a case study-delhi metro phase iii - balanced cantilever bridge

Upload: khaled-el-banna

Post on 05-Jul-2018

234 views

Category:

Documents


1 download

TRANSCRIPT

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    1/54

    A Case Study on Balanced CantileverBridges – Delhi Metro Phase III

    Piyush Santhalia – Project Engineer

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    2/54

    Case StudiesSl.No

    SpanArrangement (m)

    Project Client Contractor Status

    1 34 + 60 + 34 CC28Delhi Metro –Phase III, Line 7

    DelhiMetro

    L&T Completed

    2 60 + 60 CC28Delhi Metro –Phase III, Line 7

    L&T Super-structurepartlycompleted

    3 37 + 69 + 67 + 55

    + 34

    CC26R

    Delhi Metro –

    Phase III, Line 7

    ITD Foundation

    and Sub-structurecompleted

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    3/54

    CC28 – Balanced Cantilever Bridge

    i) 34 + 60 + 34 m ii) 60 + 60 m

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    4/54

    CC28 – Balanced Cantilever BridgeI. 34 + 60 + 34 m

    II. 60 + 60 m

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    5/54

    CC28 – Balanced Cantilever BridgeI. 34m + 60m + 34mStructure Type : Cast-in-Situ PSC Box Girder

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    6/54

    CC28 – Balanced Cantilever BridgeI. 34 + 60 + 34m Span - General Arrangement

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    7/54

    CC28 – Balanced Cantilever BridgeI. 34 + 60 + 34 Cross Sections

    Overall Width of Deck = 8.844 m

    Depth of the Box Girder: Varies from 5m at intermediate Piers to 2.1m at Mid-Span

    Area (m 2) 8.890

    Iyy (m 4) 28.79

    Area (m 2) 4.980

    Iyy (m 4) 2.63

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    8/54

    CC28 – Balanced Cantilever BridgeI. 34 + 60 + 34 Foundation & Sub - structure

    Intermediate Piers P122 and P123 are integral Piers.

    Twin Piers, each leaf of dimension 1000 X 3400 mm

    Free Bearings at P121 and P124.

    Circular Piers with 2100 mm diameter

    Pile Foundation

    1000 mm dia. , cast-in-situ bored piles.

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    9/54

    CC28 – Balanced Cantilever BridgeI. 34 + 60 + 34 Construction Sequence

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    10/54

    CC28 – Balanced Cantilever BridgeI. 34 + 60 + 34 Construction Sequence contd…

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    11/54

    CC28 – Balanced Cantilever BridgeI. 34 + 60 + 34 Construction Sequence contd…

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    12/54

    CC28 – Balanced Cantilever BridgeI. 34 + 60 + 34 Construction Sequence contd…

    Casting of Segment S8 (one just before stitch segment)

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    13/54

    CC28 – Balanced Cantilever BridgeI. 34 + 60 + 34 Construction Sequence contd…

    Casting of Stitch Segment

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    14/54

    CC28 – Balanced Cantilever BridgeI. 34 + 60 + 34 Analysis & Design

    - Midas Civil has been used for numerical modelling and Structural Analysis

    - Super Structure (Box Girder) Piers and Piles have been modelled as Line Element

    - Pile Cap has been modelled as plate element.

    - Point Spring Supports to take the effect of soil.

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    15/54

    CC28 – Balanced Cantilever BridgeI. 34 + 60 + 34 Analysis & Design

    - Concrete has been modelled with time dependent properties in Midas Civil

    - Creep and Shrinkage and compressive strength gain behaviour has been defined as

    per CEB-FIP

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    16/54

    CC28 – Balanced Cantilever BridgeI. 34 + 60 + 34 Analysis & Design

    - Internal Prestressing

    - 19T15 and 12T15 anchorages

    http://localhost/var/www/apps/conversion/tmp/scratch_3/AECOM-CC-28-NN-13001-PRESTRESSING_R3%20(Sh%201%20to%208).pdfhttp://localhost/var/www/apps/conversion/tmp/scratch_3/AECOM-CC-28-NN-13001-PRESTRESSING_R3%20(Sh%201%20to%208).pdf

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    17/54

    CC28 – Balanced Cantilever BridgeI. 34 + 60 + 34 Analysis & Design

    - Simulation of exact Construction Sequence in Midas.

    - Able to check stresses at intermediate steps in all construction stages.

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    18/54

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    19/54

    CC28 – Balanced Cantilever BridgeI. 34 + 60 + 34 Analysis & Design

    - Maximum Stress (Tension) at top Fibre Envelope (during construction)

    - Maximum Compression at Top Fibre Envelope (during construction)

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    20/54

    CC28 – Balanced Cantilever BridgeI. 34 + 60 + 34 Analysis & Design

    - Maximum Tension at Bottom Fibre Envelope (during construction)

    - Effect of stressing Tendons one by one

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    21/54

    CC28 – Balanced Cantilever BridgeI. 34 + 60 + 34 Analysis & Design

    - Results: Stress Check for Service Loads: Normal Case

    Stresses at Top Fibre due to Combination G I (N/mm 2)

    Stresses at Bottom Fibre due to Combination G I (N/mm2)

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    22/54

    CC28 – Balanced Cantilever BridgeI. 34 + 60 + 34 Analysis & Design

    - Pre-camber: Day of commissioning as the critical day

    - Precision: Only 6mm of difference between the theoretical value and theobserved value of deflection at the cantilever tips, just before stitching.

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    23/54

    CC28 – Balanced Cantilever BridgeI. 34 + 60 + 34 Analysis & Design

    - Deformation, including the effect of creep after 120 years

    Deformation due to Normal Case – after 120 years (mm)

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    24/54

    CC28 – Balanced Cantilever BridgeII. 60m + 60m

    Structure Type : Cast-in-Situ PSC Box Girder

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    25/54

    CC28 – Balanced Cantilever BridgeII. 60 + 60m Span - General Arrangement

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    26/54

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    27/54

    CC28 – Balanced Cantilever BridgeII. 60 + 60m Foundation & Sub - structure

    Intermediate Piers P217 is integral Piers.

    2300mm Diameter circular Pier

    Free Bearings at P216 & P218.

    Circular Piers with 2100 mm diameter

    Pile Foundation

    1000 mm dia. , cast-in-situ bored piles.

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    28/54

    CC28 – Balanced Cantilever BridgeII. 60 + 60m Analysis & Design

    - Midas Civil has been used for numerical modelling and Structural Analysis

    - Super Structure (Box Girder) Piers and Piles have been modelled as Line Element

    - Pile Cap has been modelled as plate element.

    - Point Spring Supports to take the effect of soil.

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    29/54

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    30/54

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    31/54

    CC28 – Balanced Cantilever BridgeII. 60 + 60m Construction Sequence contd…

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    32/54

    CC28 – Balanced Cantilever BridgeII. 60 + 60m Construction Sequence contd…

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    33/54

    CC28 – Balanced Cantilever BridgeII. 60 + 60m Analysis & Design

    - Internal Prestressing

    - 19T15 and 12T15 anchorages

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    34/54

    CC28 – Balanced Cantilever BridgeII. 60 + 60m Analysis & Design

    - Maximum Stress (Tension) at Top Fibre Envelope (during construction)

    - Maximum Compression at Top Fibre Envelope (during construction)

    Sign Convention: +ve Value of Stresses denote Tension-ve Values denote compression

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    35/54

    CC28 – Balanced Cantilever BridgeII. 60 + 60m Analysis & Design

    - Maximum Tension at Bottom Fibre Envelope (during construction)

    - Maximum Compression at Bottom Fibre Envelope (during construction)

    Sign Convention: +ve Value of Stresses denote Tension-ve Values denote compression

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    36/54

    CC28 – Balanced Cantilever BridgeII. 60 + 60m Analysis & Design

    - Results: Stress Check for Service Loads: Normal Case

    Stresses at Top Fibre due to Combination G I (N/mm2)

    Stresses at Bottom Fibre due to Combination G I (N/mm2 )

    Sign Convention: +ve Value of Stresses denote Tension-ve Values denote compression

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    37/54

    CC28 – Balanced Cantilever BridgeII. 60 + 60m Analysis & Design

    - Pre-camber: Day of commissioning as the critical day

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    38/54

    CC28 – Balanced Cantilever BridgeII. 60 + 60m Analysis & Design

    - Deformation, including the effect of creep after 120 years

    Deformation due to Normal Case – after 120 years (mm)

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    39/54

    CC26R – Balanced Cantilever BridgeI. 37 + 69.9 + 67 + 55 + 34m Span - General Arrangement

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    40/54

    CC26R – Balanced Cantilever BridgeI. 37 + 69.9 + 67 + 55 + 34m Cross SectionsOverall Width of Deck = 8.844 m

    Depth of the Box Girder: Varies from 4.7m at intermediate Piers to 2.8m at Mid-Span

    Area (m 2) 10.01

    Iyy (m 4) 28.73

    Area (m 2) 5.90

    Iyy (m 4) 6.13

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    41/54

    CC26R – Balanced Cantilever BridgeI. 37 + 69.9 + 67 + 55 + 34m Construction Sequence

    Intermediate PiersP235: Free Pier

    P236: Integral PierP237: Integral PierP238: Free Pier

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    42/54

    CC26R – Balanced Cantilever Bridge

    I. 37 + 69.9 + 67 + 55 + 34m Construction Sequence contd…

    Stresses at Top Fibre due to DL + PS + CR + SH (N/mm2)

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    43/54

    CC26R – Balanced Cantilever Bridge

    I. 37 + 69.9 + 67 + 55 + 34m Construction Sequence contd…

    Stresses at Top Fibre due to DL + PS + CR + SH (N/mm2)

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    44/54

    CC26R – Balanced Cantilever Bridge

    I. 37 + 69.9 + 67 + 55 + 34m Construction Sequence contd…

    Stresses at Top Fibre due to DL + PS + CR + SH (N/mm2)

    Stresses at Bottom Fibre due to DL + PS + CR + SH (N/mm2)

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    45/54

    CC26R – Balanced Cantilever Bridge

    I. 37 + 69.9 + 67 + 55 + 34m Construction Sequence contd…

    Stresses at Top Fibre due to DL + PS + CR + SH (N/mm2)

    Stresses at Bottom Fibre due to DL + PS + CR + SH (N/mm2)

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    46/54

    CC26R – Balanced Cantilever Bridge

    I. 37 + 69.9 + 67 + 55 + 34m Construction Sequence contd…

    Stresses at Top Fibre due to DL + PS + CR + SH (N/mm2)

    Stresses at Bottom Fibre due to DL + PS + CR + SH (N/mm2)

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    47/54

    CC26R – Balanced Cantilever Bridge

    I. 37 + 69.9 + 67 + 55 + 34m Construction Sequence contd…

    Stresses at Top Fibre due to DL + PS + CR + SH (N/mm2)

    Stresses at Bottom Fibre due to DL + PS + CR + SH (N/mm2)

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    48/54

    CC26R – Balanced Cantilever Bridge

    I. 37 + 69.9 + 67 + 55 + 34m Construction Sequence contd…

    Stresses at Top Fibre due to DL + PS + CR + SH (N/mm2)

    Stresses at Bottom Fibre due to DL + PS + CR + SH (N/mm2)

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    49/54

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    50/54

    CC26R – Balanced Cantilever Bridge

    I. 37 + 69.9 + 67 + 55 + 34m Foundation & Sub - structurePile Arrangement at P236

    Intermediate PiersP235: Free PierP236: Integral Pier

    P237: Integral PierP238: Free Pier

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    51/54

    CC26R – Balanced Cantilever Bridge

    I. 37 + 69.9 + 67 + 55 + 34m Foundation & Sub - structurePile Arrangement at P237

    Intermediate PiersP235: Free PierP236: Integral Pier

    P237: Integral PierP238: Free Pier

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    52/54

    CC26R – Balanced Cantilever Bridge

    I. 37 + 69.9 + 67 + 55 + 34m Analysis & Design

    - Internal Prestressing

    - 19T15 and 12T15 anchorages

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    53/54

    CC26R – Balanced Cantilever Bridge

    I. 37 + 69.9 + 67 + 55 + 34m Analysis & DesignStress Check for Service Loads: Normal Case

    Sign Convention: +ve Value of Stresses denote Tension-ve Values denote compression

    Stresses at Top Fibre due to Combination G I (N/mm 2)

    Stresses at Bottom Fibre due to Combination G I (N/mm 2)

  • 8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge

    54/54

    Thank You