notification and clean up of pollution incidents, provide reports, comply with CEMP, liability for pre-existing contamination.

CEMP

Emergency Response & Incident Mgmt Plan

Sch. 2 Sections 10-14 & 18 specify the minimum standards for the works relating to Stormwater, Water, Sewer, Lighting and Plant & Equipment

NA - relates to operational requirements

Sch. 10 Compliance Schedule in 4 parts as follows:

Part 1: Development Consent Conditions

Part 2: EIS & Additional Requirements

Part 3: Content of the Environmental Management Plans

Part 4: Incident Reporting Protocol

CEMP Appendix C

CEMP Appendix D

CEMP

Emergency Response & Incident Mgmt Plan

Sch.14 Knuckle Management Plan Dust & Air Quality Mgmt Sub Plan

3.2.4. Green Port Guidelines

Although Green Port Guidelines primarily relate to operational activities, where applicable to construction these guidelines will be adapted. To this end, the Green Ports Guideline compliance checklist will be reviewed and completed prior to commencement of construction to identify the criteria that are relevant to the construction phase and how relevant criteria have been addressed.

3.2.5. Port Development Code

The Port Development Code sets out the minimum criteria for the developments proposed for Port Botany after June 2009 and is supported by the Green Port Guidelines. The values espoused in the Code have been incorporated, where applicable, primarily by Patrick as input to the design consultants.

3.2.6. Knuckle Management Plan

Patrick have prepared a Knuckle Management Plan (April 2012) which contains measures for construction of the knuckle. Measures relevant to Ramp D will be implemented by Patrick, where they are relevant.

Page 13: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13 Page 13 of 60

3.3. Environmental Objectives and Targets

When setting environmental objectives and targets for the Project, consideration was given to legal and other requirements, the Project’s potential environmental impacts, available technological options, likely hazards and risks, operational requirements and the views of key stakeholder groups. The environmental objectives and targets for the Project are set out in Table 3-3 below.

Table 3-3. Environmental Objectives and Targets.

Environmental Aspect

Objective Target

Noise To minimise disturbance of residents caused by construction noise

Noise levels below applicable noise goals and

limits at sensitive receivers

Soil and water quality

To minimise water pollution caused by construction activities

No unauthorised discharges to receiving environment

Air quality To minimise adverse impacts resulting from dust generation

No instances of dust related complaints from the public

Contaminated material

To minimise adverse impacts resulting from contaminated material

Any contaminated material identified during the works is contained and promptly disposed of to an appropriately licenced facility

Heritage To preserve any Aboriginal or non-Aboriginal items of significance should these be discovered during the construction works

No instances of damage to heritage items

Flora and fauna To minimise adverse impacts on threatened flora and fauna should these be discovered during the construction works

No instances of damage to threatened flora and fauna

Waste To minimise generation of waste from the construction activities and to maximise reuse and recycling where appropriate

5% reduction in waste to landfill from forecasted amount at the start of the project

Page 14: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13 Page 14 of 60

4. Implementation and Operation

4.1. Resources, Roles, Responsibilities and Authority

The Project team’s organisational structure and overall roles and responsibilities are detailed in the PMP. The key environmental roles and responsibilities for the Project team are listed in Table 4-1 below.

The Environmental Representative (ER) as required by section B4.3 of the MCOA is to be undertaken by Patrick. The ER is to ensure that environmental management and monitoring measures are detailed in plans that comply with all approvals, obligations and commitments, and are implemented throughout construction. The ER is independent and reports to DP&I and Patrick’s corporate environmental managers.

Table 4-1. Environmental roles and responsibilities

Role Responsibilities

Environmental Engineer (EE)

The Environmental Engineer is responsible for:

being the primary contact point in relation to the environmental performance of the construction phase of the project

developing management plans and monitoring programs required under this CEMP considering and advising on matters specified in the conditions of the consent, and

all other licences and approvals relating to the environmental performance and impacts of the project

managing procedures and practices for receiving and responding to complaints and inquiries in relation to the environmental performance project

reporting all environmental incidents and near misses to the Patrick HSEQ Manager and ER immediately

facilitating an induction and training program for relevant persons involved with the construction phases, and

requiring reasonable steps to be taken to avoid or minimise unintended or adverse environmental impacts, and failing the effectiveness of such steps, to direct that relevant actions be ceased immediately should an adverse impact on the environment is likely to occur.

Project Manager The Project Manager is responsible for:

the overall control of the Project and the CEMP reviewing and approving the CEMP identifying the potential environmental aspects and impacts at the Project launch providing the necessary resources to ensure the CEMP is properly implemented ensuring all personnel are inducted into the Project environmental requirements

prior to commencement of works on site

ensuring suppliers are made aware of the environmental objectives pertaining to them through conditions of contract

providing leadership to the Project in following and supporting the CEMP in a public manner to help develop a positive environmental culture supporting environmental policy and review the performance reports and take strategic actions to continuously improve the CEMP, and

participating in incident investigations.

Page 15: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13 Page 15 of 60

Role Responsibilities

Project/Site Engineer The Project / site Engineer is responsible to the Project Manager for:

ensuring all workers and subcontractors under their control are properly inducted and instructed in the requirements of the CEMP pertaining to their part of the work

in consultation with EE and other relevant disciplines, identifying environmental risks and nominating suitable control measures prior to commencement of construction activities under their control, and

ensuring all work under their control, including subcontractors, is undertaken in accordance with this CEMP and statutory environmental requirements.

Foreman The Foreman is responsible to the Project Manager for:

supervising construction activities under their control to ensure compliance with the requirements of this CEMP and the relevant sub-plans

assisting Project/Site Engineer in identifying environmental risks and nominating suitable control measures for activities under their control

attending environmental emergencies on site ensuring all work under their control is undertaken in accordance with the CEMP and

statutory environmental requirements.

All employees and sub-contractors

All Fulton Hogan employees are responsible for undertaking their work in accordance with this CEMP and Fulton Hogan Environmental Policy as directed at their induction and as instructed by their supervisor.

All subcontractors and suppliers are responsible for ensuring that their work or product complies with the CEMP and the relevant sub-plans.

4.2. Competence, Training and Awareness

The following three main forms of environmental training will be provided on site:

Site environmental induction

Environmental awareness training, and

Toolbox talks.

4.2.1. Site Induction

Prior to commencing work on site, all Project personnel including subcontractors, will attend a site induction and all visitors will attend a visitor induction.

All Project personnel, subcontractors and consultants will be required to undertake a site induction which will, as a minimum, address the following environmental topics:

The CEMP and consequences of non-compliance with the CEMP

The requirements of due diligence and duty of care

Conditions of environmental approvals, permits and notifications

Requirements associated with community consultation

Incident notification and reporting procedures and procedures for dealing with damage and maintenance of erosion and sediment controls

Page 16: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13 Page 16 of 60

Boundaries for vegetation clearing and location of restricted access areas, as well as controls in regard to clearing and/or trimming of vegetation

Erosion and sediment controls, water quality controls and sediment basin management

Hours of work

Obligations to prevent the spread of noxious weeds during construction, and

Environmental emergency response procedures.

Records of training, competency and qualifications including dates, names and trainer details, will be registered in the Inductions Register and kept with the Project Safety Manager.

4.2.2. Environmental Awareness Training

Targeted environmental awareness training will be provided to individuals or groups of workers with a specific authority or responsibility for environmental management or those undertaking a high risk activity. This training will aim to achieve the level of awareness and competence appropriate to their assigned tasks.

The target groups and suggested topics are shown in Table 4-2 below.

Table 4-2. Environmental awareness training by topic and target group.

Target Group Topic

Project Managers and Engineers

Content and requirements of the CEMP, the sub-plans and the EWMSs

Earthworks crews Erosion and sediment control

Management of Acid Sulfate Soils

Working in and/or near waterways

Dust control

Stockpile management

Structures Crews Management of high noise generating activities

Works in waterways or in riparian zones

Concrete works

4.2.3. Toolbox Talks

A toolbox talk involves the dissemination of information to Project personnel at the field level. Generally toolbox talks generally focus on safety aspects with reference to certain Project jobs or tasks. They will also be used to disseminate environmental information. Environmental toolbox talks will cover aspects such as:

Working in or near environmentally sensitive areas

Working in waterways

Dust control

Noise management, and

Works outside standard hours.

Toolbox training will help to ensure that relevant information is communicated to the workforce and will also provide a forum for feedback on issues of interest or concern. Toolbox training will generally be prepared and delivered by site Environmental Engineer but may also be delivered by other authorised persons.

Page 17: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13 Page 17 of 60

4.3. Communication and Consultation

4.3.1. Liaison with Patrick

The following two Project team members are nominated as 24 hour contacts for environmental regulatory authorities, with the authority to take immediate action to shut down any activity, or to affect any pollution control measure:

Irina Kliger (NSW Environmental Manager) - 0488 264 613, and

Michael Terry (Project Manager) – 0416 040 587.

Patrick will be notified immediately should a pollution incident occur that causes or likely to cause harm to the environment. An incident report will be prepared and submitted to Patrick within one working day.

Fulton Hogan will also notify Patrick immediately of any site visits by the EPA, including purpose and outcome of the visit and any actions taken by Fulton Hogan in response to the visit.

4.3.2. Community Consultation and Complaints Handling

A number of community groups and local residents have been identified as stakeholders in relation to the construction phase of this project. Communication with these groups, along with NSW Ports relevant authorities and other groups is managed by Patrick as part of their community engagement for the Redevelopment Project. Specifically:

Community engagement activities are undertaken to inform and engage relevant stakeholders including the Port Botany Expansion Community Consultative Committee (CCC) and Port Botany Neighbourhood Liaison Group.

Where appropriate Patrick will also proactively issue community updates/newsletters, public displays to ensure the community is aware of potential impacts.

Representatives of the Redevelopment Project will attend and provide construction/community updates at regular community forum meetings.

More detail is available on the community page of the Redevelopment Project website at http://www.patrick.com.au/community/w1/i1002943/ along with the monthly community update, Q&As, relevant construction environmental management plans and monitoring.

There is an established complaints handling process in place to respond to issues raised by stakeholders in relation to construction. The 24 hour complaints telephone line is available to residents or stakeholders by telephoning 1800 177 722. The complaints telephone number has been proactively communicated to local residents and businesses, is on the Project website and has been published by local media.

Complaints received will be investigated and dealt with immediately by Patrick. A database of complaints is held and managed by Patrick and is shared and reported on monthly to NSW Ports.

Complaints management database will record the date and time of complaint, the method by which the complaint was made, the contact details of the complainant, the nature of the complaint/enquiry, action taken in response, who is responsible for the action, the team member that responded to the complainant, what follow ups (if any are required), if monitoring is required and, if so, when it will occur, the associated follow-up and, if no action is to be taken, the reasoning why.

Project staff will be available during office hours to visit community members to discuss and investigate where needed.

Page 18: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13 Page 18 of 60

4.3.3. Managing Cumulative Impacts From Multiple Construction Works

Fulton Hogan acknowledges that multiple contractors will be undertaking construction works on the PBRP at the same time and the potential for cumulative environmental impacts such as noise, dust, and traffic during the construction of Ramp D. The management of common environmental issues from multiple construction works will be coordinated by Patrick through regular meetings with Fulton Hogan and other contractors. Fulton Hogan will implement any additional control measures agreed upon at these meetings to minimise the adverse impact on the local communities and businesses.

4.3.4. Authority Liaison

This plan, and all environmental plans, has been designed to address client expectations and requirements, and adequately address risks and stakeholder concerns.

The MCOA requires Patrick and Fulton Hogan to consult with specific authorities and stakeholders in the preparation of this plan and sub-plans. The table below indicates approval (A) and consultation (C) required by the MCOA for each plan. These stakeholders have been consulted during the finalisation of this plan and related plans.

Plan Primarily

required by

DP

&I

EPA

Pri

mar

y

Ind

ust

rie

s

RM

S

Bo

tan

y

Ran

dw

ick

CC

C

SSR

OC

CEMP MCoA B1.3 A C C C C

Acid Sulphate Soils Management Sub-Plan MCoA B2.6 C C C

Construction Noise & Vibration Management Sub-Plan MCoA B2.20 A C C C C

Dust & Air Quality Management Sub-Plan MCoA B2.4 A C C C C C

Soil & Water Management Sub-Plan MCoA B2.5 A C C C C C C

Waste & Spoil Management Sub-Plan MCoA B2.33 A C C C

Emergency Response & Incident Management Plan MCoA B2.43 A C C C

Traffic Management Plan (incl. Port Traffic Handbook) MCoA B2.14 A C C C C C

Construction Safety Study MCoA B2.41 A

The final draft CEMP will be submitted to DP&I, EPA, Primary Industries, Botany Council and the CCC for comment. Relevant sub-plans will be submitted to these organisations, plus RMS, Randwick Council and the CCC.

After comments from these organisations, the draft final CEMP and sub-plans will be updated to account for comments. The final CEMP and relevant sub-plans will be issued to DP&I for approval and compliance certification by the DP&I. Documentation as to how Patrick and Fulton Hogan addressed stakeholder comments during consultation is available. The final CEMP will be issued to EPA, Primary Industries and Botany Council for information, as per the requirements of MCOA B1.3.

Fulton Hogan will not commence any work on-site until:

the CEMP and related documents are approved by DP&I;

a Compliance Certificate is issued by DP&I under MCOA B1.4.

Page 19: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13 Page 19 of 60

4.3.5. Hours of Work

Construction hours are:

7am to 6pm on weekdays

8am to 1pm on Saturdays, and

No works on Sundays or public holidays.

The procedure for notifying Patrick and relevant authorities in advance of any proposed extension to hours of work is included in the Construction Noise & Vibration Management Sub-Plan.

Some out of hours activities are likely to be required throughout the construction period. These activities are permitted by the MCOA and may be required to be undertaken out of hours work to:

undertake works for safety reasons for protection of workers and the public;

reduce disruption to traffic and the community;

satisfy operational requirements of government agencies or authorities; or

due to unforeseen circumstances.

Where there is a requirement for out of hours activities that are not previously authorised by the MCOA, and would be audible, Patrick is required to submit relevant information to DP&I for consideration under Condition B2.19A of the MCOA.

This would include justification of varied construction hours, appropriate notification to sensitive receivers, and noise reduction measures to be put in place. Appropriate community notification would be required, as per the Community Consultation Plan.

4.4. Emergency Preparedness and Incident Management

Environmental incidents and emergencies and management controls for dealing with these are addressed in detail in the Incident and Emergency Response Plan (IERP).

The IERP includes:

Identification of potential environmental hazards

Risk assessment of potential environmental emergencies

Emergency response procedures for different emergency scenarios

Notification requirements and emergency contacts

Roles and responsibilities during environmental emergencies, and

Periodic testing of the emergency response procedures.

All incidents will be recorded in Fulton Hogan’s Case and Action Management System (CAMs) in accordance to Fulton Hogan’s Case and Action Management Procedure and Incident Investigation, Reporting & Notification Procedure.

Page 20: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13 Page 20 of 60

5. Checking Performance

5.1. Environmental Inspections

The effectiveness of site environmental controls will be assessed on a regular basis. To document this, a number of checklists, registers and forms will be completed. These may include (but not necessarily be limited to) the following:

Environmental inspection checklists

Audit reports, and

Nonconformities (NCRs).

These will provide a means to evaluate and verify compliance with the relevant regulatory requirements and the contractual environmental requirements.

Site Environmental Engineer will conduct weekly site inspections and document the results of these inspections in an Environmental Inspection Report (refer to Appendix F).

Any non-conformances identified during site inspections or through monitoring results will be investigated to determine the cause and to ascertain the necessary corrective actions.

5.2. Environmental Monitoring

Project environmental monitoring will comprise collection and interpretation of quantitative data to evaluate compliance and to verify the effectiveness of the environmental controls on site.

Environmental monitoring will include:

Noise monitoring

Water quality monitoring, and

Weather monitoring.

The methodology, location and frequency of environmental monitoring are further described in issue-specific sub-plans. The environmental sampling and testing equipment used on the project will be calibrated in accordance with the manufacturers’ specifications and results recorded on the Calibration Equipment Register.

5.3. Environmental Nonconformities

The process for managing any environmental nonconformities will be as follows:

All nonconformities will be raised through QAntrol and CAMs systems

All nonconformities will be recorded in the Environmental Actions Register

The status of NCRs will be recorded and monitored to ensure timely closure, and

The negative trends will be identified and analysed and preventive actions initiated and implemented to prevent recurrence.

Written responses to any nonconformities raised by Patrick or the relevant authorities will be provided within the agreed timeframes or as required by the relevant contract environmental specifications.

5.4. Audits & Reporting

The CEMP compliance audits will be undertaken by suitably qualified and experienced Fulton Hogan personnel not directly associated with the project every six months, with the first audit occurring no longer than three months after commencement of construction.

The scope of internal audits may include but is not limited to:

Compliance with legislation, license, permit and approval obligations;

Page 21: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13 Page 21 of 60

Compliance with the mitigation measures in the CEMP and sub-plans;

Management of environmental nonconformities and incidents

Subcontractor management, and

Management of the environmental incidents.

Any deficiencies identified in the audit will be promptly rectified according to the level of risk.The outcomes of internal audits may also trigger the requirement to update the CEMP and/or the sub-plans.

Patrick will undertake the Annual Independent Environmental Audit as required by section B4.5 of the MCOA. Patrick will also undertake the Annual Environmental Management Report as required by section B4.2 of the MCOA.

6. Document Control and Records Management

The system used for document control and records management is detailed in the Documents and Records Management Plan. This enables the complete management of all documents, including the identification of document or drawing lists, author and recipient management and ensuring that documents remain legible and readily identifiable.

7. Review and Improvement of the CEMP

The CEMP will be reviewed at least annually to ensure compliance with legislative requirements and its suitability and effectiveness for the project and other requirements. The CEMP may be reviewed more regularly due to a change in construction activities, where targets are not achieved or in response to audit findings.

The review may be in a form of:

formal management review

second party audit, and/or

inclusion as a separate item at site meetings.

Any revisions to the CEMP as a result of management review will be issued as per Section 4.3.3 of this Plan and the Documents and Records Management Plan.

Revision History

Rev Revised By Reviewed & Approved By Date Description/Summary of Changes

0 I. Kliger P. Nadanapatham 8/07/2013 Issued to Client

Page 22: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13 Page 22 of 60

Attachments

Attachment A. Environmental Policy

The Commitment to Sustainability in combination with Fulton Hogan’s Mission and General Principles fulfils the requirement of AS/NZ ISO 14001 and defines Fulton Hogan’s environmental policy.

Page 23: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13 Page 23 of 60

Page 24: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013 Page 24 of 60

Attachment B. Environmental Risk Register

Environmental Aspect Description of RiskRisk

Score Control Measures

Responsible

Person

Dust Dust and particulate matter reducing air quality and

affecting local amenity High 21 Dust Management Sub-Plan

Environmental

Engineer

Emissions Vehicle emmissions from plant and equipment Low 2Prestart Plant and Equipment Check

Foreman

Contamination Unexpected contamination uncovered on site during

excavation or in imported fill materialMed 8 Waste Management Sub-Plan

Environmental

Engineer

Acid Sulfate Soils (ASS) ASS uncovered during earthworks High 18 Acid Sulfate Management Sub-PlanEnvironmental

Engineer

Asbestos Exposure to friable asbestos fibres High 17Asbestos Management Procedure

Waste Management Sub-Plan

Environmental

Engineer/Foreman

Unexpected findsUnexpected discovery of Aboriginal or Non-Aboriginal

heritage itemsMed 13 Unexpected Finds Procedure

Environmental

Engineer

Vegetation Clearing outsideclearing limits Med 13 Clearing and Grubbing EWMSEnvironmental

Engineer

Vegetation

Inadequate rehabilitation /revegetation of disturbed areas

following construction causing loss of habitat and erosion

and sediment issues

High 17 Clearing and Grubbing EWMS

Environmental

Engineer

Project Manager

VegetationInadequate control of noxious weeds leading to spread of

weeds High 17 Clearing and Grubbing EWMS

Environmental

Engineer

Project Manager

Erosion and sedimentationInadequate ERSED controls resulting in off site

discharges of sediment laden waterHigh 23 Erosion and Sedimentation Management Plan

Environmental

Engineer

Erosion and sedimentation Inadequate management of stockpiled materials High 21 Soil and Water Management Sub-PlanEnvironmental

Engineer

Erosion and sedimentation Mud tracking on public roads High 23 Soil and Water Management Sub-PlanEnvironmental

Engineer

Fuel and Chemical Storage Storage of fuels, chemcials and hazardous materials

causing soil and groundwater contamination High 17 Hazardous Chemicals Storage and Handling Procedure

Environmental

Engineer

Fuel and Chemical Storage Fuel/Oil spills High 17 Spills Response ProcedureEnvironmental

Engineer

Noise Causing disturbace to local residents and businesses Med 13 Noise Management Sub-Plan Environmental

Engineer

Page 25: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013 Page 25 of 60

Attachment C. Summary of MCOA Requirements

Notes:

Only items related to the Fulton Hogan scope of works has been included in the following schedules.

Items shaded in grey are assumed to be SPC and/or Patrick responsibility

SCHEDULE A: OVERALL SCOPE OF DEVELOPMENT WORKS AND GENERAL PROVISIONS

No Condition Implementation CEMP Reference

A1. GENERAL

Scope of Development

A1.1 The approved aspects of the development shall be carried out generally in accordance with:

a) Development Application DA-494-11-2003-i, lodged with Department on 26 November 2003.

b) Port Botany Expansion: Environmental Impact Statement (ten volumes), prepared by URS and dated Nov 2003;

c) Port Botany Expansion Commission of Inquiry – Primary Submission (two volumes), prepared by URS dated May 2004

d) Port Botany Expansion Commission of Inquiry – Supplementary Submission to EIS, prepared by URS and dated August 2004

e) Port Botany Expansion Environmental Impact Statement – Supplementary Submission (two volumes), prepared by URS and dated October 2004;

f) modification application MOD-107-9-2006-i, accompanied by Port Botany Expansion, Section 96(1A) Application: Modification of Consent Conditions, prepared by SPC and dated September 2006;

g) modification application MOD-134-11-2006-i, accompanied by Port Botany Expansion, Section 96(1A) Modification – Wharf Structure Design, prepared by SPC and dated November 2006;

h) modification application MOD-149-12-2006-i, accompanied by Port Botany Expansion, Section 96(1A) Modification – Application to Modify Conditions B2.9 and B2.22 of the Port Botany Consent, prepared by SPC and dated 1 December 2006;

i) modification application MOD-78-9-2007-i, accompanied by Port Botany Expansion – Modification of Conditions C2.20 & C2.25, prepared by SPC, dated July 2007;

j) modification application MOD-60-9-2008, accompanied by Port Botany Expansion – Modification of Conditions B2.46 & C2.25, prepared by SPC, dated 27 August 2008;

k) modification application MOD-68-12-2008, accompanied by a letter from SPC dated December 2008;

l) modification application MOD-08-03-2009, accompanied by a letter from NSW Ports dated 16 February 2009 and assessment report titled Port Botany Expansion – Rail Operations Section 96(1A) Modification dated February 2009;

m) modification application 494-11-2003-I MOD 8, accompanied by an assessment report titled “Port Botany Expansion – Ship Turning Area

All

CEMP, section 3.2.1

Page 26: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013 Page 26 of 60

No Condition Implementation CEMP Reference

Dredging Section 96(1A) Modification dated May 2009;

n) modification application DA-494-11-2003-i MOD 9, accompanied by an assessment report titled “Port Botany Expansion – Additional High Spot Dredging off Molineux Point Section 96(1A) Modification” dated May 2009;

o) modification application DA-494-11-2003-i MOD 10, accompanied by an assessment within letter titled “Port Botany Expansion – Section 96(1A) Modification - Additional Ship Turning Area Dredging” dated 8 July 2009;

p) modification application DA-494-11-2003-i MOD 11, accompanied by an assessment report titled “Sydney Port Botany Terminal No. 3 PKG-17.1 Planning Section 75W Modification Operations Building and Maintenance Building” dated 14 September 2011;

q) modification application DA-494-11-2003-i MOD 12, accompanied by an assessment report titled “Sydney Port Botany Terminal No. 3 PKG-17.1 Planning Section 75W Modification to Stormwater First Flush System” dated 15 February 2012 and supplementary advice provided on 6 June 2012 in relation to other proprietary SQID devices;

r) modification application DA-494-11-2003-i MOD 13, accompanied by an assessment report titled “Project No. 231658 Section 75W Modification to Stormwater System for Southern Expansion Area” dated 31 October 2012; and

s) the conditions of this consent.

Insofar as they relate to the approved development.

A1.2 In the event of an inconsistency between:

a) the conditions of this consent and any document listed from condition A.1.1(a) to (r) inclusive, the conditions of this consent shall prevail to the extent of the inconsistency; and

b) any document listed from condition A1.1(a) to (r) inclusive, the most recent document shall prevail to the extent of the inconsistency.

N/A

N/A

Statutory Requirements

A1.3 All licences, permits and approvals shall be obtained and maintained as required throughout the life of the development. No condition of this consent removes the obligation to obtain, renew or comply with such licences, permits or approvals.

All CEMP, section 3.2

Page 27: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013 Page 27 of 60

SCHEDULE B - CONSTRUCTION WORKS AND ONGOING ENVIRONMENTAL MANAGEMENT OF THE NON-OPERATIONAL ASPECTS OF THE TERMINAL

No Condition Implementation CEMP Reference

B1. GENERAL REQUIREMENTS

Application of Schedule

B1.1 The conditions in this Schedule of the consent relate the following aspects of the development:

a) development activities and works associated with the construction phase(s) of terminal footprint infrastructure including transportation and delivery of materials and construction personnel to/from the site;

b) development activities associated with the construction of terminal operations infrastructure;

c) on-going management, mitigation and monitoring associated with the development, excluding direct terminal operation matters subject to the conditions in Schedule C.

a) NSW PORTS & Patrick

b) NSW PORTS & Patrick

c) NSW PORTS & Patrick

CEMP, section 3.1

B1.2 The conditions in this Schedule of the consent must be complied with by the Applicant, or any party undertaking the activities and works referred to under condition B1.1 on behalf of the Applicant.

As above N/A

Construction Environmental Management Plan (CEMP)

B1.3 The Applicant shall prepare a Construction Environmental Management Plan (CEMP) which, must be approved by the Director-General prior to the commencement of any site preparation or construction works. The CEMP must:

Patrick / Fulton Hogan

CEMP:

-Describe all activities to be undertaken on the site during site establishment and construction; Patrick / Fulton Hogan

Section 1.4

-Describe relevant stages/phases of construction, including a work program outlining relevant timeframes for each stage/phase. Patrick / Fulton Hogan

Section 1.5

-clearly outline stages/phases of construction that require on-going environmental management monitoring and reporting up to and beyond the commencement of operations of the terminal;

Patrick / Fulton Hogan Section 1.4

-detail statutory and other obligations that the Applicant is required to fulfil during site establishment and construction, including all approvals, consultations and agreements required from authorities and other stakeholders, and key legislation and policies;

Patrick / Fulton Hogan Section 3

-include specific consideration of measures to address any requirements of the Department, DEC, DNR and the Council during site establishment and construction;

Patrick / Fulton Hogan Section 4.3.3

-describe roles and responsibilities for all relevant employees involved in site establishment or construction; Patrick / Fulton Hogan

Section 4.1

-detail how environmental performance of the site preparation and construction works will be monitored, and what actions will be taken to address identified adverse environmental impacts;

Patrick / Fulton Hogan Section 5

Page 28: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013 Page 28 of 60

No Condition Implementation CEMP Reference

-include all Management Plans/Studies and Monitoring Programs required in this schedule; Patrick / Fulton Hogan

Sections 2.3, 5

-include arrangements for community consultation and complaints handling procedures during construction; Patrick Section 4.3.2

-be made available for public inspection after approval of the Director General. Patrick / Fulton Hogan

- Separate CEMPs may be prepared and submitted for works associated with the construction of the terminal footprint. NA NA

Compliance Certification

B1.4 Prior to each of the events listed from a) to c) below, or within such period otherwise agreed by the Director-General, documentation certifying that all conditions of this consent applicable prior to that event have been complied with shall be submitted to the satisfaction of the Director-General. Where an event is to be undertaken in stages, submission of compliance certification may be staged consistent with the staging of activities relating to that event, subject to the prior agreement of the Director-General.

Patrick / Fulton Hogan

CEMP, section 4.3.3

a) commencement of construction works associated with the development;

b) commencement of each phase of construction works established under the program required under condition B1.3; and

c) completion of each phase of construction works established under the program required by condition B1.3.

The certifying documentation shall clearly outline any on-going environmental management, monitoring or reporting requirements associated with the concluded construction works phase.

B1.5 Notwithstanding condition B1.4, the Director-General may require an update report on compliance with all, or any part, of the conditions of this consent. Any such update shall meet the requirements of the Director-General and be submitted within such period as the Director-General may agree.

As above As above

B2. CONSTRUCTION ENVIRONMENTAL PERFORMANCE

Air Quality Management

Odour Impacts and Sediment Sampling

B2.1 Unless otherwise permitted by an Environment Protection Licence applicable to the development, the Applicant shall ensure that construction works are undertaken in compliance with section 129 of the protection of the Environment Operations Act 1997. [S129 prohibits odour emission without a licence]

Patrick / Fulton Hogan

Waste & Spoil Mgmt Sub-Plan

Dust Management Plan

B2.4 The Applicant shall prepare a Dust Management Plan in consultation with DEC, RTA, DOP, Botany and Randwick Councils. The Applicant shall address the requirements of these organisations in the Plan. The Applicant shall also consult with the Community Consultative Committee in

Patrick / Fulton Hogan

Dust & Air Quality Mgmt Sub-Plan

Page 29: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013 Page 29 of 60

No Condition Implementation CEMP Reference

preparation of the Plan. Plan must include, but not be limited to strategies in which the construction shall:

-minimise or prevent the emission of dust from the site;

-ensure that all trafficable areas and vehicle manoeuvring areas in or on the premises shall be maintained, at times, in a condition that will minimise the generation, or emission from the premises, of wind-blown or traffic generated dust;

-ensure that all vehicles entering and leaving the site and carrying a load that may generate dust are covered at all times, except during loading and unloading. Any such vehicles shall be covered or enclosed in a manner that will prevent emissions of dust from the vehicle at all times; and

-ensure that all dust source surfaces are sealed.

The Plan shall be approved by the Director-General prior to commencement of construction.

Soil And Water Management

Soil and Water Management Plan

B2.5 The Applicant shall prepare a Soil and Water Management Plan in consultation with DEC, RTA, DOP, DNR, Botany and Randwick Councils. The Applicant shall address the requirements of these organisations in the Plan. The Applicant shall also consult with the Community Consultative Committee in preparation of the Plan. The Plan must detail erosion and sediment controls, prepared in accordance with Managing Urban Stormwater: Soils and Construction (available from the Department of Housing) and must:

Patrick / Fulton Hogan

Soil & Water Mgmt Sub-Plan

-identify the management responses to activities that could cause soil erosion or result in the discharge of sediments and/or other pollutants from the site;

-specify standards/performance criteria for erosion, sediment, and pollution control including water sediment basin locations and discharge points, for example parameters, frequency, duration location and method; and

-describe what actions and measures will be implemented, the effectiveness these actions and measures and how they will be monitored during the works, clearly indicating who will conduct the monitoring, how the results of this monitoring would be recorded; and, if any non-compliance is detected.

The Plan shall be approved by the Director-General prior to commencement of construction.

Acid Sulphate Soils

B2.6 Prior to the commencement of construction activities, the Applicant must prepare an Acid Sulphate Soils Management Plan to assess and manage any Acid Sulphate Soils (ASS) or potential ASS (PASS). The Plan shall be prepared in accordance with the Acid Sulphate Soils Manual 1998 published by the NSW Acid Sulphate Soil Management Advisory Committee. In the event that ASS are encountered during the works, the Applicant shall notify the NSW Maritime Authority immediately.

Patrick / Fulton Hogan

Acid Sulphate Soils Mgmt Sub-Plan

Pollution Prevention

Page 30: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013 Page 30 of 60

No Condition Implementation CEMP Reference

B2.7 Unless permitted through an environment protection licence applicable to the development, the Applicant must comply with section 120 of the Protection of the Environment Operations Act 1997, which prohibits the pollution of waters. [S120 prohibits pollution without a licence.]

Patrick / Fulton Hogan

Soil & Water Mgmt Sub-Plan

Consultation with Sydney Water

B2.13 Prior to commencement of construction, the Applicant is required to consult with Sydney Water regarding the likely requirements from Sydney Water for a section 73 Compliance Certificate.

Patrick / Fulton Hogan

Construction Plan

Traffic, Transport and Infrastructure Management

Construction Traffic Management Plan

B2.14 Prior to the commencement of any construction works, the applicant must prepare a Construction Traffic Management Plan in consultation with RTA, DOP, Botany and Randwick Councils and SSROC. The Applicant shall address the requirements of these organisations in the Plan. The Applicant shall also consult with the Community Consultative Committee in preparation of the Plan. Plan must include, but not be confined to, mitigation measures identified in EIS such as:

Patrick / Fulton Hogan

Traffic Management Plan

-identification of preferred haulage routes;

-access routes and, signage and access arrangements on site;

-measures to limit the impact on Foreshore Rd. and Botany Rd.;

-need for restrictions on delivery hours and/or routes; and,

-development of traffic management measures during construction works to ensure minimal traffic disruptions

The plan must be submitted and approved by the Director-General prior to the commencement of construction.

Safety Audit

B2.15 The Applicant must undertake safety audit in accordance with RTA guidelines upon completion of works but prior to operation to ensure the safety of any road works, traffic management facilities, cycling and pedestrian provisions undertaken as part of the proposed works.

Patrick / Fulton Hogan

Traffic Management Plan

Port Traffic Handbook

B2.16 Prior to construction the Applicant must prepare a handbook and distribute it to drivers of construction related vehicles providing information on accepted routes, constraints to traffic and preferred hours of use and amenities on such routes to ensure that the impact of traffic growth on local traffic is minimised.

Patrick / Fulton Hogan

Traffic Management Plan

Rail Access to New Terminal

B2.18 The Applicant shall ensure that Grade separation of Penrhyn Road over the rail access to the new berth includes the grade separation of the inter-terminal road over the rail access to Patrick’s terminal. This is required to ensure efficient operation of both road and rail access to all

NSW PORTS

Page 31: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013 Page 31 of 60

No Condition Implementation CEMP Reference

existing and proposed new berths.

Noise and Vibration Management

Restrictions to Hours

B2.19 The Applicant shall only undertake construction activities associated with the project (with the exception of dredging construction activities) that would generate an audible noise at any residential premises during the following hours:

a) 7:00 am to 6:00 pm, Mondays to Fridays, inclusive;

b) 8:00 am to 1:00 pm on Saturdays; and

c) at no time on Sundays or public holidays.

Audible noise is defined as “noise that can be heard at the receiver”. This condition does not apply in the event of a direction from police or other relevant authority for safety or emergency reasons. Note: ‘safety or emergency reasons’ refers to emergency works which may need to be undertaken to avoid loss of life, property loss and/or to prevent environmental harm.

Patrick / Fulton Hogan

Construction Noise & Vibration Mgmt Sub-Plan

B2.19A The Applicant must seek the Director-General’s approval to conduct construction activities audible at residential premises (with the exception of dredging construction activities) outside the hours specified under condition B2.19 on a case-by-case basis. In seeking the Director-General’s approval, the Applicant shall demonstrate a need for activities to be conducted during varied hours and how local acoustic amenity will be protected, as well as details of how the EPA’s requirements with respect to the variation of hours have been addressed.

Patrick / Fulton Hogan

Construction Noise & Vibration Mgmt Sub-Plan

B2.19B For activities subject to an environmental protection licence issued by the EPA under the Protection of the Environment Operations Act 1997, conditions B2.19 and B2.19A do not apply if the EPA has approved activities to be conducted outside the hours permitted by condition B2.19.

Patrick / Fulton Hogan

NA

Construction Noise Management Plan

B2.20 Prior to the commencement of construction, the Applicant must prepare a Construction Noise Management Plan in consultation with DEC, DOP, Botany and Randwick Councils. The Plan shall include noise mitigation for piling works for diesel powered machinery, provision of training to ensure that construction workers are aware of the noise created during construction and are appropriately trained to minimise noise where possible. In addition, the Construction Noise Management Plan must:

Patrick / Fulton Hogan

Construction Noise & Vibration Mgmt Sub-Plan

-identify general activities that will be carried out and associated noise sources;

-assess construction noise impacts at the relevant receivers;

-provide details of overall management methods and procedures that will be implemented to control noise during the construction stage;

- identification of all feasible and reasonable measures to minimise noise and vibration, including but not limited to:

- using least noisy construction methods, vehicles, plant and equipment;

Page 32: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013 Page 32 of 60

No Condition Implementation CEMP Reference

- positioning and orientating noisy plant and equipment so as to minimise noise impacts on noise sensitive receivers and wildlife in Penrhyn Estuary;

- positioning items of noisy plant and equipment as far apart as is practicable from each other;

- minimising noisy activities by adopting alternative construction measures;

- carrying out above ground loading and unloading activities as far away as is practicable from noise sensitive receivers and wildlife in Penrhyn Estuary;

- designing each work site to minimise the need for truck reversing movements;

- ensuring all vehicles and self-propelled plant and equipment enter and leave the premises in a forward direction unless unforeseen accidents or other unforeseeable circumstances arise that may require reversing movements, in which case minimising any such reversing movements;

- taking all practicable steps to avoid reversing movements on the surface within the premises, and where it is impracticable to avoid reversing movements, taking all necessary steps to minimise reversing movements;

- preventing vehicle, plant and equipment queuing and idling outside the hours of construction prescribed by this consent.

-include a pro-active and reactive strategy for dealing with complaints including achieving the construction noise goals, particularly with regard to verbal and written responses;

-detail noise monitoring, reporting and response procedures consistent with DEC requirements;

-provide for internal audits of compliance of all plant and equipment;

-indicate site establishment timetabling to minimise noise impacts;

-procedures for notifying residents of construction activities likely to affect noise amenity;

-address the requirements of DEC; and

-be approved by the Director-General prior to the commencement of any works on the site.

Construction Noise Goals

B2.21 The goal for noise from construction activities as the LA10 (15 minute) should not exceed the Rating Background Level (RBL) plus 5dB(A) at sensitive receivers.

Patrick / Fulton Hogan

Construction Noise Mgmt Sub-Plan

Other Construction Noise Matters

B2.24 The Applicant is required to identify measures to be implemented to ensure that where movement alarms are fitted to vehicles, plant or equipment entering or operating on the site, such alarms are of a type that minimises noise at noise sensitive receivers.

Patrick / Fulton Hogan

Construction Noise & Vibration Mgmt Sub-Plan

Page 33: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013 Page 33 of 60

No Condition Implementation CEMP Reference

B2.25 The Applicant must install all physical noise management measures as early as is practicable during construction of the Port Botany Expansion project.

Patrick / Fulton Hogan

Construction Noise & Vibration Mgmt Sub-Plan

B2.26 The Applicant must not undertake any blasting on the premises Patrick / Fulton Hogan

No blasting

Waste Management

Construction Waste Management Plan

B2.33 Prior to the commencement of construction, the Applicant is required to prepare a Construction Waste Management Plan in consultation with Botany Council and DEC. The Plan must provide details of proposed waste management measures to minimise production and impact of wastes generated at the site including but not limited to:

Patrick / Fulton Hogan

Waste & Spoil Mgmt Sub-Plan

-identification of the type and quantities of waste that would be generated, a description of how the waste would be handled, stored, re-used, recycled, and if necessary, appropriately treated;

-identification of a designated area for the storage and collection of waste and recyclable materials top be provided on the site;

-description of how the effectiveness of these measures would be monitored and, if non-compliance detected, actions to be required;

-measures to involve and encourage employees and contractors to minimise domestic waste production on site and to reuse/recycle where possible.

Waste Management On-site

B2.34 Management of waste must be in accordance with the environment protection licence issued by EPA under the Protection of the Environment Operations Act 1997.

Patrick / Fulton Hogan

NA

B2.35 All wastes and material generated on the site during construction and operation shall be classified in accordance with the DEC’s Environmental Guidelines: Assessment, Classification and Management of Liquid and Non-Liquid Wastes prior to transporting the waste off site and be disposed of to a facility that may lawfully accept the waste.

Patrick / Fulton Hogan

Waste & Spoil Mgmt Sub-Plan

Hazardous and Industrial Waste

B2.36 Except as expressly permitted by a licence issued by the EPA under the Protection of the Environment Operations Act 1997, only the hazardous and/or industrial and/or Group A waste listed below may be generated and/or stored at the premises: -waste oil/water, hydrocarbons/water mixtures or emulsions; and -grease trap waste.

Patrick / Fulton Hogan

Waste & Spoil Mgmt Sub-Plan

Heritage Management

Potential for Discovery of Aboriginal Heritage Objects

Page 34: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013 Page 34 of 60

No Condition Implementation CEMP Reference

B2.39 If an Aboriginal object is discovered during the construction of the development, works should cease in the subject area and the Applicant shall notify DEC immediately.

Patrick / Fulton Hogan

Waste & Spoil Mgmt Sub-Plan

Hazard & Risk Management

Construction Safety Study

B2.41 The Applicant shall prepare a Construction Safety Study prior to commencement of construction of terminal operations infrastructure, accordance with Hazardous Industry Planning Advisory Paper No.7 – Construction Safety Study Guidelines (DoP, 1992). The commissioning portion of the Construction Safety Study may be submitted 2 months prior to commencement of commissioning. The study shall be submitted for the approval of Director-General prior to the commencement of construction of the terminal operations infrastructure.

Patrick / Fulton Hogan

Construction Safety Study

Fire Safety Study

B2.42 The Applicant shall prepare a Fire Safety Study prior to the commencement of construction of the terminal operations infrastructure in accordance with Hazardous Industry Planning Advisory Paper No.2 – Fire Safety Study Guidelines (DoP, 1992). The study shall be submitted for the approval of the Director-General and the Commissioner of the NSW Fire Brigades prior to the commencement of construction of the terminal operations infrastructure.

Patrick Fire Safety Study

Emergency Incident Management

Emergency Response and Incident Management Plan

B2.43 The Applicant shall develop an Emergency Response and Incident Management Plan in consultation with DEC, DOP, Council and the Community Consultative Committee. The Plan must be approved by the Director-General prior to the commencement of construction and shall detail:

Patrick / Fulton Hogan

Incident and Emergency Response Plan

-terminal security and public safety issues;

-effective spill containment and management;

-effective fire fighting capabilities;

-effective response to emergencies and critical incidents; and

-a single set of emergency procedures, consistent with the existing Port Botany Emergency Plan, should be developed that can be scaled as appropriate for any incident or emergency.

Aviation Construction Management

Impact on Aviation Operations at Sydney Airport

B2.44 The Applicant shall ensure that all aspects associated with construction considers the required lateral separation distances to minimise the interference to Sydney Airport radar and navigational systems.

Patrick / Fulton Hogan

Construction Plan

Page 35: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013 Page 35 of 60

No Condition Implementation CEMP Reference

Obstacle limitation Surface

B2.46 The Applicant shall ensure that all construction equipment is below obstacle limitation surface, unless otherwise permitted by an approval under the Airports (Protection of Airspace) Regulation 1996 and following consultation with the Department of Infrastructure, Transport, Regional Development and Local Government, Civil Aviation Safety Authority and Sydney Airport Corporation Limited.

Patrick / Fulton Hogan

Construction Plan

Terminal Construction Lighting Design

B2.47 The Applicant shall ensure design specifications of any construction lighting conform to the requirements of Regulation 94 of the Civil Aviation Regulations 1988.

Patrick / Fulton Hogan

Construction Plan

B3. COMMUNITY INFORMATION, INVOLVEMENT AND CONSULTATION

Community Information and Complaints Handling

B3.1 The Applicant must meet the following requirements in relation to community consultation and complaints management: Patrick Community Consultation Plan

-all monitoring, management and reporting documents required under the development consent shall be made publicly available; Patrick

-provide means by which public comments, inquiries and complaints can be received, and ensure that those means are adequately publicised; and Patrick

-includes details of a register to be kept of all comments, inquiries and complaints received by the above means, including the following register fields:

Patrick

-the date and time, where relevant, of the comment, inquiry or complaint; Patrick

-means by which comment, inquiry, complaint was made (telephone, fax, mail, email, person); Patrick

-any personal details of the commenter, inquirer or complainant that were provided, or if no details were provided, a note to that effect; Patrick

-the nature of the complaint; Patrick

-any action(s) taken by the Applicant in relation to the comment, inquiry or complaint, including any follow-up contact with the commenter, inquirer or complainant; and

Patrick

-if no action was taken by the Applicant in relation to the comment, inquiry or complaint, the reason(s) why no action was taken. Patrick

-Provide quarterly reports to the Department and DEC, where relevant, outlining details of complaints received. NSW PORTS & Patrick

B4. ENVIRONMENTAL MANAGEMENT, REPORTING AND AUDITING

Incident Reporting

B4.1 The Director-General shall be notified of any incident with actual or potential significant off-site impacts on people or biophysical environment Patricks / Fulton CEMP, Section 4.3.1

Page 36: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013 Page 36 of 60

No Condition Implementation CEMP Reference

within 12 hours of Applicant, or other relevant party undertaking the development, becoming aware of the incident. Full written detail of the incident shall be provided to the D-G within seven days of the date on which the incident occurred. The D-G may require additional measures to be implemented to address the cause or impact of any incident, as it relates to this consent, reported in accordance with this condition, within such period as the D-G may require.

Hogan

Annual Environmental Management Report (AEMR)

B4.2 The Applicant must prepare an Annual Environmental Management Report for the development. The Annual Environmental Management Report must:

Patricks CEMP, Section 5.4

-detail compliance with the conditions of this consent;

-contain a copy of the Complaints Register (for the preceding twelve-month period, exclusive of personal details) and details of how these complaints were addressed and resolved;

-include a comparison of the environmental impacts and performance predicted in the EIS and additional information documents provided to the Department and Commission of Inquiry;

-detail results of all environmental monitoring required under the development consent and other approvals, including interpretations and discussion by a suitably qualified person;

-contain a list of all occasions in the preceding twelve-month period when environmental performance goals have not been achieved, indicating the reason for failure to meet the goals and the action taken to prevent recurrence of that type of incident;

-be prepared within twelve months of commencement of construction, and every twelve months thereafter;

-be approved by the Director-General; and

-be made available for public inspection.

Environmental Representative

B4.3 Prior to the commencement of construction, a suitably qualified and experienced Environmental Representative(s) shall be nominated and approved by the D-G. The Environmental Representative(s) shall be employed for the duration of the construction and the on-going management, mitigation and monitoring associated with the development, excluding direct terminal operation matters subject to the conditions in Schedule C, or as otherwise agreed by the D-G. The Environmental Representative shall be:

Patricks CEMP, section 4.1

a) the primary contact point in relation to environmental performance of construction phases;

b) responsible for all Management Plans and Monitoring Programs required under this consent, in relation to construction phases;

c) responsible for considering/advising on matters specified in the conditions of this consent, and all other licences and approvals relating to the environmental performance and impacts of the construction phases;

Page 37: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013 Page 37 of 60

No Condition Implementation CEMP Reference

d) responsible for the management of procedures and practices for receiving and responding to complaints & inquiries in relation to the environmental performance of construction phases;

e) required to facilitate an induction/training program for relevant persons involved with construction phases;

f) given the authority and independence to require reasonable steps be taken to avoid or minimise unintended or adverse environmental impacts, and failing the effectiveness of such steps, to direct that relevant actions be ceased immediately should an adverse impact on environment be likely to occur.

Environmental Training

B4.4 Prior to commencement of any dredging, reclamation and construction an Environmental Training Program shall be developed and implemented to establish a framework in which relevant employees will be trained in environmental management and operation of plant and equipment, including pollution control equipment, where relevant. Program shall include, but not necessarily limited to:

Fulton Hogan CEMP, section 4.2

a) identification of relevant employment positions associated with the development that have an operational or management role related to environmental performance;

b) details of appropriate training requirements for relevant employees;

c) program for training relevant employees in operational and/ or management issues associated with environmental performance;

d) program to confirm/update environmental training and knowledge during employment of relevant persons.

Environmental Auditing

B4.5 Within one year of the commencement of construction and every year thereafter for the duration of construction a full independent environmental audit shall be undertaken by a suitably qualified person/team approved by the Director-General. Audits would be made publicly available and would:

Patricks CEMP, Section 5.4

-be carried out in accordance with ISO 14010 and ISO 14011 – Procedures for Environmental Auditing;

-assess compliance with requirements of this consent, other licences/approvals;

-assess the construction against the predictions made and conclusions drawn in the development application, EIS, additional information and Commission of Inquiry material; and

-review effectiveness of environmental management, including any environmental impact mitigation works.

Note: An independent and transparent environmental audit can verify compliance (or otherwise) with the Minister’s consent and various approvals. Auditing also provides an opportunity for continued improvement in environmental performance.

Page 38: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013 Page 38 of 60

Attachment D. Summary of EIS Requirements

Item EIS Reference Page No Relevant Text Responsibility / Actions to address

1. Executive Summary ES11.5 Paragraph 3

ES22

Some limited disturbance of potential acid sulphate soils may occur as a result of construction of the new terminal, however, any potential acid sulphate soils within the dredged area would be contained within the reclamation, or kept below the water level to prevent oxidisation.

Acid Sulfate Soil Management Sub-Plan

2. Executive Summary ES12 Paragraph 1

ES30

An Environmental Management and Monitoring Plan (EMMP) would be developed and implemented in accordance with management and monitoring measures set out in this EIS, statutory requirements and conditions of approval for the project. Construction and Operation EMPs would form an integral part of the project EMMP and would be prepared in accordance with ISO 9001:2000 and ISO 14001:1996.

CEMP

3. Chapter 16.8.1 Paragraph 5

Chapter 37.2 Table 37.1, point 12

16-22

Aside from turbidity control, the following mitigation measures would be implemented to minimise the impact of the construction on surface water flow and water quality:

construction activities would be conducted in a manner that minimises the potential for spills or leaks, including the regular inspection and maintenance of plant and equipment, and providing bunding or similar spill containment structures for onsite fuel and oil storage;

any spills or leaks would be contained/cleaned up as quickly as possible;

resealing and revegetation of all exposed surfaces as soon as practical to prevent extended exposure to erosion;

erosion and sediment control planning and implementation would apply to all areas which may be disturbed. Regular inspection of all structures would occur after heavy rain and during periods of prolonged rainfall;

a Soil and Water Management Plan (SWMP) would be prepared in accordance with the guidelines contained in Managing Urban Stormwater - Soils and Construction Manual and incorporated into the CEMP for the project. Details of erosion and sediment control measures would include:

– temporary structures such as sedimentation ponds and silt fences surrounding stockpiles to prevent offsite movement of sediment;

– control of drainage from areas adjacent to construction areas using earth bunds and diverting structures such as earth drains;

– minimisation of traffic in construction zones and provision of dedicated parking areas; and

– removal of soil from vehicle wheels and undercarriages before departing the site to reduce soil carried offsite.

Soil & Water Management Sub-Plan

4. Chapter 17.6.2 Paragraph 2

Chapter 37.2 Table 37.1,

17-14

The SWMP for construction would be based on the Managing Urban Stormwater- Soils and Construction Manual and incorporated in the CEMP. All work would be carried out to avoid contamination of site and the

Soil & Water Management Sub-Plan

Emergency Response & Incident Management

Page 39: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013 Page 39 of 60

Item EIS Reference Page No Relevant Text Responsibility / Actions to address

points 6,17,21 surrounding areas. Contamination control measures would include:

storage and handling of all dangerous goods in accordance with AS, NSW Dangerous Goods (General) Regulations 1999 and NSW EPA guidelines;

an emergency response plan to control fuel, oil and chemical spills;

machinery would be inspected regularly to identify any leaks;

provision of spill containment equipment (e.g. spill kits) located around the construction site; and

training of staff in spill clean-up procedures and use of spill kits.

Plan

5. Chapter 18.5.1

Paragraph 8

18-11

The SWMP for construction would be based on the Managing Urban Stormwater- Soils and Construction Manual and would be incorporated in the Construction EMP. All work would be carried out to avoid erosion and sedimentation of the site and the surrounding areas. Erosion and sediment control measures would include:

temporary structures to prevent offsite movement of sediment such as sedimentation ponds and silt fences surrounding stockpiles;

control of drainage from areas adjacent to construction areas using earth bunds and diverting structures such as earth drains;

dust minimisation using collected stormwater where possible;

cessation of work, or implementation of further suppression measures if excessive fugitive dust emissions are observed;

minimisation of traffic in construction zones and a dedicated parking area;

removal of soil from vehicle wheels and undercarriages; and

sealing and revegetation of all disturbed surfaces as soon as practical to prevent extended exposure to erosion.

Erosion and sediment control planning and implementation would apply to all areas which may be disturbed. Regular inspections would occur after heavy rain & during periods of prolonged rainfall.

Soil & Water Management Sub-Plan

6. Chapter 21.9.1

Paragraph 1

21-26

A detailed Construction Traffic Management Plan would be developed and incorporated into Construction EMP for the project. The plan would include detailed consideration of:

identification of preferred haulage routes;

access routes and signage, and access arrangements at the site;

measures to ensure that Foreshore Road would not be affected by:

− loading/unloading from the carriageway;

− queuing; and

Traffic Management Plan

Page 40: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013 Page 40 of 60

Item EIS Reference Page No Relevant Text Responsibility / Actions to address

− reversing manoeuvres during construction;

the need for restrictions on delivery hours and/or routes; and

the need for measures to protect pedestrians, cyclists and other motorists in the vicinity of the site.

provision of cleaning facilities for vehicles exiting the site.

7. Chapter 22.5.9

Paragraph 1

22-24

A Noise Management Plan would be developed and incorporated into the CEMP, including:

Piling noise - Where impact piling cannot be avoided, all efforts would be made to reduce noise levels from the piling hammers. Resilient dollies would be placed in between the pile and the hammer. The hammer would also be shrouded to provide acoustic attenuation where practical. The exact degree of attenuation depends on hammer design and therefore cannot be predicted accurately at this stage.

Machinery noise control – Where practical, noise levels from diesel powered machinery would be reduced by fitting noise control kits to machinery.

Awareness and training – Provision of training to ensure that construction workers are aware of the noise created during construction and are appropriately trained to minimise noise where possible.

Complaints – Complaints would be assessed and responded to in a quick and effective manner.

Noise monitoring – Noise monitoring would be conducted to assess impacts from construction noise at monthly intervals and in response to any complaints which may be received.

Construction Noise & Vibration Management Sub-Plan

CEMP Section 6 and Appendix 8a

8. Chapter 23.8.1 23-17

Dust Management Plan for construction:

apply water, through the use of water trucks, to active earthwork areas, stockpiles, gravel roads and loads of soil being transported to reduce wind blown dust emissions;

site roads to consist of coarse gravel and to be kept wet to minimize wheel generated dust emissions;

The DMP would also include safeguard measures such as:

keep the working face and areas of open excavation to a minimum;

vegetate stockpiles where material is to remain on site for long periods;

cease work if excess dust is observed, or phase down while the source is being actively investigated and suppression measures are implemented;

restrict construction traffic to defined roads and implement a speed limit;

remove soil adhering to the wheels and undercarriage of vehicles prior to departure from the site; and

progressively landscape and vegetate areas as the construction activities proceed, where practical.

Dust & Air Quality Management Sub-Plan

9. Chapter 23.9.1 23-18

Prior to and during construction, monitoring in areas considered most likely to receive dust impacts during construction would be undertaken. All monitoring would be undertaken in accordance with the NSW EPA Approved Methods for the Sampling and Analysis of Air Pollutants in NSW (2001). All monitoring devices

Dust & Air Quality Management Sub-Plan

Page 41: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013 Page 41 of 60

Item EIS Reference Page No Relevant Text Responsibility / Actions to address

would be located in accordance with AS 2922-1987 – Ambient Air – Guide for Siting of Sampling Units.

In particular, one high-volume air sampler would be installed within the residential area to the north of Foreshore Road, preferably to the south of Botany Road. This location is shown by dispersion modelling to receive the greatest dust impacts during construction. This high-volume air sampler would monitor PM10 on a six-day cycle in accordance with AS 3580.9.6-1990 – Particulate matter – PM10 – high-volume sampler with size-selective inlet.

Three dust deposition gauges would also be installed within residential areas – two in the residential area north of Foreshore Road, and one in the Matraville residential area immediately east of Amcor (Botany Road, Matraville). An additional dust deposition gauge would also be located in Penrhyn Estuary.

10. Chapter 28.10.3

Paragraph 1

28-20

Pursuant to and in accordance with SEPP 33 guidelines, following project approval NSW PORTS would conduct a construction safety study, incorporating comprehensive identification of potentially hazardous incidents that could arise during the construction of the Port Botany Expansion and setting out the organisational and operational safeguards proposed to address such incidents.

Construction Safety Study

11. Chapter 29.4.1 Paragraph 3 29-6 Temporary construction lighting would use tinted lights where possible to minimise the attraction of insects on which birds are likely to feed.

Construction Plan

12. Chapter 29.4.2 Paragraph 1 29-8 Should birds be attracted to the site, attempts would be made to discourage them from feeding or roosting by using flagging material or other deterrent methods as described [in EIS section 29.4.2 paragraph 2].

Waste & Spoil Management Sub-Plan

13. Chapter 30.5.2 Lighting during construction and operation would be carefully selected to ensure they would not infringe the provision of Regulation 94 of the Civil Aviation Regulations 1988. During the detailed design stage, CASA would be consulted for detailed guidance and appropriate restrictive controls.

Construction Plan

14. Chapter 35.4.1

Paragraph 1

35-4 The following mitigation measures would be undertaken during construction works and detailed in the Construction EMP:

efficient work scheduling and methods that minimize equipment idle time and double handling of material;

throttling down and switching off construction equipment when not in use;

switching off truck engines while they are waiting to access the site and while they are waiting to be loaded and unloaded;

switching off site office equipment and lights and using optimum lighting intensity for security and safety purposes;

careful design of temporary roads to reduce transportation distances;

regular equipment maintenance to ensure optimum ops & fuel efficiency;

the specification of energy efficient construction equipment.

Dust & Air Quality Management Sub-Plan

Page 42: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013 Page 42 of 60

Item EIS Reference Page No Relevant Text Responsibility / Actions to address

15. Chapter 37.2 Table 37.1 Point 17

37-3 Develop a SWMP, as part of the Construction EMP, to ensure an adequate standard is applied to control of contaminants which could impact groundwater quality during the construction of the Port Botany Expansion.

Soil & Water Management Sub

16. Chapter 37.2 Table 37.1 Point 21

37-3 Prepare and implement a SWMP as part of the Construction EMP to control erosion and sedimentation (as described above).

Soil & Water Management Sub

17. Chapter 37.2

Table 37.1 Point 45

37-5 Develop a Construction Traffic Management Plan with:

identification of preferred haulage routes;

access routes and signage, and access arrangements at the site;

measures to ensure that Foreshore Road would not be affected by loading/unloading from the carriageway, queuing and reversing manoeuvres;

the need for restrictions on delivery hours and/or routes; and

the need for measures to protect pedestrians, cyclists and other motorists.

Traffic Management Plan

18. Chapter 37.2, Table 37.1 Point 50

37-5 Reduce noise levels from piling hammers by placing resilient dollies in between pile and hammer, where practical. The hammer would be shrouded to provide acoustic attenuation.

Construction Noise & Vibration Management Sub

19. Chapter 37.2, Table 37.1 Point 51

37-5 Reduce noise levels from diesel powered machinery by fitting noise control kits to machinery, where practical. Construction Noise & Vibration Management Sub

20. Chapter 37.2, Table 37.1 Point 52

37-5 Conduct training to ensure construction workers are aware of noise issues and act to minimise noise where possible.

CEMP Section 5

21. Chapter 37.2 Table 37.1 Point 57

37-6 Keep the working face and areas of open excavation to a minimum. Dust & Air Quality Management Sub-Plan

22. Chapter 37.2 Table 37.1 Point 58

37-6 Apply water, through the use of water trucks, to active earthwork areas, stockpiles, gravel roads and loads of soil being transported to reduce wind blown dust emissions.

Dust & Air Quality Management Sub-Plan

23. Chapter 37.2 Table 37.1 Point 59

37-6 Ensure site roads consist of coarse gravel and are kept wet to minimise wheel generated dust emissions. Dust & Air Quality Management Sub-Plan

24. Chapter 37.2 Table 37.1 Point 60

37-6 Vegetate stockpiles where material is to remain on site for a long period of time. Dust & Air Quality Management Sub-Plan

25. Chapter 37.2 Table 37.1 Point 63

37-6 Cease or phase down work if excess fugitive dust is observed while the source is being actively investigated and suppression measures are implemented.

Dust & Air Quality Management Sub-Plan

26. Chapter 37.2 Table 37.1 Point 64

37-6 Restrict traffic to defined roads and implement a speed limit. Dust & Air Quality Management Sub-Plan

Page 43: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013 Page 43 of 60

Item EIS Reference Page No Relevant Text Responsibility / Actions to address

27. Chapter 37.2 Table 37.1 Point 65

37-6 Remove soil adhering to the wheels and undercarriage of vehicles prior to departure from the site. Dust & Air Quality Management Sub-Plan

28. Chapter 37.2 Table 37.1 Point 66

37-6 Progressively landscape and vegetate areas as the construction activities proceed. Dust & Air Quality Management Sub-Plan

29. Chapter 37.2 Table 37.1 Point 104

37-9 All construction and operation equipment to be below the OLS Construction Plan

30. Chapter 37.2 Table 37.1 Point 128

Chapter 34.4.1 Paragraph 9

37-11

Empty portable toilet facilities on a regular basis by an appropriately licensed waste management contractor Waste & Spoil Management Sub-Plan

31. Chapter 37.2 Table 37.1 Point 130

Chapter 34.4.1 Paragraphs 1,2

37-11

Develop and implement a WMP for the construction and operational phase in accordance with the requirements of the Waste Avoidance and Resource Recovery Act 2001, the Protection of the Environment Operations Act 1997, the EPA's Environmental Guidelines: Assessment, Classification & Management of Liquid & Non-Liquid Wastes (1999), the Botany Bay DCP 29 and the National Minimisation and Recycling Strategy.

The Construction WMP would require that all contractors carrying out construction works record the types, quantities and destinations of all waste material taken offsite. In addition, any licensing requirements for the management and disposal of waste from the site would be identified in the Construction WMP. All personnel would be advised of waste management and disposal procedures described in the Construction WMP prior to commencing work.

Waste & Spoil Management Sub-Plan

32. Chapter 37.2 Table 37.1 Point 131

Chapter 34.4.1 Paragraph 3

37-11

Minimise construction waste that requires disposal by accurately calculating materials brought to the site and limiting materials packaging.

Waste & Spoil Management Sub-Plan

33. Chapter 37.2 Table 37.1 Point 132

Chapter 34.4.1 Paragraph 4

37-11

Return excess construction materials which are suitable for reuse to the supplier or store for future use. Waste & Spoil Management Sub-Plan

34. Chapter 37.2 Table 37.1 Point 133

Chapter 34.4.1 Paragraph 4

37-11

Store construction wastes which are not suitable for reuse, but are able to be recycled, in dedicated and secure skips prior to recycling.

Waste & Spoil Management Sub-Plan

35. Chapter 37.2 Table 37.1 Point 134

37-11

Store, in separate skips, construction wastes which cannot be recycled. The skips would be collected by a licensed waste contractor on a regular basis and transported for disposal to a licensed landfill or recycling facility.

Waste & Spoil Management Sub-Plan

Page 44: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013 Page 44 of 60

Item EIS Reference Page No Relevant Text Responsibility / Actions to address

Chapter 34.4.1 Paragraph 4

36. Chapter 37.2 Table 37.1 Point 135

Chapter 34.4.1 Paragraph 6

37-11

Process or shred vegetation waste (trees and shrubs) into wood chip or mulch, which would then be used in the rehabilitation of areas disturbed during construction and for landscaping.

Waste & Spoil Management Sub-Plan

37. Chapter 37.2 Table 37.1 Point 136

Chapter 34.4.1 Paragraph 7

37-11

Stockpile excavated soil generated during site preparation activities for reuse in landscaping activities. Any soil which cannot be disposed of in this manner would be transported off site to a licensed landfill, after appropriate classification for the material is carried out in accordance with NSW EPA requirements.

Waste & Spoil Management Sub-Plan

38. Chapter 37.2 Table 37.1 Point 137

Chapter 34.4.1 Paragraph 8

37-12

Provide recycling facilities to maximise recycling of waste materials such as plastic and glass bottles/containers, aluminium cans and paper/cardboard. Separate bins would be provided for food waste. Collect all domestic waste on a regular basis and transported off site for disposal to a licensed landfill or recycling facility.

Waste & Spoil Management Sub-Plan

39. Chapter 37.2 Table 37.1 Point 138

37-12

Recycle scrap metal, used parts, components and machinery where practicable. Waste & Spoil Management Sub-Plan

40. Chapter 37.2 Table 37.1 Point 139

37-12

Waste oils and fluids from maintenance activities would be collected and stored and would either be reused on site or removed by a licensed waste contractor.

Waste & Spoil Management Sub-Plan

41. Chapter 38.2 38-1 Prepare Environmental Management and Monitoring Plan for construction. CEMP

42. Chapter 38.2 38-3 Prepare Emergency Response & Incident Management Plan for construction. Emergency Response & Incident Management Plan

43. Chapter 38.5 Table 38.2 Point 1

38-4 Monitor compliance of the construction activities with the Construction EMP, including EPA requirements and MCOA, on an ongoing basis.

CEMP

44. Chapter 38.5 Table 38.2 Point 5

38-5 Monitor erosion and sediment control structures in accordance with the SWMP prepared in accordance with the guidelines contained in Managing Urban Stormwater - Soils and Construction Manual and incorporated into the CEMP.

CEMP

45. Chapter 38.5 Table 38.2 Point 7

38-5 Monitor construction activities in accordance with the ASSMP. CEMP

46. Chapter 38.5 Table 38.2 Point 8,12

38-5 Monitor the extent of construction areas to ensure they do not extend beyond the defined construction zone CEMP

47. Chapter 38.5 Table 38.2 Point 15

38-6 Visual inspection of construction zones to ensure construction vehicles are using defined roads and access points. Traffic Management Plan, CEMP

Page 45: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013 Page 45 of 60

Item EIS Reference Page No Relevant Text Responsibility / Actions to address

48. Chapter 38.5 Table 38.2 Point 16

38-6 Check that on site trucks are not overloaded, that they adhere to speed limits, that their trays are covered and that materials are loaded and unloaded carefully.

Traffic Management Plan, CEMP

49. Chapter 38.5 Table 38.2 Point 17

38-6 Check that trucks arriving at the site before it opens are parked in designated holding areas and not on adjacent streets.

Traffic Management Plan, CEMP

50. Chapter 38.5 Table 38.2 Point 18

38-6 Conduct investigative noise monitoring in response to specific complaints. Construction Noise & Vibration Management Plan, CEMP

51. Chapter 38.5 Table 38.2 Point 19

38-6 Conduct noise monitoring in the vicinity of residential areas and sensitive receiver locations for each stage of construction prior to construction of infrastructure and facilities on the new terminal itself

Construction Noise Management Plan,

52. Chapter 38.5 Table 38.2 Point 20

38-6 Visually monitor dust generation from work zones to ensure that excessive dust is not being produced. Dust Management Plan, CEMP

53. Chapter 38.5 Table 38.2 Point 21

38-6 Inspect sites to ensure that adequate dust controls are being used such as regularly watering unsealed areas. Dust Management Plan, CEMP

54. Chapter 38.5 Table 38.2 Point 22

38-6 Monitor dust impacts using a high-volume air sampler, dust deposition gauges and onsite meteorological station in accordance with the EPA Approved Methods for the Sampling & Analysis of Air Pollutants (2001). Locate monitoring devices in accordance with AS 2922-1987 - Ambient Air - Guide for Siting of Sampling Units.

Dust Management Plan, CEMP

55. Chapter 38.5 Table 38.2 Point 24

38-6 Report any heritage relics discovered during construction activities to NPWS for Aboriginal relics or Heritage Office for items of European heritage. Cease works pending their consideration.

Waste & Spoil Management Sub-Plan

56. Chapter 38.5 Table 38.2 Point 14

38-6 Inspect waste receptacles to ensure that they are not being overfilled and are being collected on a regular basis. Waste & Spoil Management Sub-Plan

57. Chapter 38.5 Table 38.2 Point 14

38-6 Inspect construction zones to monitor for any unauthorised waste disposal activity. Waste & Spoil Management Sub-Plan

58. Chapter 38.5 Table 38.2 Point 14

38-6 Inspect the construction site to evaluate the effectiveness of waste storage and collection practices. Waste & Spoil Management Sub-Plan

59. Chapter 38.5 Table 38.2 Point 14

38-6 Inspect any portable toilet facilities to ensure they are being emptied on a regular basis. Waste & Spoil Management Sub-Plan

60. Chapter 38.5 Table 38.2 Point 14

38-6 Monitor waste recycling and disposal procedures to ensure they are being complied with. Waste & Spoil Management Sub-Plan

Page 46: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013 Page 46 of 60

Attachment E. Register of Relevant Legislation

Legislation Key Requirements Relevance to the Project Mechanism for Evaluating Compliance

New South Wales

Contaminated Land Management Act 1997

The main objective of this Act is to establish a process for investigating and remediating land areas where contamination presents a significant risk of harm to human health or some other aspect of the environment.

Under this act EPA has the power to:

Declare an investigation site and order and investigation

Declare a remediation site and order remediation to take place

Agree to a voluntary proposal to investigate or remediate a site

Some spoil may be contaminated as a result of previous off-site activities. Where contaminated material is found, storage and disposal procedures are to comply with the Contaminated Land Management Act 1997.

Measures for testing, handling and disposing of contaminated spoil are in the Waste & Spoil Management Sub-Plan.. Testing is used to ensure compliance.

Environmentally Hazardous Chemicals Act 1985

The purpose of this Act is to control chemicals that are environmentally hazardous. EPA may make chemical control orders (CCOs) with respect to assessed chemicals or declared chemical wastes. The CCOs may regulate the manufacture, processing, conveying, buying, selling or disposal of chemical or declared waste. A CCO may prohibit activities in relation to declared chemical wastes, except under the authority of a licence issued by EPA.

Certain chemicals used or generated may be subject to handling and disposal requirements in this Act.

Measures for identification, handling, disposal of hazardous wastes are in the Waste & Spoil Management Sub-Plan.

Environmental Planning and Assessment Act 1979

(EP&A Act)

The main objective of the EP&A Act is to ensure that proper management and development of land is undertaken incorporating the ecologically sustainable development principles. To achieve this the EP&A Act:

Ensures that development consent is obtained prior to construction;

Ensures compliance with planning consents and conditions associated with the consent;

Ensures environmental assessment is undertaken prior to development consent;

Has provision for penalties to be issued should development conditions be breached.

NSW PORTS has satisfied the requirements of the EP&A Act 1979 to date and has obtained development consent for the project.

No requirements for further development consent are anticipated.

Conditions to the development approval (Minister’s Conditions of Approval) are tracked via CEMP Appendix 2A.

National Parks and Wildlife Act 1974

Under this Act, NPWS is responsible for the care, control and management of all national parks, historic sites, nature reserves, reserves, Aboriginal areas and state game reserves. The Act governs various activities including:

Protection of flora and fauna, and Aboriginal heritage;

Licences and approvals to modify or destroy flora, fauna or Aboriginal heritage;

Penalties for breaches of the Act.

Relates to any Aboriginal heritage or relics, and protection of flora and fauna.

No Aboriginal heritage is anticipated in the project area due to previous reclamation, and minimal cutting.

Aboriginal heritage measures are in the Waste & Spoil Management Sub-Plan.

Protection of the The POEO Act is the key piece of environment protection legislation, and is administered by the EPA. The Construction of structures over Specific requirements for

Page 47: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013 Page 47 of 60

Legislation Key Requirements Relevance to the Project Mechanism for Evaluating Compliance

Environment Operations Act 1997

(POEO Act)

objective of the Act is to protect restore and enhance the quality of the environment in NSW with a need to maintain ecologically sustainable development. To achieve this the following tools are employed:

Integrated environment protection licensing;

Regulation of scheduled and non-scheduled activities;

Environmental protection offences and penalties;

Environmental protection notices;

Establishment of a general duty to notify of environmental harm;

Powers for authorised officers to investigate actual or potential pollution events.

Schedule 1 of the POEO Act lists activities that are subject to environmental licensing.

In addition to the main objective, the POEO Act assists in achieving the objectives of the Waste Avoidance and Resource Recovery Act 2001.

railway systems is an activity that is required to be licenced.

Environmental protection offences and penalties, and a duty to notify of environmental harm, apply to all personnel working on the project.

compliance are in the CEMP and sub-plans.

Training on POEO Act offences and penalties, and duty to notify, are included in induction processes.

POEO (General) Regulation 1998

The Regulation:

sets out how to calculate fees for environment protection licences, environment protection notices and noise control notices, and makes provision for adjustment or refunds of those fees;

makes provisions for load reduction agreements (load reduction agreements allow for fee rebates in return for measures taken to reduce pollution in the future);

sets out matters to be included by the EPA for the grant or refusal of a licence application;

makes it an offence to provide false or misleading information in relation to a licence application;

requires licensees to retain records used to calculate licence fees;

gives effect to the National Environment Protection (National Pollutant Inventory) Measure by requiring occupiers of certain facilities to submit data relating to the emission of certain substances;

prescribes certain matter when placed into water to be water pollution, and the methodology for testing matter in waters;

exempts certain water pollution from the water pollution offence under the Protection of the Environment Operations Act 1997;

prescribes certain forms to be used with respect to warrants relating to noise abatement directions;

declares certain bodies to be the appropriate regulatory authority in relation to certain activities for the purposes of the Protection of the Environment Operations Act 1997;

Construction activities require environmental protection licences.

Specific requirements for compliance are in the CEMP and sub-plans.

POEO (Noise Control) This Regulation repeals and remakes, with minor amendments, the provisions of the Protection of the Noise emissions from machinery. Measures for reducing

Page 48: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013 Page 48 of 60

Legislation Key Requirements Relevance to the Project Mechanism for Evaluating Compliance

Regulation 2008 Environment Operations (Noise Control) Regulation 2000:

the sounding of sirens and similar devices and the use of sound systems on vessels,

the emission of noise from the engines or exhausts of motor vehicles and vessels,

the maintenance of noise control equipment on motor vehicles and vessels,

the issue of defective vehicle notices and defective vessel notices,

the times during which it is not permissible to use certain articles if they emit noise that can be heard in any residential premises,

the inspection and testing procedures for the purpose of determining noise emission levels of certain motor vehicles, motor vehicle accessories, vessels, articles or equipment.

noise are in the Construction Noise & Vibration Mgmt Sub-Plan.

POEO (Penalty Notices) Regulation 2004

This Regulation:

sets out the offences under the Protection of the Environment Operations Act 1997 and related Acts and regulations for which penalty notices may be issued, and the amount of such fines;

specifies the organisations authorised to issue penalty notices for particular offences; and

authorises the service of a penalty notice relating to an offence, applying to an owner of a motor vehicle or vessel, on the owner without naming the address of the owner and by leaving the penalty notice on that vehicle or vessel.

Environmental protection offences and penalties, and a duty to notify of environmental harm, apply to all personnel working on the project.

Training on POEO Act offences and penalties, and duty to notify, are included in induction processes.

POEO (Waste) Regulation 2005

Schedule 1 of the regulation sets out the types of waste to which waste tracking requirements apply. Certain chemicals used or generated may be subject to tracking requirements in this regulation.

Measures for tracking hazardous wastes are in the Waste & Spoil Management Sub-Plan.

Protection of the Environment Operations Amendment (Scheduled Activities and Waste) Regulation 2008

This framework uses a mix of legislative, policy, educative and economic tools to encourage waste avoidance and the further recovery of resources. This new framework includes:

Fewer and simpler licensing categories for waste;

A streamlined waste classification system;

New resource recovery licensing categories and resource recovery exemptions; and

Clearer requirements for managing asbestos and clinical waste.

The waste regulatory framework is administered under the principal legislation of the Protection of the Environment Operations Act 1997 and the Waste Avoidance and Resource Recovery Act 2001.

Altered definitions of waste categories and disposal requirements.

Changes made by this amendment regulation have been included in the Waste & Spoil Management Sub-Plan.

Waste Avoidance and Resource

This Act promotes waste avoidance and resource recovery by: Waste is generated during construction. The principles of

Measures for minimising, handling, recycling and

Page 49: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013 Page 49 of 60

Legislation Key Requirements Relevance to the Project Mechanism for Evaluating Compliance

Recovery Act 2001 Encouraging efficient use of resources in accord with ecologically sustainable principles;

Promoting the “Avoid, reuse, recycle, dispose” hierarchy;

Ensuring industry has a responsibility for reducing and dealing with waste;

Providing penalties for breaches of this Act.

the Act are applied to all aspects of construction to reduce impacts from waste.

disposal of wastes are in the Waste & Spoil Management Sub-Plan.

Water Act 1912 An Act consolidating water rights, water and drainage and artesian wells. Provisions include a licence requirement to sink or alter an artesian bore, not to waste water taken from dams, lakes, artesian wells and bores, and not to unlawfully interfere with sub-surface water or obstruct its flow.

Construction works are within the groundwater extraction exclusion zone regulating bore use. No bore use is expected.

N/A

Water Management Act 2000 and

Water Management (General) Regulation 2004

The Water Management Act 2000 is the main piece of water legislation in NSW and governs:

Extraction of water from waterways and bores

The construction of water storage and supply structures

Development or building within the proximity of waterways

Licencing to regulate usage of water resources

Works involving the removal of obstructions from the improvement of rivers and foreshores and the prevention of erosion of lands by tidal and non-tidal waters

Permits are required to excavate protected land, remove material from protected land or do anything to detrimentally affect the flow of waters.

Groundwater extraction is not possible, as construction works are within the groundwater extraction exclusion zone. No bore use is expected.

NSW Maritime indicated that they do not require a Controlled Activity Application from NSW PORTS for this project.

N/A

Commonwealth

Environment Protection and Biodiversity Conservation Act 1999

(EPBC Act)

This Act aims to protect the environment, particularly matters of National Environmental Significance (NES). Approval is required for actions that are likely to have a significant impact on:

a matter of national environmental significance;

environment of Commonwealth land (even if taken outside Commonwealth land);

environment anywhere in the world if the action is undertaken by the Commonwealth.

Permits are required under the EPBC Act for:

certain activities in Commonwealth reserves;

activities that affect listed species or communities in Commonwealth areas; cetaceans in Commonwealth waters and outside Australian waters.

The Act contains compliance and enforcement mechanisms such as court injunctions, required environmental audits, strict civil and criminal penalties, remediation of environmental damage, liability of executive officers,

NSW PORTS has obtained Commonwealth approval, which involves migratory and threatened species protected by the Act.

Many shorebirds within Botany Bay are directly protected as listed threatened species and/or listed migratory species. Many aquatic fauna species are listed as protected.

NSW PORTS is responsible for complying with consent conditions under the EPBC Act, as defined by Deed Schedule 19.

Procedures for protecting Penrhyn Estuary are contained in the Penrhyn Estuary Protection Plan.

Page 50: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or unsigned. Copyright © 2013, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/2013 Page 50 of 60

Legislation Key Requirements Relevance to the Project Mechanism for Evaluating Compliance

and publicising contraventions.

Hazardous Waste (Regulation of Exports and Imports) Act 1989

This Act regulates export and import of hazardous waste to ensure that hazardous waste is disposed of safely. The Act requires that a permit be obtained before hazardous waste is exported from Australia or imported into Australia.

It is not anticipated that any hazardous wastes will need to be exported.

N/A

Key Policies

SEPP 33 -Hazardous and Offensive Development

Provides new definitions for 'hazardous industry', 'hazardous storage establishment', 'offensive industry' and 'offensive storage establishment'. These enable decisions to approve or refuse a development to be based on the merit of proposal. The policy also requires specified matters to be considered for proposals that are 'potentially hazardous' or 'potentially offensive'. The policy does not change the role of councils as consent authorities, land zoning, or designated development provisions of the EP&A Act.

No relevance. -

SEPP 55 - Remediation of Land

Introduces state-wide planning controls for remediation of contaminated land. Land must not be developed if it is unsuitable for a proposed use because it is contaminated. If the land is unsuitable, remediation must take place before the land is developed. The policy makes remediation permissible across the State, defines when consent is required, requires all remediation to comply with standards, ensures land is investigated if contamination is suspected, and requires councils to be notified of all remediation proposals. To assist councils and developers, the Department, in conjunction with the Environment Protection Authority, has prepared Managing Land Contamination: Planning Guidelines.

If contaminated soil is found, storage and disposal procedures are to comply with the Contaminated Land Management Act 1997.

Measures for testing, handling and disposing of contaminated soil are in the Waste & Spoil Management Sub-Plan.

SEPP (Infrastructure) 2007

Provides a consistent planning regime for infrastructure and the provision of services across NSW, along with providing for consultation with relevant public authorities during the assessment process. The SEPP supports greater flexibility in the location of infrastructure and service facilities along with improved regulatory certainty and efficiency.

No relevance. -

Botany LEP 1995 to provide planning controls for the local government area of Botany Bay City which update and consolidate into a single local environmental plan the various local planning controls that currently apply to the local government area of Botany Bay City;

to give the Council greater responsibility in environmental planning by creating broad controls;

to rationalise and simplify zoning and development controls; and

to provide direction and guidance to the community concerning desired growth and change in the local government area of Botany Bay City.

Provides zoning of area in and adjacent to project boundaries. Provides items of local heritage significance.

-

Page 51: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or printed from the Intranet. Copyright © 2009, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13 Page 51 of 60

Attachment F. Environmental Inspection Report

Inspected by:

Inspection date:

Inspection time:

Rain in the last 24hrs (mm)?

Weather conditions1:

Location/ Chainage

Issue Action Required By Whom By When Completion Sign Off

1 Sunny Scattered clouds Light showers Rain Thunderstorm Windy

Page 52: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or printed from the Intranet. Copyright © 2009, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13 Page 52 of 60

Additional notes or observations:

Results of the inspection have been discussed at Site Meeting/Toolbox Talk Yes No Results of the inspection have been communicated to: Foreman Earthworks Manager Structures Manager Project Director

Page 53: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or printed from the Intranet. Copyright © 2009, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13 Page 53 of 60

Site environmental performance evaluation criteria The following criteria are to be used when undertaking site environmental inspections:

General

The site is generally in a tidy condition

All materials and equipment are contained within the project boundary

All works are undertaken within the project boundary

Designated impervious bunded concrete wash out facilities are in place and positioned at least 50m away from natural and built drainage lines, where practicable

Clean Water Diversion

All clean water is being diverted away from the disturbed areas

All clean water diversion drains are stable

Soil Disturbance and Erosion Control

The sediment fence is installed correctly and there are no gaps

All disturbed area where no works are undertaken are properly covered or stabilised

Areas of localised soil erosion have been identified and appropriate preventative measures implemented

There are no areas of potential or actual concentrated flow that do not flow to sediment basins/traps

Slope lengths are maintained at appropriate lengths to slow flows down and minimise erosion

Page 54: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or printed from the Intranet. Copyright © 2009, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13 Page 54 of 60

Check dams are used within diversion drains where required to slow flows down and minimise erosion within the drains

Geotextile linings (or similar) is used to provide temporary surface protection in areas where appropriate (e.g. batter drains, culvert construction)

Stockpile Management

Stockpiles are sited in low-hazard areas clear of watercourses and flood prone lands

Cut-off drains on the upslope side and sediment fencing on the downslope side are in place for all stockpile areas within the site

Stockpiles are less than 2m in height

Sediment Control

Sediment control measures are constructed as close to the potential source of sediment as possible

Shakers, rubble pads or wash down areas have been installed and used to minimise the tracking of mud and soil material onto local roads

There is no mud on the roads outside of the project boundary

Sediment fencing or equivalent is provided downslope of disturbed areas that can’t be directed into a designated sediment basin

Sediment Basins and Traps

The volume markers intact and clearly visible

The inlets and outlets are stable

Accumulated sediment is below 30% of the sediment storage zone

The basins been emptied since the last rain event and restored to their design capacity (if not, explanation must be provided)

Page 55: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or printed from the Intranet. Copyright © 2009, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13 Page 55 of 60

All discharges are undertaken in accordance with Dewatering Permits

Air Quality

No visible dust leaving the site’s boundary

Dust suppression, i.e. water cart, is being used to minimise dust emissions

Clearing

Clearing limits and work boundaries are established and well defined

Clearing and Grubbing Permits have been issued for all current clearing works

Page 56: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or printed from the Intranet. Copyright © 2009, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13 Page 56 of 60

Attachment G. Consultation Register

Stakeholder Contact address Contact email Documents Sent Initial Phone

Call

Second Phone

CallThird Phone Call Package Sent

Confirmation of

Package ReceivedFeedback Comment on Feedback

Consultation

Complete

Ingrid Ilias [email protected] CEMP

Department of Planning & Infrastructure 9228 6411 Acid Sulfate Soils Management Sub-Plan

Major Projects Assessments Construction Noise Management Sub-Plan

GPO Box 39 Dust & Air Quality Management Sub-Plan

Sydney Soil and Water Management Sub-Plan

NSW 2001 Waste & Spoil Management Sub-Plan

Emergency Response and Incident

Management Plan

Traffic Management Plan

Construction Safety Study

CEMP

Acid Sulfate Soils Management Sub-Plan

Construction Noise Management Sub-Plan

Dust & Air Quality Management Sub-Plan 12/06/2013 19/06/2013 Spoke to Jennifer Sage and

had refered onto appropriate

department. Will get

department head to call me

27/6/13 or 28/6/13

6/06/2013 (by post) Yes Thank you for forwarding the environmental management plans in

regards with the above mentioned project for our records. The

Environmental Protection Authority (EPA) encourages the development

of such plans to ensure that proponents have determined how they will

meet their statutory obligations and designated environmental

objectives. However, we do not approve or endorse these documents

as our role is to set environmental objectives for environmental

management, not to be directly involved in the development of strategies

to achieve those objectives.

No comment on documentation provided Yes

Soil and Water Management Sub-Plan Left Message Left Message

Waste & Spoil Management Sub-Plan Returned message

extended response

date to 27/6/13

Emergency Response and Incident

Management Plan

CEMP

12/06/2013 N/A N/A 6/06/2013 (by post)

12/06/2013 (by email)

N/A N/A N/A N/A N/AN/A N/A N/A

[email protected]

9995-5000

YesNo objection to documentation providedFisheries NSW has no objections to the mitigation measures proposed in the

attached plans.Soil and Water Management Sub-Plan

PORT BOTANY RAMP D

CONSULTATION REGISTER

DP&I

EPA

DPI Fisheries

Sarah Deards / Jennifer Sage

Regional Operations Officer

NSW Environment Protection Authority

Level 14 59-61 Goulburn Street

Sydney

NSW 2000

Carla Ganassin

NSW Department of Primary Industries

PO Box 21

CRONULLA

NSW 2230

[email protected]

9527 8552 4254-5527

Page 57: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or printed from the Intranet. Copyright © 2009, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13 Page 57 of 60

Stakeholder Contact address Contact email Documents Sent Initial Phone

Call

Second Phone

CallThird Phone Call Package Sent

Confirmation of

Package ReceivedFeedback Comment on Feedback

Consultation

Complete

Dust & Air Quality Management Sub-Plan

Soil and Water Management Sub-Plan

Traffic Management Plan 12/06/2013 19/06/2013

Left Message

N/A 6/06/2013 (by post) Yes I have reviewed the traffic management plan you have submitted.

Please note that I can only comment on the Traffic Management Plan,

not the Dust and Air Quality Management sub plan and the Soil and

Water management sub plan. 

Yes

I have been involved in the Port Botany expansion works since it has

started so I am aware of all the current works and planned works ahead.

Please note that all regulatory signage proposed on the local road

network, even within the ports itself, approval from Botany Council must

be obtained. The Transport Management Centre will be issuing any

Road Occupancy Licenses.

RMS main concern is the operation of Foreshore Rd and Botany Rd

and in particular the traffic signals at Botany/Foreshore Rd. RMS

will monitor the usage of the right turn bay on Foreshore Rd

into Penrhyn Rd. The existing right turn bay is approx. 135m, if traffic

queues out of the right turn bay onto Foreshore Rd and effect the

through movement, the number of truck movements will be revisited.

Acknowledged

CEMP We  do not require any additional information or amendments

Construction Noise Management Sub-Plan Satisfied that all key criteria for these plans have been incorporated into

the document and at this stage has no issues with the development

Dust & Air Quality Management Sub-Plan Satisfied that all key criteria for these plans have been incorporated into

the document and at this stage has no issues with the development

Soil and Water Management Sub-Plan 12/06/2013 19/06/2013 N/A 6/06/2013 (by post) Yes We  do not require any additional information or amendments Yes

Waste & Spoil Management Sub-Plan Spoke to Stephen P

and extended

response date to

28/6/13

We  do not require any additional information or amendments

Emergency Response and Incident

Management Plan

Traffic Management Plan Any regulatory signposting (e.g. ‘No Stopping’, ‘No Parking’, ‘Works

Zone’) during the

construction period will need to be approved by the City of Botany Bay’s

(CoBB) Local Traffic Committee as CoBB is the Road Authority of

Penrhyn Road.

None proposed

Any lane occupancy on Penrhyn Road due to construction activities will

need to be

approved by CoBB.

Agreed. ROL will be required to do demolition work

where the new bridge connects to the existing

roundabout. This is now included in the TCP under

clause 6.7.

Construction truck layover in Botany Road or any residential streets

within the LGA

will not be allowed.

Acknowledged

Any construction staff parking in any residential streets within the LGA

will not be

allowed.

None proposed

CoBB will need to be informed should there is any change in the

approved CTMP

(e.g. projected truck routes, number and types of delivery vehicles etc.)

Agreed.

Stephen Poulton

City of Botany Bay Council

PO Box 331

141 Coward Street

MASCOT

NSW 2020

[email protected]

u

9366-3666

Botany

Council

RMS Nicolas Kocoski

NSW Transport Roads and Maritime

Services

Locked Bag 5100

Camperdown 1450

[email protected]

8849-2328

Page 58: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or printed from the Intranet. Copyright © 2009, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13 Page 58 of 60

Stakeholder Contact address Contact email Documents Sent Initial Phone

Call

Second Phone

CallThird Phone Call Package Sent

Confirmation of

Package ReceivedFeedback Comment on Feedback

Consultation

Complete

Construction Noise Management Sub-Plan Council supports transparency of noise monitoring data. To

demonstrate a  which

commitment to transparency Council recommend that these monthly

noise monitoring reports be made accessible to the community via a

project website. Noise monitoring data  that has been provided by

SICTL during their construction works via their website have been well

received by the community.

Noise and dust monitoring data will be accessible to

the community via a project website.

Council receives noise nuisance complaints from the Port related

operations

particularly in streets located on elevated topographies. Subsequently

Council supports Patrick's commitment to notifying the community 1

week in advance of noisy activities as specified in the construction noise

sub plan. As Council understands that the designated community

extends to Randwick LGA, Council recommends that these community

notifications could be most effectively achieved via notifications in the

local community newspaper  i.e. the southern courier which would

remove the need for extensive letterboxing/mail outs.

Notifications will be done via local community

newspaper as well as by letterbox drops.

Dust & Air Quality Management Sub-Plan Council recommends monitoring measures take into consideration of

cumulative

impacts of Dust from multiple construction activities occurring at the

terminal at the same time especially during periods of high winds.

Cumulative impacts have been addressed in sect

4.3.3 of the CEMP.

Details on proposed dust suppression measures appears to be limited

and the

sub plan provides little details of on site equipment and operational

procedures with regard to these activities. Council suggests that  this

plan demonstrate how dust suppression activities will be carried out and

to confirm the required equipment for this will be on site and operational

as and when required  throughout the project's duration.

Noted. Details of dust suppresion mitigation

measures and the equipment to be used are detailed

in Sections 5 and 7 of the AQDMP.

As per noise monitoring and reporting Council recommends that dust

monitoring

reports be made accessible to the community via a project website.

As above

Soil and Water Management Sub-Plan 12/06/2013 19/06/2013 N/A 6/06/2013 (by post) Yes This plan states the use of groundwater for dust suppression activities

whereas the dust management sub plan states the use of rainwater tank

or sea water for dust suppression. Due to potential inhalation risk from

possible volatiles in the groundwater Council suggests that  the dust

plan recommendations be utilised to minimise this exposure risk.

Agreed. SWMP has been revised accordingly. Yes

Traffic Management Plan Left Message ·         Council suggest consideration cumulative traffic impact in this TMP

in conjunction with other

construction activities occurring at terminal 3 and in the vicinity of the

Port.

Covered under clause 5.4 of the TMP.

·         A project requirement should be that no construction vehicle

stacking, loading

or unloading shall occur on, or in a manner that adversely affects the

flow of traffic along Foreshore Road and Council is pleased to see that

a designated on site truck waiting facility is being provided.

TMP includes a truck parking bay (Figure 4) to

mitigate construction traffic impact on operations.

·         Council also recommends that onsite signage and other

communications

mechanisms be utilised to notify visitors/uers of alternative access

arrangements to roads, cycle ways and footpaths  during works.

Acknowledged. Traffic control plans will

further detail necessary signage.

[email protected]

u

9399-0999

Bronwyn Englaro

Randwick City Council

30 Frances Street

RANDWICK

NSW 2031

Randwick

Council

Page 59: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or printed from the Intranet. Copyright © 2009, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13 Page 59 of 60

Stakeholder Contact address Contact email Documents Sent Initial Phone

Call

Second Phone

CallThird Phone Call Package Sent

Confirmation of

Package ReceivedFeedback Comment on Feedback

Consultation

Complete

CEMP

Acid Sulfate Soils Management Sub-Plan

Construction Noise Management Sub-Plan

Dust & Air Quality Management Sub-Plan

Soil and Water Management Sub-Plan

Waste & Spoil Management Sub-Plan

Emergency Response and Incident

Management Plan

Traffic Management Plan

Construction Safety Study

Traffic Management Plan 41437 N/A N/A 6/06/2013 (by post) Yes Confirmed over the phone that no feedback on document provided - Yes

12/06/2013

Sydney Ports

Corporation

P. Engelen, S. Hobday, P. Jerogin CEMP N/A N/A TMP Section 6.3 Existing pedestrian access (towards Patrick terminal and SPOC

building) via elevated roundabout is impacted by Ramp D works and

Ramp D construction traffic. Patrick propose to separate pedestrian 2m

wide path with concrete barriers. Please provide detail of this proposal:

is there enough space for 2m wide path plus barriers? Also will barriers

be structurally connected to protect against impact from trucks? Please

address in TMP.

TMP has been modified to show the vehicle

movements and cross section demonstrating that the

proposed 2m wide pedestrian access is feasible and

does not impact port operations. (clause 6.3)

Structural connection is under consideration however

connection to the existing bridge structure may affect

the integrity of the waterproofing in place and also

provide an avenue for water ingress. There is

potential for the durability to be compromised.

Acid Sulfate Soils Management Sub-Plan TMP Section 5.4.2 Access via the Caltex site and across the SICTL rail area is not

permitted, unless specific approval is obtained from both Caltex and

SICTL (as well as NSW Ports). This is highly unlikely in view of the

SICTL rail construction and rail operations in respectively 2013 and

2014.

Item removed from plan

Construction Noise Management Sub-Plan TMP Section 5.4 Please address the exiting construction traffic from 'southern' site. Will

this exit via the Cargolink facility? Review turning circles.

Revised plan included in new draft under Figure 4

showing construction traffic entering the site with the

site boundary fence moved to eliminate impact on

opertational traffic. Vehicles will be abble to turn right

off the roundabout if front of gate B110 and enter the

site which will be seperate from the Land Restricted

Zone.

-No Comments receivedN/A6/06/2013 (by post)N/AN/A

Package was

returned not known

at address.

Confirmed with

Patricks (Emmanuel

Diacos) that ther is

no need to resend

as Susan Rudland

has a copy of all

plans.

[email protected]

9330 6455

Helen Sloane

Southern Sydney Region of Councils

PO Box 536

HURSTVILLE

NSW 1481

12/06/2013Roberta Ryan / Susan Rudland

Urbis JHD Pty Ltd

Level 21, 321 Kent Street

SYDNEY

NSW 2000

[email protected]

Also contact Shane Hobday:

[email protected]

8233-9900

CCC, via

CCC chair

SSROC

Page 60: Document88

Construction Environmental Management Plan

Construction Environmental Management Plan | Ramp D Works |

Content ID: 7ZA-CEMP Revision: 0

This is an uncontrolled copy if photocopied or printed from the Intranet. Copyright © 2009, Fulton Hogan Ltd. All rights reserved.

Revised: 03/07/13 Page 60 of 60

Stakeholder Contact address Contact email Documents Sent Initial Phone

Call

Second Phone

CallThird Phone Call Package Sent

Confirmation of

Package ReceivedFeedback Comment on Feedback

Consultation

Complete

Dust & Air Quality Management Sub-Plan TMP Section 5.4 From the diagram it is understood that entering traffic to southern site

will enter via Cargolink. Please clarify by elaborating in text of TMP. How

will this impact queuing on Ramp B and ensure functioning of the

roundabout at bottom of Ramp B? Address and ensure that all Patrick

bound traffic on Ramp B is using the left lane.

See revised plan under Figure 4.

Soil and Water Management Sub-Plan TMP Section 5.4 Access to main 'northern' site is via Ramp C (please correct text in 5.4

that states 'Ramp B').

Correction made

Waste & Spoil Management Sub-Plan TMP Section 5.4 Review signage based on above required changes. Signage ammended accordingly

Emergency Response and Incident

Management Plan

TMP Section 5.4 Address pedestrian access to the construction site. There will be no pedestrian access to the

construction site. All personnel will arrive by vehicle

Traffic Management Plan TMP Section 5 With this proposal and the concurrent construction of the Knuckle and

Ramp D, Patrick will introduce significant construction traffic

movements on the roundabout at the bottom of Ramp C. The

roundabout was not initially designed to cater for the additional entry /

exit lanes. NSW Ports requires Patrick to confirm that Patrick has full

responsibility of the traffic on and the operation of that roundabout. NSW

Ports requires that Patrick confirm the safety of the roundabout by

means of a road safety audit.

Includeded that FH will undertake a road safety audit

once initial traffic control has been implemented to

enable the works. (clause 8.1)

Construction Safety Study Incident and

Emergency

Response Plan

Reference should be made to the Port Botany Emergency Alarm Radio

(PBEAR) which s located at the Patrick Gatehouse and is the primary

means for notifying other facilities in the Port that there is an incident on

the Patrick site. A PBEAR unit is also located and monitored at the

Mascot Police Station. The system is routinely tested every Thursday

morning.

Includeded in plan

CEMP - Section 1 Please include a section acknowledging and addressing the issue of

multiple construction contractors undertaking construction works on the

PBE at the same time and need for coordination and management of

common environmental issues (i.e. noise, dust, complaints, water,

traffic etc)

Addressed in Sect 4.3.3 of the CEMP

CEMP - General Please include table of all comments reviewed from stakeholders

identifying all comments, how they have been addressed and where

they have been addressed in the management plans.

A number of stakeholder have asked for extention of

deadline for submission of comments till next week.

The comments will be collated and included in the

CEMP by 28/06/13.

CEMP - General All references to SPC / Sydney Ports Corporation to be changed to NSW

Ports

Changed.