a winning game plan for contracting with the federal government
TRANSCRIPT
A Winning Game Plan for
Contracting
With the Federal GovernmentJames K. Cowan, Jr.540.443.2860 Direct
Amy P. Wheeler540.443.2857 Direct
[email protected]@cowanperry.com
Christy Cochrane, Virginia TechFederal Contracts Program Coordinator
Types of Federal Government
Contracts
• Background
• Main Items in Contract Type Selection− Amount of risk− Scope of work definitization
• Factors Used by Contracting Officers− Price competition− Price / cost analysis− Requirement complexity and urgency− Acquisition history
Types of Federal Government
Contracts
• Fixed-Price Contracts (FAR 16.2)
• Cost-Reimbursement Contracts (FAR 16.3)
• Incentive Contracts (FAR 16.4)
• Indefinite-Delivery Contracts (FAR 16.5)
• Time-and-Materials and Labor-Hour
Contracts (FAR 16.6)
Fixed-Price ContractsFAR 16.2
• Background / Risk Allocation
• Firm-Fixed-Price Contracts− Commercial items
− Clearly defined scope of work
− Able to determine fair and reasonable price
• Fixed-Price Contracts with Economic Price
Adjustment− Price revision (up or down) at set intervals
− Risk mitigation tool
− Revision due to industry changes
Fixed-Price ContractsFAR 16.3
• Firm-Fixed-Price, Level-of-Effort Term
Contracts− Research & Development
− Deliverable: final report
− Payment based upon level-of-effort
− General description of work
Cost-Reimbursement ContractsFAR 16.3
• Background / Risk Allocation− Allowable incurred costs
− Contract cost ceiling
− Additional requirements for Contracting Officer
• Cost Contracts− Actual, allowable costs
− No profit allowed / Educational Institutions
• Cost Sharing Contracts
Cost-Reimbursement ContractsFAR 16.3
• Cost-Plus-Fixed-Fee Contracts− Fee negotiated at execution
− FAR examples
− Types
• Completion
• Term
• Additional Types / Suggestions
Incentive ContractsFAR 16.4
• Applicability and Purpose− Cost incentive
− Technical performance incentive
− Delivery incentive
• Types− Cost plus incentive fee contracts
− Cost plus award fee contracts
Indefinite-Delivery ContractsFAR 16.5
• Applicability and Types− Definite-quantity contracts
− Requirements contracts
− Indefinite-quantity contracts
• Definite-Quantity Contracts− Defined amount of supplies/services
− Delivery date to be determined
• Requirements Contracts− Government will procure all supplies/services
within scope of work from contractor
− Maximum limit / Estimated amount
− Contractor is legally required to meet
obligations
Indefinite-Delivery ContractsFAR 16.5
• Indefinite-Delivery, Indefinite-Quantity (IDIQ)
Contracts− Delivery/task orders
− Maximum ordering limits
− Minimum award amount (consideration)
− Government prefers multiple award IDIQs
Time-and-Materials and Labor-Hour
Contracts (FAR 16.6)
• Applicability and Use − Negotiate fixed hourly rates that includes
overhead, wages, indirect costs, and profit
− Does not incentivize lower costs
− Prior authorization required to use
− Significant government oversight required
Accounting System• System must be deemed “acceptable” by
the government− Sound internal control environment,
framework and structure
− Segregation of direct costs from indirect costs− Indirect costs are generally categorized as
overhead and general & administrative costs
− Timekeeping system to identify labor efforts by
cost objectives
− Interim determination of costs charged to a
contract
− Ability to exclude “unallowable costs”
− Must follow GAAP
Incurred Cost Submission
• Every contractor who performs one or
more cost-reimbursement and/or time &
materials contracts must file with DCAA
• Due annually within 6 months of end of
contractor’s fiscal year
• Purpose is to report actual costs (both
direct and indirect) incurred on
government contracts and reconcile them
with amounts billed
• Receipt by DCAA begins audit process
Incurred Cost Submission
• Purpose of audit is to determine if a
contractor’s costs for that year are:− Reasonable;
− Allocable to the contract(s); and
− Allowable.
• Reasonable − A cost is reasonable if, in its nature and
amount, it does not exceed that which
would be incurred by a prudent person in
the conduct of a competitive business.
− Depends on a variety of circumstances
− Burden on contractor to demonstrate
Incurred Cost Submission
• Allocable
− A cost is allocable if, it is assignable or
chargeable to one or more cost
objectives on the basis of relative
benefits received or another equitable
relationship
− Is generally allocable if: − It is incurred specifically for the contract;
− It benefits both the contract and other work
and can be distributed to them in proportion
to the benefits received; or
− It is necessary to the overall operation of
the business
Incurred Cost Submission
• Allowable
− A cost is allowable only if it complies with
each of the following:
− Reasonableness;
− Allocability;
− Standards promulgated by the Cost
Accounting Standards Board, if
applicable, otherwise GAAP;
− Terms of the contract; and
− Any limitations set forth in FAR 31.2.
Affirmative Action Regulations
• Affirmative Action regulations are administered by
the Department of Labor’s Office of Federal
Contract Compliance Programs (“OFCCP”).
• http://www.dol.gov/ofccp/aboutof.html
• There is a wealth of information to be found on the
OFCCP’s home page, including sample narrative
affirmative action plans and related materials at:
• www.dol.gov/ofccp/index.htm
• Today, we will focus on recent changes and
a number of new Executive Orders
The New RulesExecutive Order 11246, its Recent Amendments and new Final Rules:
EO 13665, Prohibitions Against Pay Secrecy Policies and
Actions (amended EO 11246; final rule; effective
January 11, 2016)
EO 13672, Prohibiting Discrimination Based on Sexual
Orientation and Gender Identity (amended EO 11246; final
rule as of April 8, 2015)
EO 13658, Establishment of Minimum Wage for Federal
Contractors (final rule as of January 1, 2015; updated
January 1, 2016 & thereafter)
EO 13706, Establishing Paid Sick Leave for Federal Contractors;
Secretary of Labor to issue regulations by September 30,
2016; goes into effect January 1, 2017
EO 13673, Fair Pay and Safe Workplaces Act
The New Rules, cont.
New EEO-1 Report (formerly known as the proposed
Equal Pay Report), to be included in 2017 EEO-1
New Sex Discrimination Guidelines
• Changes to the Rehabilitation Act of
1973 (Section 503)
• Changes to the Vietnam Era Veterans
Readjustment Assistance Act (VEVRAA)
(Section 4212)
Which
rules
apply?
Executive Order 11246
Executive Order 11246 prohibits federal
government contractors and subcontractors from
discriminating in employment on the basis of
race, color, religion, national origin, sex, sexual
orientation, and gender identity, and requires
affirmative action with respect to minorities and
females to ensure nondiscrimination.
41 CFR § 60, et seq.
Executive Order 13672
An amendment to EO 11246, this rule prohibits
discrimination based on sexual orientation and/or gender
identity
Became effective on April 8, 2015 and applies to contracts
entered into on or after April 8, 2015
Amended language in all affirmative action clauses and
notices: race, color, religion, national origin, sex, sexual
orientation, and gender identity
FAQs: http://www.dol.gov/ofccp/LGBT/LGBT_FAQs.html
Complaints of discrimination under this new rule may
be investigated and enforced under both EO 11246 and
under Title VII
Executive Order 13665
Prohibitions Against Pay Secrecy and Actions; this rule
amends EO 11246 and became effective on January 11, 2016
Prohibits federal contractors from discharging or discriminating
against employees or applicants for disclosure, inquiry, or
discussion about compensation with others
Prohibits adverse treatment for disclosure, inquiry or discussion
regarding compensation with other employees
Full text of Final Rule:
https://www.gpo.gov/fdsys/pkg/FR-2015-09-11/pdf/2015-22547.pdf
EO 13665 – EEO clause
Requires that the equal opportunity clause included in covered
federal contracts and subcontracts be amended to include that
federal contractors and subcontractors must refrain from
discharging, or otherwise discriminating against, employees or
applicants who inquire about, discuss, or disclose their
compensation or the compensation of other employees or
applicants.
A contractor’s federal contracts, subcontracts, or purchase
orders may incorporate 41 CFR 60–1.4, the equal opportunity clause provision of the regulations, by reference into their contracts and subcontracts.
EO 13665 – Pay Transparency Policy
StatementContractors must incorporate the nondiscrimination provision into
their existing employee manuals or handbooks and disseminate the
nondiscrimination provision to employees and to job applicants,
verbatim, as follows:
PAY TRANSPARENCY POLICY STATEMENT
The contractor will not discharge or in any other manner
discriminate against employees or applicants because they
have inquired about, discussed, or disclosed their own pay or
the pay of another employee or applicant. However, employees
who have access to the compensation information of other
employees or applicants as a part of their essential job
functions cannot disclose the pay of other employees or
applicants to individuals who do not otherwise have access to
compensation information, unless the disclosure is (a) in
response to a formal complaint or charge, (b) in furtherance of
an investigation, proceeding, hearing, or action, including an
investigation conducted by the employer, or (c) consistent with
the contractor’s legal duty to furnish information.
Executive Order 13658
On January 1, 2015, this rule established a new minimum wage for
federal contractors ($10.10/hour) to be increased by the Secretary of
Labor on January 1, 2016 and annual thereafter, as permitted by the
Executive Order.
Applies to new contracts and replacements for expiring contracts with
the Federal Government that result from solicitations issued on or
after January 1, 2015 or to contracts that are awarded outside the
solicitation process on or after January 1, 2015.
FAQs: http://www.dol.gov/whd/flsa/eo13658/faq.htm
Effective January 1, 2016, the minimum wage is $10.15/hour.
Also, beginning January 1, 2016, tipped employees performing
work on or in connection with covered contracts generally
must be paid a minimum cash wage of $5.85/hour.
Executive Order 13706 Establishes paid sick leave for federal contractors; goes into effect
January 1, 2017.
Contracts and subcontracts must specify, as conditions of payment
in the performance of the contract or subcontract:
• Employees shall not earn less than 1 hour of paid sick leave per
30 hours worked;
• Contractors shall not set a limit of less than 56 hours accrual of
sick leave per year;
• Paid sick leave shall carry over from one year to the next; and
shall be reinstated for employees rehired by a covered
contractor within 12 months after a job separation.
• Use cannot be made contingent upon employee finding a
replacement to cover missed work time
EO 13706 – Enforcement
A contractor may not interfere with or discriminate
against employees for taking, or attempting to take, paid
sick leave as provided for under EO 13706 or in
asserting, or assisting other employees in asserting any
right or claim related to the order.
The Secretary of Labor will investigate potential
violations of, and obtain compliance with, the terms of
this order.
Full text of EO 13706: https://www.whitehouse.gov/the-
press-office/2015/09/08/executive-order-establishing-
paid-sick-leave-federal-contractors
Sections 4212 (VEVRAA) and 503 (Rehabilitation Act of 1973)
• On March 24, 2014, this section was amended to include:
Annual hiring (not incumbent) benchmark for protected veterans
(either equal to percentage of veterans in national civilian
workforce, which varies each year, or by calculated
individualized benchmarks)
Collection, documentation, and analysis of number of protected
veteran applicants and hires
Invitations to protected veterans to self-identify at pre- and post-offer
stages
Required specific language when incorporating the EEO
clause in a subcontract by reference
Job listing requirement to provide information in manner
and format permitted by state/local job services
The VEVRAA Benchmark
As of March 4, 2016, the national percentage of
veterans in the civilian labor force was 6.9%
When considering whether to customize your
benchmark, you should first examine the available
data. For example, the average percentage of veterans
in the civilian labor force for the prior 3 years (2012,
2013 and 2014) in Virginia was 11.4%; in Texas, the
average was 7.4%
Link to VEVRAA Benchmark Database, specifics and
sample data for the 5-factor test:
https://ofccp.dol-esa.gov/errd/VEVRAA.jsp
Veterans’
Infographic
In August 2015, the
OFCCP released “Am I a
Protected Veteran?” This
infographic helps
applicants and
employees determine if
they are eligible to self-
identify as protected
veterans.
Section 503 Reminder
Effective March 24, 2014, this section was amended to require:
Contractors with more than 100 employees have a workforce goal of
7% utilization of persons with disabilities, by job group
Required collection, documentation, and analysis of the
number of disabled applicants and hires
Contractors with fewer than 100 employees have a workforce
goal of 7% utilization of persons with disabilities, workforce-
wide
Application process must be inclusive of applicants with
disabilities
The OFCCP’s new Section 503 compliance
checklist is available here:
http://www.dol.gov/ofccp/regs/compliance/checklistforComplian
cewithSection503_JRF_QA_508c.pdf
The OFCCP has posted a 50-second video on its website, called “Disability Inclusion Starts
with You,” to share with employees and applicants who may be reluctant to self-identify, or
who may not understand the reasons for self-identification. It is available with and without
captioning here: http://www.dol.gov/ofccp/SelfIdVideo.html
Contractors may wish to download and post this video on their Intranet or company website to
share with employees and job applicants.
VEVRAA and Section 503
Annual Assessment and Audit
Don’t forget! Contractors must design and implement an audit
and reporting system to:
Determine the need for remedial action
Determine whether disabled individuals and protected veterans had
the opportunity to participate in the company's education, training,
recreational and social activities
Measure compliance with affirmative action plan obligations
Document actions taken to comply, and
If deficiencies are found, undertake necessary action to come into
compliance.
To Keep or Not to Keep:
Statistical Reports/Records
Selection and hiring records should be kept for three (3) years,
because federal contractors will now create auditing and reporting
systems under Sections 4212 and 503.
Any employment or personnel record kept by the contractor must be
retained for two (2) years after the record is made or the personnel
action is taken, whichever is later, but
Contractors must evaluate and document the effectiveness of
their recruiting of disabled individuals and protected veterans.
Documentation must include the criteria used to evaluate the
recruiting efforts and conclusions as to the success of those
efforts. Contractors must maintain this data, and the report
created from that data, for three (3) years.
To Keep or Not to Keep:
Statistical Reports/Records
Annual Written Report Required: At the end of the annual
assessment, the contractor will create a written report that
becomes a part of the company's AAP. The report must include:
The criteria used to evaluate the effectiveness of each outreach
and recruitment effort used; and
Provide the contractor's conclusion on the effectiveness of
the program. The criteria in the report must include an
assessment of the annual hiring data for the current year
and the two previous years (this began March 24, 2014)
Revision to EEO-1 Report
The new report, beginning in 2017, includes:
Contractors with 50 to 99 employees: Total number of
workers in a specific EEO-1 job category by race, ethnicity
and gender (same as the current EEO-1)
Contractors with 100+ employees: aggregate W-2 data in
12 pay bands (provided by the EEOC in this proposed rule)
in each EEO-1 job category, and total hours worked by
employees within each of the 12 pay bands
New EEO-1 Report
• Requires reporting of pay data already maintained in the normal
course of business.
• In consultation with the DOJ, the EEOC and OFCCP focused on
how EEO-1 pay data would be used to assess complaints of
discrimination, focus investigations, and identify employers with
existing pay disparities that might warrant further examination.
The EEOC and OFCCP anticipate that the process of reporting
pay data may encourage employers to self-monitor and comply
voluntarily if they uncover pay inequities.
EEO-1 Filing Rule Changes
Effective September 2015, if a company has multiple
establishments located at the same address, and those
establishments have the same NAICS code and the same
EIN, the establishments MUST be combined into only one
report.
Employers must provide the company’s EIN on the EEO-1
report.
EEO-1 Survey Link:
http://www.eeoc.gov/employers/eeo1survey/
Companies can now obtain and reset their EEO-1 filing
passwords. https://egov.eeoc.gov/eeo1/login_help.html
On June 14, 2016, the Office of Federal Contract Compliance Programs
announced publication of a Final Rule in the Federal Register that sets forth the
requirements that covered contractors must meet under the provisions of
Executive Order 11246 prohibiting sex discrimination in employment.
This Final Rule updates sex discrimination guidelines from 1970 with new
regulations that align with current law and address the realities of today’s
workplaces.
The Final Rule deals with a variety of sex–based barriers to equal employment
and fair pay, including compensation discrimination, sexual harassment, hostile
work environments, failure to provide workplace accommodations for pregnant
workers, and gender identity and family caregiving discrimination.
The Final Rule became effective on August 15, 2016.
Sex Discrimination Guidelines
Sex Discrimination Guidelines
Leave for childcare must be made available to men on the same
terms as it is available to women.
Contractors must provide workplace accommodations,
ranging from extra bathroom breaks to light-duty
assignments, to women affected by pregnancy, childbirth,
and related medical conditions comparable to the
accommodations that they provide to other workers similar
in their ability or inability to work, such as workers with
disabilities or occupational injuries.
Adverse treatment of an employee based upon gender-
stereotyped assumptions about family caretaking responsibilities
is discrimination.
Executive Order 13673
Will require federal contractors, at the time of bid solicitation for
contracts of $500K+, to disclose certain labor violations during the past
three (3) years
Fair Pay and Safe Workplaces Order
Will require subcontractors whose subcontracts are $500K+ to
make the same disclosures
Among other things, this EO will require the following:
Contractors must make certain disclosures at each pay period
to employees, including the number of hours worked, rate of
pay, deductions from pay, etc.
EO 13673, continued
Contractors must update their disclosures to the government
agency with which they have the contract every six months
during contract performance
Contracting agencies must consult with a Labor Compliance
Advisor and consider the disclosures made by the bidding
contractor before awarding the contract
Federal contractors with contracts over $1M may only enter into
pre-dispute arbitration agreements with employees under Title
VII, or for any tort arising from sexual harassment or assault,
with the agreement of the employee or contractor after the
dispute arises
EO 13673, continued
Phased-In Implementation Schedule:
See Associated Builders and Contractors of Southeast Texas, et al. v. Anne Rung, Administrator, Office of Federal Procurement Policy, Office of Management and Budget, et al.; USDC EDTX, 1:16-cv-00425 was filed on 10/7/16, seeking injunctive relief before the final rule takes effect.
October 25, 2016: The final rule takes effect. Mandatory disclosure and assessment of labor law compliance begins for all prime contractors under consideration for contracts with a total value greater than or equal to $50 million. The reporting disclosure period is initially limited to one (1) year and will gradually increase to three (3) years by October 25, 2018.
January 1, 2017: The Paycheck Transparency clause takes effect, requiring contractors to
provide wage statements and notice of any independent contractor relationship to their
covered workers.
April 25, 2017: The total contract value threshold for prime contracts requiring disclosure
and assessment of labor law compliance is reduced to $500,000.
October 25, 2017: Mandatory assessment begins for all subcontractors under
consideration for subcontracts with a total value greater than or equal to $500,000.
“EEO Is the Law” Poster Supplement
The EEOC’s “EEO Is the Law” poster was last revised in November 2009 and
consists of two pages. You must also post the September 2015 supplement
(see image in next slide).
Link to November 2009 “EEO Is The Law” Poster*:
http://www.dol.gov/ofccp/regs/compliance/posters/pdf/eeopost.pdf
Link to September 2015 Supplement*:
http://www.dol.gov/ofccp/regs/compliance/posters/pdf/OFCCP_EEO_Suppleme
nt_Final_JRF_QA_508c.pdf
Link to the DOL’s Poster website, for these and foreign language versions:
http://www.dol.gov/ofccp/regs/compliance/posters/ofccpost.htm
*You should also post these links on your company’s website,
along with your EEO statement, on your employment page.
Required Language/Posters
Links to pay transparency language (you may use links on your websites):
Formatted (poster):
http://www.dol.gov/ofccp/pdf/PayTransparencyNotice_JRFQA508c.pdf
Not Formatted (for inclusion as text):
http://www.dol.gov/ofccp/pdf/EO13665_PrescribedNondiscriminationPostingLan
guage_JRFQA508c.pdf
EEO is the Law poster:
http://www.dol.gov/ofccp/regs/compliance/posters/pdf/eeopost.pdf
EEO is the Law poster supplement:
http://www.dol.gov/ofccp/regs/compliance/posters/pdf/OFCCP_EEO_Supplemen
t_Final_JRF_QA_508c.pdf
You should post your company’s EEO statement.
Minimum EEO Required Tag Line:
EO Employer – M/F/Vets/Disabled, or EO Employer – Veterans/Disabled
and other protected categories
Methods for contacting employer:
Applicants with disabilities must either be able to use your online system
or submit an application in a timely manner through alternative means –
facsimile, email, phone call. This includes providing a means to contact
the contractor, other than through the online system, to request a
reasonable accommodation needed to apply and be considered for the
contractor´s jobs. Fax lines and email addresses must be attended to in
a timely fashion.
Required Language/Posters
Audits• Federal contractors are subject to audit,
generally by DCAA
− Pre-award audits: proposal pricing, forward
pricing rates or survey of accounting system
− Post-award audits: costs incurred under
contract, compliance with the Truth in
Negotiations Act or compliance with Cost
Accounting Standards
− Business system audits: significant business
systems such as accounting, estimating, billing,
purchasing, timekeeping and inventory/supply management
Intellectual Property
• Bayh-Dole Act of 1980
− In contrast with previous law, permits
contractors to retain title to a “subject
invention” developed with federal funding
− Subject invention is “any invention of a
contractor conceived or first actually
reduced to practice in the performance of work under a funding agreement
Patents
Intellectual Property
• Conception − More than a good idea, must be able to
describe with specific clarity and
precision to enable one skilled in the art
to practice
• First reduced to practice− Must be demonstrated to persons of
ordinary skill in the art that the invention
will perform its intended function beyond
the probability of failure in its intended operating environment
Patents
Intellectual Property
• Actions to retain title to invention− Must timely disclose existence of subject
invention to government
− Must affirmatively elect to retain title
− Must timely file and prosecute patent
application on invention
• Rights of government in subject invention− Non-exclusive, non-transferable, irrevocable,
paid-up license to practice or have practiced,
for on on behalf of the government, any
subject invention throughout the world
Patents
Intellectual Property
• If contractor fails to take all affirmative
steps within time frames required, the
government may request assignment
of the subject invention
• March-in-rights− If contractor fails to make reasonable
progress in bringing a technology to the
commercial market, the government can
require the contractor to license the technology to third parties
Patents
Intellectual PropertyCopyrights
• Unless prohibited by the contract,
contractor can generally assert a copyright
in a work first created under a government
contract
• Must always mark with a copyright legend
and acknowledge government’s
sponsorship
• Government gets a paid-up, nonexclusive,
irrevocable, worldwide license to
reproduce, distribute, prepare derivative
works, display, etc.
Intellectual PropertyTechnical Data and Computer Software
• Technical data “means recorded
information, regardless of the form or
method of the recording, of a scientific or
technical nature (including computer
databases and software documentation)”
• Generally, the contractor retains title to both
technical data and software and the
government receives a license to use,
reproduce, modify, release, perform,
display, or disclose the data or software
Intellectual PropertyTechnical Data and Computer Software
• The scope of the government’s rights
will depend primarily on:
1) whether the technical data or computer
software is commercial or non-commercial,
and
2) to what extent the data or software was
developed with federal versus private
funds
Intellectual PropertyTechnical Data and Computer Software
• Noncommercial Technical Data or
Computer Software
− Was item, component or process
“developed” in whole or in part with
government funds?
− Fact-specific inquiry
− Make determination at “lowest practical
level” by dividing the item, component or
process into segregable components (sub-elements or sub-routines)
Intellectual PropertyTechnical Data and Computer Software
• Unlimited Rights− Unlimited Rights are the rights of the
government to use the technical data or
software in any manner and for any
purpose and to permit others to do so
− Government gets unlimited rights in data
and software developed exclusively with
federal funds
Intellectual Property
• Unlimited Rights − Regardless of funding source, Government
also gets unlimited rights in:− Data first produced in performance of contract
− All data delivered under a contract
− Studies analyses, test data, or similar data produced for
a contract, when the work was specified as an element
of performance
− Form, fit, and function data
− Data necessary for installation, operation, maintenance,
or training purposes)
− Data otherwise publicly available or released or
disclosed by the contractor without restrictions on further
use, release or disclosure
− Data in which the government has obtained unlimited
rights under another government contract
− Note differences in DoD v. non-DoD procurements
Technical Data and Computer Software
Intellectual PropertyTechnical Data and Computer Software
• Government Purpose Rights − Government Purpose Rights are the rights
of the government to:
− Use, modify, replace, disclose, display, etc.
technical data or computer software within the
government without restriction; and
− Release or disclose technical data or computer
software outside the government and authorize
those to whom it was released or disclosed to
use, modify, replace, perform, display, etc.
technical data or computer software for U.S.
government purposes
Intellectual PropertyTechnical Data and Computer Software
• Government Purpose Rights − The government gets Government Purpose
Rights for a 5-year period in data/software:
− That pertains to items, components, or processes
developed with mixed funding except when the
government is entitled to unlimited rights; or
− Created with mixed funding in the performance of
a contract that does not require the development,
manufacture, construction, or production of items,
components, or processes
− Contractor has exclusive right to use (including to
license) the data for any commercial purpose
− After 5-year period, the government has unlimited
rights
Intellectual PropertyTechnical Data and Computer Software
• Restricted Rights − The government gets restricted rights in
computer software developed at private
expense and that is a trade secret, is
commercial or financial and confidential or
privileged, or is copyrighted computer
software
− Restricted rights allow the government to
primarily use the software on one
computer, transfer it, make archive copies,
let other government contractors use it in
support of the government
Intellectual PropertyTechnical Data and Computer Software
• Limited Rights − Limited Rights are the government’s rights to
use, modify, replace, perform, display, etc.
technical data, in whole or in part, within the
government
− The government may not release or disclose
the technical data outside the government,
use the data for manufacture, or authorize
the data to be used by another party, unless
necessary for emergency repair/overhaul or
if to a covered government support
contractor in performance of its government
support contract
Intellectual PropertyTechnical Data and Computer Software
• Specifically Negotiated License Rights− The standard license rights granted to the
government may be modified by mutual
agreement of the parties, but shall not provide
the government lesser rights than limited rights
− Specifically Negotiated License Rights must be:
− stated in a conspicuous place on the
medium on which the data is recorded;
− stated in the contract and clearly marked; or
− identified in a license agreement made a
part of the contract
Intellectual PropertyTechnical Data and Computer Software
• SBIR Data Rights− Unless the government already has unlimited
rights, the government gets special data rights –
called SBIR data rights – in all data/computer
software generated under a contract that is part of
an SBIR or STTR program
− SBIR data rights means the government’s rights to
use, modify, disclose, display, etc. data or software
generated under a SBIR/STTR award as follows:
− Limited rights in SBIR technical data; and
− Restricted rights in SBIR software
− SBIR Data Rights generally end five years after
completion of the project
Intellectual Property
• Actions to protect rights in data and
software− Proposals should identify any data/software
that contractor intends to deliver with less than
unlimited rights
− For DoD procurements, DFARS 252.227-7017
requires an offer to complete a chart (the “-
7017 chart”) identifying specifically the
data/software to be submitted, the asserted
rights category (i.e., limited rights, government
purpose rights), and the basis for the assertion
(i.e., developed with private funds developed
with mixed funds)
Technical Data and Computer Software
Intellectual PropertyTechnical Data and Computer Software
• Actions to protect rights in data and
software− The -7017 chart must be delivered with the
proposal and will become part of the contract
− Contractor will not be permitted to deviate from the
-7017 chart unless there were inadvertent
mistakes or changed circumstances (i.e., new
requirements added to scope)
− Data or software delivered under the contract must
also be marked each and every time it is submitted
to the government
Intellectual PropertyTechnical Data and Computer Software
• Actions to protect rights in data and
software
− Blanket markings are not permitted, only
data/software entitled to restriction may be
marked
− Failure to follow these requirements will result
in the technical data or software being delivered
to the government with unlimited rights
− Markings may be challenged by the government
Intellectual PropertyTechnical Data and Computer Software
• Commercial Technical Data or
Computer Software
− Government generally receives the standard
license rights provided by the contractor to
the public
− Government cannot be provided less rights
than given to the public
− If the publicly available rights do not meet
the government’s needs, it will work to
negotiate Specifically Negotiated License
Rights
Intellectual PropertyProtecting Your Rights as a Subcontractor
• Read your entire contract, including the
prime’s standard terms and conditions that
are likely on the internet and only referenced
in the agreement or purchase order
− Prime contractors cannot use their power to grant
contracts as leverage to obtain rights to a
subcontractor’s technology when awarding a
subcontract
− If subcontractor is to deliver data or software in
which it claims restrictions to fulfill an obligation of
the prime contract, subcontractor may deliver that
data/software directly to the government without
providing it to the prime contractor
Contracting Opportunities for
Small Businesses
• U.S. Small Business Administration (SBA)− Founded in 1953 under Small Business Act
− Mission
“…aid, counsel, assist and protect the
interests of small business concerns
(SBCs), to preserve free competitive
enterprise and to maintain and strengthen
the overall economy of our nation.”
• FAR Part 19, Small Business Programs− SBA assists acquisition personnel
− Ensures that small businesses are provided
the opportunity to execute “a fair proportion
of contracts for supplies and services”
Contracting Opportunities for
Small Businesses
• Determination of Small Business Status− Based upon annual revenue or number of
employees
− Thresholds set for each industry through the
North American Industry Classification System
(NAICS)
• Small Business Categories Include:
Small businesses Small disadvantaged businesses
Veteran-owned small businesses Women-owned small businesses
Service-disabled veteran-owned small businesses
Historically Underutilized Business Zones (HUBZone) small businesses
Contracting Opportunities for
Small Businesses
• FAR Subpart 19.5, Set-Asides for Small
Business− Exceeds micro-purchase threshold, but is under
the simplified acquisition threshold ($150,000)
− Automatically set-aside for small businesses
• Small Business Subcontracting Plans− $700,000 or more
− Large businesses must submit a plan to show
how they will provide maximum practical
opportunity to use small businesses to execute
their statement of work
− Format at FAR 19.704
Small Business Innovation Research
(SBIR) Program
• Background − Piloted by National Science Foundation (1972)
− Expanded to federal government (1982)
• Extramural budgets for R&D of $100 million
Department of Agriculture
(USDA)
Department of Commerce
Department of Defense (DoD) Department of Education (ED)
Department of Energy (DoE) Department of Health and
Human Services (HHS)
Department of Homeland
Security (DHS)
Department of Transportation
(DOT)
Environmental Protection
Agency (EPA)
National Aeronautics and
Space Administration (NASA)
National Science Foundation
(NSF)
SBIR Program
• SBIR Program Purposes
• Three Phased Program− Milestone-driven
− Phase I: At least two-thirds performed by SBC
− Phase II: Minimum of half performed by SBC
Phase Duration Funding Ceiling Purpose/Deliverable
I Six Months $150,000 Feasibility study or prototype to document technical merit
II 24 Months $1,000,000 Continues R&D from Phase I
III Varies No Federal Assistance
Commercialization effort. Funded privately
Small Business Technology Transfer
(STTR) Program
• Defined at 15 U.S.C. § 638 − “…research and development conducted jointly
by a small business concern and a research
institution….”
− Nonprofit organizations/public universities
• Requirements− Small business concern must execute at least
40% of the work
− Research institution must execute at least
30% of the work
STTR Program
• Three Phased Program− Milestone-driven
• Process of Partnering with University
Phase Duration Funding Ceiling Purpose/Deliverable
I Six Months $150,000 Feasibility study or prototype to document technical merit
II 24 Months $1,000,000 Continues R&D from Phase I
III Varies No Federal Assistance
Commercialization effort. Funded privately
SBIR/STTR Intellectual Property
Contract Clauses
• SBIR: FAR 52.227-20, Rights in Data –
SBIR Program (May 2014)− Terms favorable to small businesses
− Example: FAR 52.227-20(c) allows for the
contractor to assert copyright
• STTR:− No Corresponding FAR IP clause
− Include an agreement pertaining to STTR
Program Allocation of Rights to Intellectual
Property and Rights to Carry Out Follow-On
Research, Development, or
Commercialization in proposal
Working with a Public University
Contract Clauses
• Indemnification− Many public universities will be unable to agree
to clauses that include indemnity.
− The Code of Virginia addresses indemnification
at Va. Code Ann. § 2.2-1837, Risk Management
Plan for Public Liability.
− Virginia Tech prohibited from indemnifying
under a sponsored research project.
• Equipment Ownership− FAR Clause 52.245-1, Government Property
(Apr. 2012) with its Alternate II (Apr. 2012)
Working with a Public University
Contract Clauses
• Publication− The freedom to publish is a key tenant for many
universities
− Sponsors provided with a limited period of time
in which to review and provide comments
regarding items the university intends to publish
− Allows for the identification of any patentable
subject matter or the inadvertent inclusion of the
sponsor’s proprietary information
• Warranties− “Reasonable Efforts” or “Best Efforts” to
perform the research described within the
statement of work
Thank You for Attending
this CLE Presentation
250 South Main Street, Suite 226Blacksburg, Virginia 24060
p: 540.443.2850
1328 3rd Street, SWRoanoke, Virginia 24016
p: 540.777.3450
www.cowanperry.com