Background
• Windfarm – 9 turbines, 8 125 metre high 1 108 metre
• Application – 10/00951/FUL, received 21st December 2010
• Committee – 26th July 2012
• Decision – Refused
3
Notification of appeal
• Call from agent – November 2012
• Received – 18th January 2013
• Meeting with STOP
4
Tight Timetable
22/01/13 Letter from Inspectorate 05/02/13 Agreed programme submitted 11/02/13 Start date 25/02/13 Submission of Questionnaire 11/03/13 Statement of case and Statement
of Common Ground 26/03/13 Pre-Inquiry Meeting 08/04/13 Deadline for Proof of Evidence 08/05/13 Inquiry Starts – estimated 12 days sitting
5
Initial task – assemble the team!
•Resource?
• Counsel
• Witnesses
6
Submission of Statement of Case and Statement of Common Ground
• Drafts
• Statement of Case
• Statement of Common Ground
7
PIM and Conference
• Site visit
• Pre Inquiry Meeting
• Conference
8
Proofs
• Witnesses and my role
• Submission
• Final Conference – 25th April
9
Before the Inquiry begins!
• Venue
• Staff
• Library
10
The Inquiry
• Timetable – 11days
• Opening day
• Core documents and document list
• Site visit
• Staff resources
•Team
11
Issues during Inquiry
• Network Rail – adjourned
• Recovered – 5th June
• Adjournment – 19th July
• Adjournment – 11th November
12
Issues
• Resourcing
• Dates/availability
• Officers role
13
Lessons learnt
• Partnership Working - STOP
• Site visit
• Underestimate role
14
Personal Perspective
• part time
• day job!
• childcare
• conflict?
• time
•Not a witness!
15
Finished?
• Not all over yet!
• Supplementary ES
• Consultation
• Further submissions
16