A Case Study on Balanced CantileverBridges – Delhi Metro Phase III
Piyush Santhalia – Project Engineer
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
2/54
Case StudiesSl.No
SpanArrangement (m)
Project Client Contractor Status
1 34 + 60 + 34 CC28Delhi Metro –Phase III, Line 7
DelhiMetro
L&T Completed
2 60 + 60 CC28Delhi Metro –Phase III, Line 7
L&T Super-structurepartlycompleted
3 37 + 69 + 67 + 55
+ 34
CC26R
Delhi Metro –
Phase III, Line 7
ITD Foundation
and Sub-structurecompleted
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
3/54
CC28 – Balanced Cantilever Bridge
i) 34 + 60 + 34 m ii) 60 + 60 m
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
4/54
CC28 – Balanced Cantilever BridgeI. 34 + 60 + 34 m
II. 60 + 60 m
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
5/54
CC28 – Balanced Cantilever BridgeI. 34m + 60m + 34mStructure Type : Cast-in-Situ PSC Box Girder
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
6/54
CC28 – Balanced Cantilever BridgeI. 34 + 60 + 34m Span - General Arrangement
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
7/54
CC28 – Balanced Cantilever BridgeI. 34 + 60 + 34 Cross Sections
Overall Width of Deck = 8.844 m
Depth of the Box Girder: Varies from 5m at intermediate Piers to 2.1m at Mid-Span
Area (m 2) 8.890
Iyy (m 4) 28.79
Area (m 2) 4.980
Iyy (m 4) 2.63
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
8/54
CC28 – Balanced Cantilever BridgeI. 34 + 60 + 34 Foundation & Sub - structure
Intermediate Piers P122 and P123 are integral Piers.
Twin Piers, each leaf of dimension 1000 X 3400 mm
Free Bearings at P121 and P124.
Circular Piers with 2100 mm diameter
Pile Foundation
1000 mm dia. , cast-in-situ bored piles.
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
9/54
CC28 – Balanced Cantilever BridgeI. 34 + 60 + 34 Construction Sequence
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
10/54
CC28 – Balanced Cantilever BridgeI. 34 + 60 + 34 Construction Sequence contd…
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
11/54
CC28 – Balanced Cantilever BridgeI. 34 + 60 + 34 Construction Sequence contd…
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
12/54
CC28 – Balanced Cantilever BridgeI. 34 + 60 + 34 Construction Sequence contd…
Casting of Segment S8 (one just before stitch segment)
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
13/54
CC28 – Balanced Cantilever BridgeI. 34 + 60 + 34 Construction Sequence contd…
Casting of Stitch Segment
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
14/54
CC28 – Balanced Cantilever BridgeI. 34 + 60 + 34 Analysis & Design
- Midas Civil has been used for numerical modelling and Structural Analysis
- Super Structure (Box Girder) Piers and Piles have been modelled as Line Element
- Pile Cap has been modelled as plate element.
- Point Spring Supports to take the effect of soil.
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
15/54
CC28 – Balanced Cantilever BridgeI. 34 + 60 + 34 Analysis & Design
- Concrete has been modelled with time dependent properties in Midas Civil
- Creep and Shrinkage and compressive strength gain behaviour has been defined as
per CEB-FIP
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
16/54
CC28 – Balanced Cantilever BridgeI. 34 + 60 + 34 Analysis & Design
- Internal Prestressing
- 19T15 and 12T15 anchorages
http://localhost/var/www/apps/conversion/tmp/scratch_3/AECOM-CC-28-NN-13001-PRESTRESSING_R3%20(Sh%201%20to%208).pdfhttp://localhost/var/www/apps/conversion/tmp/scratch_3/AECOM-CC-28-NN-13001-PRESTRESSING_R3%20(Sh%201%20to%208).pdf
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
17/54
CC28 – Balanced Cantilever BridgeI. 34 + 60 + 34 Analysis & Design
- Simulation of exact Construction Sequence in Midas.
- Able to check stresses at intermediate steps in all construction stages.
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
18/54
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
19/54
CC28 – Balanced Cantilever BridgeI. 34 + 60 + 34 Analysis & Design
- Maximum Stress (Tension) at top Fibre Envelope (during construction)
- Maximum Compression at Top Fibre Envelope (during construction)
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
20/54
CC28 – Balanced Cantilever BridgeI. 34 + 60 + 34 Analysis & Design
- Maximum Tension at Bottom Fibre Envelope (during construction)
- Effect of stressing Tendons one by one
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
21/54
CC28 – Balanced Cantilever BridgeI. 34 + 60 + 34 Analysis & Design
- Results: Stress Check for Service Loads: Normal Case
Stresses at Top Fibre due to Combination G I (N/mm 2)
Stresses at Bottom Fibre due to Combination G I (N/mm2)
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
22/54
CC28 – Balanced Cantilever BridgeI. 34 + 60 + 34 Analysis & Design
- Pre-camber: Day of commissioning as the critical day
- Precision: Only 6mm of difference between the theoretical value and theobserved value of deflection at the cantilever tips, just before stitching.
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
23/54
CC28 – Balanced Cantilever BridgeI. 34 + 60 + 34 Analysis & Design
- Deformation, including the effect of creep after 120 years
Deformation due to Normal Case – after 120 years (mm)
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
24/54
CC28 – Balanced Cantilever BridgeII. 60m + 60m
Structure Type : Cast-in-Situ PSC Box Girder
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
25/54
CC28 – Balanced Cantilever BridgeII. 60 + 60m Span - General Arrangement
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
26/54
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
27/54
CC28 – Balanced Cantilever BridgeII. 60 + 60m Foundation & Sub - structure
Intermediate Piers P217 is integral Piers.
2300mm Diameter circular Pier
Free Bearings at P216 & P218.
Circular Piers with 2100 mm diameter
Pile Foundation
1000 mm dia. , cast-in-situ bored piles.
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
28/54
CC28 – Balanced Cantilever BridgeII. 60 + 60m Analysis & Design
- Midas Civil has been used for numerical modelling and Structural Analysis
- Super Structure (Box Girder) Piers and Piles have been modelled as Line Element
- Pile Cap has been modelled as plate element.
- Point Spring Supports to take the effect of soil.
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
29/54
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
30/54
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
31/54
CC28 – Balanced Cantilever BridgeII. 60 + 60m Construction Sequence contd…
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
32/54
CC28 – Balanced Cantilever BridgeII. 60 + 60m Construction Sequence contd…
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
33/54
CC28 – Balanced Cantilever BridgeII. 60 + 60m Analysis & Design
- Internal Prestressing
- 19T15 and 12T15 anchorages
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
34/54
CC28 – Balanced Cantilever BridgeII. 60 + 60m Analysis & Design
- Maximum Stress (Tension) at Top Fibre Envelope (during construction)
- Maximum Compression at Top Fibre Envelope (during construction)
Sign Convention: +ve Value of Stresses denote Tension-ve Values denote compression
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
35/54
CC28 – Balanced Cantilever BridgeII. 60 + 60m Analysis & Design
- Maximum Tension at Bottom Fibre Envelope (during construction)
- Maximum Compression at Bottom Fibre Envelope (during construction)
Sign Convention: +ve Value of Stresses denote Tension-ve Values denote compression
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
36/54
CC28 – Balanced Cantilever BridgeII. 60 + 60m Analysis & Design
- Results: Stress Check for Service Loads: Normal Case
Stresses at Top Fibre due to Combination G I (N/mm2)
Stresses at Bottom Fibre due to Combination G I (N/mm2 )
Sign Convention: +ve Value of Stresses denote Tension-ve Values denote compression
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
37/54
CC28 – Balanced Cantilever BridgeII. 60 + 60m Analysis & Design
- Pre-camber: Day of commissioning as the critical day
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
38/54
CC28 – Balanced Cantilever BridgeII. 60 + 60m Analysis & Design
- Deformation, including the effect of creep after 120 years
Deformation due to Normal Case – after 120 years (mm)
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
39/54
CC26R – Balanced Cantilever BridgeI. 37 + 69.9 + 67 + 55 + 34m Span - General Arrangement
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
40/54
CC26R – Balanced Cantilever BridgeI. 37 + 69.9 + 67 + 55 + 34m Cross SectionsOverall Width of Deck = 8.844 m
Depth of the Box Girder: Varies from 4.7m at intermediate Piers to 2.8m at Mid-Span
Area (m 2) 10.01
Iyy (m 4) 28.73
Area (m 2) 5.90
Iyy (m 4) 6.13
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
41/54
CC26R – Balanced Cantilever BridgeI. 37 + 69.9 + 67 + 55 + 34m Construction Sequence
Intermediate PiersP235: Free Pier
P236: Integral PierP237: Integral PierP238: Free Pier
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
42/54
CC26R – Balanced Cantilever Bridge
I. 37 + 69.9 + 67 + 55 + 34m Construction Sequence contd…
Stresses at Top Fibre due to DL + PS + CR + SH (N/mm2)
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
43/54
CC26R – Balanced Cantilever Bridge
I. 37 + 69.9 + 67 + 55 + 34m Construction Sequence contd…
Stresses at Top Fibre due to DL + PS + CR + SH (N/mm2)
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
44/54
CC26R – Balanced Cantilever Bridge
I. 37 + 69.9 + 67 + 55 + 34m Construction Sequence contd…
Stresses at Top Fibre due to DL + PS + CR + SH (N/mm2)
Stresses at Bottom Fibre due to DL + PS + CR + SH (N/mm2)
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
45/54
CC26R – Balanced Cantilever Bridge
I. 37 + 69.9 + 67 + 55 + 34m Construction Sequence contd…
Stresses at Top Fibre due to DL + PS + CR + SH (N/mm2)
Stresses at Bottom Fibre due to DL + PS + CR + SH (N/mm2)
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
46/54
CC26R – Balanced Cantilever Bridge
I. 37 + 69.9 + 67 + 55 + 34m Construction Sequence contd…
Stresses at Top Fibre due to DL + PS + CR + SH (N/mm2)
Stresses at Bottom Fibre due to DL + PS + CR + SH (N/mm2)
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
47/54
CC26R – Balanced Cantilever Bridge
I. 37 + 69.9 + 67 + 55 + 34m Construction Sequence contd…
Stresses at Top Fibre due to DL + PS + CR + SH (N/mm2)
Stresses at Bottom Fibre due to DL + PS + CR + SH (N/mm2)
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
48/54
CC26R – Balanced Cantilever Bridge
I. 37 + 69.9 + 67 + 55 + 34m Construction Sequence contd…
Stresses at Top Fibre due to DL + PS + CR + SH (N/mm2)
Stresses at Bottom Fibre due to DL + PS + CR + SH (N/mm2)
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
49/54
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
50/54
CC26R – Balanced Cantilever Bridge
I. 37 + 69.9 + 67 + 55 + 34m Foundation & Sub - structurePile Arrangement at P236
Intermediate PiersP235: Free PierP236: Integral Pier
P237: Integral PierP238: Free Pier
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
51/54
CC26R – Balanced Cantilever Bridge
I. 37 + 69.9 + 67 + 55 + 34m Foundation & Sub - structurePile Arrangement at P237
Intermediate PiersP235: Free PierP236: Integral Pier
P237: Integral PierP238: Free Pier
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
52/54
CC26R – Balanced Cantilever Bridge
I. 37 + 69.9 + 67 + 55 + 34m Analysis & Design
- Internal Prestressing
- 19T15 and 12T15 anchorages
-
8/15/2019 A Case Study-Delhi Metro Phase III - Balanced Cantilever Bridge
53/54
CC26R – Balanced Cantilever Bridge
I. 37 + 69.9 + 67 + 55 + 34m Analysis & DesignStress Check for Service Loads: Normal Case
Sign Convention: +ve Value of Stresses denote Tension-ve Values denote compression
Stresses at Top Fibre due to Combination G I (N/mm 2)
Stresses at Bottom Fibre due to Combination G I (N/mm 2)
-