a preliminary cycle 1 calibration plan for the jwst science instruments james muzerolle
TRANSCRIPT
A Preliminary Cycle 1 Calibration Plan for the
JWST Science Instruments
James Muzerolle
Timeline: Launch, ~6 months Commissioning•checkout of mechanisms, early calibrations to enable science
•Commissioning activity requests (“CARs”) now written
•Cycle 1: science obs begin as instrument modes are commissioned – need full calibrations
Cycle 1 Calibration Plan Goals
obtain all internal and celestial observations needed to fully calibrate the science instruments:
• characterization of detector effects not done or completed on the ground
• (spectro)photometric, astrometric calibration
• monitoring/stability of key metrics and effects that may change
• anything else not covered or completed during Commissioning
begin defining a baseline plan by defining the set of likely programs and drafting program “summaries”
use as input into the SODRM (Gordon et al.)
plan conceived and written by instrument leads:
NIRCam: Anton Koekemoer NIRSpec: James Muzerolle
NIRISS: Kevin Volk, Harry Ferguson MIRI: Karl Gordon
status:
all planned program summaries are complete
- 39 programs among the 4 SIs
- available at https://confluence.stsci.edu/display/JWST/Cycle+1+Calibration+plans
modified versions of all have been added to the SODRM
example program summary
grand total of 756 hours:
• 258 hrs likely to be done as parallels
• 82 hrs can be run during slews (internals)
Plan statistics
the vast majority of data volume will be obtained in parallel observations (all darks)
• need to investigate at the visit level to verify within sufficient limits
data categories shared by most/all instruments
• most common are darks, flats, flux calibration
• many external observations share the same targets: astrometric calibration field, photometric standards
MIRI and NIRSpec dominate
• more modes, monitoring, and standard stars
more than half of the programs are monitors
• darks, lamp flats, (spectro)photometric calibration
• cadences mostly notional at this point
Deliverables
• dark reference files
• bad pixel maps
• read noise measurements
• P- and L-flat reference files
• Linearity reference files
• astrometric solution and distortion reference files
• PSF images/characterization
• persistence maps
• Spectral traces
• LSF characterization
• absolute photometric calibration conversion factors
• relative throughput measures
Future work The plan will be maintained by the new JWST Calibration & Commissioning Working Group
• check completeness of deliverables (Van Dixon reference file studies)
• push further coordination with the Commissioning plan
many monitoring programs based on CARs (internals, astrometric & photometric calibration)
better define the boundaries between Commissioning and Cycle 1
• update programs as new ground test results are obtained
• plan ground-based preparatory observations (vetting of appropriate targets, etc)
- expect to phase in Cycle 1 over L+5 to L+6 months
approximate commissioning timeline:
L+ dL
+